Skip to main content

Construction Noise and Vibration Delivery Work Plan

Page 1

Mt Eden Main Works Construction Noise and Vibration Delivery Work Plan

CRL-MTE-RME-LKA-PLN-800036

Revision: 001B Date: 30 July 2020

Page 1

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

Construction Noise and Vibration Delivery Work Plan CRL-MTE-RME-LKA-PLN-800036

This document is uncontrolled when printed. This document should be printed in colour

Revision Status Revision

Date

Version details

Prepared By

Approved By

Rev A00

23 April 2020

Draft for Auckland Council Independent Peer Review

James Whitlock

-

Rev 000

16 June 2020

Final for Lodgement

James Whitlock

Peter Roan

Rev 001

29 June 2020

Final for submission

James Whitlock

Peter Roan

Rev 001A

22 July 2020

Update to address IPR and Council review

Craig Fitzgerald James Whitlock

Peter Roan

Rev 001B

30 July 2020

Update to address IPR and Council review

Craig Fitzgerald

Peter Roan

and

Approval Status Name/Title Prepared by:

James Whitlock

Signature

Date 30 July 2020

Acoustic Consultant Reviewed by:

Craig Fitzgerald

30 July 2020

Acoustic Consultant Approved by:

Peter Roan Consenting Lead

Page 2

| Mt Eden Main Works CNV DWP

30 July 2020


Construction Noise and Vibration Delivery Work Plan

Table of contents How to use this document ................................................................................ 5 1. Introduction ................................................................................................ 6 1.1

Overview of CRL Works in Mt Eden ................................................................................... 6

1.2

CNV DWP Staging .............................................................................................................. 7

1.3

Purpose of this CNV DWP .................................................................................................. 7

1.4

Relevant Conditions .......................................................................................................... 8

1.5

Sustainability ..................................................................................................................... 8

1.6

DWP Review and Updates ................................................................................................. 8

2. Mt Eden Main Works Description ............................................................... 9 2.1

Overview of Works ............................................................................................................ 9

2.2

Site Description ................................................................................................................. 9

2.3

Construction Staging and Methodology .......................................................................... 10

2.4

Transitioning from Early Works to Main Works ............................................................... 11

3. Key Personnel ........................................................................................... 12 4. Performance Standards ............................................................................ 13 4.1

Noise ............................................................................................................................... 13

4.2

Vibration ......................................................................................................................... 14

4.3

Blasting ............................................................................................................................ 15

4.4

MediaWorks .................................................................................................................... 16

5. Receivers and Building Types .................................................................... 17 5.1

Notable Receivers............................................................................................................ 17

5.2

Sensitive Receivers .......................................................................................................... 17

5.3

Full List of At-Risk Receivers ............................................................................................ 17

6. Risk assessment - Noise ............................................................................ 22 6.1

High-Noise Equipment ..................................................................................................... 22

6.2

Noise Sources for Each Stage of Works............................................................................ 23

7. Risk assessment - Vibration ...................................................................... 27 7.1

High-Vibration Equipment ............................................................................................... 27

7.2

Vibration sources for each works stage ........................................................................... 27

8. Blasting...................................................................................................... 29 8.1

Trial Blasts ....................................................................................................................... 29

9. Mitigation and Management .................................................................... 30 Page 3

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan 9.1

Training ........................................................................................................................... 30

9.2

Construction Hours.......................................................................................................... 30

9.3

Equipment Selection........................................................................................................ 31

9.4

General Mitigation Measures .......................................................................................... 31

9.5

Noise Barriers and Enclosures ......................................................................................... 32

9.6

Concrete and Paver Cutting ............................................................................................. 33

9.7

Concrete and Rock Breaking ............................................................................................ 33

9.8

Piling................................................................................................................................ 34

9.9

Blasting ............................................................................................................................ 34

9.10 Vibro-Rolling.................................................................................................................... 34

10. Communication ......................................................................................... 36 10.1 Communication Overview ............................................................................................... 36 10.2 Complaints Response ...................................................................................................... 37

11. Monitoring ................................................................................................ 38 11.1 Noise ............................................................................................................................... 38 11.2 Vibration ......................................................................................................................... 39

12. Effects in Buildings .................................................................................... 41 12.1 Noise Inside Buildings ...................................................................................................... 41 12.2 Vibration Inside Buildings ................................................................................................ 42 12.3 Management of Adverse Effects ...................................................................................... 43

Appendix A: Glossary of Terminology ............................................................. 44 Appendix B: CRL Designation Conditions for noise and vibration .................. 46 Appendix C: Site Specific Management Plans (SSCNVMPs) ............................ 62 Appendix D: Project Sustainability .................................................................. 63 Appendix E: Consultation Records .................................................................. 64

Page 4

E.1

CLG Comments ................................................................................................................ 64

E.2

Independent peer review Comments .............................................................................. 64

E.3

Auckland Council ............................................................................................................. 69

E.4

Mana Whenua ................................................................................................................. 75

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

How to use this document This Construction Noise and Vibration Delivery Work Plan (CNV DWP) will be read by people with different levels of expertise and understanding of the CRL main construction works at Mt Eden. Constructors, Link Alliance environmental and compliance personnel, Auckland Council, experts and affected parties must all be able to extract the information they need from the DWP. The primary function of the CNV DWP is to advise the constructor about the location of sensitive noise and vibration receivers, and what management and mitigation measures will be used to reduce adverse effects on those receivers. These measures have been chosen because they are the Best Practicable Option (BPO) and/or because of agreements with certain affected parties. If the Link Alliance communications team receives a noise or vibration complaint, this CNV DWP is the primary reference document.

If you are the constructor: -

Note Section 4.1 – 4.3 for the project noise and vibration limits Note Sections 6.1 and 7.1 for high noise and vibration activities, and safe distances. Check to make sure all relevant activities have been included Note Section 5.3 for list of affected receivers. Make sure they have been consulted with Note each SSCNVMP relating to receivers near your worksite. Make sure each SSCNVMP is up to date with methodology, consultation outcomes etc

If you are in the Link Alliance communication team or the Mt Eden CLG: -

Note Section 3 to see which Link Alliance and Auckland Council personnel to contact if you have concerns Note Section 6.1 and 7.1 for high noise and vibration activities See who is included in Section 5.3 – the list of affected receivers Refer to the SSCNVMPs in Appendix C to understand what has been discussed and agreed with receivers

If you are involved in the regulatory process: -

Page 5

Review Appendix B for the Designation Conditions Review Sections 6.1 and 7.1 for high noise and vibration activities, and safe distances Review Section 5.3 for list of affected receivers Review each SSCNVMP relating to any receivers of interest

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

1. Introduction The City Rail Link (CRL) project comprises the construction, operation and maintenance of a 3.4 km underground passenger railway, running between Britomart Station and the North Auckland Rail Line (NAL) in the vicinity of Mt Eden Station. The CRL also involves the construction of two new underground stations at Aotea and Karangahape and a redeveloped Mt Eden Station (refer to Figure 1-1). The design and construction of the CRL infrastructure between the Aotea and Mt Eden Stations is being delivered by the Link Alliance (LA).

Figure 1-1: CRL Route and Location

This Construction Noise and Vibration Delivery Work Plan (CNV DWP) has been prepared in relation to the Mt Eden Main Works (“main works”). This CNV DWP will become the overarching management document for all CRL constructions works in Mt Eden (excluding future public realm reinstatement works) – including enabling and early works that started before the main works.

1.1 Overview of CRL Works in Mt Eden CRL works in the Mt Eden area involve the construction of the southern section of the tunnel structures and the tie-in of the CRL railway to the existing NAL, including the construction of the redeveloped Mt Eden Station. The Mt Eden Active Construction Zone (ACZ) and Construction Support Areas (CSAs) are generally located between Nikau Street to the north, State Highway 1 (SH1) to the east, Dominion Road to the west and the existing NAL to the south. The works in this area include: • • Page 6

Operational activity required to support the tunnel boring machine (TBM) drive, including control room and plant, storage and spoil handling; Construction of a new Mt Eden Station building, incorporating passenger linkages between the new CRL platform and the modified existing NAL platform;

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan • •

• • • •

Road over rail bridges at Mt Eden Road, Normanby Road and Ruru Street with sections of road realignment; Grade separation structures for the existing and new rail lines to pass-over and connect with each other, including the Newton Junction Grade Separation Structure, the Eastern Facing Connection and the Western Facing Connection; Construction of a portal vent house building structure; Installation of retaining walls and utilities; Pedestrian and cyclist bridge structures at Fenton Street and Porters Avenue; and New road linkages within the reinstated area post-construction.

Given the nature and scale of CRL construction works in Mt Eden, works are being undertaken in a staged manner, involving: • •

•

Enabling and early works (demolition, network utility relocation and site establishment work) – early works have commenced and will continue to the end of 2020 Main construction works (construction of the underground CRL cut-and-cover tunnels, grade separation structures and trenches, station building and platforms, and tie-ins to the NAL) to commence mid-2020 through to mid-2023 Public realm reinstatement – likely from 2021 to early 2024

1.2 CNV DWP Staging To reflect the staged construction approach for CRL in the Mt Eden area, a series of CNV DWPs are being prepared. This CNV DWP addresses the potential noise and vibration exceedances related to the main works, which are detailed in the Construction Environmental Management Plan (CEMP) and summarised in Section 2 of this CNV DWP. If required, a CNV DWP will also be prepared for the future public realm reinstatement.

1.3 Purpose of this CNV DWP The purpose of this CNV DWP is to identify and provide for implementation of the Best Practicable Option (BPO) to avoid, remedy or mitigate adverse noise and vibration effects resulting from construction during the main works. These functions are required by CRL designation Condition 36. It identifies the noise and vibration performance standards and details the management and control methodologies to be implemented in order to achieve compliance. Where compliance cannot practicably be achieved, it identifies BPO mitigation measures to be implemented on a site-specific basis, and general mitigation measures to be put in place as best practice. This CNV DWP addresses the requirements of designation conditions 31 – 40 for CRL Designation 2500-6 at Mt Eden and will be implemented throughout the entire construction period. It will be the primary tool for managing construction noise and vibration effects resulting from the main works. This CNV DWP has been prepared in consultation with numerous stakeholders – noise and vibration receivers, the CRL Mana Whenua Forum, and the Mt Eden Community and Business Liaison Group – and has been reviewed by the Independent Peer Reviewer prior to submission to Auckland Council (as per CRL designation conditions 7 and 11). Page 7

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan Records of the consultation and review outcomes, including the Link Alliance’s response to matters raised, are included in Appendix E. This CNV DWP has been prepared by the Link Alliance and forms part of the CEMP for the main works.

1.4 Relevant Conditions Appendix B outlines the CRL designation conditions relevant to this CNV DWP and where they are addressed in the document. CRL construction works at Mt Eden are being undertaken in both CRL Designation 2500-6 and KiwiRail’s Designation 6300 for the existing North Auckland Railway Line (NAL). Construction occurring inside CRL Designation 2500-6 is governed by the CRL designation conditions, whereas construction in the existing railway corridor is governed by the NAL designation conditions. Because the construction activities in both CRL Designation 2500-6 and NAL Designation 6300 are often continuous or occur so closely to one another, any affected noise and vibration receivers could not tell them apart. As a consequence, a pragmatic management approach has been adopted. The same triggers and management methodologies under the CRL designation conditions will be applied to works within the existing railway corridor, to ensure a consistent approach to managing all CRL construction noise and vibration effects at Mt Eden.

1.5 Sustainability The Link Alliance is seeking an Infrastructure Sustainability Council of Australia (ISCA) Infrastructure Sustainability (IS) Rating for the main works. Further details can be found in the CEMP and Sustainability Management Plan. Main works sustainability requirements that relate directly to this CNV DWP are included in Appendix D. These requirements are imbedded within the Delivery Work Plans and Management Plans to ensure that sustainability is a key focus and ‘the way we do things’. In some cases, the IS requirements and sustainability goals enhance the designation and consent requirements.

1.6 DWP Review and Updates This CNV DWP is a live document that will be reviewed at least annually, or: • • •

as a result of a material change to the main works to address unforeseen adverse noise and vibration effects arising from construction or unresolved complaints

Refer to sections 1.9 and 6.7 of the CEMP for further detail on the review and updating process.

Page 8

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

2.

Mt Eden Main Works Description 2.1 Overview of Works

The main works involve construction along several active work fronts concurrently within the Mt Eden area at any one time, to enable the redevelopment of Mt Eden Station and establish the CRL tie-ins to the NAL. Works will be carried out in a staged fashion. The construction staging and methodologies are described in greater detail in the CEMP. Within the main works area, there are already other works occurring in accordance with the Mt Eden Enabling Works (OPW60350039) and Normanby Road Early Works (OPW60351423) outline plan packages. This CNV DWP has been prepared to address the cumulative effect where the main works and those works overlap each other. This CNV DWP has been prepared to address the entire main works area as outlined in Figure 2-1. In summary, the main works involve: • •

• • • • • •

Ground improvements, in the form of deep soil mixing (contiguous piling and grout injection), within the NAL corridor between Mt Eden Road Bridge and Normanby Road; Bulk excavations and construction of retaining walls along the NAL to provide for the rail trenches and installation of new tracks. The excavation will encounter basalt, which will be removed via rock-breaking and blasting. In places, softer ground conditions are anticipated to be encountered, which may require the use of sheet piles; Construction of the eastern and western crossover structures that enable the CRL rail lines to tie-in to the NAL; Construction of the Porters Avenue and Fenton Street pedestrian and cyclist bridges. Construction of the Normanby Road grade separation bridge, including regrading of Normanby Road and realigning the Boston Road roundabout; Redevelopment of the existing NAL platform; Construction of the CRL platform and the foundations and building structures for the Mt Eden Station building and the ventilation building; and Operation of the TBM, including the conveying of spoil material from the tunnels and the refuelling and general maintenance of the TBM within CSA 4.

2.2 Site Description The main works will be undertaken in the vicinity of the existing Mt Eden Station and along the NAL, in an existing urban environment. The main works area is generally bounded by the NAL (south), State Highway 1 (east), Dominion Road (west), and Nikau Street (north). The main works will include construction activity along Nikau Street, Ruru Street, Porters Avenue, Fenton Street, Haultain Street, Ngahura Street, Flower Street, Shaddock Street, Mt Eden Road, Normanby Road, Boston Road and Nugent Street.

Page 9

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

CRL Designation 2500-6 KiwiRail Designation 6300

Figure 2-1: Site and extent of main works

2.3 Construction Staging and Methodology The main works will be divided into several stages across the various work areas. Generally, the works along the NAL are divided into two stages to allow works on the northern (downmain) or southern (upmain) sections to correspond with the ‘single line running’ of train services through the construction area. Works within the Mt Eden Station area are divided into 12 stages. Stages 1-4 have already been addressed in the Mt Eden Enabling Works outline plan package, and stages 5-12 will be undertaken as part of the main works. For the new Mt Eden Station building and ventilation building, construction of the foundations and building structures will be undertaken as part of stages 5-12, while the finishing of the buildings, including internal and external fittings, will be completed as part of the future public realm reinstatement. The construction staging and methodologies are described in sections 2.3 and 2.4 of the CEMP. The night and weekend works (during NAL block-of-line periods) are summarised below.

2.3.1. Night and Weekend Works (Block-of-line periods) Normal hours of works are 7am to 10pm Monday to Friday and 7am to 7pm Saturday. Limited construction works (e.g. oversized plant delivery, Block of Line (BOL) works, or off-peak network utility works) may be undertaken outside the typical working hours. This is to enable worker safety or to minimise traffic disruption, in accordance with the CRL designation and resource Page 10

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan consent conditions. Operating procedures will be implemented, including communication with affected residents and businesses, to minimise any potential disturbance. Like many projects, Mt Eden main works construction is restricted at night, during weekends and public holidays because they are times of rest. But there will be times during the main works when night, weekend and public holiday construction cannot be avoided, for the following reasons: •

•

Work in the NAL railway corridor needs to occur when the trains are not running, but the NAL will remain open and active for the duration of construction. This means that BOL periods are critical times for construction. These occur during public holidays, weekends and night-times – because the commuter demand is much less – so the main works must provide for some construction during these times Some construction activities – such as trenching, tunnelling and some forms of piling – need to be completed once they have begun because, if they stop, there is a risk of ground collapse or subsidence

Section 9.2 of this CNV DWP sets out construction hours and noise and vibration conditions that require specific timing. Section 9.2.2 provides guidance for works when they must happen at night.

2.4 Transitioning from Early Works to Main Works Two enabling/early works packages at Mt Eden have been addressed in separate Outline Plans and have their own CNV DWP and associated SSCNVMPs. Those works and their DWP references are: • •

Normanby Road Early Works – CRL-MTE-RME-LKA-PLN-800007 Mt Eden Enabling Works – CRL-MTE-RME-LKA-PLN-800016

This main works CNV DWP will become the overarching management document for both the early works and main works, addressing the cumulative effects where the works overlap.

Page 11

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

3.

Key Personnel

The key personnel responsible for this CNV DWP are listed in Table 3-1. Refer to the CEMP for further detail on roles and responsibilities. Table 3-1: Key Personnel and contact details

Role NAL Main works Managers NAL - EFC1 (and WFC2) Main works Manager

Name Glen Kirk glen.kirk@linkalliance.co.nz +64 27 500 1744

NAL - EFC2 Main works Manager

Francois Pageron francois.pageron@linkalliance.co.nz +64 22 547 9013

MTN/Mt Eden Station (and WFC1) Main works Manager

Thibaut L’Hopital thibaut.l’hopital@linkalliance.co.nz +64 27 564 5756

NAL Construction Manager

Nick Adams nick.adams@linkalliance.co.nz

Environment and Sustainability Manager

Sarah Sutherland sarah.sutherland@linkalliance.co.nz

Mt Eden Main Works Senior Communications and Engagement Advisor NAL Community Manager

Sonya Leahy sonya.leahy@linkalliance.co.nz Helen Jansen helen.jansen@linkalliance.co.nz

Acoustics Specialist

James Whitlock - Marshall Day Acoustics james.whitlock@marshallday.co.nz

Environmental Advisor – Mt Eden Station

Craig Campbell craig.campbell@linkalliance.co.nz

Auckland Council Compliance and Monitoring Officer

Timothy O’Grady Timothy.ogrady@aucklandcouncil.govt.nz 021 834 584

CRL Hotline / Email Address

0800 CRL Talk (0800 275 8255) mteden@linkalliance.co.nz

Page 12

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

4.

Performance Standards 4.1 Noise 4.1.1. Construction Noise

The relevant Project Construction Noise Standards in CRL designation condition 31 can be found in Appendix B. They are summarised in Table 4-1 below. Construction noise shall be measured and assessed in accordance with the provisions of New Zealand Standard NZS 6803:1999 “Acoustics - Construction Noise”. These noise limits apply at 1m from any façade of a receiver. If any construction activity cannot practicably comply with these limits, it must be mitigated as far as practicable using the measures outlined in this CNV DWP. Specific management for identified noise receivers is outlined in the Site-Specific Construction Noise Management Plan (SSCNMP) for these receivers – see Section 4.1.2 and Appendix C. Table 4-1: CRL Designation Condition 31.1 - Construction Noise Limits

Monday to Saturday

Sundays and Public Holidays

At all other times

0700 – 2200

0700 – 2200

2200 – 0700

Occupied commercial and industrial buildings (including offices)

75 dB LAeq

75 dB LAeq

75 dB LAeq

Sensitive Noise and Vibration Receivers (excluding offices)

75 dB LAeq

60 dB LAeq

60 dB LAeq

90 dB LAFmax

75 dB LAFmax

75 dB LAFmax

Receiver Type

Bear Park Early Childhood Education Centre at 32 Akiraho Street (whilst occupied during normal opening hours)

35 dB LAeq in sleeping areas 65 dB LAeq in outdoor playing areas

4.1.2. Site Specific Construction Noise Management Plans (SSCNMP) Any predicted or measured noise exceedance must have an SSCNMP, in accordance with CRL designation condition 31, except where condition 37.2 applies – when the exceedance is less than 5 decibels and the activity does not exceed: • •

0700 – 2200: 1 period of up to 2 consecutive weeks in any 2 months 2200 – 0700: 1 period of up to 2 consecutive nights in any 10 days

In this case, monitoring shall be undertaken to confirm the actual noise levels (refer Section 11.1 of this CNV DWP). If an exceedance of noise level (i.e. condition 31 + 5 decibels) or time period occurs, then an SSCNMP must be prepared. The objective of an SSCNMP is to detail the best practicable option(s) (BPO) to avoid, remedy or mitigate adverse effects on a receiver resulting from a construction noise exceedance. SSCNMPs shall identify the following matters, as outlined in Condition 37: •

Page 13

The relevant activity, timing, duration and predicted magnitude of exceedance (Section 5.3 and Section 6.2); | Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan • •

A summary of communication and consultation undertaken with the receiver (SSCNMPs in Appendix C); The specific methods or measures employed to mitigate the noise effects (Section 9 and SSCNMPs in Appendix C).

A site-specific plan may address both construction noise and vibration, in which case it would be a SSCNVMP. All site-specific management plans prepared for the main works are attached in Appendix C.

4.2 Vibration 4.2.1. Cosmetic Building Damage The Project cosmetic building damage standards are specified in CRL designation condition 33.1. They are summarised in Table 4-2. Construction vibration shall be measured and assessed in accordance with German Standard DIN 4150-3:1999. If any construction activity cannot practicably comply with these limits, it must be mitigated as far as practicable using the measures outlined in this CNV DWP. Specific management for identified vibration receivers is outlined in the Site-Specific Construction Vibration Management Plan (SSCVMP) for these receivers – see Section 4.2.3 and Appendix C. Table 4-2: Project Construction Vibration Limits (Cosmetic Building Damage)

Short-term (transient) vibration1

Type of Structure

Long-term (continuous) vibration

PPV at PPV at horizontal horizontal plane plane of highest floor 50 – 100 Hz of highest floor

PPV at the foundation at a frequency of 1 – 10 Hz

10 – 50 Hz

(mm/s)

(mm/s)

(mm/s)

(mm/s)

(mm/s)

Commercial/Industrial

20

20 – 40

40 – 50

40

10

Residential/School

5

5 – 15

15 – 20

15

5

Historic or Sensitive Structures

3

3–8

8 – 10

8

2.5

4.2.2. Vibration Amenity The Project vibration amenity standards are specified in CRL designation conditions 34.1 and 34.2. These limits apply only in response to a complaint from a building occupant (CRL designation condition 34.3): •

1

Between 10pm and 7am vibration generated by construction activities (excluding blasting) shall not exceed:

Standard DIN 4150-3:1999 defines short-term (transient) vibration as “vibration which does not occur often enough to cause structural fatigue, and which does not produce resonance in the structure being evaluated”. Long-term (continuous) vibration is defined as all other vibration types not covered by the short-term vibration definition. Page 14 | Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

•

−

A peak particle velocity (PPV) of 0.3 mm/s when measured at any part of the floor of any bedroom

−

A noise level of 35 dB LAeq(15min) when measured in any bedroom

Between 7am and 10pm vibration generated by construction activities (excluding blasting) shall not exceed: −

A PPV of 1mm/s as measured on the floor of the receiving room for residentially occupied habitable rooms, bedrooms in temporary accommodation and medical facilities

−

A PPV of 2mm/s as measured on the floor of the receiving room for retail and office spaces (including work areas and meeting rooms)

4.2.3. Site Specific Construction Vibration Management Plans (SSCVMP) The objective of a SSCVMP is to detail the best practicable option(s) (BPO) to avoid, remedy or mitigate adverse effects on a receiver resulting from construction vibration that does not comply with the Project Vibration Standards in CRL designation conditions 33 or 34, or in response to other concerns or complaints in accordance with condition 17.1(c). SSCVMPs shall identify the matters outlined in CRL designation condition 38 – summarised as follows: • • •

The relevant activity, timing, duration and predicted magnitude of exceedance (Section 5.3 and Section 7.2) A summary of communication and consultation undertaken with the receiver (SSCVMPs in Appendix C) Site specific vibration criteria, methods or measures that addresses the issue(s) of concern (i.e. building damage, amenity or sensitive equipment).

A site-specific plan may address both construction noise and vibration, in which case it would be a SSCNVMP. All site-specific management plans prepared for the main works are attached in Appendix C.

4.3 Blasting The Project blasting standards are specified in CRL designation condition 32, and apply unless a SSCNVMP that includes an alternative blasting vibration standard is approved under CRL designation conditions 38, 39 or 40.

4.3.1. Blasting Overpressure Blasting overpressure shall not exceed the limits in Table 4-3 when measured and assessed in accordance with the provisions of Australian Standard AS 2187.2 – 2006 Explosives – storage and use Part 2: Use of explosives. Table 4-3: CRL Designation Condition 32.2 and 32.3

Receiver Type

Noise limit (dB LZpeak)

Air overpressure from blast events at façade of occupied buildings

120

Air overpressure from blast events at façade of unoccupied buildings

133

Page 15

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

4.3.2. Blasting Vibration 5.3.2.1

Cosmetic building damage

Blasting vibration shall not exceed the short-term limits in Table 4-4 when measured at the foundation of any building. Table 4-4: Project Blasting Vibration Limits (Cosmetic Building Damage)

Type of Structure

Short-term (transient) vibration PPV at the foundation at a frequency of

PPV at horizontal plane of highest floor

1 – 10 Hz

10 – 50 Hz

50 – 100 Hz

(mm/s)

(mm/s)

(mm/s)

(mm/s)

Commercial/Industrial

20

20 – 40

40 – 50

40

Residential/School

5

5 – 15

15 – 20

15

Historic or Sensitive Structures

3

3–8

8 – 10

8

5.3.2.2

Amenity

Blasting vibration shall not exceed 10mm/s PPV for 95% of blast events and 15 mm/s for 100% of blast events. Vibration shall be measured at the foundation of any occupied building, and measured and assessed in accordance with DIN 4150-3:1999.

4.4 MediaWorks The MediaWorks buildings at 3 Flower St, 71 Boston Road and 155 New North Road are notable receivers (as defined in the CRL designation conditions) because they are recording studios. Condition 16 states that a SSCNVMP must be prepared for any notable receivers within 100 metres of the designation footprint. Accordingly, SSCNVMPs have been prepared and are attached Appendix C1 (3 Flower St & 155 New North Rd) and Appendix C24 (71 Boston Road). The MediaWorks radio station Radio Tarana is at 155 New North Road. They have been consulted with, and are happy to be included in the SSCNVMP for 3 Flower St.

Page 16

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

5. Receivers and Building Types 5.1 Notable Receivers There are three ‘notable noise and vibration receivers’ in the vicinity of the main works, as defined in the CRL designation conditions. They are: • • •

MediaWorks at 3 Flower Street The Project (MediaWorks) recording studio at 71 Boston Road The Radio Tarana (MediaWorks) studio at 155 New North Road

Condition 16 states that a SSCNVMP must be prepared for any notable receivers within 100 metres of the designation footprint for construction activities (and 200 metres for blasting). Condition 40 requires an SSCNVMP for the MediaWorks building at 3 Flower St in any case. Accordingly, SSCNVMPs have been prepared and are attached Appendix C1 (3 Flower St & 155 New North Rd) and Appendix C24 (71 Boston Road). The MediaWorks radio station Radio Tarana is at 155 New North Road. They have been consulted with, and are happy to be included in the SSCNVMP for 3 Flower St.

5.2 Sensitive Receivers ‘Sensitive receivers’ are defined in the CRL designation conditions. They include dwellings, offices, schools, libraries, hospitals, rest homes, marae and other cultural centres, churches, hotels and other accommodation facilities. For the CRL Mt Eden works: • •

• • •

There are many offices along the alignment. They will be most sensitive to noise and vibration effects during the daytime There are 10 apartment complexes and 2 standalone dwellings with line-of-sight to the worksites. The majority are at the western end by the Porters Avenue intersection. Dwellings will be most sensitive at night There is one early childhood centre - Bear Park at 32 Akiraho Street. It has its own set of noise limits to protect daytime sleeping. Refer CRL designation condition 31.1 5 Porters Avenue is a community mental health outpatient clinic operating 24 hours 7 days a week Mt Eden Corrections Facility includes accommodation units and offices, though their layout is not yet known. It is reasonable to consider these as sensitive receivers. The old prison building has a Category 1 heritage listing and is potentially sensitive to construction vibration effects

5.3 Full List of At-Risk Receivers All receiver types (noise) and building types (vibration) where noise and/or vibration levels are predicted to exceed the Project standards are shown in Figure 5-1 and listed in Table 5-1. Table 5-1 also indicates which works packages will be the cause of exceedances. Receivers are numbered according to their SSCNVMP number in Appendix C of this CNV DWP. The noise and vibration sources that are predicted to cause exceedances at these receivers are listed in Sections 6.1 and 7.1. Page 17

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

Figure 5-1: Receivers – Numbered according to their SSCNVMP number

Page 18

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan Table 5-1: Receiver and Building Types, and their SSCNVMP number

2

Utilities and Drainage

Porters Bridge

Fenton Bridge

Porters & Fenton bridges Night Works

Normanby Road

Station Platform

1

MediaWorks

2 Flowers Street

Notable – Commercial

Commercial

5

House of Knives

24 Mt Eden Road

Retail/Commercial

Commercial

✓

6

110 New North Road

110 New North Road

Retail/Commercial

Commercial/Industrial

✓

9

2 Porters Ave

2 Porters Ave

Retail/Commercial

Commercial/Industrial

✓

✓

✓

✓

10

Kennards Self Storage

3 Porters Ave

Retail/Commercial

Commercial/Industrial

✓

✓

✓

✓

11

A+DF Workshop

4 Porters Ave

Retail/Commercial

Commercial/Industrial

✓

✓

✓

✓

12

Auckland DHB Mental Health Services

5 Porters Ave

Commercial

Commercial

✓

✓

✓

✓

✓

13

Eden North Apartments

6 Porters Ave/3 Ngahura Street

Sensitive – Residential

Residential

✓

✓

✓

✓

✓

14

1 Wynyard Ave

1 Wynyard Ave

Sensitive – Residential

Residential

✓

✓

✓

15

2 Wynyard Ave

2 Wynyard Ave

Sensitive – Residential

Residential

✓

✓

✓

16

Dawsons Catering

3 Fenton Street

Retail/Commercial

Commercial

✓

✓

✓

✓

17

Business Relocations

5a Fenton Street

Retail/Commercial

Commercial

✓

✓

✓

✓

✓

18

Fraser Powrie Barristers and Solicitors

5 Fenton Street

Retail/Commercial

Commercial

✓

✓

✓

✓

✓

19

Station R apartments

11 Fenton Street

Sensitive – Residential

Residential

✓

✓

✓

✓

20

2 Haultain Street

2 Haultain Street

Retail/Commercial

Commercial/Industrial

✓

✓

✓

✓

21

Bear Park

32 Akiraho Street

Sensitive - Childcare

Commercial

22

140 New North Road

140 New North Road

Sensitive – Residential

Residential

✓

✓

✓

23

Auckland Chinese Community Centre

101 Mount Eden Rd

Retail/Commercial

Commercial

24

The Project (Mediaworks)

71 Boston Road

Notable – Commercial

Commercial

25

The Horse & Trap Bar

3 Enfield St

Retail/Commercial (bar)

Commercial

✓

26

8 – 12 Boston Road

8 – 12 Boston Road

Commercial

Commercial

✓

27

IMeasureU

5 – 7 Water Street

Retail/Commercial

Commercial

✓

28

Miro Apartments

25 – 27 Enfield St

Sensitive – Residential

Residential

✓

29

22 – 24 Normanby Road

22 – 24 Normanby Road

Sensitive – Residential

Residential

✓

30

Sen Vietnamese Kitchen & Bar

26 Normanby Road

Retail/Commercial

Heritage (Colonial Ammunition Company Shot Tower)

Based on known occupancies Based on known heritage status or structural engineer preliminary recommendation Page 19 | Mt Eden Main Works CNV DWP 3

Ground Improvements

Building Type (vibration)3

Utilities and drainage

Receiver Type (noise)2

Excavation

Address

Retaining wall

SSCNVMP number Site Name (Appendix C)

Excavation and piling

Vibration Exceedance Predicted from Activity

Noise Exceedance Predicted from Activity

✓

✓

✓ ✓ ✓ ✓

✓

✓

✓

✓

✓

✓

✓ ✓

✓

✓

✓

✓

✓

✓

✓

✓

✓

✓

✓

✓

✓ ✓

✓

✓

✓

✓

✓

✓


Construction Noise and Vibration Delivery Work Plan

Page 20

✓

OfficeMax

32 Normanby Road

Retail/Commercial

Commercial/Industrial

✓

✓

✓

32

Corys Electrical and Sabato

51 - 63 Normanby Road

Retail/Commercial

Commercial/Industrial

✓

✓

✓

33

2 – 42 Harold Street

2 – 42 Harold St

Sensitive – Residential

Residential

✓

34

BDG Architects, SDM Law

2 Enfield St

Commercial

Commercial

✓

35

Normanby Road Vet Clinic

49 Normanby Road

Commercial

Commercial

✓

✓

36

Eden Oaks Apartments

1 Akiraho St

Sensitive – Residential

Residential

✓

37

3 Akiraho St Apartments

3 Akiraho St

Sensitive – Residential

Residential

✓

38

Brothers Brewery

5 Akiraho St

Commercial

Commercial

39

Regal Castings

7-9 Akiraho St

Commercial

Commercial

✓

40

Greenpeace

11 Akiraho St

Commercial

Commercial

✓

41

Gate Automation

13 Akiraho St

Commercial

Commercial

✓

✓

✓

✓

✓

42

1 Fenton St

1 Fenton St

Commercial

Commercial

✓

✓

✓

✓

✓

43

1 Porters Ave

1 Porters Ave

Commercial

Commercial

✓

✓

✓

44

1A Porters Ave

1A Porters Ave

Commercial

Commercial

✓

✓

✓

45

14 Haultain St

14 Haultain St

Commercial

Commercial

✓

✓

46

Crescendo Enterprises

12 Haultain St

Commercial

Commercial

✓

47

City Kickboxing

10 Haultain St

Commercial

Commercial

✓

48

Urban Gourmet

8 Haultain St

Commercial

Commercial

✓

49

Auckland Boxing Association

1 Ngahura St

Commercial

Commercial

✓

50

Omron Electronics/ PDQ Print

65 Boston Rd

Commercial

Commercial

51

Boston Wardrobes

57 Boston Rd

Commercial

Commercial

✓

52

Atelier Textiles

55 Boston Rd

Commercial

Commercial

53

Mt Eden Prison

Lauder Rd

Commercial/Residential

54

2 Akiraho St

2 Akiraho St

55

4 Haultain Street

56

Utilities and Drainage

Porters Bridge

✓

✓

✓

✓

✓ ✓

✓

✓

✓

✓ ✓

✓

✓

✓

✓

✓

✓

✓

✓

Heritage (old prison)

✓

✓

✓

Sensitive – Residential

Residential

✓

4 Haultain St

Commercial

Commercial

✓

✓

✓

✓

6 Haultain Street

6 Haultain St

Commercial

Commercial

✓

✓

✓

✓

57

Mt Eden Automotive

18 Mt Eden Rd

Commercial

Commercial

✓

58

Khyber Automotive

20-22 Mt Eden Rd

Commercial

Commercial

✓

| Mt Eden Main Works CNV DWP

Fenton Bridge

Excavation and piling

Porters & Fenton bridges Night Works

31

✓

✓

Vibration Exceedance Predicted from Activity

Normanby Road

Station Platform

Building Type (vibration)3

Ground Improvements

Receiver Type (noise)2

Utilities and drainage

Address

Excavation

SSCNVMP number Site Name (Appendix C)

Retaining wall

Noise Exceedance Predicted from Activity

✓

✓

✓


Construction Noise and Vibration Delivery Work Plan

Page 21

59

103 Mt Eden Rd

103 Mt Eden Rd

Sensitive – Residential

Residential

✓

61

Dress for Success

4 Boston Rd

Commercial

Commercial

✓

62

6 Boston Rd

6 Boston Rd

Commercial

Commercial

63

Designer Hire

31 Boston Rd

Commercial

Commercial

✓

64

Exit Films

33 Boston Rd

Commercial

Commercial

✓

65

Electrical Tool Services

35 Boston Rd

Commercial

Commercial

✓

66

Seventh Day tattoo studio

39 Boston Rd

Commercial

Commercial

✓

✓

✓

67

Ilabb clothing

41 Boston Rd

Commercial

Commercial

✓

✓

✓

68

Boxing Central

43 Boston Rd

Commercial

Commercial

✓

✓

✓

69

J.A. Russell Ltd

45 – 53 Boston Rd

Commercial

Commercial

✓

70

7 Fenton Street

7 Fenton Street

Commercial

Commercial

✓

71

27 Brentwood Ave

27 Brentwood Ave

Sensitive – Residential

Residential

✓

72

29 Brentwood Ave

29 Brentwood Ave

Sensitive – Residential

Residential

✓

73

31 Brentwood Ave

31 Brentwood Ave

Sensitive – Residential

Residential

✓

74

3 Wynyard Rd

3 Wynyard Rd

Sensitive – Residential

Residential

75

4 Wynyard Rd

4 Wynyard Rd

Sensitive – Residential

76

5 Wynyard Rd

5 Wynyard Rd

77

Aisha motors/Ace Consultants Ltd

78

✓

✓

✓ ✓

✓ ✓

✓

✓

✓

✓

Residential

✓

✓

✓

Sensitive – Residential

Residential

✓

✓

✓

112 New North Rd

Commercial

Commercial

33 Brentwood Ave

33 Brentwood Ave

Sensitive – Residential

Residential

✓

79

Brentwood Avenue Seventh-day Adventist Church

35 Brentwood Ave

Commercial

Commercial

✓

80

6 Wynyard Rd

6 Wynyard Rd

Sensitive – Residential

Residential

81

ECC Ltd

39 Nugent St

Commercial

Commercial

82

7 Wynyard Rd

7 Wynyard Rd

Sensitive – Residential

Residential

| Mt Eden Main Works CNV DWP

✓

✓

✓

✓ ✓

✓ ✓

Utilities and Drainage

Porters Bridge

Fenton Bridge

Excavation and piling

Porters & Fenton bridges Night Works

Vibration Exceedance Predicted from Activity

Normanby Road

Station Platform

Building Type (vibration)3

Ground Improvements

Receiver Type (noise)2

Utilities and drainage

Address

Excavation

SSCNVMP number Site Name (Appendix C)

Retaining wall

Noise Exceedance Predicted from Activity


Construction Noise and Vibration Delivery Work Plan

6. Risk assessment - Noise 6.1 High-Noise Equipment Indicative sound levels of equipment proposed for the Mt Eden main works are presented in Table 6-1. The levels assume no shielding – to provide a conservative risk assessment – and are predicted at various setback distances. The distance required to meet 75 dB (the most common daytime noise limit) is also given. Table 6-1 will be used by the Project Manager (or nominated person) to identify which equipment will require mitigation and/or management, and when. The table will be kept up to date by the Acoustics Specialist when new information becomes available through noise monitoring (Section 11.1) or other means. Table 6-1 Indicative noise levels for proposed equipment (no shielding assumed)

Equipment

4

Sound Power

Façade Noise Level (dB LAeq)

Limit Setback (m)

(dB LwA)

10m

20m

50m

100m

75 dB LAeq

Large rock breaker4 (20-30T)

121

96

90

81

73

83

Vibratory sheet piling

116

91

85

76

65

52

Concrete cutting

115

90

84

75

67

48

Bored piling (50T)

112

87

81

72

64

36

Deep Soil Mixing Rig

112

87

81

72

64

36

Small concrete/rock breaker (1-5T)

111

86

80

71

63

33

Diaphragm Wall Piling

109

84

78

69

61

28

Bored piling (40T)

109

84

78

69

61

28

Plate compactor

108

83

77

68

60

25

Hydrovac excavation

107

82

76

67

59

22

Mobile Crane (300T)

106

81

75

66

58

20

Concrete truck and pump

103

78

72

63

63

14

Static/vibratory roller

103

78

72

63

55

14

Excavator (20T)

103

78

72

63

63

14

Excavator (5T)

102

77

71

62

62

13

Mobile Crane (50T)

95

70

64

55

47

6

Generator (150kVA)

93

68

62

53

53

4

Pump (150mm dia)

93

68

62

53

53

4

Compressor

93

68

62

53

53

4

Breaking solid rock. Breaking fractured rock may be up to 10-15 decibels quieter

Page 22

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan The work sites will be screened by noise barriers (Section 9.5) where practicable. The barriers are effective at mitigating the noise levels received by passing pedestrians and occupants of ground floor levels in buildings (including via open shop doors). However, they provide little benefit for upper floor levels or buildings on higher ground that can look over the barriers to the works. Effective noise barriers reduce noise levels by 10 decibels – provided they block line-of-sight from source to receiver. This would reduce the setbacks in Table 6-1 by 2/3 (e.g. 30m without screening vs 10m with screening).

6.2 Noise Sources for Each Stage of Works The following sections present the proposed equipment for each stage of the main works. The equipment in bold were deemed to be significant sources of noise and were the basis of noise modelling. Through modelling we have generated figures showing buildings where noise standards are at risk of exceedance from each works stage. These figures also show the assessed location of equipment/noise sources. They can be accessed via the Link Alliance GIS portal: Provide hyperlink here.

The noise predictions are worst-case, with equipment positioned as close to receivers as the worksites allow, and no shielding. SSCNMPs will be required for the buildings where exceedances are predicted, as indicated in Table 5-1, unless the constructor can confirm that noisy equipment will work outside the setback distances shown in Table 6-1.

6.2.1. Utilities and Drainage Note that some of these works were assessed as part of previous works packages. More information can be found in the Mt Eden Enabling Works and Normanby Road CNV DWPs (CRL-MTE-RME-LKAPLN-800016 and CRL-MTE-RME-LKA-PLN-800007). Equipment required for this stage of works is understood to include: •

Concrete saws

•

Excavators of various sizes (5 – 25 tonne) with breaker attachments

•

3.5t loaders with forks and bucket

•

Plate compactors

•

Hydroexcavators

•

Hiabs (crane truck)

Activities are predicted to generally comply, provided they are undertaken in a manner consistent with the measures in Section 9 of this CNV DWP. The predictions represent the highest noise levels from a series of activity positions to provide a reasonable ‘worst-case’ envelope.

Page 23

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

6.2.2. Mt Eden Road Bridge, Eastern and Western Crossover Structures Equipment required for this stage of works is understood to include: •

SR 50 bored piling rigs

•

Excavators (5-20 tonne)

•

Concrete pump

•

30T mobile crane

•

8 wheeler trucks

Piling will only occur 7am – 7pm Monday – Saturday, unless the BPO demonstrates that it is required outside of these hours. Due to the location and equipment associated with these works, they will be relatively quiet and compliance is predicted for all receivers.

6.2.3. Ground Improvements Equipment required for this stage of works is understood to include: •

RG-39 Deep Soil Mixing rig

•

20T excavator

•

Grout mixing plant and pumps

•

Compressors, generators and agitators

6.2.4. Retaining Walls Equipment required for this stage of works is understood to include: •

Piling rigs (SR-40 & LB-28) with vibro-hammer

•

35 tonne excavator (block wall construction)

•

50T crawler crane

•

Concrete pumps

•

Trucks

•

10 tonne roller

Piling will only occur 7am – 7pm Monday – Saturday, unless the BPO demonstrates that it is required outside of these hours. The excavation works may involve blasting – refer Section 9.

Page 24

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

6.2.5. Bulk Excavation Equipment required for this stage of works is understood to include: •

6t – 40 tonne excavators

•

Rocker breakers of varying sizes for 6 ‐ 30t excavators

•

Trucks

•

8‐10t vibratory compaction rollers

•

400kg plate compactors

•

Down the hole hammer rig

The excavation works may involve blasting – refer Section 9.

6.2.6. Porters Avenue and Fenton Street Pedestrian Bridges Equipment required for this stage of works is understood to include: •

Piling Rigs (SR45, SR50, R516)

•

Cranes (20 – 450 tonne)

•

Excavators (8 – 10 tonne) with breaker attachments

•

Trucks and trailers

•

Concrete trucks & pumps

Piling will only occur 7am – 7pm Monday – Saturday, unless the BPO demonstrates that it is required outside of these hours. This stage of works is to include cranage at night (covered in Table 5-1 as “nightworks”).

6.2.7. Normanby Road Grade Separation and utilities bridge Equipment required for this stage of works is understood to include: •

Piling Rig (SR45 & SR30)

•

Cranes (30 – 300 tonne)

•

Excavators (6 – 20 tonne)

•

Trucks and trailers

•

Concrete trucks & pumps

•

Compactors

Piling will only occur 7am – 7pm Monday – Saturday, unless the BPO demonstrates that it is required outside of these hours. This stage of works is to include cranage at night (covered in Table 5-1 as “nightworks”).

Page 25

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

6.2.8. Station Platforms Equipment required for this stage of works is understood to include: •

Piling Rig (SR30)

•

Excavator (20 tonne)

•

Crane (30 tonne)-

•

Concrete pump

Piling will only occur 7am – 7pm Monday – Saturday, unless the BPO demonstrates that it is required outside of these hours. Proposed activities at this worksite are relatively quiet, with only excavators and trucks in use. However, the worksite shape means it comes close to a number of buildings.

6.2.1. TBM Spoil Removal Equipment required for this stage of works is understood to include: •

Excavators

•

Piling rigs

•

TBM (and associated plant e.g. cooling)

•

Spoil conveyor

•

Cranes

Piling and excavator use on this site were assessed as part of the Mt Eden Enabling works. The TBM, conveyor, and other associated plant will run 24 hours a day. As such, mitigation measures, such as enclosures and barriers, will be designed to achieve compliance with night-time noise standards at all adjacencies.

Page 26

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

7. Risk assessment - Vibration 7.1 High-Vibration Equipment Table 7-1 provides indicative construction vibration levels for proposed activities that have the potential to result in vibration in building structures. It will be used by the Project Manager (or nominated person) prior to construction to inform what equipment will require mitigation and/or management and when. This table will be kept up to date by the Acoustics Specialist when new information becomes apparent through vibration monitoring (Section 11.2) or other means. Table 7-1 Indicative vibration set back distances from typical equipment

Vibration Source

Stage(s)

Cosmetic building damage set back distance (m) Heritage buildings (2.5 mm/s PPV)

Residential buildings (5mm/s PPV)

Commercial buildings (10 mm/s PPV)

Sheet piling

Retaining walls and bulk excavation (between CH9960 - CH10020)

30

11

4

Large rock breaker (20-30T)

Enabling works – utilities and drainage

16

10

7

Retaining walls and bulk excavation (between CH10450 – CH10980) Fenton St and Porters Ave bridges Vibro roller (8T)5

Retaining walls and bulk excavation

15

10

5

Vibrated pile casings

Retaining walls and bulk excavation

15

6

3

Large plate compactor Enabling works – utilities (400kg) and drainage

10

6

3

Retaining walls and bulk excavation (between CH10450 – CH10980) Down-the-hole piling rig

Retaining walls and bulk excavation

No data yet – will be measured the first time it is used

7.2 Vibration sources for each works stage The following sections present the high-vibratory activities for each stage of the main works. The vibration predictions are worst-case, with activities positioned as close to receivers as the worksites allow.

5

Heavier 10T rollers are proposed. These may generate higher vibration levels so must be measured the first time they are used, and the data added to Table 7-1. Page 27 | Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan SSCVMPs will be required for the buildings where exceedances are predicted, as indicated in Table 5-1. Building condition surveys will be carried out for all buildings where exceedances are predicted, in accordance with Condition 46. Buildings listed in Appendix 2 of the Designation Conditions also require condition surveys. Figures showing buildings that are at risk of exceedance can be accessed via the Link Alliance GIS portal. Not all stages of main works have high-vibration equipment proposed – and in some areas this is because an alternative method is proposed to minimise effects. An example of this is the station platforms stage, where rock removal is expected but a hydraulic splitter is proposed instead of rock breaking. This technique should be used in other stages to reduce vibration risk if necessary. Specific mitigation and management measures for rock breaking, piling, vibro-rolling and blasting are included in Section 9 of this CNV DWP.

7.2.1. Retaining walls and bulk excavation This works stage will include: sheet piling (between CH9960 - CH10020), rock breaking (between CH10430 – CH10980), vibro-rolling, vibro-piling, and compaction (between CH10430 – CH10980).

7.2.2. Enabling works – utilities and drainage: Porters Ave This works stage will include rock breaking, compaction and down the hole hammer piling. No vibration data is currently available for down the hole hammer piling. The predicted exceedances are conservative and the risk will be reassessed once vibration data has been measured.

7.2.3. Fenton St & Porters Ave bridge This works stage will include rock breaking.

Page 28

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

8. Blasting Blasting is proposed as an effective method to remove basalt from the worksites between Dominion Road and Mount Eden Road. The work will be done by a blasting contractor. It is their responsibility to design and carry out the blasting programme so that vibration and air overpressure comply with the limits in CRL designation condition 32. The blasting contractor has prepared a Blasting Management Plan (BMP) refer document CRL-MTEERW-LKA-CWP-800000. It identifies the geology, drill and blast methodology, safety control measures, compliance limits and other management protocols for the blasting programme. It will be kept up to date by the blasting contractor. The blasting area is shown in the ‘Drill and Blast Methodology’ section of the BMP. The BMP states that “all blasts will be designed to be fully compliant with all applicable standards. Particular attention will be given to the local residence and Media Works NZ to minimise effects and disruption”. Despite predicted compliance, it states: “A Dilapidation Report will be commissioned by Link Alliance covering the following affected buildings”: • • • •

Residential properties on Shaddock street, Nikau street, Ruru street, Ngahura street, Akiraho street, Mount Eden road Media works NZ Commercial properties Shaddock street, Nikau street, Ruru street, Ngahura street Akiraho street Mt Eden train station platform and lines

8.1 Trial Blasts Trial blasts were carried out by Red Bull Powder Company Ltd on 5 February 2020 in order to measure the way vibration propagates through the basalt in the Mt Eden works area. The findings are summarised in Red Bull’s report ‘Link Alliance – 97 Mt Eden Rd Seed Hole Analysis’, dated February 2020. This was the first stage in the blasting process, and small amounts of explosive (charge weights) were used to minimise vibration and noise. The blasting contractor uses this data to calculate the maximum instantaneous charge weight (MIC) for each blast – the maximum amount of explosive that can be used while still achieving compliance. The trial blasts showed that compliance with the building damage limits is predicted within: • • •

50 metres for an MIC of 0.6kg 70 metres for an MIC of 1.2kg 100 metres for an MIC of 2.5kg

Subsequent production blasts in June 2020 were compliant with the building damage limits. Vibration levels remain the controlling factor. Blasting overpressure can be sufficiently suppressed through use of blast mats and overburden. Specific mitigation and management recommendations for blasting are listed in Section 9.9, and in the BMP. Page 29

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

9. Mitigation and Management 9.1 Training All staff will participate in an induction training session when they commence work on the main works. The induction will include a briefing on this CNV DWP, with attention given to the following matters: • • • • •

•

Roles and responsibilities for management of noise and vibration Construction noise and vibration limits Information about noise and vibration sources on-site Noise and vibration mitigation and management procedures The sensitivity of receivers to noise and vibration (including MediaWorks), and any operational requirements and constraints identified through communication and consultation Complaints management procedures

Awareness of current noise and vibration matters on, or near active worksites, will be addressed during site meetings and/or ‘toolbox’ training sessions.

9.2 Construction Hours 9.2.1. General Timing of Works Table 9-1 shows the general construction hours, and any special conditions related to timing. Table 9-1 Construction hours and conditions that require specific timing

Activity

Days

Times

Condition: Comment

General hours

Monday to Saturday:

0700 – 1900 hrs 1900 – 2200 hrs 0700 – 2200 hrs

31: Prioritise. 31: Minimise where practicable. 31: Minimise where practicable. 31: Avoid where practicable. 35.2: Amended by MediaWorks SSCNVMP in Appendix C1.

Sunday

2200 – 0700 hrs 0600 – 0915 hrs 1600 – 1700 hrs 1730 – 1915 hrs 2020 – 2330 hrs 0900 – 1230 hrs 1700 – 1915 hrs 1700 – 1915 hrs

Piling and road cutting

Monday to Saturday

0700 – 1900 hrs

36.3 (b): Restricted period.

Concrete/rock breaking

Monday to Saturday

Avoid Sensitive Times

35.2A: Within 100m of the MediaWorks building unless monitoring verifies compliance with the limits in Condition 35.2.

Blasting

Monday to Saturday

1032 and 1432 hrs as agreed with MediaWorks

32.6 and 35.10: Avoid MediaWorks Sensitive Times (above) during daylight hours.

MediaWorks Sensitive Times (3 Flower St)

Sundays & Public Holidays All other times (night) Monday to Friday

Saturday

Page 30

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

9.2.2. Night-time, Sunday and Public Holiday Works Normal hours of works are 7am to 7pm Monday to Saturday, extending to 10pm if required. After 10pm, the approach to night works will be as follows: • • • •

Avoid where practicable Where required, review the construction methodology to identify high noise activities that can be prioritised before 10pm, preferably before 7pm Minimise the duration of high noise activities Minimise the number of periods (e.g. complete high noise activity in one extended period rather than two shorter periods with the same overall duration)

Note that people tend to be less disturbed by low frequency, continuous engine noise, than intermittent noise or activities with special audible character (e.g. reversing beepers, whistling or shouting).

9.3 Equipment Selection Some activities have the potential to exceed the limits for construction noise and vibration at close nearby receiver distances. It is essential that appropriate mitigation and management measures are identified and employed in advance of the works to avoid exceedances. When selecting construction equipment: • • • • •

Equipment will be suitably sized for the proposed task Equipment will be well maintained Exhaust silencers will be fitted Fit or upgrade engine covers in consultation with equipment manufacturer where appropriate Substitute diesel engines with electric motors where practicable

9.4 General Mitigation Measures Best Practical Option (BPO) mitigation will be implemented throughout the construction programme to avoid exceedances. This will include, but not be limited to the following: • • • •

• • • • Page 31

Keep the construction time near noise sensitive areas to a minimum Avoid unnecessary noise, such as shouting, the use of horns, loud site radios, rough handling of material and equipment, and banging or shaking excavator buckets Avoid metal on metal contact where practicable by minimising drop height of materials, such as during loading and unloading of trucks Tonal reversing alarms shall be prohibited on site. Suitable alternatives may include flashing lights, broadband audible alarms or reversing cameras inside vehicles. Staff acting as spotters are mandatory for reversing equipment Mitigate track squeal from tracked equipment, such as excavators and piling rigs. This may include tensioning and watering or lubricating the tracks regularly Avoid high engine revs where practicable through appropriate equipment selection and turn engines off when idle / parked Avoid steep internal haul routes and keep the road surface smooth and well maintained Maximise the distance between the noise source and the nearest sensitive receiver by positioning fixed plant away from sensitive receivers, or orienting machinery to maximise | Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

• • • • •

the distance between the engine exhaust and the nearest sensitive building façade where practicable (e.g. bored piling rig, excavators and mobile cranes) Crane and secure loads using straps in preference to chains where safe and practicable Utilise power from the national grid in preference to generators where practicable Utilise noise barriers and enclosures where effective (Section 9.5) Implement further measures identified through communication and consultation with sensitive receivers (Section 10) Undertake noise and vibration monitoring to confirm compliance or identify high noise and/or vibration machinery (Section 11)

9.5 Noise Barriers and Enclosures Site boundary fences will be constructed, or existing fences upgraded as required, to provide effective noise mitigation during construction. Temporary noise barriers will be used where a construction noise limit is predicted to be exceeded and the barriers would noticeably reduce the construction noise level. Noise barriers will be installed prior to works commencing and be maintained throughout the works. Effective noise barriers typically reduce the received noise level by 10 decibels. The following guidelines will be incorporated in the design and utilisation of noise barriers: •

The panels will be constructed from materials with a minimum surface mass of 6.5 kg/m 2, including the following proprietary ‘noise curtains’: -

• • • •

Duraflex ‘Noise Control Barrier - Premium Series’ (www.duraflex.co.nz) Soundex ‘Acoustic Curtain - Performance Series' (www.ultimate-solutions.co.nz) Flexshield ‘Sonic Curtain with 4 kg/m2 mass loaded vinyl backing’ (www.flexshield.co.nz) Alternatives will be approved by a suitably qualified acoustic specialist because some proprietary noise curtains have insufficient surface mass for general use

The panels will be a minimum height of 2m, and higher if practicable to block line-of-sight The panels will be abutted or overlapped to provide a continuous screen without gaps at the bottom or sides of the panels The panels will be positioned as close as practicable to the noisy construction activity to block line-of-sight between the activity and noise sensitive receivers Where positioned on the site boundary, additional local barriers will be considered near the activity to ensure effective mitigation for sensitive receivers on upper floor levels

Noise enclosures surround the sound source with noise barriers on more than one side and include a ‘roof’. The effectiveness of noise enclosures depends on the extent that the source can be enclosed without constraining the operation of the equipment and resulting in an unacceptable occupational health and safety environment (e.g. noise exposure, heat, dust, poor lighting etc). Enclosures can also result in traffic management issues and increase construction duration for short term or transient activities. The following guidelines will be incorporated in the design and utilisation of noise enclosures: •

Page 32

Enclosures will be used for stationary plant where a noise barrier is not sufficient to achieve compliance with the noise limits and it is practicable to do so (e.g. fixed paver cutting stations, pumps, spoil handling conveying equipment etc). | Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan •

•

The enclosure can be erected using the noise curtains listed above, or alternatively, the following proprietary cutting station ‘noise enclosures’ can be used: −

Echo Barrier ‘Cutting Station’ (www.supplyforce.co.nz)

−

Soundex ‘E6/2 Quick-Tech Cutting Enclosure' (www.ultimate-solutions.co.nz)

−

Hushtec ‘Acoustic Tent’ (www.duraflex.co.nz) Alternatively, a suitably qualified and experienced acoustic specialist (such as MASNZ) will be involved in the custom design of the enclosure (an example is included as Figure B.3 in NZS 6803:1999).

9.6 Concrete and Paver Cutting • •

• •

Use noise enclosures where practicable, otherwise barriers (Section 9.5) Minimise the concrete cutting period, and, the number of cutting periods (e.g. complete all cutting in one extended period rather than two shorter periods with the same overall duration) Select blades that are sharp, maximise the number of teeth, minimise the blade width, minimise gullet depth, and have built in vibration damping slots Use a unit fitted with a blade shroud and operate with a water supply

9.7 Concrete and Rock Breaking Avoid MediaWorks broadcast ‘Sensitive Times’ for breaking within 100m of the MediaWorks studios (at 3 Flower St and 71 Boston Road), unless monitoring verifies compliance with the limits in designation Condition 35.2. Refer their SSCNVMPs in Appendices C1 and C24. Other general measures include the following: • • •

• •

• • •

Page 33

Use local noise barriers to screen the breaker tip where practicable For concrete breaking near buildings, an initial perimeter saw cut will be made at the perimeter to reduce vibration transfer For rock breaking, initial breaking will be undertaken at the perimeter of the rock face closest to neighbouring buildings where practicable. This will enable monitoring of the highest vibration levels received at nearby buildings for compliance purposes. It will also mitigate the vibration transfer from subsequent breaking by creating a ‘trench’ of fractured rock between the breaker and nearby buildings Minimise the volume of breaking (e.g. use a crushing shear or pulveriser attachment in place of a breaker, or use a cut and lift approach to enable breaking in the centre of site) Minimise the duration of breaking, and the number of breaking periods (e.g. complete all breaking in one extended period rather than two shorter periods with the same overall duration) Match the size of breaker to the scale of the works (i.e. large enough to undertake the works efficiently, but avoiding oversized units) Match the chisel/tip type to the material and use a dampened bit to avoid ringing; and Avoid ‘blank’ firing by engaging the material before commencing and stopping before it fires through the material.

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

9.8 Piling • •

Prioritise piling methods that minimise noise and vibration where practicable (e.g. augured, screw or press-in piles over impact driven or vibratory piling methods) Minimise alternating rotation of the bored piling auger to loosen spoil into the muck bin. Shaking the ‘kelly bit’ connection creates very loud banging that can result in noise complaints. It is understood this action can be avoided for general auger use but is necessary specifically when a coring barrel is used to drill through obstructions (due to Health and Safety issues related to alternative ways of loosening material from the bit).

9.9 Blasting The blasting contractor will keep the Blasting Management Plan (BMP) updated. The following general mitigation should be used: • • •

•

•

• •

A shroud will enclose the cutting head of the blast hole drilling rig where practicable Comprehensive vibration and air overpressure level predictions will be performed prior to every blast event Signature hole analysis (small trial blasts) will be undertaken to determine site specific vibration attenuation characteristics, air overpressure levels and maximum instantaneous charge weight (MIC) thresholds. Outcomes will be documented in a Trial Blast Report. This Trial Blasting Report shall be used for subsequent design of production blasting Where predicted vibration levels exceed the cosmetic building damage limits (Section 4.2.1), investigate modifications to the blasting technique (e.g. charge weight, charge layout, firing order, hole depths etc). Where blasting is the BPO and is still predicted to exceed the cosmetic building damage limits, a SSCNVMP will be prepared Where practicable and appropriate, the production blasting will commence at the closest position to sensitive receivers. Fracturing the basalt layer can reduce vibration transmission to receivers from subsequent blasts further away Blasting times will be agreed with MediaWorks and avoid Sensitive Times (Appendix C1) Startle caused by blasting will be mitigated through communicating exactly when blasts will occur (e.g. 10:32am and 2:32pm) and having an audible countdown sequence

9.10 Vibro-Rolling • • •

Avoid evening and night-time periods and Sundays/public holidays where practicable Match the size of roller to the scale of the works (i.e. large enough to undertake the works efficiently, but avoiding oversized units) Prioritise the use of static rollers over vibratory rollers

For vibratory rollers using the vibro mode: • • • • Page 34

Only use outside the predicted safe setback distances from buildings (Section 7.1) unless a suitable SSCNVMP is in place Timing will be agreed with MediaWorks and avoid Sensitive Times (Appendix C1) Match the vibration output to the scale of the works (i.e. combination of minimising the amplitude of the drum vibration and/or maximising the vibration frequency of operation) Ramp up/down (i.e. start/stop vibro mode) away from buildings (refer safe distances Section 7.1) and progress closer to buildings as required once vibro mode is constant/stable | Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan • •

Page 35

Minimise the duration (e.g. use vibro mode to settle and align aggregate, then turn vibro mode off away from buildings for subsequent static rolling compaction) Minimise the number of periods (e.g. complete all vibratory rolling in one extended period rather than two shorter periods with the same overall duration)

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

10. Communication 10.1 Communication Overview Communication with stakeholders in relation to construction noise and vibration impacts is described in the main works Communication and Consultation Plan (CCP). A summary of Community and Business Liaison Group (CLG) and Independent Peer Review (IPR) feedback relevant to this CNV DWP will be maintained in Appendix E. As a minimum, the following communication shall be undertaken: •

• •

•

•

•

Page 36

Written notification will be provided to all property occupiers within 100m of a worksite to raise awareness of the CRL project, the required construction works and the duration in their vicinity. This will be undertaken at least 10 working days prior to the commencement of works on site. The Link Alliance’s Communications and Engagement Advisor will provide monthly updates of monitoring and early work progress to affected parties. The Communications and Engagement Advisor will advise any affected parties of construction activities that are predicted or have been identified by the Acoustics Specialist to exceed the limits in Section 4 following the application of BPO mitigation identified in Section 9. The Communications and Engagement Advisor shall undertake communications with MediaWorks for their studios at 3 Flower St and 71 Boston Road in accordance with designation Condition 16, unless agreed in their SSCNVMPs in Appendices C1 and C24. The Communications and Engagement Advisor shall address any concerns and complaints regarding construction noise and vibration in accordance with Section 10. When discussing vibration concerns, it is important to convey that vibration can be felt at levels far below those that pose even the smallest risk of building damage. Startle caused by blasting will be mitigated through communicating exactly when blasts will occur (e.g. 10am and 2pm) and having an audible countdown sequence. The Communications and Engagement Advisor will provide occupants of buildings within 100m of blasting at least 24 hours’ notice.

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

10.2 Complaints Response The contact name and phone number of the Senior Communications and Engagement Advisor (Section 3), to which complaints can be directed, shall be clearly included in any written notification and on-site signage. Any construction noise and/or vibration complaint shall be recorded in a complaints file, and an investigation shall be undertaken involving the following: • •

• • • • •

•

Page 37

Identification of sources of concern, and measuring or estimating noise and/or vibration levels at the time of the complaint; A hotline phone/text number shall be established to receive complaints. Acknowledge receipt of the concern or complaint. An initial response shall be undertaken within 24 hours of receiving a complaint and resolved as soon practicable. If a reasonable complaint relates to building damage or sleep disturbance, inform the on-duty site manager as soon as practicable to cease works pending the investigation; Reporting the findings and recommendations to the Construction Manager; Actions and time taken to close-out complaint; Communication with the complainant; and Reporting of the investigation in the complaints file. A record of all concerns and/or complaints received shall include: −

The name of the person(s) who raised the concern or complaint (unless they elect not to provide this) and details of the concern or complaint;

−

Where practicable, weather conditions at the time of the concern or complaint, including wind direction and cloud cover if the complaint relates to noise;

−

Known construction activities at the time and in the vicinity of the complainant during the concern or complaint period; and

−

Remedial actions undertaken (if any) and the outcome of these, including monitoring of the activity.

If a complaint is received about vibration amenity, and a measurement demonstrates exceedance of the Project vibration limits, the following procedures will be implemented: −

Further measurements may be required to determine the extent of the exceedance and identify the activity/activities responsible;

−

Review the mitigation strategy and construction methodology to ensure BPO is applied;

−

Further measurements may be required to determine the effectiveness of BPO measures and reassess the compliance status;

−

Determine if the receiver qualifies for a SSCNVMP (Sections 4.1.2 and 4.2.3); and

−

The Senior Stakeholder and Communications Manager shall liaise with affected parties (Section 10.2).

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

11. Monitoring 11.1 Noise Construction noise shall be measured and assessed: •

During the first occurrence of high noise activities listed in Section 6.1 and in response to a noise complaint (Section 10.2) At 1m from the most affected building façade, or proxy position and adjusted for distance and façade reflections where appropriate By a suitably qualified and experienced specialist (e.g. Member of the Acoustical Society of New Zealand) in accordance with the requirements of New Zealand Standard NZS 6803: 1999 “Acoustics - Construction Noise” For a representative duration, reported with the measured level (e.g. 65 dB LAeq (30min)) The monitoring results shall be used to update Section 6.1 of this CNV DWP as appropriate.

• •

• •

A flow chart showing the process for attended noise monitoring is provided in Figure 11-1. Noise monitoring (Section 11.1): •

•

During the first use of high noise equipment (Section Error! Reference s ource not found.) In response to a reasonable complaint (Section 10.2) or to verify an exceedance

Comply with noise limits? (Section 4.1)

Yes

No

Response to a previous noncompliant measurement?

No

Review mitigation and management strategies to ensure BPO (Section 9)

Limits practicably achieved?

Yes

Qualify for SSCVMP?

Yes

Yes Prepare SSCNMP (Appendix C) (Subsequent complaints dealt with via the prepared SSCNMP) Submit findings to Project Manager

Figure 11-1 Noise Monitoring Flow Chart

Page 38

| Mt Eden Main Works CNV DWP

Revise construction methodology

No No


Construction Noise and Vibration Delivery Work Plan

11.2 Vibration Construction vibration levels shall be measured and assessed: • •

•

• •

During the first occurrence of high-vibration activities listed in Section 7.1 and in response to a vibration complaint (Section 10.2) At the closest building foundations and/or the top floor level as appropriate where consent to access the building of interest has been requested and granted, or proxy position and adjusted for distance where appropriate By a suitably qualified and experienced specialist (e.g. Member of the Acoustical Society of New Zealand) in accordance the requirements of German Standard DIN 4150-3:1999 “Structural vibration – Part 3: Effects of vibration on structures” For a representative construction duration, generally measured in 1 – 2 second intervals The monitoring results shall be used to update Section 7.1 as appropriate.

A flow chart showing the process for attended vibration monitoring is provided in Figure 11-2. The following procedures will be implemented where measured construction vibration exceeds the Project standards in condition 33: • • • •

The activity giving rise to the exceedance will cease as soon as safe and practicable to do so; Determine if the receiver qualifies for a SSCVMP (Section 4.2.3); A detailed building condition survey will be undertaken; and The Senior Communications and Engagement Advisor will liaise with the building owner throughout this process.

If damage has not occurred, then that construction activity can continue provided the measured vibration level is not exceeded further. If damage has occurred, then alternative construction methods will be investigated, subject to implementation of the best practicable option (BPO), and the Requiring Authority shall commit to repairing the damage within a reasonable timeframe after the construction phase ceases.

Page 39

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

Cosmetic Building Damage

Vibration monitoring (Section 11.2): • •

During the first use of high vibration equipment (Section 7.1) In response to a reasonable complaint (Section 10.2) or to verify an exceedance

Notify Project Manager, cease the activity, engage a structural engineer and undertake a building condition survey

Yes

Comply with cosmetic building damage limits? (Section 4.2.1)

Amenity

Engage heritage expert

No

Building damage?

Yes

No

Yes

Damage type? Structural Seek advice from structural expert before continuing

Comply with the amenity limits? (Section 4.2.2)

Yes

No

No

Heritage building?

Response to a previous noncompliant measurement?

Yes

No

Qualify for SSCVMP? Yes

Submit findings to Project Manager

| Mt Eden Main Works CNV DWP

Revise construction methodology

No

(Subsequent complaints dealt with via the prepared SSCNMP)

Page 40

Yes

Limits practicably achieved?

Prepare SSCVMP (Appendix C)

Figure 11-2 Vibration Monitoring Flow Chart

Cosmetic

Review mitigation and management strategies to ensure BPO (Section 9)

No


Construction Noise and Vibration Delivery Work Plan

12. Effects in Buildings 12.1 Noise Inside Buildings The noise level received inside, for example, an office or living room, will depend on the sound insulation performance of the façade (particularly the glazing) and room constants (such as the room dimensions and surface finishes). These factors can vary widely. The Construction Noise Standard (NZS 6803) recommends noise limits assessed at 1m from the external façade of a building, assuming a sound level difference of 20 decibels to sensitive receiving environments inside. For the purpose of estimating actual noise effects on a room by room basis, the predicted façade sound insulation performance of buildings can be generally categorised by the type of glazing / ventilation provision as follows: • • •

Sealed glazing Closed windows (openable) Open Windows

30 decibels sound level difference 25 decibels sound level difference 15 decibels sound level difference

The SSCNMPs in Appendix C will use the above assumptions initially. However, they will be updated with site specific measured performance when available. Measurements in advance of the works may be practicable in some cases. In other cases, a visual inspection may provide a more informed estimate of façade performance. ‘Noise effects matrices’ are presented in Tables 12-1 and 12-2. They enable estimation of the construction noise level received inside, based on the external noise level and façade glazing type. The noise effects matrices are indicative only, as detailed assessment requires measurement of the actual façade performance on a space by space basis. The noise effects are categorised using colour coding (explained under each table overleaf). To use the matrices, follow this three-step process: • • •

Page 41

Measure the external noise level at 1m from the façade, or estimate it from the information provided in Section 6.1 of this CNV DWP Determine the category of façade glazing sound insulation performance from the guidance above or measured on-site façade sound level difference for a specific receiver location Use the relevant lookup table to estimate the received internal noise level and associated typical effects that may be experienced using Tables 12-1 and 12-2

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan Table 12-1: Daytime noise levels in commercial & industrial buildings and habitable rooms in dwellings External Noise Level (dB LAeq)

Estimated Internal Noise Level (dB LAeq) Sealed glazing (30 dB)

Closed windows (25 dB)

Open windows (15 dB)

85

55

60

70

80

50

55

65

75

45

50

60

70

40

45

55

(Section 6.2)

•

< 50 dB LAeq

Typically acceptable

•

50 – 60 dB LAeq

Annoyance and reduction in work efficiency

•

> 60 dB LAeq

Difficulty holding a normal conversation and reduction in work efficiency

Table 12-2: Night-time noise levels in bedrooms of dwellings External Noise Level (dB LAeq)

Estimated Internal Noise Level (dB LAeq) Sealed glazing (30 dB)

Closed windows (25 dB)

Open windows (15 dB)

65

35

40

50

60

30

35

45

55

25

30

40

50

20

25

35

(Section 6.2)

•

< 35 dB LAeq

Typically acceptable

•

35 – 40 dB LAeq

Annoyance and sleep disturbance for some noise sensitive receivers

•

> 40 dB LAeq

Annoyance and sleep disturbance for most noise sensitive receivers

12.2 Vibration Inside Buildings While the primary vibration concern is typically cosmetic building damage (Section 4.2.1), people may be disturbed at levels which are significantly lower (Section 4.2.2). Potentially affected parties will be informed about the vibration levels they may experience and assured vibration damage can only occur at magnitudes well above the threshold of perception (Section 10). British Standard BS 5228-2:2009 “Code of practice for noise and vibration control on construction and open sites – Part 2: Vibration” provides the following guidance on the amenity effects of vibration: • • • •

0.14mm/s PPV 0.3 mm/s PPV 1 mm/s PPV 10 mm/s PPV

Just perceptible in the particularly sensitive environments Just perceptible in normal residential environments Typically acceptable with prior notification Likely to be intolerable for any more than a very brief period

In some cases, construction vibration can excite building structures. This is heard as ‘reradiated noise’ rather than felt as vibration within the building but is the result of a structural transmission path. Predictions of reradiated noise levels are complex and site specific. Where necessary, a Page 42

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan suitability qualified acoustic specialist will be engaged to provide guidance. Reradiated noise effects can be estimated using the guidance in Section 12.1.

12.3 Management of Adverse Effects The following process will be implemented for any construction activity that is found to exceed the relevant construction noise and vibration Project Standards: • •

•

• •

Page 43

Review the construction methodology, mitigation and management strategies to ensure they represent the BPO. The Senior Communications and Engagement Advisor (or representative) will consult with affected parties to understand their sensitivities, including times, activities and locations. Consultation will focus on a collaborative approach to managing the adverse effects from construction noise and vibration while works are undertaken in the vicinity. The Senior Communications and Engagement Advisor (or representative) will be available 24/7 during works periods. A record of consultation will be included in the relevant SSCNMP (Appendix C) or otherwise in Appendix E as appropriate. Implement measures to avoid significant adverse effects as agreed with the affected party and monitor the activity to verify the extent of any adverse effects. Temporary relocation will be considered for sensitive receivers where all practicable noise and vibration management and mitigation measures have been implemented and significant adverse noise effects and vibration are predicted. This will be in exceptional cases only, and an SSCNVMP will have been prepared. Advice from the Acoustics Specialist will be incorporated as part of the SSCNVMP process (refer Sections 4.1.2 and 4.2.3).

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

Appendix A: Glossary of Terminology Noise Ambient Noise

Ambient Noise is the all-encompassing noise associated with any given environment and is usually a composite of sounds from many sources near and far.

A-weighting

A frequency filter which is applied to a measurement of sound so as to more closely approximate the frequency bias of the human ear.

dB

Decibel – the basic measurement unit of sound. It is a logarithmic ratio of measured sound pressure level with respect to a reference level of 20 micropascals.

LAeq(T)

The A-weighted, time averaged sound level (on a logarithmic/energy basis) over the measurement period T (e.g. between 10 and 60 minutes).

LAFmax

The maximum A-weighted sound level recorded during the measurement period. Measured with fast time weighting i.e. a 125-millisecond time constant

Noise

A sound that is unwanted by, or distracting to, the receiver.

NZS 6801:2008

New Zealand Standard NZS 6801:2008 "Acoustics - Measurement of Sound"

NZS 6802:2008

New Zealand Standard NZS 6802:2008 "Acoustics - Environmental Noise”.

NZS 6803:1999

New Zealand Standard NZS 6803:1999 “Acoustics – Construction Noise”.

Vibration PPV

Peak Particle Velocity, measured in mm/s. This is the standard metric for assessing construction vibration levels.

DIN 4150-3:1999

German Standard DIN 4150-3:1999 “Structural Vibration – Part 3: Effects of vibration on structures”. This standard is adopted to assess building damage.

General Suitably qualified and experienced acoustic specialist

A person who has sufficient qualifications and experience in the relevant field(s) of acoustics (noise and/or vibration) to undertake robust measurements and assessments i.e. a Member of the Acoustical Society of New Zealand.

Other Abbreviations CRL

City Rail Link

CLG

Community and Business Liaison Group

BPO

Best Practicable Option

CNV

Construction Noise and Vibration

DWP

Delivery Work Plan

SSCNMP

Site Specific Construction Noise Management Plan

SSCVMP

Site Specific Construction Vibration Management Plan

Page 44

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan Communications records are contained in the communication and consultation plan (CCP).

Page 45

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

Appendix B: CRL Designation Conditions for noise and vibration Condition Condition Number

Relevant Section of CNV DWP

16.1

Section Error! Reference s ource not found.

Communications – Notable Noise and Vibration Receivers A SSCNVMP shall be prepared for all Notable Noise and Vibration Receivers (refer Condition 39). As part of the SSCNVMP (and further to Condition 15 of this designation), the Requiring Authority shall undertake communication and consultation, as soon as reasonably practicable (and at least once following confirmation of construction timing and methodology), with any Notable Noise and Vibration Receivers located within 200 metres of blasting, or within 100 metres (either horizontally or vertically) of the designation footprint for other construction activities. Communication and consultation with these parties should focus on a collaborative approach to manage the adverse effects from construction noise and vibration while works are undertaken in the vicinity.

16.2

31.1

The Requiring Authority shall undertake on-going communication and consultation with notable noise and vibration receivers throughout the duration of construction occurring in the vicinity. This communication shall be reported back to the “key contacts” (see Condition 13) and the Auckland Council Consent Monitoring officer for their review and confirmation of any further action to be undertaken. The Auckland Council Consent Monitoring Officer shall advise the Requiring Authority of its recommendation within 10 working days of receiving this information from the Requiring Authority.

Section Error! Reference s ource not found.

Project Standards – Construction Noise Construction noise shall comply with the following Project Standards (unless otherwise provided for in a SSCNMP which is approved under Condition 37, 39 or 40):

Section 4.1

Receiver Type

Occupied commercial and industrial buildings (including offices) Sensitive Noise and Vibration Receivers (excluding offices) Page 46

| Mt Eden Main Works CNV DWP

Monday to Saturday 0700-2200 75 dB LAeq

Sundays and Public Holidays 0700-2200 75 dB LAeq

At all other times 2200-0700 75 dB LAeq

75 dB LAeq 90 dB LAFmax

60 dB LAeq 75 dB LAFmax

60 dB LAeq 75 dB LAFmax

Refer also Communication and Consultation Plan


Construction Noise and Vibration Delivery Work Plan

Condition Condition Number Early Childhood Education Centres (whilst occupied during normal opening hours) Bear Park Early Childhood Education Centre at 32 Akiraho Street (whilst occupied during normal opening hours)

Relevant Section of CNV DWP 35 dB LAeq in sleeping areas

35 dB LAeq in sleeping areas 65 dB LAeq in outdoor playing areas

31.2

Construction noise shall be measured and assessed in accordance with the provisions of NZS 6803:1999

Section 4.1

32.1

Project Standards – Blasting Overpressure and Vibration

Section 4.3

32.1 Prior to commencement of production blasts (ie. blasting that is undertaken as part of the construction process), trial blasts (ie. preliminary blasts that occur prior to production blasts for the purpose of data acquisition), shall be undertaken to demonstrate how adverse effects will be managed and how compliance with Conditions 32.2, 32.3 and 32.4 will be achieved in production blasting. Trial blasts will determine site-specific attenuation characteristics, air overpressure levels and maximum instantaneous charge weight (MIC) thresholds. Outcomes shall be documented in a Trial Blasting Report. This Trial Blasting Report shall be used for subsequent design of production blasting. 32.2

Air overpressure from the blast events shall not exceed 120 dB L Zpeak at the facade of any occupied building measures and assessed in accordance with the provisions of the Australian Standard AS 2187.2-2006 Explosives – Storage and use – Use of explosives.

Section 4.3.1

32.3

Air overpressure from blast events shall not exceed 133dB LZpeak at the facade of any unoccupied building measured and assessed in accordance with the provisions of Australian Standard AS 2187.2-2006 Explosives – Storage and use – Use of explosives.

Section 4.3.1

32.4

Unless a SSCNVMP is approved under Conditions 38, 39 or 40 which includes an alternative blasting vibration standard:

Section 4.3

Page 47

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

Condition Condition Number

Relevant Section of CNV DWP

(a) Vibration from blast events shall not exceed 10mm/s PPV for 95% of blast events and 15mm/s for 100% blast events when measured at the foundation of any building that will be occupied during the blast event when measured and assessed in accordance with the provisions of DIN 4150-3:1999. (b) Vibration from blast events shall not in any case exceed the limits specified in Condition 33 when measured at the foundation of any building when measured and assessed in accordance with the provisions of Condition 33. 32.5

For the purposes of 32.2 and 32.3, a building is deemed to be occupied if there are persons inside only during the blast event (ie. if the occupants of a dwelling are out (eg. at work) during the blast event then the dwelling is deemed to be unoccupied).

Noted

32.6

Blasts must be performed at set times during the daytime only, between 9am and 5pm, Monday to Saturday only.

Blasting Management Plan

32.7

Comprehensive vibration and air overpressure level predictions must be performed prior to every blast event.

Blasting Management Plan

32.8

Blasting shall not be carried out where overpressure levels are predicted to be above the Project Standards in 32.1 and 32.2 at any building. Blasting shall not be carried out where vibration levels are predicted to be above the project standards in Condition 32.4 at any building.

Blasting Management Plan

32.9

These criteria may be varied only by a Site Specific Construction Noise Management Plan (SSCNMP) that has been approved under Condition 37.

Noted

33.1

Project Standards â&#x20AC;&#x201C; Construction Vibration

Section 4.2.1

Construction vibration (including blasting) shall comply with the following Project Standards for building damage (unless otherwise provided for in a SSCVMP which is approved under Condition 38, 39 or 40): Type of Structure

Page 48

Short term (transient) vibration1

| Mt Eden Main Works CNV DWP

Long-term (continuous) vibration


Construction Noise and Vibration Delivery Work Plan

Condition Condition Number

Relevant Section of CNV DWP PPV at the foundation at a frequency of

PPV at horizontal plan of highest floor (mm/s)

PPV at horizontal plane of highest floor (mm/s)

1-10Hz (mm/s)

10-50Hz (mm/s)

50-100Hz

Commercial/ Industrial

20

20-40

40-50

40

10

Residential/S chool

5

5-15

15-20

15

5

Historic/ sensitive structures

3

3-8

8-10

8

2.5

(mm/s)

Note: 1.

Standard DIN 4150-3:1999 defines short-term (transient) vibration as “vibration which does not occur often enough to cause structural fatigue and which does not produce resonance in the structure being evaluated”. Long-term (continuous) vibration is defined as all other vibration types not covered by the short-term vibration definition.

33.2

Construction vibration (including blasting) shall be measured in accordance with German Standard DIN 4150-3:1999.

Section 4.2.1

34.1

Project Standards – Construction Vibration (Amenity)

Section 4.2.2

Between the hours of 10pm and 7am vibration generated by construction activities (excluding blasting) shall not exceed: (a) a Peak Particle Velocity (PPV) of 0.3mm/s when measured at any part of the floor of any bedroom; Page 49

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

Condition Condition Number

Relevant Section of CNV DWP

(b) a noise level of 35 dB LAeq(15min) when measured in any bedroom. 34.2

Between the hours of 7am and 10pm vibration generated by construction activities (excluding blasting) shall not exceed:

Section 4.2.2

(a) A Peak Particle Velocity (PPV) of 1mm/s as measured on the floor of the receiving room for residentially occupied habitable rooms, bedrooms in temporary accommodation and medical facilities; and (b) A Peak Particle Velocity (PPV) of 2mm/s as measured on the floor of the receiving room for retail and office spaces (including work areas and meeting rooms); 34.3

The limits in 34.1 and 34.2 shall only be investigated and applied upon the receipt of a complaint from any building occupant. They shall not be applied where there is no concern from the occupant of the building.

Section 4.2.2

34.4

Where the limits in 34.1 and 34.2 are found (through measurement) to be exceeded then a SSCVMP shall be prepared for that receiver (Condition 38).

Section 4.2.3

35.1

Project Standards â&#x20AC;&#x201C; MediaWorks

Section 4.4

The noise and vibration limits set out in Conditions 35.2 and 35.3 shall apply only during Sensitive Times. For the purposes of MediaWorks, Sensitive Times are defined as follows: (a) During scheduled live broadcasting (b) During emergency/breaking news live broadcasting (c) During scheduled recording sessions If the limits are complied with in Studio 1, the noise and vibration levels in all other Studios will be acceptable. For the avoidance of doubt, (a)-(c) above include sound checks as well as actual broadcast/recording time. 35.2

Noise Limits â&#x20AC;&#x201C; Studios The noise level (whether air borne or reradiated from ground vibration) from all construction sources as received inside Studio 1 shall not exceed 30dB LAeq (5 min) and 33 dB LAeq (1 sec). These limits apply to the construction component of the total noise. However for up to

Page 50

| Mt Eden Main Works CNV DWP

Section 4.4


Construction Noise and Vibration Delivery Work Plan

Condition Condition Number

Relevant Section of CNV DWP

two periods of tunnelling, each no more than 15 consecutive days, the noise limits may be up to 5 decibels higher (ie. 35dB LAeq (5 min) and 38 dB LAeq (1 sec)) during Sensitive Times, other than during the Live Broadcasting Periods as follows: (a) Weekdays: 0600-0900 hours 1200-1230 hours 1730-1930 hours 2230-2330 hours (b) Christmas holiday season (Saturday prior to Christmas Day to Sunday following New Years Day inclusive) and weekends: 1730-1900 hours The Requiring Authority must give MediaWorks at least 12 days notice of the commencement of each such period. 35.2A

Rockbreaking shall not be used for tunnel excavation within 100m of the MediaWorks site during Sensitive Times unless compliance with the noise limits in Condition 35.2 can be demonstrated in accordance with the methodology set out in the SSCNVMP.

Section 4.4

35.3

Vibration Limits â&#x20AC;&#x201C; Studios

Section 4.4

For the protection of studio camera image quality, the construction vibration level (including blasting) as received inside Studio 1 shall not exceed 0.1mm/s PPV. This limit may be elevated by agreement of both the Requiring Authority and MediaWorks where image quality is found to be unaffected. 35.4

Noise level measurements inside Studio 1 shall be undertaken at a position that is representative to the level received within 2m from, and at a similar height to, the microphone of the main presenter(s).

35.5

Noise level measurements inside Studio 1 shall be undertaken with all doors to the studio closed.

35.6

For the protection of amenity, the construction vibration level as received in inside office areas, meeting rooms and technical suits shall not exceed 1mm/s PPV (as received on the floor of the receiving room) when those spaces are in use.

35.7

For the prevention of building damage, the construction vibration level shall not exceed the limits in Condition 33 at all times.

35.8

For the protection of sensitive equipment, the construction vibration (including blasting) level shall not exceed 200mg (2m/s 2) between 5-500Hz. Levels are to be measured on the floor supporting the Sensitive Equipment.

35.9

All attended noise and vibration measurements shall be undertaken by a suitably qualified and experienced expert.

Page 51

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

Condition Condition Number 35.10

For the avoidance of doubt, the MediaWorks conditions (Conditions 35, 40 and 66) only apply for so long as television, radio and/or interactive media facilities broadcast from the MediaWorks site.

35.11

Blasting shall not occur during MediaWorks Sensitive Times (as defined in Condition 35.1). Blasting shall occur at times to be agreed with MediaWorks and as documented in the SSCNVMP.

36.1

Construction Noise and Vibration DWP

Relevant Section of CNV DWP

Section 1

A Construction Noise and Vibration DWP shall be prepared and implemented. The objective of the Construction Noise and Vibration DWP is to provide for the development and implementation of identified best practicable option to avoid, remedy or mitigate the adverse effects on receivers of noise and vibration resulting from construction. 36.2

The Construction Noise and Vibration DWP shall:

Section 1.3

(a) Adopt the noise and vibration standards for construction set out in Conditions 31, 32, 33 and 34 of these designations; (b) Be generally consistent with the draft Construction Noise and Vibration management plan submitted as part of the Notice of Requirement documentation (dated 23 August 2013); and (c) Identify methods to achieve best practicable option for mitigating adverse effects. 36.3

Page 52

To achieve this objective, the Construction Noise and Vibration DWP shall include: (a) The roles and responsibilities of the noise and vibration personnel in the contractor team with regard to managing and monitoring adverse noise and vibration effects;

Section 3

(b) That piling and road cutting will be restricted to between the hours of 7am to 7pm, Monday to Saturday;

Section 9.2.1

(c) Construction machinery and equipment to be used and their operating noise and vibration levels;

Sections 6.1 and 7.1

(d) Identification of construction activities that are likely to create adverse noise and vibration effects, the location of these in the construction site areas, and the distance to comply with the Project Criteria in Conditions 31, 32, 33 and 34;

Sections 6.2 and Error! R eference source not found.

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

Condition Condition Number

Relevant Section of CNV DWP

(e) The timing of construction activities that are likely to create an adverse noise and vibration effect;

Section 2.3

(f) The location of sensitive noise and vibration receivers;

Section Error! Reference s ource not found. and Appendix C

(g) A record of communication and consultation with sensitive noise and vibration receivers. The record must include a clear explanation of where any comments from sensitive receivers have not been incorporated in the Construction Noise and Vibration DWP, and the reasons why not. This information must be included in the Construction Noise and Vibration DWP provided to both the Independent Peer Review Panel and Auckland Council as part of the Outline Plan process specified in Condition 11;

Section 10 and Appendices A and B

(h) Specific measures to address the concerns raised by those sensitive receivers;

Appendix C

(i) Specific training procedures for construction personnel including:

Section 9.1

(i) The project noise and vibration performance standards for construction (conditions 31, 32, 33 and 34); (ii) Information about noise and vibration sources within the construction area and the locations of sensitive noise and vibration receivers; and (iii) Construction machinery operation instructions relating to mitigating noise and vibration; (j) Methods and measures to mitigate adverse noise and vibration effects including, but not limited to, structural mitigation such as barriers and enclosures, the scheduling of high noise and vibration construction, use of low noise and vibration machinery, temporary relocation of affected receivers or any other measures or offer agreed to by the Requiring Authority and the affected receiver;

Section 9

(k) The proposed methods for monitoring construction noise and vibration to be undertaken by a suitably qualified person for the duration of construction works including:

Section 9

(i) Updating the predicted noise and vibration contours based on the final design and construction activities; (ii) Confirm which buildings are to be subject to a pre and post building condition survey in accordance with Condition 46. This includes consideration of those buildings in Appendix One and Two to these conditions;

Page 53

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

Condition Condition Number

Relevant Section of CNV DWP

(iii) The timing and location for monitoring of buildings during construction is required (Note that the flow charts contained in Appendices B and C of Appendix J of the technical noise and vibration report provided as part of the Notice of Requirement should be used as a guide); (iv) Identifying appropriate monitoring locations for receivers of construction noise and vibration; (v) Procedures for working with the Communication and Consultation Manager to respond to complaints received on construction noise and vibration, including methods to monitor and identify noise and vibration sources; (vi) Procedures for monitoring construction noise and vibration and reporting to the Auckland Council Consent Monitoring officer; and (vii) Procedures for how works will be undertaken should they be required as a result of the building condition surveys;

37.1

(l) Cross references to the specific sections in the Communication and Consultation Plan which detail how landowners and occupiers are to be communicated with around noise and vibration effects.

Throughout

Site Specific Construction Noise Management Plan (SSCNMP)

Section 4.1.2 and Appendix C

For the avoidance of doubt, this condition does not apply to MediaWorks. The objective of a SSCNMP is to detail the best practicable option to avoid, remedy or mitigate adverse effects on a receiver resulting from construction noise that does not comply with the Project Noise Standards. 37.2

Further to the Construction Noise and Vibration DWP in Condition 36, a SSCNMP shall be prepared for any receiver or activity for which air overpressure is either predicted or measured to exceed the limits in Condition 32, or where construction noise is either predicted or measured to exceed the Project Noise Standards in Condition 31, except where the exceedance of the standards in Condition 31 is less than 5 decibels and does not exceed :

Appendix C

(a) 0700-2200: 1 period of up to 2 consecutive weeks in any 2 months (b) 2200-0700: 1 period of up to 2 consecutive nights in any 10 days 37.3

Page 54

For predicted exceedances of less than 5 decibels (refer 37.2) monitoring shall be undertaken to confirm the actual noise levels. If exceedance is shown to be more than 5 decibels, or the period exceeds those detailed, then a SSCNMP will be prepared.

| Mt Eden Main Works CNV DWP

Noted


Construction Noise and Vibration Delivery Work Plan

Condition Condition Number

Relevant Section of CNV DWP

37.4

N/A

In addition to the SSCNMPs prepared in accordance with Condition 37.2, and notwithstanding Condition 37.1, the Requiring Authority shall prepare SSCNMPs specifying the best practicable option for management, methods and measures to mitigate all noise effects for the properties located at: (a) 1 Queen Street (Lot 1 DP 165403); (b) 21 Queen Street (Lot 1 DP 67723); (c) 29 Customs Street West (Lot 7 DP 77037) (d) 188 Quay Street (Lot 5 DP 63972 and Lot 1 DP 78340); and (e) 23-29 Albert Street (Lot 1 DP 116724).

37.5

SSCNMPs will identify:

Appendix C

(a) The extent to which noise may exceed the Project Noise Standards in Condition 31 or the overpressure limits in Condition 32; (b) The timing and duration of any exceedance; (c) Details of the type of activity causing any exceedance; (d) The summary of the communication and consultation undertaken with the receiver. The summary must include a clear explanation of where any comments have not been incorporated, and the reasons why not. This information must be included in the SSCNMP provided to both the Independent Peer Review Panel and Auckland Council as part of the Outline Plan process specified in Condition 11; (e) The methods and measures to mitigate noise effects, including but not limited to, potential to offer temporary relocation of affected receivers, alternative ventilation, faรงade sound insulation improvements, building condition surveys in the case of overpressure generated by blast events, or other offers made by the Requiring Authority and whether these have been agreed to by the affected receiver; (f) The reasons why the management and mitigation measures and methods reflect best practicable option. 37.6

Page 55

The SSCNMP shall be submitted for the review of Auckland Council as part of the Outline Plan. The works shall then be undertaken in accordance with the SSCNMP confirmed by the Requiring Authority as part of the Outline Plan.

| Mt Eden Main Works CNV DWP

Appendix C


Construction Noise and Vibration Delivery Work Plan

Condition Condition Number

Relevant Section of CNV DWP

38.1

Section 4.2.3 and Appendix C

Site Specific Construction Vibration Management Plan (SSCVMP) For the avoidance of doubt, this condition does not apply to MediaWorks. The objective of a SSCVMP is to detail the best practicable option to avoid, remedy or mitigate adverse effects on a receiver resulting from vibration that does not comply with the Project Vibration Standards.

38.2

Further to the Construction Noise and Vibration DWP in Condition 36, a SSCVMP shall be prepared:

Appendix C

(a) For any unoccupied building, structure or infrastructure for which construction vibration is either predicted or measured to exceed the Project Vibration Standards in Condition 33; (b) Where a complaint or concern is raised and the vibration level exceeds the amenity levels of Condition 34.2(a) and 34.2(b); (c) In response to other concerns or complaints where required (refer Condition 17).; (d) For the properties listed in Condition 37.4. 38.3

38.3 Where the amenity limits in Conditions 34.2(a) and 34.2(b) are exceeded:

Appendix C

(a) Best practicable management of vibration must be applied; and (b) The vibration activity shall be scheduled to avoid disturbance. If this is not practicable then reasonable respite periods shall be provided to reduce vibration exposure. 38.4

The limits in condition 33 may be relaxed by a SSCVMP but only for a building, structure or infrastructure that has been assessed by a suitably qualified and experienced structural engineer and where it has been deemed to be capable of withstanding higher vibration levels without sustaining building or structural damage, and where appropriate vibration and building condition monitoring regimes are in place.

Appendix C

38.5

38.5 SSCVMPs will identify:

Appendix C

(a) The timing and duration of any exceedance; (b) Details of the type of activity giving rise to any exceedance;

Page 56

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

Condition Condition Number

Relevant Section of CNV DWP

(c) Site Specific vibration criteria that addresses the issue(s) of concern (i.e. building damage, amenity and sensitive equipment). Site Specific criteria shall be determined by a suitably qualified independent vibration expert; (d) The summary of the communication and consultation undertaken with the receiver. The summary must include a clear explanation of where any comments have not been incorporated, and the reasons why not. This information must be included in the SSCVMP provided to both the Independent Peer Review Panel and Auckland Council as part of the Outline Plan process specified in Condition 11; (e) The methods and measures to mitigate vibration effects, including but not limited to, investigating alternative low-vibration construction methods, undertaking high-vibration works outside sensitive times, vibration barriers, building condition surveys, potential to offer temporary relocation of affected receivers, or other offers made by the Requiring Authority and agreed to by the affected receiver; (f) The reasons why the management and mitigation measures and methods reflect best practicable option. 38.6

The SSCVMP shall be submitted for the review of Auckland Council. The works shall then be undertaken in accordance with the SSCVMP confirmed by the Requiring Authority as part of the Outline Plan.

Appendix C

39.1

Notable Noise and Vibration Receivers

Section Error! Reference s ource not found. and Appendix C

For the avoidance of doubt, Conditions 39.5 and 39.6 do not apply to MediaWorks. Further to Condition 36, the Requiring Authority and its contractor, in conjunction with a suitably qualified expert, shall work collaboratively with each notable receiver during the preparation of a SSCNVMP to confirm the extent and management of adverse effects on each Notable Receiver. 39.2

In addition to the Construction Noise and Vibration DWP, a SSCNVMP shall be prepared for each identified Notable Receiver. The objective of the SSCNVMP is to detail the best practicable option to avoid, remedy or mitigate adverse noise and vibration effects on each Notable Receiver.

39.3

The Requiring Authority shall consult with the notable receiver throughout the duration of construction and update the SSCNVMP as required to achieve the objective in 39.2.

39.4

The SSCNVMP shall include:

Page 57

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

Condition Condition Number (a) The level at which noise and vibration effects on the notable receiver will unreasonably interfere with its operation. This will enable development of the site specific criteria. In the case of MediaWorks this is set out in Condition 40; (b) Construction activities and equipment which are likely to create adverse noise and vibration effects and the location and timing of these in relation to the notable receiver; (c) The methods and measures associated with the worksite including, but not limited to, structural mitigation such as barriers and enclosures, use of low noise and vibration machinery and the scheduling of high noise and vibration construction; (d) The methods and measures associated with the notable receiver building or operation including, but not limited to, potential for isolation of sensitive areas and equipment, dampening of reradiating surfaces and temporary relocation of affected receivers that are proposed to minimise adverse noise and vibration effects on the notable receiver; (e) Details about the methods to be adopted by the Requiring Authority to minimise construction noise and vibration effects on the notable receiver and the anticipated effectiveness of those methods; (f) A summary of the communication and consultation undertaken with the notable receiver. The summary must include a clear explanation of where any comments have not been incorporated, and the reasons why not; (g) Offers made by the Requiring Authority to the notable receiver to mitigate effects and the response by the operators, such as relocation, and whether those offers were accepted or not by the notable receiver; 39.5

If the parties cannot agree on any of the matters above they shall each appoint a suitably qualified and independent expert, who shall jointly appoint an independent and suitably qualified third expert who shall certify the following matters to be included in the SSCNVMP: (a) The level at which noise and vibration effects on the notable receiver unreasonably interfere with its operation (the certified noise and vibration limit); (b) The mitigation methods and measures within the worksite (at source) including, but not limited to, structural mitigation such as barriers and enclosures, use of low noise and vibration machinery and the scheduling of high noise and vibration construction; (c) The mitigation methods and measures at the notable receiver including but not limited to: isolation of sensitive areas and equipment; dampening of reradiating surfaces; any response to such offers; and temporary relocation of affected receivers; (d) Whether or not the mitigation methods and measures reflect best practicable management; and (e) Whether or not the residual effects are likely to cause significant disruption to the activities of the notable receiver.

Page 58

| Mt Eden Main Works CNV DWP

Relevant Section of CNV DWP


Construction Noise and Vibration Delivery Work Plan

Condition Condition Number 39.6

Following the above process the SSCNVMP shall be submitted for the review of Auckland Council as part of the Outline Plan. For the avoidance of doubt, the Requiring Authority shall not be entitled to make any changes to the SSCNVMP through the Outline Plan process following any agreement reached with the notable receiver and/or through the above certification process without the consent of the notable receiver. The works shall then be undertaken in accordance with the SSCNVMP confirmed by the Requiring Authority as part of the Outline Plan process.

40.1

Construction Noise and Vibration Management Plan – Mediaworks Further to Condition 36, a SSCNVMP shall be prepared for MediaWorks implementing the project standards in Condition 35. The MediaWorks SSCNVMP shall identify high noise or vibration plant and machinery, and list the relevant items that require testing in accordance with Condition 40.4 and 40.8.

40.2

Prior to any demolition or construction commencing, the Requiring Authority shall undertake a noise survey to determine the Transmission Loss (TL) performance of the MediaWorks building envelope. This testing shall only be undertaken outside of Sensitive Times.

40.3

Prior to any demolition or construction commencing, the Requiring Authority shall undertake a vibration survey to determine the transfer function of the MediaWorks building structure from ground vibration outside the building to reradiated noise in Studio 1. This testing shall only be undertaken outside of Sensitive Times.

40.4

All high noise plant and machinery to be used at a location where it is predicted to generate noise levels in excess of 3 dB below the limits specified in Condition 35.2 shall be tested prior to use, to determine its Sound Power Level (Lw) at a sufficient distance from the MediaWorks building to ensure compliance. These measured Lws shall be used to predict the noise level at the MediaWorks building façade(s) from proposed construction scenarios. The façade TL (refer Condition 40.2) shall then be applied to predict the noise levels in the relevant rooms.

40.5

All high noise plant and machinery may not be used until Condition 40.4 is satisfied, taking into account the cumulative noise levels from active sources on the site.

40.6

The Requiring Authority and its contractor, in conjunction with a suitably qualified expert, shall work collaboratively with MediaWorks during the preparation of a SSCNVMP to confirm the extent and management of adverse effects on MediaWorks.

Page 59

| Mt Eden Main Works CNV DWP

Relevant Section of CNV DWP

Appendix C


Construction Noise and Vibration Delivery Work Plan

Condition Condition Number 40.7

The SSCNVMP shall set out the requirements for monitoring, the number of monitors, the instrument location, any adjustments necessary if a proxy position is required and any other procedures or requirements that are necessary. The data shall be available in real time to the Requiring Authority, Auckland Council and MediaWorks.

40.8

Prior to the use of any high vibration equipment to be used at a location where it is predicted to generate vibration levels greater than 75% of the PPV vibration limits in Condition 35.3, 35.6, 35.7 and 35.8, or reradiated noise within 3 decibels of the limits in Condition 35.2, the Requiring Authority shall undertake vibration measurements at a sufficient distance from the MediaWorks building to ensure compliance, applying the transfer function required by Condition 40.3 to assess reradiated noise. These measurements shall be used to determine minimum set-back distances from the building to avoid potential exceedances of the vibration limits in Conditions 35.2, 35.3, 35.6, 35.7 and 35.8. The results of the testing and the outcomes affecting construction operations shall be set out in the SSCNVMP.

40.9

The noise and vibration levels from construction shall be monitored to determine compliance with conditions 35.2, 35.3, 35.6, 35.7 and 35.8 continuously by automated noise and vibration monitors located at positions that will represent the noise and vibration level in the relevant spaces and for the relevant noise and vibration limits. The SSCNVMP shall set out the requirements for monitoring, the instrument location, any adjustments necessary if a proxy position is required and any other procedures or requirements that are necessary including methods to exclude extraneous sources. The data shall be available in real time to the Requiring Authority, Auckland Council and MediaWorks.

40.10

Monitoring to determine compliance or otherwise with Condition 35.6 relating to office amenity shall only be undertaken in response to complaints from MediaWorks. The measurements must be attended by a suitably qualified person.

40.11

The SSCNVMP shall set out corrective action measures that must be adopted in situations where any of the noise and vibration limits in Conditions 35.2, 35.3, 35.6, 35.7 and 35.8 are exceeded and where the noise and/or vibration levels are unacceptable to MediaWorks. The corrective action measures must include the following: (a) Immediate cessation of the work(s) that is giving rise to the exceedance; (b) A procedure to require the implementation of whatever measures are necessary to reduce the noise or vibration levels; (c) A monitoring procedure to determine compliance (once the remediation works are complete); (d) A requirement to ensure that the work(s) responsible for the exceedance are not recommenced during Sensitive Times;

Page 60

| Mt Eden Main Works CNV DWP

Relevant Section of CNV DWP


Construction Noise and Vibration Delivery Work Plan

Condition Condition Number (e) A complaints procedure that is capable of effecting the immediate cessation of works including making a point of contact directly available 24 hours, seven days a week. 40.12

If there is a disagreement between the Requiring Authority and MediaWorks as to the content of the SSCNVMP, they shall each appoint a suitably qualified and independent expert, who shall jointly appoint an independent and suitably qualified third expert who shall certify the matters set out in Condition 40.11 and any other matters in dispute in the SSCNVMP.

40.13

Following the above process the SSCNVMP shall be submitted for the review of Auckland Council as part of the Outline Plan. For the avoidance of doubt, the Requiring Authority shall not be entitled to make any changes to the SSCNVMP through the Outline Plan process following any agreement reached with MediaWorks and/or through the above certification process without the consent of MediaWorks. The works shall then be undertaken in accordance with the SSCNVMP confirmed by the Requiring Authority as part of the Outline Plan process.

Page 61

| Mt Eden Main Works CNV DWP

Relevant Section of CNV DWP


Construction Noise and Vibration Delivery Work Plan

Appendix C: Site Specific Management Plans (SSCNVMPs) Refer to separate document titled “Construction Noise and Vibration Delivery Work Plan - Appendix C – Site Specific Construction Noise and Vibration Management Plans”.

Page 62

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan

Appendix D: Project Sustainability This table identifies the ISCA Credit Requirements relevant to the CNV DWP and where they are addressed in the document. Relevant section

Other Relevant Information / Comments (How is this requirement being met)

Measures to mitigate noise during construction and operation have been identified and implemented

Section 9, Appendix C

Designation conditions require this

DIS-2 Level 1

Monitoring of noise is undertaken at appropriate intervals and in response to complaints during construction.

Section 11

Designation conditions require this

DIS-2 Level 2

For construction, modelling and monitoring demonstrates no recurring or major divergences from the sites noise management goals.

Section 4.2.3

Exceedances are predicted, but will be managed through BPOs

For operation, modelling demonstrates no recurring or major exceedances of noise goals.

N/A

This CNV DWP addresses construction only

For construction, modelling and monitoring demonstrates no divergence from the noise management process in ISCA approved noise guidelines For operation, modelling demonstrates no recurring or major exceedances of noise goals.

Section 6 Section 12.3

Exceedances are predicted, but will be managed through BPOs

Credit

Requirement *

Noise DIS-2 Level 1

DIS-2 Level 3

Section 6 Section 11 Section 12.3

N/A This CNV DWP addresses construction only

Vibration DIS-3 Level 1

Measures to mitigate vibration during construction and operation have been identified and implemented

Section 9 Appendix C

Designation conditions require this

DIS-3

Monitoring of vibration is undertaken at appropriate intervals and in response to complaints during construction.

Section 11.2

Designation conditions require this

No physical damage has been caused to any buildings or structures by vibration caused by construction or operation.

Section 7 Section 12.3

Building condition surveys will be carried out as detailed in section 7 and 11.

For operation, modelling demonstrates no exceedances of vibration goals for human comfort criteria.

N/A

Level 1 DIS-3 Level 3

* Refer to ISCA Rating Tool for full details of the requirement

Page 63

| Mt Eden Main Works CNV DWP

This CNV DWP addresses construction only


Construction Noise and Vibration Delivery Work Plan

Appendix E: Consultation Records Communications records are contained in the communication and consultation plan (CCP). Community and Business Liaison Group (CLG) comments on this CNV DWP are recorded in Table E-1, the Independent peer review comments are recorded in Table E-2, and comments from Auckland Council are included in Table E-3. All communications records relating to the two Enabling Works DWPs are attached to those DWPs (refer Section 2.4).

E.1

CLG Comments

Table E-1: CLG review comments

Date

CLG Member

Comment

Response Craig Fitzgerald (MDA)

11/05/2020

Kelvin Norgrove

Just wondered if construction operating hours/days will change to allow catching up on the programme?

Thibaut and I gave a summary of works. Prioritise noisy activities between 7am-7pm Mon - Sat, extending to 10pm where required. Some night works are required to support BOL. Explained the need for these (tunnelling to comply, BOL limited short interval works needed to keep workers safe and train line operating).

Tim Harding

Will you limit work after Addressed above. 7:00pm to low-noise work? What sort of work will it be?

E.2

Independent peer review Comments

Table E-2: Independent peer review comments

DWP Section

Comment

Response

Agile comments on draft (email), dated 29 April 2020 Table 6.2

Clarity sought on extent of night works

We have been advised that night/weekend work will be required only for craning the bridge platforms. List of receivers at risk from night works has been updated and clarified. (Table 5.1)

GIS maps

Errors and comments regarding specific receivers

GIS maps updated to reflect comments, following a meeting to discuss the details

Agile comments on Rev 000 (CA-09), dated 6 July 2020 General 1. Condition 36.3 (e) requires identification of comments on the â&#x20AC;&#x153;The timing of construction activities that are likely to create an adverse noise and vibration DWP effectâ&#x20AC;?. However, descriptions in Appendix C involving timing, relate to overall work hours only. They make no mention of specific times Page 64

| Mt Eden Main Works CNV DWP

Refer our response to question 4 below. Night-works are well defined, and the specific timing of works during the daytime period is less important - unless a particular receiver has daytime sensitivity (as identified in their SSCNVMP).


Construction Noise and Vibration Delivery Work Plan when adverse effects or exceedances on the criteria are foreseen. Please also refer to 4 below. 2. Condition 36.3 (k): This condition relates to the methods for monitoring noise and vibration. mitigation measures. The following comments relate to this condition: I. Current maps only show properties at risk and not predicted vibration levels, these should be provided so as to properly enable determination of the extent of vibration expected and subsequently, appropriate mitigation measures.

The vibration maps don’t show predicted vibration levels because the lack of accuracy doesn’t warrant it. The at source mitigation and management measures are set out in Section 9. The type, location and extent of these works will evolve, so we have used a conservative approach to identify where SSCVMPs are needed. Engagement will inform any further mitigation measures to be included in the SSCVMPs. Monitoring will verify residual levels in Section 11 with feedback loops to ensure updates. The staging of the SSCNVMPs and their provisions to Auckland Council over the next four years will allow the Link Alliance to better define best practice mitigation measures. A recommendation regarding the staged provisions of the SSCNVMPs to Council is expected in the outline plan decision.

Comments on SSCNVMP’s in relation to condition 37 and 38

Page 65

II. Table 7.1 indicates that the Down-The-Hole (DTH) piling method is to be used for retaining wall and bulk excavation works, but these are not mentioned elsewhere in the CNV DWP or SSCNVMPs.

Section 7.1 notes that we have no data for this activity. Setbacks will be informed by monitoring (Section 11). Section 7.2 notes that this method is proposed in the Fenton St area.

III. DTH piling does not have a set back distance listed in 7.1 due to a lack of data, but we understand that MDA have conducted measurements with the DTH method previously. If applicable, this data should be included in 7.1 and in any relevant SSCNVMPs and vibration maps, as the method is understood to be quite vibrationally intensive and a significant noise source.

We do not have this data. DTH piling uses a percussive drill bit like a blast hole drilling rig. Blast hole drilling produces high noise levels, but low vibration levels. We expect DTH piling to be similar, and have proposed this to be verified through monitoring in Section 11. We expect the vibration risk zones in this area will be controlled by rock breaking, rather than DTH piling.

3. Condition 37.5 (a) relates to the extent to which the noise may exceed the standards in condition 31 and 32. The SSCNVMP’s do not indicate what the blasting noise exceedance is at relevant receivers in relation to condition 32 although there are notes in Section 8 that trial blasts have been used to establish likely performance. It should be confirmed that the

| Mt Eden Main Works CNV DWP

Section 8.1 has been updated to include results from recent production blasts. It also advises all blasts will be designed to be fully compliant and that vibration, not noise, has been the controlling factor. Blast noise is successfully mitigated using blast mats and overburden.


Construction Noise and Vibration Delivery Work Plan blasting plan is expecting compliance with the project criteria. 4. Condition 37.5 (b) relates to the timing and duration of any exceedance. The reference to the term 'duration' when used in conjunction with any exceedances highlighted within the specific SSCNVMP's is vague. We recommend expanding on the specific duration per phase where exceedances occur. We would suggest at least aligning it with 6803 definitions of short, medium- or long-term duration or other classification as appropriate. While we accept it is challenging to commit to a specific number of days or weeks for any specific activity, without guidance of rough duration for an exceedance of the project criteria it is very difficult for a receiver to provide appropriate feedback on what mitigation measure would be suitable. It also seems that without a basic commitment to the rough duration, mitigation measures cannot be meaningfully identified or discussed.

NZS 6803 recommends generic noise limits based on overall project duration (e.g. weeks, months, years). It is not appropriate to use this part of the Standard to give context to exceedance duration. The effects of an exceedance relate to the activity duration (e.g. hours, weeks, months). Construction staging is referenced and summarised in 2.3 and the noise maps relate to the timing of each stage. Specific timing for any given receiver will be discussed with that receiver, and their SSCNVMP will be updated accordingly.

General 5. Although we are aware that the ‘Mt Eden comments on the Main Works’ sections as part of every SSCNVMP still require updating as receivers are SSCNVMP’s communicated with, we recommend that these sections correctly address each sub-condition (a-f), in detail, as per condition 37.5. The currently highlighted sections noted for change do not cover all of these aspects and it would be inaccurate to suggest only the highlighted sections require updating.

Appendix C Table 1 addresses the generic components of a-f. In some cases, also including them in the SSCNVMP adds value (e.g. C12 5 Porters Ave – ADHB SSCNVMP). However, in almost all other cases, it would result in unnecessary repetition and would not improve usability. The SSCNVMPs are outcomes focused.

6. As for the mitigation measures, we do not feel it sufficient to just state that mitigation measures were considered but are not required as part of the BPO, as was done for the enabling works phase. We recommend that clear reasons are provided as to why the mitigation measures that were applied (and ones that were not) reflects the best practicable option, as per condition 37.7 (f).

This placeholder text is highlighted in each SSCNVMP pending engagement. It does not by any means suggest that mitigation measures aren’t required in every case. Details will be provided in each SSCNVMP once the BPO is established on a case-bycase basis.

7. It is noted at several receivers it states that the rock breaking activities will be taking place for short periods (with the mitigation measures assumed to be applied accordingly) and that other utilities works will generally be compliant. The relevant receivers, however, will be affected by at least five of the seven stages of the main works (e.g. Utilities and drainage, Retaining wall construction, Bulk excavation, Pedestrian bridge construction, Pedestrian bridge night works), which we feel is significant.

Once again, the SSCNVMPs for the Main Works are not complete. Rock breaking will be a key activity that will require mitigation and management. We have provided general mitigation options, which will form the basis of discussions with affected parties. Any other mitigation will be developed after consultation and added to the relevant SSCNVMPs.

Page 66

| Mt Eden Main Works CNV DWP

In addition, a recommendation regarding the staged provisions of the SSCNVMPs to Council is expected in the outline plan decision.


Construction Noise and Vibration Delivery Work Plan The descriptions at the receivers should, therefore, be updated to reflect the significance as well as more emphasis placed on relevant mitigation due to the significant effect. This scenario is relevant to a number of receivers where the phases overlap, especially along either side of Fenton and Haultain Street. 8. Piling is said to only occur between 7am-7pm unless the BPO demonstrates that it can occur outside if these hours. However, no assessment has been presented to support a decision to carry out the activities outside of the mentioned hours as part of the BPO. If such an assessment were to be completed, the mitigation methods would also need to be updated as the BPO would likely change to reflect the effects on recipients.

Correct. Special cases occur, and the framework of the CNV DWP has retained enough flexibility to enable adoption of the BPO. For example, C6 sheet piling was undertaken on Sundays in Boston Rd at the request of neighbouring businesses. The businesses were closed on Sunday, so avoided significant amenity effects. This opportunity was identified through the engagement process and implemented as the BPO following Council approval. In general, where pilling is expected outside of these hours and during the Block of Line, it is considered the BPO due to health and safety requirements relating to works in close proximity to the railway corridor.

9. A frequent comment for areas that are significantly exceeding the 75 dB LAeq noise limit, is â&#x20AC;&#x153;the levels will reduce rapidly as works migrate awayâ&#x20AC;?. This statement is not sufficient on its own as a means of mitigation. As well as the benefits of physical distance being of limited benefit in dense urban settings due to reflections of surrounding building, there is also significant uncertainty about how long the works will remain in close proximity. Refer also to item 4 above.

The statement is intended to highlight that the predicted levels are worst-case. It is important for receivers to understand that they will not receive 75dB+ for months at a time. We aim to provide process certainty, not level certainty. Refer response to item 4. With the staged development of the SSCNVMPs, we will be able to advice affected parties the anticipated duration of works and determine the appropriate mitigation measures through the engagement process.

10. The night works noise effects are not mentioned at any of the receivers in Appendix C which are listed as being exceeded by night works in the DWP (Table 5-1). The night time noise effect should be included at the following receivers:

These SSCNVMPs contain placeholders only. They will be updated once consultation occurs. The only night works identified to date are cranes - refer Section 9.2 and descriptions in 6.2.6 and 6.2.7.

- 3 Porters Avenue; - 5 Porters Avenue; - 6 Porters Avenue; - 11 Fenton Street; - 140 New North Road; and - 22-24 Normanby Road 11. Where the limits of cosmetic damage due to Accurate predictions of vibration are not vibration are proposed to be exceeded, an possible. We have adopted an effects expected vibration level and likely effects envelope approach. Discussing the Page 67

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan should be provided to accurately inform occupants of the extent of any vibrations and effect.. BS 5228-2 2009 may assist here. Without some quantification of effects, occupants may not be prepared for or understand the extent of the impact.

managing of potential effects with receivers is much more relatable and relevant to them than saying the vibration level will be X mm/s PPV. BS 5228-2 does not assist as it provides no guidance on effects for levels between 1 mm/s and 10 mm/s PPV. However, it does provide guidance on amenity effects, which are summarised in Section 12.2.

12. Numerous SSCNVMPs mention that they Updated references in the identified have only been prepared per condition 37 when SSCNVMPs. the construction is predicted to exceed the standards in CRL designation conditions 31 and 33. Condition 37 only sets requirements for SSCNMPs, this should be updated to include condition 38, which outlines requirements for SSCVMPs. The receivers requiring amending are: - 2 Porters Avenue; - 3 Porters Avenue; - 4 Porters Avenue; - 6 Porters Avenue; - 3 Fenton Street; - 5a Fenton Street; - 5 Fenton Street; - 11 Fenton Street; and - 32 Normanby Road.

Page 68

13. SSCNVMPs indicate that communication is only to take place where noise limits are exceeded. This should be changed to reflect exceedances on vibration criteria as well.

Updated references in the identified SSCVMPs.

14. Vibration stand-off distances listed in Section 7.1 are inconsistent, specifically in relation to the difference in set back distances listed for sheet piling and vibrated pile casings. As these activities are similar in vibratory nature, they would typically be expected to have similar attenuation rates.

We have used the extensive data set from BS 5228-2 and our own measurements to establish these values. The data is valid. To address the concerns though, we note that sheet piling is often undertaken until refusal, at which point vibration levels are often significantly higher. Casings are usually vibro driven to a certain depth, and refusal is not so common.

15. SSCNVMP’s makes reference to “cosmetic damage” when discussing vibration effects. This does not accurately represent the meaning of the DIN 4150-3 Standard which refers to “minor damage” and at no point mentions “cosmetic damage”. The standard also defines partitions becoming detached from loadbearing walls or floors as “minor damage”, which does not seem consistent with the use of “cosmetic”. This terminology should be corrected so as not to be misleading to receivers.

We responded to this question in the Normanby Rd Early works CNV DWP. The word ‘cosmetic’ is routinely used to avoid confusion with structural building damage. British Standard BS5228-2:2009 says “In some circumstances, however, it is possible for the vibrations to be sufficiently intense to promote minor damage. Typically this damage could be described as cosmetic and would amount to the initiation or extension of cracks in plasterwork, etc., rather than

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan the onset of structural distress. In more severe cases, falls of plaster or loose roof tiles or chimney pots can occur”. The quote from the DIN Standard relates to damage to non-load bearing partitions, consistent with a cosmetic effect.

Appendix C (5 Porters Ave)

16. Notwithstanding the above, Condition 38.4 only permits works to exceed the building damage limits “for a building, structure or infrastructure that has been assessed by a suitably qualified and experienced structural engineer”. No such assessment is provided in the DWP and needs to be for any site where there is an expectation of breaching the building damage limits – regardless of whether MDA deem the effect to be minor, cosmetic or otherwise.

This is incorrect. Condition 38.4 is not about exceedances of the vibration limit. It is about relaxing the limit to permit higher levels for particular receivers. In order for this to happen, a structural engineer must say it is safe to do so. An example of this is the CPO in Britomart. It is a heritage building, so would normally be categorised line 3 for vibration sensitivity. However, a structural engineer assessed the building and categorised it line 1, except line 2 for the west façade. A heritage expert was also involved with this process for this building.

Vibration levels are predicted up to >10mm/s, which would be highly likely to cause disturbance to occupants of the building, especially due to the nature of the building. No mitigation measures are proposed for these vibration levels as per condition 38.5e. Relocation may be necessary if an alternative significantly less vibrationally intensive method cannot be found.

Section 9 sets out general vibration mitigation strategies – including “less vibrationally intensive methods” – which will be put in place for this receiver as much as practicable. This SSCNVMP has not been completed yet, and more specific mitigation will be addressed at the appropriate time.

Appendix C No SSCVMP despite being highlighted in the (25-27 Enfield St) bulk excavations and retaining walls works.

E.3

Refer C28: 25 Enfield SSCNMP.

Auckland Council

Table E-3: Council peer review comments

DWP Section

Comment

Response

Styles Group comments on draft, dated 11 May 2020 Section 2.3.1

Night and weekend work may be required for safety reasons, and that is understood and explained in this section. Are night works are required for any other reason? Please see comments for Section 6.

We have been advised that night/weekend work will be required only for craning the bridge platforms.

Section 6

Risk Assessment is still in draft form and parts need to be completed.

Section 6 has been completed.

Section 6

Section 6 repeatedly advises that: Piling will only occur 7am – 7pm Monday – Saturday, unless the BPO demonstrates that it is required outside of these hours. At what stage will the BPO be confirmed?

This level of certainty cannot be provided. BPO will change as construction methods and site conditions vary.

Page 69

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan Section 6

The risk assessment states that the following receivers are at risk of night works 8, 10-12 and 71 Boston Road, 5-7 Water Street, 25 Enfield Street, 22-24, 26, 32, 5163 Normanby Road How will night works be decided (BPO) and will the SSCNVMP’s be updated?

We have been advised that night/weekend work will be required only for craning the bridge platforms. List of receivers at risk from night works has been updated and clarified. (Table 5.1)

Section 6

Does the noise at risk system mean receivers are at risk of exceedance of a determined amount of noise, such as 5dB, 10dB, 15dB above the limit? It is noted that the vibration risk system is clear: buildings at risk of cosmetic building damage from the construction. Please provide more information on the noise risk system

GIS noise maps show receivers where noise is expected to exceed 75 dBA, for each stage of works and the predicted levels. SSCNMPs have been generated for all these receivers and will be updated with predicted levels as they are developed further

Section 8

Section 8 states that: The work will be done by a blasting contractor. It is their responsibility to design and carry out the blasting programme so that vibration and air overpressure comply with the limits in CRL designation condition 32. The blasting contractor has prepared a Blasting Management Plan (BMP) – does the BMP also need review?

No comment from us. Link Alliance can provide the BMP.

Section 8

Section 8 states that: Trial blasts were carried out by Red Bull Powder Company Ltd on 5 February 2020 in order to measure the way vibration propagates through the basalt in the Mt Eden works area. The findings are summarised in Red Bull’s report ‘Link Alliance – 97 Mt Eden Rd Seed Hole Analysis’, - does this report need review Section 9.5 states that Temporary noise barriers will be used where a construction noise limit is predicted to be exceeded and the barriers would noticeably reduce the construction noise level. Could a plan be provided to show the location of the temporary noise barriers

No comment from us. Link Alliance can provide the BMP.

Sections 9.6, 9.7, 9.8 and 9.10 outline mitigation to be used where practicable. SSCNMP’s directly refer the user (contractor) back to the DWP, so either the CNV DWP or SSCNVMP’s need updating once it is known if the mitigation is practicable. We recommend that specifics are included in the SSCNVMP’s as these are live documents that can be amended when the BPO is identified. Or will the CNVDWP be updated once it is known if the mitigation is practicable or not?

Any mitigation measures that relate to the source will be shown in the DWP. Mitigation that relates to the receivers will be shown in their SSCNVMP. If changes are made, the appropriate document will be updated

Section 9.5

Sections 9.6, 9.7, 9.8 and 9.10

Page 70

| Mt Eden Main Works CNV DWP

Temporary noise barriers are most effective when they are located close to the noise source. They won’t be at fixed positions , and will move with the noise source (e.g. the breaker)


Construction Noise and Vibration Delivery Work Plan 12.3

Temporary relocation will be considered for sensitive receivers where all practicable noise and vibration management and mitigation measures have been implemented and significant adverse noise effects and vibration are predicted. This will be in exceptional cases only, and an SSCNVMP will have been prepared. Advice from the Acoustics Specialist will be incorporated as part of the SSCNVMP process (refer Sections 5.1.2 and 5.2.3). Have any receivers been identified as potentially having significant adverse noise or vibration effects that could require temporary relocation?

Decisions on temporary relocation will come about following consultation and will be shown in their SSCNVMP. We have not foreshadowed the need for relocation at this stage.

12.1

The noise effects matrices in tables 12-1 and 12-2 provide effects up to 85 dB LAeq external and 65 dB LAeq internal. Are any receivers predicted to received levels 5 dB or more higher than the levels in tables 12-1 and 12-2?

There are instances where external levels are predicted to exceed 85 dB LAeq. However, they are worst case, brief and infrequent (based on the closest point of works with no screening). Readers can see from the colour pattern that levels higher than 85 dB would be coloured red.

Appendix C

The draft SSCNVMP’s provided do not meet this objective. “We have previously agreed that where activity-specific BPO measures are implemented at source, rather than at the receiver, they are described in the CNV DWP only and not reproduced in each SSCNVMP. The reason LA want to take this approach is to avoids repetition and ensures that when BPO is updated, it only needs to be updated in the CNV DWP. However, the CNV DWP’s are not specific on the whether or not the mitigation will be implemented. This is addressed in Q7 above.

We cannot provide certainty on whether or not mitigation measures are practicable until site conditions and/or exact methodologies are established. As these elements change, and so will these “living” documents. This is the purpose of a management plan, and the purpose of the regular review process (Section 1.6).

Page 71

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan Appendix C

The SSCNVMP’s re-direct the user to the mitigation methods in the DWP. This is an approach we agreed LA could use but only for at source mitigation (e.g. enclosures around a concrete saw, or screening of rock breaking, etc) and not for mitigation at receiver, which needs to be in the SSCNVMP. The SSCNMP’s for the Main Works refer the user back to various other CNVDWP’s. For example, SSCNVMP C12 refers the user back to the Mount Eden Enabling works CNVDWP and SSCNMP C28 refers the user back to the Normanby Road early works CNVDWP. Our concern here is that the user (contractor) will need to have 3 or 4 DWP’s and if they are all 65 pages long this could affect how well the system will work for the user (contractor). Can we clarify if the Main Works CNVDWP should be stand alone document, or is suitable that multiple references are made to the previous DWP’s for the Early Works and Enabling Works? This is partly answered in section 6.2.1: The relevant content will be brought across into this section of the main works CNV DWP prior to the DWP being confirmed as part of the Outline Plan process, to ensure the content is up to date.

SSCNVMPs updated to remove references to previous DWPs

Appendix C

Q11: Table 1 shows the SSCNVMP components. To address conditions 37.5 and 38.5 the table shows: CNV DWP Section 6 identifies predicted noise and/or vibration exceedances using the modelling outputs in Sections 6.2 and 7.2. It identifies the need for an SSCNVMP. Each SSCNVMP summarises the consultation undertaken with individual receivers regarding the predicted exceedances. Section 6 does not provide predicted noise levels or the exceedances, but does provide set back distances for various activities. Could the SSCNMP’s provide the set back distances so we can get an approximation of the potential exceedance?

Table 5.1 will provide expected levels at each receiver for each works stage. Levels are also shown on the noise maps.

Appendix C

SSCNVMP’s 2 – 27, 31 Refer to both Mt Eden Main Works CNV DWP and Mt Eden Enabling Works CNV DWP SSCNVMP’s 28 – 30 Refer to both Mt Eden Main Works CNV DWP and Mt Eden Early Works CNV DWP

References removed

Page 72

| Mt Eden Main Works CNV DWP


Construction Noise and Vibration Delivery Work Plan Appendix C

SSCNVMP’s incorrect references and assessments. Some of the SSCNVMP’s seem to have incorrect references and assessments. For example, C2 (12-14 Nikau Street) states that the south façade is predicted to be exposed to noise levels up to 93 dB LAeq during the closest demolition and bored piling activities. This is a significant exceedance exceeding the 75 dB LAeq noise limit. C2 states that The predicted construction noise effects from Table 10-1 in Section 10.1 are predicted to be typically acceptable, but with the potential for some disturbance. Table 10.1 in the Main Works CNV DWP refers to communication. Assuming that the reference should be made to is to 12.1? This table shows that the predicted noise levels of 93 dB LAeq will result in Difficulty holding a normal conversation and reduction in work efficiency, which is not consistent with the comments in the SSCNMP. Please confirm if the predicted noise level of 93 dB LAeq is correct and what the correct CNVDWP reference should be.

SSCNVMPs updated

Appendix C

SSCNVMP’s 34 – 81 have not been completed yet.

The framework for SSCNVMP 32 to 82 has now been completed. Each SSCNVMP will be finalised when consultation with the individual landowners has been completed and mitigation options agreed.

Styles Group comments on Rev 000, dated 10 July 2020 Section 6 (Night Works)

If the BPO is not known at this stage (when SSCNVMP’s are being reviewed) then will there be time to review the BPO and is a further review of SSCNVMP required if the BPO triggers the need for unplanned night works?

The purpose of the certification process is to ensure the management framework is fit for purpose. It is a living document that will evolve with the works. It includes feedback loops to verify predicted levels as representative and response protocols as BPO. In addition, a recommendation regarding the staged provisions of the SSCNVMPs to Council is expected in the outline plan decision.

Section 6 (Night Works)

Page 73

We agree with the steps for night works, but it is still not clear what the actual process if/when the need for unplanned night works is identified. We assume that this will go back though compliance for review. Please confirm.

| Mt Eden Main Works CNV DWP

Section 9.2 sets out construction hours and approach for necessary night works. Review would be required if there is a material change in accordance with Section 1.6. External review/re-certification of the CNV DWP and/or SSCNVMPs is triggered by the matters set out in Section 1.6.


Construction Noise and Vibration Delivery Work Plan Section 6 GIS Maps

How do we access the portal for the GIS noise maps (if it is required)?

Section 7 (Risk assessment – Vibration)

Please provide more detail on the use of the hydraulic splitter instead of rock breaking. Has the hydraulic splitter been considered for use in any other stages of rock breaking?

Section 8 (Blasting)

We do not have a copy of the BMP. If the BMP is provided we can review the blasting effects. We appreciate that the barriers will be temporary but are there locations where you already know they will be needed. Can you provide a plan showing the locations of temporary noise barriers (if the locations are known)? This plan will assist the contractors and the council monitoring officer. In section 11.1 of the DWP, part of the process for dealing with a noise exceedance is to prepare (or update) a SSCNMP. When this is required will Councils compliance officer be notified? We recommend this is included in the step diagram figure 11-1. Same with vibration in section 11.2 and figure 11-2. This would be in line with the LA process set out in section 1.6.

BMP has been provided by Link Alliance.

A further review will be required when the mitigation measures are known (the site conditions and/or exact methodologies are established).

The purpose of the certification process is to ensure the management framework is fit for purpose.

Section 9 (Mitigation and Management)

Section 11 (Monitoring)

Appendix C

PDF versions of the maps have been provided. We are still working to enable external access to the GIS maps. The hydraulic splitter was proposed by Link Alliance for the Station Platforms stage only. Section 7.2 states that it should be considered in other locations too, but we note that it may not be practicable in all instances.

Map has been developed and provided.

The DWPs and SSCNVMPs are living documents and must have the freedom to be updated as necessary. The purpose of the certification process is to ensure the management framework is fit for purpose. External review/re-certification of the CNV DWP and/or SSCNVMPs is triggered by the matters set out in Section 1.6.

A recommendation regarding the staged provisions of the SSCNVMPs to Council is expected in the outline plan decision. Any subsequent external review/re-certification of the CNV DWP and/or SSCNVMPs is triggered by the matters set out in Section 1.6. Appendix C

Appendix C

Appendix C Page 74

Table 5.1 does not provide the expected levels at each receiver and there are no noise maps included in the documents for review. Please confirm which the details in table 121 are correct and that they are consistent with the comments in the SSCNVMP’s (e.g. C2 (12-14 Nikau Street).

Is there an update on the following proposed building modifications for 5

| Mt Eden Main Works CNV DWP

Noise levels are provided on the maps. PDFs have been provided.

Table 12-1 provides general guidance for the initial screening by the contractor and affected parties. Conversations with each receiver involve more context (e.g. sensitivity, façade performance, duration of works) so we don’t constrain the discussion just to the descriptions in Table 12-1. These upgrades have been reflected in their SSCNVMP.


Construction Noise and Vibration Delivery Work Plan Porters Avenue?: - Secondary glazing to north and north-east facing windows. Note â&#x20AC;&#x201C; secondary glazing involves retro-fitting an acrylic pane inside the existing glazing, with an airgap of 50mm or more. It does not change the existing glazing - Upgrading the sound insulation of the lintels (above ceiling level) to reduce sound entering offices via the ceiling path. When will the SSCVMPâ&#x20AC;&#x2122;s be completed?

Appendix C

E.4

Engagement to inform the Main Works SSCNVMPs is due to commence. This may prioritise receivers near early works to ensure necessary SSCNVMPs are complete prior to the works commencing. There is no set end date.

Mana Whenua

The CNV DWP was issued to Mana Whenua in May 2020 for review.

Page 75

| Mt Eden Main Works CNV DWP


Turn static files into dynamic content formats.

Create a flipbook
Construction Noise and Vibration Delivery Work Plan by City Rail Link Ltd - Issuu