Summary of the water volume, and progress of water shortage prevention and mitigation measures in Rayong and Chonburi Provinces for 2014 13 February 2014 Water War Room
0
SUMMARY
OF THE WATER VOLUME, AND PROGRESS OF WATER SHORTAGE
PREVENTION AND MITIGATION MEASURES IN RAYONG AND PROVINCES FOR 2015-16
CHONBURI
On February 13th 2015 the combined water volume in the 3 reservoirs is = 175.6 MCM. (63.8%) • Decrease since yesterday= -1.11 MCM. •
Water diversion through tunnel from the KlongYai res. to NongPlaLai res. presently stopped due to Klong Yai Res. level being lower than Nongplalai Res.
Water transfer from Prasae Reservoir to Klongyai Reservoir Currently, pumping stopped for pipeline construction
The Royal Irrigation Department has temporarily raised the spillway level at Klongyai and Prasae Reservoirs by 0.50m
1
OVERVIEW
OF WATER SITUATION IN
Chachoengsao Reserve Pond P2
P4
RAYONG-CHONBURI AREA FEBRUARY 13TH 2015
Chonburi
P1
Rayong
Bangphra
Nongkho
Dokkrai
Nongplalai
Klong Yai
Prasae
117.00
21.40
71.40
163.75
40.10
248.00
49.56
13.22
30.27
129.25
16.04
213.08
42%
62%
42%
79%
40%
86%
37.51
12.22
27.27
115.75
13.04
193.08
-0.23
-0.24
-
0.298
0.039
P3
P5 P6
Private Pond
Reservoir capacity (MCM) Current storage volume (MCM) 13 Percentage of reservoir capacity Useable storage volume Samnakbok (excluding Dead Storage) Reserve Pond (MCM) Inflow into reservoir (MCM)
P7
Bang Phra res. P9
49.6
82
P-BPN P8
3.2
Nong Kho res.
P10
0.337
-
Water volume compared -2.15 -1.43 -3.55 -3.20 -1.27 to previous week -4.32 (-decrease, +increase) -3.56 -8.02 (MCM) Total water volume in 62.78 ล้าน ลบ.ม. 175.55 ล้าน ลบ.ม. each area (45.4%) (63.8%) Note: * When storage volume falls below 15.2 MCM, it is not possible to transfer water from Klongyai Reservoir to Nongplalai Reservoir
28
213.1
16.0
Khlong Yai res. 129.3 P11Pla Lai res. 30.3 Nong P12 P-NP3 P13 Dok Krai res. P14
Prasae res.
P
28
120 P7
P15
180
P16
Raw Water Pipe Line (EW)
Source of data: Royal Irrigation Department
Demand 2557 (MCM.) Supply (MCM.) Pump Station Raw Water Pipe Line (RID)
Existing Pipe Network
Existing Pipe Network
Constructing Pipe Network
2 Constructing Pipe Network
SUMMARY OF WATER SHORTAGE PREVENTION AND MITIGATION MEASURES IN RAYONG AND CHONBURI PROVINCES Planned water volume Measure
Status
2015 มี.ค.
1. Primary measures 1.1 Water diversion via pumping 7.5 from Prasae to Klongyai Reservoir through the RID’s PS–KY pipeline the Klongnamdaeng Canal 1.2 Water diversion via pumping the RID’s PS–KY pipeline connection to Eastwater’s PSNPL pipeline 1.3 Pump water from Rayong River back to Nongplalai Reservoir using RID’s Wat Lahanyai pump station. 1.4 Pump water from Rayong River 1.5 Water transfer from Bangpakong River รวม 7.5
เม.ย.
พ.ค.
มิ.ย.
ก.ค.
ส.ค.
ก.ย.
ต.ค.
พ.ย.
ธ.ค.
รวม
7.5
9.0
9.0
9.0
15.0
15.0
15.0
15.0
15.0
117
1.0
1.0
7.5
9.0
9.0
9.0
Pumping scheduled to start in March 2015 Currently in the process of requesting water allocation and pipeline connection authorization from RID. MOU for water usage scheduled for signing on 19 Feb ‘15 -In process of requesting authorization from ERC to lay pipe across petroleum pipeline
2.0 0.5
0.5
1.0
1.5
3.0
4.5
4.5
1.5
15.0
16.5
19.0
20.5
20.0
17.0
135
3
PROGRESS OF WATER SHORTAGE PREVENTION AND MITIGATION MEASURES IN CHONBURI PROVINCES
Measure
Water volume (MCM)
Planned implementation
10-20
Apr-July 2015
RAYONG AND
Status
2. Eastwater’s secondary measures
Private pond in Chonburi area
Under construction
4
Simulation of water volume in main Rayong Reservoirs
13 Feb. 15 175.6 MCM.
Scenario with Prasae-Konglyai water transfer and reduction of water send to Chonburi
WATER SITUATION
OF
NONGPLALAI, DOKKRAI
Source of data: Royal Irrigation Department
AND
KLONGYAI RESERVOIRS
WATER SITUATION
OF
BANGPHRA
Source of data: Royal Irrigation Department
AND
NONGKHO RESERVOIRS
7
WATER SITUATION
OF
PRASAE RESERVOIR
Source of data: Royal Irrigation Department
8
WATER SITUATION
OF
DOKKRAI RESERVOIR (BY YEAR)
Source of data: Royal Irrigation Department
WATER SITUATION
OF
NONGPLALAI RESERVOIR (BY YEAR)
Source of data: Royal Irrigation Department
WATER SITUATION
OF
KLONGYAI RESERVOIR (BY YEAR)
Source of data: Royal Irrigation Department
Progress of pipe-laying of Prasae-Nongplalai pipeline
30 km from beginning (Prasae reservoir to Junction point with new pipeline) 20 km at end (junction with existing RID pipeline to Nongplalai Reservoir)
Location of laid pipeline Progress Summary : 30 km. section (beginning) – 12 construction teams; length of laid pipe: 15,990.50 m. (59.55%) as of 12 Feb 2015
: 20 km section (tail end) – 9 construction teams; length of laid pipe: 18,183.90 m. (78.70%) : Total length of laid pipe 34,174.40 m. (68.41%)
TUBMA RESERVOIR DEVELOPMENT PROJECT OBJECTIVE To develop raw water reservoir to increase water supply by 47 MCM per year by pumping water from Rayong River and Tabma canal to be stored at the Tabma reservoir P
Tabma Canal pumping station
P Tabma pond pumping station
P
Investment:
Bt.2,200 mil
Capacity:
47 MCM per year
Project duration:
60 months
Progress update:
58.01%
Operating date:
End 2015 (Expedited to be complete by Sep. 2015, RY River pump ready Jun. 2015)
Progress:
Started construction of Tubma Canal and Rayong River pump stations and pipe laying (10,044 m). Main pump station design is
Source : East Water
being finalized. 13
13
End of Presentation
14