YOUR CONSTRUCTION CONSULTANTS

1.
OVERVIEW OF GOODRICH
FOR OVER 30 YEARS, GOODRICH CONSULTING HAS BEEN DELIVERING EXCEPTIONAL CONSTRUCTION CONSULTANCY TO CLIENTS ACROSS THE UK

Founded in 1992, the company has grown from strength to strength, seeing the team expand at its Northampton headquarters, and the acquisition of a Birmingham and Bristol office The ownermanaged firm is led by seven Partners, supported by an experienced team of project managers, project surveyors, building surveyors, and technical administrators.
Our team is what sets us apart, alongside our commitment to delivering an outstanding service on every project we work on. With expertise from client and contractor backgrounds, our workforce ranges in experience levels, enabling us to fit the right team for your job.
We aim to provide our clients with dedicated experts to support the smooth and successful delivery of your vision, from conception to completion and beyond, through the following core service lines:
• Project Management
• Employer’s Agent
• Quantity Surveying
• Building Consultancy
• Principal Designer
Reliability and flexibility are key to any successful project, which is why we adopt a forwardthinking, proactive approach to our work, supported by our industry knowledge, ongoing research and benchmarking of current market trends.
In addition to our core services noted above, we also offer the following supplemental services:
• Dilapidations
• Building Survey
• Licence to Alter
• Party Wall
• Clerk of Works, or Quality Monitoring
• Fund Monitoring
• Facilities and Property Management
We are proud to have developed strong repeat partnerships with our clients, some of which span over the 30 years we have been in business. Our enviable position as experts in industrial, commercial, and education sectors has enabled us to enter new areas such as retail, retirement living, infrastructure, hotel, life science, and occupier fitout. Our people and portfolio of work allow us to provide invaluable insight across a variety of industry sectors.
2.
OUR CORE OFFERING

Project Management
We have an incredibly strong team of experienced project managers, who are responsible for the successful delivery of your construction project. Working closely with our clients, the team are well equipped to organise, control, and monitor ongoing construction operations. In addition to our project management team, we have a strong and capable technical administration department, which ensures all crucial paperwork is completed. We pride ourselves on the hands-on leadership and guidance we offer, from pre-commencement to completion.
Quantity Surveying
The quantity surveying team’s strengths lie in their diverse backgrounds within client organisations, professional practice and contracting. This breadth of exposure enables us to offer broad skillsets and experience on all projects across our sectors.
Our technical administration department provides additional support to the surveying team, ensuring the work produced is issued promptly and of the highest quality
With our team’s collective industry expertise, combined with a wealth of benchmarking data we acquire from our live projects, we can provide our clients with recommendations that accurately align with the changing business landscape.
In addition, we have access to RICS Membership, BCIS data, CostX measurement software and JCT online, whilst actively supporting quantity surveying apprenticeships with Nottingham Trent University, allowing us to continue onboarding new talent for the future of construction.

WE UNDERSTAND OUR CLIENT’S REQUIREMENTS, WORKING SEAMLESSLY TO PROVIDE PROACTIVE ADVICE ON A RANGE OF TECHNICAL ISSUES
Employer’s Agent
As employer’s agent, we ensure the project is structured correctly and that the investment value of the scheme is protected. As well as representing our client, we will administer the contract and complete all appointments, warranties, and other key legal documents, alongside organising, chairing, and recording meetings / key events.
We are there to support, advise and organise our clients. Depending on the requirement the role will be fulfilled by one of our senior project managers or project surveyors, with backup support from the wider technical team.
Principal Designer
As a business, we have invested heavily in training key members of the project management team as principal designers. As members of the APS, Association for Project Safety, we are competent in influencing how risks to health and safety are managed throughout the project.
When appointed as project managers on a scheme, we can extend our appointment to include principal designers where required.
Building Consultancy
The breadth of experience within our professional team means that we have worked across all property sectors, which allows us to provide our clients with detailed and reliable advice across the full property life cycle.
We understand our clients’ requirements, working seamlessly to provide proactive advice on a range of technical issues, including acquisition surveys and fund monitoring reporting, technical due diligence, landlord and tenant dilapidations claims, planned preventative maintenance, party wall matters, together with building refurbishment and fit out project management and contract administration services for projects of all shapes and sizes.
It is our professional team’s experience, knowledge, understanding and logical, lateral thinking that affords us the ability to provide the accurate, timely and focused advice our clients expect.

WITH THE BUSINESS LANDSCAPE CONSTANTLY CHANGING, WE UNDERSTAND THE IMPORTANCE OF PROVIDING OUR CLIENTS WITH ACCURATE COST PROJECTIONS
Data Analysis
Goodrich’s benchmarking data is solely based on contract data, thereby ensuring that only realworld information is used when compiling the benchmark ranges. The use of ‘real life’ contract data, rather than estimates or contractors’ cost plans, better reflects the fluctuations in materials, labour and rates. The data is continuously updated; this is undertaken on each contract sum analysis and only once the contract is awarded.
We understand that accurate cost information is paramount to allow our clients to have the confidence to make informed decisions throughout key project stages We have collated over 6 years of detailed I&L cost data, encompassing 13.33 million sq ft and just over £1 billion in combined value.
We have provided cost advice on a wide variety of building types ranging from £100k to £100m, and everything in between.


3.
ADDITIONAL SERVICES

Dilapidations
We work for both Landlords and Tenants, preparing schedules of dilapidations for Landlords and responding to schedules on behalf of Tenants. Our experienced team reviews all the legal documentation in preparing/responding to schedules, inspecting the demise for breaches under the terms of the lease and conducting negotiations to conclude the claim in accordance with the lease terms.
We also provide consultancy advice on dilapidation strategies including assessment of liability and obligations in preparation of lease events.
Building Survey
Our team of building consultants can carry out a detailed inspection and report on the structure and fabric of the property together with comments on the condition of the services, predominantly for the owner/occupiers. The report will also recommend additional specialist inspections and reports as required, i.e. services, environmental, deleterious materials, DDA, etc.
Licence to Alter
We will conduct a technical review of a tenant/occupier’s proposed works to assess the suitability of information received and compliance with Lease Terms or Covenants. Comment upon the impact on the structure and fabric of the property, and on the statutory and legal compliance of the proposed works. The report will also provide advice on reinstatement requirements to be considered for inclusion with any formal Licence to Alter.
Party Wall
We will manage negotiations on behalf of the building owner or adjoining owner of the terms and conditions applicable where works are affecting a party wall, having due regard to the Party Wall etc. Act 1996.

Quality Monitoring
We recognise the importance of quality when it comes to building. That’s why we have a mix of experts, many with building surveying and on-site backgrounds, who are placed to provide a constructive view on the quality and appropriateness of your built asset as the works progress.
Fund Monitoring
We have provided fund monitoring services to Barwood Capital, NatWest, Octopus and Handelsbanken for a variety of building projects. We are practical and realistic, providing guidance and advice as the project progresses from the agreement of funding through to completion.
Facilities and Property Management
We can care for your asset as part of our facilities and property management services, in a way that suits your business.
Covering all services from a soft-landing handover to operators and occupiers, management and provision of all hard and soft facilities services to the asset and occupiers, management of all operational health and safety compliance, budget and financial management, and reactive services management.
Our consultative services available include property operating budgets, services charge advice, operating lifecycle plans and operational best practice advice.
OUR CLIENTS 4.















5. Environmental Social Governance

At Goodrich, we understand the importance of being strategic in our approach to social responsibility We’re committed to raising awareness of both our individual and collective impact on the planet.
In partnership with Planet Mark, we gather and analyse key data across our business to gain valuable insight into our carbon footprint. This helps us identify the areas where change is most needed and where we can make the biggest difference With this knowledge, we can make informed decisions that drive meaningful improvements, not just within our business, but in the wider community too.
Reducing our environmental footprint is a responsibility we take seriously We are focused on taking proactive, forward-thinking steps that support positive change for the planet and society, helping to build a more sustainable future for all.
As our business continues to grow, we recognise that balancing progress with sustainability presents its challenges. However, we remain committed to exploring new initiatives that help us meet our carbon reduction goals.
Each year, we report on our performance across the following key categories:
Scope 1
The emissions from sources that a company creates directly.
Scope 2
The emissions a company creates indirectly, associated with the energy it purchases
Scope 3
The emissions that are not produced by the company itself, but by those within the company’s value chain.
Our teams also play a vital role in driving our CSR efforts. Every year, each team is encouraged to support their local communities, schools, and charities by organising at least two CSR events to encourage a culture inspired by involvement and impact.

6.
Case Studies
CASE STUDY
Project Name:
Client Name:
Project Details:
Project Address:
Project Value:
Contract Duration:
Key Facts:



660,000 sq ft unit for Ball Engineering
SEGRO plc / Ball
Engineering
Full turnkey construction of a new 660,000 sq ft building to operate as a can making facility for Ball
Maynard Road, Burton Latimer, Northampton NN15 5ZS
£51 million
63 weeks
▪ The building is split into four distinct areas which are the offices, the production hall, the storage area and the technical rooms. There are detailed / complex M&E installations throughout the manufacturing hall
▪ EPC A rated
▪ Close working with the occupier was required to provide infrastructure for their plant install machinery
▪ 15 staged early access dates helped the occupier maintain the go live programme. Goodrich managed over £8 million worth of change requests for this project
▪ The technical rooms act to support the 24-hour can production operation and house equipment, spares and supplies
▪ Within the building there are a number of ATEX rated rooms that hold flammable liquids and specialist trenches and sumps to collect and hold liquid spillages

CASE STUDY
Project Name:
Client Name:
Project Details:
Project Address:
Project Value:
Contract Duration:
Key Facts:



Project Gray, Biggleswade
Co-op Supply and Logistics
Fit-out of 800,000 sq ft warehouse, office, separate vehicle maintenance unit, de-kit building, HGV wash and weigh station.
This development comprised 64 dock bays, a freezer box of 80,000 sq ft, chill marshall, offices, restaurant and other welfare and office amenities; respecting the diverse workforce and the health and wellbeing of all employees.
Symmetry Park, Gold Road, Biggleswade
£33 million
35 weeks
Office and welfare areas developed following WELL principles and cultural requirements of the diverse heritage of staff and workforce.


CASE STUDY
Project Name:
Client Name:
Project Details:
Project Address:
Project Value:
Contract Duration:
Key Facts:



The Arc, Snodland
Wrenbridge Land Limited, OBO LaSalle Asset Management and Coal Pension Properties
The project comprised the design and construction of four industrial units and two roadside offerings at the junction of the A228 and Peter’s Bridge, Holborough Road, Snodland. Industrial Units A and D are detached, Units B and C are semi-detached and all with integral offices, together with external works including parking and circulation areas, footpaths, drainage, and external lighting. The roadside offerings comprise a drivethru Costa Coffee and Mcdonald’s.
The 4 industrial units total circa 122,000 sq ft (GIA’s)
Unit A - 68,783 sq ft
Unit B - 20,667 sq ft
Unit C - 14,510 sq ft
Unit D - 17,922 sq ft
Holborough Road, Snodland, Kent
£12 million
52 weeks
• The Grade A units sit on an 8-acre site located to the north of Snodland Town Centre in a very prominent position, with direct access to the A228
• The units benefit from up-to-date modern amenities including car charging points and a pocket park to the south of the site
• The project has also achieved BREEAM ‘Excellent’ and an EPC ‘A’ rating


CASE STUDY
Project Name:
Client Name:
Project Details:
Project Address:
Project Value:
Contract Duration:
Key Facts:



Esmere Gardens, Moreton-in-Marsh
Taylor and Taylor Limited
A new build 60-bedroom residential care home, which is constructed over two floors and totalling 33,500 sq ft
Fosseway Farm, Stowe Road, Moreton-in-Marsh GL56 0DS
£8.05 million
75 weeks
• The care home has been built to strict Cotswold Planning Design Guidelines and features attractive, contemporary design together with the use of traditional Cotswold materials
• 100% en-suite provision set over two floors within a 1.4 acre site with stunning views of the Cotswolds
• Extensive range of facilities including a café, dining rooms, a hairdresser, cinema lounge, resident lounges and informal seating areas
• 21 car parking spaces with EV charging points available, directly accessed from Fosse Way
• Extensive landscaping with private gardens that fit into the local surroundings
• Adjacent sports and social facilities available for residents to join


CASE STUDY


Bedford Girls’ School, Sixth Form Common Room and Café Refurbishment Project Project Name:
Client Name:
Project Details:
Project Address:
Project Value:
Contract Duration:
Key Facts:
“I
like working with professionals like Goodrich Consulting. The project was very well managed.”
Jean-Marc Hodgkin
Bursar

The Harpur Trust
The spaces were converted back in 2005 and were in need of a refresh as the common room had slowly developed into an uninspiring corridor. The area itself felt dark with a miss match of furniture and fittings, and little connection to the inner garden courtyard. The café was underutilised due to a lack of cooking facilities, with students preferring to use local shops for lunch. We developed the brief with the school with these key design drivers in mind
Cardington Road, Bedford
We had a strict project limit of £550,000 including fees, planning costs, equipment, furniture, building works and VAT
We had the 6 weeks during the summer break to deliver the scheme
The post-pandemic economy was a serious consideration on this scheme, and the team had concerns about furniture and equipment availability, along with contractor interest and availability. Therefore, we brought in specialist furniture and catering advisors and recommended early contractor involvement from October 2021. We also advised on placing orders for the furniture, café servery, equipment and bifold doors at the earliest opportunity. The sector demanded negotiation, and the school managed to gain agreement from the charity board. Securing this flexibility was a key decision in the successful delivery of this scheme.
A short delivery programme is always a key consideration on school projects, so we arranged for the asbestos, structural and services inspections during the half-term break.
One of the most important aspects was that the project cost was immovable on this scheme and therefore our estimating, contractor negotiation and postcontract cost control had to be accurate. Due to our team’s efforts, the project came in just under budget and, most importantly, met the client’s brief fully.


CASE STUDY
Project Name:
Client Name:
Project Details:
Project Address:
Project Value:
Contract Duration:
Key Facts:



Northampton School for Boys, Leisure Centre
Northampton School for Boys
The project consisted of a new build swimming pool and health and fitness suite
Billing Road, Northampton
£4.2 million
57 weeks
• The project was developed with low running costs in mind. The new pool and water treatment plant is tier 1 in terms of quality, therein reducing the cost of maintaining the facility
• The swimming pool is a 2-metre-deep competition pool with a 9-metrelong movable floor
• The scheme also included a dance studio, fitness suite, entrance foyer and a variety of changing areas


CASE STUDY
Project Name:
Client Name:
Project Details:
Project Address:
Project Value:
Contract Duration:
Key Facts:


Base Build Monitoring and Fit-Out of Customer Fulfilment Centre, Purfleet
Fit-out of a newly built warehouse, including construction of mezzanine floors, M&E, refrigeration services, internal partitions and division walls, office fitout, lifts, protection, fuelling facilities, vehicle wash and associated builders’ work
Purfleet Road, Aveley, Essex
£70 million
60 weeks (Base Build and Fit-Out)
• Ocado new automated Fulfilment Centre
• BREEAM ‘Excellent’
• Works completed in May 2021
• Design Team consisted of Goodrich, Architects Ashton Smith Associates, Fairhurst (Civil & Structural Engineers) and MBA Consulting Engineers on the building services

Ocado
CASE STUDY
Project Name:
Client Name:
Project Details:
Project Address:
Contract Duration:
Key Facts:

SmartParc, Infrastructure
SEGRO

The scheme involves the construction of 9 new building plots totalling two million sq ft across a brown field site of over 100 acres. The works involved extensive road infrastructure, footpaths, below ground services including utilities, drainage and DH&C pipework and various forms of highway works.
Spondon, Derby DE21 7BS
125 weeks
• The infrastructure includes the installation of District Heating and Cooling to provide energy efficiencies to all plots on the park
• Significant offsite utility reinforcement works
• Significant Highways works including liaising with Highways England

CASE STUDY
Project Name:
Client Name:
Project Details:
Project Address:
Project Value:
Contract Duration:
Key Facts:


East Midlands Airport

A new sortation hub, 232,506 sq ft parcel hub with two storey integral offices which house a new Call Centre space for the UK International Gateway to other DHL hubs
Castle Donington, Derby
£56 million
62 weeks
• Extension and turnkey fit-out and integration of automation into the existing aviation hub
• All works were undertaken during a ‘live’ operation
• The project achieved a BREEAM ‘Excellent’ and EPC ‘A’ rating


DHL Aviation
CASE STUDY
Project Name:
Project Details:
Project Value:
Contract Duration:
Key Facts:


Enabling and Infrastructure, Bristol
The site is a new industrial/distribution development located in Bristol, extending to 65 acres.
£10-£15 million
15 months
The works aim to secure viability for future development. The site will offer a variety of unit sizes ranging from 133,438 - 584,361 sq ft within three separate phases. Future development to achieve BREEAM rating ‘Excellent’.
Goodrich was appointed to commission and manage the early-stage enabling works. These include:
• Ecology Mitigation: Reptile clearance and establishment of a suitable receiver zone
• Public Right Of Way (PRoW) Diversion: Management of the design and application process
• Archaeological Investigations: Archaeological geophysical survey and follow-on evaluation that comprised 112no trenches. The survey work identified a significant level of interest and required a programme of strip, map and sample excavation across the site to remove any future development constraint within the boundary
• Rhine Diversion and Water Vole Translocation: Diversion of a surface water flood rhine to maximise the developable area, including securing permissions from Natural England and translocation of water voles
• Electrical Infrastructure Upgrade: Management of the application process and provision of a new 10MVA primary sub-station
• Foul Water Pump Station and Rising Main: Management of the S104 technical and legal applications to secure a new foul water connection for the development site
• Site Clearance and Upfilling: Procuring civil design and contractor appointment to undertake a package of site strip, disposal and upfilling to provide a suitable load-bearing plateau for future development
CASE STUDY
Project Name:
Client Name:
Project Details:
Project Address/ Postcode:
Project Value:
Contract Duration:
Key Facts:



Bicester Gateway
Bloombridge Development Partners
12 ‘Knowledge Economy’ Units in Use Class E. 14,972 m2 (161,157 sq ft)
Bicester Gateway, Oxfordshire OX 25 2PA
£20 million
The project is currently Pre-Contract. The planning decision was received on the 11th of November 2022.
The proposals specifically target the Knowledge Economy market with specific features of the buildings, including:
• Enhanced elevational treatments
• Increased power supply
• Planning for flues/louvres to be obtained with the base build application
• A higher percentage of base build office space
• A roof level plant deck with capacity for Cat B plant to suit a laboratory occupier
• BREEAM ‘Excellent’
• Standalone swift tower to suit the local ecology, without compromising the appearance of the buildings

CASE STUDY
Letchworth Gateway Project Name:
Client Name:
Project Details:
Project Address:
Project Value:
Contract Duration:
Key Facts:


Aberdeen Asset Management
Construction of a new Aldi supermarket, Travelodge hotel, McDonald’s and coffee drive-thru.
Ave One, Letchworth Garden City
£8.6 million
66 weeks
The project incorporated a single-storey Aldi supermarket and a three-storey hotel operated by Travelodge, providing 73 bedrooms comprising 36 family rooms, 33 double rooms and four accessible rooms. The ground floor level of the hotel also houses a breakfast space for guests in a small bar area.
The scheme involved a single-storey restaurant/drive-thru unit operated by McDonald’s Restaurants and a coffee shop with a drive-thru facility.

CASE STUDY
Project Name:
Client Name:
Project Details:
Project Address:
Project Value:
Contract Duration:
Key Facts:


Southern Hub, Poyle
DHL Express
New 142,350 sq ft DHL Express Headquarters and Parcel Sortation Hub with integral offices
Southern Hub, Unit 1 Horton Rd, Colnbrook, Slough SL3 0BB
£19 million
47 weeks
• Works involved the demolition and remediation of existing buildings
• Solar PV panels to the roof to align with DHL’s ‘go green’ strategy
• Full fit-out of offices, external service yard areas i.e. fuel islands, vehicle wash facilities
• BREEAM ‘Excellent’ and EPC ‘A’



CASE STUDY
Project Name:
Client Name:
Project Details:
Project Address:
Project Value:
Contract Duration:
Key Facts:


iFLY London
iFLY Indoor Skydiving Ltd
iFLY at The O2
O2 Arena, Drawdock Road, North Greenwich, SE10 0BB
£5.5 million
55 weeks

The new wind tunnel is the fourth indoor skydiving facility built and operated in the United Kingdom by iFLY. It is the first of the new generation 9 tunnels to be built in the UK and the most powerful to date.
The entrance/reception area incorporate a licensed bar to entertain flyers and those attending events at the O2.
iFLY was granted a licence that enables them to operate the wind tunnel late into the evening, to provide an exhilarating experience for visitors and concert/event goers.


CASE STUDY
Project Name:
Client Name:
Project Details:
Project Address:
Project Value:
Contract Duration:
Key Facts:


New Build Retail Park, Travis Perkins
Travis Perkins
Construction of a Travis Perkins Branch and new build retail park
Marsh Barton Industrial Estate, Exeter
£3,966,464
47 weeks

• The site was previously occupied by a large printing company which covered virtually the entire area of the site. A large-scale demolition and remediation project had to be undertaken to prepare the site for redevelopment
• Due to the flooding risk in this part of Exeter, a wide variety of flood prevention measures were included in the build works
• Given the shared boundary with two motor dealerships, the works needed to be undertaken in a careful and thoughtful manner to avoid disruption