City Rail Link (CRL) – Waitematā Station (Britomart) Community Liaison Group Meeting MINUTES Rā: Wā: Wāhi:
5 September 2024 5:00pm – 6:00pm Old Chinese Restaurant, corner of Scene and Britomart
Attendees: Project representative Alex Vaineritua (AV) Lily Boyask (LB) Catherine Edmeades (CE) Sally Logan (SL)
Title CRL Stakeholder and Communications Senior Advisor CRL Stakeholder and Communications Advisor Stellar Stakeholder Manager JFC
CLG attendees Richard Noel Adam Jenifer
ITEM
UPDATE/ACTIONS
1
Welcome – Alex Vaineritua
• AV welcomed attendees, introduced the meeting agenda, housekeeping. • CRL project progress update - Signalling commissioned - 2026 opening date - KHP final sky element to be installed soon Question: Are all the sky elements different on each station? AV: Yes Question: How much testing and training needs to be completed after the November practical completion date? AV: We will do some of that testing and commissioning, then we (CRL Ltd) hand over to AT and KR to do their part of testing in preparation for operations. Question: I am trying to understand how long after handover it will be until opening. AV: We are all in discussion about this (AT, KR, CRL Ltd) at the moment to better understand how long this will take.
Page | 1
CRLL – CLG