In December 2023 study by the utility, Santee Cooper determined: • In order to serve 50-60MW of load, will take 12 months • In order to serve 400MW of load, will take 24 months Owner will deliver two (2) Virginia 39/52/65 MVAT transformers Access to Dataroom - Email will.harker@bridge-commercial.com
BCP
BERKELEY COMMERCE PARK
CHARLESTON, SOUTH CAROLINA
DATA CENTER DEVELOPMENT OPPORTUNITY | 400 MW CAMPUS 50MW Available Immediately