Uptown Business Association March 2017

Page 1

Uptown Business Association Update| 9 March 2017


Contracts


Nikau St stormwater diversion

Mt Eden Road shaft Water Street shaft Nikau Street shaft New pipe

Old pipe

Clash


Shaft Locations

Three gross pollutant traps being installed upstream in Normanby and Boston Roads.


The CLG • AT is required by the CRL designation conditions to establish CLGs in the areas of surface works for: • • • • •

regular updates on construction progress feedback on the development of various work plans input into a regular forum monitoring the effects on the community reporting concerns and issues to AT proposing potential initiatives on the interim use of properties acquired by the CRL

• The Mt Eden CLG was established in November 2015 • For the Nikau St work it met fortnightly from September to November 2016


Management Plan / Detailed Works Plans • Construction Environmental Management Plan • Erosion and Sediment Control Plan • Contamination DWP • Air Quality DWP • Transport, Access and Parking DWP • Construction Noise and Vibration Management Plan • Historic Character DWP • Communication and Consultation Plan • Trees and Vegetation DWP


Utilities Investigation April/May • Boston Rd, Normanby, Mt Eden Roads • Ruru, Nikau, Flower Sts • Flyers to neighbourhood and work with immediately affected adjacent parties Sept/Nov • Watercare installing new valve in watermain so that when it is shut down or CRL, no threat to supply. Xmas • During block of lines, may relocate utilities under rail corridor benefits overall programme and less disruption at busier times Jan-March 2018 • Vector’s installing power supply for tunnels from Kingsland up New North Rd to Ruru St


Consents and Property •

Submissions on Aotea to NAL alteration including Porters Ave closed

•

Nikau Street stormwater diversion Outline Plan of Works approved and resource consents pending

•

Global utilities consent being prepared

•

All surface property purchased

•

Subterranean negotiations started – 91 in total


Mixed Use Development Vision


Pretty pics of mt eden and porters etc


Communication •

Mt Eden Community Liaison Group in place

•

0800 number in place – CRL TALK 275 8255

•

Fortnightly stakeholder e-newsletters

•

Hoarding development with adjacent businesses

•

Stakeholder engagement on traffic, works, etc


New mt eden station Plus words re closure New north rd and mt eden rd buses double deckers? Zopne fares


CRL Ltd - establishment •

Chairman Sir Brian Roche

•

He will lead CRLL establishment with CRL project director

•

Director appointments underway

•

Section 4A Public Finance Act company (mechanical) establishment on track for March approval by Crown

•

Constitution being developed

•

Transition from April to 30 June

•

CRLL fully operational from 1 July 2017