CRL Presentation to FP Committee Nov 24 2017

Page 1

City Rail Link Ltd (CRLL) Establishment Process • Board established 1 July 2017 with chair & four directors

• Comprehensive director induction process including technical workshops • Former AT staff now CRLL employees

• New look and feel, including website • New IT systems, processes and policies in place


Bird’s eye view – Contract 1 Bentonite storage tanks at Britomart


Project Update – Britomart Contract 1 • About halfway through the 15-20 metre deep diaphragm wall construction to form the twin tunnels • Early 2018, underpin the CPO with steel beams across the walls and transfer weight of CPO onto structure • Walls become part of the permanent structure • Eventual streetscape at 50% design stage

• Contract progressing to programme with no significant inground obstruction encountered


Contract 1 – ‘Sandrine’ the diaphragm wall cutter or ‘hydrofraise’ at work within the former CPO building


Proposed – Aotea Station entrance


Project Update – Commercial Bay (DSC) • The two tunnels are taking shape as they cross the site from east to west • They will eventually connect to sections of tunnel under Lower Queen Street from the Britomart works and at Customs Street from the Albert Street works • Good progress to meet adjacent CRL contract timeframes


CRL tunnels being constructed through ‘Commercial Bay’


CRL tunnel entrance under construction through ‘Commercial Bay’


Project Update – Albert Street Contract 2 • Excavation depth halfway- nine of the 18m- between Wyndham and Swanson Streets • Traffic decks in place from Wyndham to Wolfe Streets • Customs/Albert Street intersection complete and traffic back to two lanes each way • Excavation was challenging during wet weather and in sticky clay layers. Contractor making good progress in firm soils.


Customs Street & Albert Street intersection


Excavation - CRL tunnel trench being constructed along Albert Street. 300 cubic metres of spoil being removed daily.


Project Update – Procurement Contract 6 Mt Eden stormwater works - successfully tendered within agreed budget including transfer of ground condition risks

Contract 7 Comprehensive review of the procurement strategy undertaken. Consultation with market to follow Contract 3 RFT release mid 2018

Contracts 5 & 8 Procurement strategies under development


Contract 1 – diaphragm wall cutter blades


Proposed - Mt Eden Station entrance


Project Delivery Agreement •

Project Delivery Agreement (PDA) between CRL and sponsors on what and how we deliver is in line with cost and programme

•

The PDA documents the open & cooperative relationship between CRLL and its sponsors

•

The PDA sets out: - The terms on which CRLL is to deliver the Project - Key delivery objectives - Basis of Sponsor funding - Processes for review, approvals and assurance

•

Includes a Target Delivery Cost* of $3.37bn (P50); and

•

Target Delivery Date* of March 2024

•

The PDA reserves certain decision making rights of the Council and Crown, including to approve the suppliers for all main works contracts (C3,C5, C6. C7 , C8 & C9) and the release of RfPs for contracts C3 and C7

*The PDA notes that the targets will be confirmed once contracts are let


Bird’s eye view – CRL tunnels under construction through Commercial Bay


Look Ahead • January - advance Aotea canopy removal and utility relocation on west side of Albert Street between Victoria & Wellesley Streets

• 2018 - start of the tunnel box at the southern end of Albert Street • Albert Street hoardings off footpath and street look & movements improved • Mid 2018 - work starts to pile and excavate across Lower Queen Street • Future proofing for longer trains


CRL tunnel trench under construction between Albert & Wyndham Streets


Where to find out more: CityRailLink.co.nz and follow us on Facebook, Instagram, YouTube and LinkedIn