Resource management is the key factor of the project management in today’s construction industry. Resources like
material and labour have significant impact on construction projects, Project schedules obtained from network scheduling
technique generally have unwished resource fluctuation that are clumsy, costly, inoperable and not fulfilling the max availability
of resource at a particular time on construction sites. Resource leveling is essential in project management due to these
undesirable and costly resource demands. Typically, schedules with improved resource profiles can be derived by shifting the
activities within their float times considering the schedule of fixed duration found by various method like Critical Path method,
Precedence diagram method ,etc. However, if the project time duration can be extended, It is commended to find a schedule with
a extensive resource leveling so far as a longer duration permits for extra float time for overall activities. In the modern era of
development a project