CHESAPEAKE PIPELINE REPLACEMENT NEIGHBORHOOD MEETING APRIL 14, 2021


INTRODUCTIONS

 Centennial Water & Sanitation District 

Jon Klassen – Project Manager

 JR Engineering 

Tristan Bonser – Water Resources Manager

Rocky Carns – Senior Construction Inspector

 Brannan Construction 

Luke Lopez – Senior Project Manager

Jake Jennings – General Superintendent


PROJECT LOCATION Staging Area

Toepfer Park

Water Main Replacement


CHESAPEAKE HISTORY  Chesapeake Lane  Chesapeake Place

Installed in 1988

8-inch ductile iron pipe

Installed in 1988

Approximately 1,705 linear feet

6-inch ductile iron pipe

2015 – 2020

Approximately 300 linear feet

2015 – 2020

6 main breaks

2 valve replacements

1 fire hydrant replacement

2 main breaks


CHESAPEAKE REPAIR HISTORY


PROJECT INFORMATION & SCHEDULES


PROJECT SCOPE  Staging area  Water main removal and replacement 

Temporary water system

Valve replacements

Fire hydrant replacement

Disinfection and testing

 Cleanup and Restoration  Asphalt 

Temporary patching

Mill and overlay

STAGING AREA


OVERALL PROJECT SCHEDULE

Mobilization 4/26 – 4/27

Phase 1 4/28 – 5/5

Phase 2 5/6 – 5/21

Phase 3 5/24 – 6/18

Phase 4 6/21 – 7/12

Completion 7/13 – 7/23


STAGING AREA Toepfer Park

 Adjacent to Toepfer Park  License Agreement with Douglas County

 Stabilized Surface  Security Fence  Storage of Materials and Equipment 

Will be transported between staging area and Chesapeake Lane/Place

 Trucks Entering/Exiting Signs on Venneford Ranch Rd


MOBILIZATION SCHEDULE

April 26 Traffic Control

April 26 – 27 Staging Area and Erosion Control


PHASE 1 CONSTRUCTION – VALVE REPLACEMENT

 Replacement of valve in

Chesapeake Ln  Install temporary water service to

16 homes on Chesapeake Ln  Temporary water service

interruption to 9 homes on Chesapeake St


TEMPORARY WATER SYSTEM  Temporary water system will be installed in phases to match removal and replacement of the water main  Water service to the temporary main will be supplied through fire hydrants 

Same source as permanent system and meets all water quality standards

 Temporary water main will be buried at street crossings and bridged across driveways  Connections to homes will be made through existing valve near street 

No change to how water will be metered and read by District

 Outdoor watering limited while on temporary system


TEMPORARY WATER SYSTEM


TEMPORARY WATER SYSTEM


PHASE 1 SCHEDULE

April 28 – May 4 Temporary Water

May 5 Valve Replacement


PHASE 2 CONSTRUCTION – WATER MAIN

 Remove and Replace 650 LF of

water main  Remove and replace 16 water

service connections  Disinfection and testing  Remove temporary water system  Asphalt patching


WATER MAIN REMOVAL AND REPLACEMENT

 Excavate and remove existing soil and pipe bedding material  Disconnect existing water services and remove existing ductile iron water main  Install new bedding material and new PVC water main

 Install and connect new water services  Install and compact new structural backfill  Pressure test and disinfect new water main

 Place temporary asphalt patch along pipe trench


WATER MAIN REMOVAL AND REPLACEMENT


PHASE 2 SCHEDULE

May 6 – May 10 Water Main Replacement

May 11 – May 13 Disinfection & Testing

May 14 – May 19 Water Service Installation

May 20 – May 21 Remove Temp Water System Asphalt Patching


PHASE 3 CONSTRUCTION – WATER MAIN

 Install temporary water system to

18 homes  Remove and replace 720 LF of

water main  Remove and replace 18 water

service connections  Disinfection and testing  Remove temporary system  Asphalt patching


PHASE 3 SCHEDULE

May 24 – May 28 Install Temp Water System

June 1 – June 7 Water Main Replacement

June 8 – June 10 Disinfection & Testing

June 11 – June 16 Water Service Installation

June 17 – June 18 Remove Temp Water System Asphalt Patching


PHASE 4 CONSTRUCTION – WATER MAIN  Install temporary water service to

16 homes  Remove and replace 550 LF of

water main  Remove and replace 16 water

service connections  Disinfection and testing  Removal of temporary water

system  Asphalt patching


PHASE 4 SCHEDULE

June 21 – June 25 Install Temp Water System

June 28 – June 30 Water Main Replacement

July 1 – July 3 Disinfection & Testing

July 5 – July 8 Water Service Installation

July 9 – July 12 Remove Temp Water System Asphalt Patching


COMPLETION SCHEDULE

July 13 – July 15 Cleanup Restoration

July 19 – July 23 Mill and Overlay Asphalt


OVERALL PROJECT SCHEDULE


KEY CONTACTS

 Brannan Construction Company 

Luke Lopez – Senior Project Manager; llopez@brannan1.com; 303-534-1231

Jake Jennings – General Superintendent; jjennings@brannan1.com; 303-419-1957

 Centennial Water & Sanitation District 

Jon Klassen – Project Manager; jklassen@highlandsranch.org; 303-791-0430

Emergency After Hours – 720-408-7034


FREQUENTLY ASKED QUESTIONS  Who is performing the water main replacement?

 What are the construction hours?  Will there be water service interruptions?  Will it be necessary to flush the water lines during or after construction?

 What will construction traffic be like?  Will access to driveways be interrupted?  Will residents be able to park on the street?

 Will there be any restrictions on water use?  Will construction updates be provided?