C5 or North Auckland/Western Line Contract Contract spans 4.6km of the North Auckland/Western Line across the Maungawhau (previously Mt Eden) station site between Dominion Road in the west and Khyber Pass Road to the east • Contract connects the North Auckland/Western Line and City Rail Link tunnels

• New track built for maximum speeds of 60kph

• Demolition work began in 2019, construction in 2020, and all work to be completed in October 2023

• 4 new bridges constructed and one temporary bridge for pedestrians built and later removed

• Twin tracks reduced temporarily to one and single line running through the station area continued for 3 years with minimal disruption or delay to services

• Design of new bridges reflects the Maungawhau area’s cultural and historic past

• 3 unsafe level crossings removed

• Removed basalt reborn as pavers on streets surrounding site

• Contract involved more than 1.5 million work hours

• Utility diversions included moving the big Huia 2 water main supplying central Auckland away from work site

• More than 150,000m3 of spoil removed • 25,000m3 of concrete used and counting

• Completed works will help improve travel times for rail commuters when the world class City Rail Link opens in 2025

• 1.3km long section of track replaced and realigned • Rebuilt section includes 71 sections of track each 70 metres long, 4375 sleepers, 50 masts supporting 3.75km of overhead electric line

• The C5 contract is the first contract to be completed by Link Alliance.

Waitematā Station (Britomart)

Maungawhau Station

(Britomart)

Queen Street

Te Waihorotiu Station

Under Construction Contract 3 - Alliance  Stations and tunnels  Western Line connection --- Rail Systems

Te Waihorotiu Station

Karanga-a-Hape Station

Under Construction

Contract 3 - Alliance  Stations and tunnels  Western Line connection Complete --- Rail Systems  Contract 1  DSC  Contract 8 notShopping shown • Waitematā Station Downtown • Centre Newmarket CityRailLink.co.nz (Britomart) • Strand (complete) • Lower Queen St • Ōtāhuhu (complete)

CRLL0507 NAL fact sheet KK v1

Waitematā Station

Queen Street


Turn static files into dynamic content formats.

Create a flipbook
North Auckland Line work Fact Sheet by City Rail Link Ltd - Issuu