Skip to main content

Council Infrastructure Committee Feb 2016

Page 1

CRL – Enabling works Infrastructure Committee update I March 2016

1


Enabling works construction areas

2


Pipe jacking A micro TBM will drill a small tunnel under Albert Street installing the pipe as it goes. This is done by powerful hydraulic jacks pushing specially designed pipes through the ground behind a cutting head that excavates the ground at the same time.

The process 1.

Clear utilities at pipe jack shafts

2.

Set up the launch shaft at Albert/Victoria Streets, and reception shafts at Swanson St and Wellesley St

3.

MTBM pushes from launch shaft to reception shaft

4.

Remove MBTM from reception shaft and reinstate

3


Britomart to Downtown Shopping Centre •

Pedestrian access maintained.

•

Front/west entrance of Britomart station closes January 2017, with entrance and temporary accommodation at the rear/east end.

•

Buses removed from Tyler, Galway and Lower Queen Streets to new locations on 17 April 2016.

•

Lower Queen Street closed to traffic with a street activation programme from May 2016 to May 2017.

•

Underground walkway removed between Britomart and DSC by 29 May 2016.

4


5

Albert Street from Customs to Wyndham Street Downtown Shopping Centre (DSC) •

Precinct Properties develop their DSC site and construct the CRL tunnels below. Work due to begin May 2016 with completion by 2019

CRL Enabling works •

Pedestrian and cyclist access maintained

•

Buses relocated from Albert St

•

Orakei main sewer strengthening and jacking of new stormwater line along Albert St from Swanson to Wellesley St

•

Shafts at the intersections of Albert St and Swanson, Victoria West and Wellesley Sts from Feb 2016 – May 2017

•

Pedestrians only on Swanson St, reduced to two traffic lanes on Victoria St West and Wellesley Sts

•

Constructing tunnels up Albert St to the southern side of Wyndham St: May 2016 - late 2018 – traffic reduced to one lane each way.


6

Draft start dates 2015 Nov

Dec

2016 Jan

Feb

Mar

Apr

Contract 1

Queen Street

May

Jun

Jul

2017 Aug

Sep

Oct

CPO (Civil Works) Demolition starts

Downtown DSC

Contract 2

Dec

Jan

Feb

Apr

- Tyler and Galway Street (access change, buses removed and reversing Tyler) - Lower Queen Street buses removed - Interim bus plan operational

Britomart Temp Accom

Pipe jack

Nov

Victoria St (east/west constraint)

Albert St cut and cover

Lower Albert St (partially closed to through traffic) Albert St (Victoria to Custom) service lanes only)

Custom St/Albert St intersection

May


7

Traffic challenge

Congestion conditions. Expected congestion – additional bus priority lanes as mitigation.

PT Objectives: - Retain levels of service. - Allow for customer growth. - Target mode shift to PT.

Buses need to move out of lower CBD for CRL –51% of trips affected.

Stage 1 complete

Stage 2 in design for 17/4/16


Build is On campaign Late February – May 2016 Advertising in newspapers and radio, bus backs, Google videos and a travel planning website KEY MESSAGES • Fewer on-street car parks, and slower traffic flows • Make a travel plan • Car pool, catch the bus, train or ferry, walk or cycle.

• Consider changing your work hours, or work from home some days.

8


Mode shift during construction ďƒ˜ During early work construction it is important that current and forecast demands on the road network can be supported, so that the city keeps moving ďƒ˜ To achieve this, a mode shift towards bus, trains, ferries and active transport (walking and cycling) is needed.

9


Bus Priority Measures To address the changes to bus routes and the need to encourage a mode shift a range of bus priority measures were proposed : •

24/7 Bus priority lanes (improved amenity – reliability, punctuality for customers)

•

Bus route diversions

•

Future planning – the majority of the bus lanes will remain in place after the CRL early works are completed

10


Bus stop and route changes

11

 Virtually every bus route has to change primarily because of the closure of Albert St and Britomart to buses.

 Needed to ensure that bus passengers could still easily access downtown and connect to the train station and ferry services.  Over a year of analysis and modelling by AT, Aurecon and Flow to assess how to shift the buses within the city centre  Numerous options were explored.


Phase 1 – bus priority measures

12


Phase 2 – bus priority measures

13


Consents

14

Consent lodged

Hearing

Appeal

Hearing Result

NoR 2012

2013

2014

2015

Pipejack 2014

2015

None

Approved

Enabling works regional consents 2014

2015

None

Approved

Britomart NoR 2015

November 2015

?

?

?

NoR Alterations 2015/16

?

?

?

?

Main works regional consents 2016

?

?

?

?

NoR confirmed


Property • • • • • •

Vast majority of the 68 surface properties needed have been acquired Most in main construction site adjacent to Mt Eden Station About $90m spent on property Sub surface negotiations start next year CRL portfolio has about 40,000 sqm of property - most commercial Less than 5% vacancy

15


16

CRL Programme

16


Transport - Conclusions • There is an established way of approach transport appraisal based on straight line growth forecasts and values of time with fixed population and employment patterns, but it is not clear that it reflects what actually happens

• In reality transport drives land use patterns just as much as land use drives transport demand

17


Turn static files into dynamic content formats.

Create a flipbook
Council Infrastructure Committee Feb 2016 by City Rail Link Ltd - Issuu