Page 1

Recommendation on an outline plan of works under s176A of the Resource Management Act 1991 Application number:

OPW60310921

Requiring authority:

City Rail Link Limited (“CRLL”)

Designation:

Designation ID 1714 City Rail Link

Site address:

Albert Street, central Auckland

Legal description: Proposed works / project: To undertake temporary removal and/or cut back of building canopies and relocation of underground utilities along the western side of Albert Street from Wellesley Street to Victoria Street West.

RECOMMENDATION Having read the outline plan of works (“OPW”), supporting documents, and the report and recommendations prepared on behalf of the Council, I am satisfied I have sufficient information to consider the matters required by the Resource Management Act 1991 (“RMA”) and to make a recommendation to CRLL as the requiring authority. Pursuant to section 176A of the RMA the Auckland Council requests no changes to the outline plan of works, as detailed in the documentation in schedule 1 below, as: • • •

The proposed works / project are within the scope of the designation (and associated conditions); The outline plan of works has sufficient detail to describe the proposed works and any proposed measures to manage adverse effects under section 176A(3); and The proposed works include appropriate measures to manage any adverse effects.

Advice note The recommendation on this outline plan of works recognises the scope of works enabled by the relevant designation. This covers only any activity that would otherwise infringe a rule in the district plan under the RMA. The requiring authority is responsible for identifying and obtaining all other necessary consents and permits. These may include: •

• • •

any relevant resource consents both under any relevant national environmental standard (e.g. NES for Assessing and Managing Contaminants in Soil to Protect Human Health) and any relevant regional rules under the operative and proposed regional plan(s) and regional coastal plan(s) the Building Act 2004 any relevant Auckland Council bylaws the Heritage New Zealand Pouhere Taonga Act 2014.

OPW60310921 Page 1


Recommendation approved by

Leigh McGregor Duty Commissioner 6 December 2017

OPW60310921 Page 2


Schedule 1 1.

The proposed works / project have been confirmed as falling within the scope of the designation and satisfying section 176A on the basis of being undertaken in accordance with the plans and all information submitted with the outline plan of works, detailed below, and all referenced by the Council as consent number OPW60310921. • •

Outline Plan of Works and assessment prepared by Aurecon, dated 17 October 2017 Reports as follows:

Report title and reference

Author

Rev

Dated

CRL-PAT-RME-000-RPT-0102 OUTLINE PLAN Albert Street Canopy and Utility Relocation Works, including all appendices

Aurecon

3

17 October 2017

CRL-PAT-RME-000-RPT-0097 Transport Access and Parking Delivery Work Plan, including all appendices

Flow

1

November 2017

Rp001 r05 20170511 Construction Noise and Vibration Delivery Work Plan

Marshall Day Acoustics

6

23 November 2017

CRL-PAT-RME-000-RPT-0095 Historic Character Delivery Work Plan Archaeology

Clough & Associates

4

16 October 2017

CRL-PAT-RME-000-RPT-0098 Contamination Delivery Work Plan

Golder

1

November 2017

CRL-PAT-RME-000-RPT-0099 Air Quality Delivery Work Plan

Golder

0

October 2017

CRL-PAT-RME-000-RPT-0103 SOCIAL IMPACT AND BUSINESS DISRUPTION DELIVERY WORK PLAN Albert Street Canopy Removal and Utilities Relocation

Aurecon

4

24 November 2017

Communication and Consultation Plan

Fritha Witton

4

17 October 2017

Plan title and reference

Author

Rev

Dated

C2.1: Canopy Removal Albert St, CBD (L2LS Long Term Contraflow), PXJ-0778, Sheet 1 of 3

Connectus

1

July 2017

C2.1: Canopy Removal Albert St, CBD (L2LS Long Term Contraflow), PXJ-0778, Sheet 2 of 3

Connectus

1

July 2017

C2.1: Canopy Removal Albert St, CBD (L2LS Long Term Contraflow), PXJ-0778, Sheet 3 of 3

Connectus

1

July 2017

•

Plans:

OPW60310921 Schedule 1

Page 1


•

Other information:

Other

Author

Email – CRL Albert St Canopy and Utility CCP and SIBD comment

Blair Masefield

29 November 2017

Email – CRL – Albert St Canopy Removal and Utilities Relocation OPW – CNV DWP

Jon Styles

17 November 2017

Email – CRL CEMP review

Laura Scaife

16 November 2017

Email – CRL – Albert St OPW – Designation and RC conditions

Myfanwy Eaves

13 November 2017

171110 Albert St Utility Relocation DWP Peer Review HGT2

Hamish Speakman

10 November 2017

Email - CRL – Albert St Canopy Removal and Utilities Relocation OPW – CDWP

Marija Jukic

10 November 2017

Email – CRL Albert St Canopy Removal and Utilities Relocation OPW – AQ DWP

Paul Crimmins

8 November 2017

OPW60310921 Schedule 1

Rev

Dated

Page 2