An effective and well-known method for the early completion of construction projects is the overlap of the project’s
critical activities or phases that would normally be carried out in sequence. Overlapping technique reduce the project completion
time with minimum cost overrun.
Overlapping is also called fast-tracking mechanism. It is risky because it increases the probability of rework that result in
increasing the cost of the project.
The Overlapping in construction projects must be carried out effectively because each pair of activities cannot overlap, since
some previous activity may not allow overlap due to maximum rework. There are various overlapping strategies that exist in a
construction project which all can result in time-saving. so, the cost of these strategies varies significantly depending on the
overall Rework.
A favorable overlapping strategy leads to minimal time savings costs. To find such a strategy, the question arises: “Which
activities have to be overlapped and to what extent to reduce.