Summary of the water volume, and progress of water shortage prevention and mitigation measures in Rayong and Chonburi Provinces for 2014 2 February 2014 Water War Room
0
SUMMARY
OF THE WATER VOLUME, AND PROGRESS OF WATER SHORTAGE
PREVENTION AND MITIGATION MEASURES IN RAYONG AND PROVINCES FOR 2015-16
CHONBURI
On February 2nd 2015 the combined water volume in the 3 reservoirs is = 188.58 MCM. (68.5%) • Decrease since yesterday= -1.05 MCM. •
Water diversion through tunnel from the KlongYai res. to NongPlaLai res. presently stopped due to Klong Yai Res. level being lower than Nongplalai Res.
Water transfer from Prasae Reservoir to Klongyai Reservoir Currently, pumping stopped for pipeline construction
The Royal Irrigation Department has temporarily raised the spillway level at Klongyai and Prasae Reservoirs by 0.50m
1
OVERVIEW
OF WATER SITUATION IN
Chachoengsao Reserve Pond P2
P4
RAYONG-CHONBURI AREA FEBRUARY 2ND 2015
Chonburi
P1
Rayong
Bangphra
Nongkho
Dokkrai
Nongplalai
Klong Yai
Prasae
117.00
21.40
71.40
163.75
40.10
248.00
52.62
15.14
35.83
134.45
18.30
220.28
45%
71%
50%
82%
46%
89%
40.57
14.14
32.83
120.95
15.30
200.28
-0.23
-0.04
-
0.320
0.171
P3
P5 P6
Private Pond
Reservoir capacity (MCM) Current storage volume (MCM) 13 Percentage of reservoir capacity Useable storage volume Samnakbok (excluding Dead Storage) Reserve Pond (MCM) Inflow into reservoir (MCM)
P7
Bang Phra res. P9
52.6
82
P-BPN P8
15.1
Nong Kho res.
P10
0.491
-
Water volume compared -1.50 -0.44 -2.76 -3.00 -1.10 to previous week -3.96 (-decrease, +increase) -1.94 -6.86 (MCM) Total water volume in 67.76 MCM 188.58 MCM each area (49%) (68.5%) Note: * When storage volume falls below 15.2 MCM, it is not possible to transfer water from Klongyai Reservoir to Nongplalai Reservoir
28
220.3
18.3
Khlong Yai res. 134.5 P11Pla Lai res. 35.8 Nong P12 P-NP3 P13 Dok Krai res. P14
Prasae res.
P
28
120 P7
P15
180
P16
Raw Water Pipe Line (EW)
Source of data: Royal Irrigation Department
Demand 2557 (MCM.) Supply (MCM.) Pump Station Raw Water Pipe Line (RID)
Existing Pipe Network
Existing Pipe Network
Constructing Pipe Network
2 Constructing Pipe Network
SUMMARY OF WATER SHORTAGE PREVENTION AND MITIGATION MEASURES IN RAYONG AND CHONBURI PROVINCES Measure
Water volume (MCM(
1. Primary measure: Water transfer from Prasae watershed to Klongyai watershed 1.1 Water diversion via pumping from Prasae Reservoir to Klongyai Reservoir through the RID’s Prasae – Klongyai pipeline connection to Eastwater’s Prasae- Nongplalai pipeline and the Klongnamdaeng Canal
67.5
Mar –Oct 2015 RID and Eastwater The connection is planned to be and Dec 2015 completed in February 2015 and 9 Months pumping to start in March 2015
1.2 Construction of temporary pump station at Prase Reservoir
45
Jun-Dec 2015 6 เดือน
RID and East Water
Pumps and motors are purchased, with installation and permit request expected to take 4 months. Pumping should start in June 2015.
2. Supporting measures 2.1 Pumping sideflow from the Rayong River back to Nongplalai Reservoir using RID’s Lahanyai pump station
2
Sep-Oct 2015
RID and East Water
Currently coordinating with RID to improve the pump system
Schedule
Responsible party
-
2.2 Pump extra water from Bangpakong River using Eastwater’s Bangpakong River pump stations 2.3 Reduce the water volume sent from Nongplalai to the Chonburi area by using water from Bangpakong River รวม
สถานะ
15
Jul-Dec 2015
East Water
Pump systems are ready and standing by - The volume of water that can be pumped depends on the condition of Bangpakong River
129.5
3
PROGRESS OF WATER SHORTAGE PREVENTION AND MITIGATION MEASURES IN CHONBURI PROVINCES
Measure
Water volume (MCM)
Planned implementation
10-20
Apr-July 2015
RAYONG AND
Status
2. Eastwater’s secondary measures Private pond in Chonburi area
Under construction
4
Simulation of water volume in main Rayong Reservoirs
2 Feb. 15 188.6 MCM.
Scenario with Prasae-Konglyai water transfer and reduction of water send to Chonburi
WATER SITUATION
OF
NONGPLALAI, DOKKRAI
Source of data: Royal Irrigation Department
AND
KLONGYAI RESERVOIRS
WATER SITUATION
OF
BANGPHRA
Source of data: Royal Irrigation Department
AND
NONGKHO RESERVOIRS
7
WATER SITUATION
OF
PRASAE RESERVOIR
Source of data: Royal Irrigation Department
8
WATER SITUATION
OF
DOKKRAI RESERVOIR (BY YEAR)
Source of data: Royal Irrigation Department
WATER SITUATION
OF
NONGPLALAI RESERVOIR (BY YEAR)
Source of data: Royal Irrigation Department
WATER SITUATION
OF
KLONGYAI RESERVOIR (BY YEAR)
Source of data: Royal Irrigation Department
Progress of pipe-laying of Prasae-Nongplalai pipeline
30 km from beginning (Prasae reservoir to Junction point with new pipeline) 20 km at end (junction with existing RID pipeline to Nongplalai Reservoir)
Location of laid pipeline Progress Summary : 30 km. section (beginning) – 12 construction teams; length of laid pipe: 13,578.5 m. (50.57%) as of 2 Feb 2015
: 20 km section (tail end) – 9 construction teams; length of laid pipe: 17,343.9 m. (75.07%) : Total length of laid paid 30,922.4 m. (61.90%)
Progress of pipe-laying of Prasae-Nongplalai pipeline
30 km from beginning (Prasae reservoir to Junction point with new pipeline) 20 km at end (junction with existing RID pipeline to Nongplalai Reservoir)
Location of laid pipeline Progress Summary : 30 km. section (beginning) – 8 construction teams; length of laid pipe: 8,699.5 m. (32.40%) as of 12 Jan 2015
: 20 km section (tail end) – 11 construction teams; length of laid pipe: 15,738.9 m. (68.12%) : Total length of laid paid 24,438.4 m. (48.92%)
TUBMA RESERVOIR DEVELOPMENT PROJECT OBJECTIVE To develop raw water reservoir to increase water supply by 47 MCM per year by pumping water from Rayong River and Tabma canal to be stored at the Tabma reservoir P
Tabma Canal pumping station
P Tabma pond pumping station
P
Investment:
Bt.2,200 mil
Capacity:
47 MCM per year
Project duration:
60 months
Progress update:
58.01%
Operating date:
End 2015 (Expedited to be complete by Sep. 2015, RY River pump ready Jun. 2015)
Progress:
Started construction of
Tubma Canal and Rayong River pump stations and pipe laying (10,044 m). Main pump station design is
Source : East Water
being finalized. 14
14
End of Presentation