CRL Update WaitematÄ Local Board
2
CRL scope
3
CRL enabling works contracts C1
DSC
C2
4
ECI – Early Contractor Involvement Phase
Scope
ECI 1
Detailed design – integrating contractor knowledge
ECI 2
Commercial negotiation
ECI 3
Construction
5
CRL contract start dates
Contract
Start date
Scope
C2
September 2015
Pipe-jack
C1
January 2016
Full scope
DSC
March 2016
TBC
C2 (+)
May 2016
Customs & Albert
6
C1 contract works
7
C2 contract works
Britomart to Downtown Shopping Centre – C1 •
Pedestrian access maintained.
•
Front/west end of Britomart station closed, use rear/east entrance
•
Lower Queen Street closed to vehicles.
•
Temporary bridging and decking for pedestrians and cyclists on lower Queen Street.
•
Underground walkway removed between Britomart and DSC.
•
Buses removed from Tyler, Galway and Lower Queen Streets. Where possible bus stops will be moved to new permanent locations.
•
No left turn for traffic from Quay into Albert Street.
•
Temporary construction accommodation at the rear/east entrance of Britomart.
8
Albert Street from Customs to Wyndham Street – C2 Downtown Shopping Centre (DSC) •
DSC developed as a laneway retail development and 36-level tower, constructing the CRL below. Work due to begin mid-2016 with completion by 2019
CRL Early Works •
Pedestrian access maintained.
•
Buses removed from Albert St. Where possible bus stops will be moved to new permanent locations.
•
Some impact for up to 16 months due to stormwater line relocation
•
Constructing cut and cover tunnels up Albert Street to the southern side of Wyndham St
•
Custom St left open.
9
10
Impacts of construction contracts Contract Victoria St
C2
Lower Albert St
C2
Custom St West
C1
Tyler St & Galway St
C1
Lower Queen St
C1
Albert St (Victoria St to Custom St)
C2
Custom St East
Construction start date
C2
1/09/2015
1/01/2016
1/05/2016