Western Line integration
Information on CRL’s Mt Eden rail corridor works February 2020
Managing the impacts of our construction activity Just as we did during the planning phase for our early works, we are now preparing a suite of management plans for Auckland Council approval that set out how we will manage the effects of our main construction works on people and the environment. They include specific measures to address environmental effects such as noise, vibration, traffic, air quality,
contamination, silt and sediment, groundwater and settlement.
we prepare are as effective and responsive as possible.
We are also preparing a Social Impact and Business Disruption management plan, and in doing so are seeking input from people living and working within the vicinity of our construction areas. We need to understand how people could be affected so that the management plans
We incorporate this feedback into the management plans and submit them to Council for approval. Once approved, the construction teams will work in a manner that ensures the measures outlined in these plans are in place to minimise the effects on the environment and impacts to nearby businesses and residents.
LA0006_09.03.20
Where to go for more information We’ll be adding more information about upcoming works in both the Mt Eden Station and Western Line construction sites to the Mt Eden section of City Rail Link’s website at CityRailLink.co.nz
The Link Alliance’s Mt Eden project team is also hosting regular community information sessions at its site office at 97 Mt Eden Road. Dates and times are promoted in our monthly Mt Eden newsletter and on CRL’s website and Facebook page.
If you have any questions or concerns about project works in the Mt Eden area, please contact the Mt Eden Station team: 0800 CRL TALK (choose option 5 for Mt Eden works)
mteden@linkalliance.co.nz
The Link Alliance will design, construct and deliver CRL’s twin rail tunnels, two new underground stations and a new Mt Eden station building. The Link Alliance includes seven companies with a wealth of experience in delivering large-scale infrastructure projects in New Zealand and overseas. The companies in the Link Alliance are: Vinci Construction Grands Projet S.A.S, Soletanche Bachy International NZ, Downer New Zealand Ltd, Tonkin & Taylor, AECOM New Zealand Ltd, WSP, City Rail Link Ltd.
LA0006 Western line C5 works brochure.indd 1-2
View towards Mt Eden Station redevelopment from Ruru St Extension
As part of the City Rail Link (CRL) project, the existing Mt Eden train station will be enlarged and redeveloped to incorporate a modern new station building and an additional platform for the new CRL line. The station will also remain a stop for Western Line services, making it a busy rail junction for passengers travelling to and from the city centre or connecting to other services via Newmarket.
When the CRL opens in 2024, it will provide access to two new city centre stations – Karangahape (under Karangahape Road) and Aotea (under Albert Street) – between Mt Eden and Britomart stations. Britomart will operate as a two-way through station, enabling Auckland’s rail network to double in capacity to carry up to 54,000 passengers an hour at peak times. The CRL will also provide travel time savings for many rail users. From Mt Eden, a train to Karangahape will take just three minutes, while Aotea and Britomart will be a six and nine-minute journey respectively.
Prior to 2024, significant changes need to be made in and around the rail corridor at Mt Eden to integrate the new CRL lines with the existing rail infrastructure and construct new overbridges for vehicles and/or pedestrians and cyclists. This brochure outlines the key rail and road network changes that will be made in Mt Eden for the CRL project, when construction is scheduled to occur and what sort of impacts you might expect from these works. More information is available on CRL’s website at www.cityraillink.co.nz
9/03/20 11:29 AM
Concept design for overbridge from Ngahura St to Fenton St
Looking ahead to the main works Key activities happening in and around the rail corridor over the next few years include closing the Normanby Rd level crossing and constructing a new road bridge over the rail line; building new pedestrian and cycle bridges over the Western Line from Porters Ave to Wynyard St, Fenton St to Ngahura St and the new station building to the Western Line platform; and constructing trenches, bridges, retaining walls and tunnels for the new CRL rail lines, both within the rail corridor and on CRLowned land we’ve cleared for construction
purposes. There will also be widespread changes to rail infrastructure, including signals, overhead electrical lines, tracks and an extended Western Line platform that caters for nine-car trains. The information below divides the Mt Eden rail corridor works (extending from the Dominion Rd flyover to the SH1 flyover by Mt Eden Prison) into three geographic areas. Activities will overlap as different work starts and finishes. Dates are indicative but will be confirmed as planning is finalised.
Eastern-Facing Connection (east of Mt Eden Rd towards Normanby Rd)
Early works along the rail corridor at Mt Eden In the first half of 2020, we’ll start early works in a number of locations along the Mt Eden rail corridor to prepare for the main CRL construction works. These include: • Diverting utility services away from the rail line along Fenton St and Normanby Rd.
• On 30 May, the Mt Eden Station will close for about four years while the new station building and CRL tunnels and tracks are constructed. Trains will run on one line (referred to as ‘single line running’) through Mt Eden to keep freight and passenger services operating on the network while our team works on the other side of the
corridor, but trains will not stop at the station. Visit www.cityraillink.co.nz/mteden-train-station-closure-crl for more on the station closure. The Normanby Rd level crossing will temporarily close over Easter weekend while bridge foundation and utility works are undertaken in that area. Pedestrians will still be able to cross on the eastern side.
• Removal of parking on Fenton St and the rail-side of Haultain St to accommodate construction • Some noise, vibration and dust from construction activities • Some traffic disruption when temporary lane or road closures are required Our normal hours of work are: Monday to Friday 7am-7pm, and Saturday 7am-2pm. If we need to do work outside these hours, we will notify this in advance.
INDICATIVE DATES
Commencement of single line running on the southern-most track and removal of rail assets from the northern side of the corridor
From Q3 2020
What we’ll do to minimise the impact of these works:
Construction of retaining walls required for rail trenches. This will include piling, rock breaking and installing capping beams
Q3 2020 – Q4 2022
• Providing plenty of advance warning of our works to allow people to plan for any disruption
Construction of temporary utility services bridge over Normanby Rd level crossing
Q3 2020 – Q4 2020
Construction of split-level cross-over structure, which will enable trains to connect to the new CRL line
Q4 2020 – Q4 2021
Bulk earthworks for rail trenches
Q1 2021 – Q4 2022
Construction of Normanby Rd road-over-rail bridge. Normanby Rd will close for approximately six months to accommodate this work
Q3 2021 – Q2 2022
Realignment of Boston Rd / Normanby Rd / Nugent St roundabout to accommodate new Normanby Rd bridge
Q2 2021 – Q2 2022
Mt Eden Rd to the Fenton / Ngahura St end of station platform INDICATIVE DATES
Closure of Mt Eden Station
30 May 2020
Construction of additional Mt Eden Rd bridge for CRL line
Q3 2020 – Q3 2021
Removal of station access ramp from Mt Eden Rd
Q3 2020
• Building the foundations for a temporary utility services bridge across the rail line on Normanby Rd.
Demolition of existing Western Line platform and staged construction of an extended and re-aligned platform
Q1 2021 – Q4 2022
• Undertaking ground strengthening works in the corridor between Mt Eden Rd and Normanby Rd before rail trench construction begins.
Construction of the new Mt Eden Station building
Q1 2021 – late 2022
• Erect construction hoardings to secure work sites and help minimise noise and dust for neighbouring properties • Introduce measures to control soil movement, including washing the wheels of trucks before they leave site • Use water to suppress dust • Install monitoring equipment to measure air quality, ground water levels and ground and building movement • Erect thick mats and enclosures around plant and equipment to minimise construction-related noise • Maintain access to public and private property • Manage contractor parking to minimise the use of on-street parking spaces wherever possible • Attended noise and vibration monitoring when work is anticipated to be particularly disruptive. This ensures we comply with the levels specified in our consent condition • Directing trucks to use main arterial routes as much as possible
Western-Facing Connection (from Fenton St towards Porters Ave)
Two significant closures will also occur in the station area during this period to enable utility diversion and construction work to be carried out: • On 10 April (Easter weekend), the Porters Ave level crossing will permanently close to vehicles. Pedestrians and cyclists will still be able to cross the tracks in this area until the new Porters Ave pedestrian/ cycle overbridge opens in 2021. View of Porters Ave pedestrian bridge from Wynyard St
LA0006 Western line C5 works brochure.indd 4
• Truck and machinery movements
ACTIVITIES
ACTIVITIES
• Diverting utilities on Mt Eden Road to enable us to construct an additional Mt Eden Rd bridge for the CRL line to pass underneath.
What to expect from the main works
ACTIVITIES
INDICATIVE DATES
Closure of Porters Ave level crossing to vehicles
10 April 2020
Track removal and construction of rail trench (incl. bulk earthworks, blasting and piling for retaining walls) and rail cross-over structures
Staged from Q3 2020 – Q1 2023
Construction of Porters Ave overbridge
Q3 2020 – Q3 2021
Staged re-instatements of Fenton St after utility relocation works and footbridge construction
Q4 2020 – Q3 2022
Construction of Fenton St to Ngahura St overbridge
Q1 2021 – Q3 2022
A mechanical water mister suppressing dust