Mt Eden CLG Presentation - 7 July 2021

Page 1

Mt Eden Community Liaison Group meeting 7 July 2021


Agenda • Introduction • Communications & Engagement Team update

• Basque Park overview • Mt Eden Station update

• Tunnel Boring Machine update • North Auckland Line update

• Development Response update • Q&A

2


Communications & Engagement Team update • Urban realm feedback received and Urban Design Delivery Works Plan (DWP) to be presented back to CLG in late August • Meetings with residential apartment blocks around the Mt Eden site ongoing • New look notifications and a better process coming soon

• Quarterly stakeholder survey results

Happy Matariki from the Link Alliance Mt Eden team!

“Ko ngā mihi o Matariki” which translates to “Matariki (Māori New Year) Greetings”. 3


Tiaan John Project Engineer – Mt Eden Utilities

4


Basque Park works overview As part of the City Rail Link upgrade at Mt Eden station a wastewater pipe needs to be diverted to Basque Park:

•

One quarter of the park’s total area will be fenced off for construction

• On site for a maximum of 12 months (starting October at the earliest) • Park will be restored to its original state post-construction

• Working hours Mon-Sat 7am-7pm (but will likely be shorter)

5


Why Basque Park? • The gravity wastewater solution is the asset owner Watercare’s preference. Pump systems and siphon options will only be accepted by Watercare when there is no gravity system available. • Alternatives have been considered, but this is the best solution due to: – Reduced ongoing maintenance and operation

– Separation of storm and wastewater pipes – Upgrading of ageing infrastructure

6


Basque Park works overview Noise and vibration • Understandably noise will be a concern for local residents. Our extensive surveys to date show the levels are ‘acceptable’ under Auckland Council’s guidelines (less than 70dB). • These can be variable so we will monitor on-site during construction to make sure we address any exceedances.

7


Basque Park works overview Trees • To avoid damage, 5 young trees will be relocated and replanted/replaced at the end of construction. Access and traffic •

Short road closures (hours not days)

•

Committed to working with residents to minimise.

Parking • Up to 10 parking spaces will be temporarily lost. Combination of 120 min and unrestricted.

8


Basque Park works overview Community As well as being committed to minimising disruption, while the Link Alliance is in the park, we’d like to celebrate the space with you, the local community.

9


Basque Park works overview Our timeline

10


Thibaut L'Hopital Mt Eden Station Project Manager

11


Mt Eden works update Key progress updates: • Nikau Street utilities works

• Cut and cover tunnels • Station building & vent building • North Auckland Line platform

12


Mt Eden works update

13


Mt Eden works update

14


Mt Eden works update

15


Mt Eden works update

16


17


Andy Strong TBM Project Engineer

18


19


Tunnel Boring Machine works update Ongoing/Completed Works:

• Installation of 52No. Permanent Rings (9 x 1.1m) (53 x 1.6m) Total 86.2m Excavated

• Permanent conveyor install • Spoil storage shelter

• First Cutterhead intervention Upcoming Works:

• Restart tunnelling

• 24/7 shift work starts 12/07/21 • First HV cable extension • First conveyor belt extension

20


Tunnel Boring Machine works update

Conveyor Install

Spoil Basin Conveyor

21


Mined Tunnel works update Completed Work in progress

Ongoing/Completed Works: • MC50 Box excavation • MC50 Tunnel 60m excavated • 24/5 shift work ongoing Upcoming Works: • Excavation of MC50/20 Cavern

`

51%

22


MTE Mined Tunnel works update

Plug of Storm Water Pipe

MC50 Box Excavation 23


MTE Mined Tunnel works update

Mucking Out During Excavation

924 and 8T Working Side by Side

Lattice Girder Installation 24


Nick Adams Deputy Construction Manager North Auckland Line

25


North Auckland Line (NAL) update Key progress updates:

•

Mt Eden Road bridge completed;

•

Normanby Road level crossing closed to traffic;

•

Porters Ave bridge foundations;

•

Piling for Normanby Road bridge foundations;

•

Boston Road roundabout relocated;

•

Stormwater works within Normanby Road.

26


North Auckland Line (NAL) update

27


Piet Ubels Development Response Manager

28


Development Response update Key progress updates: •

Business support activity

•

Pop up coffee cart

•

Upcoming events

•

Hoarding art

•

Artwork on silos

29


30


31


32


33


Questions & Answers

34


For more information • City Rail Link website - www.cityraillink.co.nz • 0800 CRL TALK – choose option 5 for Mt Eden Station • Email the Mt Eden Station team at mteden@linkalliance.co.nz