Oak Hills Constructors, the joint-venture of Granite Construction and Ralph L. Wadsworth, are making progress on the Utah Department of Transportation’s U.S. 89: Farmington to I-84 Project.
Service
Construction crews from Oak Hills Constructors [Granite Construction and Ralph L. Wadsworth joint venture] are making steady progress on the Utah Department of Transportation’s U.S. 89: Farmington to I-84 Project.
The latest construction milestone highlighted crews placing 18 beams for the new interchange bridge at Gordon Avenue in Layton over a span of three days. see CONSTRUCTORS page 6
Specializing in New, Used & Rebuilt Replacement Parts
• Undercarriage Parts • Field Service • Equipment Sales • Attachments • Full Service Shop • Hydraulic Cylinder Repair • New and Used Parts • Track Repair • Teeth & Edges We Buy Salvage Equipment Alternative to the dealer for all makes & models
Sales
Utah Track & Welding Service & Sales
801-972-8939
6382 West 2100 South, Salt Lake City, Utah 84128 • www.utahtrackandwelding.com • sam@utahtrackandwelding.com
Page 2 • May 23, 2021 • www.constructionequipmentguide.com • Utah State Supplement • Construction Equipment Guide
PROVEN TECHNOLOGY HIGH UPTIME At Sandvik we have combined years of industry expertise and the latest advances in technology to develop pioneering mobile crushing and screening solutions for you. Utilizing Sandvik’s renowned, proven technology and smart process solutions, such as My Fleet remote monitoring, our equipment is designed to increase operational ELjCIENCY OPTIMIZE PRODUCTIVITY AND MAXIMIZE UPTIME
WANT TO BE A SANDVIK DEALER? CONTACT US TODAY ROCKTECHNOLOGY.SANDVIK
tim.winslow@sandvik.com
720-471-0718
Construction Equipment Guide • Utah State Supplement • www.constructionequipmentguide.com • May 23, 2021 • Page 3
Page 4 • May 23, 2021 • www.constructionequipmentguide.com • Utah State Supplement • Construction Equipment Guide
Firm to Submit Application for $595M Hydrogen Hub in Delta Mitsubishi Power Americas and Magnum Development recently announced that its jointly developed Advanced Clean Energy Storage Project has been invited by the U.S. Department of Energy’s [DOE] Loan Programs Office to submit a Part II Application for up to $595 million under the Title 17 Innovative Energy Loan Guarantee Program to develop a proposed green hydrogen hub in Delta, Utah. The green hydrogen hub is part of a broad effort to support decarbonization efforts across the western United States. The DOE program finances projects that accelerate commercial deployment of innovative energy technology that avoids, reduces or sequesters greenhouse gas or air pollutant emissions. The green hydrogen hub at the Advanced Clean Energy Storage Project would interconnect green hydrogen production, storage and distribution in the west. Green hydrogen — which is hydrogen produced from renewable energy sources — will support decarbonizing multiple industries including power, transportation and manufacturing. Haddington Ventures, the financial advisor of the project and equity sponsor of Magnum Development, will submit the Part II Application this summer. If successful, the project will enter due diligence for the potential loan guarantee. Additionally, Haddington Ventures is responsible for interfacing with the DOE as well as managing the Equity Syndication Program [ESP] to provide construction capital on behalf of the Advanced Clean Energy Storage Project. If the project reaches loan closing, debt financing from the DOE would support construction of the green hydrogen hub, which ultimately targets building more than 1,000 megawatts [MW] of electrolysis facilities capable of producing more than 450 metric tons per day of green hydrogen. The hydrogen would be stored in the Advanced Clean Energy Storage Project’s salt caverns, which are natural geological formations providing safe, reliable and cost-effective bulk storage of hydrogen. The massive salt for-
mation is adjacent to the Intermountain Power Project near Delta, Utah, with transmission interconnections to major demand centers and significant renewable energy resource opportunities in the region. The project’s salt caverns will be capable of holding more than 5,500 metric tons of hydrogen. From an energy storage perspective, one cavern holds the equivalent of 150 gigawatt hours [GWh] of carbonfree dispatchable energy and/or decarbonized fuel that can be used in other industries. By comparison, a U.S. Energy Information Administration [EIA] 2020 report estimates the current installed base of battery energy storage across the United States at 1.2 GWh. Therefore, using salt caverns for energy storage is a significant opportunity to expand energy storage resources throughout the United States and further supports the increased build-out of renewable energy. “We look forward to working with the Department of Energy to explore financing opportunities for innovative renewable energy projects like ours that not only will help decarbonize the west, but also will support hundreds of clean energy jobs in Millard County and across the state of Utah,” said Craig Broussard, president and CEO of Magnum Development. “Together with our partner Magnum, we have been planning and developing the world’s largest renewable energy storage project for several years,” said Paul Browning, president and CEO of Mitsubishi Power Americas. “We would welcome the Department of Energy’s support to help us realize utility-scale green hydrogen production, storage and distribution to decarbonize power and other industries throughout the western U.S. Our green hydrogen hub will help bring a change in power.” About Mitsubishi Power Americas Inc. Mitsubishi Power Americas Inc., headquartered in Lake Mary, Fla., employs more than 2,000 power generation, energy storage and digital solutions experts and profes-
sionals. Its employees are focused on empowering customers to affordably and reliably combat climate change while also advancing human prosperity throughout North and South America. Mitsubishi Power’s power generation solutions include natural gas, steam, aero-derivative, geothermal, distributed renewable technologies, environmental controls and services. Energy storage solutions include green hydrogen and battery energy storage systems. Mitsubishi Power also offers digital solutions that enable autonomous operations and maintenance of power assets. Mitsubishi Power Ltd. is a wholly owned subsidiary of Mitsubishi Heavy Industries Ltd. [MHI]. Headquartered in Tokyo, Japan, MHI is a heavy machinery manufacturer with engineering and manufacturing businesses spanning energy, infrastructure, transport, aerospace and defense. For more information, visit power.mhi.com. About Magnum Development Magnum Development LLC owns and controls the only known “Gulf Coast” style domal-quality salt formation in the western United States. Magnum was originally funded by Haddington Energy Partners III in 2008 to support a variety of projects centered around a large salt body near Delta, Utah. About Haddington Ventures Founded in 1998, Haddington Ventures LLC oversees a growing portfolio of successful conventional and renewable energy businesses that are bringing innovative new infrastructure to the U.S. energy sector. Haddington Ventures, through its private equity funds, generally makes control-oriented investments in portfolio companies acquiring or developing energy infrastructure underwritten by long term contracts. Haddington Ventures is led by a team of senior energy professionals who have invested more than $1.5 billion in companies focused on energy infrastructure across multiple private equity funds and co-investment partnerships.
Bangerter Hwy. Closes for New Construction Drivers in southwestern Salt Lake County are advised to plan ahead for a six-month closure of 10400 South in South Jordan. The road will be closed to east-west traffic at Bangerter Highway through November while crews construct a new freeway-style interchange. Three new freeway-style interchanges are currently under construction along Bangerter Highway at 6200 South, 10400 South and 12600 South. These interchanges will eliminate stoplights for Bangerter Highway drivers and improve safety by removing cross traffic. This continues a multi-year program of upgrading Bangerter Highway by converting intersections to interchanges to accommodate current and future growth in this part of the state. The Bangerter Interchanges project coordinated closely with the cities and local businesses when planning the closure of both 10400 South and 12600 South. Overlapping the two closures [12600 South is expected to open in August] saves at least a year from the schedule, along with millions of taxpayer dollars from the budget, versus building the interchanges one after the other. “This area is really growing and that’s why we’re so focused on converting each of these intersections into interchanges,” said Marwan Farah, UDOT Bangerter interchanges project manager. “Closing 10400 South means we can build the interchange more quickly and safely, at a lower cost to taxpayers.” During the closure, Bangerter Highway will remain open in both directions, and the traffic signal at 10400 South will be removed permanently. In addition, right turns both on and off 10400 South will still be open. For more information, visit udot.utah.gov/bangerter.
Construction Equipment Guide • Utah State Supplement • www.constructionequipmentguide.com • May 23, 2021 • Page 5
NO HA HASSLES SS ES. NO H HIDDE IDDEN COSTS O S. NO O KIDDIN KID NG.
UTAH SALT LT LAKE L CITY Y 4343 Century Dr. Salt Lake City, UTT 84123 Phone: 801-262-5761 Fax: 801-262-5780
SPRINGVILLE 1350 South 2000 West Springville, UT 84663 Phone: 801-794-1463 Fax: 801-794-1414
LOGAN 453 North 1000 West Logan, UT 84321 Phone: 435-752-1533 Fax: 435-752-5722
All rights reserved. CASE is a trademark registered in the United States and many other countries, owned by or licensed to CNH Industrial N.V., its subsidiaries bsidiaries or affiliates.
CED DAR CITY 4822 North N Main Street Ceddar City, UT 84720 Phoone: 435-586-4406 Faxx: 435-586-2362 Email: del.maxedon@centuryeq.com
Page 6 • May 23, 2021 • www.constructionequipmentguide.com • Utah State Supplement • Construction Equipment Guide
Joint-Venture Slides 18 Girders Into Place On U.S. 89 Job CONSTRUCTORS from page 1
Crews were able to make quick work of that portion of the project, however, there were certain aspects of the job that has presented its challenges for the contractor. The project calls for reconstructing U.S. 89 by removing the existing pavement and replacing it with allnew asphalt. Crews are widening the highway to three lanes in each direction and replacing all of the existing at-grade intersections with four new interchanges. “The most challenging aspect of this project, by a long shot, has been the relocation of existing utilities,” said Michael Romero, U.S. 89 project director. “There are more than 150 miles of utilities in our 9-mile project area. Originally, U.S. 89 was envisioned as crossing over the local streets, but based on public input we changed the design, and now U.S. 89 crosses under local streets. This change added a ton of complexity to the design, because now we have to find a spot for all of these utilities that are being displaced as we lower these sections of the highway. “Another main challenge is maintaining access to the local communities while we rebuild the highway,” Romero added. “Our contractor has a complex phasing plan that keeps all existing lanes open on U.S. 89 during weekdays, limits most lane closures to nights and weekends and keeps local streets open.” Additional construction includes two new overpasses built at Nicholls Road and Crestwood Road, with those local streets crossing over U.S. 89, and new frontage roads on both sides of the highway are being constructed to help maintain access to local neighborhoods. “U.S. 89 had old, failing pavement, and at the same time the highway had not been modified to accommodate the number of vehicles that use it every day,” said Romero. “Removing stoplights will both enhance safety and keep traffic moving. We’re also building a new frontage road system, and a new 3-mile extension of Gordon Avenue, a city street that will be a new east-west connection from U.S. 89. to I-15.” The U.S. 89 project also will improve safety and mobility on U.S. 89 and at connections with
Avenue extension, along with the new interchange bridges [and two additional bridges over the highway at Nicholls Road and Crestwood Road] will make it easier for local residents to get around their neighborhoods as well as easier to get on the highway. The new Gordon Avenue interchange and road extension is being planned and built in partnership with the city of Layton to allow for future economic development, including a new planned ‘town center.’ Finally, the new pavement will extend the life of the road surface and provide a better ride for drivers.” Project Impacts As the U.S. 89 project team is working to relocate more than 150 The project calls for reconstructing U.S. 89 by removing the existing pavement and replacing it with all new asphalt. Crews are widening the highway to three lanes in each direction and replacing all of the existing at-grade intersections with four new interchanges.
local cross streets by: • Widening U.S. 89 to three lanes in each direction from Main Street in Farmington to State Route 193 in Layton; • Adding interchanges — bridges over U.S. 89 with on/off ramps — at 200 North/400 North, Oak Hills Drive, Gordon Avenue and Antelope Drive. The project also will improve connections between U.S. 89 and Main Street, S.R. 193 and Interstate 84. Some sections of new frontage road will be constructed to improve access to existing frontage roads and local streets.
This will help local traffic access the new interchanges and cross efficiently. The frontage roads will include shared shoulders that will also function as a parallel bicycle route. “We like to say we’re building the right project for this area, designed to meet the needs of the community now and in the future,” said Romero. “Adding the third lane in each direction on U.S. 89, along with eliminating all at-grade intersections, will allow traffic to flow much more smoothly and safely through 2040. The new frontage road system and Gordon
The latest construction milestone highlighted crews placing 18 beams for the new interchange bridge at Gordon Avenue in Layton over a span of three days.
Additional construction includes two new overpasses built at Nicholls Road and Crestwood Road.
mi. of utilities across the corridor, earthwork is ongoing as crews begin creating the new drainage ponds, highway ramps and east side frontage road alignment. The focus of work is near 200 North/400 North in Fruit Heights, Oak Hills Drive and Gordon Avenue, although work is occurring throughout the project area. Impacts to travel on U.S. 89 can include shoulder closures, nighttime and weekend lane closures, one-way traffic operations on local side streets and frontage roads, intermittent driveway access interruptions and increased activity from construction equipment and trucks. The project is scheduled for completion in 2023.
Construction Equipment Guide • Utah State Supplement • www.constructionequipmentguide.com • May 23, 2021 • Page 7
New Construction...
Rio Tinto to Build Tellurium Plant at Kennecott Mine Site
Rio Tinto expects to begin production of tellurium in the fourth quarter of 2021, creating a new North American supply chain.
Rio Tinto will begin construction on a new plant that will recover tellurium, a critical mineral used in solar panels, from copper refining at its Kennecott mine near Salt Lake City, Utah. Rio Tinto is investing $2.9 million to set up the plant, which will recover tellurium as a by-product of copper smelting, extracting a valuable mineral from waste streams. The plant will have a capacity to produce approximately 20 tpy of tellurium. Rio Tinto expects to begin production of tellurium in the fourth quarter of 2021, creating a new North American supply chain. Tellurium is an essential component of cadmium telluride, a semiconductor used to manufacture thin film photovoltaic [PV] solar panels. Thin films made of this compound can efficiently convert sunlight into electricity. Tellurium also can be used as an additive to steel and copper to improve machinability, making these metals easier to cut. It also can be added to lead to increase resistance to sulfuric acid, vibration and fatigue. “The minerals and metals we produce are essential to accelerate the transition to renewable energy,” Rio Tinto Kennecott Managing Director Gaby Poirier said. “Adding tellurium to our product portfolio provides customers in North America with a secure and reliable source of tellurium produced at the highest environmental and labor standards with renewable energy. Rio Tinto is committed to using innovation to reduce waste in our production process and extract
as much value as possible from the material that we mine and process.” Utah Gov. Spencer Cox added, “With abundant natural resources, Utah is ideally positioned to help supply the critical minerals essential to maintain American manufacturing competitiveness. Rio Tinto’s smelter at Kennecott is one of only two that is capable of producing copper and other critical minerals. The new tellurium plant is another valuable contribution to critical mineral independence and energy security in the U.S.” Along with producing almost 20 percent of U.S. copper, Kennecott’s smelting process also recovers gold, silver, lead carbonate, platinum, palladium and selenium, while molybdenum is recovered from the Copperton concentrator. In total, nine products are currently recovered from the ore extracted at Kennecott. About Rio Tinto Rio Tinto is a partner with the U.S. Department of Energy’s Critical Materials Institute [CMI] and works closely with CMI experts to discover further ways to economically recover critical mineral byproducts such as rhenium, tellurium and lithium. The company also is investing in new facilities to extract battery grade lithium from waste rock at its Boron, Calif., mine site and highquality scandium oxide from waste streams at its metallurgical complex in Sorel-Tracy, Quebec, Canada.
The Next Closing Date is June 9, 2021
FULL PAGE 10.125”x10.625”
Open 13 Time $635 $590
1/2 PAGE 10.125”x5.25” or 5”x10.625”
Open 13 Time $525 $445
1/4 PAGE 5”x5.25”
Open 13 Time $355 $330
UTAH PUBLISHING 2021 Issue# 13 15 17 19 21
Closing June 9 July 7 August 4 August 31 September 29
Publishing June 20 July 18 August 15 September 12 October 10
Page 8 • May 23, 2021 • www.constructionequipmentguide.com • Utah State Supplement • Construction Equipment Guide
GET VERTICAL Boom and scissor lifts now available!
BOOM LIFTS
Up, overr,, out or a combination of all three, articulated and telescopic boom lifts get you where you need to go to get the job done. Gain access to hard-to-reach areas with precision positioning, obstacle navigation and unmatched outreach. Emission-free and quiet operation allow for out and over positioning in indoor work environments where sensitivity is required.
When your project demands height, Wheeler has the equipment for you. Boom and scissor lifts are now available for rent or purchase. chase. Plus, we’ve got the parts and service to keep your personnel lifts running safely and nd at peak performance.
SCISSOR LIFTS
Offering both slab and rough terrain scissor lifts, Wheeler has your work-atheight needs covered whether operating on firm, level surfaces or soft, uneven dirt. Large work platforms increase efficiency and capacity while compact footprints provide access in tight spaces. Quiet, electric motors give you the flexibility to work both indoors and outside.
PARTS
|
RENTAL
|
SALES
| SERVICE
Contact Wheeler Machinery Co. C for more information. Call 800-662-8650 or visit wheeelercat.com/aerial