Skip to main content

Alabama 1 January 4, 2017

Page 1

ALABAMA STATE EDITION

231

65

72 Florence

2

Huntsville

20 Decatur

72

565 59

43

A Supplement to:

231

431

31

5

Gadsden

78 59 Anniston

20

Birmingham Bessemer

82 Tuscaloosa

65 280

20 82 Auburn

®

80

85

Selma

Phenix City

Montgomery

82 65

January 4 2017

231

43 84 431 331

84

84 52

Vol. XXX • No. 1

31

45

“The Nation’s Best Read Construction Newspaper… Founded in 1957.”

Dothan

65 98

Mobile

10

Your Alabama Connection • Rich Olivier, Atlanta, GA • 1-800-409-1479

Ala. Sees Terrorist Explosive Device Analytical Center By Cindy Riley

Construction efforts continue at the Redstone Arsenal in Huntsville, Ala., on Phase III of the Terrorist Explosive Device Analytical Center (TEDAC). TEDAC was established in 2003 to serve as the single interagency organization to receive, fully analyze and exploit all terrorist improvised explosive devices of interest to the United States. The Center performs IED exploitation using both established and novel forensic techniques and performs these activities in a high-capacity, multi-agency, collaborative environment using experienced scientists, engineers, and technicians. “This project is so interesting because of all the security requirements, and knowing that we are assisting with fighting the war on terror,” said Crystal Lucas, P.E., project manager of general contractor Turner Construction, an international construction services company that maintains an office in Huntsville. “The biggest challenge was meeting the aggressive schedule on a design-build project with client-driven changes based on real-time needs.” Composed of 30 partner agencies, including the FBI, the Department of Defense and the Department of Homeland Security, TEDAC was formerly based at the FBI laboratory in Quantico, Va. The relocation to Alabama centralizes the government’s efforts regarding IEDs and terrorism. Redstone Arsenal is home to the FBI’s Hazardous Devices School, the ATF’s National Center for Explosives Training and Research and other operations. In February 2016, James Comey, FBI Director, joined Alabama U.S. Sen. Richard Shelby and Lt. General Larry Wyche in a ribbon cutting that officially opened the new TEDAC facilities. Greg Carl, TEDAC director also was in attendance, along with other officials. The latest construction taking place is a significant addition, according to Chris Colster, a public affairs officer of the U.S. Army Garrison, Redstone. “We welcome the increasing FBI presence on Redstone Arsenal, and appreciate the value that they add to our team, community and our nation’s defense,” said Colster. “As we transition as ‘America’s Garrison of the Future,’ the synergy that exists here will be more and more critical, and the expansion of the FBI TEDAC brings new and needed capability to our team.” The current multi-million dollar project taking shape is managed by the U.S. Army Corps of Engineers (USACE). Turner Construction has worked on numerous USACE projects in the Huntsville area and on Redstone Arsenal’s campus. The TEDAC job was awarded in April 2015, with Phase

CEG CORRESPONDENT

III construction expected to be completed by mid-March 2017. Work began on site in August 2015, with design work starting in May 2015. “The repository is substantially complete, and everything is going fine,” said Lucas. “The repository is in final finishes and final cleaning stage. The collaboration center and visitors screening facility are in the MEP rough-in stage.”

Lucas said attention to detail is crucial during construction, adding that the work is different from more traditional projects her firm has been responsible for completing. “The security requirements and access to the site make this project unique, along with all the STC-rated walls.” Wade Wooley, P.E., area engineer, North Regional Area see TEDAC page 6

Turner Construction photo

Construction efforts continue at the Redstone Arsenal in Huntsville, Ala., on Phase III of the Terrorist Explosive Device Analytical Center (TEDAC).


Page 2 • January 4, 2017 • www.constructionequipmentguide.com • Alabama State Supplement • Construction Equipment Guide


Construction Equipment Guide • Alabama State Supplement • www.constructionequipmentguide.com • January 4, 2017 • Page 3

THE NEW

P ro Pro os sK Know now w! !

7/˿ 9 Compact TTrack Loader

®

Sales - Ren ntal - Parts - Service S Since 1938 Huntsville

Birming gham Mobile

Oxford

Pensacola

Phone: 800-239-2694

Monttgomery

Atlanta

www.cowin.com


Page 4 • January 4, 2017 • www.constructionequipmentguide.com • Alabama State Supplement • Construction Equipment Guide

Construction Equipment Guide • Alabama State Supplement • www.constructionequipmentguide.com • January 4, 2017 • Page 5

S IP 4 PA SK AYMEN M TS

0 F

I

8

S

ZERO DO OWN N

Working hard and saving big ha as never been easie er. Thompson Tractor Co. is built to help lp your business succeed s every d day – b by y ensuring i you’ve ’ got g t the th right i ht machine ne with ith the th protection t tion you need d for your ur nextt job. j b

T®

I

S.

FOR MORE M INFORMA ATION TION CONTTACT ACT YOUR NEAREST THOMPSON HOMPSON TRACTOR LOCA ATION TION FOR DET ET TAILS. AILS.

For a limited time, receive 0% fin nancing for 48 mon nths with zero down and skip up to four payments when you finance a new w Cat machine by January 31, 2017*.

ALABAMA

1-800-RENT T--CAT AT www thompsontractor com www.thompsontractor.com

SKID STEER LOADERS

COM MP PACT TRACK L LOADERS

MULLTI TI TERRAIN LOADERS

MINI EXCA AV VATORS

BACK KHOE LOADERS DERS

SMALL DOZERS

CO OMP PACT WHEEL LOADERS

SMALL WHEE EL LOADERS

TELEHANDLERS

EXCA CA AVATORS

*Offer valid from October 1, 2016 to January 31, 2017 on select new models of machines manufacturred by Caterpillar Inc. Building Construction uction Products Division. Offer available ble only at participating Cat dealers. Offer is available to customers in the t USA only and cannot be combined d with any other offers. Customer skip p payments, financing and published rate are subject to credit approval through ough Cat Financial. Offer subject to machine availability. Final machine prices are subject to change. The Equ uipment Protection Plan (EPP) applies to select models and is provided thro ough Cat Financial for use at participating ting Cat dealers. Offer may change without ithout prior notice and additional terms and conditions may apply. © 2016 Caterpillar. All Righ hts Reserved. CA AT T, CA ATERPILLAR, TERPILLAR, BUI BUIL LT FOR IT LT T,, their respective logos, “Caterpillar terpillar Y Yellow ellow,” the “Power Edge” trade rade dress, as well as corporate and product identity used herein, are trademarks marks of Caterpillar and may not be e used without permission.

FL

AUBURN (334) 321-2030

DOTHAN (334) 673-3300

MOBILE (251) 452-1180

BIRMINGHAM (205) 326-0334

HUNTSVILLE (256) 532-3001

MONTGOMERY (334) 262-1101

OXFORD/ANNISTON TON SHELBY COUNTY (256) 835-57377 (205) 664-9489 PENSACOLA (850) 471-67100

TUSCALOOSA (205) 247-3402


Page 6 • January 4, 2017 • www.constructionequipmentguide.com • Alabama State Supplement • Construction Equipment Guide

Turner Construction Works to Complete TEDAC in Ala.

Turner Construction photo

The TEDAC job was awarded in April 2015, with Phase III construction expected to be completed by mid-March 2017. TEDAC from page 1

Office, U.S. Army Corps of Engineers, said every effort is being made to meet an aggressive construction schedule. Wooley noted that working on three separate facilities requires a great deal of focus and the ability to multi-task. “For the repository, crews are currently working on shelving installation in the warehouse, along with finishing work ongoing in file storage, administration and the café. Collaboration work includes MEP rough-in and interior wall erection and finishing. Crews also are awaiting permanent power in order to energize equipment for the visitors screening facility. “Site prep, structure, exterior walls and roofing are complete on all three buildings,” said Wooley. “MEP rough-in for the repository is complete, as is HVAC operational, lighting and final painting in the warehouse area. Café equipment also has been installed. For the collaboration building, mechanical equipment set on roof and curtain wall installation are nearing completion, while the MEP rough-in and interior walls are erected and partially finished on the visitors screening facility. Building the 28,500-sq. ft. (2,647 sq m) collaboration center requires close coordination of subcontractors, due to topography. The back side of the building has several feet of backfill, making waterproofing critical prior to backfill work. In addition, early completion of the roof was needed so that installation of roof-mounted equipment could begin as soon as possible. Wooley said the 700 sq. ft. (65 sq m) visitors screening facility is small and involves relatively simple construction; however, the concern is that it would be easy to underestimate the time required to construct it, and therefore, fail to properly schedule resources needed to complete the structure on schedule. According to Wooley, the aggressive schedule for the 28,000 sq. ft. (2,601 sq m) repository required collaborative review and early approval of the design, in order to meet the delivery schedule. As with the collaboration facility, the back

Turner Construction photo

Wade Wooley, P.E., area engineer, North Regional Area Office, U.S. Army Corps of Engineers, said every effort is being made to meet an aggressive construction schedule.

side of the building required attention to detail in applying waterproofing in preparation for backfill. Key tasks yet to be carried out on the project include the shelving in the repository warehouse, testing and commissioning of HVAC, testing electrical systems, air barrier, café equipment and completing of the exterior metal panels. The collaboration structure still needs interior finishes, installation of furniture, ceiling work, as well HVAC and air barrier testing. Many of the same tasks are required for the visitors screening facility. Wooley said the elements have had very little impact, so far. “Initial site work was being performed in winter 2015/20 16, so a few days were lost due to weather, but nothing significant. There’s no reason to expect weather to be a concern going forward.” While preparing the wooded site for new construction, environmental clearances were required to avoid small areas of archaeological significance. Sub-surface stabilization also was needed under a portion of the site. Regarding the necessary clearing and grading on the project, “The Army sells all marketable timber, so coordination was necessary to have the Army remove timber in a timely manner, to avoid impact to the start of construction. Coordination went well. Some unsuitable soil was discovered, but nothing out of the ordinary, said Wooley. “There’s nothing unusual about the structures, methods of construction, or materials used; however, site security is a bit more stringent than on many construction sites. A vetting process is used to clear all construction personnel prior to access to the site. The contractor has to be diligent in planning work to assure adequate time is allowed for the clearance process.” Heavy machinery being used to complete the TEDAC structures includes dozers, trackhoes, dump trucks and vibratory sheeps-foot compactors for the site work. Mobile and steel-track cranes were used for steel erection. Some of the main materials being used during Phase III construction

include concrete slab-on-grade, precast and/or masonry with metal wall panels, standard drywall finishes in most areas and a curtain-wall system. “As with most projects, finish work, such as trim, paint, door/hardware adjustments, take much more time than rough-in. Also, final connection and testing of communications network will require careful attention to detail to assure the system is operating properly,” said Wooley. The project will bring greater exposure to TEDAC’s ongoing efforts. Before its creation, no single government entity was responsible for analyzing and exploiting intelligence gleaned from improvised explosive devices. Since then, TEDAC has examined more than 105,000 IEDs from around the globe, providing intelligence to the military, law enforcement and the intelligence community at home and abroad. TEDAC includes representatives from the Department of Justice, international partner agencies and members of the intelligence community. It coordinates efforts from law enforcement to intelligence to military, to gather and share intelligence about these devices, along with helping to disarm and disrupt IEDs and linking them to their makers and preventing future attacks. For more than a decade, TEDAC has proven to be a crucial tool in the war on terror. The FBI and its partners at Redstone Arsenal — alongside the FBI’s Hazardous Devices School and the ATF’s National Center for Explosives Training and Research — join to advance TEDAC’s mission by enhancing collaboration and further strengthening a government-wide approach to countering IEDs and other explosives threats. As work continues on the latest stage of TEDAC construction, those involved with the project are pleased with the work that’s taken place so far. The final phase of the new facilities is expected to be completed sometime in 2020. (This story also can be found on Construction Equipment Guide’s website at www.constructionequipmentguide.com.) CEG


Construction Equipment Guide • Alabama State Supplement • www.constructionequipmentguide.com • January 4, 2017 • Page 7


Page 8 • January 4, 2017 • www.constructionequipmentguide.com • Alabama State Supplement • Construction Equipment Guide


Turn static files into dynamic content formats.

Create a flipbook