C6: Mt Eden stormwater realignment works CLG meeting – 31st of January, 2018


CRL C6 project


•

•

•

•

•

Bought by Vinci SA at the end of 2017

Infrastructure but concentrate on in ground

Christchurch based but NZ focused

March Family

Founded 1971

March Construction C6 PROJECT

•

Vinci SA is a French organisation which is one of the largest construction companies in the world


•

•

•

•

>30 TBMs from 0.5mØ – 5.5mØ

140km of tunnels in last 10 years

MTBM manufacturer as well as installer

Over 40 years in business

France based (Saint-Jory, near Toulouse)

Bessac

•


•

•

•

All tunnelling works completed from Water Street

Tunnelling method involves the use of an AVN 2000 AB MTBM

Less time taken for construction of the tunnel

Single drive from Water St to Nikau St

The Tunnel

•


The Shafts Water St (the Drive Shaft) 16m deep secant pile construction • 8.5m internal diameter • 0.75m piles bored with a Soilmec SR40 drill rig (50 tonne) • 50-80 tonne crawler crane Mt Eden Rd 18m deep access chamber • 2.5m internal diameter • Casing installed by Liebherr LRB155 (70 tonne) drill rig • 50-80 tonne crawler crane Nikau St (the receiving shaft) 15m deep shaft • 9.4m internal diameter stepped down to 5.6mØ • Pre cast concrete caissons • 50-80 tonne crawler crane • 30-35 ton excavator with rock breaker


•

•

Works will then be continuous from this period through until January 2019 at Water St and Nikau St. Mt Eden Rd will be to some extent dependent on tunnelling progress.

First site works – Mid February at Water St with hoardings going up followed by Mt Eden Rd and Nikau St

Timing/Programme

•

GPTs: GPT1 (Boston Rd-late February) GPT2 (Boston Rd-Mid March) GPT3 (Normanby Rd-Early April) Completion will be early May with each GPT taking about four weeks.

• • • •


•

•

Noise: • Rock breaking at Nikau St • Generators at Water St • General construction activity

Hours of Work: • 7.00am to 7.00pm • 24 hours for MTBM

Impacts

•

Traffic: • Site establishment of plant • Truck movements


•

•

•

•

Martin Hughes on 027 3846576

Contacts: Graeme Inglis on 027 4557299 or the 0800 CRLTALK (2758255)

The MBJV will at all times keep communication open

March and Bessac have good reputations when it comes to working with communities

The work sites are quite contained with activities restricted to within the boundaries apart from truck movements.