Page 1


Management Science

Pre-Test Questions

Course Introduction

Management Science is an interdisciplinary field that applies analytical methods and quantitative techniques to decision-making processes in organizations. The course covers a range of topics including linear programming, simulation, decision analysis, and forecasting, enabling students to solve complex management problems and optimize operations. Emphasis is placed on the use of mathematical models, computational tools, and practical case studies to develop effective strategies in areas such as resource allocation, scheduling, and supply chain management. By integrating theory with real-world applications, Management Science equips students with the skills needed to tackle organizational challenges and improve overall performance.

Recommended Textbook

Project Management A Managerial Approach 10th Edition by Jack R. Meredith

Available Study Resources on Quizplus

13 Chapters

683 Verified Questions

683 Flashcards

Source URL: https://quizplus.com/study-set/2431 Page 2

Chapter 1: Projects in Contemporary Organizations

Available Study Resources on Quizplus for this Chatper

46 Verified Questions

46 Flashcards

Source URL: https://quizplus.com/quiz/48288

Sample Questions

Q1) When done properly,project management begins with __________.

A)stakeholder interviews

B)scope definition

C)the initial concept for the project

D)budget estimation

Answer: C

Q2) The conventional project life cycle can be described as a pattern characterized by

A)parabolic progress

B)logarithmic progress

C)slow-rapid-slow progress

D)extremely slow progress

Answer: C

Q3) In a conventional project life cycle,as work progresses,uncertainty about the expected outcome should __________.

A)become a constant

B)decrease

C)increase

D)be fully removed

Answer: B

To view all questions and flashcards with answers, click on the resource link above. Page 3

Chapter 2: Strategic Management and Project Selection

Available Study Resources on Quizplus for this Chatper

45 Verified Questions

45 Flashcards

Source URL: https://quizplus.com/quiz/48289

Sample Questions

Q1) The underlying premise of the real options approach is that __________.

A)delaying an investment may lead to greater returns or may lead to elimination of marginal projects

B)rushing into an investment more quickly may lead to lower returns or may lead to elimination of marginal projects

C)delaying an investment may lead to increased costs due to delays

D)rushing into an investment more quickly may lead to less risk

Answer: A

Q2) Wheelwright identified four separate categories of projects.Which of the following are not one of those categories?

A)Sacred cow projects

B)Platform projects

C)Breakthrough projects

D)R&D projects

Answer: A

To view all questions and flashcards with answers, click on the resource link above. Page 4

Chapter 3: The Project Manager

Available Study Resources on Quizplus for this Chatper

55 Verified Questions

55 Flashcards

Source URL: https://quizplus.com/quiz/48290

Sample Questions

Q1) __________ result(s)when the demands made on an individual are greater than the person's ability to cope with them,particularly when the person has a high need for achievement.

A)Stress

B)Culture

C)Balance

D)Contingency plans

Answer: A

Q2) During the __________ stage of the project lifecycle,there is no significant difference in the importance that project managers place on the three goals of cost,time,and scope.

A)main

B)formation

C)buildup

D)phaseout

Answer: B

To view all questions and flashcards with answers, click on the resource link above. Page 5

Chapter 4: Managing Conflict and the Art of Negotiation

Available Study Resources on Quizplus for this Chatper

53 Verified Questions

53 Flashcards

Source URL: https://quizplus.com/quiz/48291

Sample Questions

Q1) List and describe the three basic causes for change in projects.

Q2) Thomas and Kilmann identified five strategies people use to deal with conflict.List and briefly describe these.

Q3) Partnering is an attempt to __________ the risk associated with subcontracting.

A)mitigate

B)increase

C)absorb

D)allow

Q4) Identify three basic causes for change in projects.

Q5) Which of the following is not one of the four points of principled negotiation?

A)Insist on using objective criteria

B)Focus on interest not positions

C)Invent options for mutual gain before trying to reach an agreement

D)Separate people from the problem

Q6) The boundaries between departments or functions represent __________.

A)interfaces

B)challenges

C)Pareto locations

D)risk mitigation

Q7) Describe the four points of principled negotiation described by Fisher.

To view all questions and flashcards with answers, click on the resource link above. Page 6

Chapter 5: The Project in the Organizational Structure

Available Study Resources on Quizplus for this Chatper

61 Verified Questions

61 Flashcards

Source URL: https://quizplus.com/quiz/48292

Sample Questions

Q1) Explain how a company can go about implementing a PMO.

Q2) Identify the statement that is not a major advantage of placing a project within the pure project organization.

A)The functional manager retains full line authority over project team members.

B)The lines of communication are shortened in regards to the project's resources.

C)Centralized authority tends to increase the speed of decision-making.

D)A holistic approach to performing the project is supported.

Q3) In which organizational structure does the project manager have the highest level of authority?

A)Functional

B)Weak matrix

C)Strong matrix

D)Projectized

Q4) Project priorities are more of a concern in the __________ stages of the project life cycle.

A)earlier

B)later

C)middle

D)final

To view all questions and flashcards with answers, click on the resource link above. Page 7

Chapter 6: Activity Planning: Traditional and Agile

Available Study Resources on Quizplus for this Chatper

44 Verified Questions

44 Flashcards

Source URL: https://quizplus.com/quiz/48293

Sample Questions

Q1) Once the project charter is completed and the project approved,a more detailed project plan can be developed.Which of the following issues is not addressed in the detailed project plan?

A)Developing a plan for managing the human resources assigned to the project

B)Developing a plan for continuously monitoring and improving project work processes

C)Developing the Work Breakdown Structure

D)Developing a list of skilled workers to hire

Q2) During initial project planning,activities are identified and sorted.In completing this process,each level in the hierarchy should limit the number of activities to a range between __________.

A)5 to 10 activities

B)0 to 5 activities

C)2 to 20 activities

D)10 to 20 activities

Q3) The __________ chart is a tree diagram used to represent a hierarchical plan.

A)PERT

B)GANTT

C)PMBOK

D)Gozinto

To view all questions and flashcards with answers, click on the resource link above. Page 8

Chapter 7: Budgeting and Risk Management

Available Study Resources on Quizplus for this Chatper

55 Verified Questions

55 Flashcards

Source URL: https://quizplus.com/quiz/48294

Sample Questions

Q1) If a project budget is over funded,it will often __________.

A)produce waste

B)encourage slack management

C)improve morale

D)produce waste and encourage slack management

Q2) The budget process generally begins when the top management invites each division to submit a__________ for the upcoming year.

A)budget request

B)predictive budget

C)budget estimate

D)predictive request

Q3) Suppose that a person requires eight hours to complete a work element on the first attempt.That person has a learning rate of 90 percent for this work element.This person should require __________ hours to complete this work element on the fourth attempt.

A)5.83

B)6.48

C)7.2

D)8.8

Q4) Identify some of the common problems faced by the project budgeter.

Page 9

To view all questions and flashcards with answers, click on the resource link above.

Chapter 8: Scheduling

Available Study Resources on Quizplus for this Chatper

56 Verified Questions

56 Flashcards

Source URL: https://quizplus.com/quiz/48295

Sample Questions

Q1) Task H has duration of 5 days,an early start of 25 days,an early finish of 30 days,a late start of 25 days,and a late finish of 30 days.There are __________ days of slack for task H.

A)0

B)5

C)10

D)20

Q2) With simulation,the model is repeated many times and the model's output for each repetition is used to construct a statistical distribution of all the outcomes.This shows the _____ of the decision

A)risk profile

B)critical path

C)maximum completion time

D)average completion time

Q3) The variance of a population is a measure of the population's __________.

A)dispersion

B)proportion

C)uniqueness

D)skewness

Q4) Explain the difference between total slack and free slack in a network.

To view all questions and flashcards with answers, click on the resource link above. Page 10

Chapter 9: Resource Allocation

Available Study Resources on Quizplus for this Chatper

53 Verified Questions

53 Flashcards

Source URL: https://quizplus.com/quiz/48296

Sample Questions

Q1) __________ are tasks that logically follow a particular task in time.

A)Successor

B)Strays

C)Predecessors

D)Critical

Q2) If the crash cost is $2,500,the normal cost is $1,500,the crash time is 4,and the normal time is 6,what is the slope?

A)-1,500

B)-1,000

C)-750

D)-500

Q3) When crashing a project,our first task is to develop __________.

A)a table or graph of the cost of a project as a function of the project's possible completion dates

B)a schedule that shows the risks associated with each activity in the project

C)a list that shows the activities and the events of a project without referring to the costs

D)a table showing the noncritical activities and the cost associated with each of those activities

To view all questions and flashcards with answers, click on the resource link above.

11

Chapter 10: Monitoring and Information Systems

Available Study Resources on Quizplus for this Chatper

53 Verified Questions

53 Flashcards

Source URL: https://quizplus.com/quiz/48297

Sample Questions

Q1) If EV = $500,AC = $475,PV = $450; SV = ________.

A)$50

B)$25

C)90%

D)95%

Q2) If CPI = 1.05,then __________ is favorable.

A)time variance

B)schedule variance

C)cost variance

D)performance variance

Q3) Vague or incomplete project requirements are an example of which telltale sign that a project is in trouble?

A)Muddy waters

B)Mysterious stakeholders

C)Unconstrained constraints

D)Scope creep

Q4) List and describe five telltale signs of project trouble it is wise to monitor.

Q5) Identify the main complaints associated with meetings.

Q6) Identify some of the benefits when timely reports are delivered to the proper people by the project management information system.

To view all questions and flashcards with answers, click on the resource link above. Page 12

Chapter 11: Project Control

Available Study Resources on Quizplus for this Chatper

48 Verified Questions

48 Flashcards

Source URL: https://quizplus.com/quiz/48298

Sample Questions

Q1) __________ are seen as much the same as a report card.

A)Postcontrols

B)WBSs

C)Critical ratios

D)Cybernetics

Q2) Project changes result from three basic causes.Which of the following is not one of those causes?

A)Uncertainty about the technology on which the work of the project or its output is based

B)An increase in the knowledge base or sophistication of the client / user leading to scope creep

C)Changes to the environment in which the project is being completed

D)A modification of the rules applying to the process of carrying out the project or to its output

Q3) The stewardship of human resources requires __________ the growth and development of people.

A)flattening

B)demolition

C)controlling and maintaining

D)mandating

To view all questions and flashcards with answers, click on the resource link above. Page 13

Chapter 12: Project Auditing

Available Study Resources on Quizplus for this Chatper

63 Verified Questions

63 Flashcards

Source URL: https://quizplus.com/quiz/48299

Sample Questions

Q1) Managerial audits look at __________ and their use.

A)managerial systems

B)subordinate systems

C)manual systems

D)ethical policies

Q2) Match the following project stages with the associated value of a project audit.

A)Initiation

B)Baseline schedule

C)Implementation

D)Preliminary plan / schedule budget

1)Less useful,plan frozen,flexibility of team limited

2)More or less useful,depending on importance of project methodology to successful implementation

3)Very useful,particularly for setting measurement standards to ensure conformance with standards

4)Significant value if audit takes place early-prior to 25 percent completion of initial planning stage

Q3) List and describe the points that should be contained in the formal report of a project audit.

Q4) Discuss the differences between a project audit and a financial audit.

To view all questions and flashcards with answers, click on the resource link above. Page 14

Chapter 13: Project Closure and Benefits Realization

Available Study Resources on Quizplus for this Chatper

51 Verified Questions

51 Flashcards

Source URL: https://quizplus.com/quiz/48300

Sample Questions

Q1) During the implementation of project closure,the closure manager should ensure that __________.

A)delivery and implementation of project results were accomplished regardless of closure method

B)formal acceptance of the project is obtained from the project team

C)formal acceptance of the project is acknowledged by the client

D)the project's documentation is shredded

Q2) Cutting a project's budget sufficiently to stop progress without actually killing the project is referred to as __________.

A)closure by addition

B)closure by extinction

C)closure by starvation

D)closure by subtraction

Q3) The four types of project closures are __________.

A)extinction,addition,integration,and aggravation

B)extinction,addition,integration,and starvation

C)extinction,inclination,integration,and starvation

D)extinction,addition,implementation,and starvation

Q4) Describe the subjects that should be addressed in the final report.

Q5) Briefly describe the four fundamentally different ways to close out a project.

Page 15

To view all questions and flashcards with answers, click on the resource link above.