BILTMORE PREPARATORY ACADEMY CONSTRUCTION UPDATES Updated Project Photo

Creighton School District is partnering with SPS+ Architects and McCarthy Building Co. to replace and modernize Biltmore Preparatory Academy. This project will deliver a new, approximately 75,000-square-foot, state-of-the-art K–8 campus on the existing Phoenix site, purpose-built for the existing dual language Spanish emersion program.

Project Updates Demolition for Phase 1 is complete! Earthwork is also well underway. Site grading and leveling have been completed to prepare the area for construction, while crews continue installing underground utilities that will support the new facilities. Building foundations have officially begun, with footings and concrete slabs now being installed. These elements form the base of the future buildings and provide the first visible glimpse of the new campus taking shape. As construction progresses over the coming months, families and staff will begin to see the footprint of the upcoming buildings emerge from the ground.


Campus and Community Impacts As the first day of school approaches, the construction team is working closely with school staff to ensure the campus is ready to welcome students back for a successful year. Significant effort is being made to prepare the jobsite, establish clear safety measures, and coordinate campus operations so that daily school activities can continue smoothly while construction is underway. Our top priority is maintaining a safe learning environment for students, teachers, and visitors. We are committed to ensuring that students can enjoy a fun, productive, and safe school year while exciting improvements to the campus continue to take shape.

Construction Timeline

2026 MAY

Desig n

JUN

JUL

AUG

SEP

OCT

NOV

DEC

JAN

FEB

MAR

APR

2027 MAY

JUN

JUL

AUG

SEP

OCT

we are here! Phase 1 New Buildings Phase 2 Parking and Fields

Project Milestones and Upcoming Events • Completing foundations week of August 17 • Masonry walls start the week of August of 26 x

NOV


Meet Your BPA Construction Team!

Chad Smith

Silvino Villanueva

Valery Gonzalez

Project Manager

Project Superintendent

Sr. Project Engineer

Ben Parker

Morgan Ellig

Sue Peacor

Director of Construction & Bond

K-12 Director

Project Manager

Do you have feedback for the BPA construction team? Click the link below to share your thoughts directly with Creighton’s Construction Team.

Feedback for BPA Construction