CRL Connection

March 2016

Concept interior of the redeveloped Britomart Station showing ticketing and retail

Downer and Soletanche Bachy Joint Venture

Japanese

もし、 このファクトシートを理解する必要があれば、 下 記のメール経由で我々にご連絡ください。

Russian

The City Rail Link includes turning Britomart Station from a terminus to a through station. Those who will be doing this in a sensitive heritage building are the Soletanche Bachy and Downer Joint Venture. They bring broad experience to the extremely complex engineering requirements of the project. Sited in the former Chief Post Office (CPO), the station is internationally recognised for its innovative but also heritage-sympathetic architecture. The same attention to heritage will be vital to the next stage of its life. Soletanche Bachy, a multinational company renowned for foundation projects in sensitive heritage sites, has worked on underground metros in most of the world’s major cities. It has restored historical monuments such as the Arc de Triomphe and Grand Palais in Paris and the Bolshoi Theatre in Moscow. It also redeveloped St Pancras Railway Station in London, known as “the cathedral of railways,” as a Eurostar Terminus for the Channel Tunnel Rail Link (CTRL).

Если Вам необходима помощь в разъяснении содержимого в данном бюллетене, просим адресовать Ваши вопросы на нижеуказанную электронную почту.

Simplified Chinese 如果您对这简报有任何疑问请以下的邮箱联系我们

Korean

본 자료표에 관한 더 많은 정보를 원하시면 하단의 이메일 주소로 연락 주시기 바랍니다.

Arabic ‫ةرشنلا اذه مهف يف ةدعاسم ىلإ ةجاحب تنك اذإ‬، ‫ىجري‬ ‫هاندأ ينورتكلإلا ديربلا ناونع ربع انب لاصتالا‬.

visit our Facebook page www.facebook.com/cityraillink Funding partner:

website AT.govt.nz/CRL email CRLproject@AT.govt.nz

CRL Newsletter | Page 1


Return to front page

Downer and Soletanche Bachy Joint Venture (continued)

Interior of St Pancras Station, with Eurostar train awaiting departure (2010)

Downer converted the Chief Post Office into Britomart Station in two stages to create a two-level basement concourse (2003) Downer, a leading provider of infrastructure and communication services, has been part of the New Zealand community for over a century. Downer designs, builds, maintains and operates key infrastructure around the country including the Homer Tunnel providing access to Milford Sound, Pukeahu National War Memorial Park and Arras Tunnel in Wellington as well as maintaining significant roading, telecommunications and water assets around the country. In Auckland, Downer built the Chief Post Office, Britomart Station,

Electrical Multiple Unit (EMU) Rail Depot and has recently completed upgrades to the waterfront at Devonport and Westhaven. The joint venture will start constructing temporary accommodation for Britomart Station’s ticketing and customer service operations in July. This will be followed by underpinning the CPO building to allow the construction of the rail tunnels beneath, reinstating Britomart Station and upgrading the surrounding urban space and roads.

website AT.govt.nz/CRL

CRL Newsletter | Page 2


Return to front page

CRL story goes up on Victoria Street West After months of preparation work for the pipe jack shafts, the hoarding enclosing the first shaft on Victoria Street West (Mai Thai corner) will be completed in early April. Our first large-scale opportunity to tell the CRL story, the colourful hoardings will show the latest designs for the new stations and the role the CRL will play in creating an integrated public transport system for the entire city. The next pipe jack hoardings will be on Victoria Street West (Surf and Snow corner) followed by those on Wellesley Street West.

RAINS, MORE OFTEN

A better connected Auckland

RE T

What it means for Aucklanders

Twice as many trains through Britomart

MO

City Rail Link

Faster, more frequent journeys

Exciting modern architecture, more shared spaces and a people-friendly city

Hoarding artwork going up on Victoria Street in early April

What we are doing about traffic flows The CRL is just one of a number of CBD construction projects whose complexity requires an extra focus on traffic flows. Auckland Transport Operations Centre (ATOC) has established a 7am to 7pm control team to maintain optimum traffic flows. AT will also provide extra buses daily, if needed, wherever possible. To keep the city moving while the CRL is constructed, AT has also: • Created 53,179 more bus, rail and ferry weekday average seats • Installed 24/7 bus lanes on Victoria West, Albert, Wellesley West Streets and Mayoral Drive, with more to come on Queen, Customs and Hobson Streets • Launched the Build is ON campaign encouraging CBD peak hour commuters to shift from vehicles to public transport, carpooling, walking or cycling.

email CRLproject@AT.govt.nz

CRL Newsletter | Page 3

Aucklan project


Return to front page

Early works construction Orakei Main Sewer strengthening Victoria Street West (Mai Thai corner) Construction hoardings up for approx. 10 months April 2016

•

Hoardings erected

May 2016

•

Excavation of shaft

July 2016

• TBM enters shaft and travels below Albert Street to Victoria Street West (Surf and Snow corner) to strengthen sewer

May – December 2016

•

Shaft filled

January 2017

•

Road re-opened to traffic

Stormwater pipe construction schedule (approx.) Victoria Street West (Surf and Snow corner) Construction hoardings up for approx. 14 months June 2016

•

Hoardings, gantry and 6m high acoustic shed and 20m piling drill erected

July 2016

•

Excavate shaft

September – November 2016

•

TBM enters shaft and travels below Albert Street to Swanson Street

November 2016 – January 2017

•

TBM re-enters shaft and travels below Albert Street to Wellesley Street

December 2016 – May 2017

•

Shaft filled

•

Hoardings removed

•

Road returned to original layout for traffic

May 2017

Swanson Street (New Zealand Trade Centre corner) Construction hoardings up for approx. 10 months June 2016

•

Swanson Street closes to traffic, footpaths remain open, hoardings erected, excavate shaft

January 2017

•

TBM removed from shaft

February 2017

•

Shaft filled

•

Hoardings removed

•

Swanson Street reopens to traffic

March 2017

website AT.govt.nz/CRL

CRL Newsletter | Page 4


Return to front page

Early works construction (continued) Wellesley Street West (Central City Hotel corner) Construction hoardings up for approx. 11 months •

Hoardings erected

•

Excavate shaft

February 2017

•

TBM removed from shaft

March 2017

•

Shaft filled

•

Hoardings removed

•

Road re-opens to traffic

May 2016

April 2017

ON!

The build is

Lower Queen, Tyler, Galway and Commerce Streets 17 April 2016

Mid April 2016

•

Buses removed from Lower Queen Street, Tyler and Galway Streets

•

Traffic reversed to go in Tyler Street and out Galway Street

•

Buses go back in Commerce Street and a mid-block pedestrian crossing installed

•

New raised speed bump to slow traffic at the intersection of Galway and Commerce Streets

•

Pedestrian crossings installed on Tyler and Galway Streets

Auckland’s latest activation space Lower Queen Street becomes the city’s newest activation space next month after buses are relocated on 17th April. It will be transformed into a flexible, multi-use space for large to small events while providing pedestrian movement through the area. Auckland is a city in transition, with the CRL vital to that change so expect to see activities that celebrate its transformation. Image showing an activation in Lower Queen Street Please sign me up to the CRL Early Works Newsletter email list.

email CRLproject@AT.govt.nz

CRL Newsletter | Page 5


Turn static files into dynamic content formats.

Create a flipbook
CRL Connection Newsletter March 2016 by City Rail Link Ltd - Issuu