Advanced Project Management Exam Materials - 682 Verified Questions

Page 1


Advanced Project Management

Exam Materials

Course Introduction

Advanced Project Management delves into the strategic, analytical, and leadership skills necessary to manage complex projects in dynamic organizational environments. The course explores advanced techniques in project planning, risk management, resource allocation, and stakeholder engagement, while introducing methodologies such as Agile, Lean, and Six Sigma. Students will analyze real-world case studies, address challenges related to project integration and change, and utilize contemporary project management software tools. Emphasis is placed on leadership, communication, and decision-making skills to ensure project success within scope, time, and budget constraints.

Recommended Textbook

Contemporary Project Management 4th Edition by Timothy Kloppenborg

Available Study Resources on Quizplus

15 Chapters

682 Verified Questions

682 Flashcards

Source URL: https://quizplus.com/study-set/2359

Page 2

Chapter 1: Introduction to Project Management

Available Study Resources on Quizplus for this Chatper

49 Verified Questions

49 Flashcards

Source URL: https://quizplus.com/quiz/46875

Sample Questions

Q1) Integration Management,one of the 10 PMBOK Guide Knowledge Areas,represents the processes and activities to identify,define,combine,unify,and coordinate the various processes and project management activities.

A)True

B)False Answer: True

Q2) In reality,many projects are fully successful in some ways,but less successful in others.

A)True

B)False Answer: True

Q3) Some projects are considered successful if they reap business benefits like increased profitability,even if completed late or over budget.

A)True

B)False Answer: True

To view all questions and flashcards with answers, click on the resource link above.

Page 3

Chapter 2: Project Selection and Prioritization

Available Study Resources on Quizplus for this Chatper

52 Verified Questions

52 Flashcards

Source URL: https://quizplus.com/quiz/46876

Sample Questions

Q1) Based on the information provided in Figure 2-1,which project has the highest probability of success?

A) Project A

B) Project B

C) Project C

D) Project D

Answer: B

Q2) Payback period models do not consider the amount of profit that may be generated after the costs are paid.

A)True

B)False

Answer: True

Q3) Many writers have stated that for strategic objectives to be effective,they should be:

A) broad - to cover many dimensions of the business

B) measurable - to track progress

C) unachievable - to inspire maximum performance

D) resource based - to focus on the inputs

Answer: B

To view all questions and flashcards with answers, click on the resource link above.

4

Chapter 3: Chartering Projects

Available Study Resources on Quizplus for this Chatper

39 Verified Questions

39 Flashcards

Source URL: https://quizplus.com/quiz/46877

Sample Questions

Q1) During iteration planning in an agile project,agreement is reached regarding:

A) the length of the next sprint.

B) detailed stakeholder requirements.

C) the definition of done.

D) positive and negative risks.

Answer: C

Q2) The project master network is a high-level plan that indicates a few significant accomplishments that are anticipated over the life of the project.

A)True

B)False

Answer: False

Q3) The charter signing represents the transition from the high-level project initiation stage into the more detailed project planning stage.

A)True

B)False

Answer: True

To view all questions and flashcards with answers, click on the resource link above.

Page 5

Chapter 4: Organizational Capability: Structure, Culture and Roles

Available Study Resources on Quizplus for this Chatper

50 Verified Questions

50 Flashcards

Source URL: https://quizplus.com/quiz/46878

Sample Questions

Q1) If the project scope is hard to define early in the project and/or much change is expected,an Agile project management approach often works better.

A)True

B)False

Q2) Which of the following roles and attributes do NOT describe the core team members on a project?

A) Core team members often make project decisions jointly with the project manager.

B) Core team members are the small group of people who are usually on the project from start to finish.

C) Core team members join the project on a temporary basis to perform specific project activities as necessary.

D) Core team members may supervise the work of subject matter experts who are brought in on an as-needed basis.

Q3) In "role cultures" reliable workers follow formal designations of responsibility with utmost respect for regulations and laws.

A)True

B)False

To view all questions and flashcards with answers, click on the resource link above. Page 6

Chapter 5: Leading and Managing Project Teams

Available Study Resources on Quizplus for this Chatper

46 Verified Questions

46 Flashcards

Source URL: https://quizplus.com/quiz/46879

Sample Questions

Q1) When many members of the project team disagree,then delaying the decision,gathering more data,or agreeing to let one person make the decision may be in order.

A)True

B)False

Q2) All of the following are among the steps of the negotiation process EXCEPT:

A) clarify both parties' interests

B) work toward a common goal

C) use "good cop / bad cop" technique

D) clarify and confirm agreements

Q3) Agile teams require motivated members with a higher level of commitment,and agile teams have all of the following desirable traits EXCEPT:

A) Question everything

B) Argue about everything

C) Fail their way to success

D) Deliver value

Q4) High-performing project teams start with the personal values of team members.List these values and discuss three ways that a project manager can strive to improve upon them.

To view all questions and flashcards with answers, click on the resource link above. Page 7

Chapter 6: Stakeholder Analysis and Communication Planning

Available Study Resources on Quizplus for this Chatper

46 Verified Questions

46 Flashcards

Source URL: https://quizplus.com/quiz/46880

Sample Questions

Q1) A communications management plan is a repository of information regarding all project stakeholders,and is often in the format of a matrix.

A)True

B)False

Q2) Communications to stakeholders are necessary for which of the following reasons?

A) to help them take ownership of the project and make timely decisions

B) to keep them at arms length so progress can continue

C) to shift the burden of risk from the project team to the stakeholders

D) to provide input to team performance reviews

Q3) Which of these is<u> NOT</u> one of the three methods of communication that will be documented in a communication plan?

A) Push methods

B) Virtual methods

C) Interactive methods

D) Pull methods

Q4) Describe the approach you would use to build relationships with key external stakeholders.

To view all questions and flashcards with answers, click on the resource link above. Page 8

Chapter 7: Scope Planning

Available Study Resources on Quizplus for this Chatper

44 Verified Questions

44 Flashcards

Source URL: https://quizplus.com/quiz/46881

Sample Questions

Q1) Baselining is defined as a method of dividing the project scope into many parts that,when combined,would constitute the project deliverable.

A)True

B)False

Q2) The project scope statement establishes the project boundaries by stating what features and work elements are included (in scope)and which are excluded  (out of scope).

A)True

B)False

Q3) Failure to include project management in the WBS will increase the likelihood that the project will not be completed on time and within budget.

A)True

B)False

Q4) What are some of the benefits of creating a Work Breakdown Structure (WBS)?

Q5) A Work Breakdown Structure must be decomposed at least four levels in order to be effective.

A)True

B)False

Q6) Explain how scope is defined on agile projects.

Page 9

To view all questions and flashcards with answers, click on the resource link above.

Chapter 8: Scheduling Projects

Available Study Resources on Quizplus for this Chatper

56 Verified Questions

56 Flashcards

Source URL: https://quizplus.com/quiz/46882

Sample Questions

Q1) Which of the following statements correctly describes the critical path?

A) The sequence of activities that represents the shortest path through the project network.

B) It determines the latest possible end date of the project.

C) It consists only of activities with zero float (slack).

D) It consists only of activities with lag times

Q2) Consider the network scheduling data presented in Figure 7-6.How many days of slack are associated with activity F?

A) 0

B) 15

C) 80

D) 107

Q3) In order for activities to be useful as schedule building blocks,they should have tangible output that can be verified.

A)True

B)False

Q4) Describe free float and how you can use it to your advantage in scheduling and managing a project.

To view all questions and flashcards with answers, click on the resource link above.

Chapter 9: Resourcing Projects

Available Study Resources on Quizplus for this Chatper

45 Verified Questions

45 Flashcards

Source URL: https://quizplus.com/quiz/46883

Sample Questions

Q1) Consider the project crashing information presented in Figure 8-4.What is the incremental cost to achieve a one-day reduction in the duration of this project in the most cost efficient manner?

A) $ 30

B) $ 35

C) $ 40

D) $ 60

Q2) Crashing is a project schedule compression technique that expedites a project by executing activities at the same time that ordinarily would be done one after the other.

A)True

B)False

Q3) Crashing almost always accelerates the schedule while increasing project risk,whereas fast tracking almost always accelerates the schedule while increasing project cost.

A)True

B)False

Q4) What is a responsibility assignment matrix (RAM)? Describe how you might use a responsibility assignment matrix to manage the resources assigned to your project.

To view all questions and flashcards with answers, click on the resource link above. Page 11

Chapter 10: Budgeting Projects

Available Study Resources on Quizplus for this Chatper

46 Verified Questions

46 Flashcards

Source URL: https://quizplus.com/quiz/46884

Sample Questions

Q1) The project scope does not come into play when considering fixed and variable cost choices.

A)True

B)False

Q2) "Unknown unknowns" are unexpected events which can occur when the project is underway.All of the following accurately describe an implication associated with unknown unknowns EXCEPT:

A) They are usually discovered during risk identification

B) They need to be covered in the project budget.

C) They usually require the use of management reserve.

D) They usually cause an increase in cost and / or schedule.

Q3) Most projects will employ bottom-up estimating at some point to serve as a basis for estimating cash flow needs and for controlling the project.

A)True

B)False

Q4) Both normal and special cause variation add to project cost and need to be considered by project managers.

A)True

B)False

To view all questions and flashcards with answers, click on the resource link above. Page 12

Chapter 11: Project Risk Planning

Available Study Resources on Quizplus for this Chatper

45 Verified Questions

45 Flashcards

Source URL: https://quizplus.com/quiz/46885

Sample Questions

Q1) Plan Risk Responses is the process of developing options and actions to enhance opportunities and reduce threats to project objectives.

A)True

B)False

Q2) All of the following methods have proven to be useful techniques to help project teams identify the risks that might impact the project EXCEPT:

A) reviewing project documents

B) documenting lessons learned

C) interviewing stakeholders

D) brainstorming among team members and subject matter experts

Q3) A project risk is anything that may impact the project team's ability to achieve the general project success measures and the specific project stakeholders' priorities.

A)True

B)False

Q4) How might you approach the prioritization of the risk events identified by your project team and subject matter experts? How would you use the results of this prioritization effort to guide the development of risk responses?

To view all questions and flashcards with answers, click on the resource link above.

Chapter 12: Project Quality Planning and Project Kick-Off

Available Study Resources on Quizplus for this Chatper

45 Verified Questions

45 Flashcards

Source URL: https://quizplus.com/quiz/46886

Sample Questions

Q1) W.Edwards Deming asserted that managers need to understand both serial variation and sequential variation and then work to reduce both.

A)True

B)False

Q2) DMAIC is a disciplined process that includes five phases: Define,Measure,Analyze,Improve and Control.DMAIC is most typically associated with which of the following quality improvement approaches?

A) Malcolm Baldrige

B) Total Quality Management (TQM)

C) Six Sigma

D) ISO 9001:2008

Q3) Which of the following serves as a pre-condition that must be met in order for a project kick-off meeting to be successful?

A) An atmosphere of trust and relationship building should be set by all.

B) Project performance results should be calculated and made available to team members.

C) Compensation packages and benefits plans should be shared with all team members.

D) The meeting location should always be off-site

To view all questions and flashcards with answers, click on the resource link above.

Page 14

Chapter 13: Project Supply Chain Management

Available Study Resources on Quizplus for this Chatper

45 Verified Questions

45 Flashcards

Source URL: https://quizplus.com/quiz/46887

Sample Questions

Q1) During procurement planning,the project team determines which needs can best be met by acquiring products and services from an outside provider,and which can be accomplished by the team.

A)True

B)False

Q2) Evaluations of prospective suppliers by project teams often involve all of the following approaches EXCEPT:

A) financial condition analysis

B) facility visits

C) supplier surveys

D) prototyping

Q3) Evaluation criteria used to rate proposals and other supplier characteristics might include all of these EXCEPT:

A) supply quality

B) personal relationships with senior management

C) inbound transportation cost

D) replenishment lead time

To view all questions and flashcards with answers, click on the resource link above. Page 15

Chapter 14: Determining Project Progress and Results

Available Study Resources on Quizplus for this Chatper

44 Verified Questions

44 Flashcards

Source URL: https://quizplus.com/quiz/46888

Sample Questions

Q1) Change control is a process wherein change proposals to various project planning elements are:

A) acknowledged, formally documented, and either approved or declined after review.

B) uniformly approved, documented and sent to the team for re-baselining and implementation.

C) uniformly denied, but documented for lessons learned.

D) documented and sent to the team, where the proposed changes will be voted on.

Q2) Some organizations rely upon a formal group authorized and responsible for reviewing,evaluating,approving,delaying,or rejecting any changes to any aspect of the project plan by following a formal communication method of documenting the decision process.This group is typically known as a:

A) stakeholder review board.

B) change control board.

C) project evaluation committee.

D) steering committee

Q3) Describe how you would adopt a balanced score card approach to evaluate your project performance.Your response should identify specific measures you would use as well as the approach you would take to obtain the measures you identify.

To view all questions and flashcards with answers, click on the resource link above.

Page 16

Chapter 15: Finishing the Project and Realizing the Benefits

Available Study Resources on Quizplus for this Chatper

30 Verified Questions

30 Flashcards

Source URL: https://quizplus.com/quiz/46889

Sample Questions

Q1) The Validate Scope process occurs with interim deliverables throughout the project and with final deliverables near the end.

A)True

B)False

Q2) Helping good workers to secure good follow-on work is one of the most important things a project manager must do near the end of the project.

A)True

B)False

Q3) When a project is completed on time,the project team must accomplish all of the following activities EXCEPT:

A) use alternative dispute resolution

B) capture and share lessons learned

C) plan a smooth transition of deliverables into ongoing operations

D) secure customer feedback and approval

Q4) More organizations effectively collect lessons learned than effectively disseminate and use them.

A)True

B)False

Q5) What is "validate scope" and why is it important to the project?