Redeemer Campus Master Planning Budget 7-2023

Page 1

Redeemer Campus Master Planning Estimated costs and key deliverables request to budget to date 07/18/2023 Item

Activity

External service provider

Campus master planning activities Project Management & Architectural Cushman & Consultant Wakefield 1

Administrative

$ 108,800

Contracted Cost

$108,000

Expense to date

$ 67,200

$61,875

Expected Spend

$59,987

$14,903

internal

Visioning & Programming

2

Estimated Cost

$61,875

Total Key Deliverables

$59,987

$10,000

$0

$24,903

$61,875

Concept Design / Master Planning LAS/ Ennead

3

$ 154,200

$159,235

$152,970

$2,536

$2,536

$11,032

$2,231

4

Pre-Design Cost Estimating

$ 6,000

5

Final Master Plan & Report

$ 14,400 $ 6,200

Consultant Reimbursables Contingency Subtotal Additional potential pre-design costs Add’l cost estimation

Other

$ 4,000 $ 360,800

$152,970

$294,642

$8,000

 Value and goals identification with congregation, partners, and community  Site, code, and zoning research/analysis  HP & sustainability assessment  Documentation of existing space  ~20 visioning and programming sessions and meetings with congregation, ministry teams, Council & staff  Development of campus and ministry programming space options/needs (space types, sizes, functional criteria) using congregation, partner, and community input  Final Visioning document  Final Programming document  Zoning & building code impact assessment  ~10 master planning meetings and presentations with congregation, ministry teams, Council & staff  Site evaluation based on Vision & Programming options (e.g., physical site, access, parking, environmental)  Building evaluation based on Vision & Programming (codes, materials/conditions, structural/infrastructure systems  Conceptual Drawing and documents showing land use, new or existing building development, access/circulation, landscape

 Preliminary cost estimation for proposed options $0

$2,536

$8,801

$11,032

$140 $342,678

 RFP creation and process mgmt..  Architectural consulting support  Planning process coordination & mgmt

 Final Campus Master Plan report and presentation

$140 $10,000 $28,801

$10,000 $323,443

$8,000

$8,000

Civil Engineering Traffic Engineering

TBD, if necessary

TBD, if necessary

Building Scanning

6

$19,780

$19,780

$19,780

The need and specific expense for these line items and cost categories will depend on the options defined as part of the concept design/master planning and cost estimating steps.

Geotech Survey Pre-design costs, if necessary

$0 $ 0 - $ 139,200

Total estimated costs 7/18/2023v2

$362,458 $360,800 - $500,000

$314,422

$36,801

$351,223

Variance against contracted cost is based on unneeded services from Cushman and Wakefield.