Skip to main content

Water Situation_2015-05-11_en

Page 1

Summary of the water volume, and progress of water shortage prevention and mitigation measures in Rayong and Chonburi Provinces for 2015 11 May 2015 Water War Room

0


SUMMARY

OF THE WATER VOLUME, AND PROGRESS OF WATER SHORTAGE

PREVENTION AND MITIGATION MEASURES IN RAYONG AND PROVINCES FOR 2015-16

CHONBURI

 On May 11th 2015 the combined water volume in the 3 reservoirs is = 118.05 MCM. (42.9%) • Increase since yesterday= 2.13 MCM. PRASAE RESERVOIR– NONGPLALAI RESERVOIR WATER DIVERSION  PUMPED WATER VOLUME 11 MAY 2015  CUMULATIVE PUMPED VOLUME MAY 2015  TOTAL CUMULATIVE PUMPED VOLUME

284,749 2,652,644 9,265,843

MCM. MCM MCM.

 PRASAE- NONGPLALAI PUMP STATION: COMPLETED POUR OF LEAN CONCRETE FOR FOUNDATION SLAB AND STARTED ARRANGING RE-BAR FOR FOUNDATION SLAB (1)  PIPELAYING FOR 30 KM SECTION: CURRENTLY JAKING PIPE ACROSS ROUTE 344 (2)  HEAD TANK: STARTED DRIVING FOUNDATION PILES (3) (1)

(2)

(3)

1


OVERVIEW

OF WATER SITUATION IN

Chachoengsao Reserve Pond P2

P4

RAYONG-CHONBURI AREA 11TH MAY 2015

Chonburi

P1

Rayong

Bangphra

Nongkho

Dokkrai

Nongplalai

Klong Yai

Prasae

117.00

21.40

71.40

163.75

40.10

248.00

38.40

5.49

20.98

87.90

9.18

167.70

33%

26%

29%

54%

23%

68%

26.35

4.49

17.98

74.40

6.18

147.70

0.00

0.18

1.118

1.849

0.002

P3

P5 P6

Private Pond

Reservoir capacity (MCM) Current storage volume (MCM) 13 Percentage of reservoir capacity Useable storage volume Samnakbok (excluding Dead Storage) Reserve Pond (MCM) Inflow into reservoir (MCM)

P7

Bang Phra res. P9

38.4

82

P-BPN P8

5.5

Nong Kho res.

P10

2.969

-

Water volume compared -1.35 +0.05 +1.96 +0.16 -0.51 to previous week -7.55 (-decrease, +increase) -1.30 +1.61 (MCM) Total water volume in 43.89 MCM 118.05 MCM each area (31.7%) (42.9%) Note: * When storage volume falls below 15.2 MCM, it is not possible to transfer water from Klongyai Reservoir to Nongplalai Reservoir

28

167.7

9.2

Khlong Yai res. 87.9 P11Pla Lai res. 21.0 Nong P12 P-NP3 P13 Dok Krai res. P14

Prasae res.

P

28

120 P7

P15

180

P16

Raw Water Pipe Line (EW)

Source of data: Royal Irrigation Department

Demand 2557 (MCM.) Supply (MCM.) Pump Station Raw Water Pipe Line (RID)

Existing Pipe Network

Existing Pipe Network

Constructing Pipe Network

2 Constructing Pipe Network


SUMMARY OF WATER SHORTAGE PREVENTION AND MITIGATION MEASURES IN RAYONG AND CHONBURI PROVINCES Planned water volume Measure

Planned

1. Primary measures 1.1 Water diversion via pumping from Prasae Reservoir

2015 Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

Total

7.5

7.5

9.0

9.0

9.0

15.0

15.0

15.0

15.0

15.0

117

6.61

2.65

Actual

Mar

1.3 Pump water from Rayong River back to Nongplalai Reservoir using RID’s Wat Lahanyai pump station. 1.4 Pump water from Rayong River 1.5 Water transfer from Bangpakong River รวม

7.5

9.0

Pumping in progress -Pipe-laying progress -30 km (beginning) section ~5,300 m remaining

9.27

1.0

7.5

Status (as of 11 May ‘15)

9.0

9.0

1.0

2.0 0.5

0.5

1.0

1.5

3.0

4.5

4.5

1.5

15.0

16.5

19.0

20.5

20.0

17.0

135

3


Simulation of water volume in main Rayong Reservoirs

11 May. ‘15 Water Volume: 118.44 MCM.

4


WATER SITUATION

OF

NONGPLALAI, DOKKRAI

Source of data: Royal Irrigation Department

AND

KLONGYAI RESERVOIRS


WATER SITUATION

OF

BANGPHRA

Source of data: Royal Irrigation Department

AND

NONGKHO RESERVOIRS

6


WATER SITUATION

OF

PRASAE RESERVOIR

Source of data: Royal Irrigation Department

7


WATER SITUATION

OF

DOKKRAI RESERVOIR (BY YEAR)

Source of data: Royal Irrigation Department


WATER SITUATION

OF

NONGPLALAI RESERVOIR (BY YEAR)

Source of data: Royal Irrigation Department


WATER SITUATION

OF

KLONGYAI RESERVOIR (BY YEAR)

Source of data: Royal Irrigation Department


WATER SITUATION

OF

BANGPHRA RESERVOIR (BY YEAR)

Source of data: Royal Irrigation Department


WATER SITUATION

OF

NONGKHO RESERVOIR (BY YEAR)

Source of data: Royal Irrigation Department


Progress of pipe-laying of Prasae-Nongplalai pipeline

30 km from beginning (Prasae reservoir to Junction point with new pipeline) 20 km at end (junction with existing RID pipeline to Nongplalai Reservoir)

Location of laid pipeline Progress Summary : 30 km. section (beginning) – ~5,300 m. remaining as of 30 Mar 2015

: 20 km section (tail end) – Completed


สถานีสบ ู นา้ Pumping Station

่ นา้ อ่างเก็บนา้ ประแสร์-หนองปลาไหล, East Water) (โครงการวางท่อสง Outlet

Prasae Reservoir

Prasae Pump Station (New)

Existing Prasae Pump Station


สถานีสบ ู นา้ Pumping Station

(Prasae Reservoir-Nongplalai Reservoir pipeline system construction project, East Water) No.

Item

1

Pumps and motors

2

Procurement of pump accessories and control system (M&E)

3

Construction of pump station

Mar ‘15

Apr ’15

May ’15

Jun ’15

Excavation Foundation and base slab work Lower level walls Installation of pumps and accessories & testing

Planned progress Actual progress

(1)

 PRASAE- NONGPLALAI PUMP STATION:

 

COMPLETED POUR OF LEAN CONCRETE FOR FOUNDATION SLAB AND STARTED ARRANGING REBAR FOR FOUNDATION SLAB (1) PIPELAYING FOR 30 KM SECTION: CURRENTLY JACKING PIPE ACROSS ROUTE 344 (2) HEAD TANK: STARTED DRIVING FOUNDATION PILES (3)

Aug ’15

Manufactured and ready for installation (6 sets)

Land clearing

4

Jul ’15

(3)

(2)

Sep ’15


TUBMA RESERVOIR DEVELOPMENT PROJECT OBJECTIVE To develop raw water reservoir to increase water supply by 47 MCM per year by pumping water from Rayong River and Tubma canal to be stored at the Tubma reservoir P

Tabma Canal pumping station

P Tabma pond pumping station

P

Investment:

Bt.2,200 mil

Capacity:

47 MCM per year

Project duration:

60 months

Progress update:

61.2%

Operating date:

End 2015 (Expedited to be complete

by Sep. 2015, RY River pump ready Jun. 2015) Progress:

(2) (3)

(1)

Base slabs of (1) Tubma Canal and (2) Rayong River pump stations are built and

pipe laying is in progress (10,044 m). Main pump station design is being

Source : East Water

finalized. (3) Water retaining berm is being constructed.


End of Presentation

17


Turn static files into dynamic content formats.

Create a flipbook
Water Situation_2015-05-11_en by eastwatergroups - Issuu