BILTMORE PREPARATORY ACADEMY CONSTRUCTION UPDATES Updated Project Photo
Creighton School District is partnering with SPS+ Architects and McCarthy Building Co. to replace and modernize Biltmore Preparatory Academy. This project will deliver a new, approximately 75,000-square-foot, state-of-the-art K–8 campus on the existing Phoenix site, purpose-built for the existing dual language Spanish emersion program.
Project Updates Demolition for Phase 1 is complete! Earthwork is also well underway. Site grading and leveling have been completed to prepare the area for construction, while crews continue installing underground utilities that will support the new facilities. Building foundations have officially begun, with footings and concrete slabs now being installed. These elements form the base of the future buildings and provide the first visible glimpse of the new campus taking shape. As construction progresses over the coming months, families and staff will begin to see the footprint of the upcoming buildings emerge from the ground.
Campus and Community Impacts As the first day of school approaches, the construction team is working closely with school staff to ensure the campus is ready to welcome students back for a successful year. Significant effort is being made to prepare the jobsite, establish clear safety measures, and coordinate campus operations so that daily school activities can continue smoothly while construction is underway. Our top priority is maintaining a safe learning environment for students, teachers, and visitors. We are committed to ensuring that students can enjoy a fun, productive, and safe school year while exciting improvements to the campus continue to take shape.
Construction Timeline
2026 MAY
Desig n
JUN
JUL
AUG
SEP
OCT
NOV
DEC
JAN
FEB
MAR
APR
2027 MAY
JUN
JUL
AUG
SEP
OCT
we are here! Phase 1 New Buildings Phase 2 Parking and Fields
Project Milestones and Upcoming Events • Completing foundations week of August 17 • Masonry walls start the week of August of 26 x
NOV
Meet Your BPA Construction Team!
Chad Smith
Silvino Villanueva
Valery Gonzalez
Project Manager
Project Superintendent
Sr. Project Engineer
Ben Parker
Morgan Ellig
Sue Peacor
Director of Construction & Bond
K-12 Director
Project Manager
Do you have feedback for the BPA construction team? Click the link below to share your thoughts directly with Creighton’s Construction Team.
Feedback for BPA Construction
Progress Photos!