Improvement and Asphalting of State Highway and Major District Road of Koppal District

Page 1

International Research Journal of Engineering and Technology (IRJET)

e-ISSN: 2395 -0056

Volume: 04 Issue: 07 | July -2017

p-ISSN: 2395-0072

www.irjet.net

Improvement and Asphalting of State Highway and Major District Road of Koppal District B VINAYAKA1, TILAK.P.KURUGOD2 1Mtech,

Reva College of engineering, Bangalore, Karnataka, India Reva College of engineering, Bangalore, Karnataka, India ---------------------------------------------------------------------***--------------------------------------------------------------------2Mtech,

Table -1: Details of selected road stretch of MDR

Abstract - It is a well-known fact that India is developing

country with an ample spread of Road network. Road network plays an important role in overall development of the country. In this regard improvement and asphalting needs to be the given due consideration for maintaining of existing road network. In this regard improvement and asphalting of two major network is carried out. Various studies and coast of work was estimated as well. Work of the same was carried out in Koppal district choosing both SH and MDR network. PWD department shall have a through studies of the Road network and decide the action to be taken like resurfacing or restructuring for better maintence of road network

SL.NO

1

NAME OF THE ROAD

KAVALOORMANGALOOR

ROAD CATEGORY.

MDR

LENGTH IN KOPPAL

6.80 KM

TALUK

3

LENGTH IN

43.20 KM

YALBURGA TALUK TOTAL LENGTH

50.00 KM

Table -2 Details of selected stretch of state highway

1. INTRODUCTION

SL.NO The proposed improvement of both the State highway and Major district road of Koppal district. In case of Major district road KAVALOOR-MANGALOOR road from km. 17.00 to 26.00 in Yelburga tq. Similarly in the case of State highway RARAVI – BELUR SH-63 from km. 141.00 to 162.20. These selected stretch for the overall improvement, restructuring, resurfacing and asphalting as per requirement of the present condition. Detailed studies of the road network was carried out in order to obtain the existing condition details. Bar chart and CBR design method was followed for overall designing of the road network. Overall cost of the project was estimated and was submitted to the PWD department for insight of the work to be carried out.

1

LENGTH

NAME OF THE ROAD

RARAVI BELUR

ROAD CATEGORY.

SH

LENGTH IN

44.78 KM

2

GANGAVATI TALUK

3

LENGTH IN KOPPAL

4

7.61 KM

LENGTH IN

51.39 KM

YALBURGA TALUK TOTAL LENGTH

The proposed improvement of SH RARAVI – BELUR SH-63 from km. 141.00 to 162.20. The total length of the road recognized for improvement is 103.78 Kms

103.78 KM

Table 1 and 2 gives the detail outline of the total length of the Road network in that particular stretch. On this particular road stretch certain length of road is elected based on the reconnaissance survey in order to understand and find out the best alternative for improvement. Complete stretch is surveyed and selected stretch details are identified based on the service it caters and alternative measures are been chosen for the same. Tables 3 and 4 gives us the details of the length of the selected stretch for overall improvement.

The proposed improvements to MDR Kavallor-Mangaloor road in Koppal district starts at Ch.18.25 Km (near Mannapur village limit) and ends at Ch. 26.00Km( Near Kukanur town). The total length of the road taken up for improvements is 7.75 Kms from near Mannapur to Kukanur Ch: 18.25 to 26.00KM taken for improvements.

Impact Factor value: 5.181

DETAILS

TALUK

1.1 Details of study area

|

LENGTH

2

Key Words: Asphalting, Improvement, CBR, Estimation, MDR, SH, Resurfacing and Restructuring.

© 2017, IRJET

DETAILS

|

ISO 9001:2008 Certified Journal

| Page 617


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.