Coylton Section 36 Newsletter

Page 1

Coylton Greener Grid Park Public Consultation September 2024

Thank you for attending public consultations for Coylton Greener Grid Park. Coylton already has planning permission for a Greener Grid Park of up to 50MW, currently under construction. We are making an application to the Scottish Government under section 36 of the Electricity Act 1989 to increase the operating capacity of the Greener Grid Park above 50MW. We expect the visual appearance of the project to remain the same as the consented application.

OCHILTREE

DRONGAN

Coylton Greener Grid Park

Coylton Greener Grid Park Increased Capacity, Same Visual Appearance Consented 50MW Application, Under Construction

© Crown copyright and database rights 2022 Ordnance Survey 0100031673

Section 36 Application to Increase Capacity

146.6m

146.6m

El Sub Sta

El Sub Sta

Electricity Distribution Site

Electricity Distribution Site

8

8

9

9

10

10 6

6

11

11

4

4 3

5

3

7

1

1

2

2

12

7

LEGEND

1 2 3 4 5

APPLICATION SITE BOUNDARY NOISE ATTENUATION/ SECURITY FENCING (4.5m high) COMMS HOUSE (5.63m high) AUX TRANSFORMER (2.50m high) INDICATIVE BATTERY BLOCK STORES (2.60m high) OFFICES (3.60m high)

7

LEGEND 6 7 8 9 10 11 12

GATE (4.5m high) PROPOSED SuDS POND EXISTING TREES & HEDGEROWS PROPOSED TREES & HEDGEROWS PROPOSED WILDFLOWER PLANTING HV EQUIPMENT (8m high) UNDER CONSTRUCTION

The highlighted area in yellow (12) is currently under construction.

Project website: www.statkraft.co.uk/coylton

1 2 3 4 5

APPLICATION SITE BOUNDARY NOISE ATTENUATION/ SECURITY FENCING (4.5m high) COMMS HOUSE (5.63m high) AUX TRANSFORMER (2.50m high) INDICATIVE BATTERY BLOCK STORES (2.60m high) OFFICES (3.60m high)

6 7 8 9 10 11

GATE (4.5m high) PROPOSED SuDS POND EXISTING TREES & HEDGEROWS PROPOSED TREES & HEDGEROWS PROPOSED WILDFLOWER PLANTING HV EQUIPMENT (8m high)

Statkraft intends to submit a Section 36 application in 2024 to increase the energy capacity of the project and we expect the visual appearance to remain the same as the consented 50MW application.