Construction works contract 1 Erosion and sediment control plan

Page 1

Auckland City Rail Link In association with:

CONSTRUCTION WORKS CONTRACT 1 EROSION AND SEDIMENT CONTROL PLAN Document ref: CRL-BTM-ENV-DOW-PLN-000287

Revision: 9 August 2018

Erosion and Sediment Control Plan


Version history Rev.

Date

Version details

Prepared by

Reviewed by

1

December 2015

Draft for Auckland Transport Review

Costas Chryssafis

J Urquhart, P Roan

2

January 2016

Draft for CLG Review

Costas Chryssafis

R Jenkins

3

April 2016

Draft incorporating Auckland Council comments

Costas Chryssafis

J Urquhart, R Purdy

4

May 2016

Draft incorporating CLG comments

Costas Chryssafis

J Urquhart, P Roan, R Jenkins

5

May 2016

Draft for Auckland Transport Review

Costas Chryssafis

J Urquhart, P Roan

6

June 2016

Final

Costas Chryssafis

J Urquhart, P Roan, R Jenkins

7

April 2017

Updated Final to capture design changes

Costas Chryssafis

R Purdy

8

October 2017

Annual plan review

Costas Chryssafis

R Purdy

9

August 2018

Annual plan review

Costas Chryssafis

S Sutherland

Distribution Date

Version

Issued to

Quantity & type

Approved for the DSBJV by

21 December 2015

Draft

Auckland Transport for review

1x Electronic

D Burtenshaw

22 January 2016

Draft

Community Liaison Group

1 x Electronic

D Burtenshaw

13 May 2016

Draft

Community Liaison Group

1 x Electronic

D Burtenshaw

20 May 2016

Draft

Auckland Transport for review

1 x Electronic

D Burtenshaw

2 June 2016

Final

Auckland Transport

1x Electronic 1 x Hard copy

D Burtenshaw

April 2017

Final – updated

DSBJV

1x Electronic

S Sutherland

22 November 2017

Draft

CRLL

1x Electronic

D Burtenshaw

21 December 2017

Draft

Auckland Council

1 x Electronic

D Burtenshaw

2 July 2018

Final

CRLL, Auckland Council

1 x Electronic

D Burtenshaw

19 December 2019

Draft

CRLL, Auckland Council

1 x Electronic

D Burtenshaw

This document remains the property of DSBJV. Its contents are confidential and shall not be reproduced, destroyed or given away without express, written permission of DSBJV. The electronic version of this document in FULCRUM on designated serves(s) is the Master Copy and is a controlled document. Unless specifically noted, thereon, other copies of this document are uncontrolled.

Erosion and Sediment Control Plan

August 2018


p:\30850\30850.0500 planning\30850.0512 (erosion and sediment)\issueddocuments\annual review 2017\crl-btm-env-dow-pln-000287 updated escp rev 8.docx

Erosion and Sediment Control Plan

August 2018


Table of contents 1

2

3

4

5 6 7 8 9

Introduction 1.1 Purpose of the Erosion and Sediment Control Plan 1.2 Relevant Conditions 1.3 Sustainability 1.4 ESCP review and updates Project Description 2.1 Overview 2.2 Active Construction Zones (ACZ) 2.3 Construction Support Areas 2.4 Staging of construction works and duration 2.5 Construction aspects 2.5.1 Site establishment 2.5.2 Excavation 2.5.3 Backfill 2.6 Site geology and groundwater 2.7 Catchment boundaries Erosion and Sediment Control Approach 3.1 Key principles and approaches 3.2 General erosion and sediment control measures Specific erosion and sediment control measures 4.1 General 4.2 Perimeter controls 4.3 Vehicle access 4.4 Dewatering of excavation 4.5 Treatment plant 4.6 High risk spillage areas 4.7 Extreme weather events 4.8 Construction stormwater management 4.9 Stockpile management 4.10 Kerbside management 4.11 Specific erosion and sediment control measures 4.12 Certification of sediment control devices 4.13 Modification to structural controls Monitoring and Maintenance Roles and Responsibilities Environmental Training 7.1 Project staff Complaints 8.1 Complaints response ESCP Review 9.1 ESCP Review 9.2 ESCP Updates

Appendix A :

ISCA Requirements

Appendix B :

Chemical Treatment Management Plan

Appendix C :

Staging Plans

Erosion and Sediment Control Plan

1 1 2 6 6 7 7 7 8 11 11 11 11 12 12 13 14 14 15 16 16 16 17 18 18 19 19 19 19 20 20 22 23 24 26 27 27 28 28 29 29 29

August 2018


Appendix D :

Drawings

Appendix E :

CLG comments

Appendix F:

Register of Plan Updates

Erosion and Sediment Control Plan

August 2018


Glossary of terms Term

Definition

ACZ

Active Construction Zone

AC

Auckland Council

ARI

Annual Return Interval

AT

Auckland Transport

BTC

Britomart Transport Centre

CEMP

Construction Environmental Management Plan

CLG

Community Liaison Group

CPO

Former Chief Post Office building

CRL

City Rail Link

CRLL

City Rail Link Limited

CSA

Construction Support Area

CTMP

Chemical Treatment Management Plan

ECBF

East Coast Bays Formation

ESCP

Erosion and Sediment Control Plan

DSBJV

Downer Soletanche Bachy Joint Venture

DWP

Delivery Work Plan

GD005

Auckland Council Erosion & Sediment Control Guide for Land Disturbing Activities in the Auckland Region – Guideline Document 2016/005

IS

Infrastructure Sustainability

ISCA

Infrastructure Sustainability Council of Australia

TSS

Total Suspended Solids

Erosion and Sediment Control Plan

August 2018


1

1

Introduction

The City Rail Link (CRL) project comprises the construction, operation and maintenance of a 3.4 km underground passenger railway, running between Britomart Station and the North Auckland Rail Line in the vicinity of Mt Eden station. The works relating to this Erosion and Sediment Control Plan (ESCP) constitute part of the enabling works for the CRL. The works (the Project) involve the construction of an extension to the existing passenger rail network from the current termination point within the Britomart Transport Centre (BTC), westwards underneath the former Chief Post Office building (CPO) and Lower Queen Street. The Project footprint is shown generally by the blue shaded area in Figure 1.1 below.

LEGEND CRL alignment BTC designation CRL designation C1 worksite

Figure 1.1: Project Footprint

1.1

Purpose of the Erosion and Sediment Control Plan

This ESCP has been prepared to manage all bulk earthworks to minimise any discharge of debris, soil, sediment or sediment-laden water beyond the construction site to either land and/or stormwater drainage systems. The ESCP is required under Condition 45 of the CRL Britomart to Wyndham Street land use consent R/REG/2014/5430 and addresses the requirements of Conditions 46 to 62 of this consent. It also addresses Conditions 99 to 101 of discharge permit R/REG/2014/5436. This ESCP outlines: •

Relevant resource consent conditions;

•

Identification of active construction zones (ACZ) and construction support areas (CSA);

•

Specific erosion and sediment controls to be implemented for each ACZ, along with the transport of spoil;

•

ESCP measures to be implemented to manage any contaminated soils or ground water encountered;

•

Monitoring and maintenance requirements; and

•

Methods for managing complaints and complaint response procedures.

Erosion and Sediment Control Plan

August 2018


2 If required to assist in the settlement and capture of sediment during the construction works, a chemical treatment plant will be established on site. A Chemical Treatment Management Plan (CTMP) is attached as Appendix B of this ESCP to address the relevant resource consent conditions (specifically Conditions 48(f) and 50 -53) relating to the operation and management of the on-site chemical treatment plant. This ESCP has been prepared by Tonkin & Taylor Ltd (T+T) for the Downer Soletanche Bachy Joint Venture (the Contractor – DSBJV) and forms part of the Construction Environmental Management Plan (CEMP) for the Project.

1.2

Relevant Conditions

Table 1.1 outlines the resource consent conditions relevant to this ESCP and where they are addressed in the document. Table 1.1: Condition No.

Relevant resource consent conditions and section where addressed in the ESCP Condition

Relevant section of the ESCP Land Use Consent R/REG/2014/5430

Erosion and Sediment Control Plan (“ESCP”) 45

At least 20 working days prior to the commencement of construction, a finalised ESCP which provides for the management of all bulk earthworks to minimise any discharge of debris, soil, sediment or sediment-laden water beyond the site to either land and/or stormwater drainage systems shall be prepared and submitted to the Council (Team Leader Central Monitoring) for certification.

This document

46

No construction activity shall commence until certification from Council is provided.

1.3 and 9

47

The Consent Holder shall request the Council’s (Team Leader Central Monitoring) determination as to whether the ESCP can be certified, in writing, within 10 working days of receipt of the ESCP.

1.3 and 9

48

The ESCP shall include, but not be limited to, the following matters: a. Identification of construction zones and construction support areas; b. Specific erosion and sediment control works for each Active Construction Zone (location, dimensions, capacity supporting calculations and design drawings), which should be in line with Industry Best Practice that will meet or exceed the performance of measures detailed in Auckland Council Technical Publication No. 90, Erosion & Sediment Control: Guidelines for Land Disturbing Activities in the Auckland Region (TP90); c. Catchment boundaries; d. The timing and duration of construction and operation of control works (in relation to the staging and sequencing of bulk earthworks); e. Details relating to the management of exposed areas; f. Reference to the Chemical Treatment Management Plan and confirmation of ESC measures necessary to give effect to that plan; g. Reference to the Contaminated Soils Management Plan and confirmation of ESC measures necessary to give effect to that plan;

Erosion and Sediment Control Plan

2.2 and 2.3 4 and 4.11

2.7 2.4 2.5 4.5 and Appendix B 3 and 5 5, 6, 7 and 8

August 2018


3 Condition No.

Condition

Relevant section of the ESCP

h. Monitoring and maintenance requirements, including information on complaint investigation and response procedures, training, and roles and responsibilities. 49

Any Change to the ESCP shall be submitted to the Council (Team Leader Central Monitoring) for certification. No activity reliant upon a change to the ESCP can be undertaken until the change has been certified. The Consent Holder shall request the Council’s (Team Leader Central Monitoring) determination as to whether the proposed change can be certified, in writing, within 10 working days of submission of the change.

1.3 and 9

Chemical Treatment Management Plan (“CTMP”) 50

At least 20 working days prior to the commencement of construction, a CTMP which confirms the measures that will be taken to ensure that construction of the Project or Project Stage will be generally consistent with the Water Quality Assessment and the Industrial and Trade Activities Assessment prepared by Golder Associates (NZ) Limited, both dated December 2014 shall be submitted to Council (Team Leader Central Monitoring) for certification.

Appendix B

51

The Consent Holder shall request the Council’s (Team Leader Central Monitoring) determination as to whether the CTMP can be certified, in writing, within 10 working days of receipt of the CTMP.

Appendix B

52

The CTMP shall include, but not be limited to, the following matters: a. Specific design details of the chemical treatment system based on a batch dosing methodology for the site’s settlement tanks, including the potential for use of non-chemical flocculants (e.g. chitin based flocculants such as Haloklear); b. Monitoring, maintenance (including post-storm) and contingency programme (including a record sheet); c. Details of optimum dosage (including assumptions); d. Results of initial chemical treatment trial; e. A spill contingency plan; and f. Details of the person or bodies that will hold responsibility for the long term operation and maintenance of the chemical treatment system and the organisational structure which will support this system.

Appendix B

53

Any change to the CTMP shall be submitted to the Council (Team Leader Central Monitoring) for certification. No activity reliant upon a change to the CTMP can be undertaken until the change has been certified. The Consent Holder shall request that the Council’s (Team Leader Central Monitoring) determination as to whether the proposed change can be certified, in writing, within 10 working days of submission of the change.

Appendix B

As-built Certification 54

Prior to construction (bulk earthworks) commencing, a certificate signed by a senior qualified person shall be submitted to the Council (Team Leader Central Monitoring) to certify that the erosion and sediment controls have been constructed in accordance with the certified ESCP(s) as required by Condition 45 of this consent.

4.12

55

Certified controls shall include diversion bunds, silt fences, and sumps. The certification for these subsequent measures shall be supplied

3 and 4

Erosion and Sediment Control Plan

August 2018


4 Condition No.

Condition

Relevant section of the ESCP

immediately upon completion of construction of those measures. Information supplied, if applicable, shall include: a. Contributing catchment area; b. Shape of structure (dimension of structure); c. Position of inlets/outlets; and d. Stabilisation of the structure General Performance Standards 56

The Consent Holder shall ensure that there shall be no deposition of earth, mud, dirt or debris on any road or footpath resulting from bulk earthworks on the subject site. In the event that such deposition does occur, it shall immediately be removed. In no instance shall roads or footpaths be washed down with water without appropriate erosion and sediment control measures in place to prevent contamination of the stormwater drainage system, watercourses or receiving waters.

3, 4.3, 4.9, 4.10 and 4.11

57

The operational effectiveness and efficiency of all erosion and sediment control measures specifically required as a condition of resource consent, including the certified ESCP referred to in Condition 45, shall be maintained throughout the duration of bulk earthworks, or until the Project site is permanently stabilised against erosion.

3, 4, 5 and 6

58

The site shall be progressively stabilised against erosion at all stages of earthworks activity, and shall be sequenced to minimise the discharge of contaminants to groundwater or surface water.

3

59

The Consent Holder shall ensure that the erosion and sediment control measures shall be constructed and maintained in accordance with Auckland Council’s Technical Publication 90: Erosion and Sediment Control Guidelines for Soil Disturbing Activities in the Auckland Region, and any amendments to this document, except where a higher standard is detailed in the documents referred to in conditions above, in which case the higher standard shall apply.

3

60

Sediment control measures shall be inspected on a weekly basis and after a significant storm event to ensure effective operation. In the event that a discharge of debris, soil, silt, sediment or sediment-laden water occurs, the activity which resulted in the discharge shall cease immediately and the discharge shall be mitigated and/or rectified to the satisfaction of the Council (Team Leader Central Monitoring).

5

61

The Consent Holder shall ensure that all material removed from or delivered to the Project site shall be covered during transportation.

2.5.2

62

Upon completion or abandonment of bulk earthworks on the Project site all areas of bare earth shall be permanently stablished against erosion to the satisfaction of the Council (Team Leader Central Monitoring).

4.11

Washwater and Wastewater Discharges – Discharge Permit R/REG/2014/5436 Structural Controls 99

The Consent Holder shall ensure that the following structural controls are constructed for the following catchment areas and designed requirements and they are completed prior to discharges commencing from the site.

Appendix B 1

Settlement tanks are located in Construction Support Area A (Galway Street) as opposed to Construction Support Area B / Construction Support Area 2 (Lower Queen Street) in order to create a more efficient CSA layout

11

Erosion and Sediment Control Plan

August 2018


5 Condition No.

100

Condition

Relevant section of the ESCP

Works

Device catchment area

Design requirements

Settlement Tanks (2X 12,000l tanks), located in CSAs 2 and 4

All ACZs

Discharge levels as per monitoring Condition 101

Bunding Environmentally Hazardous Substances

As required

110% of largest container

In the event that any minor modifications to the structural controls system are required, the following information shall be provided to Council: a. Plans and drawings outlining the details of the modifications; and b. Supporting information that details how the proposal does not affect the capacity or performance of stormwater management systems. All information shall be submitted to, and the proposed modifications certified by the Council (Team Leader Central Monitoring), prior to implementation.

4.13 and Appendix B

Discharge Monitoring 101

Within 30 days of the installation of the water treatment system, and prior to operation, a discharge monitoring programme, to assess the ongoing adequacy of all management practices, shall be developed and submitted to the Council (Team Leader Central Monitoring) for certification. The monitoring programme shall include, but not be limited to: a. Sampling location for final discharge from the site(s); b. Sampling locations on site (i.e. swale inlets, outlets etc.); c. Methods and procedures for discharge sampling on a quarterly basis; d. Monitoring parameters for analysis, which shall include: Daily • Turbidity (NTU) • pH Weekly • Total Suspended Solids mg/L • Copper (total) mg/L • Zinc (total) mg/L • Lead (total) mg/L • Total Petroleum Hydrocarbons mg/L e. Identified trigger levels for each of the above parameters. These trigger levels shall be developed with reference to the ANZECC Guidelines for water quality where applicable; and f. The methods and procedures for investigating and reporting stormwater discharge monitoring results to the Council (Team Leader Central Monitoring).

Erosion and Sediment Control Plan

5 and Appendix B

August 2018


6

1.3

Sustainability

City Rail Link Limited (CRLL) is seeking an Infrastructure Sustainability Council of Australia (ISCA) Infrastructure Sustainability (IS) Rating. Further details can be found in the Project CEMP and Sustainability Rating Management Plan. Project sustainability requirements that relate directly to this ESCP are included in Appendix A. These requirements are embedded within this ESCP to ensure that sustainability is a key focus and ‘the way we do things’. In some cases the IS requirements and sustainability goals enhance the designation requirements.

1.4

ESCP review and updates

This ESCP is a live document that will be reviewed and updated if needed during the course of the Project to reflect material changes associated with construction techniques or the natural environment. Any material changes to the ESCP must be certified by Auckland Council (AC) prior to any on-site activity reliant upon the change commencing. A formal review process is described in Section 9 of this ESCP.

Erosion and Sediment Control Plan

August 2018


7

2

Project Description

2.1

Overview

The Project involves the construction of an extension to the existing passenger rail network from the current termination point within the BTC, westwards underneath the CPO and Lower Queen Street. Separate works are being undertaken to continue the CRL tunnels from this point under the Downtown Shopping Centre site (which is to be redeveloped by Precinct Properties), and then up Albert Street. Significant works beneath the CPO will be undertaken, with the construction of two new rail tunnels extending westwards beneath the basement floor level. In Lower Queen Street, piling will be extended across the road corridor, excavation undertaken to form the tunnels followed by reinstatement of the road corridor following the completion of works. During construction, existing ticketing and retail functions and pedestrian access to the station will be accommodated in Station Plaza, at the rear of the CPO building. Surface works will also be required in QEII Square associated with the Downtown Shopping Centre redevelopment, including construction of the CRL rail tunnels beneath this site (Precinct Properties scope of work). All of the land within the Project area (at the surface) has been previously disturbed. A detailed description of the construction works is provided in the CEMP.

2.2

Active Construction Zones (ACZ)

The Project will be divided into four discrete ACZ as shown in Figure 2.1.

Figure 2.1: Active Construction Zones

The referencing of Project ACZs adopted in this ESCP reflects that of the BTC designation in order to ensure consistency across all Project Delivery Work Plans and Environmental Management Plans. It

Erosion and Sediment Control Plan

August 2018


8 is noted that under the resource consents, the Project area is separated into two larger ACZs: ACZ A (CPO) and ACZ B (Lower Queen Street) – refer to Figure 2.3. A summary of the works required in the four ACZs is outlined in Table 2.1 Table 2.1:

Summary of key construction activities within each ACZ 2

Active Construction Zone

Key construction activities

A

Britomart Station modifications • Modification of existing platforms and track lines • Installation of temporary access stairs, station entry and egress

B

Accommodation within Station Plaza • Construction of temporary accommodation buildings and facilities and relocation of ticketing, staff facilities, public amenities, retail/kiosk areas from the CPO building • Installation of services.

C

CPO Building Works • Removal of the CPO fixtures and fittings, including the timber floor • Saw cutting and demolition of the concrete ground floor in the main ticket hall and processing concrete for use as backfill later • Installation of guide walls, diaphragm walls and underpinning structures to provide support for the CPO • Soil excavation • Construction of the base slab, walls and roof for the new rail tunnels • Backfill excavation • Reinstatement and fit out of CPO building

D

Lower Queen Street • Bentonite plant located adjacent to the south west corner of the CPO building on Lower Queen Street • Carry out piling and underpinning works • Soil excavation • Construct base slab, walls and roofs for new rail tunnels • Backfill excavation • Reinstatement of Lower Queen Street

2.3

Construction Support Areas

Three construction support areas (CSA) will be established to support the ACZs as outlined in Table 2.2 and shown on Figure 2.2. The three CSAs will support the ACZs and provide for general activities, such as site offices and construction personnel amenities, machinery parking and storage, loading/unloading and temporary storage of construction materials, waste storage and collection. Although unlikely, temporary storage of excavated spoil may be required in unforeseen circumstances (for example, breakdown of construction plant). Any temporary stockpiles shall not exceed 24 m³ per ACZ 3 and shall be appropriately covered as outlined in the Project Air Quality DWP (Appendix L of the CEMP). 2 3

Note these activities are not in order of programme In accordance with Condition 71(e) of discharge permit R/REG/2014/5437

Erosion and Sediment Control Plan

August 2018


9 All yards and construction areas will be fully fenced at the perimeter and made secure for the safety of the general public. Signage will be placed near the entrances of all construction yards that will include Project information, including the Project Hotline number. All storage of material and equipment associated with the construction works will take place within the boundaries of the Project area. Table 2.2:

Construction Support Areas

Construction Support Area

Location

Construction zone supported

Area

Key Plant/Activities

A

Galway Street

Supports temporary accommodation works in Station Plaza

400 m2

• Material storage • Crane location and access to CSA A • Stormwater and groundwater treatment tanks

B

Lower Queen Street

Supports CPO and Lower Queen Street construction

3,500 m2

• Bentonite treatment plant • Jet grout pump and mixing plant • Material storage

C

Tyler Street

Provides construction access to the CPO

400 m2

• Temporary site office during Stage 1 of the Project • Material storage • Crane location and access for CSA C • Main vehicle entrance to the CPO building

Erosion and Sediment Control Plan

August 2018


10

Figure 2.2: Construction Support Areas

Note: Blue hatched areas on Figure 2.2 show the areas of the Lower Queen Street that will be maintained as traffic lanes in order to provide vehicle access from Lower Queen Street to Tyler Street and Galway Street into Lower Queen Street The referencing of Project CSAs adopted in this ESCP reflects that of the BTC designation to ensure consistency across all Project Delivery Work Plans and Environmental Management Plans. It is noted that under the resource consents, the Project area is separated into two CSAs – CSA 1 and CSA 2 – refer to Figure 2.3.

Figure 2.3: Resource Consent ACZ and CSA referencing

Erosion and Sediment Control Plan

August 2018


11

2.4

Staging of construction works and duration

The staging and expected duration of the Project works are summarised in Table 2.3. The construction works programme is anticipated to commence in July 2016 and be completed by August 2020 – a duration of 50 months. Table 2.3:

Staging of construction works

Stage and ACZ

Dates

Approximate Duration

Stage 1 / ACZ B – Temporary station access, construction of temporary accommodation in Station Plaza and streetscape works.

July 2016 to January 2017

7 months

Stage 2 / ACZ C – CPO building works, piling, removal of CPO ground floor

January to May 2017

4 months

Stage 3 / ACZ C and D – piling, CPO underpinning excavation, tunnel construction and backfilling.

May 2017 to May 2020

36 months

Stage 4 / ACZ A, B, C and D – Reinstatement & station fit out.

May to August 2020

4 months

Refer to the staging plans provided at Appendix C for further details on Project staging and the main construction activities in each stage.

2.5

Construction aspects

2.5.1

Site establishment

Site establishment activities will include site clearance, establishment of temporary accommodation buildings within Station Plaza to the rear of the BTC, ground preparation, and the establishment of erosion and sediment control measures prior to any construction activities occurring. Once the construction sites are established, stormwater runoff from impervious areas of the construction sites will be captured and treated according to this ESCP. Section 2.2 of the CEMP provides further details on site establishment and temporary accommodation works.

2.5.2

Excavation

Excavation of both Lower Queen Street and beneath the CPO will be conducted concurrently. The area of the proposed excavations will extend to approximately 14 – 16 m below ground level (bgl). The length of the excavation in Lower Queen Street will be approximately 26-28 m from the edge of the CPO building across Lower Queen Street, with the width approximately 22 – 25 m along the CPO frontage. Approximately 20,000 m3 of material will be excavated from the Lower Queen Street and CPO excavations. Lower Queen Street will be excavated using long-reach excavators at road level excavating between props, which will be lowered into the excavation and installed using a mobile crane. Final trimming and pump station excavation will be undertaken by a small excavator lowered into the trench, feeding a long-reach at road level. Spoil will be loaded directly onto truck and trailers, covered and transported from the site. Excavation beneath the CPO will take place in two phases. Initially, excavation will be conducted from inside the building, with two excavators excavating each rail tunnel. The spoil from the northern and southern tunnel will be loaded out onto six wheeler trucks backed into the CPO through the north-easterm door.. Spoil will be covered before being transported from the site.

Erosion and Sediment Control Plan

August 2018


12 Once the second level of struts have been installed within the CPO, the CPO excavators will be demobilised. Eight tonne excavators and tracked skid-steer loaders will be lowered into the excavation at the interface of the Lower Queen Street excavation and CPO. Working beneath the props, the excavators will progress eastwards beneath the CPO, feeding the tracked skid-steer loaders, which will move the material to long-reach excavators waiting on Lower Queen Street. The expected earthwork volumes and areas for each ACZ are outlined in Table 2.4. Table 2.4:

Earthwork volumes

ACZ

Earthwork volume (cut) m3

Earthwork volume (fill) m3

Earthwork area (exposed) m2

A

N/A

N/A

N/A

B

N/A

N/A

N/A

C

10,000

4,000

1,000

D

10,000

7,000

1,500

2.5.3

Backfill

Approximately 11, 000m³ of material will be required for the Project, primarily to backfill the CPO and Lower Queen Street excavations. Crushed concrete will be used as backfill, where practicable, in order to reduce the quantity of imported fill required. •

In Lower Queen Street, backfill material will be placed over the tunnels by a loader at road level, spread and compacted by plant in the trench.

•

Within the CPO, the material will carted by skid-steer loader from the Lower Queen Street façade to the eastern end of the building, progressively filling towards Lower Queen Street. Material will be compacted in layers as it is placed.

•

Props will be removed progressively as backfill progresses. The props will be re-used or recycled off site.

2.6

Site geology and groundwater

The geology of the Project area has been established by earlier investigations for the CRL Britomart to Wyndham Street enabling works. The general stratigraphic sequence comprises fill overlying Tauranga Group overlying East Coast Bays Formation (ECBF) within the Waitemata Group. A brief description of the stratigraphic units for the Project area is provided below: •

Fill – asphalt or concrete pavement underlain by granular basecourse and/or sub-base. Fill materials may comprise re-worked natural soils (silts, sands and gravels) or waste materials such as ash, clinker and demolition rubble.

•

Auckland Volcanic Field – the Albert Park Volcano, located east of Queen Street is close to the Britomart to Wyndham Street section of the CRL project.

•

Tauranga Group – alluvial and marine sediments comprising peat, mud, silt, sand and gravel.

•

ECBF – alternating sandstone and siltstone beds with a completely weathered (residual soil) upper surface.

The Waitemata aquifer is the dominant hydrogeological unit in the central and southern part of the Auckland Central Business District. Key aspects of the hydrogeological model for the Britomart to Wyndham Street enabling works are: •

Localised/perched groundwater heads in un-weathered ECBF and weathered ECBF of 1 to 2 m are recorded. Seasonal groundwater level variations are likely to be about 2 m and responses

Erosion and Sediment Control Plan

August 2018


13 to rainfall events can result in a 0.4 m variation. The perched groundwater is not hydraulically connected to the underlying regional ECBF (lower) groundwater level. •

2.7

The groundwater level in the Fill, Tauranga Group and ECBF in the reclaimed area is close to sea level and groundwater flow is north towards the harbour. The groundwater in the Fill is complex due to the mixture of materials present and is highly dynamic, being controlled principally by tidal effects close to the sea and the drainage-recharge influences of the stormwater drainage system. Together with other network utility service lines (many over a century old and potentially ‘leaky’), the backfill in these service trenches is considered to form rapid flow conduits for groundwater movement.

Catchment boundaries

Stormwater runoff will be controlled and managed throughout the Project. Only limited stormwater inflow into the cut and cover excavation within Lower Queen Street (ACZ D) is expected. The volume of stormwater inflow into this area will be reduced by the provision of a barrier wall around the perimeter of excavations. Excavations within the CPO (ACZ C) will be contained within the CPO building and hence not subject to external weather conditions. The total Project catchment area contributing to stormwater inflow into the excavations will be approximately 800 m2. The catchment boundaries and associated information are shown on Figure 1 in Appendix D.

Erosion and Sediment Control Plan

August 2018


14

3

Erosion and Sediment Control Approach

3.1

Key principles and approaches

Erosion and sediment control measures will be implemented in order to minimise the extent of soil erosion and sediment yield from the Project site during the works. The erosion and sediment control measures will be designed, implemented and monitored in accordance with Auckland Council Erosion and Sediment Control Guide for Land Disturbing Activities in the Auckland Region Guidance Document 2016/005 (GD005) 4. In some circumstances, and where appropriate, measures exceeding the requirements of GD005 will be used where there is a greater risk of erosion and sediment runoff effects associated with undertaking the works. All sediment control measures will be fully established within each ACZ before physical works commence in that area. Key principles underpinning this ESCP include: •

Viewing the Project works holistically, such that all construction activities, and the full effects of these construction activities, are considered as a whole.

•

Implementing a team approach for design, implementation, maintenance and disestablishment of erosion and sediment control measures. This will ensure “ownership” of the erosion and sediment control measures and therefore better implementation and maintenance.

•

Undertaking pre-construction meetings for each specific package of works and having regular weekly meetings (toolbox meetings) on site with relevant personnel and AC officers.

•

Preparing a detailed schedule of construction activities, with monthly updates, and providing these to AC.

•

Maintaining a register of control measures and “As Built” information to allow for quick referencing and understanding of erosion and sediment control measures.

•

Including both physical and non-physical elements within the methodologies to be employed such as: −

Pre-construction investigation and testing to confirm the nature of the ground materials and to identify the presence of any contamination.

−

Providing interceptors to minimise the ingress of rainfall and surface runoff into the construction zones and thus minimise the erosion and sediment generation process to be dealt with during construction.

−

Protecting the construction zones from flooding and ensuring that the protection measures do not lead to increased flood risk of adjacent properties.

−

Providing a sediment settling and retention device to manage and treat sediment laden water collected during construction and discharge it at an acceptable quality into the receiving environment 5.

−

Isolating, treating and disposing of any contaminated materials encountered (refer also to the Project Contamination Delivery Work Plan).

−

Providing measures which prevent spillage from higher risk construction activities such as bentonite processing and concrete production areas.

−

Identifying and managing risk at high risk areas.

GD005 is an update of Auckland Council Technical Publication 90 – Erosion and Sediment Control Guidelines for Land Disturbing Activities in the Auckland Region. While TP90 is referred to in resource consent R/REG/2014/5430 condition 48, GD005 is now best practice for erosion and sediment control and has superseded TP90 5 Water quality in the receiving environment is outlined in Section 4.6.3 of the Auckland City Rail Link Britomart to Wyndham Water Quality Assessment dated December and prepared by Golder Associates 4

Erosion and Sediment Control Plan

August 2018


15

3.2

−

Responding to weather patterns.

−

Ensuring construction workers are aware of the erosion and sediment controls employed and do not remove them without seeking appropriate approval.

General erosion and sediment control measures

The following general erosion and sediment control measures will be employed: •

Provide silt fences, silt capture at catchpits and bunding at surface works to prevent dirty water ingress into the public stormwater system. Silt capture at catchpits will be managed to ensure that it does not exacerbate flooding during rainfall events.

•

Provide bunding around excavations to a level above the design flood plain in order to protect the excavations from flood inundation via surface runoff and flood plains during extreme rainfall events, recognising that any inundation could flood the BTC and place the rail service at risk.

•

Minimising groundwater ingress into the excavations.

•

Provision of a settling tank to receive water pumped from the excavations for settling and capturing sediment, enabling water of suitable quality to be discharged into the receiving stormwater drainage system.

•

Provision of assisted sediment settlement if required, using chemical or non-chemical flocculants, the latter being preferred if effective. A batch dosing methodology will be deployed.

•

The Project’s water quality discharge goal is consistent with standards set out in the Water Quality Assessment report prepared by Golder Associates (dated December 2014), namely, minimum water clarity of 10 cm measured with a black disk, TSS concentration of less than 50 g/m3 for 95% of the time, pH between 5 and 9, and no visible TPH (refer to CTMP in Appendix B for further details).

•

It is assumed that there will be no stormwater capacity limitations for discharging the treated water from the site.

•

All material removed from or delivered to the Project site will be covered during transportation.

•

Stabilised entrance ways will be established at ingress and egress points of the site. Road vehicles carting to and from the site will remain on sealed accesses while within the site boundaries. The roads and footpaths will be cleaned regularly and maintained to ensure that they remain free from soil and material, which could be tracked off the site.

•

High risk spillage areas will be bunded for the containment and management of any spilled materials.

•

Any contaminated soils encountered will be managed as described in the Contamination Delivery Work Plan (DWP) provided at Appendix K to the CEMP. The general intent is to isolate any contaminated materials from the rest of the excavated materials and dispose of them as outlined in the Contamination DWP.

•

Dust control measures will be applied to construction activities including stockpiles, concrete cutting, demolition work, earthmoving, general construction activities, and bentonite powder handling. Details of the measures to be implemented are outlined in the Project Air Quality DWP provided at Appendix L to the CEMP.

Erosion and Sediment Control Plan

August 2018


16

4

Specific erosion and sediment control measures

4.1

General

The erosion and sediment control measures that will be implemented for the Project are based on the principles outlined in Section 3.2. Section 4.11 of this ESCP outlines specific erosion and sediment control measures applicable to each construction activity and ACZ.

4.2

Perimeter controls

Perimeter controls will be provided for the works in ACZ D (Lower Queen Street). These will take the form of a barrier wall around the excavations (within the construction area), of sufficient height to provide flood protection against high return period rainfall events as well as keeping clean runoff out of the site. Given the importance of avoiding flooding of the rail service, protection against rainfall events with an Annual Return Interval (ARI) of at least 1 in 200 years will be adopted. The location of the barrier wall is shown on Figure 4.1 (in blue). Council flood hazard maps show 1 in 100 year ARI flood depths of up to 0.2 m in the vicinity of the works in Lower Queen Street. The barrier wall will be no higher than 0.5 m. The barrier wall will be constructed with blockwork or reinforced concrete and bonded at its base to the road surface.. The overland flow path along Lower Queen Street will be maintained during excavation by way of a 4m wide shared access driveway located to the west of the excavation (Figure 4.1 and 4.2). With the barrier wall in place, diaphragm walls installed to significantly reduce the groundwater ingress, and subsurface work below the CPO contained within the building footprint, only limited volumes of water will need to be managed within the excavations. As such, the construction methodology minimises the ESCP measures required for the cut and cover excavation and tunnel construction.

Erosion and Sediment Control Plan

August 2018


17 Figure 4.1: Key ESC measures installed onsite, and stormwater/groundwater water pumping and treatment plan.

Figure 4.2: Overland Flow Path

4.3

Vehicle access

Vehicle access for the transport of excavated materials from the site and delivery of materials to the site will be via sealed access ramps on the northern and southern sides of the Lower Queen Street excavation (ACZ D). Vehicles transporting material to and from the site will not be passing over excavated ground. The expected construction traffic volumes are outlined in Table 4.1 Table 4.1:

Expected construction traffic volumes

Construction Stage and ACZ

Light Vehicles Per Day

Trucks Per Day

Total Vehicles Per Day

Stage 1 (ACZ B) – Temporary western station access

30

4 to 10

34 - 40

Stage 2 (ACZ C) – CPO under pinning & tunnel excavation

40

20 to 35

60 – 75

Stage 3 (ACZ A and D) – Tunnel construction

40

20 to 35

60 – 75

Stage 4 (All ACZ) – Reinstatement & station fit out

30

4 to 10

34 - 40

Erosion and Sediment Control Plan

August 2018


18

4.4

Dewatering of excavation

The rainwater and groundwater inflow rates expected to enter the excavations within the Project area are summarised in Table 4.2. Table 4.2:

Water inflow rates

Rainfall event average recurrence interval (ARI)

24 hour rainfall depth (mm)

Rainfall ingress in 24 hour rainfall event 6

Groundwater inflow 7 (m3/day)

(m3)

Total water ingress in 24 hours during design rainfall event + groundwater (m3)

1 in 2 year

76

60

250

310

1 in 5 year

99

80

250

330

1 in 20 year

145

120

250

370

1 in 100 year

188

147

250

507

No more than 5 m3/day of groundwater ingress is expected through the temporary perimeter cut-off walls. This means that the majority of the predicted groundwater ingress will be through the bottom of the excavations prior to casting of concrete base slabs for the new rail tunnels. Excavations within the CPO and in Lower Queens Street will be sloped towards a low point on the eastern side of the Lower Queen Street excavations. A pump sump/sediment pit will be constructed at the drainage low point for the capture of coarse sediment before pumping to a treatment system at street level that will be located outside the south east corner of the CPO, adjacent to the glasshouse (within CSA A). The pump system will comprise two pumps in order to handle low and high inflows into the excavations.

4.5

Treatment plant

A settlement based treatment plant will be located in CSA A, adjacent to the south east corner of the CPO building and next to the glasshouse (refer to Figure 2.2). The plant will include chemical treatment capability to assist the settlement process when required. A CTMP is provided in Appendix B of this ESCP and outlines the treatment plant including: •

Treatment design flow;

•

Dosing system;

•

Flocculation tank;

•

Lamella clarifier;

•

Sludge thickening tanks;

•

Monitoring of water quality;

•

Spill contingency plan; and

6

Based on 800 m2 exposed excavation area in Lower Queen Street.

7

Based on predicted maximum short term tunnel inflow rates given in Table 10 of PDP groundwater effects assessment – Britomart to Wyndham report, December 2014. Of the amount shown, 84% (210 m3/day) is estimated to be contributed from the excavations within the CPO.

Erosion and Sediment Control Plan

August 2018


19 Responsibilities for the operation and maintenance of the CTP.

•

4.6

High risk spillage areas

High risk spillage areas within the construction site include: •

The bentonite treatment plant, located adjacent to the south west corner of the CPO building on Lower Queen Street;

•

Jet Grouting Plant, located adjacent the north western corner of the CPO building on Lower Queen Street; and

•

Other areas around the work site where concrete production is required.

Areas around these activities will be bunded as appropriate to prevent any spillages escaping from the site. The bund will include collection sumps, and pumps for transferring contaminated fluids to trucks for disposal off site at suitable facilities. Refer to the Industrial and Trade Activities Environmental Management Plan (ITA EMP) provided at Appendix N to the CEMP for more detail on the management of the above construction activities. In addition, during bulk excavation works, several higher risk areas of the site will be reconfigured to drain to the onsite water treatment plant (Figure 4.1). This includes:

4.7

•

A bunded wheel wash area to the south of the excavation, and the surrounding hardstand area, and

•

A bunded spoil load out area to the north of the excavation.

Extreme weather events

A large portion of the work will be contained within the CPO building, and flood protection measures will be put in place around the perimeter of the Lower Queen Street works. As such, extreme weather events are expected to have only a small influence on the construction activity. Contingency measures for the Project will address inundation of the excavations. All erosion and sediment control devices will be inspected after a storm event to ensure they are still operating effectively.

4.8

Construction stormwater management

Once the Projects ACZs and CSAs are established, stormwater runoff from impervious areas will be captured and treated according to this ESCP. Design of the temporary stormwater management facilities for the yards will be provided to AC as they become available to comply with the relevant resource consent conditions.

4.9

Stockpile management

Only limited, temporary stockpiling of material will take place during construction of the Project. Generally, excavated material will be sorted into contaminated material, managed fill and clean material and directly loaded on to trucks for disposal off site. Backfill material delivered to site will be placed directly in the backfill zones. Any temporary stockpiles of excavated or construction materials will not exceed 24 m3 of spoil at any one time in each ACZ in accordance with Condition 71(e) of the Projects discharge to air permit R/REG/2014/5437. Stockpiles will be managed to prevent sediment runoff or airborne dust from them by applying one or more of the following measures:

Erosion and Sediment Control Plan

August 2018


20 •

Use of covers.

•

Light compaction of stockpile surfaces.

•

Light wetting for dust suppression.

•

Bunding.

Refer to the Project Air Quality DWP for further detail on the management of dust from any stockpiles.

4.10

Kerbside management

The Project includes kerbside management changes (including footpath widening) that will require cutting and laying of concrete along Tyler and Galway Streets. Erosion and sediment controls measures to manage this activity will include: •

Dust management measures outlined in the Air Quality DWP.

•

Continuous cleaning of kerbside and sidewalks.

•

Avoidance of placing materials and equipment on or near footpaths.

•

Effective reinstatement and site tidying.

4.11

Specific erosion and sediment control measures

Table 4.3 outlines the specific ESC measures to be implemented for the various construction activities proposed. Table 4.3:

Construction activities and related erosion and sediment control approach

Construction Activity

Approx. Duration

Specific ESC measure(s)

Stage 1 – Site establishment, temporary accommodation and streetscape works 7 months

• Install filter socks around plant storage yards. • Install and manage geotextile and filter socks under and around nearby stormwater catchpit grates in such a way as to avoid exacerbated flooding during rainfall events.

• Removal of raised floor in former banking chamber • Protection of heritage features in the CPO

Up to 3 months

• Apply dust control measures specified in Air Quality DWP.

• Saw cutting and demolition of CPO concrete ground floor

3 months

• Apply appropriate dust control measures specified in the Air Quality DWP. • Any water used for concrete saw cutting or from processing of existing concrete is to be collected and disposed of off-site.

• Site establishment and temporary site office

Stage 2– CPO building works

Stage 3 – CPO and Lower Queen Street Works – CPO diaphragm wall construction and underpinning, piling, excavation, tunnel construction, backfilling and reinstatement CPO Works

Erosion and Sediment Control Plan

August 2018


21 Construction Activity

Approx. Duration

Specific ESC measure(s)

• Construction of diaphragm walls using bentonite slurry and cement

6 months

• Form a containment bund or similar around bentonite processing facility to contain any spillages escaping from site. Bentonite spillage to be collected for reuse or transfer to bentonite plant. • Collection of all cement and bentonite slurry washings/spillage during pouring is to be reused or disposed of off-site.

• Underpinning of CPO

4 months

• Apply dust control measures set out in Air Quality DWP. • Capture contaminated water and discharge into treatment plant or dispose off-site.

• Excavate and backfill beneath the CPO building

8- 10 months

• Dewatering of excavation by sloping excavations to a low sump/sediment pit for coarse sediment capture. Captured water will then be pumped to a settling tank, assisted with chemical treatment if required, at ground surface. Water to be quality checked prior to discharging into stormwater system. • Excavator loading directly to waiting trucks for immediate transfer of spoil off-site for disposal at an approved landfill. • Cleaning up of any spillage of ground materials. Water from the excavation is to be collected and pumped to settling tanks. • Load out area for waiting trucks is bunded and drains to the water treatment plant. Truck tyres can be manually washed in this area if required. • All concrete washings/spillage during pouring is to be collected at a low point in the excavation and disposed of off-site.

• Construction of concrete tunnel base slabs and walls

6- 7 months

• Collection of all contaminated washings/ spillage during pouring is to be collected and disposed of offsite.

• CPO concrete floor reinstatement • Reinstatement of CPO fixtures and fitting

Up to 15 months

• Clean any concrete spillage immediately. • Capture contaminated water and discharge into treatment plant or dispose offsite as appropriate depending on nature of the contamination.

Lower Queen Street Works Remove Lower Queen Street concrete asphalt road surface and utilities • Piling under Lower Queen Street using anger procedure

Erosion and Sediment Control Plan

3 months

Install geotextile and filter socks under and around nearby stormwater catchpit grates.

3- 4 months

• Immediate transfer of spoil into trucks for off-site disposal. • Collection of soil contaminated water into settling tanks, assisted with chemical treatment if required, prior to stormwater network discharge.

August 2018


22 Construction Activity

Approx. Duration

Specific ESC measure(s)

• Excavate below Lower Queen Street for tunnels

3 months

• Form a barrier wall around the excavation to prevent clean water entering the work site and provide protection against flooding risk. • Maintain overland flow path along Lower Queen Street across the excavations (pipe or bridge) • Dewatering of excavation by sloping excavations to a low sump/sediment pit for coarse sediment capture. Captured water will then be pumped to a settling tank, assisted with chemical treatment if required, at ground surface. Water to be quality checked prior to discharging into stormwater system. • Excavator loading directly to waiting trucks for immediate transfer of spoil off-site for disposal at an approved landfill. • Load out area for waiting trucks is bunded and drains to the water treatment plant. Truck tyres can be manually washed in this area if required. • Cleaning any spillage of ground materials will be required especially when loading disposal trucks. Contaminated water to be collected and transferred to settling tanks prior to discharge.

• Construction of concrete tunnel base slabs and walls

6 months

• Collection of all contaminated washings/ spillage during pouring to be collected and disposed off-site.

• Backfilling and reinstatement of Lower Queen Street

12 months

• Apply dust control measures in accordance with the Air Quality DWP • Leave all ESC measures in place until all Lower Queen Street works are complete. All Stage 3 Works

• Collection of groundwater during construction of tunnel walls

Up to 12 months

• Collection of all water runoff at a low sump/sediment pit for coarse sediment capture. Captured water will then be pumped to a settling tank at ground surface. Water to be quality checked prior to discharging into stormwater system.

• Backfill to underside of structures

3 months

• Apply dust control measures in accordance with the Air Quality DWP. • Leave all ESC measures in place until all CPO building works are complete.

3 months

• Apply dust control measures in accordance with the Air Quality DWP.

Stage 4 – Reinstatement • Backfilling and reinstatement Station Plaza and Streetscape in Project area

4.12

Certification of sediment control devices

Prior to construction (bulk earthworks) commencing, a certificate signed by a senior qualified person shall be submitted to AC (Team Leader Central Monitoring) to certify that the erosion and sediment

Erosion and Sediment Control Plan

August 2018


23 controls relevant to the enabling works have been constructed in accordance with the certified ESCP. Certification details of diversion bunds and sumps will be supplied immediately upon completion of construction. Information supplied (if applicable) will include: a b c d

4.13

contributing catchment area; shape of structure (dimensions of structure); position of inlets/outlets; and stabilisation of the structure.

Modification to structural controls

In the event that any minor modifications to the structural controls system (treatment tanks) are required during the Project, the following information shall be provided to AC: a b

Plans and drawings outlining the details of the modifications; and Supporting information that details how the proposal does not affect the capacity or performance of stormwater management systems.

All information shall be submitted to, and the proposed modifications certified by AC (Team Leader Central Monitoring), prior to implementation.

Erosion and Sediment Control Plan

August 2018


24

5

Monitoring and Maintenance

As part of the erosion and sediment control measures, on-going monitoring will be undertaken for the full duration of the works. This will ensure that all of the control measures detailed in this ESCP have been properly implemented and are functioning effectively. Monitoring and maintenance activities will include: a b c d

e f g h i

j

Seven day weather forecast. Works will be programmed in accordance with weather predictions. Monitoring of turbidity and pH of the water exiting the clarifier will be undertaken automatically and be recorded on site. Correlation testing will be undertaken during commissioning of the treatment plant to confirm the turbidity value equivalent to the required clarity and Total Suspended Solids values. If assisted settlement is required using non-chemical or chemical coagulants/flocculants, monitoring of dosing rates will be included. The application of the coagulants/flocculants will be carried out in accordance with best practice principles and the CTMP in Appendix B. Sludge accumulation in the sludge thickening tanks, will be trucked off-site when the sludge has reached a sufficient volume and thickened constituency. Daily monitoring of the containment measures at the high risk spillage areas and undertaking maintenance of these as required. Daily monitoring and cleaning of the spoil load out areas/site entrances. Regular monitoring of the surface silt control measures (silt fences, catchpit silt capture and bunding) for silt capture effectiveness and non-exacerbation of flooding during rainfall events. Monitoring of excavated materials and groundwater quality for any evidence of contamination requiring special management measures (refer to the Contamination DWP for details). Other on-site activities such as storage of chemicals, refuelling facilities and practices, site offices, temporary stockpiles, dust control, noise control, etc. will be monitored and maintained in accordance with the specified standards outline in the relevant DWPs and the CRL and BTC designation and resource consent conditions.

The monitoring activity items and frequency proposed are summarised in Table 5.1. Table 5.1:

Summary of monitoring activity

Aspect

Frequency

Location

Monitoring details

Influent water quality entering the treatment plant

Details provided in the CTMP (provided at Appendix B)

Reporting Monthly compliance reports sent to AC consent officer

Effluent water quality exiting the settlement process Seven day weather forecast

Daily

From two or more reliable forecast sources

Record daily

Sediment accumulation in settlement tank

Monthly

In settlement tank

Use staff with round plate on bottom to rest on silt surface, or other effective means

Erosion and Sediment Control Plan

August 2018


25 Aspect

Frequency

Location

Monitoring details

Bentonite processing area

Daily

At processing area

Check for spillages, effective containment and need for off-site disposal of contaminated fluids Refer also to the ITA EMP

Concrete production areas

At production areas

Surface silt control measures

Daily

At silt control measures

Clean, adjust and replace control measures as required

Check excavated materials and groundwater for any contamination

Daily initially during excavations, then less frequent if safe to do so

At points of excavation

Testing of soil and water samples

Clean water diversions (bunds), barriers (sediment) and overland flow paths

Weekly and before forecast rain events

In Lower Queen Street

Visual check that the bunds and barriers are intact and clean

Stockpiles

Daily

Within excavations and possibly Lower Queen Street

Visual check that dust control and sediment runoff prevention measures are effective

Drains and sumps / pumps

Daily

Within excavations

Visual check that drains and pumps are not blocked and are operating satisfactorily

Other site activities

Weekly

At respective site activities

Visual inspection

Erosion and Sediment Control Plan

Reporting

August 2018


26

6

Roles and Responsibilities

The key management roles in relation to environmental management during construction are outlined in the Project CEMP. Specific roles relating to this ESCP are detailed in Table 6.1. Table 6.1:

Roles and responsibilities

Role

Responsibilities

Construction Manager

• Inspection of works to assess compliance with the ESCP and sub-plans – including operation and maintenance of the Chemical Treatment System and daily monitoring.

Environmental and Sustainability Manager

• On-site compliance with designation and resource consent conditions and other requirements, and tracking compliance information. • Report to CRLL changes to construction techniques or natural environmental changes which require alterations to approved ESCP or new resource consents. • Prepare, review and update the ESCP and CTMP. • Facilitate and oversee environmental monitoring -– including daily Chemical Treatment System monitoring.

Erosion and Sediment Control Engineer

• Ensure all erosion and sediment control measures are constructed and implemented in accordance with the ESCP and industry standards. • Hold ongoing weekly or fortnightly meetings with Site Supervisors and other necessary personal to review the effectiveness of the erosion and sediment control measures that have been implemented.

Site Supervisors

• Hold preconstruction meeting prior to the commencement of work in each ACZ and advise all staff of erosion and sediment control measures to be put in place. • Attend ongoing weekly or fortnightly meetings to review the effectiveness of the erosion and sediment control measures that have been implemented.

All staff

• Undergo erosion and sediment control training. • Not relocate or alter erosion and sediment control devices without appropriate authority.

Erosion and Sediment Control Plan

August 2018


27

7

Environmental Training

7.1

Project staff

All Project staff (contractors and subcontractors) will undergo general environmental awareness training and training about their responsibilities relating to this ESCP. Training requirements are described in full detail within the CEMP. Specific training requirements relating to this ESCP are outlined in Table 7.1. Table 7.1:

ESCP training requirements

Training requirements

Frequency

Attendance

Training on ESCP requirements and resource consent conditions. Record to be kept of all training material and attendees.

As required and during new staff induction

All new staff members

Tool box meetings on site to include erosion and sediment control as a standard agenda item. Record to be kept of all training material and attendees.

Weekly tool box meetings, or as required (e.g. start of new substantial activity)

Erosion and Sediment Control Engineer, Site supervisors, delegated staff member and duty managers

Construction, maintenance and inspections of erosion and sediment control devices

As required

Erosion and Sediment Control Engineer, Site supervisors, and delegated staff members

Responding to complaints regarding erosion and sediment control and water discharges.

As required and during new staff induction

Site manager, delegated staff member and duty managers

Erosion and Sediment Control Plan

August 2018


28

8

Complaints

Procedures for investigating and responding to complaints are set out in Section 12 of the Project Communication and Consultation Plan and Section 5.3 of the CEMP. It is important to ensure that any complaints are recorded and promptly investigated to identify and resolve the cause of the complaint. The requirements and procedures relating to complaints are detailed below. The requirements and procedures relating to consultation with neighbouring sensitive receivers is otherwise set out in the Communication and Consultation Plan.

8.1

Complaints response

The Project Hotline will be clearly included in any written Project notifications and on signage located in proximity to the Project area. Any erosion and sediment control complaints received by the Project Hotline will be recorded in a complaints file, and investigation will be undertaken as outlined in the CEMP and the Project Communication and Consultation Plan. The investigation will involve the following: •

Information about the incident as described by the complaint.

•

Acknowledge receipt of the concern or complaint. An initial response shall be undertaken within 24 hours of receiving a complaint, and resolved as soon practicable.

•

Weather conditions at the time of the complaint.

•

Reporting the findings and recommendations.

•

Actions and time taken to close-out complaint.

•

Communication with the complainant.

•

Reporting of the investigation in the complaints file.

A record of all concerns and / or complaints received will include, where applicable: •

The name of the person(s) who raised the concern or complaint (unless they elect not to provide this) and details of the concern or complaint.

•

Weather conditions at the time of the concern or complaint, including wind direction.

•

Details of any observed discharge coming from the site by the person investigating the complaint.

•

Known construction activities at the time and in the vicinity of the complainant during the concern or complaint period.

•

Remedial actions undertaken (if any) and the outcome of these, including monitoring of the activity.

An investigation of the complaint will require the site supervisor or delegated staff member to go around the whole site and make visual observations about activities occurring on site. This may also include going to the location where the complainant observed the impact. At all times during the complaints investigation, appropriate health and safety procedures must be followed.

Erosion and Sediment Control Plan

August 2018


29

9

ESCP Review

This ESCP has undergone a review process with the Community Liaison Group (CLG) established for the Project and a suitably qualified independent peer reviewer. An explanation of how any comments from the CLG and Peer Reviewer are addressed in this ESCP is provided in Appendix E.

9.1

ESCP Review

This ESCP will be reviewed throughout the course of the Project: a b

To reflect material changes associated with changes to construction techniques, the natural environment or due to unresolved complaints; and As part of the annual management review of the ESCP.

A management review of the ESCP will be undertaken by the Project Management Team and CRLL representatives. The management review will be organised by the Environmental and Sustainability Manager and the Project team will be informed of any changes to this ESCP through the regular Project communications processes. The review will take into consideration: •

Compliance with the resource consent conditions, the CEMP, DWPs and EMPS (including site specific plans) and material changes to these plans

•

Any significant changes to construction activities or methods

•

Key changes to roles and responsibilities within the Project team

•

Changes in industry best practice standards

•

Changes in legal or other requirements (social and environmental legal requirements, consent conditions, CRLL objectives and relevant policies, plans, standards, specifications and guidelines)

•

Results of inspections, monitoring and reporting procedures associated with the management of adverse effects during construction

•

Comments or recommendations from AC regarding the CEMP, DWPs and EMPs

•

Unresolved complaints and any response to complaints and remedial action taken to address the complaint.

9.2

ESCP Updates

The process for updating this ESCP as a result of material changes to the Project or the annual review, is as follows (refer to CRL designation Condition 23 for further information): •

Any material change to this ESCP must be consistent with the purpose and objective of the relevant conditions listed in Table 1.1 of this document.

•

Affected parties and the CLG must be notified of the review and any material change proposed to this ESCP.

•

This ESCP must clearly document the comments and inputs received from affected parties in relation to any material changes, along with a clear explanation of where any comments have not been incorporated, and the reasons why not.

•

Any material change proposed to this ESCP shall be subject to an independent peer review as required by CRL Condition 11.

•

Any material change proposed to this ESCP relating to an adverse effect shall be submitted for approval to Auckland Council Compliance and Monitoring Officer, at least 10 working days prior to the proposed changes taking effect. If any changes are not agreed, the relevant provisions of the RMA relating to approval of outline plans shall apply.

Erosion and Sediment Control Plan

August 2018


30 A copy of the original ESCP document and subsequent versions will be kept for the Project records, and marked as obsolete. Each new / updated version of the ESCP documentation will be issued with a version number and date to eliminate obsolete ESCP documentation being used. A summary of the review process will be provided annually to AC and otherwise be made available on request.

Erosion and Sediment Control Plan

August 2018


31

10

Management and Control of Documents

All project documentation is created, reviewed, approved, issued, revised, retained, and superseded in accordance with the project’s Document Management & Control Plan, which includes the requirement for records of review and authorisation to be maintained. The following documents support the processes described in this ESCP: 1. Project Induction 1.1. Full Induction Presentation Content 1.2. Full Induction Register 2. Toolbox Talks Records 3. Pre-construction Meeting Records (completed prior to each major stage of works) 4. Communication and Complaints Register 5. Environmental Site Inspection Records 5.1. Weekly site inspection reports 5.2. Monthly site inspection reports 6. Water treatment plant monitoring records 6.1. Daily inspection sheets 6.2. Weekly sample results 7. Erosion and Sediment Control Measures 7.1. Register of measures/as-built plans 7.2. Certification document 8. Chemical Treatment Management Plan (Appendix B) 9. Annual Review 9.1. Record of review of DWP

Erosion and Sediment Control Plan

August 2018


Appendix A:

ISCA Requirements

Table A identifies the ISCA Credit Requirements relevant to this ESCP and the CTMP and where they are addressed in the document. Table A: ISCA Requirements Credit

Requirement *

Relevant section

Comments

WAT-2 Level 1

Opportunities to reduce water use identified

Section 4.2

Project Sustainability Opportunities Register

WAT-3 Level 1

Identify non-potable sources that match demand

Section 4.2

Project Sustainability Opportunities Register

LAN-1 Level 3

>75% of the land used for the project is on previously disturbed land

Sections 2.1 and 2.2

LAN-2 Level 1

Conservation of topsoils, subsoils etc. has been considered

Section 4.9

Also refer to the Waste Avoidance and Resource Recovery Management Plan

LAN-2 Level 2

Subsoil and top soil is separated and protected from erosion etc.

Sections 4.2, 4.9

Also refer to the Waste Avoidance and Resource Recovery Management Plan

LAN-2 Level 2

95% of topsoil retains its productivity and is beneficially reused on or nearby to the project

LAN-3 Level 3

Assessment of contamination and remediation measures

Sections 3.1, 3.2, 5

Refer also to the Contamination DWP

LAN-4 Level 1

Run-off, flood risk and potential to increase flood risk have been included so there is no increase in flood risk

Sections 3.1, 3.2 4.2, 4.7

Refer also to the Industrial and Trade Activities Environmental Management Plan

DIS-1 Level 1

Baseline studies of existing receiving water environment have been carried out for the project

Sections 2.6, 3.1

Also refer to the Water Quality Assessment Report by Golder Associates, dated Dec 2014 and the Chemical Treatment Management Plan (Appendix B)

DIS-1 Level 1

Predictions for receiving water quality impacts have been developed for construction

Sections 2.7, 4.4 Appendix B: Chemical Treatment Management Plan Section 1.1, 2.1.1, 2.3

Also refer to the Water Quality Assessment Report by Golder Associates, dated Dec 2014 and the Chemical Treatment Management Plan (Appendix B)

DIS-1 Level 1

Measures to minimise adverse impacts to local receiving water quality

Sections 2.5.2, 2.5.3, 2.7, 3.1, 3.2, 4.2, 4.3, 4.4, 4.5, 4.6, 4.7, 4.8, 4.9, 4.10, 4.11, 4.12, 5, 6

Also refer to the Chemical Treatment Management Plan (Appendix B) and Contaminated Soils DWP

Note – Topsoil is limited to garden/planted areas as the remainder has been developed. Refer to the Waste Avoidance and Resource Recovery Management Plan


Credit

Requirement * identified and implemented

Relevant section Appendix B: Chemical Treatment Management Plan Section 1.1, 2.1, 3, 4, 6

DIS-1 Level 1

Monitoring of water discharges and receiving waters is undertaken at appropriate intervals and at times of discharge during construction

Section 3.2, 4.11, 5 Appendix B: Chemical Treatment Management Plan Section 3

DIS-1 Level 2

Modelling demonstrates no exceedances of water quality goals

Section 3.2 Appendix B: Chemical Treatment Management Plan Section 2.3

DIS-1 Level 2

All stormwater leaving the site is treated or filtered in accordance with appropriate urban stormwater guidelines unless it occurs during a 6 hour 1 in 5 year storm event

Section 3.2, 4.2, 4.4, 4.5, 4.8, 4.9, 4.10, 5 Appendix B: Chemical Treatment Management Plan Sections 2 and 3

* Refer to ISCA Rating Tool for full details of the requirement

Comments


Appendix B:

Chemical Treatment Management Plan


Appendix C:

Staging Plans


Appendix D:

Drawings

Figure 1

Catchment Boundaries

•


Appendix E:

CLG comments

Community Liaison Group Comments

•

Comments received from the CLG are as follows: Date

CLG Member

Comment

Response

19 January 2016

Tim Coffey

Will the flood barrier around the Lower Queen Street excavation impede pedestrian access?

No, the barrier will be inside the construction area. Pedestrian access along Lower Queen Street will be maintained at all times during the construction works, however during works in Lower Queen Street (Stage 3), access will be directed to the western side of the street. Section 4.2 of the ESCP updated to clarify location of bund.

4 May 2016

Coopers and Company

Section 9, ESCP Review, sets out the formal review process and mentions taking into account comments or recommendations of Council but doesn’t mention the CLG. Condition 19 states that the consent holder is required to consult with the CLG upon the review of this plan. Reference should be included here of this obligation.

Section 9 text has been updated to reference Condition 19 requirement to consult with the CLG upon the review of the ESCP.

4 May 2016

Coopers and Company

It should be noted that Appendix B - Chemical Treatment Management Plan is in response to Condition 50.

Section 1.1 text updated to specifically reference Conditions 48 (f) and 50 -53 which sets out the requirement for Chemical Treatment Management Plan. Appendix B, Section 12 states that the CTMP is required under Condition 50 of the CRL Britomart to Wyndham Street land use consent R/REG/2014/5430 and Conditions 99 to 104 of discharge permit R/REG/2014/5436.

4 May 2016

Coopers and Company

Appendix C – Staging Plans are dated 14/11/14 and refer to the possibility of the upper floors of the CPO remaining tenanted in stage 1 (May to October 2016) and vacated for Stage 2 (October to June 2017). Need to ensure these dates marry with dates advised through Public Works Act process. Our understanding is that they currently do but have not yet seen final Public Works Act proposal. Also the plans refer to the upper levels of the CPO as

The Staging Plans dates are not supposed to correspond with the tenancy of the upper floors of the CPO building. Dates and plans detailing the tenancy of the CPO upper floors as site office and for storage will be agreed with Cooper and Company through the Public Works Act process.

th

No amendments made to this ESCP.


being used as a site office and for storage. Cooper and Company would like details of what areas are proposed to be used for - given their interest in receiving the upper floors of the CPO back in the same high quality fit-out as they were at the time AT takes possession. 4 May 2016

Coopers and Company

Appendix D -CLG comments, no comments are included. Does this mean none were received?

One CLG comment was received and is referenced above in this table.

13 May 2016

Coopers and Company

Section 4.9 has a typo ““will not be exceed”

Section 4.9 text updated to correct typo.


Appendix F:

Register of Plan Updates

Annual Review

• Plan

Updates

Date

ESCP

Updates have been made to the following sections: • Glossary – insert reference to GDoo5 – Auckland Council Erosion and Sediment Control Guide for Land disturbing Activities in the Auckland Region, which has superseded TP90 • Section 2.4 – change to construction programme • Section 3.1 – updated reference from TP90 to GD005 • Section 3.2 – deletion of reference regarding work being undertaken largely under roof to reflect the removal of the canopy over the Lower Queen Street excavation, originally proposed • Section 4.5 – update text to reflect the treatment plant installed by Filtec Ltd for the DSBJV • Section 4.11 – change to construction method for concrete processing from the CPO ground floor demolition • Section 5 – text updated to reflect monitoring and maintenance requirements associated with the installed treatment plant • Appendix D – update to drawings with treatment plant drawings now included in the CTMP

September 2017

CTMP

• Section 1.1. – minor change to text to refer to no, or very limited rainfall contribution • Section 2 – updated text throughout section to reflect the treatment plant installed by Filtec Ltd for the DSBJV • Appendix C – inclusion of drawings of installed treatment plant

September 2017

ESCP

Updates have included: • Section 2.4 update to the construction works timing • Section 2.5.2 change to load of method of spoil from CPO as conveyor belt no longer required • Section 4.2 Updated to include a plan showing the location of the key ESC installed on the site, and the overland flow path and text associated with this • Section 4.5 removed reference to temporary storage tank as no longer required. • Section 4.6 addition of high risk bunded areas associated with bulk excavation works. • Table 4.3 updated to include spoil load out area controls, and removal of reference to conveyor belt. • Section 5.0 and Table 5.1 removed reference to vehicle access ramps as no vehicle ramps into excavation. • Updated various references throughout the document from Auckland Transport to CRLL where appropriate.

August 2018

CTMP

Updates have included: • Section 2.1 update to the description of the treatment plant to reflect what has been installed. • Section 2.1.1 Update to the pumping system flow rate to reflect the system installed.

July 2018


• Section 2.1.1.1 Deleted pumping capacity scenario under low flows as pumping system has already been installed as described in Section 2.1.1 • Section 2.3 Changed contingency measures as sucker trucks no longer required since trade waste agreement has been in place. • Section 2.3 Deleted reference to temporary storage tank as no longer required. • Updated various references throughout the document from Auckland Transport to CRLL where appropriate.