Advanced Project Management Solved Exam Questions - 1066 Verified Questions

Page 1


Advanced Project Management

Solved Exam Questions

Course Introduction

Advanced Project Management explores the principles, methodologies, and tools necessary to plan, execute, and lead complex projects across diverse industries. Emphasizing both traditional and contemporary project management approaches, including Agile and hybrid frameworks, the course covers strategic alignment, risk assessment, stakeholder engagement, resource optimization, performance measurement, and adaptive leadership. Through case studies and practical assignments, students enhance their ability to manage project constraints such as scope, cost, and schedule while mastering communication, negotiation, and decision-making skills critical for successful project delivery in dynamic environments.

Recommended Textbook

Information Technology Project Management 9th Edition by Kathy Schwalbe

Available Study Resources on Quizplus

13 Chapters

1066 Verified Questions

1066 Flashcards

Source URL: https://quizplus.com/study-set/264

Page 2

Chapter 1: Introduction to Project Management

Available Study Resources on Quizplus for this Chatper

91 Verified Questions

91 Flashcards

Source URL: https://quizplus.com/quiz/4342

Sample Questions

Q1) Until the 1980s, project management primarily focused on providing schedule and resource data to top management in the military, computer, and construction industries.

A)True

B)False

Answer: True

Q2) Responsibility assignment matrices and project organizational charts are examples of tools used in procurement management.

A)True

B)False

Answer: False

Q3) Ethics is a set of principles that guides decision making based on _____ of what is considered right and wrong.

Answer: personal values

Q4) Project management _____ describe the key competencies that project managers must develop.

Answer: knowledge areas

Q5) The term "_____" refers to work done in organizations to sustain the business. Answer: Operations

To view all questions and flashcards with answers, click on the resource link above. Page 3

Chapter 2: The Project Management Information

Technology

Context

Available Study Resources on Quizplus for this Chatper

85 Verified Questions

85 Flashcards

Source URL: https://quizplus.com/quiz/4343

Sample Questions

Q1) In what type of organizational structure do project managers have the most authority?

A) Functional

B) Project

C) Matrix

D) Circular

Answer: B

Q2) Which characteristic of organizational culture refers to the degree to which employees identify with the organization as a whole, rather than with their types of job or profession?

A) Member identity

B) People focus

C) Group emphasis

D) Unit integration

Answer: A

Q3) The last phase of the traditional project life cycle is the implementation phase.

A)True

B)False

Answer: False

Page 4

To view all questions and flashcards with answers, click on the resource link above.

Chapter 3: The Project Management Process Groups

Available Study Resources on Quizplus for this Chatper

83 Verified Questions

83 Flashcards

Source URL: https://quizplus.com/quiz/4344

Sample Questions

Q1) The kick-off meeting is always held before the business case and project charter are completed.

A)True

B)False

Answer: False

Q2) What tool provides a basis for creating the project schedule and performing earned value management for measuring and forecasting project performance?

A) scope statement

B) cost management plan

C) work breakdown structure

D) project charter

Answer: C

Q3) Which process includes measuring progress toward project objectives and taking corrective action to match progress with the plan?

A) Planning

B) Monitoring and controlling

C) Executing

D) Initiating

Answer: B

To view all questions and flashcards with answers, click on the resource link above.

Page 5

Chapter 4: Project Integration Management

Available Study Resources on Quizplus for this Chatper

83 Verified Questions

83 Flashcards

Source URL: https://quizplus.com/quiz/4345

Sample Questions

Q1) Change requests are always made in writing.

A)True

B)False

Q2) _____ involves determining long-term objectives by analyzing the strengths and weaknesses, studying opportunities and threats, predicting future trends, and projecting the need for new products and services.

Q3) Which section of the project plan lists the planned dates for completing key deliverables?

A) schedule

B) closing

C) budget

D) objectives

Q4) Many projects fail because of unclear requirements and expectations, so starting with a payback analysis makes a lot of sense.

A)True

B)False

Q5) The _____ is the discount rate that results in an NPV of zero for a project.

Q6) _____ factors include relevant government or industry standards, the organization's infrastructure, and marketplace conditions.

Page 6

To view all questions and flashcards with answers, click on the resource link above.

Chapter 5: Project Scope Management

Available Study Resources on Quizplus for this Chatper

77 Verified Questions

77 Flashcards

Source URL: https://quizplus.com/quiz/4346

Sample Questions

Q1) The main outputs of _____are the project scope statement and updates to project documents.

Q2) Project scope statements must include the project boundaries, constraints, and assumptions.

A)True

B)False

Q3) Subdividing the project deliverables into smaller pieces is known as _____.

Q4) Creating the _____ involves subdividing the major project deliverables into smaller, more manageable components.

Q5) Which process involves generating ideas by comparing specific project practices or product characteristics to those of other projects or products inside or outside the performing organization?

A) variance

B) benchmarking

C) prototyping

D) decomposition

Q6) Deliverables are only product-related, such as a piece of hardware or software.

A)True

B)False

Page 7

To view all questions and flashcards with answers, click on the resource link above.

Chapter 6: Project Schedule Management

Available Study Resources on Quizplus for this Chatper

99 Verified Questions

99 Flashcards

Source URL: https://quizplus.com/quiz/4347

Sample Questions

Q1) In the activity defining process, the project team should review the _____ and activity attributes with project stakeholders before moving on to the next step in project schedule management.

Q2) Network diagrams are the preferred technique for showing activity sequencing.

A)True

B)False

Q3) In a network diagram, a(n) _____ is the starting and ending point of an activity.

Q4) What term is used for the amount of time an activity can be delayed from its early start without delaying the planned project finish date?

A) total slack

B) free float

C) backward pass

D) forward pass

Q5) A drawback of the project management software is that it does not have the capacity to calculate the critical path(s) for a project.

A)True

B)False

Q6) _____ involves the processes required to ensure timely completion of a project.

To view all questions and flashcards with answers, click on the resource link above. Page 8

Chapter 7: Project Cost Management

Available Study Resources on Quizplus for this Chatper

98 Verified Questions

98 Flashcards

Source URL: https://quizplus.com/quiz/4348

Sample Questions

Q1) IT project managers must be able to present and discuss project information both in financial and technical terms.

A)True

B)False

Q2) A cost management plan can include organizational procedures links, control thresholds, and process descriptions.

A)True

B)False

Q3) The formulas for variances and indexes start with EV, the earned value.

A)True

B)False

Q4) The main outputs of the _____ process are a cost performance baseline, project funding requirements, and project document updates.

Q5) _____ costing helps to see a big-picture view of the cost of a project throughout its life cycle.

Q6) The main output of the planning cost management process is a(n) _____.

Q7) The main outputs of the _____ process are activity cost estimates, basis of estimates, and project document updates.

Page 9

To view all questions and flashcards with answers, click on the resource link above.

Chapter 8: Project Quality Management

Available Study Resources on Quizplus for this Chatper

81 Verified Questions

81 Flashcards

Source URL: https://quizplus.com/quiz/4349

Sample Questions

Q1) The main outputs of which process are a quality management plan, quality metrics, project management plan updates, and project documents updates?

A) controlling quality

B) planning quality management

C) quality certification

D) performing quality assurance

Q2) Which addresses how well a product or service performs the customer's intended use?

A) reliability

B) performance

C) maintainability

D) functionality

Q3) Genichi Taguchi's _____ methods focus on eliminating defects by substituting scientific inquiry for trial-and-error methods.

Q4) _____ are groups of nonsupervisors and work leaders in a single company department who volunteer to conduct group studies on how to improve the effectiveness of work in their department.

Q5) Complete the formula: sample size = 0.25 * ( _____ /acceptable error)<sup>2</sup>

To view all questions and flashcards with answers, click on the resource link above. Page 10

Chapter 9: Project Resource Management

Available Study Resources on Quizplus for this Chatper

85 Verified Questions

85 Flashcards

Source URL: https://quizplus.com/quiz/4350

Sample Questions

Q1) A RAM is used only to assign detailed work activities.

A)True

B)False

Q2) What needs are at the bottom of Maslow's structure?

A) esteem

B) self-actualization

C) physiological

D) social

Q3) Which test presents subjects with a series of ambiguous pictures and asks them to develop a spontaneous story for each picture, assuming they will project their own needs into the story?

A) RAM

B) MBTI

C) TAT

D) RACI

Q4) Which concept refers to matching certain behaviors of the other person?

A) empathic listening

B) rapport

C) synergy

D) mirroring

To view all questions and flashcards with answers, click on the resource link above. Page 11

Chapter 10: Project Communications Management

Available Study Resources on Quizplus for this Chatper

73 Verified Questions

73 Flashcards

Source URL: https://quizplus.com/quiz/4351

Sample Questions

Q1) Rarely does the receiver interpret a message exactly as the sender intended.

A)True

B)False

Q2) What is performance reporting? What are some methods used for performance reporting?

Q3) Good information technology project managers must have strong technical and communication skills.

A)True

B)False

Q4) Describe the concepts of informal methods for distributing information. How do they compare to formal methods for distributing information?

Q5) Communication becomes simpler when you increase the number of team members.

A)True

B)False

Q6) Status reports should be written in a consistent format, regardless of the stakeholders' needs.

A)True

B)False

Q7) What are the guidelines for conducting effective meetings?

To view all questions and flashcards with answers, click on the resource link above. Page 12

Chapter 11: Project Risk Management

Available Study Resources on Quizplus for this Chatper

79 Verified Questions

79 Flashcards

Source URL: https://quizplus.com/quiz/4352

Sample Questions

Q1) Risk events refer to specific, certain events that may occur to the detriment or enhancement of the project.

A)True

B)False

Q2) A(n) _____ is a document that contains results of various risk management processes.

Q3) Risk utility rises at a decreasing rate for a _____ person.

A) risk-seeking

B) risk-averse

C) risk-neutral

D) risk-indifferent

Q4) What are the basic response strategies for negative risks? Describe each strategy.

Q5) Which document contains results of various risk management processes; it is often displayed in a table or spreadsheet format?

A) risk register

B) influence diagram

C) process flow chart

D) work breakdown structure

Q6) _____ involves accepting the consequences should a risk occur.

Page 13

To view all questions and flashcards with answers, click on the resource link above.

Chapter 12: Project Procurement Management

Available Study Resources on Quizplus for this Chatper

82 Verified Questions

82 Flashcards

Source URL: https://quizplus.com/quiz/4353

Sample Questions

Q1) What are some of the advantages that outsourcing offers which is encouraging many companies to adopt it?

Q2) A(n) _____ is also known as a tender or quote, short for quotation.

Q3) Procurement statements of work are an output of the _____ process.

Q4) Which process of project procurement management involves managing relationships with sellers, monitoring contract performance, making changes as needed, and closing contracts?

A) negotiating procurements

B) settling contracts

C) deciding on the services to procure

D) controlling procurements

Q5) What is the first step in project procurement management?

A) closing procurement management.

B) controlling procurements.

C) conducting procurements.

D) planning procurement management.

Q6) In unit pricing, the total value of the contract is a function of the quantities needed to complete the work.

A)True

B)False

Page 14

To view all questions and flashcards with answers, click on the resource link above.

Chapter 13: Project Stakeholder Management

Available Study Resources on Quizplus for this Chatper

50 Verified Questions

50 Flashcards

Source URL: https://quizplus.com/quiz/4354

Sample Questions

Q1) Which process involves monitoring stakeholder relationships and adjusting plans and strategies for engaging stakeholders as needed?

A) planning stakeholder management

B) identifying stakeholders

C) managing stakeholder engagement

D) monitoring stakeholder engagement

Q2) Communication and interpersonal skills are important for successful project stakeholder management.

A)True

B)False

Q3) Stakeholders might change during a project due to employee turnover, partnerships, and other events.

A)True

B)False

Q4) Projects often do not cause any changes in an organization.

A)True

B)False

Q5) What is a stakeholder register and what information must be included in it?

Q6) Identify and describe the processes involved in project stakeholder management.

Page 15

To view all questions and flashcards with answers, click on the resource link above.