Clifford L. Allenby Building E-blast Volume 1, Issue 2
April 2019
Introduction In this edition of our monthly E-blast, we explore how the building is designed to perform as efficiently as possible, how innovative heating and cooling systems will create a comfortable environment, and what you can do to help the building achieve Zero Net Energy (ZNE).
Reinforcing at shear walls and deck at 1st floor west side.
Construction Update
Architectural wall forms at north side of 1st floor.
Save the Date
Clifford L. Allenby Building Town Hall April 10, 2019, 1:00pm Bateson Building Atrium We welcome your questions, comments, and suggestions for topics for future E-blasts. Please submit to OStreet@chhs.ca.gov
At this time, the placement of the concrete slab at the first floor is complete. Shear wall and column concrete are complete on the east side of the first floor, and reinforcing is in progress on the west side. Architectural wall forms between the first and second floors have been erected on the north side. Chilled water piping is in use, servicing the Clifford L. Allenby Building, the California Department of Food & Agriculture, and the California Department of Veterans Affairs.
Concrete placement 1st floor west side.
Work in April will include completion of walls and columns to the second floor on the west side, architectural walls to the second floor on the east side, and the forming of the second-floor deck. Shear walls and columns to 2nd Floor at the east side.
Questions, comments, suggestions? Please submit to OStreet@chhs.ca.gov
Clifford L. Allenby Building E-blast_Volume 1_Issue 2_April 2019