­­Construction Quality Auditing

Page 1

International Research Journal of Engineering and Technology (IRJET)

e-ISSN: 2395 -0056

Volume: 04 Issue: 02 | Feb -2017

p-ISSN: 2395-0072

www.irjet.net

Construction Quality Auditing Saurabh Jamadagni1, Prof.B.V.Birajdar2, 1M.E.CIVIL

(CONSTRCUTION &MANAGEMENT) ENGINEERING STUDENT, DEPARTMENT OF CIVIL ENGINEERING 2HEAD OF THE DEPARTMENT OF CIVIL ENGIEERING 1,2Tatyasaheb Kore Institute of Engineering and Technology, Warananagar, Tal: Panhala, Dist: Kolhapur, Maharashtra, India-416113

---------------------------------------------------------------------***--------------------------------------------------------------------1.1 Factors affecting to the Construction Quality

Abstract –

Construction quality is one of the most important factors during the construction projects; and in that auditing also plays very vital role to maintaining the quality of the projects during their various parameters. This study highlights the factors affecting on constriction quality.A questionnaire was used to gather the relevant data from members of Kolhapur’s residential projects builders. In that involves 72 factors divided into four categories which are Engineering group, Contractor Group, Quality Control Group, Customer satisfaction group. The Relative Importance Index (R.I.I.) was determined and the factors were ranked. The top factors mainly affecting to the construction quality that are to be described. Recommendations have been made in the study of address these factors.

Key Words: Construction, Quality, Auditing 1. INTRODUCTION

In this paper total seventy two factors are to be identified by the literature survey, which are to be affected construction quality are classified under the four primary groups that are 1)Engineering group 2) contractor group 3)Quality control Department and 4)Customer group. In the Engineering group consist of the following factors which are affected to the construction quality:01)Quality of Material,2)Material Varriance,3)Material Reuse 4)Test samples results 5)Structural Design 6)Mix Design 02)Contractor group having 01)skilful labour,02)well working equipments,03)Proper sequence of work 4)Drawing plans 03)Quality Control Department consist of the factors which are mentioned as 01)Technical knowledge to Quality Control Department group 02)mortar proportion used at site project,03)Brand of Material, 4)Material Inspection at site,5)All material test results,06)Checklist filling before work starts07)Rework 04)Customer satisfaction group consist of the factors are 01)Natural ventilations,02)Natural Lighting,3)Slopes of toilets, terraces, kitchen platforms,4)Parking area space,5)water availability05) Fire fighting and solar system. 2)METHODOLGY: The questionnaire survey was carried out in the various

In construction projects quality is very major part for client as well

construction projects. The total 26 samples were taken from

as customer also, because almost all customers giving priority at

Kolhapur city, on which 16 samples values cost of more than 10

the time of selection of their homes that in how much manner the

cores, and the 10 samples are to be taken which having cost of less

builder will gives specifications of project, their quality and the way

than ten cores. In that samples four groups were created which are

in which superior material is to be used in the projects, in that case

Engineering group, then Contractor Group,03) Quality control

customer will also accept for giving more money to the builder for

Department Group and 4)Customer satisfaction group. For the

having the amenities. Through the auditing is to be conducted

analysing data the Relative Importance Technique (R.I.I.) used.

almost 3 to 4 times in the yaer,either by internally or externally auditors, so due to that all help to maintain the all specification at

03) QUESTIONNAIRE DESIGN: In that design of questionnaire is

site, and also helping for maintain safety requirements which are

very simple and under stable for respondents. The advantage is in

helpful to customers also.

smaller timing getting more accuracy in final outcome. Factors affecting the construction quality were identified through the literature survey. The questionnaire required the respondents to rank factors affecting construction quality with the scale of rating01)reprents very low effect 02) represents

low effect

03)represents medium effect 04)high effects,05)very high effects

© 2017, IRJET

|

Impact Factor value: 5.181

|

ISO 9001:2008 Certified Journal

|

Page 1500


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
­­Construction Quality Auditing by IRJET Journal - Issuu