LACROSSE AVENUE EXTENSION BY: TEAM TENN (SHAUNITA CABLE, JOEL GRADIN, ETHAN HARDT, JAROD SHANNON) SPONSOR: WELCH COMER ENGINEERS (MELISSA CLEVELAND, JACK GRIFFING) Background The Riverstone Development in Coeur d'Alene, ID.

has seen a rise in population and requires a new point of access. Further, a trailhead for the Centennial Trail and a connection to it are desired.

Intersection Design Objectives ❖ Provide a safe and walkable connection for pedestrians • Redesign ramps to meet ADA standards • Place mast arms close to ramps ❖ Ease congestion by designing a signalized intersection

Road Extension Design Objectives

❖ Relieve congestion in the Riverstone Development Area ❖ Provide vehicular, pedestrian, and bicycle access to the Centennial Trail ❖ Provide access and utilities for future developments along Lacrosse Avenue

Parking Lot Design Objectives

❖ Additional parking for Centennial Trail users

Cost Estimate

❖ Secondary fire access and connection to Bellerive Lane

❖Goal Budget: $1,800,000

❖ Parking for a future City park nearby

❖Proposed Cost: $1,520,000