Crews from Guy F. Atkinson are executing a $107 million upgrade to the Pomona Freeway (SR 60) between the I-710 Long Beach and San Gabriel River (I-605) freeways to extend the lifespan of the highway.
By Irwin Rapoport CEG CORRESPONDENT
Crews from Guy F. Atkinson are upgrading approximately 10 mi. of the Pomona Freeway (SR 60) between the I710 Long Beach (I-710) and San Gabriel River (I-605) freeways to extend the lifespan of the highway. The $107 million initiative, financed by state and federal funds and being overseen by the California Department of Transportation, started in the summer of 2019 and should be
completed in the winter of 2024/2025. “This project is to restore the roadway and improve the ride quality by rehabilitating the existing lanes with pavement that will extend the life of the roadway a minimum of 40 years, only requiring minimal maintenance by Caltrans once completed,” said Peter Jones, Caltrans spokesperson of District 7. “SR 60 is a major thoroughfare serving commuters between Los Angeles, San Bernardino and Riverside counties. As a result of heavy use, it is being rehabilitated in both directions.”
SACRAMENTO ONLINE EQUIPMENT AUCTION
Construction Details The work includes the placement of concrete and asphalt pavement; safety improvements; the installation of new guardrail systems, new lights and sign structures; and improvements to pedestrian ramps. Atkinson crews have been hard at work, meeting benchmarks and overcoming challenges. The 2021 construction season is focusing on improving safety and visibility. “Work is moving smoothly with concurrent operations on see PAVING page 8
WOODBURN ONLINE EQUIPMENT AUCTION
Friday, August 27th, 2021 @ 8:30am Saturday, August 14th, 2021 @ 8:30am 4751 Power Inn Rd., Sacramento, CA 95826 17129 Highway 99E NE, Woodburn, OR 97071
www.barnoneauction.com | (866) www.BARNONEAUCTION.com 866 372 - 372- -1700 1700
Page 2 • July 4, 2021 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide
Fontana:
909-822-2200 •
Santa Fe Springs:
562-777-0775
NEW EQUIPMENT. Finance program Option 1: Low rate financing (0.9% for 60M) + 3 year 5,000-hour powertrain and hydraulics extended warranty
Doosan DL200
Option 2: Low rate financing (0.9% for 36M) + 5 year 7,500-hour powertrain and hydraulics extended warranty
Scott Equipment 14635 Valley Blvd. Fontana, CA 92335 909-822-2200
10918 Shoemaker Ave. Santa Fe Springs, CA 90670 562-777-0775
Construction Equipment Guide • California State Supplement • www.constructionequipmentguide.com • July 4, 2021 • Page 3
Let’s talk size for a minute. Cat® small excavvators can handle smaller jobs or space-constrained applications cations at a low cost per p hour. That means more productive p and more profitable jobs. And now, yyou can take advantage gge of the latest offer for these machines and get big savingss — a low financing rate to lower your payments and free up cash. Small excavators. Big savings. Exactly the right sizze for you.
0% for 36 months* This special financing rate is available on eligible new models through December 31, 2021. Contact your California Cat dealer for more details and to see a list of o eligible models or visit cat.com/bigsavings.
www.hawthornecat.com San Diego County 800-437-4228
ww ww.holtca.com Cenntral Northern California 8000-452-5888
www.petersoncat.com Bay Area & Northern California, Oregon, and Southwest Washington 844-349-4353
www.quinncompany.com Central & Southern California 888-842-2155
*Offer Offer valid from July 11, 2021 through December 31 31, 2021 on new 311 through 3188 Cat® excavators sold by participating Cat dealers to customers in the USA. Purchase must occur during offer period. Offer subject to machine availability and credit approval by Cat Financial. Not all customers will qualify. Offer may change without prior notice and cannot be com mbined with any other offers. Additional terms and conditions may apply. Contact your Cat dealer for details. © 2021 Caterpillar. All Rights Reserved. CA AT, T, CA ATERPILLAR, TERPILLAR, LET’S DO THE WORK, WORK K, their respective logos, “Caterpillar Corporate YYellow”, the “Power Edge” and Cat “Modern Hex” trade dress as well as corporate and product identity used herein, are trademarks of Caterpillar and may not be used without permission.
Page 4 • July 4, 2021 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide
Water Pipeline Construction Under Way in Santa Cruz
For this prohect, crews have been working around California Street, from the Santa Cruz Wastewater Treatment Facility to Laurel Street. After that, and until July 6, construction will take place on Laurel Street to Chestnut Street.
Crews are hard at work constructing 8 mi. of water pipeline that will serve as lifeblood for the Pure Water Soquel Project in Santa Cruz. The project began on May 24. Three distinct components of building are set to take place during the next several months. From late May until June 15 crews had been working around California Street, from the Santa Cruz Wastewater Treatment Facility to Laurel Street. After that, and until around July 6, construction will take place on Laurel Street to Chestnut Street. The third scheduled construction phase will run from July 6 through Aug. 12 on Chestnut to the west end of the Laurel Street Bridge.
The project aims to address seawater intrusion occurring in the Santa Cruz Mid County Groundwater Basin, and the issue of overdraft, as mandated by the State Water Resources Control Board. That means more water is being used and drawn out in the underground reservoir than replenished. The basin is the only source of drinking water from 41st Avenue in Capitola to La Selva Beach. The Pure Water Soquel project is twofold: reduce seawater contamination and bolster groundwater levels in the aquifer. “We are challenged by both drought and an overdrafted groundwater basin,” said Melanie Mow Schumacher, communica-
The Pure water project at-large, including the recycled water facility, pump station and water purification center, is scheduled to be completed and up and running by 2025,
tions manager of the Soquel Creek Water District. “We kind of have that coupled with the fact that we rely on 100 percent of local water in our county…we’re not connected to any state or federal import system,” Mow Schumacher said. Funds to build the water pipeline are coming out of a $50 million grant from the State Water Resources Control Board. The water district has also secured a low-interest loan from the federal EPA and a grant from the Bureau of Reclamation, according to Mow Schumacher.
Construction on the water pipeline portion of the project is slated to continue though the end of 2022, Mow Schumacher said. The seawater intrusion prevention wells, near the Capitola area, are expected to be drilled and completed by early July. The Pure water project at-large, including the recycled water facility, pump station and water purification center, is scheduled to be completed and up and running by 2025, Mow Schumacher said. For more information, visit https://www.soquelcreekwater.org/256/ Construction-Updates.
Caltrans Awards $34M for Transportation Upgrade Projects Caltrans recently awarded $34 million in state and federal funds to cities, counties, tribes and transit agencies throughout California to improve the state’s transportation network. The grant money — including $25 million funded by Senate Bill (SB) 1, the Road Repair and Accountability Act of 2017 — will be used to plan sustainable transportation projects that reduce greenhouse gas emissions, improve the state highway system, enhance access to safe walkways and bikeways and increase natural disaster preparedness. “Investing in transportation planning is essential to our goal of providing a safe, sustainable system that advances equity and livability throughout the state,” said said Caltrans Director Toks Omishakin. “These grants will help
our communities create more connected routes for all residents, regardless of whether they travel by car, bike, foot or mass transit.” In total, Caltrans allocated: • $17.4 million — including $12.38 million from SB 1 — in Sustainable Communities Competitive and Technical Grants to 50 local, regional, tribal and transit agencies for climate change adaptation, complete streets, transportation and land use planning and natural disaster preparedness. This includes more than $4 million to fund planning for 13 projects that improve safety and access for people who walk and bike. • $12.5 million in Sustainable Communities Formula Grants, completely funded by SB 1, to metropoli-
tan planning organizations to further regional transportation plans and sustainable communities strategies. • $4 million in federally funded Strategic Partnership Grants to nine projects that will plan for nextgeneration freeways, improve transit options between communities, research alternative funding for road repairs, and advance the timely and efficient movement of goods throughout the state. Caltrans awards planning grants each year through a competitive process to encourage local and regional projects. Applications are evaluated on how they further state transportation goals by identifying and addressing statewide, interregional or regional transportation deficiencies on the highway system.
Construction Equipment Guide • California State Supplement • www.constructionequipmentguide.com • July 4, 2021 • Page 5
What can you haul in a side dump trailer? Nearly anything.
Superior Stability
Faster Cycle Times
Easier Unloading
With construction grade tires and an ability to haul dirt, rock, millings, riprap and other materials, our trailers help solve the everyday challenges of the construction industry. When we build trailers, we build solutions. 800-779-8099 • sidedump.com
Page 6 • July 4, 2021 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide
Construction Equipment Guide • California State Supplement • www.constructionequipmentguide.com • July 4, 2021 • Page 7
Lakeside 12345 Mapleview St. Lakeside, CA 92040 619.441.3690 Corona 22099 Knabe Rd. Corona, CA 92883 951.277.7620 Bakersfield 9150 Golden State Hwy. Bakersfield, CA 93308 661.387.6090 Fresno 4501 E. Volvo Ave. Fresno, CA 93725 559.834.4420 Turlock 1275 Venture Ln. Turlock, CA 95380 209.410.6710
Equipment built to work as hard as you do.
San Leandro 1944 Marina Blvd. San Leandro, CA 94577 510.357.9131 Sacramento 8594 Fruitridge Rd. Sacramento, CA 95826 916.504.2300
Find us on social media: facebook.com/volvoces VolvoCES volvoces
You work hard every day, and need to get the job done right the first time. At Volvo Construction Equipment & Services, we know that your work is important. When it comes to machines that are rugged, reliable and productive, Volvo is the market leader. Our equipment lineup will give you the capability to tackle every job — and unmatched performance that keeps you up and running. Give us a call to learn more, and to take advantage of our latest financing offers.
vcesvolvo.com
*All financing conditions, including customer qualification, final approved transaction terms, and down payment amount are subject to Volvo Financial Services (VFS) credit underwriting guidelines and advance policy. VFS reserves the right to amend or discontinue these offers at any time without notice. Available in both the U.S. and Canada. Offer expires August 31, 2021.
Rates as low as
0% FOR 36 MONTHS
*
Page 8 • July 4, 2021 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide
Crews Perform Excavation On ‘Distressed’ SR 60 Highway PAVING from page 1
a nightly basis throughout the project,” said the Guy F. Atkinson team. “Traffic control, vandalism of traffic control items and homeless encampments are some of the challenges facing the crews. The presence of the CHP units are effective in mitigating the challenges of public traffic incidents and homeless encampment and deterring vandalism.” Excavation is focusing on the roadways and for the new drainage structures, as well as for new sign structure and new bridge approach slabs. Crews are upgrading and replacing concrete and asphalt paving. Excavation and demolition activities are expected to generate 160,000 cu. yds. of concrete, 760,000 lbs. of steel and 24,000 tons of asphalt. “The Class III aggregate base was recycled from the excavated existing concrete ” said Sepand Minovi, Caltrans resident engineer. “This is not only beneficial to reducing our environmental footprint, but a cost savings to the contractor.” Peak days thus far have many Guy F. Atkinson Construction and subcontractor personnel on-site. The major subcontractors are RV Concrete for replacement of individual slab replacements and bridge approach slabs; BC Traffic Specialist for traffic control, removal and installation of new overhead signs and sign structures, temporary and permanent striping and roadside signs; All American Asphalt Co. for paving the ramp and shoulders with hot mix asphalt concrete; Cooper Engineering for concrete median barrier; RE Mason for grinding new and existing pavement for smoothness; and Sierra Landscape for irrigation and planting. Other equipment being used includes: grinders, slip form machinery and volumetric trucks. “The main wear and tear issues are tires and hydraulic issues,” said a
The project is financed by state and federal funds and being overseen by the California Department of Transportation. It began in the summer of 2019 and should be completed in the winter of 2024/2025.
The Class III aggregate base was recycled from the excavated existing concrete. This is not only beneficial to reducing our environmental footprint, but a cost saver to the contractor.
representative with Guy F. Atkinson. “Even though on-site mechanics are provided, routine maintenance is key to stay organ-
The work includes the placement of concrete and asphalt pavement; safety improvements; the installation of new guardrail systems; new lights and sign structures; and improvements to pedestrian ramps.
ized and communication is also key for quick repairs.” In addition, electrical and fiber optic com-
munication lines are being removed and replaced. In terms of bridge work, new approach slabs are being installed. Key equipment for these operations has crews using excavators, loaders, paving machines, graders, concrete grinders, compacting rollers, Super 10 trucks, and concrete mixers manufactured by Cat, John Deere and other well-known firms. In the Southern California area, Atkinson purchases and rents equipment from BC Rentals. The work, which is being done nightly from Mondays to Saturdays (8 p.m. to 6 a.m.), is being enhanced by a series of 55hour closures between Friday at 10 p.m. and Monday at 6 a.m., which has crews from working round-the clock to maximize their efforts. see PAVING page 10
SR 60 is a major thoroughfare serving commuters between Los Angeles, San Bernardino and Riverside counties. As a result of heavy use, it is being rehabilitated in both directions.
Construction Equipment Guide • California State Supplement • www.constructionequipmentguide.com • July 4, 2021 • Page 9
4191 Power Inn Road, Suite D Sacramento, CA 95826
PIRTEK Power Inn 916-737-7777
1997 Burroughs Ave San Leandro, CA 94577
PIRTEK San Leandro 510-568-5000
San Francisco, CA
PIRTEK SFO 650-532-9200
Page 10 • July 4, 2021 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide
Guy F. Atkinson Uses Strategic Staging to Get Job Done
Excavation and demolition activities are expected to generate 160,000 cu. yds. of concrete, 760,000 lbs. of steel and 24,000 tons of asphalt.
The weekend closures are being This project is to restore the roadway and improve the ride quality by rehabilitating the lanes with pavement that will extend the life of the roadway a minimum of 40 years, implemented to minimize overall existing only requiring minimal maintenance by Caltrans once completed. Necessary traffic impacts. Improvements “Although not a full freeway A 2009 Pavement Condition Survey closure, motorists should expect delays and Inventory indicated that the existing SR 60 are strongly advised to use alternate pavement is distressed and needs major routes,” stated the project web page. rehabilitation. ”Residents and local businesses located “The cracked slabs, corner breaks and near the freeway may experience noise, continued deterioration of the pavement has vibrations and dust associated with conseverely impacted the ride quality of the struction activities.” existing roadway,” stated the project web “At times, California Highway Patrol page. [CHP] units were not available due to the The project is designed to enhance safety, pandemic or occupied with protesting sites,” improve ride quality, increase pavement said Minovi. “Caltrans Construction reached service life and reduce maintenance expen- out to other CHP offices outside of our ditures. area with positive response and they provid“Upgrading Metal Beam Guard Railing ed our detailed requests. Some of the chalto Midwest Guardrail System and imple- lenges of night work are people driving menting reflective markers for visibility [is under influence, speeding and traffic inci- A crucial part of the project requires upgrading Metal Beam Guard Railing to an important aspect of the work],” said dents, which causes delays and safety issues. Midwest Guardrail System and implementing reflective markers for visibility. Minovi. “Upgrading overhead sign panels to During the extended weekend closures, Kretroreflective signs and removing the cat- rail concrete barrier is used to separate the being resolved quickly.” site is crucial,” said Minovi. “Traffic control walks will increase visibility and deter graf- construction crew from traffic. The conThe safety of construction personnel is is placed on nightly basis, with CHP units fiti. And new Thermo traffic stripes to tractor is very experienced working on paramount. present at the job site and performing speed replace the faded existing pavement mark- Caltrans projects, which resonate to issues “Lowering the speed limit within the job reducing rounds every hour. There is at ings will enhance safety.” least a 6-foot buffer between A Caltrans design team workers and live traffic.” designed the infrastructure Atkinson and Caltrans projupgrade for the stretch of SR ect teams have formed a solid 60 (which has five lanes in partnership. each direction) that was built “The main objective of the in the mid- to late 1960s and project team is teamwork and carries a large amount comcollaboration, flexibility and muter and commercial traffic managing uncertainty and daily. thoroughness,” said Minovi, “Replacing pavement while “by ensuring the construction providing the same existing completion on time and within number of lanes to public at budget, in compliance with the same time [was a chalproject plans and specificalenge],” said Minovi. tions and by serving the best “Standard construction equipthe interests of the public. The ment and material was used, crews are extremely experibut strategic staging to enced, which makes for a increase productivity was A 2009 Pavement Condition Survey Inventory indicated that the existing SR-60 pavement is distressed and quick paving operation.” needs major rehabilitation. key.” CEG PAVING from page 8
Construction Equipment Guide • California State Supplement • www.constructionequipmentguide.com • July 4, 2021 • Page 11
Hawthorne Cat Opens New Oceanside, Chula Vista Shops
Hawthorne Cat, the Cat equipment dealer in San Diego, the Hawaiian Islands and the Pacific Region, has announced the opening of its new store in Oceanside, Calif. Additionally, its Chula Vista store has moved to a larger, more convenient location,. Throughout 2021, Hawthrone Cat also will be expanding its services so customers can also have maintenance work done on their equipment at the San Diego branch stores. Hawthorne’s technical support and service team takes great pride in delivering the best customer experience in the industry. “Experience the Hawthorne difference for all of your equipment, parts and service needs,” said Ross Farmer, corporate machinery sales and rentals manager. “We
are excited to be opening these two new branches to better serve San Diego County” Visit the new Hawthorne Cat Oceanside branch at 2401 Industry St., Oceanside, Calif., 92054. Hours of operation are 6:30 a.m. to 5:00 p.m., Monday through Friday. The branch can be reached at (760) 5294700. The Chula Vista location has moved to 1751 4th Ave., Chula Vista, Calif., 91911 Hours of operation are 6:30 a.m. to 5:00 p.m., Monday through Friday. The branch can be reached at (619) 336-2500. Hawthorne Cat currently has five stores in San Diego County, with a total of 13 locations throughout San Diego, Hawaii and the Pacific Region. Customers can rent, buy equipment or purchase parts at all of its branches.
2017 NEW HOLLAND U80C…$68,200 W003197, 1,020 Hrs
2016 NEW HOLLAND C238…$38,500 W002639, 1,800 Hrs
2016 NEW HOLLAND C238…$42,900 W002391, 1,115 Hrs
2019 NEW HOLLAND B95C…$61,000 W002878, 900 Hrs
Two locations in California to Serve You! 14635 Valley Blvd. Fontana, CA 92335
909.822.2200
10918 Shoemaker Ave. Santa Fe Springs, CA 90670
www.scottequip.com
C A L L U S T O D AY !
562.777.0775
Page 12 • July 4, 2021 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide
Central California Power JCB
SoCal JCB
19487 Broken Ct, Shafter, CA 93263 (661) 589-2870 www.ccp-jcb.com
14675 Valley Blvd., Fontana, Ca. 92335 866-522-7225 www.socaljcb.com
N&S Tractor 1960 Highway 20 Colusa, CA 95932 (530) 458-2166 2173 Blossom Street Dos Palos, CA 93620-2313 (209) 392-2161
600 S. State Highway 59 Merced, CA 95341-6928 (209) 383-5888
20280 Main St. Stratford, CA 93266 (559) 947-3301
1340 W. Charter Way 1215 West Glenwood Ave Stockton, CA 95206 Turlock, CA 95380-5703 (209) 944-5500 (209) 634-1777 www.nstractor.com
827 North Tehama St Willows, CA 95988 (530) 934-3382 3056 Colusa Highway Yuba City, CA 95993 (530) 923-7675