Product Development Management Test Questions - 1197 Verified Questions

Page 1


Product Development Management

Test Questions

Course Introduction

Product Development Management explores the strategic and operational aspects of bringing new products to market, from initial idea generation through to commercialization. The course covers key topics such as market research, product design, prototyping, project management, cross-functional team collaboration, and lifecycle management. Students learn methodologies like stage-gate processes, agile development, and lean innovation, developing skills to manage risk, align product features with customer needs, and ensure timely and cost-effective delivery. By analyzing real-world case studies and engaging in practical assignments, students gain hands-on experience in planning, executing, and optimizing product development initiatives within a competitive business environment.

Recommended Textbook

Successful Project Management 6th Edition by Jack Gido

Available Study Resources on Quizplus 13 Chapters

1197 Verified Questions

1197 Flashcards

Source URL: https://quizplus.com/study-set/3621 Page 2

Chapter 1: Project Management Concepts

Available Study Resources on Quizplus for this Chatper

79 Verified Questions

79 Flashcards

Source URL: https://quizplus.com/quiz/71896

Sample Questions

Q1) The following mechanisms help to assure quality expectations are met:

A)Audits, inspections, and standards throughout the project.

B)Inspections only at the end of the project.

C)Only a list of standards is needed at the start of the project

D)No mechanisms are needed to assure quality.

Answer: A

Q2) The stakeholder register is a convenient tool to keep

A)stakeholders at a distance from the project.

B)all stakeholder information consolidated and up-to-date.

C)all communications open to all stakeholders.

D)lessons learned.

Answer: B

Q3) The project objective requires completing the project work scope and producing all the deliverables by a certain time and within budget.

A)True

B)False

Answer: True

Q4) Give an example of a project objective.

Answer: Answers will vary.Response includes a deliverable, schedule, and budget.

To view all questions and flashcards with answers, click on the resource link above. Page 3

Chapter 2: Identifying and Selecting Projects

Available Study Resources on Quizplus for this Chatper

70 Verified Questions

70 Flashcards

Source URL: https://quizplus.com/quiz/71897

Sample Questions

Q1) Every project that is identified is selected to be completed.

A)True

B)False

Answer: False

Q2) The project purpose in the project charter may include prior documents for selecting the project.

A)True

B)False

Answer: False

Q3) A request for proposals helps the organization decide which contractor to use.

A)True

B)False

Answer: True

Q4) An assumption for a construction project could be

A)the materials to be used to construct the building.

B)a grant will be secured to help fund the project.

C)the regulations and codes required for the building.

D)the size of the building that is to be constructed.

Answer: B

To view all questions and flashcards with answers, click on the resource link above. Page 4

Chapter 3: Developing Project Proposals

Available Study Resources on Quizplus for this Chatper

112 Verified Questions

112 Flashcards

Source URL: https://quizplus.com/quiz/71898

Sample Questions

Q1) The reputation of the company that announced the RFP should be evaluated as a factor as well as the reputation of the contractor when making a bid or no-bid decision.

A)True

B)False

Answer: True

Q2) For clarification on a specific proposal, a customer may send a list of questions to be answered.

A)True

B)False

Answer: True

Q3) Describe at least three criteria that a customer could use to evaluate a contractor's proposal.

Answer: Responses will vary.Answers should describe at least three of the following: compliance, understanding of need, soundness and practicality of the proposed solution, experience, realism of the schedule, price, benefit to organization, and value. Customers evaluate contractors' proposals in many different ways.

To view all questions and flashcards with answers, click on the resource link above. Page 5

Chapter 4: Defining Scope, Quality, Responsibility, and Activity Sequence

Available Study Resources on Quizplus for this Chatper

129 Verified Questions

129 Flashcards

Source URL: https://quizplus.com/quiz/71899

Sample Questions

Q1) An understanding of project deliverables would also be a setback to developing a good working relationship with the customer.

A)True

B)False

Q2) A shows their appropriate sequence and defines the dependent relationships indicating how the activities need to be performed to accomplish the overall project work scope and produce the deliverables.

A)responsibility assignment matrix

B)network diagram

C)work breakdown structure

D)project scope document

Q3) If the scope seems much less than originally anticipated by the customer, the customer and contractor would have to agree on increasing the budget, extending the schedule, reducing the scope, or some combination thereof.

A)True

B)False

Q4) Certain activities in a network diagram have to be done in serial sequence.

A)True

B)False

To view all questions and flashcards with answers, click on the resource link above. Page 6

Chapter 5: Developing the Schedule

Available Study Resources on Quizplus for this Chatper

86 Verified Questions

86 Flashcards

Source URL: https://quizplus.com/quiz/71900

Sample Questions

Q1) The estimated duration for an activity must be based on the estimated quantity of resources required to perform the activity.

A)True

B)False

Q2) The total completion time is 25 days.Task A is planned to take seven days.Task B is planned to take five days.Task C is planned to take eight days.The tasks have a serial relationship.How much slack does the project have?

A)Negative 5 days slack.

B)Positive 5 days slack.

C)Positive 17 days slack.

D)Positive 3 days slack.

Q3) It is a good practice to have the person who will be responsible for performing a specific activity estimate the duration that other resources would need to complete that activity.

A)True

B)False

Q4) Schedule control involves four steps.List the four steps in order.

To view all questions and flashcards with answers, click on the resource link above.

7

Chapter 6: Resource Utilization

Available Study Resources on Quizplus for this Chatper

22 Verified Questions

22 Flashcards

Source URL: https://quizplus.com/quiz/71901

Sample Questions

Q1) The statement, "Network diagrams illustrate the technical constraints among activities," means the activities are constrained because

A)each of the activities are independent from the other activities.

B)one activity cannot be started until the predecessors are finished.

C)the activities use different resources to be completed.

D)some activities use the same resources that may not be available.

Q2) Resource leveling, or smoothing, is a method for

A)developing a schedule that attempts to minimize the fluctuations in requirements for resources.

B)making sure all the resources do the same amount of work.

C)making sure every task has the same number of resources.

D)extending the project to have the least number of resources used per day.

Q3) Activities can be delayed only to the point where all their positive slack is used up, as any further delays would cause the project to

A)increase costs of all the activities in the project.

B)extend beyond the project completion time.

C)be completed ahead of schedule.

D)increase its requirements for additional resources for all activities.

To view all questions and flashcards with answers, click on the resource link above. Page 8

Chapter 7: Determining Costs, Budget, and Earned Value

Available Study Resources on Quizplus for this Chatper

69 Verified Questions

69 Flashcards

Source URL: https://quizplus.com/quiz/71902

Sample Questions

Q1) The is the product of the percent complete and the sum of the estimated costs of all the specific activities that make up a work package or the project.

A)total budgeted cost TBC)

B)cumulative budgeted cost CBC)

C)cumulative actual cost CAC)

D)cumulative earned value CEV)

Q2) Plot curves on the same graph to reveal any trends toward improving or deteriorating cost performance.

A)AC, TBC, EV

B)actual cost and budgeted cost

C)CBC, CAC, and CEV

D)CBC, PV, and BCWS

Q3) The budget for each work package is

A)charged completely on the first day of the work package.

B)charged at the end of the project.

C)distributed over the duration of the work package.

D)charged completely on the last day of the work package.

To view all questions and flashcards with answers, click on the resource link above.

9

Chapter 8: Managing Risk

Available Study Resources on Quizplus for this Chatper

45 Verified Questions

45 Flashcards

Source URL: https://quizplus.com/quiz/71903

Sample Questions

Q1) includes determining which risks may adversely affect the project objective and what the impact of each risk might be if it occurs.

A)Risk modification

B)Risk avoidance

C)Risk identification

D)Risk acceptance

Q2) If the risks seem too great, the contractor may decide to not bid on a proposed project.

A)True

B)False

Q3) are a good forum for regularly reviewing, updating, and addressing risks.

A)Social gatherings of the team

B)Project meetings

C)Problem solving meetings

D)Project planning meetings

Q4) Risks are prioritized based on

A)the likelihood of occurrence and degree of impact.

B)the order they are identified.

C)the gut feeling of the project team.

D)the priorities set in a different project.

Page 10

To view all questions and flashcards with answers, click on the resource link above.

Chapter 9: Closing the Project

Available Study Resources on Quizplus for this Chatper

42 Verified Questions

42 Flashcards

Source URL: https://quizplus.com/quiz/71904

Sample Questions

Q1) Why should the project organization establish a knowledge base system for the organization?

Q2) Just as important as having the internal post-project meetings within the project organization is having a post-project evaluation meeting with the customer or sponsor.

A)True

B)False

Q3) The project team should wait until the end of the project to capture and document lessons learned.

A)True

B)False

Q4) Participants of should include the project manager, key project team members, and key representatives of the customer's organization who were involved with the project.

A)a post-project evaluation meeting with the customer or sponsor

B)a project progress meeting with project stakeholders

C)an analysis session with the project team

D)a pre-RFP meeting with the customer

Q5) What type of knowledge base system should be established by the project organization?

To view all questions and flashcards with answers, click on the resource link above. Page 11

Chapter 10: The Project Manager

Available Study Resources on Quizplus for this Chatper

129 Verified Questions

129 Flashcards

Source URL: https://quizplus.com/quiz/71905

Sample Questions

Q1) Good interpersonal skills enable a project manager to empathize with individuals when special circumstances arise.

A)True

B)False

Q2) is one of the ways to develop the skills necessary to be an effective project manager.

A)Learn from others

B)Talk to groups

C)Limit exposure to other project teams

D)Receive a single journal subscription

Q3) A high level of communication is especially important early in the project to build a competitive working relationship with the project team and to establish low expectations with the customer.

A)True

B)False

Q4) Conduct a self-evaluation, and learn from your mistakes to be an effective project manager.

A)True

B)False

To view all questions and flashcards with answers, click on the resource link above.

Page 12

Chapter 11: The Project Team

Available Study Resources on Quizplus for this Chatper

225 Verified Questions

225 Flashcards

Source URL: https://quizplus.com/quiz/71906

Sample Questions

Q1) Withholding or falsifying information is acceptable.

A)True

B)False

Q2) A potential conflict on projects is Schedule where conflict can result from differences of opinion about the sequence in which the work should be done or about how long the work should take.

A)True

B)False

Q3) Customers and suppliers want to do business with people they can

A)keep at a distance.

B)manipulate.

C)trust.

D)cheat.

Q4) Project team members should stereotype or make assumptions about a team member's behavior or performance based on their diversity.

A)True

B)False

Q5) List some dimensions of diversity:

Q6) List examples of situations that provide an opportunity for unethical behavior:

To view all questions and flashcards with answers, click on the resource link above. Page 13

Chapter 12: Project Communication and Documentation

Available Study Resources on Quizplus for this Chatper

124 Verified Questions

124 Flashcards

Source URL: https://quizplus.com/quiz/71907

Sample Questions

Q1) Lengthy dissertations or voluminous extraneous attachments may be perception of being flooded with emails or electronic messages and be more of a hindrance than a help.

A)True

B)False

Q2) Listening is more than just letting the other person talk.It must be

A)a passive, not an active, process.

B)an impatient, not a patient, process.

C)an reactive, not a proactive, process.

D)an active, not a passive, process.

Q3) The project manager should prepare notes or a final outline to use or refer to during the presentation.

A)True

B)False

Q4) Body language can be used not only by the person talking, but also by the listener, as a way of providing feedback to the person talking.

A)True

B)False

Q5) List some common barriers to effective listening:

To view all questions and flashcards with answers, click on the resource link above. Page 14

Chapter 13: Project Management Organizational Structures

Available Study Resources on Quizplus for this Chatper

65 Verified Questions

65 Flashcards

Source URL: https://quizplus.com/quiz/71908

Sample Questions

Q1) work groups consist of individuals who perform the same function, such as engineering or manufacturing.

A)An autonomous project organizational structure

B)A functional organizational structure

C)A matrix organizational structure

D)A project management office

Q2) allows efficient utilization of resources by having individuals from various functions assigned to work on specific projects.

A)an autonomous project organizational structure

B)a functional organizational structure

C)a matrix organizational structure

D)a project management office

Q3) A disadvantage of a functional organizational structure is that there is a lack of customer focus.

A)True

B)False

To view all questions and flashcards with answers, click on the resource link above. Page 15