Skip to main content

Construction noise and vibration DWP

Page 1

NIKAU STREET STORMWATER MAIN REALIGNMENT CONSTRUCTION NOISE AND VIBRATION DELIVERY WORK PLAN (CNV DWP) Rp 002 r8.0 2016651A | 11 April 2018


84 Symonds Street PO Box 5811 Wellesley Street Auckland 1141 New Zealand T: +64 9 379 7822 F: +64 9 309 3540 www.marshallday.com

Project:

NIKAU STREET STORMWATER MAIN REALIGNMENT

Prepared for:

MBJV28 Mt Eden Rd Auckland

Attention:

Graeme Inglis

Report No.:

Rp 002 r8.0 2016651A

Disclaimer Reports produced by Marshall Day Acoustics Limited are based on a specific scope, conditions and limitations, as agreed between Marshall Day Acoustics and the Client. Information and/or report(s) prepared by Marshall Day Acoustics may not be suitable for uses other than the specific project. No parties other than the Client should use any information and/or report(s) without first conferring with Marshall Day Acoustics. The advice given herein is for acoustic purposes only. Relevant authorities and experts should be consulted with regard to compliance with regulations or requirements governing areas other than acoustics. Copyright The concepts and information contained in this document are the property of Marshall Day Acoustics Limited. Use or copying of this document in whole or in part without the written permission of Marshall Day Acoustics constitutes an infringement of copyright. Information shall not be assigned to a third party without prior consent.

Document Control Status:

Rev:

Comments

Date:

Author:

Reviewer:

Draft

5.0

Final for Consent

9 Dec 2016

-

Craig Fitzgerald

Draft

6.0

CSA at 28 Mt Eden Road

9 Aug 2017

-

Craig Fitzgerald

Draft

7.0

MBJV update

10 Apr 2018

Craig Fitzgerald

James Whitlock

Final

8.0

For MediaWorks review

11 Apr 2018

Craig Fitzgerald

-

Cover Photo: Creative Agency 514-806-1644


TABLE OF CONTENTS 1.0

INTRODUCTION .......................................................................................................................................... 5

2.0

PROJECT DESCRIPTION ............................................................................................................................... 5

2.1

Overview ..................................................................................................................................................... 5

2.2

Programme ................................................................................................................................................. 7

2.3

Key Personnel ............................................................................................................................................. 7

3.0

PERFORMANCE STANDARDS ..................................................................................................................... 8

3.1

Noise ............................................................................................................................................................ 8

3.2

Vibration ...................................................................................................................................................... 9

3.3

MediaWorks.............................................................................................................................................. 10

4.0

PREDICTED CONSTRUCTION NOISE AND VIBRATION LEVELS ............................................................... 10

4.1

Noise .......................................................................................................................................................... 10

4.2

Vibration .................................................................................................................................................... 11

5.0

MITIGATION AND MANAGEMENT .......................................................................................................... 12

5.1

Training ...................................................................................................................................................... 12

5.2

Construction Hours................................................................................................................................... 12

5.3

Mechanical Plant Selection ...................................................................................................................... 13

5.4

General Mitigation Measures .................................................................................................................. 13

5.5

Noise Barriers and Enclosures ................................................................................................................. 14

6.0

COMMUNICATION ................................................................................................................................... 14

6.1

Communication Overview ....................................................................................................................... 14

6.2

Complaints Response ............................................................................................................................... 15

7.0

MONITORING ............................................................................................................................................ 15

7.1

Noise .......................................................................................................................................................... 15

7.2

Vibration .................................................................................................................................................... 16

8.0

AFFECTED PARTIES ................................................................................................................................... 19

8.1

Airborne Noise .......................................................................................................................................... 19

8.2

Reradiated Noise ...................................................................................................................................... 21

8.3

Management of Adverse Effects ............................................................................................................. 21

9.0

CNV DWP REVIEW AND UPDATING (INCLUDING SSCNMP AND SSCNMP) ......................................... 22

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

3 of 73


APPENDIX A GLOSSARY OF TERMINOLOGY APPENDIX B NOISE LEVEL PREDICTIONS APPENDIX C VIBRATION REGRESSION CURVES APPENDIX D SITE SPECIFIC MANAGEMENT PLANS APPENDIX E COMMUNICATIONS RECORDS APPENDIX F RELEVANT CONDITIONS

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

4 of 73


1.0

INTRODUCTION As part of the City Rail Link (CRL) works, the existing Nikau Street stormwater main is required to be realigned to enable the future construction of the CRL tunnels. This Construction Noise and Vibration Delivery Work Plan (CNV DWP) has been prepared to manage the adverse effects relating to construction noise and vibration during the construction of the Project. It is required under Condition 36 of the CRL designation. The objective of this CNV DWP is to provide for the development and implementation of the identified best practicable option to avoid, remedy or mitigate the adverse effects on receivers of noise and vibration resulting from construction of the Project. It builds on the Marshall Day Acoustics Assessment of Construction Noise and Vibration (report Rp 001 r4.0 2016651A, 9 August 2017). Some construction activities are predicted to exceed the Project performance standards. Where compliance cannot be achieved within the CRL designation, site specific management plans will be implemented. Site Specific Construction Noise Management Plans (SSCNMP) and Site Specific Construction Vibration Management Plans (SSCVMP) are required under Conditions 37, 38, 39 and 40 of the CRL designation to detail the best practicable option to avoid, remedy or mitigate adverse effects on a receiver resulting from noise or vibration that does not comply with the Project Noise and Vibration Standards. This CNV DWP is a live document that will be reviewed and updated during the course of the Project to reflect material changes. Any such changes to this CNV DWP must be submitted to Auckland Council (AC) for review at least 10 working days prior to any on-site activity reliant upon the change commencing. A formal review process is described in Section 9.0 of this DWP. Potentially affected parties have been identified in this DWP and an outline SSCNMP or SSCVMP for each is contained in Appendix D. A glossary of terminology is included in Appendix A.

2.0

PROJECT DESCRIPTION

2.1

Overview The full project description is included in the CEMP. In summary, a pipe jacking machine is proposed to drive a replacement stormwater main between the Water Street (drive) and Nikau Street (retrieval) sites. Spoil is proposed to be removed from site during the day and stockpiled overnight. In addition to these main works, the following ancillary works will be required: •

Demolition of 26 Mt Eden Road

•

Demolition of 16 -18 Ruru Street (to enable construction of reception shaft)

•

Construction of a cavern of approximately 7m to connect the realigned section of pipe from the Nikau Street site to the existing stormwater main at the Ruru Street site

•

A mined connection to the existing pipe at Water Street

•

Three new connections are required to connect the realigned Nikau Street Stormwater Main to the existing stormwater mains within Ruru Street at the corner of Nikau Street and Ruru Street.

•

In addition, three permanent access shafts are proposed within the reception and launch shafts during reinstatement at Water Street, Mount Eden Road and Nikau Street to accommodate access associated with the ongoing operation and maintenance of the realigned Nikau Street Stormwater Main.

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

5 of 73


•

Three new Gross Pollutant Traps (GPT’s) on Boston Road (two) and Normanby Road (one). These works will require excavating pits of approximately 5 m wide, 5 m long and 7.9 m deep to install new 2.5 m wide GPTs and manholes.

The extent and locations of the shaft and work sites are shown in Figure 1 and Figure 2. Figure 1: Project extent and work sites1 Mt Eden Rd Access Shaft

Nikau St Retrieval Shaft Water St Drive Shaft Figure 2: Project extent and work sites2

GPT3

GPT2 GPT1

1

CRL-MTE-UTI-000-DRG-1101[7.0]

2

CRL-MTE-UTI-000-DRG-1961[1.0]

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

6 of 73


2.2

Programme The works will take up to 13 months, commencing March 2018. The construction sequence is summarised as follows and detailed in section 2.0 of the CEMP: 1. Building demolition 2. Construct new Mount Eden Road access shaft 3. Construct new Water Street launch shaft 4. Launch pipe jack from Water Street shaft driving towards Nikau Street Shaft 5. Construct new Nikau Street reception shaft and retrieve pipe jack 6. Connect new pipe to existing stormwater main and reinstate worksites The majority of construction works will occur during the daytime, with the exception of pipe jacking at the Water Street site, which is programmed to work through the night, 6 days per week. Activities with potential to generate significant levels of noise and vibration are primarily as follows:

2.3

•

Demolition of the building structure at 26 Mt Eden Road (2-week period in May 2018)

•

Demolition of the building structure at 16 -18 Ruru Street (2-week period in April 2018)

•

Rock breaking of the retrieval shaft at 16 -18 Ruru Street (5-week period in July/August 2018)

•

Sheet piling to provide temporary shoring for the GPT sites (1-2 days per site during installation and 1 day per site for removal between April and June 2018)

•

Pavement / concrete cutting will be required for short periods (circa a few hours in duration) on a number of occasions during the site setup phase at each worksite. The number of periods and duration of each period will be minimised and communicated to stakeholders in advance.

Key Personnel This CNV DWP has been prepared by Craig Fitzgerald from Marshall Day Acoustics, a Member of the Acoustical Society of New Zealand (MASNZ). The key personnel responsible for this CNV DWP are detailed in Table 1. The Noise and Vibration Monitoring Manager will be responsible for implementing this CNV DWP. The Monitoring Manager will receive suitable training from the Specialist Noise and Vibration Advisor. Table 1: Key Personnel Contact Information Role

Name

Organisation

Phone

Email

Construction Manager

Graeme Inglis

MBJV

027 455 7299

ginglis@marchcon.co.nz

Communications Manager

Graeme Inglis

MBJV

027 455 7299

ginglis@marchcon.co.nz

Noise & Vibration Monitoring Manager

Tony Sage

MBJV

022 584 7285

tsage@carchcon.co.nz

Specialist Noise & Vibration Advisor

Craig Fitzgerald

Marshall Day Acoustics

09 373 7822 021 534 899

craig.fitzgerald@marshallday.co.nz

Compliance and Monitoring Officer

Laura Scaife

Auckland Council

09 377 3107 021 828 369

laura.scaife@aucklandcouncil.govt.nz

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

7 of 73


3.0

PERFORMANCE STANDARDS

3.1

Noise

3.1.1 CRL Designation Conditions The relevant Project Construction Noise Standards in CRL designation Condition 31 are summarised in Table 2 (overleaf). Rock blasting is not required, so condition 32 is not relevant. Construction noise shall be measured and assessed in accordance with the provisions of New Zealand Standard NZS 6803:1999 “Acoustics - Construction Noise”. These noise limits apply at 1m from the most exposed façade of a receiver. If any construction activity cannot practicably comply with these limits, it must be mitigated as far as practicable using the measures outlined in this CNV DWP. Table 2: CRL Designation Condition 31.1 - Construction Noise Limits relating to NoR 6

Receiver Type

Occupied commercial and industrial buildings (including offices)

Sensitive Noise and Vibration Receivers (excluding offices)

Monday to Saturday

Sundays and Public Holidays

0700 – 2200

0700 – 2200

75 dB LAeq

75 dB LAeq

75 dB LAeq

75 dB LAeq

60 dB LAeq

60 dB LAeq

90 dB LAFmax

75 dB LAFmax

75 dB LAFmax

Early Childhood Education Centres (whilst occupied during normal opening hours) Bear Park Early Childhood Education Centre at 32 Akiraho Street (whilst occupied during normal opening hours)

At all other times 2200 – 0700

35 dB LAeq in sleeping areas

35 dB LAeq in sleeping areas 65 dB LAeq in outdoor playing areas

3.1.2 Site Specific Construction Noise Management Plans Any predicted or measured exceedance from activities occurring in the CRL designation must have a SSCNMP in accordance with CRL designation Condition 31, except with reference to condition 37.2 where the exceedance is less than 5 decibels and does not exceed: •

0700-2200: 1 period of up to 2 consecutive weeks in any 2 months; or

•

2200-0700: 1 period of up to 2 consecutive nights in any 10 days.

For predicted exceedances of less than 5 decibels, monitoring shall be undertaken to confirm the actual noise levels (refer Section 7.1 of this DWP). The objective of a SSCNMP is to detail the best practicable option(s) to avoid, remedy or mitigate adverse effects on a receiver resulting from construction noise that does not comply with CRL designation Condition 31. SSCNMPs shall identify the matters outlined in CRL designation Condition 37, summarised as follows: •

The relevant activity, its timing, duration and predicted magnitude of exceedance (refer to Section 4.1 of this DWP);

•

A summary of the communication and consultation undertaken with the receiver; and

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

8 of 73


•

The specific methods or measures employed to mitigate the noise effects (refer to Section 5.0 and this DWP).

A Site Specific plan may address both construction noise and vibration, in which case it would be a SSCNVMP. Site specific management plans are included in Appendix D.

3.2

Vibration

3.2.1 Building Damage The relevant Project Construction Vibration (building damage) Standards in CRL designation Condition 33 are summarised in Table 3. Note that there are no heritage or sensitive structures identified in close proximity to the work sites or TBM alignment. Construction vibration shall be measured and assessed in accordance with German Standard DIN 4150-3:1999. If any construction activity cannot practicably comply with these limits, it must be mitigated as far as practicable using the measures outlined in this CNV DWP. Table 3: Project Construction Vibration Limits (Building Damage) Short-term (transient) vibration1

Type of Structure

PPV at the foundation at a frequency of

Commercial/

Long-term (continuous) vibration PPV at horizontal plane of highest floor

PPV at horizontal plane of highest floor

1-10Hz

10-50Hz

50-100Hz

(mm/s)

(mm/s)

(mm/s)

(mm/s)

(mm/s)

20

20 – 40

40 – 50

40

10

5

5 – 15

15 – 20

15

5

Industrial Residential/ School Note: 1.

Standard DIN 4150-3:1999 defines short-term (transient) vibration as “vibration which does not occur often enough to cause structural fatigue and which does not produce resonance in the structure being evaluated”. Long-term (continuous) vibration is defined as all other vibration types not covered by the short-term vibration definition.

3.2.2 Amenity The relevant Project construction vibration (amenity) standards are contained in CRL designation Condition 34. Construction vibration shall not exceed: •

35 dB LAeq(15min) and 0.3 mm/s PPV in bedrooms between 2200 – 0700hrs

•

1mm/s in dwellings 2mm/s in retail and office spaces between 2200 – 0700 hrs

This requirement is to be applied only when a complaint from a building occupant has been received.

3.2.3 Site Specific Construction Vibration Management Plans The objective of a SSCVMP is to detail the best practicable option to avoid, remedy or mitigate adverse effects on a receiver resulting from construction vibration that does not comply with CRL designation Conditions 33 or 34, or in response to other concerns or complaints in accordance with

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

9 of 73


CRL designation Condition 17. SSCVMPs shall identify the matters outlined in CRL designation Condition 38, summarised as follows: •

The relevant activity, its timing, duration and predicted magnitude of exceedance (refer to Section 4.2 of this DWP);

•

A summary of the communication and consultation undertaken with the receiver; and

•

Site specific vibration criteria, methods or measures that addresses the issue(s) of concern (i.e. building damage, amenity or sensitive equipment).

A Site Specific plan may address both noise and vibration, in which case it would be a SSCNVMP. Project site specific management plans are included in Appendix D.

3.3

MediaWorks MediaWorks is a Notable Receiver, with specific noise and vibration requirements contained in Conditions 16, 35, 39 and 40. The construction methodology for the Nikau Street shaft has been planned to avoid exceedances of the relevant construction noise and vibration levels at MediaWorks. Regardless, a SSCNVMP for MediaWorks is required by Condition 40 and is included in Appendix D18. Mitigation, management, communication and consultation protocols applying to the MediaWorks buildings (excluding Studio 1), are included in this CNV DWP. However, Studio 1 specific performance standards, predicted levels and monitoring requirements are contained in Appendix D18.

4.0

PREDICTED CONSTRUCTION NOISE AND VIBRATION LEVELS

4.1

Noise Indicative unmitigated sound levels for the proposed equipment are presented in Table 4 at various receiver set back distances. This table shall be used to inform when and what equipment will require mitigation or management and shall be kept up to date when new information becomes apparent through noise monitoring or other means. Note that the pipe jacking machine is considered for vibration only. Table 4: Indicative noise levels from proposed equipment at 1m from a façade (unmitigated)

Equipment

Typical Operating Sound Power (dB LwA)

Noise Level (dB LAeq) at a distance (m) 5

10

20

50

Large excavator (30T) mounted breaker

121

102

96

90

82

Sheet piling (GPT shoring)

116

97

91

85

77

Circular saws

115

96

90

84

76

Rotary drilling rig

114

95

89

83

75

Large rotary bored piling rig

112

93

87

81

73

Small excavator (1.5T) mounted breaker

111

92

86

80

72

Plate compactor (backfilling)

108

89

83

77

69

Hydro-vac (utilities excavation)

107

88

82

76

68

Directional drill

105

86

80

74

66

20T Excavator

103

84

78

72

64

Mini soldier piling rig

103

84

78

72

64

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

10 of 73


Equipment

Typical Operating Sound Power (dB LwA)

Noise Level (dB LAeq) at a distance (m) 5

10

20

50

Concrete truck and pump

103

84

78

72

64

Mobile crane

99

80

74

68

60

Desanding Unit

98

79

73

67

66

Water treatment plant (silt buster)

93

74

68

62

54

Large genset (acoustic/containerised)

93

74

68

62

54

Road truck (idling)

84

65

59

53

45

Noise contours for particularly noisy activities at each site and night works are included in Appendix B. Based on the modelling results, SSCNMPs are predicted to be required for the following buildings (note those with strikethrough are no longer required by this version of this DWP but are still included in Appendix B for reference):

4.2

•

24 Mt Eden Road (Mt Eden Road Site)

•

32 Nikau Street SSCNMP (Nikau Street Site)

•

36-38 Nikau Street SSCNMP (Nikau Street Site)

•

10 Ruru Street SSCNMP (Nikau Street Site)

•

27-29 Shaddock Street SSCNMP (Nikau Street Site)

•

33 Shaddock Street SSCNMP (Nikau Street Site)

•

11 Water Street SSCNMP (Water Street Site)

•

12 Boston Road SSCNMP (Water Street Site)

•

41 – 43 Boston Road SSCNMP (GPT1)

•

45 Boston Road SSCNMP (GPT2)

•

47 Boston Road SSCNMP (GPT1 and GPT2)

•

24 Normanby Road (GPT3)

•

39 Boston Road (GPT1)

•

55 Boston Road (GPT2)

•

32 Normanby Road (GPT3)

•

61 Normanby Road (GPT3)

Vibration The risk radii for high vibration sources are listed below in Table 5. The table indicates the distance inside which there is a risk of cosmetic building damage (e.g. plaster cracking). The table should be maintained up to date and be representative of the equipment on-site and include the results of onsite vibration monitoring. A more detailed vibration regression curve for the identified vibration sources is included in Appendix C.

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

11 of 73


Table 5: Indicative setback distances (m) to comply with vibration limits at building foundations Emission Risk Radius (m) Vibration Source Commercial/Industrial

Residential

Rock breaker

7

10

Sheet piling (GPT shoring)

4

11

Pipe jacking machine

2

4

Building demolition also has the potential to produce high levels of vibration, generally from one-off events, such as dropping of concrete or other heavy items. However, the buildings to be removed are low rise, with concrete block walls and timber or steel framing. As such high vibration events will largely be avoided. However residual vibration will be avoided by nibbling concrete and lowering the structure in parts rather than pulling it down in large panels. Accordingly, compliance is considered to be readily achievable. Based on the equipment listed and the proposed location of this equipment during the various construction phases of the Project, SSCVMPs will be required for the following buildings (included in Appendix D): •

31 Shaddock Street (pipejacking)

5.0

MITIGATION AND MANAGEMENT

5.1

Training All staff will participate in an induction training session when they commence work on the Project. The induction will include a briefing on this CNV DWP, with attention given to the following matters: •

Roles and responsibilities for management of noise and vibration matters.

•

Construction noise and vibration limits.

•

Information about noise and vibration sources on-site.

•

Noise and vibration mitigation and management procedures.

•

The sensitivity of receivers to noise and vibration (including MediaWorks), and any operational requirements and constraints identified through communication and consultation.

•

Complaints management procedures.

Awareness of current noise and vibration matters on, or near active worksites, will be addressed during site meetings and/or ‘toolbox’ training sessions.

5.2

Construction Hours •

Normal construction hours are Monday to Saturday, 0700 – 1900 hrs

•

Piling and road cutting hours shall be restricted to Monday to Saturday, 0700 – 1900 hrs in accordance with condition 36.3 (b)

•

Rock breaking at the Nikau Street site shall initially be timed to occur outside Sensitive Times to enable demonstration of compliance with Condition 35.2 prior to any expansion of the works period. Sensitive Times are defined in Condition 35.2 as 0600-0900 hrs, 1200-1230 hrs, 17301930 hrs 2230-2330 hrs on weekdays, 1730 – 1900 hrs on weekends and a defined two-week period spanning Christmas Day and New Year’s Day.

•

The pipe jacking support activities at the Water Street launch site will operate 24 hours, 6 days per week.

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

12 of 73


5.3

Mechanical Plant Selection Some activities have the potential to exceed the Project construction noise and vibration limits at close receiver distances (e.g. piling, demolition). It is essential that appropriate mitigation and management measures are identified and employed in advance of the works to avoid exceedances. When selecting construction equipment, where practicable:

5.4

•

Quiet and low vibration construction methods will be used in favour of noisy/high vibration construction methods (e.g. bored piling rather than vibrated sheet piling)

•

Equipment will be well maintained

•

Exhaust silencers will be fitted

•

Fit or upgrade engine covers in consultation with equipment manufacturer

•

Substitute diesel engines with electric motors

General Mitigation Measures Best Practical Option (BPO) mitigation will be implemented throughout the construction programme to avoid exceedances. This will include, but not be limited to the following: •

Keep the construction time near noise sensitive areas to a minimum

•

Avoid unnecessary noise, such as shouting, the use of horns, loud site radios, rough handling of material and equipment, and banging or shaking excavator buckets

•

Avoid metal on metal contact where practicable by minimising drop height of materials, such as during the erection and dismantling of scaffold and the loading and unloading of trucks

•

Avoid alternating rotation of the bored piling auger to loosen spoil into the muck bin. The kelly bit connection creates very loud banging that often results in noise complaints. It is understood this action is generally unnecessary for auger use (soft ground) but is necessary if a coring barrel is required to drill through hard ground or obstructions.

•

Tonal reversing alarms shall be prohibited on site. Suitable alternatives may include flashing lights, broadband audible alarms or reversing cameras inside vehicles

•

Mitigate track squeal from tracked equipment, such as excavators and piling rigs. This may include tensioning and watering or lubricating the tracks regularly

•

Avoid high engine revs where practicable through appropriate equipment selection and turn engines off when idle / parked

•

Avoid steep internal haul routes and keep the road surface smooth and well maintained

•

Maximise the distance between the noise source and the nearest sensitive receiver by positioning fixed plant away from sensitive receivers, or orienting machinery to maximise the distance between the engine exhaust and the nearest sensitive building façade where practicable (e.g. excavators and piling rigs)

•

Crane and secure loads using straps in preference to chains where safe and practicable

•

Utilise power from the national grid in preference to generators where practicable

•

For concrete/rock breakers, match the chisel/tip to the material to be broken and avoid ‘blank’ firing by engaging the material before commencing and stopping before it fires through the material

•

Where plant is identified as being particularly noisy and/or vibration inducing, action will be taken to reduce emissions. This may involve the fitting of mitigation devices, such as silencers, enclosures or isolation pads

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

13 of 73


5.5

•

Utilise noise barriers and enclosures where effective (refer Section 5.5)

•

Implement further measures identified through communication and consultation with sensitive receivers (refer Section 6.1)

•

Undertake noise and vibration monitoring to confirm compliance, or identify high noise and/or vibration machinery (refer Section 7)

Noise Barriers and Enclosures Noise barriers would typically reduce levels at ground floor receivers by 10 decibels. Above the ground floor, where there is line of sight to the activity, barriers will provide little acoustic benefit. The barriers and/or enclosures will be installed prior to the identified works commencing. The following guidelines must be incorporated in the design and utilisation of noise barriers: •

Rigid noise barriers with a minimum surface mass of 6kg/m2 (e.g. 12mm plywood or 6mm fibre cement), or flexible temporary noise curtains (e.g. Soundex ‘performance series' or Flexshield ‘Sonic Curtains with 4kg/m2 mass loaded vinyl backing’)

•

Positioned to block line of sight between the construction activity and receiving position(s), with site perimeter hoardings, typically at least 2m high

•

Positioned as close as practicable to the noisy construction activity

•

Abutted or overlapped to provide a continuous screen

The following guidelines must be incorporated in the design and utilisation of noise enclosures (note that enclosures surround the noise source on all sides (including a roof) as opposed to a barrier which is a single leaf structure: •

Enclosures will be used where a noise barrier is not sufficient to achieve compliance with the noise limits and it is practicable to do so (e.g. stationary plant such as compressors, pumps, generators, air tools and road cutting activities)

•

Enclosures shall be designed by a suitably qualified and experienced acoustic specialist

•

Consideration must be given to air supply or other requirements as needed. These elements may require acoustic treatment too

6.0

COMMUNICATION

6.1

Communication Overview Communication with Project stakeholders in relation to construction noise and vibration impacts is described in the Project Communication and Consultation Plan. A summary of communication with sensitive receivers will be maintained in Appendix E of this CNV DWP, including a clear explanation of where any comments from sensitive receivers have not been incorporated, and the reasons why not, as well as any outstanding issues or disputes. As a minimum, the following communication shall be undertaken: •

Written notification of the Project description shall be provided to MediaWorks and all property occupiers within 50m of a worksite and 15m of the pipe jacking alignment to raise awareness of the Project, the required construction works and their duration in their vicinity. This should be undertaken at least 20 working days prior to the commencement of works on site

•

The Communications Manager shall advise any affected parties of construction activities that are predicted to exceed the limits in Section 4 following the application of BPO mitigation identified in Section 5. Where avoidance of exceedances is impractical, consultation shall be undertaken to avoid significant adverse effects

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

14 of 73


6.2

•

The Communications Manager shall provide monthly updates of monitoring and project progress to affected parties

•

The Communications Manager shall undertake communications with MediaWorks in accordance with CRL condition 16. This shall include weekly updates of monitoring and project progress to MediaWorks (unless otherwise agreed with MediaWorks). In the event of breaking news, MediaWorks is to advise the Communications Manger as soon as possible. The contractor shall modify their activities as soon as is practicable with specific regard to safety to ensure compliance with the standards in CRL condition 35.2.

•

The Communications Manager shall address any concerns and complaints regarding construction noise and vibration in accordance with Section 6.2. When discussing vibration concerns, it is important to convey that vibration can be felt at levels far below those that pose even the smallest risk of building damage

Complaints Response The contact name and phone number of the Communications Manager, to which complaints can be directed, shall be clearly included in any written notification and on-site signage. Any construction noise and/or vibration complaint shall be recorded in a complaints file, and an investigation shall be undertaken involving the following: •

Identification of sources of concern, and measuring or estimating noise and/or vibration levels at the time of the complaint

•

A hotline phone/text number shall be established to receive complaints. Acknowledge receipt of the concern or complaint. An initial response shall be undertaken within 8 hours of receiving a complaint, and resolved as soon practicable. If a reasonable complaint relates to building damage or sleep disturbance, inform the on-duty site manager as soon as practicable to cease works pending the investigation

•

Reporting the findings and recommendations to the Construction Manager

•

Actions and time taken to close-out complaint

•

Communication with the complainant

•

Reporting of the investigation in the complaints file

A record of all concerns and/or complaints received shall include: •

The name of the person(s) who raised the concern or complaint (unless they elect not to provide this) and details of the concern or complaint

•

Where practicable, weather conditions at the time of the concern or complaint, including wind direction and cloud cover if the complaint relates to noise

•

Known construction activities at the time and in the vicinity of the complainant during the concern or complaint period

•

Remedial actions undertaken (if any) and the outcome of these, including monitoring of the activity

7.0

MONITORING

7.1

Noise Construction noise shall be measured and assessed:

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

15 of 73


•

By a suitably qualified acoustics expert (e.g. Member of the Acoustical Society of New Zealand) and in accordance with the requirements of New Zealand Standard NZS 6803: 1999 “Acoustics Construction Noise”

•

During first occurrence on-site of sheet piling, rock breaking, night works and in response to reasonable noise complaint being received

•

At one metre from the most affected building façade, or, if this position is not accessible, at an equivalent position where practicable. If this is not possible, measured noise levels shall be undertaken at a proxy position and adjusted for distance and façade reflections as appropriate

•

For a representative duration not less than 15 minutes and not greater than 60 minutes. The noise level shall be reported with the measurement duration, e.g. 65 dB LAeq (15min)

•

The monitoring results shall be used to update Table 4 and made available to Council

A flow chart showing the process for attended noise monitoring is included Figure 3. Further noise monitoring requirements are detailed in Appendix D18 for MediaWorks Studio 1. Figure 3: Noise Monitoring Flow Chart Undertake attended noise monitoring (Section 7.1): • • • •

During the first use of high noise equipment (Section 4.1) In response to a reasonable complaint (Section 6.2) To verify an exceedance (Section 7.1) As required by an SSCNMP (Appendix D)

Comply with the project standards? (Section 3.1)

No

Notify Noise & Vibration Monitoring Manager and review mitigation and management strategies to ensure BPO (Section 5)

Yes Can project standards be practically achieved?

Yes

Identified mitigation and management opportunities

Yes

Revise construction methodology

Does the receiver qualify for a SSCNMP? (CRL 37)

No

No

In response to a previous noncompliant measurement?

Yes

7.2

No

No

Yes Prepare SSCNMP in consultation with the affected parties (Appendix D)

Submit report(s) to Noise & Vibration Monitoring Manager within one week of action taken

Vibration Construction vibration levels shall be measured and assessed:

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

16 of 73


•

By a suitably qualified acoustics expert (e.g. Member of the Acoustical Society of New Zealand)

•

In accordance the requirements of German Standard DIN 4150-3:1999 “Structural vibration – Part 3: Effects of vibration on structures”

•

During the first use on site of sheet piling rig, rock breaking and other phases of construction when vibration has potential to exceed the building damage limits, or in response to reasonable complaint being receiver

•

At the closest building foundations

•

For a representative construction duration, measured at one second intervals

•

By a suitably qualified and experienced specialist

•

Vibration monitoring requires consent to access the building of interest.

•

The monitoring results shall be used to update Table 5 as appropriate

Re-radiated noise from construction vibration shall be measured and assessed by the Specialist Noise & Vibration Advisor (or approved representative) as follows: •

In response to a reasonable complaint being received

•

Inside the inhabited room(s) of interest, or, if this position is not accessible, in an equivalent room where practicable. If this is not possible, measured vibration levels shall be undertaken at a proxy position and adjusted for distance and building response as appropriate.

•

For a representative duration not less than 15 minutes and not greater than 60 minutes for fluctuating noise sources. A representative duration of less than 10 minutes may be suitable for steady noise sources (as determined by the monitoring engineer). The noise level shall be reported with the measurement duration, e.g. 35 dB LAeq (15min). The monitoring reports shall be used to update Appendix C of this DWP.

•

The monitoring results shall be used to update Section 4 of this DWP and made available to Council.

A flow chart showing the process for attended vibration monitoring is included as Figure 4 overleaf. Further vibration monitoring requirements are detailed in Appendix D18 for MediaWorks Studio 1.

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

17 of 73


Figure 4: Vibration Monitoring Flow Chart Undertake attended vibration monitoring (Section 7.2): • • • •

During the first use of high vibration equipment (Section 4.2) In response to a reasonable complaint (Section 6.2) To verify an exceedance (Section 7.2) As required by an SSCVMP (Appendix D)

Cosmetic Building Damage Comply with the cosmetic building damage project standards? (Section 3.2)

No

Yes

Notify Noise & Vibration Monitoring Manager, cease the activity, engage a structural engineer and undertake a building condition survey

Yes

Is the building classified as heritage?

Engage heritage expert

No

Is there damage as a result of the activity? No Amenity

Yes

Type of damage?

Structural

Cosmetic

Seek advice from structural engineer before continuing

Comply with amenity project standards? (Section 3.2)

No

Notify Noise & Vibration Monitoring Manager and review mitigation and management strategies to ensure BPO (Section 5) Yes

Yes Yes

Identified mitigation and management opportunities?

No

No

Response to a previous noncompliant measurement? Yes

Yes

Revise construction methodology

Can the project standards be practically achieved?

No

Does the receiver qualify for a SSCVMP? (CRL 38)

No

Yes Prepare SSCVMP in consultation with the affected parties (Appendix D)

Submit report(s) to Noise & Vibration Monitoring Manager within one week of action taken

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

18 of 73


7.2.1 Vibration – Cosmetic Damage The following procedures will be implemented where measured construction vibration exceeds the Project standard: •

The activity giving rise to the exceedance should cease as soon as safe and practicable to do so

•

Determine if the receiver qualifies for a SSCVMP as outlined in Section 3.2.3 of this CNV DWP

•

A detailed building condition survey will be undertaken

•

The Communications Manager will liaise with the building owner throughout this process

If damage has not occurred, then that activity can continue provided the measured vibration level is not exceeded further. If damage has occurred, then alternative construction methods should be investigated, subject to implementation of the best practicable option (BPO), and the Requiring Authority shall commit to repairing the damage within a reasonable timeframe after the construction phase ceases.

7.2.2 Vibration – Amenity In the event that a complaint is received and a measurement demonstrates exceedance of the Project vibration or reradiated noise amenity limits, the following procedures will be implemented. •

Further measurements may be required to determine the extent of the exceedance and identify the activity/activities responsible

•

Review the mitigation strategy and construction methodology to ensure BPO is applied

•

Further measurements may be required to determine the effectiveness of BPO measures and reassess the compliance status

•

Determine if the receiver qualifies for a SSCNVMP as outlined in Section 3.2.2 of this DWP

•

The Communications Manager shall liaise with affected parties as outlined in 8.0 of this DWP

8.0

AFFECTED PARTIES

8.1

Airborne Noise

8.1.1 Façade Sound Insulation The noise level received inside, for example an office or living room, will depend on the sound insulation performance of the façade (particularly the glazing) and room constants (such as the room dimensions and surface finishes). These factors can vary widely. The Construction Noise Standard (NZS 6803) recommends noise limits assessed at 1m from the external façade of a building, assuming a sound level difference of 20 decibels to sensitive receiving environments inside. For the purpose of estimating actual noise effects on a room by room basis, the predicted façade sound insulation performance of buildings can be generally categorised by the type of glazing / ventilation provision as follows: •

Sealed glazing

30 decibels sound level difference

•

Operable windows

25 decibels sound level difference

•

Open Windows

15 decibels sound level difference.

The SSCNMPs in Appendix D will use the above assumptions initially. However, they will be updated with site specific measured performance when available. Measurements in advance of the works may be practicable in some cases. In other cases, a visual inspection may provide a more informed estimate of façade performance.

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

19 of 73


8.1.2 Noise Effects ‘Noise effects matrices’ are presented in Table 6 and Table 7. They enable estimation of the construction noise level received inside, based on the external noise level and façade glazing type. The noise effects matrices are indicative only, as detailed assessment requires measurement of the actual façade performance on a space by space basis. The noise effects are categorised generally using the following colour coding: •

Green:

Acceptable

•

Orange:

Appreciable

•

Red:

Significant

To use the matrices, follow this three step process: •

Measure the external noise level at 1m from the façade, or estimate it from Section 4.1

•

Determine the category of façade glazing sound insulation performance from Section 8.1.1 of this CNV DWP or measured on-site façade sound level difference for a specific receiver location; and

•

Use the relevant lookup table to estimate the received internal noise level, and associated typical effects that may be experienced, using Table 6 and Table 7.

Table 6: Daytime noise levels in commercial & industrial buildings and habitable rooms in dwellings External Noise Level (dB LAeq)

Estimated Internal Noise Level (dB LAeq)

(refer Appendix B)

Sealed glazing (30 dB)

Operable windows (25 dB)

Open windows (15 dB)

95

65

70

80

90

60

65

75

85

55

60

70

80

50

55

65

75

45

50

60

70

40

45

55

65

35

40

50

•

< 50 dB LAeq

Typically acceptable

•

50 – 60 dB LAeq

Annoyance and reduction in work efficiency

•

> 60 dB LAeq

Difficulty holding a normal conversation and reduction in work efficiency

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

20 of 73


Table 7: Night-time noise levels in bedrooms of dwellings External Noise Level (dB LAeq)

8.2

Estimated Internal Noise Level (dB LAeq)

(refer Appendix B)

Sealed glazing (30 dB)

Operable windows (25 dB)

Open windows (15 dB)

75

45

50

60

70

40

45

55

65

35

40

50

60

30

35

45

55

25

30

40

50

20

25

35

•

< 35 dB LAeq

Typically acceptable

•

35 – 40 dB LAeq

Annoyance and sleep disturbance for some noise sensitive receivers

•

> 40 dB LAeq

Annoyance and sleep disturbance for most noise sensitive receivers

Reradiated Noise The effects can be estimated with reference to the qualitative statements from Section 8.1.

8.3

Management of Adverse Effects The following process will be implemented for any construction activity that is found to exceed the relevant construction noise and vibration conditions: •

Review the construction methodology, mitigation and management strategies to ensure they represent the BPO

•

The Communications Manager will consult with affected parties to understand their particular sensitivities, including times, activities and locations. Consultation should focus on a collaborative approach to managing the adverse effects from construction noise and vibration while works are undertaken in the vicinity. The Communications Manager (or representative) shall be available 24/7 during works periods. A record of consultation will be included in the relevant SSCNMP (refer to Appendix D) or otherwise in Appendix E as appropriate.

•

Implement measures to avoid significant adverse effects as agreed with the affected party and monitor the activity to verify the extent of any adverse effects

•

The installation of mechanical ventilation will be considered for noise sensitive receivers where external windows must be closed in order to avoid significant adverse noise effects and no alternative ventilation system is present. This will be implemented only after all other general noise management and mitigation have been deemed impracticable

•

Temporary relocation will be considered for sensitive receivers where all practicable noise and vibration management and mitigation measures have been implemented and significant adverse noise effects are predicted. This will be in exceptional cases only, and advice from the Specialist Noise and Vibration Advisor will be sought prior

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

21 of 73


9.0

CNV DWP REVIEW AND UPDATING (INCLUDING SSCNMP AND SSCNMP) In accordance with conditions 7.5 and 11, this CNV DWP will undergo a review process with the relevant CRL Community Liaison Group (CLG) and a suitably qualified independent peer reviewer before being issued. The CNV DWP (including SSCNMPs and SSCVMPs) will be updated throughout the course of the Project to reflect changes associated with construction techniques, equipment or due to unresolved complaints. The review period will be no less than annually in accordance with condition 22. The review(s) will take into consideration: •

Compliance with the CRL designation conditions

•

Any significant changes to construction activities or methods

•

Key changes to roles and responsibilities within the Project team

•

Changes in industry best practice standards

•

Results of inspections, monitoring and reporting procedures associated with the management of adverse effects during construction

•

Comments or recommendations from Auckland Council

•

Unresolved complaints and any response to complaints and remedial action taken to address the complaint

The process for updating this CNV DWP (including SSCNVMPs) as a result of a material change to the Project or the annual review, is as follows (refer to CRL designation Condition 23): •

Affected parties and the CLG must be notified of the review and any material change proposed to this DWP

•

This DWP must clearly document the comments and inputs received from affected parties in relation to any material changes, along with a clear explanation of where any comments have not been incorporated, and the reasons why not

•

Any material change proposed to this DWP shall be subject to an independent peer review as required by CRL designation Condition 11

•

Any material change proposed to this DWP relating to an adverse effect shall be submitted for approval to Auckland Council Compliance and Monitoring Officer, at least 10 working days prior to the proposed changes taking effect. If any changes are not agreed, the relevant provisions of the RMA relating to approval of outline plans shall apply

A copy of the original CNV DWP document and subsequent versions will be kept for the Project records, and marked as obsolete. Each new / updated version of the CNV DWP documentation will be issued with a version number and date to eliminate obsolete CNV DWP documentation being used. A summary of the review process will be provided annually to Auckland Council and otherwise be made available on request.

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

22 of 73


APPENDIX A GLOSSARY OF TERMINOLOGY Noise Ambient Noise

Ambient Noise is the all-encompassing noise associated with any given environment and is usually a composite of sounds from many sources near and far.

A-weighting

A frequency filter which is applied to a measurement of sound so as to more closely approximate the frequency bias of the human ear.

dB

Decibel – the basic measurement unit of sound. It is a logarithmic ratio of measured sound pressure level with respect to a reference level of 20 micropascals.

LAeq(T)

The A-weighted, time averaged sound level (on a logarithmic/energy basis) over the measurement period T (e.g. between 10 and 60 minutes).

LAFmax

The maximum A-weighted sound level recorded during the measurement period. Measured with fast time weighting i.e. a 125 millisecond time constant

Noise

A sound that is unwanted by, or distracting to, the receiver.

NZS 6801:2008

New Zealand Standard NZS 6801:2008 "Acoustics - Measurement of Sound"

NZS 6802:2008

New Zealand Standard NZS 6802:2008 "Acoustics - Environmental Noise”.

NZS 6803:1999

New Zealand Standard NZS 6803:1999 “Acoustics – Construction Noise”. Vibration

PPV

Peak Particle Velocity, measured in mm/s. This is the standard metric for assessing construction vibration levels.

DIN 4150-3:1999

German Standard DIN 4150-3:1999 “Structural Vibration – Part 3: Effects of vibration on structures”. This standard is generally adopted in NZ to assess building damage. General

Suitably qualified and experienced acoustic specialist

A person who has sufficient qualifications and experience in the relevant field(s) of acoustics (noise and/or vibration) to undertake robust measurements and assessments i.e. a Member of the Acoustical Society of New Zealand. Other Abbreviations

CRL

City Rail Link

CLG

Community Liaison Group

BPO

Best Practicable Option

CNV

Construction Noise and Vibration

DWP

Delivery Work Plan

SSCNMP

Site Specific Construction Noise Management Plan

SSCNVMP

Site Specific Construction Noise and Vibration Management Plan

SSCVMP

Site Specific Construction Vibration Management Plan

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

23 of 73


APPENDIX B NOISE LEVEL PREDICTIONS Figure 1A: Mt Eden Road Site – Piling on Rd Figure 1B: Mt Eden Road Site – Piling On Site Figure 2: Mt Eden Road Site – Night Works Figure 3: Nikau Street Site – Rotary Drilling Figure 4: Nikau Street Site – Rock Breaking Figure 5: Water Street Site – Piling Figure 5A: Water Street Site – Night Works Figure 6: GPT1 – Sheet Piling Figure 7: GPT2 – Sheet Piling Figure 8: GPT3 – Sheet Piling Figure 9: GPT3 – Hydro Vac

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

24 of 73


3D Perspective looking NE

3D Perspective looking SW

Rotary Drilling Rig

Excavator loading idle truck

Noise Level (dB LAeq) Key:

55 60 65 70 75

Noise source Buildings Property boundary 2m acoustic hoardings

Client: MBJV

City Rail Link - Mt Eden Stormwater Diversion Path: J:\JOBS\2016\201608cn\07 SoundPLAN\CRL Mt Eden Stormwater Filename: Nikau St - Piling.SGS, Prepared: cmf, Date: 10 April 2018 The noise contours in this Figure were obtained by computer interpolation between calculated grid points. There is an Figure 3: Nikau St Site - Rotary Drilling interpolation accuracy of +/- 1.5dB. For precise noise levels at specific location, refer to point receiver calculations.

>=

Scale @ A3 1:1000 0

5 10

20

30

40

50 m

60 65 70 75 80 80


3D Perspective looking NE

3D Perspective looking SW

Excavator with rock breaker 5m below ground level

Excavator loading idle truck

Noise Level (dB LAeq) Key:

55 60 65 70 75

Noise source Buildings Property boundary 2m acoustic hoardings

Client: MBJV

City Rail Link - Mt Eden Stormwater Diversion Path: J:\JOBS\2016\201608cn\07 SoundPLAN\CRL Mt Eden Stormwater Filename: Nikau St - Rock Breaking.SGS, Prepared: cmf, Date: 10 April 2018 The noise contours in this Figure were obtained by computer interpolation between calculated grid points. There is an Figure 4: Nikau St Site - Rock Breaking interpolation accuracy of +/- 1.5dB. For precise noise levels at specific location, refer to point receiver calculations.

>=

Scale @ A3 1:1000 0

5 10

20

30

40

50 m

60 65 70 75 80 80


3D Perspective looking SE

3D Perspective looking NW

Idle Truck

Bored Piling Rig Excavator

Noise Level (dB LAeq) Key:

55 60 65 70 75

Noise source Buildings Property boundary 2m acoustic hoardings

City Rail Link - Mt Eden Stormwater Diversion Figure 5: Water St Site - Piling

Client: MBJV Path: J:\JOBS\2016\201608cn\07 SoundPLAN\CRL Mt Eden Stormwater Filename: Water St Shaft - Piling.SGS, Prepared: cmf, Date: 10 April 2018 The noise contours in this Figure were obtained by computer interpolation between calculated grid points. There is an interpolation accuracy of +/- 1.5dB. For precise noise levels at specific location, refer to point receiver calculations.

>=

60 65 70 75 80 80

Scale @ A3 1:1000 0

5 10

20

30

40

50 m


3D Perspective looking SE

3D Perspective looking NW

Generator Crane

Slurry Pump Generator

Desanding Unit

Noise Level (dB LAeq)

Key: Noise source

55 60 65 70 75

Desanding Unit Buildings Property boundary 2m acoustic hoardings

City Rail Link - Mt Eden Stormwater Diversion Figure 5A: Water St Site - Night Works

Client: MBJV Path: J:\JOBS\2016\201608cn\07 SoundPLAN\CRL Mt Eden Stormwater Filename: Water St Shaft - Night Works.SGS, Prepared: cmf, Date: 10 April 2018 The noise contours in this Figure were obtained by computer interpolation between calculated grid points. There is an interpolation accuracy of +/- 1.5dB. For precise noise levels at specific location, refer to point receiver calculations.

>=

Scale @ A3 1:1000 0

5 10

20

30

40

50 m

60 65 70 75 80 80


Car Park

Sheet Piling GPT1

3D Perspective looking NE GPT2

Car Park

3D Perspective looking SE

GPT3

Noise Level (dB LAeq) Key:

55 60 65 70 75

Noise source Buildings Property boundary 2m acoustic hoardings

City Rail Link - Mt Eden Stormwater Diversion Figure 6: GPT1 - Sheet Piling (temp shoring)

Client: MBJV Path: J:\JOBS\2016\201608cn\07 SoundPLAN\CRL Mt Eden Stormwater Filename: GPT1 - Concrete Cutting.SGS, Prepared: cmf, Date: 9 April 2018 The noise contours in this Figure were obtained by computer interpolation between calculated grid points. There is an interpolation accuracy of +/- 1.5dB. For precise noise levels at specific location, refer to point receiver calculations.

>=

Scale @ A3 1:1000 0

5 10

20

30

40

50 m

60 65 70 75 80 80


Car Park

GPT1

3D Perspective looking NE Sheet Piling GPT2

Car Park

3D Perspective looking SE

GPT3

Noise Level (dB LAeq) Key:

55 60 65 70 75

Noise source Buildings Property boundary 2m acoustic hoardings

City Rail Link - Mt Eden Stormwater Diversion Figure 7: GPT2 - Sheet Piling (temp shoring)

Client: MBJV Path: J:\JOBS\2016\201608cn\07 SoundPLAN\CRL Mt Eden Stormwater Filename: GPT2 - Concrete Cutting.SGS, Prepared: cmf, Date: 9 April 2018 The noise contours in this Figure were obtained by computer interpolation between calculated grid points. There is an interpolation accuracy of +/- 1.5dB. For precise noise levels at specific location, refer to point receiver calculations.

>=

Scale @ A3 1:1000 0

5 10

20

30

40

50 m

60 65 70 75 80 80


Car Park

GPT1

3D Perspective looking SE

3D Perspective looking NE GPT2

Car Park

GPT3 Sheet Piling

Noise Level (dB LAeq) Key:

55 60 65 70 75

Noise source Buildings Property boundary 2m acoustic hoardings

Client: MBJV

City Rail Link - Mt Eden Stormwater Diversion Path: J:\JOBS\2016\201608cn\07 SoundPLAN\CRL Mt Eden Stormwater Filename: GPT3 - Concrete Cutting.SGS, Prepared: cmf, Date: 9 April 2018 noise contours in this Figure were obtained by computer interpolation between calculated grid points. There is an Figure 8: GPT3 - Sheet Piling (temp shoring) The interpolation accuracy of +/- 1.5dB. For precise noise levels at specific location, refer to point receiver calculations.

>=

Scale @ A3 1:1000 0

5 10

20

30

40

50 m

60 65 70 75 80 80


APPENDIX C VIBRATION REGRESSION CURVES

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

25 of 73


APPENDIX D SITE SPECIFIC MANAGEMENT PLANS The following site specific plans are included in this appendix: •

D1 24 Mt Eden Road SSCNMP (Mt Eden Road Site)

•

D2 32 Nikau Street SSCNMP (Nikau Street Site)

•

D3 36-38 Nikau Street SSCNMP (Nikau Street Site)

•

D4 10 Ruru Street SSCNMP (Nikau Street Site)

•

D5 27-29 Shaddock Street SSCNMP (Nikau Street Site)

•

D6 31 Shaddock Street SSCVMP (Nikau Street Site)

•

D7 33 Shaddock Street SSCNMP (Nikau Street Site)

•

D8 11 Water Street SSCNMP (Water Street Site)

•

D9 12 Boston Road SSCNMP (Water Street Site)

•

D10 41 – 43 Boston Road SSCNMP (GPT1)

•

D11 45 Boston Road SSCNMP (GPT2)

•

D12 47 – 49 Boston Road SSCNMP (GPT1 and GPT2)

•

D13 24 Normanby Road SSCNMP (GPT3)

•

D14 39 Boston Road SSCNMP (GPT1)

•

D15 55 Boston Road SSCNMP (GPT2)

•

D16 32 Normanby Road SSCNMP (GPT3)

•

D17 61 Normanby Road SSCNMP (GPT3)

•

D18 MediaWorks SSCNVMP (Nikau Street Site)

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

26 of 73


D1

24 Mt Eden Road SSCNMP (Mt Eden Road Site) This SSCNMP is no longer required because there are no night works proposed at the Mt Eden site and daytime compliance can be readily achieved.

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

27 of 73


D2

32 Nikau Street SSCNMP (Nikau Street Site)

D2.1 Introduction This draft Site Specific Construction Noise Management Plan (SSCNMP) is for Lightning Lab, a commercial building located at 32 Nikau Street. A SSCNMP is required because construction is predicted to exceed the Project Noise Standards in CRL Condition 31. This SSCNMP has been prepared in accordance with CRL Condition 37 and is Appendix D2 of the CRL Construction Noise and Vibration Delivery Work Plan (CNV DWP). It is a supplementary document that builds on the Project CNV DWP, and therefore, directly references relevant sections of the DWP to avoid repetition. The objective of this SSCNMP is to detail the best practicable option(s) to avoid, remedy or mitigate the identified adverse effects from noise exceedances at 32 Nikau Street. Section D2.2 identifies the noise sensitive spaces, the predicted or measured façade sound insulation performance, predicted noise effects and recommended consultation thresholds. As required under CRL Condition 37.5, Section D2.3 presents: •

The extent to which noise may exceed the Project Noise Standards (refer Table D2.3.1)

•

The timing and duration of any exceedance (refer Table D2.3.1)

•

The type of activity causing any exceedance (refer Table D2.3.1)

•

A summary of the communication and consultation with the receiver (refer Table D2.3.2)

•

The methods and measures to mitigate noise effects (refer Table D2.3.2)

•

A statement of why they reflect best practicable option (refer Table D2.3.2)

This draft SSCNMP has been prepared by Marshall Day Acoustics Ltd and forms part of the Construction Environmental Management Plan (CEMP) for the Project.

D2.2 Building Details Pre Construction Consultation Graeme Inglis (MBJV) and Craig Fitzgerald (Marshall Day Acoustics) met with tenant representative Phil Thompson (Aurora) on 9 April 2018. The matters discussed included an overview of the project, general project programme including 2-week windows for demolition and rock breaking activities, overview of the CNV DWP and this SSCNMP, communications triggers and protocol, building layout and identification of noise sensitive spaces. The ground floor level fronting Nikau St includes a meeting room on the north-west corner with extensive glazing and one louvred window. They were advised that the louvred window would limit the sound insulation performance across the façade, but they responded saying that there were other meeting room(s) on the eastern side of the building that could be used when noise levels were high during demolition and rock breaking. Prior communication of the timeframes for these activities was considered as an acceptable means of managing effects. Other spaces on the west side of the ground floor include a kitchen (not noise sensitive) and open plan office. The office has no windows in the concrete block façade. The noise level received in the office will be controlled by noise ingress via the roof, which is long run steel over an exposed plywood sarking ceiling. A basement level is used for car parking. A mezzanine roof and outdoor deck area is used for social purposes and is not noise sensitive. Façade Sound Insulation Performance The commercial office building at 32 Nikau Street is constructed from a mix of masonry and timber framed walls with sealed glazing. The estimated sound level difference across the façade with the This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

28 of 73


windows and doors closed is 25 decibels. On this basis, the predicted construction noise effects can be determined from Table 7 in Section 8.1.2. Consultation Trigger Level In addition to regular communication, specific consultation should be undertaken prior to construction works that are predicted to exceed 75 dB LAeq at the façade during the day. The consultation process is set out in Section 8.3 of the CNV DWP.

D2.3 Activity Detail and Consultation Table D2.3.1 details activities that are predicted to exceed the noise limits in CRL Condition 31 and the predicted noise effects. Table D2.3.2 provides a summary of consultation with the property owners and/or tenants representatives and methods and measures to mitigate noise effects and a statement of why they reflect best practicable option. Table D2.3.1: Activity Detail (Noise) ** indicative examples only** #

Activity Details

Predicted Noise Effects

1

Activity Period Duration Days Hours

Piling XX 201X – YY 201X X months Monday to Saturday X – Y hours

Location: External noise level: Façade performance: Internal noise level: Potential noise effects:

West façade 75 – 80 dB LAeq 25 decibels sound level difference 50 – 55 dB LAeq Annoyance and reduction in work efficiency

2

Activity Period Duration Days Hours

X X X X X

Receiver: Location: External noise level: Façade performance: Internal noise level: Potential noise effects:

X X X X X X

Table D2.3.2: Consultation **indicative examples only** #

Details

1

Receiver Date Name Phone Email CRL rep

Matters discussed Owner DD/MM/YY X X X X

A. Employ additional local hoardings and/or enclosures around noisy plant if non-compliant and practicable B. Communications Manger to liaise and provide monitoring results and notification of upcoming works C. Manage unnecessary impact sounds, e.g. careful handling and by using strops in place of chains Conclusion: Considered to be the BPO because it considers the needs of the stakeholder and mitigates and manages the noise levels as far as practicable.

2

Receiver Date Name Phone Email CRL rep

Tenant DD/MM/YY X X X X

A. B. C. BPO Conclusion:

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

29 of 73


D3

36-38 Nikau Street SSCNMP (Nikau Street Site)

D3.1 Introduction This draft Site Specific Construction Noise Management Plan (SSCNMP) is for a warehouse located at 36-38 Nikau Street. A SSCNMP is required because construction is predicted to exceed the Project Noise Standards in CRL Condition 31. This SSCNMP has been prepared in accordance with CRL Condition 37 and is Appendix D3 of the CRL Construction Noise and Vibration Delivery Work Plan (CNV DWP). It is a supplementary document that builds on the Project CNV DWP, and therefore, directly references relevant sections of the DWP to avoid repetition. The objective of this SSCNMP is to detail the best practicable option(s) to avoid, remedy or mitigate the identified adverse effects from noise exceedances at 36-38 Nikau Street. Section D3.2 identifies the noise sensitive spaces, the predicted or measured façade sound insulation performance, predicted noise effects and recommended consultation thresholds. As required under CRL Condition 37.5, Section D3.3 presents: •

The extent to which noise may exceed the Project Noise Standards (refer Table D3.3.1)

•

The timing and duration of any exceedance (refer Table D3.3.1)

•

The type of activity causing any exceedance (refer Table D3.3.1)

•

A summary of the communication and consultation with the receiver (refer Table D3.3.2)

•

The methods and measures to mitigate noise effects (refer Table D3.3.2)

•

A statement of why they reflect best practicable option (refer Table D3.3.2)

This draft SSCNMP has been prepared by Marshall Day Acoustics Ltd and forms part of the Construction Environmental Management Plan (CEMP) for the Project.

D3.2 Building Details Pre Construction Consultation **TBC** Summarise meeting(s), including information on building layout, noise sensitive spaces and the identification of specific tenant sensitivities that require further investigation. Façade Sound Insulation Performance**TBC** The industrial warehouse at 36-38 Nikau Street is constructed from masonry blockwork, with four steel rolling doors on the western façade and a steel profiled roof. The estimated sound level difference across the façade with the windows and doors closed is 25 decibels. On this basis, the predicted construction noise effects can be determined from Table 7 in Section 8.1.2. Consultation Trigger Level **TBC** In addition to regular communication, specific consultation should be undertaken prior to construction works that are predicted to exceed 75 dB LAeq at the façade during the day. The consultation process is set out in Section 8.3 of the CNV DWP.

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

30 of 73


D3.3 Activity Detail and Consultation Table D3.3.1 details activities that are predicted to exceed the noise limits in CRL Condition 31 and the predicted noise effects. Table D3.3.2 provides a summary of consultation with the property owners and/or tenants representatives and identifies methods and measures to mitigate noise effects and a statement of why they reflect best practicable option. Table D3.3.1: Activity Detail (Noise) ** indicative examples only** #

Activity Details

Predicted Noise Effects

1

Activity Period Duration Days Hours

Piling XX 201X – YY 201X X months Monday to Saturday X – Y hours

Location: External noise level: Façade performance: Internal noise level: Potential noise effects:

West façade 75 – 80 dB LAeq 25 decibels sound level difference 50 – 55 dB LAeq Annoyance and reduction in work efficiency

2

Activity Period Duration Days Hours

X X X X X

Receiver: Location: External noise level: Façade performance: Internal noise level: Potential noise effects:

X X X X X X

Table D3.3.2: Consultation **indicative examples only** #

Details

1

Receiver Date Name Phone Email CRL rep

Matters discussed Owner DD/MM/YY X X X X

A. Employ additional local hoardings and/or enclosures around noisy plant if non-compliant and practicable B. Communications Manger to liaise and provide monitoring results and notification of upcoming works C. Manage unnecessary impact sounds, e.g. careful handling and by using strops in place of chains Conclusion: Considered to be the BPO because it considers the needs of the stakeholder and mitigates and manages the noise levels as far as practicable.

2

Receiver Date Name Phone Email CRL rep

Tenant DD/MM/YY X X X X

A. B. C. Conclusion:

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

31 of 73


D4

10 Ruru Street SSCNMP (Nikau Street Site)

D4.1 Introduction This draft Site Specific Construction Noise Management Plan (SSCNMP) is for apartments located at 10 Ruru Street. A SSCNMP is required because construction is predicted to exceed the Project Noise Standards in CRL Condition 31. This SSCNMP has been prepared in accordance with CRL Condition 37 and is Appendix D4 of the CRL Construction Noise and Vibration Delivery Work Plan (CNV DWP). It is a supplementary document that builds on the Project CNV DWP, and therefore, directly references relevant sections of the DWP to avoid repetition. The objective of this SSCNMP is to detail the best practicable option(s) to avoid, remedy or mitigate the identified adverse effects from noise exceedances at 10 Ruru Street. Section D4.2 identifies the noise sensitive spaces, the predicted or measured façade sound insulation performance, predicted noise effects and recommended consultation thresholds. As required under CRL Condition 37.5, Section D4.3 presents: •

The extent to which noise may exceed the Project Noise Standards (refer Table D4.3.1)

•

The timing and duration of any exceedance (refer Table D4.3.1)

•

The type of activity causing any exceedance (refer Table D4.3.1)

•

A summary of the communication and consultation with the receiver (refer Table D4.3.2)

•

The methods and measures to mitigate noise effects (refer Table D4.3.2)

•

A statement of why they reflect best practicable option (refer Table D4.3.2)

This draft SSCNMP has been prepared by Marshall Day Acoustics Ltd and forms part of the Construction Environmental Management Plan (CEMP) for the Project.

D4.2 Building Details Pre Construction Consultation **TBC** Summarise meeting(s), including information on building layout, noise sensitive spaces and the identification of specific tenant sensitivities that require further investigation. Façade Sound Insulation Performance**TBC** The apartments at 10 Ruru Street have linear weatherboard façades with operable glazing and a steel pitched roof. The estimated sound level difference across the façade with the windows and doors closed is 30 decibels. On this basis, the predicted construction noise effects can be determined from Table 7 in Section 8.1.2. Consultation Trigger Level **TBC** In addition to regular communication, specific consultation should be undertaken prior to construction works that are predicted to exceed 80 dB LAeq at the façade during the day. The consultation process is set out in Section 8.3 of the CNV DWP.

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

32 of 73


D4.3 Activity Detail and Consultation Table D4.3.1 details activities that are predicted to exceed the noise limits in CRL Condition 31 and the predicted noise effects. Table D4.3.2 provides a summary of consultation with the property owners and/or tenants representatives and identifies methods and measures to mitigate noise effects and a statement of why they reflect best practicable option. Table D4.3.1: Activity Detail (Noise) ** indicative examples only** #

Activity Details

Predicted Noise Effects

1

Activity Period Duration Days Hours

Piling XX 201X – YY 201X X months Monday to Saturday X – Y hours

Location: External noise level: Façade performance: Internal noise level: Potential noise effects:

South façade 80 – 85 dB LAeq 25 decibels sound level difference 50 – 55 dB LAeq Annoyance

2

Activity Period Duration Days Hours

X X X X X

Receiver: Location: External noise level: Façade performance: Internal noise level: Potential noise effects:

X X X X X X

Table D4.3.2: Consultation **indicative examples only** #

Details

1

Receiver Date Name Phone Email CRL rep

Matters discussed Owner DD/MM/YY X X X X

A. Employ additional local hoardings and/or enclosures around noisy plant if non-compliant and practicable B. Communications Manger to liaise and provide monitoring results and notification of upcoming works C. Manage unnecessary impact sounds, e.g. careful handling and by using strops in place of chains Conclusion: Considered to be the BPO because it considers the needs of the stakeholder and mitigates and manages the noise levels as far as practicable.

2

Receiver Date Name Phone Email CRL rep

Tenant DD/MM/YY X X X X

A. B. C. Conclusion:

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

33 of 73


D5

27-29 Shaddock Street SSCNMP (Nikau Street Site) This SSCNMP is no longer required because the predicted noise levels in Appendix B Figure 3 are predicted to comply with 75 dB LAeq at this building facade. Furthermore, it would appear this building is no longer occupied (used for storage). Therefore, there are no noise and vibration sensitive receivers regardless.

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

34 of 73


D6

31 Shaddock Street SSCVMP (Nikau Street Site)

D6.1 Introduction This draft Site Specific Construction Vibration Management Plan (SSCVMP) is for a dwelling located at 31 Shaddock Street. A SSCVMP is required because construction is predicted to exceed the Project Vibration Amenity Standards in CRL Condition 34. This SSCVMP has been prepared in accordance with CRL Condition 38 and is Appendix D6 of the CRL Construction Noise and Vibration Delivery Work Plan (CNV DWP). It is a supplementary document that builds on the Project CNV DWP, and therefore, directly references relevant sections of the DWP to avoid repetition. The objective of this SSCVMP is to detail the best practicable option(s) to avoid, remedy or mitigate the identified adverse effects from vibration exceedances at 31 Shaddock Street. Section D6.2 identifies the noise and vibration sensitive spaces, site specific criteria, predicted effects and recommended consultation thresholds. As required under CRL Condition 38.5, Section D6.3 presents: •

The extent to which noise may exceed the Project Amenity Standards (refer Table D6.3.1)

•

The timing and duration of any exceedance (refer Table D6.3.1)

•

The type of activity causing any exceedance (refer Table D6.3.1)

•

Site Specific vibration criteria that addresses concerns regarding amenity (refer Table D6.3.1)

•

A summary of the communication and consultation with the receiver (refer Table D6.3.2)

•

The methods and measures to mitigate noise effects (refer Table D6.3.2)

•

A statement of why they reflect best practicable option (refer Table D6.3.2)

This draft SSCNMP has been prepared by Marshall Day Acoustics Ltd and forms part of the Construction Environmental Management Plan (CEMP) for the Project.

D4.2 Building Details Pre Construction Consultation **TBC** Summarise meeting(s), including information on building layout, noise and vibration sensitive spaces and the identification of specific tenant sensitivities that require further investigation. Façade Sound Insulation Performance**TBC** The vibration transfer function will need to be established once the project starts as it cannot be readily predicted with any accuracy. Consultation Trigger Level **TBC** In addition to regular communication, specific consultation should be undertaken prior to construction works that are predicted to exceed 35 dB LAeq or 0.3mm/s PPV in a bedroom at night. The consultation process is set out in Section 8.3 of the CNV DWP.

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

35 of 73


D6.3 Activity Detail and Consultation Table D6.3.1 details activities that are predicted to exceed the noise or vibration limits in CRL Condition 34 and the predicted effects. Table D6.3.2 provides a summary of consultation with the property owners and/or tenants representatives and identifies methods and measures to mitigate noise and vibration effects and a statement of why they reflect best practicable option. Table D6.3.1: Activity Detail (Noise) ** indicative examples only** #

Activity Details

Predicted Noise Effects

1

Activity Period Duration Days Hours

TBM tunnelling XX 201X â&#x20AC;&#x201C; YY 201X X months Monday to Sunday 10pm â&#x20AC;&#x201C; 7am

Location: Internal noise level: Vibration level: Site specific limits: Potential noise effects:

Bedrooms 35 dB LAeq 0.3 mm/s PPV TBC Sleep disturbance

2

Activity Period Duration Days Hours

X X X X X

Location: Internal noise level: Vibration level: Site specific limits: Potential noise effects:

X X X X X

Table D6.3.2: Consultation **indicative examples only** #

Details

1

Receiver Date Name Phone Email CRL rep

Owner DD/MM/YY X X X X

A. Vibration monitoring to be undertaken

Receiver Date Name Phone Email CRL rep

Tenant DD/MM/YY X X X X

A.

2

Matters discussed

B. Communications Manger to liaise and provide monitoring results and notification of upcoming works Conclusion: Considered to be the BPO because it considers the needs of the stakeholder and mitigates and manages the vibration levels as far as practicable.

B. C. Conclusion:

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

36 of 73


D7

33 Shaddock Street SSCNMP (Nikau Street Site)

D7.1 Introduction This draft Site Specific Construction Noise Management Plan (SSCNMP) is for a commercial building located at 33 Shaddock Street. A SSCNMP is required because construction is predicted to exceed the Project Noise Standards in CRL Condition 31. This SSCNMP has been prepared in accordance with CRL Condition 37 and is Appendix D7 of the CRL Construction Noise and Vibration Delivery Work Plan (CNV DWP). It is a supplementary document that builds on the Project CNV DWP, and therefore, directly references relevant sections of the DWP to avoid repetition. The objective of this SSCNMP is to detail the best practicable option(s) to avoid, remedy or mitigate the identified adverse effects from noise exceedances at 33 Shaddock Street. Section D7.2 identifies the noise sensitive spaces, the predicted or measured façade sound insulation performance, predicted noise effects and recommended consultation thresholds. As required under CRL Condition 37.5, Section D7.3 presents: •

The extent to which noise may exceed the Project Noise Standards (refer Table D7.3.1)

•

The timing and duration of any exceedance (refer Table D7.3.1)

•

The type of activity causing any exceedance (refer Table D7.3.1)

•

A summary of the communication and consultation with the receiver (refer Table D7.3.2)

•

The methods and measures to mitigate noise effects (refer Table D7.3.2)

•

A statement of why they reflect best practicable option (refer Table D7.3.2)

This draft SSCNMP has been prepared by Marshall Day Acoustics Ltd and forms part of the Construction Environmental Management Plan (CEMP) for the Project.

D7.2 Building Details Pre Construction Consultation **TBC** Summarise meeting(s), including information on building layout, noise sensitive spaces and the identification of specific tenant sensitivities that require further investigation. Façade Sound Insulation Performance**TBC** The commercial building at 33 Shaddock Street has masonry façades, sealed glazing and a profiled steel roof with suspended ceiling. The estimated sound level difference across the façade with the windows and doors closed is 25 decibels. On this basis, the predicted construction noise effects can be determined from Table 7 in Section 8.1.2. Consultation Trigger Level **TBC** In addition to regular communication, specific consultation should be undertaken prior to construction works that are predicted to exceed 75 dB LAeq at the façade during the day. The consultation process is set out in Section 8.3 of the CNV DWP.

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

37 of 73


D7.3 Activity Detail and Consultation Table D7.3.1 details activities that are predicted to exceed the noise limits in CRL Condition 31 and the predicted noise effects. Table D7.3.2 provides a summary of consultation with the property owners and/or tenants representatives and identifies methods and measures to mitigate noise effects and a statement of why they reflect best practicable option. Table D7.3.1: Activity Detail (Noise) ** indicative examples only** #

Activity Details

Predicted Noise Effects

1

Activity Period Duration Days Hours

Piling XX 201X – YY 201X X months Monday to Saturday X – Y hours

Location: External noise level: Façade performance: Internal noise level: Potential noise effects:

North and east façades 75 – 80 dB LAeq 25 decibels sound level difference 50 – 55 dB LAeq Annoyance and reduction in work efficiency

2

Activity Period Duration Days Hours

X X X X X

Receiver: Location: External noise level: Façade performance: Internal noise level: Potential noise effects:

X X X X X X

Table D7.3.2: Consultation **indicative examples only** #

Details

1

Receiver Date Name Phone Email CRL rep

Matters discussed Owner DD/MM/YY X X X X

A. Employ additional local hoardings and/or enclosures around noisy plant if non-compliant and practicable B. Communications Manger to liaise and provide monitoring results and notification of upcoming works C. Manage unnecessary impact sounds, e.g. careful handling and by using strops in place of chains Conclusion: Considered to be the BPO because it considers the needs of the stakeholder and mitigates and manages the noise levels as far as practicable.

2

Receiver Date Name Phone Email CRL rep

Tenant DD/MM/YY X X X X

A. B. C. Conclusion:

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

38 of 73


D8

11 Water Street SSCNMP (Water Street Site) This SSCNMP is no longer required because the building is owned by Auckland Transport and it is unoccupied (previously part of the site at 28 Mt Eden Road, currently used as the site office). Therefore, there are no noise and vibration sensitive receivers.

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

39 of 73


D9

12 Boston Road SSCNMP (Water Street Site)

D9.1 Introduction This draft Site Specific Construction Noise Management Plan (SSCNMP) is for a commercial building located at 12 Boston Road. A SSCNMP is required because construction is predicted to exceed the Project Noise Standards in CRL Condition 31. This SSCNMP has been prepared in accordance with CRL Condition 37 and is Appendix D9 of the CRL Construction Noise and Vibration Delivery Work Plan (CNV DWP). It is a supplementary document that builds on the Project CNV DWP, and therefore, directly references relevant sections of the DWP to avoid repetition. The objective of this SSCNMP is to detail the best practicable option(s) to avoid, remedy or mitigate the identified adverse effects from noise exceedances at 12 Boston Road. Section D9.2 identifies the noise sensitive spaces, the predicted or measured façade sound insulation performance, predicted noise effects and recommended consultation thresholds. As required under CRL Condition 37.5, Section D9.3 presents: •

The extent to which noise may exceed the Project Noise Standards (refer Table D9.3.1)

•

The timing and duration of any exceedance (refer Table D9.3.1)

•

The type of activity causing any exceedance (refer Table D9.3.1)

•

A summary of the communication and consultation with the receiver (refer Table D9.3.2)

•

The methods and measures to mitigate noise effects (refer Table D9.3.2)

•

A statement of why they reflect best practicable option (refer Table D9.3.2)

This draft SSCNMP has been prepared by Marshall Day Acoustics Ltd and forms part of the Construction Environmental Management Plan (CEMP) for the Project.

D9.2 Building Details Pre Construction Consultation **TBC** Summarise meeting(s), including information on building layout, noise sensitive spaces and the identification of specific tenant sensitivities that require further investigation. Façade Sound Insulation Performance**TBC** The building at 12 Boston Road is a commercial building constructed from a mix of masonry and timber framed walls with sealed glazing. The estimated sound level difference across the façade with the windows and doors closed is 30 decibels. On this basis, the predicted construction noise effects can be determined from Table 7 in Section 8.1.2. Consultation Trigger Level **TBC** In addition to regular communication, specific consultation should be undertaken prior to construction works that are predicted to exceed 80 dB LAeq at the façade during the day with the windows and doors. The consultation process is set out in Section 8.3 of the CNV DWP.

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

40 of 73


D9.3 Activity Detail and Consultation Table D9.3.1 details activities that are predicted to exceed the noise limits in CRL Condition 31 and the predicted noise effects. Table D9.3.2 provides a summary of consultation with the property owners and/or tenants representatives and identifies methods and measures to mitigate noise effects and a statement of why they reflect best practicable option. Table D9.3.1: Activity Detail (Noise) ** indicative examples only** #

Activity Details

Predicted Noise Effects

1

Activity Period Duration Days Hours

Piling XX 201X – YY 201X X months Monday to Saturday X – Y hours

Location: External noise level: Façade performance: Internal noise level: Potential noise effects:

South façade 75 – 80 dB LAeq 25 decibels sound level difference 45 – 50 dB LAeq Typically acceptable

2

Activity Period Duration Days Hours

X X X X X

Receiver: Location: External noise level: Façade performance: Internal noise level: Potential noise effects:

X X X X X X

Table D9.3.2: Consultation **indicative examples only** #

Details

1

Receiver Date Name Phone Email CRL rep

Matters discussed Owner DD/MM/YY X X X X

A. Employ additional local hoardings and/or enclosures around noisy plant if non-compliant and practicable B. Communications Manger to liaise and provide monitoring results and notification of upcoming works C. Manage unnecessary impact sounds, e.g. careful handling and by using strops in place of chains Conclusion: Considered to be the BPO because it considers the needs of the stakeholder and mitigates and manages the noise levels as far as practicable.

2

Receiver Date Name Phone Email CRL rep

Tenant DD/MM/YY X X X X

A. B. C. Conclusion:

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

41 of 73


D10

41 – 43 Boston Road SSCNMP (GPT1)

D10.1 Introduction This draft Site Specific Construction Noise Management Plan (SSCNMP) is for a commercial building located at 41 – 43 Boston Road. A CNVMP is required to satisfy AUP OIP rule E25.6.29 (5), however for consistency, this SSCNMP is prepared in accordance with the CRL conditions because construction is predicted to exceed the Project Noise Standards in CRL Condition 31. This SSCNMP has been prepared in accordance with CRL Condition 37 and is Appendix D10 of the CRL Construction Noise and Vibration Delivery Work Plan (CNV DWP). It is a supplementary document that builds on the Project CNV DWP, and therefore, directly references relevant sections of the DWP to avoid repetition. The objective of this SSCNMP is to detail the best practicable option(s) to avoid, remedy or mitigate the identified adverse effects from noise exceedances at 41 – 43 Boston Road. Section D10.2 identifies the noise sensitive spaces, the predicted or measured façade sound insulation performance, predicted noise effects and recommended consultation thresholds. As required under CRL Condition 37.5, Section D10.3 presents: •

The extent to which noise may exceed the Project Noise Standards (refer Table D10.3.1)

•

The timing and duration of any exceedance (refer Table D10.3.1)

•

The type of activity causing any exceedance (refer Table D10.3.1)

•

A summary of the communication and consultation with the receiver (refer Table D10.3.2)

•

The methods and measures to mitigate noise effects (refer Table D10.3.2)

•

A statement of why they reflect best practicable option (refer Table D10.3.2)

This draft SSCNMP has been prepared by Marshall Day Acoustics Ltd and forms part of the Construction Environmental Management Plan (CEMP) for the Project.

D10.2 Building Details Pre Construction Consultation **TBC** Summarise meeting(s), including information on building layout, noise sensitive spaces and the identification of specific tenant sensitivities that require further investigation. Façade Sound Insulation Performance**TBC** The building at 41 – 43 Boston Road is a commercial building occupied by a gym, office and retail shop. The building is constructed from a mix of masonry and timber framed walls, roller doors, sealed glazing and a skillion roof. The estimated sound level difference across the façade with the windows and doors closed is 25 decibels. On this basis, the predicted construction noise effects can be determined from Table 7 in Section 8.1.2. Consultation Trigger Level **TBC** In addition to regular communication, specific consultation should be undertaken prior to construction works that are predicted to exceed 75 dB LAeq at the façade during the day with the windows and doors. The consultation process is set out in Section 8.3 of the CNV DWP.

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

42 of 73


D10.3 Activity Detail and Consultation Table D10.3.1 details activities that are predicted to exceed the noise limits in AUP OIP rule E25.6.29 and the predicted noise effects. Table D10.3.2 provides a summary of consultation with the property owners and/or tenants representatives and identifies methods and measures to mitigate noise effects and a statement of why they reflect best practicable option. Table D10.3.1: Activity Detail (Noise) ** indicative examples only** #

Activity Details

Predicted Noise Effects

1

Activity Period Duration Days Hours

Piling XX 201X – YY 201X X months Monday to Saturday X – Y hours

Location: External noise level: Façade performance: Internal noise level: Potential noise effects:

South façade 75 – 80 dB LAeq 25 decibels sound level difference 50 – 55 dB LAeq Typically acceptable

2

Activity Period Duration Days Hours

X X X X X

Receiver: Location: External noise level: Façade performance: Internal noise level: Potential noise effects:

X X X X X X

Table D10.3.2: Consultation **indicative examples only** #

Details

1

Receiver Date Name Phone Email CRL rep

Matters discussed Owner DD/MM/YY X X X X

A. Employ additional local hoardings and/or enclosures around noisy plant if non-compliant and practicable B. Communications Manger to liaise and provide monitoring results and notification of upcoming works C. Manage unnecessary impact sounds, e.g. careful handling and by using strops in place of chains Conclusion: Considered to be the BPO because it considers the needs of the stakeholder and mitigates and manages the noise levels as far as practicable.

2

Receiver Date Name Phone Email CRL rep

Tenant DD/MM/YY X X X X

A. B. C. Conclusion:

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

43 of 73


D11

45 Boston Road SSCNMP (GPT1 and GPT2) This SSCNMP is no longer required because the building on this site has been demolished. It is currently a carpark, and therefore, there are no noise and vibration sensitive receivers.

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

44 of 73


D12

47 – 49 Boston Road SSCNMP (GPT1 and GPT2)

D12.1 Introduction This draft Site Specific Construction Noise Management Plan (SSCNMP) is for a commercial buildings located at 47 – 49 Boston Road. CNVMP is required to satisfy AUP OIP rule E25.6.29 (5), however for consistency, this SSCNMP is prepared in accordance with the CRL conditions because construction is predicted to exceed the Project Noise Standards in CRL Condition 31. This SSCNMP has been prepared in accordance with CRL Condition 37 and is Appendix D12 of the CRL Construction Noise and Vibration Delivery Work Plan (CNV DWP). It is a supplementary document that builds on the Project CNV DWP, and therefore, directly references relevant sections of the DWP to avoid repetition. The objective of this SSCNMP is to detail the best practicable option(s) to avoid, remedy or mitigate the identified adverse effects from noise exceedances at 47 – 49 Boston Road. Section D12.2 identifies the noise sensitive spaces, the predicted or measured façade sound insulation performance, predicted noise effects and recommended consultation thresholds. As required under CRL Condition 37.5, Section D12.3 presents: •

The extent to which noise may exceed the Project Noise Standards (refer Table D12.3.1)

•

The timing and duration of any exceedance (refer Table D12.3.1)

•

The type of activity causing any exceedance (refer Table D12.3.1)

•

A summary of the communication and consultation with the receiver (refer Table D12.3.2)

•

The methods and measures to mitigate noise effects (refer Table D12.3.2)

•

A statement of why they reflect best practicable option (refer Table D12.3.2)

This draft SSCNMP has been prepared by Marshall Day Acoustics Ltd and forms part of the Construction Environmental Management Plan (CEMP) for the Project.

D12.2 Building Details Pre Construction Consultation **TBC** Summarise meeting(s), including information on building layout, noise sensitive spaces and the identification of specific tenant sensitivities that require further investigation. Façade Sound Insulation Performance**TBC** The building at 47 – 49 Boston Road is a commercial building occupied by offices and a retail shop. The building is of masonry construction and sealed glazing. The estimated sound level difference across the façade with the windows and doors closed is 30 decibels. On this basis, the predicted construction noise effects can be determined from Table 7 in Section 8.1.2. Consultation Trigger Level **TBC** In addition to regular communication, specific consultation should be undertaken prior to construction works that are predicted to exceed 80 dB LAeq at the façade during the day with the windows and doors. The consultation process is set out in Section 8.3 of the CNV DWP.

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

45 of 73


D12.3 Activity Detail and Consultation Table D12.3.1 details activities that are predicted to exceed the noise limits in AUP OIP rule E25.6.29and the predicted noise effects. Table D12.3.2 provides a summary of consultation with the property owners and/or tenants representatives and identifies methods and measures to mitigate noise effects and a statement of why they reflect best practicable option. Table D12.3.1: Activity Detail (Noise) ** indicative examples only** #

Activity Details

Predicted Noise Effects

1

Activity Period Duration Days Hours

Piling XX 201X – YY 201X X months Monday to Saturday X – Y hours

Location: External noise level: Façade performance: Internal noise level: Potential noise effects:

South façade 75 – 80 dB LAeq 30 decibels sound level difference 45 – 50 dB LAeq Typically acceptable

2

Activity Period Duration Days Hours

X X X X X

Receiver: Location: External noise level: Façade performance: Internal noise level: Potential noise effects:

X X X X X X

Table D12.3.2: Consultation **indicative examples only** #

Details

1

Receiver Date Name Phone Email CRL rep

Matters discussed Owner DD/MM/YY X X X X

A. Employ additional local hoardings and/or enclosures around noisy plant if non-compliant and practicable B. Communications Manger to liaise and provide monitoring results and notification of upcoming works C. Manage unnecessary impact sounds, e.g. careful handling and by using strops in place of chains Conclusion: Considered to be the BPO because it considers the needs of the stakeholder and mitigates and manages the noise levels as far as practicable.

2

Receiver Date Name Phone Email CRL rep

Tenant DD/MM/YY X X X X

A. B. C. Conclusion:

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

46 of 73


D13

24 Normanby Road SSCNMP (GPT3)

D13.1 Introduction This draft Site Specific Construction Noise Management Plan (SSCNMP) is for apartments located at 24 Normanby Road. A SSCNMP is required because construction is predicted to exceed the Project Noise Standards in CRL Condition 31. This SSCNMP has been prepared in accordance with CRL Condition 37 and is Appendix D13 of the CRL Construction Noise and Vibration Delivery Work Plan (CNV DWP). It is a supplementary document that builds on the Project CNV DWP, and therefore, directly references relevant sections of the DWP to avoid repetition. The objective of this SSCNMP is to detail the best practicable option(s) to avoid, remedy or mitigate the identified adverse effects from noise exceedances at 24 Normanby Road. Section D13.2 identifies the noise sensitive spaces, the predicted or measured façade sound insulation performance, predicted noise effects and recommended consultation thresholds. As required under CRL Condition 37.5, Section D13.3 presents: •

The extent to which noise may exceed the Project Noise Standards (refer Table D13.3.1)

•

The timing and duration of any exceedance (refer Table D13.3.1)

•

The type of activity causing any exceedance (refer Table D13.3.1)

•

A summary of the communication and consultation with the receiver (refer Table D13.3.2)

•

The methods and measures to mitigate noise effects (refer Table D13.3.2)

•

A statement of why they reflect best practicable option (refer Table D13.3.2)

This draft SSCNMP has been prepared by Marshall Day Acoustics Ltd and forms part of the Construction Environmental Management Plan (CEMP) for the Project.

D13.2 Building Details Pre Construction Consultation **TBC** Summarise meeting(s), including information on building layout, noise sensitive spaces and the identification of specific tenant sensitivities that require further investigation. Façade Sound Insulation Performance**TBC** The apartments at 24 Normanby Road have linear weatherboard façades with operable glazing and a steel pitched roof. The estimated sound level difference across the façade with the windows and doors closed is 30 decibels. On this basis, the predicted construction noise effects can be determined from Table 7 in Section 8.1.2. Consultation Trigger Level **TBC** In addition to regular communication, specific consultation should be undertaken prior to construction works that are predicted to exceed 80 dB LAeq at the façade during the day with the windows and doors. The consultation process is set out in Section 8.3 of the CNV DWP.

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

47 of 73


D13.3 Activity Detail and Consultation Table D13.3.1 details activities that are predicted to exceed the noise limits in CRL Condition 31 and the predicted noise effects. Table D13.3.2 provides a summary of consultation with the property owners and/or tenants representatives and identifies methods and measures to mitigate noise effects and a statement of why they reflect best practicable option. Table D13.3.1: Activity Detail (Noise) ** indicative examples only** #

Activity Details

Predicted Noise Effects

1

Activity Period Duration Days Hours

Sheet piling XX 201X – YY 201X 1-2 days Wed to Thu X – Y hours

Location: External noise level: Façade performance: Internal noise level: Potential noise effects:

East façade 80 – 85 dB LAeq 30 decibels sound level difference 50 – 55 dB LAeq Annoyance and reduction in work efficiency

2

Activity Period Duration Days Hours

X X X X X

Receiver: Location: External noise level: Façade performance: Internal noise level: Potential noise effects:

X X X X X X

Table D13.3.2: Consultation **indicative examples only** #

Details

1

Receiver Date Name Phone Email CRL rep

Matters discussed Owner DD/MM/YY X X X X

A. Employ additional local hoardings and/or enclosures around noisy plant if non-compliant and practicable B. Communications Manger to liaise and provide monitoring results and notification of upcoming works C. Manage unnecessary impact sounds, e.g. careful handling and by using strops in place of chains Conclusion: Considered to be the BPO because it considers the needs of the stakeholder and mitigates and manages the noise levels as far as practicable.

2

Receiver Date Name Phone Email CRL rep

Tenant DD/MM/YY X X X X

A. B. C. Conclusion:

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

48 of 73


D14

39 Boston Road SSCNMP (GPT1)

D14.1 Introduction This draft Site Specific Construction Noise Management Plan (SSCNMP) is for the commercial building located at 39 Boston Road. A SSCNMP is required because construction is predicted to exceed the Project Noise Standards in CRL Condition 31. This SSCNMP has been prepared in accordance with CRL Condition 37 and is Appendix D14 of the CRL Construction Noise and Vibration Delivery Work Plan (CNV DWP). It is a supplementary document that builds on the Project CNV DWP, and therefore directly references relevant sections of the DWP to avoid repetition. The objective of this SSCNMP is to detail the best practicable option(s) to avoid, remedy or mitigate the identified adverse effects from noise exceedances at 39 Boston Road. Section D14.2 identifies the noise sensitive spaces, the predicted or measured façade sound insulation performance, predicted noise effects and recommended consultation thresholds. As required under CRL Condition 37.5, Section D14.3 presents: •

The extent to which noise may exceed the Project Noise Standards (refer Table D14.3.1)

•

The timing and duration of any exceedance (refer Table D14.3.1)

•

The type of activity causing any exceedance (refer Table D14.3.1)

•

A summary of the communication and consultation with the receiver (refer Table D14.3.2)

•

The methods and measures to mitigate noise effects (refer Table D14.3.2)

•

A statement of why they reflect best practicable option (refer Table D14.3.2)

This draft SSCNMP has been prepared by Marshall Day Acoustics Ltd and forms part of the Construction Environmental Management Plan (CEMP) for the Project.

D14.2 Building Details Pre Construction Consultation **TBC** Summarise meeting(s), including information on building layout, noise sensitive spaces and the identification of specific tenant sensitivities that require further investigation. Façade Sound Insulation Performance**TBC** The building at 39 Boston is a commercial building with concrete block walls and limited sealed glazing. The estimated sound level difference across the façade with the windows and doors closed is 30 decibels. On this basis, the predicted construction noise effects can be determined from Table 7 in Section 8.1.2. Consultation Trigger Level **TBC** In addition to regular communication, specific consultation should be undertaken prior to construction works that are predicted to exceed 80 dB LAeq at the façade during the day with the windows and doors. The consultation process is set out in Section 8.3 of the CNV DWP.

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

49 of 73


D14.3 Activity Detail and Consultation Table D14.3.1 details activities that are predicted to exceed the noise limits in CRL Condition 31 and the predicted noise effects. Table D14.3.2 provides a summary of consultation with the property owners and/or tenants representatives and identifies methods and measures to mitigate noise effects and a statement of why they reflect best practicable option. Table D14.3.1: Activity Detail (Noise) ** indicative examples only** #

Activity Details

Predicted Noise Effects

1

Activity Period Duration Days Hours

Sheet piling XX 201X – YY 201X 1-2 days Wed to Thu X – Y hours

Location: External noise level: Façade performance: Internal noise level: Potential noise effects:

South façade 75 – 80 dB LAeq 30 decibels sound level difference 45 – 50 dB LAeq Generally acceptable

2

Activity Period Duration Days Hours

X X X X X

Receiver: Location: External noise level: Façade performance: Internal noise level: Potential noise effects:

X X X X X X

Table D14.3.2: Consultation **indicative examples only** #

Details

1

Receiver Date Name Phone Email CRL rep

Matters discussed Owner DD/MM/YY X X X X

A. Employ additional local hoardings and/or enclosures around noisy plant if non-compliant and practicable B. Communications Manger to liaise and provide monitoring results and notification of upcoming works C. Manage unnecessary impact sounds, e.g. careful handling and by using strops in place of chains Conclusion: Considered to be the BPO because it considers the needs of the stakeholder and mitigates and manages the noise levels as far as practicable.

2

Receiver Date Name Phone Email CRL rep

Tenant DD/MM/YY X X X X

A. B. C. Conclusion:

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

50 of 73


D15

55 Boston Road SSCNMP (GPT2)

D15.1 Introduction This draft Site Specific Construction Noise Management Plan (SSCNMP) is for the commercial building located at 55 Boston Road. A SSCNMP is required because construction is predicted to exceed the Project Noise Standards in CRL Condition 31. This SSCNMP has been prepared in accordance with CRL Condition 37 and is Appendix D15 of the CRL Construction Noise and Vibration Delivery Work Plan (CNV DWP). It is a supplementary document that builds on the Project CNV DWP, and therefore directly references relevant sections of the DWP to avoid repetition. The objective of this SSCNMP is to detail the best practicable option(s) to avoid, remedy or mitigate the identified adverse effects from noise exceedances at 55 Boston Road. Section D15.2 identifies the noise sensitive spaces, the predicted or measured façade sound insulation performance, predicted noise effects and recommended consultation thresholds. As required under CRL Condition 37.5, Section D15.3 presents: •

The extent to which noise may exceed the Project Noise Standards (refer Table D15.3.1)

•

The timing and duration of any exceedance (refer Table D15.3.1)

•

The type of activity causing any exceedance (refer Table D15.3.1)

•

A summary of the communication and consultation with the receiver (refer Table D15.3.2)

•

The methods and measures to mitigate noise effects (refer Table D15.3.2)

•

A statement of why they reflect best practicable option (refer Table D15.3.2)

This draft SSCNMP has been prepared by Marshall Day Acoustics Ltd and forms part of the Construction Environmental Management Plan (CEMP) for the Project.

D15.2 Building Details Pre Construction Consultation **TBC** Summarise meeting(s), including information on building layout, noise sensitive spaces and the identification of specific tenant sensitivities that require further investigation. Façade Sound Insulation Performance**TBC** The building at 55 Boston Road is a commercial building. The exposed façade where the noise levels are predicted to exceed 75 dB LAeq during sheet piling works is concrete block with limited sealed glazing. The estimated sound level difference across the façade with the windows and doors closed is 30 decibels. On this basis, the predicted construction noise effects can be determined from Table 7 in Section 8.1.2. Consultation Trigger Level **TBC** In addition to regular communication, specific consultation should be undertaken prior to construction works that are predicted to exceed 80 dB LAeq at the façade during the day with the windows and doors. The consultation process is set out in Section 8.3 of the CNV DWP.

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

51 of 73


D15.3 Activity Detail and Consultation Table D15.3.1 details activities that are predicted to exceed the noise limits in CRL Condition 31 and the predicted noise effects. Table D15.3.2 provides a summary of consultation with the property owners and/or tenants representatives and identifies methods and measures to mitigate noise effects and a statement of why they reflect best practicable option. Table D15.3.1: Activity Detail (Noise) ** indicative examples only** #

Activity Details

Predicted Noise Effects

1

Activity Period Duration Days Hours

Sheet piling XX 201X – YY 201X 1-2 days Wed to Thu X – Y hours

Location: External noise level: Façade performance: Internal noise level: Potential noise effects:

East façade 75 – 80 dB LAeq 25 decibels sound level difference 45 – 50 dB LAeq Generally acceptable

2

Activity Period Duration Days Hours

X X X X X

Receiver: Location: External noise level: Façade performance: Internal noise level: Potential noise effects:

X X X X X X

Table D15.3.2: Consultation **indicative examples only** #

Details

1

Receiver Date Name Phone Email CRL rep

Matters discussed Owner DD/MM/YY X X X X

A. Employ additional local hoardings and/or enclosures around noisy plant if non-compliant and practicable B. Communications Manger to liaise and provide monitoring results and notification of upcoming works C. Manage unnecessary impact sounds, e.g. careful handling and by using strops in place of chains Conclusion: Considered to be the BPO because it considers the needs of the stakeholder and mitigates and manages the noise levels as far as practicable.

2

Receiver Date Name Phone Email CRL rep

Tenant DD/MM/YY X X X X

A. B. C. Conclusion:

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

52 of 73


D16

32 Normanby Road SSCNMP (GPT3)

D16.1 Introduction This draft Site Specific Construction Noise Management Plan (SSCNMP) is for the commercial building located at 32 Normanby Road. A SSCNMP is required because construction is predicted to exceed the Project Noise Standards in CRL Condition 31. This SSCNMP has been prepared in accordance with CRL Condition 37 and is Appendix D16 of the CRL Construction Noise and Vibration Delivery Work Plan (CNV DWP). It is a supplementary document that builds on the Project CNV DWP, and therefore, directly references relevant sections of the DWP to avoid repetition. The objective of this SSCNMP is to detail the best practicable option(s) to avoid, remedy or mitigate the identified adverse effects from noise exceedances at 32 Normanby Road. Section D16.2 identifies the noise sensitive spaces, the predicted or measured façade sound insulation performance, predicted noise effects and recommended consultation thresholds. As required under CRL Condition 37.5, Section D16.3 presents: •

The extent to which noise may exceed the Project Noise Standards (refer Table D16.3.1)

•

The timing and duration of any exceedance (refer Table D16.3.1)

•

The type of activity causing any exceedance (refer Table D16.3.1)

•

A summary of the communication and consultation with the receiver (refer Table D16.3.2)

•

The methods and measures to mitigate noise effects (refer Table D16.3.2)

•

A statement of why they reflect best practicable option (refer Table D16.3.2)

This draft SSCNMP has been prepared by Marshall Day Acoustics Ltd and forms part of the Construction Environmental Management Plan (CEMP) for the Project.

D16.2 Building Details Pre Construction Consultation **TBC** Summarise meeting(s), including information on building layout, noise sensitive spaces and the identification of specific tenant sensitivities that require further investigation. Façade Sound Insulation Performance**TBC** The building at 32 Normanby Road is a commercial building with extensive sealed glazing façade. The estimated sound level difference across the façade with the windows and doors closed is 30 decibels. On this basis, the predicted construction noise effects can be determined from Table 7 in Section 8.1.2. Consultation Trigger Level **TBC** In addition to regular communication, specific consultation should be undertaken prior to construction works that are predicted to exceed 80 dB LAeq at the façade during the day with the windows and doors. The consultation process is set out in Section 8.3 of the CNV DWP.

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

53 of 73


D16.3 Activity Detail and Consultation Table D16.3.1 details activities that are predicted to exceed the noise limits in CRL Condition 31 and the predicted noise effects. Table D16.3.2 provides a summary of consultation with the property owners and/or tenants representatives and identifies methods and measures to mitigate noise effects and a statement of why they reflect best practicable option. Table D16.3.1: Activity Detail (Noise) ** indicative examples only** #

Activity Details

Predicted Noise Effects

1

Activity Period Duration Days Hours

Sheet piling XX 201X – YY 201X 1-2 days Wed to Thu X – Y hours

Location: External noise level: Façade performance: Internal noise level: Potential noise effects:

East façade 80 – 85 dB LAeq 30 decibels sound level difference 50 – 55 dB LAeq Annoyance and reduction in work efficiency

2

Activity Period Duration Days Hours

X X X X X

Receiver: Location: External noise level: Façade performance: Internal noise level: Potential noise effects:

X X X X X X

Table D16.3.2: Consultation **indicative examples only** #

Details

1

Receiver Date Name Phone Email CRL rep

Matters discussed Owner DD/MM/YY X X X X

A. Employ additional local hoardings and/or enclosures around noisy plant if non-compliant and practicable B. Communications Manger to liaise and provide monitoring results and notification of upcoming works C. Manage unnecessary impact sounds, e.g. careful handling and by using strops in place of chains Conclusion: Considered to be the BPO because it considers the needs of the stakeholder and mitigates and manages the noise levels as far as practicable.

2

Receiver Date Name Phone Email CRL rep

Tenant DD/MM/YY X X X X

A. B. C. Conclusion:

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

54 of 73


D17

61 Normanby Road SSCNMP (GPT3)

D17.1 Introduction This draft Site Specific Construction Noise Management Plan (SSCNMP) is for the commercial building located at 61 Normanby Road. A SSCNMP is required because construction is predicted to exceed the Project Noise Standards in CRL Condition 31. This SSCNMP has been prepared in accordance with CRL Condition 37 and is Appendix D17 of the CRL Construction Noise and Vibration Delivery Work Plan (CNV DWP). It is a supplementary document that builds on the Project CNV DWP, and therefore, directly references relevant sections of the DWP to avoid repetition. The objective of this SSCNMP is to detail the best practicable option(s) to avoid, remedy or mitigate the identified adverse effects from noise exceedances at 61 Normanby Road. Section D17.2 identifies the noise sensitive spaces, the predicted or measured façade sound insulation performance, predicted noise effects and recommended consultation thresholds. As required under CRL Condition 37.5, Section D17.3 presents: •

The extent to which noise may exceed the Project Noise Standards (refer Table D17.3.1)

•

The timing and duration of any exceedance (refer Table D17.3.1)

•

The type of activity causing any exceedance (refer Table D17.3.1)

•

A summary of the communication and consultation with the receiver (refer Table D17.3.2)

•

The methods and measures to mitigate noise effects (refer Table D17.3.2)

•

A statement of why they reflect best practicable option (refer Table D17.3.2)

This draft SSCNMP has been prepared by Marshall Day Acoustics Ltd and forms part of the Construction Environmental Management Plan (CEMP) for the Project.

D17.2 Building Details Pre Construction Consultation Graeme Inglis (MBJV) and Craig Fitzgerald (Marshall Day Acoustics) met with Corys Electrical CEO Steve Priest and Corporate Services Manager Michelle Munro on 9 April 2018. The matters discussed included an overview of the project, general project programme including 1-2 days of sheet piling required to install temporary shoring and 1 day to remove temporary shoring for the GPT3 pit, overview of the CNV DWP and this SSCNMP, communications triggers and protocol, building layout and identification of noise and vibration sensitive spaces / equipment. The key issue for Steve Priest was vibration sensitivity, particularly lighting stock and a server rack located on the ground floor in the northwest corner of the building, approximate 25 – 30m from the proposed sheet piling works. Vibration levels of 2 – 3mm/s are predicted at this setback, including a conservative safety margin. The server rack is sturdy and on rubber wheel castors locked to avoid lateral movement. The light bulbs were individually wrapped in cardboard and stacked well on shelves to minimise movement. It was explained that vibration will be unlikely to affect these items and any effects would be more likely amenity related, and suitably addressed with prior communication. On the first floor, three offices are located in the north-west corner of the building overlooking the GPT3 site. A training room is located further south on the west façade. However, Steve Priest advised that, with prior notification, all occupants could be relocated to other offices during sheet piling works to avoid significant adverse noise and/or vibration amenity effects.

Façade Sound Insulation Performance This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

55 of 73


The building at 61 Normanby Road is a commercial building with extensive sealed glazing façade. The estimated sound level difference across the façade with the windows and doors closed is 30 decibels. On this basis, the predicted construction noise effects can be determined from Table 7 in Section 8.1.2. Consultation Trigger Level In addition to regular communication, specific consultation should be undertaken prior to construction works that are predicted to exceed 80 dB LAeq at the façade during the day with the windows and doors. The consultation process is set out in Section 8.3 of the CNV DWP.

D17.3 Activity Detail and Consultation Table D17.3.1 details activities that are predicted to exceed the noise limits in CRL Condition 31 and the predicted noise effects. Table D17.3.2 provides a summary of consultation with the property owners and/or tenants representatives and identifies methods and measures to mitigate noise effects and a statement of why they reflect best practicable option. Table D17.3.1: Activity Detail (Noise) ** indicative examples only** #

Activity Details

Predicted Noise Effects

1

Activity Period Duration Days Hours

Sheet piling XX 201X – YY 201X 1-2 days Wed to Thu X – Y hours

Location: External noise level: Façade performance: Internal noise level: Potential noise effects:

West façade 80 – 85 dB LAeq 30 decibels sound level difference 50 – 55 dB LAeq Annoyance and reduction in work efficiency

2

Activity Period Duration Days Hours

X X X X X

Receiver: Location: External noise level: Façade performance: Internal noise level: Potential noise effects:

X X X X X X

Table D17.3.2: Consultation **indicative examples only** #

Details

1

Receiver Date Name Phone Email CRL rep

Matters discussed Owner DD/MM/YY X X X X

A. Employ additional local hoardings and/or enclosures around noisy plant if non-compliant and practicable B. Communications Manger to liaise and provide monitoring results and notification of upcoming works C. Manage unnecessary impact sounds, e.g. careful handling and by using strops in place of chains Conclusion: Considered to be the BPO because it considers the needs of the stakeholder and mitigates and manages the noise levels as far as practicable.

2

Receiver Date Name Phone Email CRL rep

Tenant DD/MM/YY X X X X

A. B. C. Conclusion:

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

56 of 73


D18

MediaWorks SSCNVMP (Nikau Street Site)

D18.1 Introduction This Site Specific Construction Noise and Vibration Management Plan (SSCNVMP) is for the MediaWorks Building at 3 Flower Street. It is required to satisfy CRL Conditions 35, 39 and 40. It is Appendix D18 of the CRL Construction Noise and Vibration Delivery Work Plan (CNV DWP). It is a supplementary document that builds on the Project CNV DWP, and therefore, directly references relevant sections of the DWP to avoid repetition. Together, the CNV DWP and MediaWorks SSCNVMP are consistent with the draft MediaWorks SSCNVMP4. It must be implemented for works within 100m, and blasting activities within 200m of the MediaWorks Building. The objective of this SSCNVMP is to detail the best practicable option(s) to avoid, remedy or mitigate the identified adverse effects on MediaWorks. It contains, or references: •

Details of those responsible for implementing this SSCNVMP (refer CNV DWP Section 2.3)

•

MediaWorks noise and vibration sensitive spaces (refer Section D18.2)

•

The relevant Project Standards (the general requirements in CNV DWP Section 3.0 and the MediaWorks specific requirements for Studio 1 are summarised in Section D18.3)

•

Predicted construction noise and vibration levels and transfer functions (refer Section D18.4)

•

Mitigation and management measures (refer CNV DWP Section 5.0)

•

Communication protocol (refer CNV DWP Section 6.0)

•

Monitoring (refer CNV DWP Section 7.0 and Section D18.5 specifically for Studio 1)

•

Contingency measures (refer CNV DWP Section 8.0 and Section D18.6 specifically for Studio 1).

•

SSCNVMP review process (refer CNV DWP Section 9.0 and CRL condition 40.13)

This SSCNVMP has been prepared by Marshall Day Acoustics Ltd and forms part of the Construction Environmental Management Plan (CEMP) for the Project.

D18.2 Project Standards The relevant Construction Noise Project Standards are summarised in Table 18.2.1. Table D18.2.1: Construction Noise – MediaWorks Condition

Requirement

Limit5

Assessment location (period)

31.1

General6

75 dB LAeq

External façade (all times)

35.2

Studio 17, 8

30 dB LAeq (5 min) 9 33 dB LAeq (1 sec)

Inside Studio 1 (Sensitive Times)

4

Project Agreement in respect of the City Rail Link between Auckland Transport (AT) and MediaWorks Holdings Limited (Mediaworks), reference item 6 and Appendix 1. 5

In assessing compliance with the limit, the cumulative level of all sources shall be considered

6

Measured and assessed in accordance with the provisions of New Zealand Standard NZS 6803:1999 “Acoustics Construction Noise” 7

Sensitive times defined in CRL Conditions 35.1 – 35.3 and summarised below

8

Limits may be up to 5 decibels higher for defined periods with the specified notifications detailed in condition 35.2

9

Position representative main presenter(s) microphone and with the doors and windows closed (Conditions 35.4/5)

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

57 of 73


The relevant Construction Vibration Project Standards are summarised in Table 18.2.2. Table 18.2.2: Construction Vibration – MediaWorks Condition

Requirement

Limit

Assessment location10 (period)

33.1

Building Damage

1-100Hz: 10 mm/s PPV

Horizontal plane of highest floor level

35.3

Studio 1

0.1 mm/s PPV11

Floor of Studio 1 (Sensitive Times). If compliant in Studio 1, vibration in other studios will be acceptable.

35.6

Amenity

1 mm/s PPV

Floor of office areas, meeting rooms and technical suites (occupied times).

35.8

Sensitive Equipment

200mg (2 m/s) 5 – 500 Hz

Floor supporting sensitive equipment

The operational requirements and constraints provided by MediaWorks for Studio 1 are detailed in CRL Conditions 35.1 – 35.3 and summarised as follows: •

Sensitive Times are defined as: - During scheduled live broadcasting - During emergency/breaking news live broadcasting - During scheduled recording sessions

•

Live Broadcasting Periods are defined as: - Weekdays: 0600 – 0900 hrs, 1200 – 1230 hrs, 1730 – 1930 hrs and 2230 – 2330 hrs - Christmas holiday season (Saturday prior to Christmas Day to Sunday following New Year’s Day inclusive): 1730 – 1900 hrs

D18.3 Building Details Pre Construction Consultation Graeme Inglis (MBJV), Richard Jenkins and Jenny Chu (CRLL), Craig Fitzgerald and Pranaya Thaker (Marshall Day Acoustics), met with Emma Michell (MediaWorks) on 5 April 2018. The matters discussed included: •

An overview of the project

•

General programme (including 2-week windows for demolition and rock breaking activities)

•

Predicted noise and vibration levels (compliance with all relevant conditions at MediaWorks)

•

The mitigation, management and timing measures employed to avoid effects on MediaWorks

•

An overview of the CNV DWP and specific measures in this SSCNVMP

•

Communications and consultation triggers and protocol

•

Proposed noise and vibration monitoring

10

These are the measurement locations where required by the Standard. For monitoring, proxy locations can be used with established transfer functions (refer condition 40.9) 11

Limit may be elevated by agreement with MediaWorks

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

58 of 73


•

A tour was provided to identify noise and vibration sensitive spaces and identify suitable locations for monitoring equipment (completed 6 April 2018).

Actions included: •

MediaWorks to provide floor plans (complete 9 April 2018)

•

MDA to identify proposed monitor locations on supplied drawings (refer Figures in D18.5). Where agreed, liaise with MediaWorks electricians to provide power supply to monitors.

•

Supply CNV DWP and MediaWorks SSCNVMP by 10/11 April 2018 for review and feedback

D18.4 Predicted Construction Noise and Vibration Levels In accordance with CRL condition 40.1, high noise and vibration equipment items are identified in Section 4.0 of the CNV DWP. Noise (excluding Studio 1) Rock breaking, rock drilling and concrete cutting activities at the Nikau St site are predicted to generate the highest noise levels. These activities are predicted to result in noise levels of 60 – 70 dB LAeq on the most exposed façade of the MediaWorks building which comply with the 75 dB LAeq limit at the external façade. Regardless, as agreed during mediation, secondary glazing shall be installed to further mitigate residual noise levels in office areas on level 2 of the MediaWorks building12. Vibration (excluding Studio 1) Rock breaking vibration received in the MediaWorks building office areas, meeting rooms and technical suites is predicted to be imperceptible and readily compliant with the 1mm/s PPV amenity limits in CRL condition 35.5 (discussed further for Studio 1 below). Refer to CNV DWP Appendix C for vibration regression curves. Studio 1 Noise and Vibration The rock breaking works are approximately 90m from Studio 1. The vibration levels received in Studio 1 are predicted to be 0.1mm/s PPV, which is at the Studio 1 limit specified in CRL condition 35.3. However, it should be acknowledged that these predictions are indicative only and are beyond the reliable tolerances of the prediction method. Regardless, CRL Condition 35.2A limits rock breaking within 100 metres during defined Sensitive Times (as defined in Condition 35.2) unless compliance with the limits in Condition 35.2 can be demonstrated. Therefore, the first instance of rock breaking will be timed to occur outside Sensitive Times to enable measurement and demonstration of compliance with Condition 35.2 prior to expanding the works period. This approach aligns with the requirements of CRL conditions 40.3 and 40.8 and addresses any residual risk of exceedance. Furthermore, it is noted that the 0.1mm/s PPV vibration limit primarily controls reradiated noise levels to below 30 dB LAeq (5 min) and 33 dB LAeq (1 sec) specified in CRL condition 35.2. This relationship was established in an SLR report during the CRL hearings process13. It determined that the airborne noise component received in the Studio was negligible (transfer function in the order 80 decibels) and that the only residual noise effect would be from reradiated noise. This relationship will be used as the initial basis to satisfy Conditions 40.2 and 40.3, however, will be reviewed following monitoring of the first occurrence of rock breaking (described in the previous paragraph).

12

Project Agreement in respect of the City Rail Link between Auckland Transport (AT) and MediaWorks Holdings Limited (Mediaworks), reference item 7 and Appendix 2. 13

SLR report Mediaworks Investigations Borehole and Studio Vibration, 610.12219.00400-R1, dated 21 October 2013

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

59 of 73


D18.5 Studio 1 Monitoring Overview Noise and vibration monitoring inside Studio 1 shall be undertaken by a suitably qualified and experienced acoustic specialist in accordance conditions 35 and 40. This shall include continuous automated noise and vibration monitoring in accordance with condition 40.9. The data shall be available in real time to City Rail Link Limited, Auckland Council and MediaWorks. Prior to any demolition or construction commencing, additional proxy noise and vibration controls shall be determined, and agreed upon by MediaWorks, that enable on-site compliance management. The proxy controls shall be determined in accordance with conditions 40.2 and 40.3 and included for reference in the Tables D18.2. System Setup The monitoring systems are automated, in that data is automatically uploaded to a secure website (or similar) which allows the results to be available to key personnel on demand or by email/text alerts. Monitoring will be undertaken at two locations prior to commencement of the demolition and rock breaking activities at the Nikau Street site. The monitoring will: •

Measure vibration received in relevant areas of the MediaWorks building, and reradiated noise in Studio 1

•

Establish transfer functions between these areas

These transfer functions will allow subsequent measurements during the remainder of construction period to be undertaken at fewer locations. These would be the ‘proxy’ locations and would be reviewed and agreed upon by MediaWorks prior to their use. Monitoring may occur at locations simultaneously or sequentially provided the vibration sources of interest are captured, and compliance with the conditions can be demonstrated. The monitoring locations may change over time to accommodate different phases of construction, but throughout there will be a consistent focus on Studio 1. Condition 35.2 sets out reradiated noise controls for Studio 1. Compliance with these limits implies that vibration and reradiated noise will be adequately controlled in all other areas of the MediaWorks building. This assumption should be confirmed by short duration parallel monitoring at an early stage during construction. Vibration measurements are likely to be influenced by other activities causing vibration in the building (e.g. people walking past the transducers, moving equipment, doors slamming etc.). This can be managed in the first instance through appropriate placement of the monitors, but can also be managed by processing the data statistically or comparing simultaneous monitoring data from the two vibration monitors to ensure these anomalous events are not interpreted as construction events. The trigger threshold for text/email alerts will also be modified as appropriate to reduce the number of ‘false positives’ in accordance with Condition 35.3 by agreement of both the Requiring Authority and MediaWorks. Monitoring Equipment Construction vibration will be monitored using Syscom MR3000C units. The units would typically be placed on the basement floor near the façade closest to the construction works and/or in Studio 1. Alternatively, they may be placed on the top floor near the same façade. They do not require fixings (i.e. clamps, adhesives) to be installed, however weighing down with a sandbag is recommended. They are best located This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

60 of 73


away from foot traffic to avoid being bumped. The units record numerical vibration levels. The data is accessed remotely via the 3G network. If a preset monitoring trigger level is exceeded, it will alert the monitoring manager. Construction noise will be measured using a 01dB Cube Smart Noise Monitoring Terminal unit. An external microphone will be placed on the outside of the faรงade that faces the construction works. The unit records numerical noise levels. The data is accessed remotely via the 3G mobile phone network. If a preset monitoring trigger level is exceeded, it will capture a short audio recording and alert the monitoring manager. Review of the monitoring data and audio may help identify the source and inform construction methodology, mitigation opportunities and communication. With mains power, the units operate autonomously, only requiring access for yearly maintenance and calibration. The units use a conventional house plug and draw between 2 and 3.6 watts of power, which is similar to a mobile phone charger. Monitoring Locations The monitoring locations agreed in consultation with MediaWorks are as follows:

Studio 1 Vibration monitor

Roof Noise monitor

Foundations Vibration monitor

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

61 of 73


D18.6 Contingency Measures As required by CRL condition 40.11, where any of the noise and vibration limits for Studio 1 in conditions 35.2, 35.3, 35.7 and 35.8 are exceeded, and where the noise and/or vibration levels are unacceptable to MediaWorks, the following corrective action measures shall apply: •

Cease the work giving rise to the exceedance as soon as safe and practicable to do so

•

Review the construction methodology, mitigation and management strategies to ensure they represent the BPO and reduce the noise or vibration levels.

•

Monitor to determine compliance once the remediation works are complete

•

Ensure that the work responsible for the exceedance is not recommenced during Sensitive Times

Table D18.6.1 details activities that are predicted to exceed the limits in D18.2 and the predicted effects. Table D18.6.2 provides a summary of consultation with MediaWorks representatives and identifies methods and measures to mitigate noise effects and a statement of why they reflect best practicable option. Table D18.6.1: Activity Detail (Noise) ** indicative examples only** #

Activity Details

Predicted Noise Effects

1

Activity Period Duration Days Hours

Rock breaking XX 201X – YY 201X X months Monday to Saturday X – Y hours

Location: Studio vibration level: Transfer Function: Reradiated noise level: Potential effects:

South façade 0.2mm/s PPV N/A 35 dB LAeq Effects on broadcast quality

2

Activity Period Duration Days Hours

X X X X X

Location: Studio vibration level: Transfer Function: Reradiated noise level: Potential effects:

X X X X X

Table D18.6.2: Consultation in accordance with CRL Conditions 16 and 40.6 **indicative examples only** #

Details

1

Date Name Phone Email CRL rep

Matters discussed DD/MM/YY X X X X

A. Works during Sensitive Times (excluding rock breaking) B. Communications Manger to liaise and provide monitoring results and notification of upcoming works C. Manage unnecessary impact sounds, e.g. careful handling and by using strops in place of chains Conclusion: Considered to be the BPO because it considers the needs of the stakeholder, ensures compliance and mitigates and manages the noise levels as far as practicable.

2

Date Name Phone Email CRL rep

DD/MM/YY X X X X

A. B. C. Conclusion:

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

62 of 73


APPENDIX E COMMUNICATIONS RECORDS Communications records are contained in the CRL C6 communication and consultation plan. CLG comments on this DWP are contained in Table 8 and the Independent peer review comments are included in Table 9. Table 8: CLG review comments Date

CLG Member

Comment

Response

14/11/2016

Margaret Main (email)

â&#x20AC;&#x153;Noise Management Plan. This indicated that there would be a meeting with residents/owners on site prior to the project to assess current noise levels and potential noise issues - how will this be arranged and when might this potentially happen??â&#x20AC;?

Matter addressed by others in relation to the Communications and Consultation Plan.

15/11/2016

N/A

N/A

Presented CNV DWP to CLG. Feedback received confirmed that notification in advance of predicted noise exceedances is considered to be a suitable and satisfactory management measure. Also identified that Beop studio is occasionally used for noise sensitive activities, however with advanced notification, adaptable and potentially accommodating of high noise periods.

Table 9: Independent peer review comments DWP Section

Comment

Response

2.4

Add Monitoring Manager details to Table 1

Role included, details to be confirmed once contractor is appointed

2.4

Add details to Table 1 for contact at Auckland Council for noise and vibration

Role included, details to be confirmed once contractor is appointed

3

Add reference to specific criteria in condition 35, and explanation why they are not applied (this is implicit from later sections but not in this section)

Not necessary and addressed in response to comment on Section 3.2.3 (refer response below).

3

Add figures that show and label all noise and vibration receivers

No change. The SSCNVMPs are based on the noise modelling in Appendix B which clearly identifies relevant sites/buildings.

3.2.2

Add reference to the other vibration criteria in condition 34.2

Included daytime criteria

3.2.3

The approach taken with respect to the MediaWorks site is technically appropriate. However, condition 40 could be interpreted as requiring a SSCVNMP regardless.

Section expanded to provide discussion on relevant of MediaWorks conditions specifically.

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

63 of 73


5.2

List sensitive times from condition 35.2 in the CNV DWP

Included.

5.5

Show on figures specific locations where site hoardings will be erected.

No change. The noise model includes indicative noise barrier locations. These will be updated when the contractor is appointed.

7

Even when measurements show there is compliance with limits, some management action may be appropriate. Add steps in Figures 3 and 4 for any noise and vibration management improvements identified to be implemented.

Figures 3 and 4 have been updated with a process to implement identified mitigation and management opportunities when compliant.

7

Add details of the noise and vibration monitoring equipment to be kept on site (or otherwise), and cross reference section 2.4 for trained staff.

No change. Unnecessary, but could be included once the contractor is appointed, details of equipment are known and staff are trained.

7

Add requirement for periodic/regular noise and vibration monitoring. Identify locations for periodic monitoring on a figure.

No change. Refer Sections 7.1 and 7.2 for general timing and locations. Specific times and locations are not practicable to determine in advance.

7

Add procedure for providing monitoring data to Auckland Council.

Added to last bullet point in Sections 7.1 and 7.2 respectively.

Appendix B

Noise barriers/hoardings have been modelled as continuous around work sites, inconsistent with the site plans which have large gaps for vehicle access. Adjust noise modelling to include realistic/consistent gaps in hoardings

No change. The noise model includes indicative noise barrier locations. These will be updated when the contractor is appointed. Gates should be noise barriers and closed when not in use.

Appendix F

Add condition 35 to Table 11

Not applicable. Only necessary in relation to Sensitive Times, however, this is included in the relevant section in response to Comment on Section 5.2.

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

64 of 73


APPENDIX F RELEVANT CONDITIONS Table 10 identifies the relevant CRL designation conditions and where they are addressed in the document. Table 10: CRL Conditions and CNV DWP section where addressed Condition Description

CNV DWP ref.

16

Communications – Notable Noise and Vibration Receivers

16.1

A SSCNVMP shall be prepared for all Notable Noise and Vibration Receivers (refer Condition 39). As part of the SSCNVMP (and further to Condition 15 of this designation), the Requiring Authority shall undertake communication and consultation, as soon as reasonably practicable (and at least once following confirmation of construction timing and methodology), with any Notable Noise and Vibration Receivers located within 200 metres of blasting, or within 100 metres (either horizontally or vertically) of the designation footprint for other construction activities. Communication and consultation with these parties should focus on a collaborative approach to manage the adverse effects from construction noise and vibration while works are undertaken in the vicinity

Section 3.2.3

16.2

The Requiring Authority shall undertake on-going communication and consultation with notable noise and vibration receivers throughout the duration of construction occurring in the vicinity. This communication shall be reported back to the “key contacts” (see Condition 13) and the Auckland Council Consent Monitoring officer for their review and confirmation of any further action to be undertaken. The Auckland Council Consent Monitoring Officer shall advise the Requiring Authority of its recommendation within 10 working days of receiving this information from the Requiring Authority.

Section 3.2.3

35

Project Standards – MediaWorks

35.1

The noise and vibration limits set out in Conditions 35.2 and 35.3 shall apply only during Sensitive Times. For the purposes of MediaWorks, Sensitive Times are defined as follows:

Appendix D18.2

(a) During scheduled live broadcasting (b) During emergency/breaking news live broadcasting (c) During scheduled recording sessions If the limits are complied with in Studio 1, the noise and vibration levels in all other Studios will be acceptable. For the avoidance of doubt, (a)-(c) above include sound checks as well as actual broadcast/recording time. 35.2

Noise Limits – Studios The noise level (whether air borne or reradiated from ground vibration) from all construction sources as received inside Studio 1 shall not exceed 30 dB LAeq (5 min) and 33 dB LAeq (1 sec). These limits apply to the construction component of the total noise. However for up to two periods of tunnelling, each no more than 15 consecutive days, the noise limits may be up to 5 decibels higher (ie. 35 dB LAeq (5 min) and 38 dB LAeq (1 sec)) during Sensitive Times, other than during the Live Broadcasting Periods as follows:

Appendix D18.2

(a) Weekdays: 0600-0900 hours 1200-1230 hours 1730-1930 hours 2230-2330 hours (b) Christmas holiday season (Saturday prior to Christmas Day to Sunday following New Years Day inclusive) and weekends: 1730-1900 hours This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

65 of 73


The Requiring Authority must give MediaWorks at least 12 days notice of the commencement of each such period. 35.2A

Rockbreaking shall not be used for tunnel excavation within 100m of the MediaWorks site during Sensitive Times unless compliance with the noise limits in Condition 35.2 can be demonstrated in accordance with the methodology set out in the SSCNVMP.

Appendix D18.4

35.3

Vibration Limits â&#x20AC;&#x201C; Studios For the protection of studio camera image quality, the construction vibration level (including blasting) as received inside Studio 1 shall not exceed 0.1mm/s PPV. This limit may be elevated by agreement of both the Requiring Authority and MediaWorks where image quality is found to be unaffected.

Appendix D18.2

35.4

Noise level measurements inside Studio 1 shall be undertaken at a position that is representative of the level received within 2m from, and at a similar height to, the microphone of the main presenter(s).

Appendix D18.2

35.5

Noise level measurements inside Studio 1 shall be undertaken with all doors to the studio closed.

Appendix D18.2

35.6

For the protection of amenity, the construction vibration level as received inside office areas, meeting rooms and technical suites shall not exceed 1mm/s PPV (as received on the floor of the receiving room) when those spaces are in use.

Appendix D18.2

35.7

For the protection of sensitive equipment, the construction vibration level (including blasting) shall not exceed 200mg (2m/s2) between 5-500Hz. Levels are to be measured on the floor supporting the Sensitive Equipment.

Appendix D18.2

35.8

All attended noise and vibration measurements shall be undertaken by a suitably qualified and experienced expert.

Appendix D18.5

35.9

For the avoidance of doubt, the MediaWorks conditions (Conditions 35, 40 and 66) only apply for so long as television, radio and/or interactive media facilities broadcast from the MediaWorks site.

N/A

35.10

Blasting shall not occur during MediaWorks Sensitive Times (as defined in Condition 35.1). Blasting shall occur at times to be agreed with MediaWorks and as documented in the SSCNVMP.

N/A

36

Construction Noise and Vibration DWP For the avoidance of doubt, this condition is applicable to the management of construction noise and vibration on all receivers, including sensitive and notable receivers.

36.1

A Construction Noise and Vibration DWP shall be prepared and implemented. The objective of the Construction Noise and Vibration DWP is to provide for the development and implementation of identified best practicable option to avoid, remedy or mitigate the adverse effects on receivers of noise and vibration resulting from construction.

This document

36.2

The Construction Noise and Vibration DWP shall:

Sections 3 & 5

a)

Adopt the noise and vibration standards for construction set out in Conditions 31, 32, 33 and 34 of these designations;

b) Be generally consistent with the draft Construction Noise and Vibration management plan submitted as part of the Notice of Requirement documentation (dated 23 August 2013); and c) 36.3

Identify methods to achieve best practicable option for mitigating adverse effects.

To achieve this objective, the Construction Noise and Vibration DWP shall include:

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

66 of 73


a) The roles and responsibilities of the noise and vibration personnel in the contractor team with regard to managing and monitoring adverse noise and vibration effects;

Sections 2 & 5

b) That piling and road cutting will be restricted to between the hours of 7am to 7pm, Monday to Saturday;

Section 5

c) Construction machinery and equipment to be used and their operating noise and vibration levels;

Section 4, Appendix B & C

d) Identification of construction activities that are likely to create adverse noise and vibration effects, the location of these in the construction site areas, and the distance to comply with the Project Criteria in Conditions 31, 32, 33 and 34;

Section 4, Appendix D

e) The timing of construction activities that are likely to create an adverse noise and vibration effect;

Section 4, Appendix D

f) The location of sensitive noise and vibration receivers;

Section 4, Appendix B, C, D

g) A record of communication and consultation with sensitive noise and vibration receivers. The record must include a clear explanation of where any comments from sensitive receivers have not been incorporated in the Construction Noise and Vibration DWP, and the reasons why not. This information must be included in the Construction Noise and Vibration DWP provided to both the Independent Peer Review Panel and Auckland Council as part of the Outline Plan process specified in Condition 11;

Section 6, Appendix E

h) Specific measures to address the concerns raised by those sensitive receivers;

Sections 6, 7, 8, Appendix D

i) Specific training procedures for construction personnel including;

Section 5

I. The project noise and vibration performance standards for construction (conditions 31, 32, 33 and 34); II. Information about noise and vibration sources within the construction area and the locations of sensitive noise and vibration receivers; and III. Construction machinery operation instructions relating to mitigating noise and vibration; j) Methods and measures to mitigate adverse noise and vibration effects including, but not limited to, structural mitigation such as barriers and enclosures, the scheduling of high noise and vibration construction, use of low noise and vibration machinery, temporary relocation of affected receivers or any other measures or offer agreed to by the Requiring Authority and the affected receiver;

Sections 5, 6, 7, Appendix B & C

k) The proposed methods for monitoring construction noise and vibration to be undertaken by a suitably qualified person for the duration of construction works including:

Sections 4, 7, 8, Appendix B - E

I. Updating the predicted noise and vibration contours based on the final design and construction activities; II. Confirm which buildings are to be subject to a pre and post building condition survey in accordance with Condition 46. This includes consideration of those buildings in Appendix One and Two to these conditions; III. The timing and location for monitoring of buildings during construction is required (Note that the flow charts contained in Appendices B and C of

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

67 of 73


Appendix J of the technical noise and vibration report provided as part of the Notice of Requirement should be used as a guide); IV. Identifying appropriate monitoring locations for receivers of construction noise and vibration; V. Procedures for working with the Communication and Consultation Manager to respond to complaints received on construction noise and vibration, including methods to monitor and identify noise and vibration sources; VI. Procedures for monitoring construction noise and vibration and reporting to the Auckland Council Consent Monitoring officer; and VII. Procedures for how works will be undertaken should they be required as a result of the building condition surveys; l) Cross references to the specific sections in the Communication and Consultation Plan which detail how landowners and occupiers are to be communicated with around noise and vibration effects.

Section 6, Appendix D

37

Site Specific Construction Noise Management Plan (SSCNMP)

37.1

The objective of a SSCNMP is to detail the best practicable option to avoid, remedy or mitigate adverse effects on a receiver resulting from construction noise that does not comply with the Project Noise Standards.

Appendix D

37.2

Further to the Construction Noise and Vibration DWP in Condition 36, a SSCNMP shall be prepared for any receiver or activity for which air overpressure is either predicted or measured to exceed the limits in Condition 32, or where construction noise is either predicted or measured to exceed the Project Noise Standards in Condition 31, except where the exceedance of the standards in Condition 31 is less than 5 decibels and does not exceed:

Sections 3, 4, Appendix D

a)

0700-2200: 1 period of up to 2 consecutive weeks in any 2 months

b) 2200-0700: 1 period of up to 2 consecutive nights in any 10 days. 37.3

For predicted exceedances of less than 5 decibels (refer 37.2) monitoring shall be undertaken to confirm the actual noise levels. If exceedance is shown to be more than 5 decibels, or the period exceeds those detailed, then a SSCNMP will be prepared.

Sections 7

37.4

In addition to the SSCNMPs prepared in accordance with Condition 37.2, and notwithstanding Condition 37.1, the Requiring Authority shall prepare SSCNMPs specifying the best practicable option for management, methods and measures to mitigate all noise effects for the properties located at:

N/A

a)

1 Queen Street (Lot 1 DP 165403);

b) 21 Queen Street (Lot 1 DP 67723); c)

29 Customs Street West (Lot 7 DP 77037)

d) 188 Quay Street (Lot 5 DP 63972 and Lot 1 DP 78340); and e) 37.5

23-29 Albert Street (Lot 1 DP 116724).

SSCNMPs will identify: a)

The extent to which noise may exceed the Project Noise Standards in Condition 31 or the overpressure limits in Condition 32;

Section 4, Appendix D

b) The timing and duration of any exceedance; c)

Details of the type of activity causing any exceedance;

d) The summary of the communication and consultation undertaken with the receiver. The summary must include a clear explanation of where any comments have not been incorporated, and the reasons why not. This information must be

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

68 of 73


included in the SSCNMP provided to both the Independent Peer Review Panel and Auckland Council as part of the Outline Plan process specified in Condition 11; e)

The methods and measures to mitigate noise effects, including but not limited to, potential to offer temporary relocation of affected receivers, alternative ventilation, faรงade sound insulation improvements, building condition surveys in the case of overpressure generated by blast events, or other offers made by the Requiring Authority and whether these have been agreed to by the affected receiver;

f)

The reasons why the management and mitigation measures and methods reflect best practicable option.

37.6

The SSCNMP shall be submitted for the review of Auckland Council as part of the Outline Plan. The works shall then be undertaken in accordance with the SSCNMP confirmed by the Requiring Authority as part of the Outline Plan.

38

Site Specific Construction Vibration Management Plan (SSCVMP)

38.1

The objective of a SSCVMP is to detail the best practicable option to avoid, remedy or mitigate adverse effects on a receiver resulting from vibration that does not comply with the Project Vibration Standards.

Appendix D

38.2

Further to the Construction Noise and Vibration DWP in Condition 36, a SSCVMP shall be prepared:

Sections 3, 4, 6 Appendix D

a)

Section 8

For any unoccupied buildings, structure or infrastructure for which construction vibration is either predicted or measured to exceed the Project Vibration Standards in Condition 33;

b) Where a complaint or concern is raised and the vibration level exceeds the amenity levels of Condition 34.2(a) and 34.2(b); c)

In response to other concerns or complaints where required (refer to Condition 17); and

d) For the properties listed in Condition 37.4. 38.3

Where the amenity limits in Conditions 34.2(a) and 34.2(b) are exceeded: a)

Section 3

Best practicable management of vibration must be applied; and

b) The vibration activity shall be scheduled to avoid disturbance. If this is not practicable then reasonable respite periods shall be provided to reduce vibration exposure. 38.4

The limits in condition 33 may be relaxed by a SSCVMP but only for a building, structure or infrastructure that has been assessed by a suitably qualified and experienced structural engineer and where it has been deemed to be capable of withstanding higher vibration levels without sustaining building or structural damage, and where appropriate vibration and building condition monitoring regimes are in place.

Section 3

38.5

SSCVMPs will identify:

Section 4, Appendix D

a)

The timing and duration of any exceedance;

b) Details of the type of activity giving rise to any exceedance; c)

Site Specific vibration criteria that addresses the issue(s) of concern (i.e. building damage, amenity and sensitive equipment). Site Specific criteria shall be determined by a suitably qualified independent vibration expert;

d) The summary of the communication and consultation undertaken with the receiver. The summary must include a clear explanation of where any comments have not been incorporated, and the reasons why not. This information must be included in the SSCVMP provided to both the Independent Peer Review Panel and Auckland Council as part of the Outline Plan process specified in Condition 11; This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

69 of 73


e)

The methods and measures to mitigate vibration effects, including but not limited to, investigating alternative low-vibration construction methods, undertaking highvibration works outside sensitive times, vibration barriers, building condition surveys, potential to offer temporary relocation of affected receivers, or other offers made by the Requiring Authority and agreed to by the affected receiver.

f)

The reasons why the management and mitigation measures and methods reflect best practicable option.

38.6

The SSCVMP shall be submitted for the review of Auckland Council. The works shall then be undertaken in accordance with the SSCVMP confirmed by the Requiring Authority as part of the Outline Plan.

39

Notable Noise and Vibration Receivers

Section 8 & 9, Appendix D

For the avoidance of doubt, Conditions 39.5 and 39.6 do not apply to MediaWorks. 39.1

Further to Condition 36, the Requiring Authority and its contractor, in conjunction with a suitably qualified expert, shall work collaboratively with each notable receiver during the preparation of a SSCNVMP to confirm the extent and management of adverse effects on each Notable Receiver

Appendix D18.3

39.2

In addition to the Construction Noise and Vibration DWP, a SSCNVMP shall be prepared for each identified Notable Receiver. The objective of the SSCNVMP is to detail the best practicable option to avoid, remedy or mitigate adverse noise and vibration effects on each Notable Receiver.

Appendix D18.1

39.3

The Requiring Authority shall consult with the notable receiver throughout the duration of construction and update the SSCNVMP as required to achieve the objective in 39.2.

Appendix D18.1

39.4

The SSCNVMP shall include:

Appendix D18

a)

The level at which noise and vibration effects on the notable receiver will unreasonably interfere with its operation. This will enable development of the site specific criteria. In the case of MediaWorks this is set out in Condition 40;

b) Construction activities and equipment which are likely to create adverse noise and vibration effects and the location and timing of these in relation to the notable receiver; c)

The methods and measures associated with the worksite including, but not limited to, structural mitigation such as barriers and enclosures, use of low noise and vibration machinery and the scheduling of high noise and vibration construction;

d) The methods and measures associated with the notable receiver building or operation including, but not limited to, potential for isolation of sensitive areas and equipment, dampening of reradiating surfaces and temporary relocation of affected receivers that are proposed to minimise adverse noise and vibration effects on the notable receiver;

39.5

e)

Details about the methods to be adopted by the Requiring Authority to minimise construction noise and vibration effects on the notable receiver and the anticipated effectiveness of those methods;

f)

A summary of the communication and consultation undertaken with the notable receiver. The summary must include a clear explanation of where any comments have not been incorporated, and the reasons why not;

g)

Offers made by the Requiring Authority to the notable receiver to mitigate effects and the response by the operators, such as relocation, and whether those offers were accepted or not by the notable receiver;

If the parties cannot agree on any of the matters above they shall each appoint a suitably qualified and independent expert, who shall jointly appoint an independent and

N/A

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

70 of 73


suitably qualified third expert who shall certify the following matters to be included in the SSCNVMP: a)

The level at which noise and vibration effects on the notable receiver unreasonably interfere with its operation (the certified noise and vibration limit);

b) The mitigation methods and measures within the worksite (at source) including, but not limited to, structural mitigation such as barriers and enclosures, use of low noise and vibration machinery and the scheduling of high noise and vibration construction; c)

The mitigation methods and measures at the notable receiver including but not limited to: isolation of sensitive areas and equipment; dampening of reradiating surfaces; any response to such offers; and temporary relocation of affected receivers;

d) Whether or not the mitigation methods and measures reflect best practicable management; and e)

Whether or not the residual effects are likely to cause significant disruption to the activities of the notable receiver.

39.6

Following the above process the SSCNVMP shall be submitted for the review of Auckland Council as part of the Outline Plan. For the avoidance of doubt, the Requiring Authority shall not be entitled to make any changes to the SSCNVMP through the Outline Plan process following any agreement reached with the notable receiver and/or through the above certification process without the consent of the notable receiver. The works shall then be undertaken in accordance with the SSCNVMP confirmed by the Requiring Authority as part of the Outline Plan process.

40

Construction Noise and Vibration Management Plan – Medial Works

N/A

Further to Condition 36, a SSCNVMP shall be prepared for the MediaWorks site implementing the project standards in Condition 35. 40.1

The MediaWorks SSCNVMP shall identify high noise or vibration plant and machinery, and list the relevant items that require testing in accordance with Condition 40.4 and 40.8.

Appendix D18.4

40.2

Prior to any demolition or construction commencing, the Requiring Authority shall undertake a noise survey to determine the Transmission Loss (TL) performance of the MediaWorks building envelope. This testing shall only be undertaken outside of Sensitive Times.

Appendix D18.4

40.3

Prior to any demolition or construction commencing, the Requiring Authority shall undertake a vibration survey to determine the transfer function of the MediaWorks building structure from ground vibration outside the building to reradiated noise in Studio 1. This testing shall only be undertaken outside of Sensitive Times.

Appendix D18.4

40.4

All high noise plant and machinery to be used at a location where it is predicted to generate noise levels in excess of 3 dB below the limits specified in Condition 35.2 shall be tested prior to use, to determine its Sound Power Level (Lw) at a sufficient distance from the MediaWorks building to ensure compliance. These measured Lws shall be used to predict the noise level at the MediaWorks building façade(s) from proposed construction scenarios. The façade TL (refer Condition 40.2) shall then be applied to predict the noise levels in the relevant rooms.

Appendix D18.4

40.5

All high noise plant and machinery may not be used until Condition 40.4 is satisfied, taking into account the cumulative noise levels from active sources on the site.

Appendix D18.4

40.6

The Requiring Authority and its contractor, in conjunction with a suitably qualified expert, shall work collaboratively with MediaWorks during the preparation of a SSCNVMP to confirm the extent and management of adverse effects on MediaWorks.

Appendix D18.3

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

71 of 73


40.7

The SSCNVMP shall set out the requirements for monitoring, the number of monitors, the instrument location, any adjustments necessary if a proxy position is required and any other procedures or requirements that are necessary. The data shall be available in real time to the Requiring Authority, Auckland Council and MediaWorks.

Appendix D18.5

40.8

Prior to the use of any high vibration equipment to be used at a location where it is predicted to generate vibration levels greater than 75% of the Condition 33-35 limits relating to the MediaWorks building, the Requiring Authority shall undertake vibration measurements at a sufficient distrance from the MediaWorks building to ensure compliance. These measurements shall be used to determine minimum set-back distances from the building to avoid potential exceedances of the vibration limits in Conditions 35.3, 35.6, 35.7 and 35.8. Reradiated noise values in Studio 1 shall be calculated using the measured transfer function, as required by Condition 40.3. The results of the testing and the outcomes affecting construction operations shall be set out in the SSCNVMP

Appendix D18.3

40.9

The noise and vibration levels from construction shall be monitored to determine compliance with conditions 35.2 35.3, 35.6, 35.7 and 35.8 continuously by automated noise and vibration monitors located at positions that will represent the noise and vibration level in the relevant spaces and for the relevant noise and vibration limits. The SSCNVMP shall set out the requirements for monitoring, the instrument location, any adjustments necessary if a proxy position is required and any other procedures or requirements that are necessary including methods to exclude extraneous sources. The data shall be available in real time to the Requiring Authority, Auckland Council and MediaWorks.

Appendix D18.2

40.10

Monitoring to determine compliance or otherwise with Condition 35.6 relating to office amenity shall only be undertaken in response to complaints from MediaWorks. The measurements must be attended by a suitably qualified person.

Appendix D18.2

40.11

The SSCNVMP shall set out corrective action measures that must be adopted in situations where any of the noise and vibration limits in Conditions 35.2, 35.3, 35.6, 35.7 and 35.8 are exceeded and where the noise and/or vibration levels are unacceptable to MediaWorks. The corrective action measures must include the following:

Appendix D18.2

(a) Immediate cessation of the work(s) that is giving rise to the exceedance; (b) A procedure to require the implementation of whatever measures are necessary to reduce the noise or vibration levels; (c) A monitoring procedure to determine compliance (once the remediation works are complete); (d) A requirement to ensure that the work(s) responsible for the exceedance are not recommenced during Sensitive Times; (e) A complaints procedure that is capable of effecting the immediate cessation of works including making a point of contact directly available 24 hours, seven days a week. 40.12

If there is a disagreement between the Requiring Authority and MediaWorks as to the content of the SSCNVMP, they shall each appoint a suitably qualified and independent expert, who shall jointly appoint an independent and suitably qualified third expert who shall certify the matters set out in Condition 40.11 and any other matters in dispute in the SSCNVMP.

Appendix D18.2

40.13

Following the above process the SSCNVMP shall be submitted for the review of Auckland Council as part of the Outline Plan. For the avoidance of doubt, the Requiring Authority shall not be entitled to make any changes to the SSCNVMP through the Outline Plan process following any agreement reached with MediaWorks and/or through the above certification process without the consent of MediaWorks. The works

Appendix D18.2

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

72 of 73


shall then be undertaken in accordance with the SSCNVMP confirmed by the Requiring Authority as part of the Outline Plan process.

This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited Rp 002 r8.0 2016651A cmf (Construction Noise and Vibration Delivery Work Plan).docx

73 of 73


Turn static files into dynamic content formats.

Create a flipbook
Construction noise and vibration DWP by City Rail Link Ltd - Issuu