Duty Commissioner Recommendation Decision Mt Eden demolition

Page 1

Recommendation on an outline plan of works under s176A of the Resource Management Act 1991 Application number(s):

OPW60335715

Requiring authority's name:

City Rail Link Limited

Site address:

Project area bounded by NAL (south), Ngahura Street (west), Mt Eden Road (east) and Nikau Street (north).

Legal description:

Allotment 205-206 Section 10 Suburbs of Auckland, Lot 1 DP 53063, Lot 1 DP 57203, Lot 1 DP 43875, Lot 1 DP 57108, Lot 1 DP 183867, Lot 2 DP 183867, Lot 2 DP 40971, Lot 1 DP 40971, Lot 1 DP 99657, Lot 1 DP 150226, Lot 1 DP 102341, Lot 1 Section 6 Deeds Plan 45 Blue, Lot 1 DP 95398, Part Lot 17 Section 6 Deeds Plan 45 (blue), Lot DP 81116, Lot 2 DP 99657, Lot 21 Section 6 Deeds Plan 45 Blue, Lot 22 Section 6 Deeds Plan 45 Blue, Lot 2 DP 150226, Lot 1 DP 78367, Lot 1 DP 171412, Part Lot 15 Section 2 Deeds Plan 45(blue), Lot 1 DP 123665, Part Lot 1 DP 55364 and Part Lot 2 DP 55364

Proposed work / project: The demolition of buildings in the project area including foundations, and the removal and disposal of all demolished material and disturbed ground to enable underground works to occur for the proposed underground station at Mt Eden and provide a platform for the release of the tunnelling bore machine.

Recommendation I have read the outline plan of works (OPW), supporting documents, and the report and recommendations on the OPW. I am satisfied that I have sufficient information to consider the matters required by the Resource Management Act 1991 (RMA) and make a recommendation under delegated authority. Acting under delegated authority, under section 176A, the Auckland Council recommends requesting the following changes to the outline plan of works. The outline plan of works does show: • The proposed works / project are within the scope of the designation (and associated conditions); and • The outline plan of works has sufficient detail to describe the proposed works and measures to manage adverse effects under s176A(3). The following changes are recommended to be requested to better manage adverse effects from the proposed works:


1.

The C3 Alliance Contractor investigates and if practicable takes steps necessary to relocate the pohutukawa trees T12 and T13 identified in Trees and Vegetation Delivery Work Plan.

2.

The Construction Noise and Vibration Delivery Work Plan is amended via a nonmaterial change process to reflect the agreement between the technical experts that noise levels are predicated as received at 1m from the façade.

3.

The C3 Alliance Contractor should provide to Auckland Council the final version of the MediaWorks Site Specific Construction Noise and Vibration Management Plan as a material change using the designation processes set out in Condition 23.6 of the City Rail Link Limited Designation.

4.

The Contamination Delivery Work Plan is amended via a non-material change process to require soils being disposed off-site to be sampled at a minimum rate of 1 in 250m3.

Advice notes 1.

This recommendation on the outline plan of works recognises the scope of works enabled under the CRLL Designation. This covers only any activity that would otherwise infringe a rule in a District Plan under the RMA. The requiring authority is responsible for identifying and obtaining all other necessary consents and permits. These may include: •

• • •

Any relevant resource consents both under any relevant national environmental standard (e.g. NES for assessing and managing contaminants in soil to protect human health), and any relevant regional rules under the operative and proposed regional plan(s) and regional coastal plan(s) the Building Act 2004 any relevant Auckland Council bylaws Heritage New Zealand Pouhere Taonga Act 2014.

Recommendation approved by

Barry Kaye

Duty Commissioner

7 May 2019


Schedule 1 1.

The proposed works / project has been confirmed as falling within the scope of the designation and satisfying s176A RMA on the basis of the recommended changes to manage demolition effects and being undertaken in accordance with the plans and all information submitted with the outline plan of works, as detailed below, and all referenced by the Council as OPW60335715. •

Outline Plan of Works and assessment prepared by Aurecon, dated 7 March 2019

Report title and reference

Author

Rev

Dated

CRL-MTE-RME-000-RPT-0118 Mt Eden Demolition Works Outline Plan

Aurecon

02

7 March 2019

CRL-MTE-RME-000-RPT-0119 Construction Environmental Management Plan

Aurecon

02

22 February 2019

CRL-MTE-RME-000-RPT-0139 Erosion and Sediment Control Plan

Aurecon

01

15 January 2019

CRL-MTE-RME-000-RPT-0121 Transport Access and Parking Delivery Work Plan

Aurecon

04

5 February 2019

CRL-MTE-RME-000-RPT-0122 Construction Noise and Vibration Delivery Work Plan

Marshall Day Acoustics

R04

24 January 2019

CRL-MTE-RME-000-RPT-0124 Historic Character Delivery Work Plan Archaeology Section

Clough and Associates Ltd

05

22 February 2019

CRL-MTE-RME-000-RPT-0125 Contamination Delivery Work Plan

Golder Associates (NZ) Ltd

Rev0

4 March 2019

CRL-MTE-RME-000-RPT-0126 Air Quality Delivery Work Plan

Golder Associates (NZ) Ltd

Rev0

4 March 2019

CRL-MTE-RME-000-RPT-0128 Trees and Vegetation Delivery Work Plan

Amenity Tree Consultants Ltd

02

26 February 2019

CRL-MTE-RME-000-RPT-0120 Social Impact and Business Disruption Delivery Work Plan

Aurecon

03

8 March 2019

CRL-MTE-RME-000-RPT-0128 Communication and Consultation Plan

Aurecon

01

11 February 2019

•

Communication and technical memos provided during application processing

Email correspondence and reference

Author

Dated

Email request for technical comments

Warwick Pascoe

13 March 2019

Email with technical memo AQDWP

Paul Crimmins

19 March 2019

Email with technical memo Social Impacts and Business Disruption DWP

Dr Jennifer Joynt

22 March 2019

Email with technical memo CEMP and ESCP

Tim O'Grady

22 March 2019

Email with technical memo TAP DWP

Hamish Speakman

22 March 2019

Email with technical memo HC DWP

Myfanwy Eaves

25 March 2019

Email with technical memo CDWP

Marija Jukic

25 March 2019


Email with technical memo CNV DWP

Daniel Winter

25 March 2019

Email with matters of clarification to CRL

Warwick Pascoe

27 March 2019

Email with technical memo TV DWP

Howell Davies

28 March 2019

Email with response from CRL re TV DWP

Simon Lough

29 March 2019

Email with response from CRL re TAP DWP, CNV DWP, SSCNVMP, and CDWP

Aidan KirkbyMcLeod

12 April 2019

Email conclusion re TAP DWP

Hamish Speakman

16 April 2019

Email conclusion re CDWP

Marija Jukic

18 April 2019

Email conclusion re CNV DWP

Daniel Winter

23 April 2019