Summary of the water volume, and progress of water shortage prevention and mitigation measures in Rayong and Chonburi Provinces for 2014 2 February 2014 Water War Room

0


SUMMARY

OF THE WATER VOLUME, AND PROGRESS OF WATER SHORTAGE

PREVENTION AND MITIGATION MEASURES IN RAYONG AND PROVINCES FOR 2015-16

CHONBURI

 On February 2nd 2015 the combined water volume in the 3 reservoirs is = 188.58 MCM. (68.5%) • Decrease since yesterday= -1.05 MCM. •

Water diversion through tunnel from the KlongYai res. to NongPlaLai res. presently stopped due to Klong Yai Res. level being lower than Nongplalai Res.

Water transfer from Prasae Reservoir to Klongyai Reservoir  Currently, pumping stopped for pipeline construction

The Royal Irrigation Department has temporarily raised the spillway level at Klongyai and Prasae Reservoirs by 0.50m

1


OVERVIEW

OF WATER SITUATION IN

Chachoengsao Reserve Pond P2

P4

RAYONG-CHONBURI AREA FEBRUARY 2ND 2015

Chonburi

P1

Rayong

Bangphra

Nongkho

Dokkrai

Nongplalai

Klong Yai

Prasae

117.00

21.40

71.40

163.75

40.10

248.00

52.62

15.14

35.83

134.45

18.30

220.28

45%

71%

50%

82%

46%

89%

40.57

14.14

32.83

120.95

15.30

200.28

-0.23

-0.04

-

0.320

0.171

P3

P5 P6

Private Pond

Reservoir capacity (MCM) Current storage volume (MCM) 13 Percentage of reservoir capacity Useable storage volume Samnakbok (excluding Dead Storage) Reserve Pond (MCM) Inflow into reservoir (MCM)

P7

Bang Phra res. P9

52.6

82

P-BPN P8

15.1

Nong Kho res.

P10

0.491

-

Water volume compared -1.50 -0.44 -2.76 -3.00 -1.10 to previous week -3.96 (-decrease, +increase) -1.94 -6.86 (MCM) Total water volume in 67.76 MCM 188.58 MCM each area (49%) (68.5%) Note: * When storage volume falls below 15.2 MCM, it is not possible to transfer water from Klongyai Reservoir to Nongplalai Reservoir

28

220.3

18.3

Khlong Yai res. 134.5 P11Pla Lai res. 35.8 Nong P12 P-NP3 P13 Dok Krai res. P14

Prasae res.

P

28

120 P7

P15

180

P16

Raw Water Pipe Line (EW)

Source of data: Royal Irrigation Department

Demand 2557 (MCM.) Supply (MCM.) Pump Station Raw Water Pipe Line (RID)

Existing Pipe Network

Existing Pipe Network

Constructing Pipe Network

2 Constructing Pipe Network


SUMMARY OF WATER SHORTAGE PREVENTION AND MITIGATION MEASURES IN RAYONG AND CHONBURI PROVINCES Measure

Water volume (MCM(

1. Primary measure: Water transfer from Prasae watershed to Klongyai watershed 1.1 Water diversion via pumping from Prasae Reservoir to Klongyai Reservoir through the RID’s Prasae – Klongyai pipeline connection to Eastwater’s Prasae- Nongplalai pipeline and the Klongnamdaeng Canal

67.5

Mar –Oct 2015 RID and Eastwater The connection is planned to be and Dec 2015 completed in February 2015 and 9 Months pumping to start in March 2015

1.2 Construction of temporary pump station at Prase Reservoir

45

Jun-Dec 2015 6 เดือน

RID and East Water

Pumps and motors are purchased, with installation and permit request expected to take 4 months. Pumping should start in June 2015.

2. Supporting measures 2.1 Pumping sideflow from the Rayong River back to Nongplalai Reservoir using RID’s Lahanyai pump station

2

Sep-Oct 2015

RID and East Water

Currently coordinating with RID to improve the pump system

Schedule

Responsible party

-

2.2 Pump extra water from Bangpakong River using Eastwater’s Bangpakong River pump stations 2.3 Reduce the water volume sent from Nongplalai to the Chonburi area by using water from Bangpakong River รวม

สถานะ

15

Jul-Dec 2015

East Water

Pump systems are ready and standing by - The volume of water that can be pumped depends on the condition of Bangpakong River

129.5

3


PROGRESS OF WATER SHORTAGE PREVENTION AND MITIGATION MEASURES IN CHONBURI PROVINCES

Measure

Water volume (MCM)

Planned implementation

10-20

Apr-July 2015

RAYONG AND

Status

2. Eastwater’s secondary measures Private pond in Chonburi area

Under construction

4


Simulation of water volume in main Rayong Reservoirs

2 Feb. 15 188.6 MCM.

Scenario with Prasae-Konglyai water transfer and reduction of water send to Chonburi


WATER SITUATION

OF

NONGPLALAI, DOKKRAI

Source of data: Royal Irrigation Department

AND

KLONGYAI RESERVOIRS


WATER SITUATION

OF

BANGPHRA

Source of data: Royal Irrigation Department

AND

NONGKHO RESERVOIRS

7


WATER SITUATION

OF

PRASAE RESERVOIR

Source of data: Royal Irrigation Department

8


WATER SITUATION

OF

DOKKRAI RESERVOIR (BY YEAR)

Source of data: Royal Irrigation Department


WATER SITUATION

OF

NONGPLALAI RESERVOIR (BY YEAR)

Source of data: Royal Irrigation Department


WATER SITUATION

OF

KLONGYAI RESERVOIR (BY YEAR)

Source of data: Royal Irrigation Department


Progress of pipe-laying of Prasae-Nongplalai pipeline

30 km from beginning (Prasae reservoir to Junction point with new pipeline) 20 km at end (junction with existing RID pipeline to Nongplalai Reservoir)

Location of laid pipeline Progress Summary : 30 km. section (beginning) – 12 construction teams; length of laid pipe: 13,578.5 m. (50.57%) as of 2 Feb 2015

: 20 km section (tail end) – 9 construction teams; length of laid pipe: 17,343.9 m. (75.07%) : Total length of laid paid 30,922.4 m. (61.90%)


Progress of pipe-laying of Prasae-Nongplalai pipeline

30 km from beginning (Prasae reservoir to Junction point with new pipeline) 20 km at end (junction with existing RID pipeline to Nongplalai Reservoir)

Location of laid pipeline Progress Summary : 30 km. section (beginning) – 8 construction teams; length of laid pipe: 8,699.5 m. (32.40%) as of 12 Jan 2015

: 20 km section (tail end) – 11 construction teams; length of laid pipe: 15,738.9 m. (68.12%) : Total length of laid paid 24,438.4 m. (48.92%)


TUBMA RESERVOIR DEVELOPMENT PROJECT OBJECTIVE To develop raw water reservoir to increase water supply by 47 MCM per year by pumping water from Rayong River and Tabma canal to be stored at the Tabma reservoir P

Tabma Canal pumping station

P Tabma pond pumping station

P

Investment:

Bt.2,200 mil

Capacity:

47 MCM per year

Project duration:

60 months

Progress update:

58.01%

Operating date:

End 2015 (Expedited to be complete by Sep. 2015, RY River pump ready Jun. 2015)

Progress:

Started construction of

Tubma Canal and Rayong River pump stations and pipe laying (10,044 m). Main pump station design is

Source : East Water

being finalized. 14

14


End of Presentation