Management Information Systems Exam Bank - 1226 Verified Questions

Page 1


Management Information Systems

Exam Bank

Course Introduction

Management Information Systems (MIS) examines the integration of people, technology, and processes to collect, process, store, and disseminate information within an organization. This course explores how businesses leverage information systems to improve decision-making, enhance operational efficiency, and achieve competitive advantage. Students will learn about the components of MIS, system development and implementation, information security, and the role of ethical considerations in information management. Practical case studies and real-world examples are used to illustrate how information systems support business objectives and adapt to changing technological landscapes.

Recommended Textbook

Successful Project Management with Microsoft Project 2010 5th Edition by Jack Gido

Available Study Resources on Quizplus

14 Chapters

1226 Verified Questions

1226 Flashcards

Source URL: https://quizplus.com/study-set/455

Page 2

Chapter 1: Project Management Concepts

Available Study Resources on Quizplus for this Chatper

74 Verified Questions

74 Flashcards

Source URL: https://quizplus.com/quiz/8069

Sample Questions

Q1) A project's stakeholders will always include only representatives from the sponsor's organization.

A)True

B)False

Answer: False

Q2) Resources are identified and selected in the

A) initiating phase.

B) planning phase.

C) performing phase.

D) closing phase.

Answer: B

Q3) The amount the sponsor has agreed to pay for acceptable project deliverables is the project budget.

A)True

B)False

Answer: True

Q4) People are the only resource used in a project.

A)True

B)False

Answer: False

Page 3

To view all questions and flashcards with answers, click on the resource link above.

Chapter 2: Identifying and Selecting Projects

Available Study Resources on Quizplus for this Chatper

70 Verified Questions

70 Flashcards

Source URL: https://quizplus.com/quiz/8070

Sample Questions

Q1) A bidders meeting may be held to

A) clarify the RFP and answer any questions from potential bidders.

B) provide additional information only to those that attend the meeting.

C) provide an unfair advantage to those at the meeting.

D) solicit feedback on the clarity of the RFP to change the project requirements.

Answer: A

Q2) The sponsor designee is the project manager of the project.

A)True

B)False

Answer: False

Q3) The project justification includes the key assumptions for the project.

A)True

B)False

Answer: True

Q4) A contract might be for a fixed price; the customer will pay the contractor whatever the actual costs are for the materials and the time.

A)True

B)False Answer: False

To view all questions and flashcards with answers, click on the resource link above. Page 4

Chapter 3: Developing Project Proposals

Available Study Resources on Quizplus for this Chatper

111 Verified Questions

111 Flashcards

Source URL: https://quizplus.com/quiz/8071

Sample Questions

Q1) Taking credit for outcomes that others have accomplished is a way to build yourself for others to respect you.

A)True

B)False

Answer: False

Q2) Fixed-price contracts are most appropriate for projects that A) take less than one year to complete. B) are with customers that want a single payment date. C) are well defined and entail little risk.

D) involve risk.

Answer: C

Q3) Inclusion of an organization chart or assigned responsibility is helpful for the customer to evaluate the expertise of the project staff.

A)True

B)False

Answer: False

To view all questions and flashcards with answers, click on the resource link above. Page 5

Chapter 4: Defining Scope, Quality, Responsibility, and Activity Sequence

Available Study Resources on Quizplus for this Chatper

129 Verified Questions

129 Flashcards

Source URL: https://quizplus.com/quiz/8072

Sample Questions

Q1) A responsibility assignment matrix defines who will be pay for the work.

A)True

B)False

Q2) The __________ may need to describe certain inspection techniques, testing procedures, or specific testing equipment or facilities that must be used.

A) statement of work

B) customer requirement

C) deliverables

D) acceptance criteria

Q3) It is common to progressively elaborate the network diagram

A) as the network diagram is being built the first time.

B) at the onset of the project.

C) as the project progresses and more information is known or becomes clear.

D) at the end of the project.

Q4) It is easier to define the specific activities for near-term work; but as more information is known or becomes clear, the project team can progressively elaborate the specific activities.

A)True

B)False

6

To view all questions and flashcards with answers, click on the resource link above.

Chapter 5: Developing the Schedule

Available Study Resources on Quizplus for this Chatper

79 Verified Questions

79 Flashcards

Source URL: https://quizplus.com/quiz/8073

Sample Questions

Q1) The contractor may not want to commit to completing the project by a specific date until the customer has approved the contract.

A)True

B)False

Q2) A Gantt chart is the often the name for the network diagram tool for planning and scheduling.

A)True

B)False

Q3) Padding estimates with the vision of becoming a hero when the activities are completed in less time than estimated is not a good practice.

A)True

B)False

Q4) If the planned corrective actions do not result in an acceptable schedule, then A) the project should be terminated.

B) the steps for schedule control need to be repeated.

C) the original project plan was best and should be used.

D) the customer should decide what should be done.

Q5) Schedule control involves four steps. List the four steps in order.

To view all questions and flashcards with answers, click on the resource link above. Page 7

Chapter 6: Resource Utilization

Available Study Resources on Quizplus for this Chatper

21 Verified Questions

21 Flashcards

Source URL: https://quizplus.com/quiz/8074

Sample Questions

Q1) A resource requirements plan illustrates

A) who is responsible for which activities.

B) the amount of labor expenses for the project.

C) the expected utilization of resources by time period during the time span of the project.

D) the budget for material and cost resources.

Q2) ________ assist with the complexity of generating a resource-leveled schedule and resource requirements graphs and tables.

A) Project management information systems

B) Formulas and techniques

C) Trial and error techniques

D) Calendaring systems

Q3) Resource utilization charts based on each activity's earliest start time are said to be based

A) on availability times.

B) an as-late-as-possible (ALAP) schedule.

C) on an as-soon-as-possible (ASAP) schedule.

D) on a limited schedule plan.

To view all questions and flashcards with answers, click on the resource link above.

8

Chapter 7: Determining Costs, Budget, and Earned Value

Available Study Resources on Quizplus for this Chatper

69 Verified Questions

69 Flashcards

Source URL: https://quizplus.com/quiz/8075

Sample Questions

Q1) The key to effective cost control is to analyze cost performance on a regular and timely basis.

A)True

B)False

Q2) When evaluating work packages that have a negative cost variance, you should focus on taking corrective actions to reduce the costs of:

A) activities that have a small cost estimate.

B) activities that have a moderate cost estimate.

C) activities that have a large cost estimate.

D) all the activities in the project.

Q3) Calculate the forecasted cost at completion if the total budgeted cost is $15,000, the cumulative actual cost is $10,000, and the cumulative earned value is $12,000.

A) FCAC = $7,000

B) FCAC =$17,000

C) FCAC =$13,000

D) FCAC = $37,000

Q4) It is important to manage the cash flow on a project.

A)True

B)False

To view all questions and flashcards with answers, click on the resource link above. Page 9

Chapter 8: Managing Risk

Available Study Resources on Quizplus for this Chatper

45 Verified Questions

45 Flashcards

Source URL: https://quizplus.com/quiz/8076

Sample Questions

Q1) With knowledge of potential risks, the contractor can include contingency or management reserve amounts in the bid price.

A)True

B)False

Q2) Risk management involves identifying, assessing, and responding to project risks in order to minimize the likelihood of occurrence and/or potential impact of adverse events on the accomplishment of the project objective.

A)True

B)False

Q3) Risk identification is determining which risks may adversely affect the development of the project work breakdown structure and what the impact of each risk might be if it occurs.

A)True

B)False

Q4) A risk assessment matrix is a tool for

A) making a person responsible for the risk.

B) stating if the risk will be avoided, accepted, or mitigated.

C) examining the results of the project.

D) assessing and managing risks.

To view all questions and flashcards with answers, click on the resource link above. Page 10

Chapter 9: Closing the Project

Available Study Resources on Quizplus for this Chatper

42 Verified Questions

42 Flashcards

Source URL: https://quizplus.com/quiz/8077

Sample Questions

Q1) The project organization should establish a __________ that includes an easily accessible repository that encourages project managers and teams to retrieve lessons learned and information from previous projects.

A) document storage routine

B) file structure

C) knowledge base system

D) revision process

Q2) Projects also can be terminated by the sponsor or customer.

A)True

B)False

Q3) Projects also can be terminated by the sponsor or customer because the project needs have changed.

A)True

B)False

Q4) Lessons learned could be helpful in bidding, planning, and/or performing future projects.

A)True

B)False

To view all questions and flashcards with answers, click on the resource link above. Page 11

Chapter 10: The Project Manager

Available Study Resources on Quizplus for this Chatper

129 Verified Questions

129 Flashcards

Source URL: https://quizplus.com/quiz/8078

Sample Questions

Q1) During the project life cycle, project managers encounter many occasions to employ their negotiating skills in interactions with the sponsor or customer, the project organization's management, subcontractors, vendors, and end users of the project's end product The subject of negotiations can be contract terms and conditions, obtaining specific resources to staff the project, subcontractor prices, vendor delivery schedules, payment for damages, the cost or schedule impact of changes, customer approval of designs, the need for rework if quality standards were not met, the best approach to resolve a technical performance issue, interpretation of acceptance criteria or test results, approaches to get the project back on track if it is behind schedule and/or over budget, and so forth.

A)True

B)False

Q2) Stress is likely to be high when a project is in jeopardy of not meeting its objective. A)True B)False

Q3) Effective project managers communicate and share information in one way. A)True B)False

To view all questions and flashcards with answers, click on the resource link above.

Page 12

Chapter 11: The Project Team

Available Study Resources on Quizplus for this Chatper

225 Verified Questions

225 Flashcards

Source URL: https://quizplus.com/quiz/8079

Sample Questions

Q1) In the __________ approach, each person must approach the conflict with a constructive attitude and a willingness to work in good faith with the others to resolve the issue.

A) Collaborating, Confronting, or Problem Solving

B) Avoiding or Withdrawing

C) Competing or Forcing

D) Accommodating or Smoothing

Q2) ________ is necessary within a project organization, and in project business relationships with customers, suppliers, and subcontractors.

A) Keeping secrets

B) Ethical behavior

C) Withholding information

D) Falsifying results

Q3) Unethical actions should be encouraged, acknowledged, and appreciated.

A)True

B)False

Q4) Poor communication is important to project team effectiveness.

A)True

B)False

Q5) List examples of situations that provide an opportunity for unethical behavior:

Page 13

To view all questions and flashcards with answers, click on the resource link above.

Chapter 12: Project Communication and Documentation

Available Study Resources on Quizplus for this Chatper

121 Verified Questions

121 Flashcards

Source URL: https://quizplus.com/quiz/8080

Sample Questions

Q1) _______ allows the live exchange of information among members of the project team.

A) Email

B) Verbal communication

C) Teleconferencing

D) Written communication

Q2) It is important to wait for all the meeting attendees instead of starting the meeting on time.

A)True

B)False

Q3) When making key points, explain to the audience why they are important.

A)True

B)False

Q4) Knowledge of the audience doesn't matter and neither does their level of knowledge or familiarity with the subject.

A)True

B)False

Q5) When responding to questions, be candid and arrogant.

A)True

B)False

Page 14

To view all questions and flashcards with answers, click on the resource link above.

Chapter 13: Project Management Organizational Structures

Available Study Resources on Quizplus for this Chatper

65 Verified Questions

65 Flashcards

Source URL: https://quizplus.com/quiz/8081

Sample Questions

Q1) In _________, multiple projects are worked on at any one time, and these projects vary in size and complexity.

A) an autonomous project organizational structure

B) a functional organizational structure

C) a matrix organizational structure

D) a project management office

Q2) In _______, team members may be assigned to the project either full-time or part-time.

A) an autonomous project organizational structure

B) a functional organizational structure

C) a matrix organizational structure

D) a project management office

Q3) A disadvantage of an autonomous project organizational structure is that there is a potential for duplication of activities on several concurrent projects.

A)True

B)False

To view all questions and flashcards with answers, click on the resource link above. Page 15

Chapter 14: Project Management Information Systems

Available Study Resources on Quizplus for this Chatper

46 Verified Questions

46 Flashcards

Source URL: https://quizplus.com/quiz/8068

Sample Questions

Q1) ________ are uncertain events or circumstances that could have an impact on a project.

A) Project plans

B) Project resources

C) Project risks

D) Project activities

Q2) _______ features of most systems that are available to help include approval process and routing, change order management, contract management and automation, meeting management and action items, project charter information, requirements management, and time-off requests.

A) The communication

B) The budgeting and cost management

C) The sales and business development

D) The documentation management

Q3) When selecting a PMIS, consideration of the "look" and "feel" of the system should be given to all of the following except

A) how much experience others in the office have with the system.

B) available short-cut keys and color displays.

C) the consistency among screens.

D) the ease with which data can be entered.

To view all questions and flashcards with answers, click on the resource link above. Page 16

Turn static files into dynamic content formats.

Create a flipbook
Management Information Systems Exam Bank - 1226 Verified Questions by Quizplus - Issuu