S UMMER IS FINALLY HERE — WE HOPE !! After a rather cool spring, summer is finally here— we hope! Here’s our brief “what’s happening” around here— projects, security, gallery rentals, ongoing sustainability initiatives…..
Project Update
HVAC Project
The HVAC project was completed as of March 31st! We were on time and on budget—with even a little funding to spare. Our final reports have been sent to the Government. As with any new equipment, a few minor bugs are being worked on under warranty. The equipment is however ticking along just great!
Vertical Lift — First
The electrical upgrade and emergency generator project was also completed as of March 31st. Over the last couple of months, there were some minor deficiencies being addressed — again covered under warranty. The good news is that
The lift was installed by March 31st and has been inspected and signed off by both the BC Safety Authority and the City Building Inspector. Final touch ups, installation of the graphics, cleaning, took place during the month of April. On April 27th, the lift was “officially” opened. Pauline and Margaret (a long time volunteer) were the first to ride the lift! Minor tweaking is still underway to make sure it is easy to understand and use for our visitor.
The project also included entering artifact information into Mammoth; the reinterpretation and reinstallation of artifacts; the development and implementation of new signage and graphics and security upgrades.
The fire suppression and
there will be NO more intentional power outages to contend with.
you. So, you won’t have to work in the dark for that hour!
On a go forward basis, the emergency generator will be tested monthly from 7 AM—8 AM. You may hear the generators running but there will be no power shut downs that should affect
www.bchydro.com www.crd.bc.ca www.livesmartbc.ca
I IN THIS ISSUE : P ROJECT U PDATES
1
P ROJECTS & PMO U PDATE
2
DID YOU KNOW ?
2
A bronze statue of Dr. Helmcken (created and donated by artist Armando Barbon) was installed. The buildings were reopened on May 19th. The Dr. Helmcken bronze was also publicly unveiled. (Con’t on pg 2)
Helmcken House and St. Ann’s Schoolhouse
Electrical Upgrade
monitoring project (launched last June) was completed in May. The system has been signed off by the various Inspectors and both buildings now have fire protection.
Peoples Gallery
A DDITIONAL L INKS :
The new native plant garden above and beside the generator room is beginning to fill out too and some new signage has been installed.
O UR R ECYCLING P ROGRAM STATS : G LASS / TIN = 2683 CU FT O RGANICS = 2012 CU FT C ARDBOARD = 11232 CU FT SHREDDED PAPER 1980 LBS I T IS E STIMATED THAT NINE - 40 FOOT TRAILER LOADS KEPT OUT OF THE LANDFILL EACH YEAR !!