New Building Presentation

Page 1

GENERAL UPDATE 29 MARCH 2012


NEW SU BUILD

/ THREE PHASE < March 2013

< July 2013

< September 2013


NEW SU BUILD

/ NEW LOCATION


NEW SU BUILD

• • • • •

/ OUR BUILDING

Social Engaging Reflect our purpose Sit comfortably in it’s surroundings Offer similar services to our current basis and enable us to improve on these services • Not to fall out-of-scope, bearing in mind the new campus masterplan


NEW SU BUILD

/ NEW LOCATION


NEW SU BUILD

/ BUILDING SHAPE


NEW SU BUILD

/ EXTERIOR


NEW SU BUILD

/ ARRANGEMENT


NEW SU BUILD

/ GENERAL ARRANGEMENT


NEW SU BUILD

/ GENERAL ARRANGEMENT


NEW SU BUILD

/ NATURAL LIGHT


NEW SU BUILD

/ OTHER FACTS

• Total budget is £8.8 million • Of which construction is £5.4 million • Internal size 3000 sq/m • 64% bigger than the space at Frenchay SU


NEW SU BUILD

/ KEY DATES

• Planning Application / 27th April 2012 – Can take 13 weeks to process

• Building Stars / 27th August 2012 • Move in / July 2013 • Official Opening / Freshers 2013