Construction Management Techniques to Complete the Project within Time Period and Estimated Cost: A Case Study of Residential Building Ankit Dharmaprakash Sawai1, Sham Shivaji Lohar2 1M.E
Student, Department of Civil Engineering, Construction Management, Imperial College of Engineering & Research, Wagholi Pune, India. 2Assistant Professor, Department of Civil Engineering, Imperial College of Engineering & Research, Wagholi Pune, India. ---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - This study required the Pune World City
increased, bad work quality. The infrastructure venture requires more numbers of skilled workers, updated equipment, soft wares, and proper project management, which will save time and increases productivity.
Lohegaon Project Building Project "Pride World City Lohegaon Project" This world-class project is located on a 400-hectare site in Dhanori, which will be the center of Pune with 1, 2. 3 BHK apartments / apartments. As an example of research. The Building Control Strategies discussed in this study include a comparative analysis between the Microsoft Project Design Plan (MSP) Techniques and the Aluminum formwork (MIVAN) Technique. Construction Review, Lean Construction Technique, Value Engineering Technique, Gantt Chart, System Evaluation System and Review System (PERT), Critical Method Method (CPM), Balance Line, Workflow Structure, Network Analysis, Graphic Test Method and Review (GERT), Project Sensitivity Analysis, Cost Profit Analysis and much more and features such as project size, project location, Type of Financial Client Source, Project Complex, Construction Capacity, Buildings, Buildings, Storage, and the latest and others include aspects that affect the Building. Management strategies in the Indian construction industry.
There are many construction management techniques in the Indian construction industry, but which construction techniques is best for the construction project is important to complete project in time period, cost and quality. In these case study of the construction of residential building, some strategies are used like Gannt Chart (MSP) Microsoft project planning software, (MIVAN) Aluminum formwork Construction Technique, Work Breakdown structure, using these strategies, from these strategies which is useful to achieve the construction cost and quality and the completion of the project within time period.
1.1 Construction Project Management According to Opara,[1] (1986) design operation design is the overall planning, collaboration and control operation of a design from launch to finish aimed at meeting client needs in order to produce a feasible and completely feasible design. Construction Project Management is what applies to the construction assiduity. The most common liabilities of construction operation Association of America (CMAA) fall under seven orders, Project operation Planning, cost operation, time operation, Quality Management, Contract Administration, Safety Management and CM Professional Practice which integrates specific functions similar as defining liabilities and operation structure of the design operation platoon, planning and directing through design operation, defining places and functions and developing design and design identification contracts. Arnaboldiet.al, (2004)
Key Words: Construction Management Techniques,
Management Strategies, MIVAN Techniques, Work Breakdown Structure, Microsoft Project Planning, Time Management, Gantt chart.
1. INTRODUCTION Construction is an important part of development and is an important sector of the Indian economy. India has the second largest population in the world and in the future the demand for housing is rising sharply due to this problem India will need a lot to plan land grabbing and quickly create settlements. Today there is an increase in population so that that speed of construction is given greater importance especially to large housing projects. Fortunately, some of the advanced technology of rapid construction speed is already available in the country e.g. Pre-construction, autoclaved blocks, tunnel formwork, aluminum formwork (MIVAN Technology) building etc.
1.2 Functions of Construction Project Management According to Adedeji (1989), building planning is an important and difficult task in implementing and developing construction plans. It includes special selection, job description, amount of money needed and duration of each job, as well as identification of any relationship between different jobs. Building a building plan is an important task in the operation of a building, especially if the plan is not
The objections of construction quality is serious issue in the Indian construction industry. For fruitful quality work, for example, unviability of skilled workers, poor working techniques, bad condition of equipment’s, old working methods and so forth it will require more time, cost will