CRC Update| 9 March 2017
Construction •
CPO interior being dismantled
•
Albert St pipejack halfway, now on second bore to Wellesley St
•
Half the piles completed for the Albert St tunnels
•
Utility investigations started in advance of the main works in the Aotea Station area
•
Bulk excavation has started at the Precinct site
Property and Consents •
All surface property purchased
•
Subterranean negotiations started – 91 in total
•
Regional consents in Environment Court – 2 appeals
•
Nikau Street stormwater diversion consent lodged
•
Alterations to designation in progress
•
Global utilities consent being prepared
Procurement • • • •
C7 linewide systems EOI released in January and RFT likely in April C3 pre qualification documents released February, EOI planned for April, RFT October C6 RFT planned for March C5 contract model underway
Sustainability •
First annual sustainability review published Nov 2016
•
Social outcomes strategy completed Feb 2017
•
Leading rating awarded for C1 and C2 design and construction planning
•
World first awarded for integrating Mana Whenua values
Design •
Reference designs for all stations completed
•
Reference designs for contracts C3 to C9 being translated into specification clauses for the procurement documentation
•
Agreement reached with Auckland Council design office on scope and quality of urban realm reinstatement of Albert Street
•
Reinstatement presented to Waitemataa Local board and CCAB with positive feedback
Communication • • • •
• • • •
Community Liaison Groups (4) in place and monthly Mana Whenua Forum Fortnightly stakeholder e-newsletters Hoarding development with adjacent businesses Stakeholder engagement on traffic, advance utility works, designation alterations, business claims etc Instagram initiated January 2017 Regular social/media milestone releases Strategy being updated to reflect regional consents and upcoming works Preparation for CRLL internal and external comms
CRL Ltd - establishment •
Chairman Sir Brian Roche (SBR) has met with project management team
•
SBR to lead CRLL establishment with CRL project director
•
Director appointments underway
•
Section 4A Public Finance Act company (mechanical) establishment on track for March approval by Crown
•
Constitution being developed
•
Transition from April to 30 June
•
CRLL fully operational from 1 July 2017
AT/CRLL Transition CRLL Establishment • •
Agreement
Parties
Status
Completion
Sponsors
Crown and Council
Draft
April
Project delivery
Crown, Council and CRLL
Draft
April
Finance - AT to provide SAP processing support
AT asset transfer
CRLL and AT
Draft
April
Metro - operational interface
AT partnering
CRLL and AT
Draft
April
KRG partnering
CRLL and KRG
Draft
June
AT leading Major work streams affected: HR - CRLL to largely manage IT - AT to support CRLL
•
Role of AT Board