ENABLING WORKS CONTRACT 2 CONSTRUCTION NOISE AND VIBRATION DELIVERY WORK PLAN Separable Portion 1 – Cut and Cover Works Document Ref: CRL-PAT-ENV-CON-PLN-000903 Revision: 06
FINAL 3rd June 2016
COMMERCIAL IN CONFIDENCE
This page intentionally left blank.
DOCUMENT INFORMATION Organisation:
Connectus
Document Title:
Construction Noise and Vibration Delivery Work Plan
Fulcrum Document Number:
CRL-PAT-ENV-CON-PLN-000903
Document based on MMS No:
n/a
Client:
Auckland Transport
Project:
CRL Enabling Works: Contract Two
Location:
Auckland CBD
Project No:
2665
REVISION HISTORY Rev
Date
Details
01a
22/09/2015
1
st
Draft for Connectus review
nd
Author
Approver
C. Drewery
C. Hind
01b
28/09/2015
2 Draft – AT Review Sent as Rev 01 to AT
C. Drewery
C. Hind
02
02/10/2015
Draft for Consultation
C. Drewery
C. Hind
03
02/11/2015
Draft for IPRP – incorporating CLG Comments
C. Drewery
C. Hind
04
26/02/2016
Draft for AT and Connectus Review – incorporating IPRP comments and updated methodology
C. Drewery
C. Hind
05
21/03/2016
Final
C.Drewery
C.Hind
06
3/06/2016
Final incorporating Council review comments
C.Drewery
C.Hind
This document remains the property of Connectus. Its contents are confidential and shall not be reproduced, destroyed or given away without the express, written permission of Connects. The electronic version of this document in MMS Database on designated server(s) is the Master Copy and is a controlled document. Unless specifically noted thereon, other copies of this document are uncontrolled.
This page intentionally left blank
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Table of Contents Document information .........................................................................................................................3 Revision History ..................................................................................................................................3 Acoustic Glossary ...............................................................................................................................3 1
Introduction........................................................................................................................5 1.1
Purpose of Construction Noise and Vibration DWP
7
1.2
Designation Condition Requirements
7
2
Project Description........................................................................................................... 18 2.1
Summary of Methodology
18
2.2
Hours of Operation
23
3
Roles and Responsibilities ............................................................................................... 24 3.1
4
CNV DWP Author
24
Noise and Vibration Criteria ............................................................................................. 25 4.1
Noise Criteria
25
4.2
Vibration Criteria – Building Damage
25
4.3
Vibration Criteria – Amenity
26
5
Equipment and Noise and Vibration Source Data ............................................................. 27 5.1
Noise Sources
27
5.2
Vibration Sources
34
6
Affected Parties ............................................................................................................... 36 6.1
Noise
36
6.2
Vibration – Building Damage
38
7
General Management Procedures and Mitigation Measures ............................................. 40 7.1
Construction Noise and Vibration Management Schedules
40
7.2
Training
40
7.3
Construction Traffic and Deliveries
41
7.4
Plant and Equipment
41
7.5
Pneumatic Breakers
42
7.6
Piling and Compaction
42
7.7
Noise Barriers and Enclosures
43
7.8
Traffic tyre noise
44
7.9
Scheduling of Activities
44
8
Site Specific Construction Management Plans ................................................................. 45 8.1
Site Specific Construction Noise Management Plan (SSCNMP)
45 Page 1
Connectus Project #: 2665 Client: Auckland Transport
8.2
Site specific Construction Vibration Management Plan (SSCVMP)
46
8.3
Site Specific Construction Noise and Vibration Management Plan (SSCNVMP)
47
9
10
11
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Communicaton ................................................................................................................ 48 9.1
Communication
48
9.2
Complaints Procedure
49
Monitoring ....................................................................................................................... 50 10.1 Noise
50
10.2 Vibration
53
10.3 Reporting
56
10.4 Building Condition Surveys
56
Contingency Measures .................................................................................................... 57 11.1 Management Process
57
11.2 Noise
57
11.3 Vibration – Building Damage
57
11.4 Vibration – Amenity
58
11.5 Discussion
58
Appendix A: ISCA Requirements........................................................................................................ A Appendix B: Schedule of Identified At-Risk Receivers, Structures and Services (Vibration)................. B Appendix C: Schedule of Identified At-Risk Receivers (Noise) ............................................................ C Appendix D: Record of Communication / Consultation with notable and Sensitive Receivers .............. D Appendix E: Record of CLG & Independent Peer Review comments .................................................. E CLG Comments
1
Independent Peer Review – CNV DWP
2
Independent Peer Review – SSCNVMP
7
Appendix F: Construction noise and vibration induction ...................................................................... F Appendix G: Noise Monitoring Template ............................................................................................ G Appendix H: Vibration Monitoring Template ........................................................................................ H Appendix I: SIte Specific Construction Noise and Vibration Management Plans ................................... I
Page 2
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
ACOUSTIC GLOSSARY Term
Definition
dB
A unit of measurement on a logarithmic scale which describes the magnitude of sound pressure with respect to a reference value (20 µPa) ‘
CFA
Continuous Flight Auger
LAeq(T)
The ‘A’-weighted “Time-Average Sound Pressure Level” (also known as the “Equivalent Continuous Sound Pressure Level”). The Time-Average Sound Pressure Level is the constant value of A-Weighted Sound Pressure Level, for a given period (T), that would be equivalent in sound energy to the timevarying A-Weighted Sound Pressure Level measured over the same period [Unit: dB(A)]
LAFmax(T)
The maximum value of A-Weighted Sound Pressure Level measured using an ‘F’ time weighting during the period T. [Unit: dB(A)]
PPV
The peak particle velocity (PPV) is defined as the maximum instantaneous positive or negative peak of the vibration signal. PPV is often used in monitoring of blasting vibration since it is related to the stresses that are experienced by buildings.
NZS 6803:1999
New Zealand Standard NZS 6803:1999 “Acoustics – Construction Noise”.
DIN 4150-3:1999
German Standard DIN 4150-3:1999 “Structural Vibration – Part 3: Effects of vibration on structures”. This standard is generally adopted in NZ to assess building damage.
BS 5228-2:2009
British Standard BS 5228-2:2009 “Code of practice for noise and vibration control on construction and open sites – Part 2: Vibration”. This is the standard adopted for this Project to assess human response to construction.
SSCNMP
Site Specific Construction Noise Management Plan
SSCVMP
Site Specific Construction Vibration Management Plan
SSCNVMP
Site Specific Construction Noise and Vibration Management Plan
Page 3
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
This page intentionally left blank
Page 4
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
1 INTRODUCTION The City Rail Link (CRL) project comprises the construction, operation and maintenance of a 3.4 km underground passenger railway, running between Britomart Station and the North Auckland Rail Line in the vicinity of Mt Eden station. The works relating to this Construction Noise and Vibration Delivery Work Plan (CNV DWP) constitute part of the enabling works for the CRL. The works (the Project) involve the construction of twin rail tunnels within the Albert Street road corridor from Customs Street West to Wyndham Street. The tunnels will be constructed using a staged cut and cover method and are expected to take 33 months to complete. Figure 1 outlines the extent of works for the Project. This CNV DWP has been prepared by AECOM New Zealand Limited (AECOM) and forms part of the Construction Environmental Management Plan (CEMP) for the Project. Some aspects of construction noise and vibration management are detailed outside of this CNV DWP. Procedures relating to environmental training, including noise and vibration site management procedures are detailed within Section 4.2 of the Project CEMP. Communications and environmental complaints procedures for the Project are provided in the Project Communication and Consultation Plan. (Appendix O of the Project CEMP).
Page 5
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Figure 1 Extent of Project Works
Page 6
Connectus Project #: 2665 Client: Auckland Transport
1.1
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
PURPOSE OF CONSTRUCTION NOISE AND VIBRATION DWP
The purpose of this CNV DWP is to identify and provide for implementation of the Best Practicable Option (BPO) to avoid, remedy or mitigate adverse noise and vibration effects resulting from construction of the Project. It identifies the noise and vibration performance standards that must, where practicable, be complied with and details the management and control methodologies to be implemented in order to achieve compliance. Where compliance cannot be achieved, the CNV DWP identifies BPO mitigation measures to be implemented on a site specific basis. The CNV DWP is generally consistent with the draft CNVMP dated 25 July 20121 which was provided as part of the Notice of Requirement documentation for CRL. This CNV DWP will be implemented throughout the entire construction period and will be the primary tool for the management of construction noise and vibration effects resulting from the Project. It is a ‘living document’ which may undergo expansion and updates as the Project progresses and working conditions become clearer. Designation Conditions 22 and 23 set out the CNV DWP review and update process that must be followed. This process is summarised as follows:
This CNV DWP is required to be reviewed annually or as a result of a material change to the Project or to address unforeseen adverse effects arising from construction or unresolved complaints. The review may be initiated by either Auckland Council or the Requiring Authority. Condition 23 requires affected parties to be notified of the review and any material change proposed to this CNV DWP (including SSCNVMPs, SSCNMPs and SSCVMPs).
This CNV DWP must clearly document the comments and inputs received by the Requiring Authority from affected parties about the material change, along with a clear explanation of where any comments have not been incorporated, and the reasons why not.
Any material change proposed to this CNV DWP shall be subject to an independent peer review as required by Condition 11.
Following the independent peer review any material change proposed to this CNV DWP relating to an adverse effect shall be submitted for approval to Auckland Council Compliance and Monitoring Officer, at least 10 working days prior to the proposed changes taking effect. If any changes are not agreed, the relevant provisions of the RMA relating to approval of outline plans shall apply.
It is intended that the noise and vibration schedules in Appendices B and C of this CNV DWP will be updated as necessary with actual noise and vibration levels of the equipment used on site. Providing that the noise and vibration effects at the affected properties are either reduced or maintained at the same level with the mitigation measures identified in this CNV DWP implemented, it is not intended to re-submit the CNV DWP for review/approval. This CNV DWP has been prepared in consultation with a Community Liaison Group (CLG) and has undergone Independent Peer Review prior to submission to Auckland Council (as per designation conditions 7 and 11). A record of consultation outcomes (CLG and IPR) is included in Appendix E.
1.2
DESIGNATION CONDITION REQUIREMENTS
Table 1 identifies the CRL designation conditions that specify what is to be addressed by the CNV DWP, and in turn which sections of the CNV DWP address these conditions.
1
Designation Condition 36.2 (b) incorrectly references 23 August 2013 as the document date.
Page 7
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Table 1 CNV DWP conditions and the relevant sections of this document
Condition Number
Relevant Section
Condition Communications – Notable Noise and Vibration Receivers
16.1
16.2
A SSCNVMP shall be prepared for all Notable Noise and Vibration Receivers (refer Condition 39). As part of the SSCNVMP (and further to Condition 15 of this designation), the Requiring Authority shall undertake communication and consultation, as soon as reasonably practicable (and at least once following confirmation of construction timing and methodology), with any Notable Noise and Vibration Receivers located within 200 metres of blasting, or within 100 metres (either horizontally or vertically) of the designation footprint for other construction activities. Communication and consultation with these parties should focus on a collaborative approach to manage the adverse effects from construction noise and vibration while works are undertaken in the vicinity.
9.1
The Requiring Authority shall undertake on-going communication and consultation with notable noise and vibration receivers throughout the duration of construction occurring in the vicinity. This communication shall be reported back to the “key contacts” (see Condition 13) and the Auckland Council Consent Monitoring officer for their review and confirmation of any further action to be undertaken. The Auckland Council Consent Monitoring Officer shall advise the Requiring Authority of its recommendation within 10 working days of receiving this information from the Requiring Authority.
9.1
Project Standards - Construction Noise Construction noise shall comply with the following Project Standards (unless otherwise provided for in a SSCNMP which is approved under Condition 37, 39 or 40): Receiver Type Occupied commercial and industrial buildings (including offices)
Monday to Saturday
Sundays and Public Holidays
At all other times
0700 – 2200
0700 – 2200
2200 – 0700
75 dB LAeq
75 dB LAeq
75 dB LAeq
75 dB LAeq
65 dB LAeq 1
60 dB LAeq
90 dB LAFmax
80 dB LAFmax2
75 dB LAFmax
31.1 Sensitive Noise and Vibration Receivers (excluding offices)
Early Childhood Education Centres (whilst occupied during normal opening hours)
35 dB LAeq in sleeping areas
Page 8
4.1 (Bear Park not impacted by project works)
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Condition Number Bear Park Early Childhood Education Centre at 32 Akiraho Street (whilst occupied during normal opening hours) 31.2
Relevant Section
Condition 35 dB LAeq in sleeping areas 65 dB LAeq in outdoor playing areas
Construction noise shall be measured and assessed in accordance with the provisions of NZS 6803:1999
10.1
Project Standards - Construction Vibration
33.1
Construction vibration (including blasting) shall comply with the following Project Standards for building damage (unless otherwise provided for in a SSCVMP which is approved under Condition 38, 39 or 40) Long-term 1 Short-term (transient) vibration (continuous) vibration PPV at horizontal Type of Structure PPV at the foundation at a frequency of plane of highest PPV at horizontal floor plane of highest 1-10Hz 10-50 Hz 50-100 Hz (mm/s) floor (mm/s) (mm/s) (mm/s) (mm/s) Commercial/ 20 20 – 40 40 – 50 40 10 Industrial Residential/ 5 5 – 15 15 – 20 15 5 School Historic or sensitive structures 3 3–8 8 – 10 8 2.5 Note: 1. Standard DIN 4150-3:1999 defines short-term (transient) vibration as “vibration which does not occur often enough to cause structural fatigue and which does not produce resonance in the structure being evaluated”. Long-term (continuous) vibration is defined as all other vibration types not covered by the short-term vibration definition. 33.1Construction vibration (including blasting) shall be measured in accordance with German Standard DIN 4150-3:1999. Note: Standard DIN 4150-3:1999 defines short-term (transient) vibration as “vibration which does not occur often enough to cause structural fatigue and which does not produce resonance in the structure being evaluated”. Long-term (continuous) vibration is defined as all other vibration types not covered by the short-term vibration definition.
Page 9
4.2
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Condition Number 33.2
Relevant Section
Condition Construction vibration (including blasting) shall be measured in accordance with German Standard DIN 4150-3:1999.
10.2
Project Standards - Construction Vibration (Amenity) Between the hours of 10pm and 7am vibration generated by construction activities (excluding blasting) shall not exceed: 34.1
(a) a Peak Particle Velocity (PPV) of 0.3mm/s when measured at any part of the floor of any bedroom;
4.3
(b) a noise level of 35 dB LAeq(15min) when measured in any bedroom.
4.3
Between the hours of 7am and 10pm vibration generated by construction activities (excluding blasting) shall not exceed: (a) A Peak Particle Velocity (PPV) of 1mm/s as measured on the floor of the receiving room for residentially occupied habitable rooms, bedrooms in temporary accommodation and medical facilities; and
4.3
(b) A Peak Particle Velocity (PPV) of 2mm/s as measured on the floor of the receiving room for retail and office spaces (including work areas and meeting rooms);
4.3
34.3
The limits in 34.1 and 34.2 shall only be investigated and applied upon the receipt of a complaint from any building occupant. They shall not be applied where there is no concern from the occupant of the building.
4.3
34.4
Where the limits in 34.1 and 34.2 are found (through measurement) to be exceeded then a SSCVMP shall be prepared for that receiver (Condition 38).
8.2
34.2
Construction Noise and Vibration DWP For the avoidance of doubt, this condition is applicable to the management of construction noise and vibration on all receivers, including sensitive and notable receivers. 36.1
A Construction Noise and Vibration DWP shall be prepared and implemented. The objective of the Construction Noise and Vibration DWP is to provide for the development and implementation of identified best practicable option to avoid, remedy or mitigate the adverse effects on receivers of noise and vibration resulting from construction.
1.1
The Construction Noise and Vibration DWP shall: 36.2
(a) Adopt the noise and vibration standards for construction set out in Conditions 31, 32, 33 and 34 of these designations;
4
(b) Be generally consistent with the draft Construction Noise and Vibration management plan submitted as part of the Notice of Requirement documentation (dated 23 August 2013); and
1.1
Page 10
Connectus Project #: 2665 Client: Auckland Transport
Condition Number
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Relevant Section
Condition (c) Identify methods to achieve best practicable option for mitigating adverse effects.
7
To achieve this objective, the Construction Noise and Vibration DWP shall include:
36.3
(a) The roles and responsibilities of the noise and vibration personnel in the contractor team with regard to managing and monitoring adverse noise and vibration effects;
3
(b) That piling and road cutting will be restricted to between the hours of 7am to 7pm, Monday to Saturday;
2.2
(c) Construction machinery and equipment to be used and their operating noise and vibration levels;
5
(d) Identification of construction activities that are likely to create adverse noise and vibration effects, the location of these in the construction site areas, and the distance to comply with the Project Criteria in Conditions 31, 32, 33 and 34;
5& Appendix C
(e) The timing of construction activities that are likely to create an adverse noise and vibration effect;
Appendix C
(f) The location of sensitive noise and vibration receivers;
6
(g) A record of communication and consultation with sensitive noise and vibration receivers. The record must include a clear explanation of where any comments from sensitive receivers have not been incorporated in the Construction Noise and Vibration DWP, and the reasons why not. This information must be included in the Construction Noise and Vibration DWP provided to both the Independent Peer Review Panel and Auckland Council as part of the Outline Plan process specified in Condition 11;
Appendix D
(h) Specific measures to address the concerns raised by those sensitive receivers;
Appendix D
(i) Specific training procedures for construction personnel including:
7.2
(i) The project noise and vibration performance standards for construction (conditions 31, 32, 33 and 34);
7.2
(ii) Information about noise and vibration sources within the construction area and the locations of sensitive noise and vibration receivers; and
7.2
(iii) Construction machinery operation instructions relating to mitigating noise and vibration;
7.2
(j) Methods and measures to mitigate adverse noise and vibration effects including, but not limited to, structural mitigation such as barriers and enclosures, the scheduling of high noise and vibration construction, use of low noise and vibration machinery, temporary relocation of affected receivers or any other measures or offer agreed to by the Requiring Authority and the affected receiver;
7
(k) The proposed methods for monitoring construction noise and vibration to be undertaken by a suitably qualified person for the duration of construction works including:
10
(i) Updating the predicted noise and vibration contours based on the final design and construction activities;
10
Page 11
Connectus Project #: 2665 Client: Auckland Transport
Condition Number
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Relevant Section
Condition (ii) Confirm which buildings are to be subject to a pre and post building condition survey in accordance with Condition 46. This includes consideration of those buildings in Appendix One and Two to these conditions;
10.4
(iii) The timing and location for monitoring of buildings during construction is required (Note that the flow charts contained in Appendices B and C of Appendix J of the technical noise and vibration report provided as part of the Notice of Requirement should be used as a guide);
10
(iv) Identifying appropriate monitoring locations for receivers of construction noise and vibration;
10
(v) Procedures for working with the Communication and Consultation Manager to respond to complaints received on construction noise and vibration, including methods to monitor and identify noise and vibration sources;
9.2
(vi) Procedures for monitoring construction noise and vibration and reporting to the Auckland Council Consent Monitoring officer; and
10
(vii) Procedures for how works will be undertaken should they be required as a result of the building condition surveys;
10.4
(l) Cross references to the specific sections in the Communication and Consultation Plan which detail how landowners and occupiers are to be communicated with around noise and vibration effects.
9.1
Site Specific Construction Noise Management Plan (SSCNMP) 37.1
37.2
The objective of a SSCNMP is to detail the best practicable option to avoid, remedy or mitigate adverse effects on a receiver resulting from construction noise that does not comply with the Project Noise Standards.
8.1
Further to the Construction Noise and Vibration DWP in Condition 36, a SSCNMP shall be prepared for any receiver or activity for which air overpressure is either predicted or measured to exceed the limits in Condition 32, or where construction noise is either predicted or measured to exceed the Project Noise Standards in Condition 31, except where the exceedance of the standards in Condition 31 is less than 5 decibels and does not exceed : (a) 0700-2200: 1 period of up to 2 consecutive weeks in any 2 months
8.1
(b) 2200-0700: 1 period of up to 2 consecutive nights in any 10 days
8.1
37.3
For predicted exceedances of less than 5 decibels (refer 37.2) monitoring shall be undertaken to confirm the actual noise levels. If exceedance is shown to be more than 5 decibels, or the period exceeds those detailed, then a SSCNMP will be prepared.
8.1
37.4
In addition to the SSCNMPs prepared in accordance with Condition 37.2, and notwithstanding Condition 37.1, the Requiring Authority shall prepare SSCNMPs specifying the best practicable option for management, methods and measures to mitigate all noise effects for the properties located at: (a) 1 Queen Street (Lot 1 DP 165403);
8.1
Page 12
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Condition Number
Relevant Section
Condition (b) (c) (d) (e)
21 Queen Street (Lot 1 DP 67723); 29 Customs Street West (Lot 7 DP 77037) 188 Quay Street (Lot 5 DP 63972 and Lot 1 DP 78340); and 23-29 Albert Street (Lot 1 DP 116724).
SSCNMPs will identify:
37.5
37.6
(a) The extent to which noise may exceed the Project Noise Standards in Condition 31 or the overpressure limits in Condition 32;
8.1
(b) The timing and duration of any exceedance;
8.1
(c) Details of the type of activity causing any exceedance;
8.1
(d) The summary of the communication and consultation undertaken with the receiver. The summary must include a clear explanation of where any comments have not been incorporated, and the reasons why not. This information must be included in the SSCNMP provided to both the Independent Peer Review Panel and Auckland Council as part of the Outline Plan process specified in Condition 11;
8.1
(e) The methods and measures to mitigate noise effects, including but not limited to, potential to offer temporary relocation of affected receivers, alternative ventilation, faรงade sound insulation improvements, building condition surveys in the case of overpressure generated by blast events, or other offers made by the Requiring Authority and whether these have been agreed to by the affected receiver;
8.1
(f) The reasons why the management and mitigation measures and methods reflect best practicable option.
8.1
The SSCNMP shall be submitted for the review of Auckland Council as part of the Outline Plan. The works shall then be undertaken in accordance with the SSCNMP confirmed by the Requiring Authority as part of the Outline Plan.
8.1
Site Specific Construction Vibration Management Plan (SSCVMP) 38.1
The objective of a SSCVMP is to detail the best practicable option to avoid, remedy or mitigate adverse effects on a receiver resulting from vibration that does not comply with the Project Vibration Standards.
8.2
38.2
Further to the Construction Noise and Vibration DWP in Condition 36, a SSCVMP shall be prepared: (a) For any unoccupied building, structure or infrastructure for which construction vibration is either predicted or measured to exceed the Project Vibration Standards in Condition 33; (b) Where a complaint or concern is raised and the vibration level exceeds the amenity levels of Condition 34.2(a) and 34.2(b); (c) In response to other concerns or complaints where required (refer Condition 17). (d) For the properties listed in Condition 37.4.
8.2
Page 13
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Condition Number
Relevant Section
Condition Where the amenity limits in Conditions 34.2(a) and 34.2(b) are exceeded:
38.3
38.4
(a) Best practicable management of vibration must be applied; and
8.2
(b) The vibration activity shall be scheduled to avoid disturbance. If this is not practicable then reasonable respite periods shall be provided to reduce vibration exposure.
8.2
The limits in condition 33 may be relaxed by a SSCVMP but only for a building, structure or infrastructure that has been assessed by a suitably qualified and experienced structural engineer and where it has been deemed to be capable of withstanding higher vibration levels without sustaining building or structural damage, and where appropriate vibration and building condition monitoring regimes are in place.
8.2
SSCVMPs will identify:
38.5
(a) The timing and duration of any exceedance;
8.2
(b) Details of the type of activity giving rise to any exceedance;
8.2
(c) Site Specific vibration criteria that addresses the issue(s) of concern (i.e. building damage, amenity and sensitive equipment). Site Specific criteria shall be determined by a suitably qualified independent vibration expert;
8.2
(d) The summary of the communication and consultation undertaken with the receiver. The summary must include a clear explanation of where any comments have not been incorporated, and the reasons why not. This information must be included in the SSCVMP provided to both the Independent Peer Review Panel and Auckland Council as part of the Outline Plan process specified in Condition 11;
8.2
(e) The methods and measures to mitigate vibration effects, including but not limited to, investigating alternative low-vibration construction methods, undertaking high-vibration works outside sensitive times, vibration barriers, building condition surveys, potential to offer temporary relocation of affected receivers, or other offers made by the Requiring Authority and agreed to by the affected receiver.
8.2
(f) The reasons why the management and mitigation measures and methods reflect best practicable option. 38.6
The SSCVMP shall be submitted for the review of Auckland Council. The works shall then be undertaken in accordance with the SSCVMP confirmed by the Requiring Authority as part of the Outline Plan.
8.2
Notable Noise and Vibration Receivers 39.1
Further to Condition 36, the Requiring Authority and its contractor, in conjunction with a suitably qualified expert, shall work collaboratively with each notable receiver during the preparation of a SSCNVMP to confirm the extent and management of adverse effects on each Notable Receiver.
Page 14
8.1, 8.2
Connectus Project #: 2665 Client: Auckland Transport
Condition Number 39.2
39.3
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Relevant Section
Condition In addition to the Construction Noise and Vibration DWP, a SSCNVMP shall be prepared for each identified Notable Receiver. The objective of the SSCNVMP is to detail the best practicable option to avoid, remedy or mitigate adverse noise and vibration effects on each Notable Receiver.
8.1, 8.2
The Requiring Authority shall consult with the notable receiver throughout the duration of construction and update the SSCNVMP as required to achieve the objective in 39.2.
8.1, 8.2
The SSCNVMP shall include:
8.1, 8.2
(a) The level at which noise and vibration effects on the notable receiver will unreasonably interfere with its operation. This will enable development of the site specific criteria. (b) Construction activities and equipment which are likely to create adverse noise and vibration effects and the location and timing of these in relation to the notable receiver; (c) The methods and measures associated with the worksite including, but not limited to, structural mitigation such as barriers and enclosures, use of low noise and vibration machinery and the scheduling of high noise and vibration construction; 39.4
(d) The methods and measures associated with the notable receiver building or operation including, but not limited to, potential for isolation of sensitive areas and equipment, dampening of reradiating surfaces and temporary relocation of affected receivers that are proposed to minimise adverse noise and vibration effects on the notable receiver; (e) Details about the methods to be adopted by the Requiring Authority to minimise construction noise and vibration effects on the notable receiver and the anticipated effectiveness of those methods; (f) A summary of the communication and consultation undertaken with the notable receiver. The summary must include a clear explanation of where any comments have not been incorporated and the reasons why not. (g) Offers made by the Requiring Authority to the notable receiver to mitigate effects and the response by the operators, such as relocation, and whether those offers were accepted or not by the notable receiver; If the parties cannot agree on any of the matters above they shall each appoint a suitably qualified and independent expert, who shall jointly appoint an independent and suitably qualified third expert who shall certify the following matters to be included in the SSCNVMP:
39.5
(a) The level at which noise and vibration effects on the notable receiver unreasonably interfere with its operation (the certified noise and vibration limit); (b) The mitigation methods and measures within the worksite (at source) including, but not limited to, structural mitigation such as barriers and enclosures, use of low noise and vibration machinery and the scheduling of high noise and vibration construction; (c) The mitigation methods and measures at the notable receiver including but not limited to: isolation of sensitive areas and
Page 15
8.1, 8.2
Connectus Project #: 2665 Client: Auckland Transport
Condition Number
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Condition equipment; dampening of reradiating surfaces; any response to such offers; and temporary relocation of affected receivers;
Relevant Section
(d) Whether or not the mitigation methods and measures reflect best practicable management; and (e) Whether or not the residual effects are likely to cause significant disruption to the activities of the notable receiver.
39.6
Following the above process the SSCNVMP shall be submitted for the review of Auckland Council as part of the Outline Plan. For the avoidance of doubt, the Requiring Authority shall not be entitled to make any changes to the SSCNVMP through the Outline Plan process following any agreement reached with the notable receiver and/or through the above certification process without the consent of the notable receiver. The works shall then be undertaken in accordance with the SSCNVMP confirmed by the Requiring Authority as part of the Outline Plan process.
Page 16
8.1, 8.2
Connectus Project #: 2665 Client: Auckland Transport
1.2.1
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Sustainability
AT is seeking an Infrastructure Sustainability Council of Australia (ISCA) Infrastructure Sustainability (IS) rating for the CRL enabling works. Full details are included in the Project’s Sustainability Management Plan. Project sustainability requirements that relate directly to the CNV DWP are included in Appendix A.
Page 17
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
2 PROJECT DESCRIPTION This section presents a summary of the Project in relation to the matters required to be addressed by the CNV DWP. A detailed description of the construction works is provided in the CEMP.
2.1
SUMMARY OF METHODOLOGY
Connectus will use a cut and cover method to construct two parallel rail tunnels within the Albert Street road corridor between Customs Street and Wyndham Street. The total length of the tunnel for the Project will be 340m. A number of utilities are required to be removed, relocated, or supported during construction. Generally, the Project works will consist of: 1.
Utilities relocation and exposure
2.
Piling and capping beam construction within Albert Street (including relocating of any relevant services)
3.
Piling and road deck construction within the Customs Street Intersection
4.
Trench Excavation, including using shotcrete and Rock Dowelling
5.
Construction and waterproofing of the rail tunnels
6.
Backfilling of the trench, including construction of the new road pavement.
2.1.1
Utilities relocation and exposure
The location of utility service cables/pipes/ducts (gas, electricity, phone, wastewater, stormwater) (herein collectively referred to as utilities) within the Project footprint have been identified through site inspections and liaison with Network Utility Operators, including Vector Electricity, Vector Gas, Vector Communications, Chorus, Auckland Council and Vodafone. It is not feasible to completely avoid all utilities, although wherever possible piling locations and other construction activities have been selected to avoid conflict with services. This CNV DWP covers only those utility works within the designation footprint and separate provision has been made for utility works required outside of the designation footprint. Utility relocation works required for Project construction includes works both inside and outside of the trench alignment. All works outside of the trench will be completed prior to excavation works, while the works within the trench will be completed during trench excavation or as the trench is being backfilled on completion of tunnel construction. Further detail on utilities relocation can be found in the CRL Contract 2 CEMP. 2.1.2
Piling and capping beam construction within Albert Street
Piling is required as the initial stage of construction for the Project. It includes the installation of cased continuous flight auger (CFA) piles and the construction of the pilecap on the western side of Albert Street. Figure 2 shows the location and staging of the piling (the sequence will be confirmed closer to construction). The asphalt surface of the road reserve will be removed and the utilities relocated. Piling will then occur, and a Pile-Cap constructed to connect the piles along the western side of Albert Street. Reinforcing will be installed and concrete placed.
Page 18
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Figure 2 Piling Stages (shown in different colours – the sequence will be confirmed closer to construction)
2.1.2.1
Continuous Traffic Deck
Continuous steel traffic decks will be installed along each side of the main trench along Albert Street during the piling and capping stage of construction. The traffic deck along the western side of the trench will extend between Swanson Street and Customs Street, and will be used by general traffic along Albert Street. The traffic deck along the eastern side of the trench will extend between Wyndham Street and Customs Street and will be limited to use by construction traffic only. The eastern deck (construction traffic deck) will provide continuous access into the excavation along the length of the trench and additional construction site set down and plant space to supplement the southern and northern compounds. In addition to the continuous traffic decks, two pedestrian bridges will span the trench, located on the north side of the Wyndham Street and Swanson Street intersections. 2.1.3
Customs Street intersection piling and road deck construction
Piling and construction of a temporary deck structure at the Customs Street/Albert Street intersection will permit traffic to cross over, while tunnel construction occurs underneath. The deck will be constructed in four stages as shown in Figure 3. This will enable traffic to utilise the intersection during construction and avoids closing the intersection completely. Each stage requires pile installation and jet-grouting followed by excavation to approximately 2m depth to allow the construction of the concrete deck. Once all four piling and deck sections are complete, excavation and tunnel construction can commence beneath the live intersection. In addition to supporting the traffic deck, the piles and jet-grout columns hold back the soil during excavation beneath the deck and stop water from entering the excavation site. After tunnel construction the area under the deck will be backfilled, and the deck structure ‘buried’ (i.e. the deck will no longer be a separate deck structure and will be incorporated in the area immediately below the intersection pavement).
Page 19
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Figure 3 Staged construction of road deck – sections of the deck will be constructed in 4 stages (sequentially)
Page 20
Connectus Project #: 2665 Client: Auckland Transport
2.1.4
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Trench Excavation and spoil handling
Trench excavation will be carried out in layers (starting at the southern end) as shown in Figure 4 with installation of temporary struts and ground anchors as the depth increases. As excavation progresses, steel waler beams and struts will be installed in combination with ground anchors to support the piled trench walls. In addition, shotcrete and/or rockfall mesh with pins will be applied to the sides of the trench to stabilise the excavation face. Shotcrete will be spray applied, rockfall mesh is installed by driving short pins into the soil and attaching the mesh to the pins. As the trench becomes deeper, excavators and loaders will be located inside the trench to break material from the natural face of the trench and transport material to stockpiles. On the construction deck above, cranes and excavators will reach down to remove material from the trench to load onto trucks for offsite disposal.
Figure 4 Excavation – layers
Page 21
Connectus Project #: 2665 Client: Auckland Transport
2.1.5
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Waterproofing and tunnel construction
The construction of the rail tunnels will be a rolling process with multiple work faces progressing simultaneously. The tunnel works will start at the southern end of Albert Street when the excavation plant is clear of the base of the tunnel. Tunnel construction will be broken into 12m lengths, and comprises the following tasks: -
Base drainage and blinding Waterproofing Base foundation and construction Wall construction Roof construction Roof waterproofing.
Figure 5 shows a typical cross section for the cut and cover tunnels. Concrete will be pumped to the works by pump machinery that is initially located at the compound on the southern side of Albert Street. The pump machinery is moved onto the construction deck as the works proceed further north. Figure 5 Typical cross section for the Albert Street Cut and Cover Tunnels
2.1.6
Trench backfilling
As the construction of the tunnels progresses, back filling of the cut and cover excavation in the Custom Street Intersection and Albert Street trench will occur. The trench backfill will be placed on top of the tunnel structure after construction has been completed for a sufficient length (approximately 50m), including the installation of the waterproofing membrane, and will continue to follow the tunnel Page 22
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
construction as it progresses. A layer of concrete blinding (or similar) will be placed over the roof membrane for protection from the trench backfill works. Material will be delivered to site by trucks on the construction deck. Trucks will deposit the fill material onto the floor of the deck structure and it will be collected and tipped into the trench by a loader. Works to complete new utility routes or reinstate existing utilities will be co-ordinated with the filling operation as it reaches the upper layers. Finally, the construction of the new permanent road pavement will occur in stages after the trench backfill has been completed. 2.1.7
Temporary Pavement
Where required in order to maintain traffic movements, it will be necessary to put down a temporary pavement. Temporary pavements will consist of unbound granular material with a bituminous seal, concrete panels or steel plates on the surface.
2.2
HOURS OF OPERATION
Works will generally be undertaken between 7am and 7pm Monday to Saturday. Designation Condition 36.3(b) requires that piling and road cutting will be restricted to between the hours of 7am to 7pm, Monday to Saturday. Night time works are proposed for installation of the permanent wearing course at the Customs Street intersection (2 nights total).
Page 23
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
3 ROLES AND RESPONSIBILITIES The key personnel responsible for this CNV DWP are identified Table 2. However, all site personnel are responsible for following the requirements of the CNV DWP. Table 2 Key Personnel Role
Person Responsible for CNV DWP Project Director Communication and Consultation Manager Acoustics Specialist Noise and Vibration Monitoring Noise Monitoring Trained Site Personnel Auckland Council – Team Leader Central Monitoring Public complaint contact number Senior Monitoring Inspector
Name
Organisation
Phone
Alasdair Mawdsley
Connectus
021 2404153
Alasdair.mawdsley@mcdgroup. com
Chris Powell
Connectus
021 596 036
Chris.Powell@mcdgroup.com
Allan HowardSmith
Connectus
021 361158
alan.howardsmith@hawkins.co.nz
Claire Drewery
AECOM
021 821 025
Claire.drewery@aecom.com
Nick Henrys
AECOM
021 993 730
Nick.Henrys@aecom.com
Alasdair Mawdsley
Connectus
021 240 4153
Alasdair.Mawdsley@mcdgroup. com
Adam Duncan
Auckland Council
09 353 9041
adam.duncan@aucklandcouncil .govt.nz
-
Auckland Transport
09 447 4343
CRLProject@aucklandtransport .govt.nz
Fiona Harte
Auckland Council
021828369
Fiona.Harte@aucklandcouncil.g ovt.nz
All personnel working on the Project, including contractor employees and subcontractors, are responsible for following the requirements of this CNV DWP. They must be briefed on this CNV DWP and sign an induction form such as the one provided in Appendix F, and any noise and vibration schedules that relate to the work they will be carrying out.
3.1
CNV DWP AUTHOR
This CNV DWP has been prepared by Claire Drewery, Principal Acoustic Consultant at AECOM and the nominated Acoustics Specialist for the Project. Claire has 14 years’ professional experience as an acoustic consultant and she holds a Diploma in Acoustics and Noise Control. Claire is a Member of the Institute of Acoustics.
Page 24
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
4 NOISE AND VIBRATION CRITERIA 4.1
NOISE CRITERIA
Construction noise will be measured and assessed in accordance with New Zealand Standard NZS6803:1999 “Acoustics – Construction Noise”. Construction noise will be managed to comply with the Project Standards (unless otherwise provided for in an approved SSCNMP). The Project Standards for construction noise are detailed in Table 3 and are applicable 1m from any building façade. Section 5.1 of the CNV DWP details equipment and associated noise levels for construction activities. Section 10 of the CNV DWP details how construction activities will be measured/ assessed against the noise criteria. If any construction activity cannot practicably comply with these limits, a SSCNMP will be produced in accordance with Section 8.1 of this CNV DWP. Table 3 Construction Noise Limits Monday to Saturday 0700 – 2200
Sundays and Public Holidays 0700 – 2200
All other times 2200 – 0700
Occupied commercial and industrial buildings (including offices)
75 dB LAeq
75 dB LAeq
75 dB LAeq
Sensitive Noise and Vibration Receivers (excluding offices)
75 dB LAeq
65 dB LAeq
60 dB LAeq
90 dB LAFmax
80 dB LAFmax
75 dB LAFmax
Receiver type
Early Childhood Education Centres (whilst occupied 35 dB LAeq in sleeping areas during normal opening hours) Note: Sensitive receivers (usually building occupants) whose amenity needs to be considered with regards to noise and/or vibration effects; includes but is not limited to dwellings, hotels, educational facilities (including day care facilities), hospitals, places of worship, laboratories, studios, theatres and auditoria.
4.2
VIBRATION CRITERIA – BUILDING DAMAGE
Construction vibration will be measured and assessed in accordance with German Standards DIN 4150-3:1999 “Structural Vibration – Part 3 Effects of Vibration on Structures”. Construction vibration will be managed to comply with the Project Standards for building damage (unless otherwise provided for in an approved SSCVMP). The limits for construction vibration are detailed in Table 4. Section 5.2 of the CNV DWP details equipment and vibration regression curves for construction activities. Section 10 of the CNV DWP details how construction activities will be measured/ assessed against the vibration criteria. If any construction activity cannot practicably comply with these limits, a SSCVMP will be produced in accordance with Section 8.2 of this CNV DWP.
Page 25
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Table 4 Construction Vibration Limits – Building Damage Long-term (continuous) vibration
Short-term (transient) vibration*
1 – 10 Hz (mm/s)
10 – 50 Hz (mm/s)
50 – 100 Hz (mm/s)
PPV at horizontal plane of highest floor (mm/s)
Commercial / Industrial
20
20-40
40-50
40
10
Residential / School
5
5 – 15
15 – 20
15
5
Type of structure
PPV at the foundation at a frequency of:
PPV at horizontal plane of the highest floor (mm/s)
Historic or sensitive 3 3–8 8 – 10 8 2.5 structures * DIN 4150-3:1999 defines short-term (transient) vibration as “vibration which does not occur enough to cause structural fatigue and which does not produce resonance in the structure being evaluated” Long-term (continuous) vibration is defined as all other vibration types not covered by the short-term vibration definition.
4.3
VIBRATION CRITERIA – AMENITY
4.3.1
Night time criteria
Between the hours of 10pm and 7am vibration generated by construction activities (excluding blasting) shall not exceed: a) a Peak Particle Velocity (PPV) of 0.3mm/s when measured at any part of the floor of any bedroom; b) a noise level of 35 dB LAeq(15min) when measured in any bedroom. 4.3.2
Day time criteria
Between the hours of 7am and 10pm vibration generated by construction activities (excluding blasting) shall not exceed: a) A Peak Particle Velocity (PPV) of 1mm/s as measured on the floor of the receiving room for residentially occupied habitable rooms, bedrooms in temporary accommodation and medical facilities; and b) A Peak Particle Velocity (PPV) of 2mm/s as measured on the floor of the receiving room for retail and office spaces (including work areas and meeting rooms); Designation Condition 34.3 states that the limits identified in Sections 4.3.1 and 4.3.2 of this CNV DWP need only be investigated and applied upon the receipt of a complaint from any building occupant. They shall not be applied where there is no concern from the occupant of the building. When a complaint occurs, and the limits are found (through measurement) to be exceeded then a SSCVMP shall be prepared for that receiver.
Page 26
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
5 EQUIPMENT AND NOISE AND VIBRATION SOURCE DATA 5.1
NOISE SOURCES
Various construction processes and pieces of equipment will act as noise sources on site. Table 5 details predicted noise levels from proposed significant noise sources at various receiver setback distances. The noise data has been taken from British Standard 5228-1:2009 “Code of practice for noise and vibration control on construction and open sites�, manufacturers data or the AECOM database of noise measurements. The noise levels do not account for mitigation. The noise levels detailed in Table 5 are placeholders. All equipment will be measured operating independently and then actual equipment noise levels and model numbers will be recorded and updated within the table. These updates to the information that is detailed in Table 5 will be provided in Appendix C as schedules to the CNV DWP. Providing that the noise effects at the affected properties are either reduced or maintained at the same level with the mitigation measures identified in this CNV DWP implemented, it is not intended to re-submit the CNV DWP for review/approval. This information allows identification of the need for mitigation or management to achieve compliance with the Project noise criteria. Section 7 of this CNV DWP provides details of management procedures and mitigation measures. The work activities described in "work phase" CEP 308-001 Customs Street Intersection Piling and Road Deck Construction are specific to that construction area. The work activities described in the other "work phases" will occur throughout the Albert St and Custom St construction areas.. Table 5 Equipment noise levels
Works Phase
CEP 308-001 Customs Street Intersection Piling and Road Deck Construction
Equipment
Type of works
Sound pressure level dB LAeq 5m
10m
20m
50m
Concrete core drill (type TBC)
Surface removal and service clearing
91
85
79
71
Vacuum Excavation
Surface removal and service clearing
84
78
72
64
Soilmec Hydraulic Rotary Rig (est SR80)
Auger drilling and pile casing installation
88
82
76
68
Concrete Truck
Concrete delivery
83
77
71
63
Crane
Service crane and pile reinforcement install
82
76
70
62
Mecbo tracked Concrete Pump
Concrete placement
84
78
72
64
Excavator (est 15t)
Excavation post piling
79
73
67
59
SM-20 Hydraulic Micro drilling Rig
Jet Grouting
82
76
70
62
Hydro-demolition high pressure pump
Removal of concrete encasement on SW main
87
81
75
67
Page 27
Connectus Project #: 2665 Client: Auckland Transport
Works Phase
CEP 309-001 Albert Street Piling and Capping Beam
CEP 311-001 Excavation and Spoil Handling
CEP 316-001 Trench Backfilling
Equipment
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Type of works
Sound pressure level dB LAeq 5m
10m
20m
50m
Bob cat loader
Handling materials
82
76
70
62
Crane (est. 40t)
Unloading and placing service supports, steel reinforcement and formwork
82
76
70
62
Concrete saw
Demolition of storm water chamber roof
93
87
81
73
Angle grinder
Pile breaking
86
80
74
66
Excavator mounted concrete breaker
Break back over pour on the piles
90
84
78
70
Concrete vibrators
Concrete placement
75
69
63
55
Roller compactor
Installation of permanent wearing course
85
79
73
65
Concrete boom pump
Placement of concrete in deck slab
86
80
74
66
Concrete core drill (type TBC)
Surface removal and service clearing
91
85
79
71
Vacuum Excavation (Type TBC)
Surface removal and service clearing
95
89
83
75
Soilmec Hydraulic Rotary Rig (est SR80)
Auger drilling and pile casing installation
88
82
76
68
Crane est 40t
Service crane and pile reinforcement install
82
76
70
62
Mecbo tracked Concrete Pump
Concrete placement
84
78
72
64
Concrete truck
Concrete delivery
83
77
71
63
Concrete breaker
Installation of pile cap
90
84
78
70
Excavator (est 15t)
Excavation post piling
79
73
67
59
Crawler crane with clamshell bucket 80t
General works, installing temp works, excavation
81
75
69
61
Road planer / milling machine
Removing the road surface
88
82
76
68
Excavators 12-20t
Excavation, installing temp works
7684
7078
6472
5664
Front end wheel loader
Spoil handling
86
80
74
66
6-wheel tipper trucks
Spoil handling, spoil cartage
85
79
73
65
Long reach excavator
Excavation
81
75
69
61
Excavators 5-15t
Spreading fill material, removing temp works
7179
6573
5967
5159
Front end wheel
Fill handling
86
80
74
66 Page 28
Connectus Project #: 2665 Client: Auckland Transport
Works Phase
Equipment
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Type of works
Sound pressure level dB LAeq 5m
10m
20m
50m
loader
CEP 320-001 Waterproofing and Tunnel Construction
CEP 321-001 Shotcrete Installation and Strip Drain Installation
CEP 321-002 Rock Dowel Installation
Bobcat loader
Fill handling
82
76
70
62
6-wheel tipper trucks
Fill delivery
85
79
73
65
roller compactors
Compacting fill
85
79
73
65
plate compactors
Compacting fill in low clearance areas
86
80
74
66
Concrete pump
Pumping flowable fill to site
84
78
72
64
Telehandlers
Moving materials
85
79
73
65
Telescopic Crawler Crane
Moving and placement of materials
77
71
65
57
Crawler crane (surface) est 50t
Material lowering from delivery bay to workface
81
75
69
61
Mobile concrete pump
Concrete placement
86
80
74
66
Static pump and boom
Concrete placement
86
80
74
66
Rough terrain scissor lift
Working platforms for wall works
84
78
72
64
Telehandlers
Moving materials
85
79
73
65
Excavator
Moving materials
79
73
67
59
Crawler crane (surface) est 50t
Material lowering from delivery bay to workface
81
75
69
61
Static concrete pump
Concrete feed from truck to workface
86
80
74
66
Diesel compressor
Shotcrete production
79
73
67
59
Diesel generator
Power to shotcrete plant
71
65
59
51
Excavator mounted drill rig
Drilling holes for rockfall pins
92
86
80
72
Rough terrain knuckle booms
Working platforms for shotcrete install
73
67
61
53
Telehandlers
Moving materials
85
79
73
65
Excavator
Moving materials
79
73
67
59
Angle grinder
Pile breaking
86
80
74
66
Excavator mounted rock breaker
Pile breaking
90
84
78
70
Concrete core drill
Drill through pile
91
85
79
71
Excavator mounted drill rig
Drill rock dowel hole
92
86
80
72
Crawler crane est. 50t
Material lowering from delivery bay to workface
81
75
69
61
Water bowser
Drilling and cleaning of drill holes
87
81
75
67 Page 29
Connectus Project #: 2665 Client: Auckland Transport
Works Phase
CEP 306-001 Ground and Stormwater Management
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Equipment
Type of works
Sound pressure level dB LAeq 5m
10m
20m
50m
Diesel compressor
Drilling and cleaning of drill holes
79
73
67
59
petrol/diesel generator
power to plant
71
65
59
51
Grout pump
Grouting rock dowel
86
80
74
66
Crane
Unloading WTP / establishment works
81
75
69
61
Forklift
Transporting chemical containers
82
76
70
62
80 KVA Generator
Power supply
71
65
59
51
Primary pump
Dewaters trench to WTP at low flow
75
69
63
55
Secondary pump
Dewater trench to WTP at max treatment flow
75
69
63
55
High flow pump
Dewater trench direct to SW in an emergency
75
69
63
55
Water supply pump
Treated water distribution
75
69
63
55
It should be noted that although mains power will be utilised where practicable, backup generators will be on site for safety reasons and to ensure completion of critical activities in a timely fashion in case of a loss of mains power. Noise from generators has therefore been considered in this CNV DWP. 5.1.1
Cumulative noise sources
During the construction works it is likely that several items of equipment will be operating simultaneously in the same area. Table 6 below gives indicative cumulative noise levels from equipment items that may be operating at the same time, based on the worst-case assumption that all equipment items are located at the same point. Table 7 details distances from the construction activities where the noise limits are predicted to be achieved with no mitigation. Table 6 Indicative cumulative equipment noise levels
Works Phase CEP 308-001 Customs Street Intersection
Construction Activity
Equipment
Service Location and exposure
Concrete saw Vacuum Excavation
Cumulative Sound pressure level, dB LAeq 5m
10m
20m
50m
94
88
82
74
Page 30
Connectus Project #: 2665 Client: Auckland Transport
Works Phase Piling and Road Deck Construction
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Construction Activity Installation of CFA piles
Jet Grouting
Excavation and support of exposed services Binding and fixing of reinforcement
CEP 309-001 Albert Street Piling and Capping Beam
Placement of concrete Installation of permanent wearing course (night) Stormwater pumping station demolition Stormwater line demolition Service location and exposure Installation of CFA piles
Installation of pile cap CEP 311-001 Excavation and Spoil Handling
Removal of existing road surface st
Excavation 1 layer Excavation 2nd Layer to Bottom
Equipment Soilmec Hydraulic Rotary Rig (est SR80) Excavator (est 15t) Concrete truck Mecbo tracked Concrete Pump Crane (40t) SM-20 Hydraulic Micro drilling Rig Vacuum Excavation Excavator (est 15t) Bob cat Grinder Mecbo tracked Concrete Pump Excavator mounted concrete breaker Crane (40t) Concrete boom pump Concrete vibrators Roller compactor
Concrete core drill (type TBC) Concrete saw Crane (40t) Hydro-demolition high pressure pump Concrete saw Vacuum Excavation Soilmec Hydraulic Rotary Rig (est SR80) Excavator (est 15t) Concrete truck Mecbo tracked Concrete Pump Crane (40t) Excavator (est 15t) Concrete breaker Crane (40t) Road planer / milling machine Excavator 20t 6-wheel tipper trucks (10t) Excavator 20t Small excavator (5t – 14t) 6-wheel tipper trucks (10t) Excavator 14t Front end wheel loader Crawler crane with clamshell bucket (80t) or long reach excavator 6-wheel tipper trucks (10t)
Cumulative Sound pressure level, dB LAeq 5m
10m
20m
50m
91
85
79
71
86
80
74
66
84
78
72
64
93
87
81
73
86
80
74
66
85
79
73
65
89
83
77
69
87
81
75
67
94
88
82
74
91
85
79
71
91
85
79
71
90
84
78
70
85
79
73
65
88
82
76
68
Page 31
Connectus Project #: 2665 Client: Auckland Transport
Works Phase CEP 316-001 Trench Backfilling
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Construction Activity Trench backfilling
CEP 320-001 Waterproofing and Tunnel Construction
Waterproofing and tunnel construction (day)
CEP 321-001 Shotcrete and Strip Drain Installation
Rock fall protection netting
CEP 321-002 Rock Dowel Installation
Shotcrete placement
Pre-drilling
Drilling and rock dowel installation
CEP 306-001 Ground and Stormwater Management
Ground and stormwater management
Equipment Excavators 5-15t Front end wheel loader Bobcat loader 6-wheel tipper trucks roller compactors plate compactors Concrete pump Telehandlers Telescopic Crawler Crane Rough terrain scissor lift Mobile concrete pump or Static pump and boom Crane Delivery trucks Excavator mounted drill rig Crane Delivery trucks Diesel compressor Diesel generator Rough terrain knuckle booms or Robotic nozzle manipulator Concrete trucks Static concrete pump Angle grinder Excavator-mounted rock breaker Concrete core drill Telehandlers Excavator-mounted drill rig Water bowser Diesel compressor Petrol/diesel generator Crawler crane est 50t Delivery trucks Crane Forklift 80KVA Generator Primary pump Secondary pump High flow pump WTP Water supply pump
Cumulative Sound pressure level, dB LAeq 5m
10m
20m
50m
93
87
81
73
91
85
79
71
92
86
80
72
89
83
76
69
94
88
82
74
95
89
83
75
86
80
74
66
Page 32
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Table 7 Distance from activity where noise limits are predicted to be achieved with no mitigation
Works Phase
CEP 308-001 Customs Street Intersection Piling and Road Deck Construction
Construction Activity
Service Location and exposure Installation of CFA piles Jet Grouting Excavation and support of exposed services Binding and fixing of reinforcement
Installation of permanent wearing course (night) Stormwater pumping station demolition Stormwater line demolition
CEP 311-001 Excavation and Spoil Handling
Service location and exposure Installation of CFA piles Installation of pile cap Removal of existing road surface
CEP 320-001 Waterproofing and Tunnel Construction CEP 321-001 Shotcrete and Strip Drain Installation CEP 321-002 Rock Dowel Installation CEP 306-001 Ground and Stormwater Management
32
15 40 20 90* 25 20 55 32 32 25
st
Excavation 1 layer Excavation 2nd Layer to Bottom
CEP 316-001 Trench Backfilling
55
50
Placement of concrete
CEP 309-001 Albert Street Piling and Capping Beam
Distance from activity where noise limits will be achieved (m)
20 25
Trench backfilling 40 Waterproofing and tunnel construction 32 Rock fall protection netting 40 Shotcrete placement 25 Pre-drilling Drilling and rock dowel installation
45 47
Ground and stormwater management 20
*night time works
Page 33
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
All construction activities detailed in Table 7 are likely to require mitigation to comply with the noise limits.
5.2
VIBRATION SOURCES
Some construction activities are predicted to generate high levels of vibration including piling, excavation, compaction and breaking. Figure 6 shows the regression curves for the most significant vibration generating activities. Table 8 summarises the setback distance from each of these activities inside of which exceedance of the building damage criteria detailed in Section 4.2 of this CNV DWP may occur at the foundation of receiving buildings. The table will be kept up to date and be representative of the actual equipment on-site and include the results of on-site vibration monitoring. The updates to the information that is detailed in Table 8 will be provided in Appendix B as schedules to the CNV DWP.Providing that the vibration effects at the affected properties are either reduced or maintained at the same level with the mitigation measures identified in this CNV DWP implemented, it is not intended to re-submit the CNV DWP for review/approval. The vibration monitoring procedure is detailed in Section 10 of this CNV DWP. Hand held pneumatic breakers are not included in the regression curves but they typically generate vibration levels of 1mm/s at 10 metres. Vibration monitoring will be carried out on site, in accordance with Section 10.2 of this CNV DWP, once vibration generating activities commence.
Figure 6 Regression curves for significant vibration generating activities
Page 34
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Table 8 Vibration emission radii for building damage criteria
Works Phase
Type of Works
Vibration Source
Emission radius (m) Historic/Sensitive
Residential
Commercial
CEP 308-001 Customs Street Intersection Piling and Road Deck Construction
Break back over pour on the piles
Excavatormounted rock breaker (900 kg)
16
10
7
Installation of permanent wearing course
Compaction (17t roller)
15
8
4
CEP 309-001 Albert Street Piling and Capping Beam
Auger drilling and pile casing installation
Piling (Auger)
3
2
1
CEP 316-001 Trench Backfilling
Compacting fill
Compaction (17t roller)
15
8
4
CEP 321-002 Rock Dowel Installation
Pile breaking
Excavatormounted rock breaker (900 kg)
16
10
7
Page 35
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
6 AFFECTED PARTIES 6.1
NOISE
Table 9 identifies buildings where construction activities are predicted to exceed the noise limits before mitigation has been applied. Figure 7 shows the location of these noise affected buildings. Table 9 Buildings predicted to receive noise levels exceeding the Project noise limits before mitigation is applied
Address
Building type/ comments
11-27 Customs Street
Commercial
15 Albert Street
Vacant
13 Albert Street
Vacant
9 Albert Street
Mixed Use
5 Albert Street
Commercial
3 Albert Street
Commercial
17 Albert Street
Commercial
22 Customs Street
Commercial
51 Albert Street
Commercial
41-45 Albert Street
Residential
23-29 Albert Street
Commercial
38 Wyndham Street
Commercial
58 Albert Street
Commercial
63 Albert Street
Commercial
61 Albert Street
Mixed Use
57 Albert Street
Commercial
55 Albert Street
Commercial
37-39 Albert Street
Construction Site
35 Albert Street
Construction Site
52-56 Albert Street
Commercial
8 Albert Street
Mixed Use
70-74 Albert Street
Mixed Use
46-50 Albert Street
Commercial
12-26 Swanson Street
Commercial
22-26 Albert Street
Residential
65-71 Albert Street
District Court
34-36 Wyndham Street
Commercial
29 Customs Street
Commercial
33 Wyndham Street
Commercial
76 Albert Street
Residential
26 Wyndham Street
Commercial
6 Wolfe Street
Vacant
9 Wolfe Street
Commercial Page 36
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Address
Building type/ comments
18 Federal Street
Residential
188 Quay Street
Commercial
48-52 Wyndham Street
Commercial
45-53 Queen Street
Commercial
24 Wyndham Street
Commercial
12-26 Swanson Street
Commercial
14 Federal Street
Commercial
10 Federal Street
Mixed Use
20 Wyndham Street
Residential
1 St Patricks Square
Church
Figure 7 Location of the noise affected parties.
Section 7 of this CNV DWP details general mitigation and management measures that will be implemented in respect of these exceedances. Appendix C contains noise schedules for each construction activity and identifies which of the receivers identified in Table 9 are affected by that activity, the noise level at the receiver due to the activity and specific mitigation/ management measures. A Site Specific Construction Noise Management Plan (SSCNMP) will be prepared in accordance with Section 8.1 of this CNV DWP for receivers where noise is predicted to exceed the noise limits (refer Appendix I of this CNV DWP).
Page 37
Connectus Project #: 2665 Client: Auckland Transport
6.2
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
VIBRATION – BUILDING DAMAGE
Some buildings fall within the predicted building damage emission radii identified in Table 8. These buildings may be at risk of exceeding the building damage vibration limits. Table 10 summarises the buildings that may be at risk. Figure 8 shows the location of these vibration affected buildings. The building classification has been determined from the building condition and structural surveys that have been carried out by AECOM. Table 10: Buildings predicted to receive noise levels exceeding the Project noise limits before mitigation is applied
Address
Building Classification
22 Customs Street
Historic / vibration sensitive
5 Albert Street
Historic / vibration sensitive
9 Albert Street
Historic / vibration sensitive
13 Albert Street
Historic / vibration sensitive
3 Albert Street
Commercial
15 Albert Street
Historic / vibration sensitive
17 Albert Street
Historic / vibration sensitive
11-27 Customs Street
Commercial
35 Albert Street
Construction site
23-29 Albert Street
Commercial
37-39 Albert Street
Construction site
41-45 Albert Street
Historic / vibration sensitive
51 Albert Street
Historic / vibration sensitive
55 Albert Street
Historic / vibration sensitive
61 Albert Street
Historic / vibration sensitive
57 Albert Street
Historic / vibration sensitive
38 Wyndham Street
Commercial
58 Albert Street
Commercial
63 Albert Street
Commercial
52-56 Albert Street
Historic / vibration sensitive
46-50 Albert Street
Historic / vibration sensitive
12-26 Swanson Street
Commercial
8 Albert Street
Residential
70-74 Albert Street
Residential
22-26 Albert Street
Residential
65-71 Albert Street
Historic / vibration sensitive
34-36 Wyndham Street
Historic / vibration sensitive
Bluestone Wall
Historic / vibration sensitive
Section 7 of this CNV DWP details general mitigation and management measures that will be implemented. Appendix B contains vibration schedules for construction activities and identifies which of the receivers identified in Table 10 are affected by that activity, the noise level at the receiver due to the activity and specific mitigation/ management measures.
Page 38
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
A Site Specific Construction Vibration Management Plan (SSCVMP) will be prepared in accordance with Section 8.2 of this CNV DWP for receivers where vibration is predicted to exceed the building damage vibration limits (refer Appendix I of this CNV DWP). Figure 8 Location of the vibration affected parties
6.2.1
Vibration Effects on Infrastructure Assets
Infrastructure assets, such as underground pipework, that are located near high vibration generating activities will be identified prior to commencing construction and included as the Schedule in Appendix B. Risk assessments of relevant infrastructure assets will be undertaken, and be managed through SSCVMPs (Section 8.2 of this CNV DWP).
Page 39
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
7 GENERAL MANAGEMENT PROCEDURES AND MITIGATION MEASURES The proposed works have the potential to exceed the relevant construction noise and vibration limits at the closest receivers. To avoid/minimise exceedances it is vital that appropriate mitigation and management measures are utilised. Best Practicable Option (BPO) mitigation will be implemented throughout the construction programme to avoid exceedances of the noise and vibration criteria. This will include, but not be limited to the mitigation measures detailed in this section of the CNV DWP. Mitigation of the effects of noise and vibration on affected parties in proximity to the Project is also outlined in sections 4.2 and 5.2 of the Project Social Impact and Business Disruption Delivery Work Plan (Appendix D of the Project CEMP), as a result of consultation with affected parties.
7.1
CONSTRUCTION NOISE AND VIBRATION MANAGEMENT SCHEDULES
Construction noise and vibration management schedules to this CNV DWP have been prepared for the construction activities listed in Table 6 – refer Appendix B for vibration and Appendix C for noise. The schedules identify the potentially affected neighbours, the noise and vibration levels at these neighbours, the proposed methodology and equipment to be used and specific mitigation/ management measures. The schedules will be checked and updated as necessary prior to commencement of each phase of construction works and at regular intervals (monthly as a minimum) throughout the duration of the works.
7.2
TRAINING
Procedures relating to environmental training, including noise and vibration site management procedures are detailed within Section 4.2 of the Project CEMP. As a minimum before commencing work on site all personnel will receive training based on this CNV DWP and relevant to their scope of works. If required, specific training will be provided for site personnel. Training will cover:
Roles and responsibilities for managing noise and vibration
Familiarisation with noise and vibration limits
Details of noise and vibration sources on-site
Noise and vibration mitigation and management procedures
Location of sensitive receivers
Construction noise and vibration effects on receivers
Details of any operational requirements and constraints identified through communication and consultation
Complaints management procedures
Other administrative and training procedures that will be adopted are:
Ensure site personnel communicate using the radio/phone rather than shouting.
Include clauses that require compliance with this CNV DWP in subcontractor agreements. Page 40
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Provide a protocol for handling noise and vibration complaints that includes recording, reporting and acting on complaints. Further detail is provided in the Communication and Consultation Plan (Appendix O of the Project CEMP)
Organise work to be undertaken during the Standard hours where reasonable and practical and safe to do so. Exceptions include works associated with installation of the permanent wearing course at the Customs Street intersection and steel fixing of the tunnel roof, which are proposed to take place during the night time, and works that may require full road closure, such as moving large equipment between work sites.
7.3
CONSTRUCTION TRAFFIC AND DELIVERIES
Noise mitigation and management procedures for construction traffic and deliveries shall include:
Fit engine exhausts with silencers.
Use broadband reversing alarms.
Avoid slamming doors.
Minimise speed and engine revs.
No stereos operated on site.
Minimise the use of horns.
Turn engines off when stationary for extended periods of time.
Place bedding layer or resilient liner in truck trays.
Use rubber seals around tailgates.
Minimise track squeal from tracked equipment such as excavators by greasing the tracks regularly.
7.4
PLANT AND EQUIPMENT
Designation Condition 21.1 (m) requires that site offices and less noisy construction activities be located at the edge of the construction yards where practicable. Plant and equipment noise and vibration mitigation and management procedures shall include:
Select plant and equipment based on noise and vibration emission levels.
Turn off plant and equipment or throttle them down to a minimum when not in use.
Select appropriately sized equipment for the task.
Use mufflers and engine covers/screens where appropriate.
Ensure equipment is operated in the correct manner and correctly maintained including replacement of engine covers, repair of defective silencing equipment, tightening of rattling components, repair of leakages in compressed air lines and shutting down of equipment not in use.
Avoid where possible the night-time use of equipment which generates impulsive noise: o
impact piling
o
dropping materials from a height
o
metal-to-metal contact on equipment.
Minimise drop height of materials when transferring (e.g. loading and unloading vehicles and storage areas).
Enclose generators with an effective muffler. Page 41
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Use power from Vector Electricity Network rather than from generators where practicable.
Reduce noise and vibration emissions from plant that has the potential to exceed the criteria by installing silencers, vibration isolation or other appropriate mitigation.
Maximise the distance between the engine exhausts of fixed plant and the nearest sensitive building façade.
Place tools and equipment on the ground – do not drop.
Cover surfaces with resilient material where tools/equipment are placed.
Do not drag equipment on the ground.
Avoid striking bare metal with tools.
Where spoil is being removed into a dump truck, or fill materials are being scooped from a dump truck, position the dump truck to minimise tracking movements.
When using concrete mixers on site do not let aggregates fall from excessive height and do not hammer the drum.
Use broadband reversing alarms on all mobile equipment.
7.5
PNEUMATIC BREAKERS
Noise and vibration mitigation and management procedures for breaking activities shall include:
Select the right size equipment for the job to minimise the length of time taken to complete the operation.
Use the lowest noise equipment available.
Do not “blank” fire the hammer. The activating valve should only be operated with the hammer in contact with the surface to be broken.
Keep breaker bushes and shaft greased as necessary.
Use correct chisel / tip shape for the type of material being broken.
Where work is contained within a compact area, use acoustic screens which block line of sight between breaker and sensitive receivers.
7.6
PILING AND COMPACTION
Noise and vibration mitigation and management procedures for piling and compaction activities shall include:
Avoid dynamic compaction using large tamping weights.
Minimise cable slap and chain clink.
Provide mufflers and engine covers/screens where appropriate.
Remove obstructions which may exacerbate vibration transmission where appropriate, prior to piling operations.
Page 42
Connectus Project #: 2665 Client: Auckland Transport
7.7
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
NOISE BARRIERS AND ENCLOSURES
Noise barriers or enclosures will be used in areas where the noise limits are predicted to be exceeded, and where they provide effective mitigation. Noise barriers will generally only be effective for ground floor receivers where noise levels would be reduced by approximately 10 dB. For a noise barrier to be effective it must cut line of sight between the source and receiver. Receivers on the first floor and above will be able to see over the noise barrier and it will provide little attenuation. Noise barriers will be required around all work areas.. The noise barriers should be a minimum of 1.8m high. An effective noise barrier is constructed as follows:
Positioned to cut line of sight between the construction work and receiver
Positioned as close as practicable to the noisy construction activity
Abutted or overlapped to provide a continuous screen with no gaps at the base or between panels. 2
Noise barriers will generally be constructed from plywood with a minimum surface mass of 10kg/m . However, proprietary products such as Flex Shield are available that have a lower surface mass but provide the same or better levels of noise attenuation. Flex Shield barriers will be utilised during utilities relocation and piling due to the temporary/ mobile nature of these works. Relocatable noise barriers will be erected around all utilities relocation work sites and around all piling sites. Permanent noise barriers will be erected around the southern construction compound as soon as it is set up and around the perimeter of the excavation works, see Figure 9. Figure 9 Location of Noise Barriers
Noise enclosures should be utilised where practicable as they provide better attenuation to receivers above ground floor level. Noise enclosures, with suitable ventilation, are likely to be required for concrete cutting, breaking and compacting. Where enclosures are proposed they shall be designed by the Acoustics Specialist - refer to Table 2 in Section 3 of this CNV DWP.
Page 43
Connectus Project #: 2665 Client: Auckland Transport
7.8
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
TRAFFIC TYRE NOISE
The Project requires public traffic to be routed over temporary traffic decks or through road works at various stages. Vehicle movements may cause temporary decks, steel plates and manholes to rock or move – giving rise to nuisance noises. Sharp changes in the level of the road surface may result in tyre noise. Connectus will use the following methods to reduce these issues so far as reasonably practicable, especially where the noise source will exist for long periods:
7.9
Firmly fix traffic decks to the road or other structural elements to prevent motion.
Place rubber beneath traffic decks and steel road plates where movement occurs.
Provide smooth transitions between changes in road surface level.
Ensure manhole covers are re-fitted correctly.
SCHEDULING OF ACTIVITIES
Scheduling of construction activities can be a key tool for managing construction noise and vibration effects. The time of day and the duration of the construction activities will be adjusted after consultation, where possible, to avoid particularly sensitive times for affected receivers. Consideration will also be given to respite periods and avoidance of activity on certain days (if requested by affected neighbours), where practicable. Night time disturbance to nearby residential receivers will be reduced by carrying out noisy activities during the day. However, the majority of affected properties are commercial, so night works may be preferable in some specific locations.
Page 44
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
8 SITE SPECIFIC CONSTRUCTION MANAGEMENT PLANS 8.1
SITE SPECIFIC CONSTRUCTION NOISE MANAGEMENT PLAN (SSCNMP)
The objective of a SSCNMP is to detail the best practicable option to avoid, remedy or mitigate adverse effects on a receiver resulting from construction noise that does not comply with the Project Noise Standards. A SSCNMP will be prepared for any receiver or activity where construction noise is either predicted or measured to exceed the Project Noise Standards identified in Section 4 of this CNV DWP, except where the exceedance is less than 5 decibels and does not exceed: a. 0700-2200: 1 period of up to 2 consecutive weeks in any 2 months b. 2200-0700: 1 period of up to 2 consecutive nights in any 10 days For predicted exceedances of less than 5 decibels monitoring shall be undertaken to confirm the actual noise levels. If exceedance is shown to be more than 5 decibels, or the period exceeds those detailed, then a SSCNMP must be prepared (refer designation Condition 37.3). The SSCNMP will identify: a) The extent to which noise may exceed the Project Noise Standards in designation Condition 31; b) The timing and duration of any exceedance; c) Details of the type of activity causing any exceedance; d) The summary of the communication and consultation undertaken with the receiver. The summary must include a clear explanation of where any comments have not been incorporated and the reasons why not. This information must be included in the SSCNMP provided to both the Independent Peer Review Panel and Auckland Council as part of the Outline Plan process specified in Condition 11; e) The methods and measures to mitigate noise effects, including but not limited to, potential to offer temporary relocation of affected receivers, alternative ventilation, faรงade sound insulation improvements, building condition surveys in the case of overpressure generated by blast events, or other offers made by the Requiring Authority and whether these have been agreed to by the affected receiver; f)
The reasons why the management and mitigation measures and methods reflect best practicable option.
The SSCNMP will be submitted for review to Auckland Council prior to commencing the works included in the SSCNMP as part of the Outline Plan. The works shall then be undertaken in accordance with the SSCNMP confirmed by the Requiring Authority as part of the Outline Plan. A SSCNMP will be prepared for the only notable receiver (Auckland District Court) affected by the works covered in this CNV DWP and for 23-29 Albert Street in accordance with Condition 37.4. In addition, SSCNMPs will be prepared for Stamford Plaza and Stamford Residences in accordance with the agreements they have in place with Auckland Transport.
Page 45
Connectus Project #: 2665 Client: Auckland Transport
8.2
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
SITE SPECIFIC CONSTRUCTION VIBRATION MANAGEMENT PLAN (SSCVMP)
The objective of a SSCVMP is to detail the best practicable option to avoid, remedy or mitigate adverse effects on a receiver resulting from vibration that does not comply with the Project Vibration Standards. A SSCVMP will be prepared: a) For any unoccupied building, structure or infrastructure for which construction vibration is either predicted or measured to exceed the Project Vibration Standards as detailed in Section 4.2 of this CNV DWP; b) Where a complaint or concern is raised and the vibration level exceeds the amenity levels as detailed in Section 4.3 of this CNV DWP. c) In response to other concerns or complaints where required (refer designation Condition 17). Where the amenity limits are exceeded: a) Best practicable management of vibration will be applied; and b) The vibration activity will be scheduled to avoid disturbance. If this is not practicable then reasonable respite periods will be provided to reduce vibration exposure. The limits identified in Section 4.2 of this CNV DWP may be relaxed by a SSCVMP but only for a building, structure or infrastructure that has been assessed by a suitably qualified and experienced structural engineer and where it has been deemed to be capable of withstanding higher vibration levels without sustaining building or structural damage, and where appropriate vibration and building condition monitoring regimes are in place. The SSCVMP will identify: a) The timing and duration of the exceedance; b) Details of the type of activity giving rise to the exceedance; c) Site Specific vibration criteria that addresses the issue(s) of concern (i.e. building damage, amenity and sensitive equipment). Site Specific criteria shall be determined by a suitably qualified independent vibration expert; d) The summary of the communication and consultation undertaken with the receiver. The summary must include a clear explanation of where any comments have not been incorporated, and the reasons why not. This information must be included in the SSCVMP provided to both the Independent Peer Review Panel and Auckland Council as part of the Outline Plan process specified in Condition 11; e) The methods and measures to mitigate vibration effects, including but not limited to, investigating alternative low-vibration construction methods, undertaking high-vibration works outside sensitive times, vibration barriers, building condition surveys, potential to offer temporary relocation of affected receivers, or other offers made by the Requiring Authority and agreed to by the affected receiver. The SSCVMP will be submitted for review to Auckland Council prior to commencing the works included in the SSCVMP as part of the Outline Plan. The works shall then be undertaken in accordance with the SSCVMP confirmed by the Requiring Authority as part of the Outline Plan. A SSCVMP will be prepared for the only notable receiver (Auckland District Court) affected by the works covered in this CNV DWP and for 23-29 Albert Street in accordance with Condition 37.4. In addition, SSCVMPs will be prepared for Stamford Plaza and Stamford Residences in accordance with the agreements they have in place with Auckland Transport.
Page 46
Connectus Project #: 2665 Client: Auckland Transport
8.3
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
SITE SPECIFIC CONSTRUCTION NOISE AND VIBRATION MANAGEMENT PLAN (SSCNVMP)
The conditions allow for SSCNMPs and SSCVMPs to be combined to form SSCNVMPs. Some site specific plans may therefore consider both noise and vibration. The SSCNVMPs that have been prepared for the Project cover a particular construction activity, a specific area of works or an individual building and are summarised in Table 11 and are included in full in Appendix I of this CNV DWP. Table 11 SSCNVMPs
Document Reference
Document Name
Revision
Date
CRL-PAT-ENV-CONPLN-001182
Customs Street Intersection Works
04
3 June 2016
CRL-PAT-ENV-CONPLN-001263
Advanced Utilities Works
03
3rd June 2016
CRL-PAT-ENV-CONPLN-001189
Albert Street Piling Works
03
3 June 2016
CRL-PAT-ENV-CONPLN-001187
Excavation Works
03
3rd June 2016
CRL-PAT-ENV-CONPLN-001184
Tunnel Construction Works
03
3rd June 2016
CRL-PAT-ENV-CONPLN-001188
Trench Backfilling and Reinstatement Works
03
3rd June 2016
CRL-PAT-ENV-CONPLN-001264
41 Albert Street
03
3rd June 2016
CRL-PAT-ENV-CONPLN-001265
District Court
03
3rd June 2016
CRL-PAT-ENV-CONPLN-001186
Stamford Plaza Hotel
07
25th May 2016
CRL-PAT-ENV-CONPLN-001185
Stamford Residences
09
3rd June 2016
rd
rd
Page 47
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
9 COMMUNICATON 9.1
COMMUNICATION
Good community communication practices are a key component for the management of disruption from construction activities. Prior to construction commencing, clear communication channels will be established between the project team and those in the community potentially most affected by construction activities. It is important that information is provided in a transparent and consistent manner in relation to exposure, duration, mitigation and management measures. Designation Condition 36.3(g) requires a record to be kept of communication and consultation with sensitive receivers with regard to construction noise and vibration impacts. A template for keeping this record is provided in Appendix D of this CNV DWP. The record includes details of when the communication/ consultation occurred, what the comments were from the sensitive receivers, where the comments have been incorporated into the CNV DWP and an explanation of where any comments from sensitive receivers have not been incorporated in the CNV DWP, including the reasons why not. Designation Condition 16.1 requires that communication and consultation is undertaken, as soon as reasonably practicable (and at least once following confirmation of construction timing and methodology), with any Notable Noise and Vibration Receivers located within 100 metres of the designation footprint. Again the template for keeping a record of communication and consultation with Notable Noise and Vibration Receivers is provided in Appendix D of this CNV DWP. On-going communication and consultation will be undertaken with notable noise and vibration receivers throughout the duration of construction occurring in the vicinity. This communication will be reported back to the “key contacts” (see designation Condition 13) and the Auckland Council Consent Monitoring officer for their review and confirmation of any further action to be undertaken. The Communication and Consultation Manager for the Project has a key responsibility to keep the community informed of construction activities. The following methodology sets out best practice communication to the community with regards to Noise and Vibration generated by the Project. Further detail on communications procedures for the Project is provided in the Communication and Consultation Plan.
There will always be a contact person available on site during works, and their contact details will be prominently displayed at the entrance to the site(s) so that they are clearly visible to the public.
Where the contact details for stakeholders are already known (i.e. sensitive receivers and Notable Noise and Vibration Receivers), Connectus’ Communication and Consultation Manager will make contact to engage in a consultative process. This may involve a face to face meeting or may be carried out over the phone as suits the needs of the stakeholder. Through this discussion and an information pack, Connectus will provide stakeholders the following information:
The nature of the project
The site and facilities layout
Dates for key milestones (road closures, site establishments and disestablishment etc.)
Contact details for the communication process,
The complaints management process.
Page 48
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Where changes are made to any of the above items, in particular to hours of operation or to likely duration of the operation, affected residents and property owners will be notified.
9.2
Individual notification shall be provided and meetings offered to all neighbours that are predicted to experience noise or vibration levels that exceed the limits detailed in Section 4 of the CNV DWP after the BPO mitigation as detailed in Section 6 has been applied. Where it is impractical to avoid an exceedance, consultation shall be undertaken to avoid significant adverse effects.
Ongoing consultation will be continued throughout the works with Notable Noise and Vibration receivers and any other neighbours raising concerns.
Further information will be regularly provided to affected parties with an update on the progress of the works, and the specific activities (including locations) due to be undertaken next. Updates will be provided every month.
A record will be kept of all communications
All concerns and complaints regarding construction noise and vibration will be dealt with in accordance with Section 9.2 of this CNV DWP.
COMPLAINTS PROCEDURE
Procedures relating to environmental complaints are detailed within Section 6 of the Communication and Consultation Plan (Appendix O of the Project CEMP). All complaints will be recorded in a Project Complaints Register. Connectus will provide Auckland Council's Noise Complaints Team with contact details for the CRL Complaints Team to ensure Auckland Council can pass CRL related noise complaints to the Project quickly. This is intended to minimise the resolution time in the event that a member of the public does not call the CRL Complaints Team directly.
Page 49
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
10 MONITORING A B&K 2250 Sound Level Meter will be located at the site office for the duration of the works. A B&K 2250 Sound Level Meter and two Rion NL21s noise loggers will also be available for use on the Project and stored at the AECOM office (8 Mahuhu Crescent). An Instantel Minimate Plus vibration logger will be stored at the AECOM office.
10.1 NOISE Construction noise will be measured and assessed in accordance with the requirements of New Zealand Standard NZS 6803: 1999 “Acoustics - Construction Noise� Noise monitoring will be conducted by the Acoustic Specialist or trained noise monitoring staff as identified in Section 3 of this CNV DWP. The equipment noise levels detailed in Table 5 are placeholders. All equipment that is predicted to exceed 75 dB LAeq at 5m will be measured operating off-site prior to operation on site, where practicable. Where this is not practicable it will be measured when first operating on site. Actual equipment noise levels at 5m and equipment model numbers will be recorded. This information will be used to update the noise schedules in Appendix C of this CNV DWP within one week of the measurements being undertaken. The SSCNVMPs identify monitoring locations and the timing of monitoring at the most affected receivers. In addition to the monitoring identified in the SSCNVMPs noise monitoring will be carried out at positions representative of noise sensitive locations, see Figure 11, at least every month, to check ongoing compliance with the construction noise limits. The monitoring position will be at first floor level. Figure 11 Noise monitoring locations
Page 50
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Noise should be measured 1m from the most affected faรงade of the building, or in the area which relates to a noise complaint. If it is not practicable to measure at this position, measurements can be taken at a representative location and adjusted for distance and faรงade reflections if necessary. Measurements should also be taken at a known distance, such as 5m, from the noise generating equipment to establish source noise levels. Additional measurement positions may be necessary if the initial measurement results indicate that noise may exceed criteria at other areas of the building faรงade. These measurements may be undertaken 1m from the faรงade if windows are normally open or inside the building if windows are normally closed. Where internal measurements are required it will be necessary to control noise from local sources, such as people using the telephone, to ensure only construction noise is measured. Noise monitoring will be conducted for 10-15 minutes at each measurement position, during representative construction activity. The noise level will be reported with the measurement duration (e.g. 65 dB LAeq (15min)) Noise monitoring will also be undertaken in response to reasonable noise complaints, or if the construction methodology changes such that noise criteria may be exceeded at other locations. Figure 12 outlines the process to be followed when monitoring noise.
Page 51
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Figure 12 Noise Monitoring Flowchart
Page 52
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
10.2 VIBRATION Construction vibration levels will be measured and assessed in accordance with the requirements of German Standard DIN 4150-3:1999 “Structural vibration – Part 3: Effects of vibration on structures”. Prior to construction, trial measurements of high-vibration activities will be undertaken to establish Project specific ground attenuation characteristics and safe distances. The SSCNVMPs identify vibration monitoring locations and the timing of monitoring at the most affected receivers. In addition to the monitoring identified in the SSCNVMPs vibration monitoring will be carried out at positions representative of vibration sensitive locations, see Figure 13, at least every month, to check ongoing compliance with the construction vibration limits. Figure 13 Vibration monitoring locations
Vibration monitoring shall only be undertaken by the Acoustic Specialist or trained vibration monitoring staff as identified in Section 3 of this CNV DWP. Vibration shall initially be measured at the closest building foundations (usually at basement or ground floor level) and this requires consent to access the building of interest. Additional measurement positions may be necessary if the initial measurement results indicate that vibration may exceed criteria within other areas of the building. It may also be necessary to measure vibration levels in the habitable areas of buildings in response to a complaint. Vibration monitoring will be conducted during representative construction activities and comprise measurements of peak particle velocity (PPV) at one second intervals. The duration of the vibration measurements will be sufficient to capture the highest vibration level from the source. The vibration monitoring equipment (geophones) will be fixed to building structural members (e.g. with clamps, cable ties, or weighed down with sandbags).
Page 53
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
The geophones will ideally be located at or near the faรงade of the building facing the vibration source and will be located away from areas where extraneous vibration (e.g. from footfall or building services) could affect the results. The monitoring results shall be used to update the vibration schedules in Appendix B of this CNV DWP within one week of the measurements being undertaken. Vibration monitoring shall also be undertaken in response to reasonable vibration complaints, or if the construction methodology changes such that vibration criteria may be exceeded at other locations. Figure 14 outlines the process to be followed when monitoring vibration.
Page 54
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Figure 14 Vibration monitoring flowchart
Page 55
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
10.3 REPORTING All noise and vibration monitoring shall be summarised in a report and submitted to the Communication and Consultation Manager and the Environment and Sustainability Manager (ESM) within one week of the assessment. The reports shall be kept at the site office and made available to AT or Auckland Council upon request.
10.4 BUILDING CONDITION SURVEYS A detailed pre-construction building condition survey will be undertaken at all of the identified buildings and services detailed in the vibration schedules, Appendix B, before construction begins on the Project. Designation Condition 46 describes the process for building condition surveys. The building condition surveys will generally be undertaken as follows:
The building surveys will be undertaken by an independent senior qualified person
The survey shall include: o
Any information about the type of foundations
o
Existing levels of damage (aesthetic, superficial, affecting levels of serviceability)
o
Whether observed damage is associated with structural damage
o
Susceptibility of building or structure to further movement
o
Photographic evidence
The consent holder will provide the building condition survey structure survey report to the property owner and the Council within 15 working days of the survey being undertaken
If requested by a building or structure owner where a pre-construction survey was undertaken, Connectus will undertake a visual inspection. This is in addition to monthly visual inspections until the completion of Dewatering of the Project
Connectus shall carry out visual inspections of the surrounding ground and external building facades of the listed buildings adjacent to the tunnel trench to monitor any deterioration or movement of any pre-existing cracks
The building condition surveys will be conducted by a suitably qualified person as identified in Section 4.1.2 of the Project CEMP. During the pre-construction building condition survey, it will be determined if the building is classified as Commercial / Industrial / School or a Historic or sensitive structure in terms of designation Condition 33. The foundation type of the building or service will also be determined. The buildings and services may require further surveys during construction if complaints are made or if the vibration criteria have been exceeded. A post-construction condition survey of the same buildings and services will be conducted a week after the conclusion of works in the area that have the potential to generate vibration at levels approaching or exceeding the limits in Condition 33. A report will then be prepared. Where a post-construction building condition survey confirms that the building has deteriorated as the result of construction the damage will be rectified.
Page 56
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
11 CONTINGENCY MEASURES This section describes contingency measures to be implemented in the event that the noise and/or vibration limits specified in an approved SSCNVMP are exceeded. The Communication and Consultation Manager will liaise with affected parties (refer Section 9 of this CNV DWP) throughout the following processes.
11.1 MANAGEMENT PROCESS Where any construction activity is predicted and/or measured to exceed the construction noise or vibration limits the following process will be applied:
Check that the BPO and all relevant management measures have been implemented (refer Section 7 of this CNV DWP and Section 5 of the relevant SSCNVMP)
Communication and Consultation Manager to consult with all affected parties, as defined in Section 9, to understand their particular sensitivities, including times, activities and locations. The Communication and Consultation Manager or their representative shall be available 24/7.
Carry out noise and/or vibration monitoring of the construction activity to verify the extent of any adverse effects (refer Section 10 of this CNV DWP).
Implement further mitigation and/or contingency measures to avoid significant adverse effects as agreed with the affected party (refer Sections 11.2 to 11.5 of this CNV DWP).
11.2 NOISE If noise monitoring demonstrates non-compliance with the noise limits identified in the approved SSCNVMP, the following procedures shall be implemented:
Undertake additional noise measurements, as necessary, to determine the extent of the exceedance.
Discuss additional mitigation options with the Project Manager as soon as the extent of the exceedance has been determined. This may include immediately stopping works.
Undertake noise measurements once recommended mitigation measures have been implemented to confirm that the mitigation has been effective and the noise limits are now being met.
Preparation of a report recording the findings of the survey and detailing additional mitigation or management options. Copies of the report will be provided to AT, the Project Manager, Communication and Consultation Manager and Sustainability Manager.
11.3 VIBRATION – BUILDING DAMAGE If vibration monitoring demonstrates non-compliance with the vibration building damage limits identified in the approved SSCNVMP, the construction activity responsible for the exceedance shall cease as soon as safe and practicable to do so. A detailed building condition survey shall then be undertaken by a suitably qualified engineer. The survey shall include, but not be limited to, the following:
Determination of building specific vibration damage risk thresholds;
Existing condition of building including existing levels of any aesthetic damage or structural damage; Page 57
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Recording (including photographs) the major features of the buildings including location, type, construction, age and present condition, including defects (cracks);
Identifying foundation type of the building;
Preparation of a report recording the findings of the survey. A copy of the report will be given to the building owner and another copy will be kept at the site office.
If damage has not occurred then that activity can continue provided the measured vibration level is not exceeded further. If minor damage has occurred, such as cosmetic cracks, further mitigation will be applied if practicable. However, the activity can continue provided the measured vibration level is not exceeded further. If moderate or severe damage has occurred and the best practicable option has been implemented, it will be necessary to stop work, if safe to do so, and investigate alternative construction methods. All damage due to construction activities will be repaired within a reasonable timeframe after the construction phase ceases.
11.4 VIBRATION – AMENITY If a complaint is made by a building occupant with regard to vibration levels, vibration monitoring will be conducted in the relevant rooms of the building. If the limits are found to be exceeded then a SSCVMP will be prepared for that receiver.
11.5 DISCUSSION Where noise and vibration impacts are unavoidable and significant after all reasonable and practicable measures are implemented, alternative mitigation measures, such as temporary relocation or the provision of architectural treatments, will be considered. Temporary relocation involves the relocation of affected occupants for short periods of time where all reasonable and practicable measures and respite periods are implemented and further mitigation is impractical. Architectural treatments may also be sought and involve the provision of alternative ventilation where windows are to remain closed in order to further mitigate noise effects.
Page 58
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
APPENDIX A: ISCA REQUIREMENTS
Page A
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
AT and Connectus are seeking an Infrastructure Sustainability Council of Australia (ISCA) Infrastructure Sustainability (IS) Rating for the CRL Enabling Works. This appendix details IS requirements that are different, or additional to the Project’s Consent Requirements. It is essential that these requirements are met to achieve the Project’s sustainability goals, however they are not consent requirements to be certified by Auckland Council. These IS rating requirements are included as an appendix because they are not yet fixed. They remain subject to change as the Project’s sustainability program evolves. Applicable ISCA requirements that relate to this CNV DWP are listed below along with their associated target Levels. ISCA Category
Target Level
Construction Requirements
How we aim to achieve this
DIS 2 - Noise
2
Predictions for noise have been developed for construction of the project
Compliance with the CNV DWP
AND Measures to mitigate noise during construction have been identified and implemented
Completed in the AEE Changes dealt with in Section 4 and Site Specific Plans Section 7
AND Monitoring of noise is undertaken at appropriate intervals and in response to complaints during construction
Section 10
AND
Modelling – Section 5, 6, and 8 and Appendix B and C
Modelling and monitoring demonstrates no recurring or major divergence from the noise management process as outlined in the project consents and this CNVMP
Monitoring – Section 9 Section 11 – Noise management process we should not diverge from.
Stretch Target (to achieve level three) Modelling and Monitoring demonstrates no divergence from the noise management process. DIS 3 Vibration
2
Dilapidation surveys have been undertaken for properties potentially impacted by vibration
Section 10.4
AND Predictions for vibration have been developed for construction of the project
AND
Appendix B + Largely done in the AEE
Section 7
Measure to mitigate vibration during construction have been identified and implemented. AND
Page 1
Connectus Project #: 2665 Client: Auckland Transport
ISCA Category
Target Level
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Construction Requirements
How we aim to achieve this
Monitoring of vibration is undertaken at appropriate intervals and in response to complaints during construction.
Section 10
AND Sensitive facilities that may be impacted by vibration have been identified and baseline vibration studies have been carried out
Baseline vibration studies in the AEE
AND Modelling and monitoring demonstrates no exceedances of vibration goals for structural damage to buildings and structures AND
Sections 10 and 11
Section 11
No physical damage has been caused to any building or structures by vibration caused by construction.
Page 2
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
APPENDIX B: Schedule of Identified At-Risk Receivers, Structures and Services (Vibration)
Page B
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Advanced Utilities Relocation This is a schedule to the Construction Noise and Vibration DWP for the CRL Contract 2 Enabling Works project. This schedule provides specific assessment of the following activity: Construction Activity
Area of works
Activity Start Date
Duration
Advanced Utilities Relocation Works
Customs St Intersection Stormwater Works
Early May
50 days
Swanson St West Stormwater Works
Early August
12 days
Swanson St East Early Stormwater Works
Early August
20 days
Swanson St East Stormwater Works ANZ Connection
Early September
15 days
Wyndham St Stormwater Works
Early May
25 days
Kingston-Wyndham St Stormwater Works
Early May
35 days
Combined Service Trench – Western Footpath including crossings
Early May
60 days
Wyndham St Chorus Works
Early June
15 days
Hours
7am – 7pm Mon - Sat
Vibration sources
Equipment
Excavator mounted concrete breaker
Construction activity
Concrete breaking
Emission radius (m) Historic/sensitive
Residential
Commercial
16
10
7
At-risk Receivers
Address
Building type
Distance to works (m)
Risk class
38 Wyndham Street
Commercial
1
High
3 Albert Street
Commercial
1
High
63 Albert Street
Commercial
2
High
65-71 Albert Street
Historic / vibration sensitive
2
High
Predicted Vibration (no mitigation) PPV
Management/ mitigation required
Page 1
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Address
Building type
Distance to works (m)
Risk class
12-26 Swanson Street
Commercial
2
High
61 Albert Street
Historic / Vibration Sensitive
2
High
57 Albert Street
Historic / Vibration Sensitive
2
High
41 Albert Street
Historic / Vibration Sensitive
2
High
58 Albert Street
Commercial
2
High
52-56 Albert Street
Historic / Vibration Sensitive
2
High
51 Albert Street
Historic / Vibration Sensitive
2
High
55 Albert Street
Historic / Vibration Sensitive
2
High
22 Customs Street
Historic / Vibration Sensitive
3
High
22-26 Albert Street
Residential
4
High
11-27 Customs Street
Commercial
7
Medium
70-74 Albert Street
Residential
8
High
Bluestone Wall
Historic / Vibration Sensitive
9
High
34-36 Wyndham Street
Historic / Vibration Sensitive
10
High
Predicted Vibration (no mitigation) PPV
Management/ mitigation required
At-risk Services (e.g. roads, underground pipes etc.)
Reference
Address
Receiver type/ comments
Distance to works
Risk class (High or Medium)
Management/ mitigation required
Page 2
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Piling This is a schedule to the Construction Noise and Vibration DWP for the CRL Contract 2 Enabling Works project. This schedule provides specific assessment of the following activity: Construction Activity
Area of works
Activity Start Date
Activity End Date
Hours
Piling
Install CFA piles
Customs Deck 1 through to Wolfe Street - West side
20 Sep2016
05 Oct 2016
South East Quarter
26 Oct 2016
12 Dec 2016
7am – 7pm
South West Quarter
22 Dec 2016
07 Mar 2017
Mon - Sat
North East Quarter
10 Mar 2017
06 Apr 2017
Wolfe Street - West side
24 Apr 2017
26 Apr 2017
Pile Caps and Traffic Decks
Build pile cap & deck
Customs Deck 1 through to Wolfe Street - West side
27 Sep 2016
18 Oct 2016
South East Quarter
02 Nov 2016
23 Dec 2016
South West Quarter
12 Jan 2017
03 Mar 2017
Build cap only West side ANZ to Wolfe Street
27 Feb 2017
15 Mar 2017
North East Quarter
17 Mar 2017
24 Apr 2017
Build deck ANZ to Wolfe Street
13 Apr 2017
08 May 2017
7am – 7pm Mon - Sat
Vibration sources
Equipment
Construction activity
Emission radius (m) Historic/sensitive
Residential
Commercial
Soilmec Hydraulic Rotary Rig (est SR80)
Installation of CFA piles
3
2
1
Excavator mounted concrete breaker
Utilities location and exposure and installation of pile cap
16
10
7
Page 3
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
At-risk Receivers
Address
Building type
Distance to works (m)
Risk class
Predicted Vibration (no mitigation) PPV
Management/ mitigation required
Installation of CFA piles 22 Customs Street
Historic / vibration sensitive
3
Medium
5 Albert Street
Historic / vibration sensitive
5
9 Albert Street
Historic / vibration sensitive
5
13 Albert Street
Historic / vibration sensitive
5
15 Albert Street
Historic / vibration sensitive
5
17 Albert Street
Historic / vibration sensitive
5
Medium Medium Medium Medium Medium
Utilities Location and Installation of Pile Caps 22 Customs Street
Historic / vibration sensitive
3
High
5 Albert Street
Historic / vibration sensitive
5
High
9 Albert Street
Historic / vibration sensitive
5
High
3 Albert Street
Commercial
5
High
17 Albert Street
Historic / vibration sensitive
5
High
23-29 Albert Street
Commercial
6
High
55 Albert Street
Historic / vibration sensitive
6
High
61 Albert Street
Historic / vibration sensitive
6
High
41 Albert Street
Historic / vibration sensitive
6
High
57 Albert Street
Historic / vibration sensitive
6
High
38 Wyndham Street
Commercial
7
High
58 Albert Street
Commercial
7
High
63 Albert Street
Commercial
7
High
8 Albert Street
Residential
8
High
70-74 Albert Street
Residential
8
High
22-26 Albert Street
Residential
9
High Page 4
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
At-risk Services (e.g. roads, underground pipes etc.)
Reference
Address
Receiver type/ comments
Distance to works
Risk class (High or Medium)
Management/ mitigation required
Excavation This is a schedule to the Construction Noise and Vibration DWP for the CRL Contract 2 Enabling Works project. This schedule provides specific assessment of the following activity: Construction Activity
Remove existing road surface
Excavation 1st Layer
nd
Excavation 2 to Bottom
Area of works
Activity Start Date
Activity End Date
Hours
South end to Ch550
23 Mar 2017
28 Mar 2017
Ch550 to Swanson
23 Mar 2017
27 Mar 2017
7am – 7pm
Swanson to Wolfe
26 May 2017
30 May 2017
Mon – Sat
Wolfe to North end
03 Jul 2017
05 Jul 2017
South end to Ch550
29 Mar 2017
04 Apr 2017
Ch550 to Swanson
28 Mar 2017
19 Apr 2017
7am – 7pm
Swanson to Wolfe
31 May 2017
28 Jun 2017
Mon – Sat
Wolfe to North end
06 Jul 2017
02 Aug 2017
South end to Ch550
21 Apr 2017
01 Sep 2017
Ch550 to Swanson
20 Apr 2017
07 Sep 2017
7am – 7pm
Swanson to Wolfe
29 Jun 2017
05 Dec 2017
Mon – Sat
Wolfe to North end
03 Aug 2017
23 Mar 2018
Vibration sources
Equipment
Excavator mounted concrete breaker
Construction activity
Pre-drilling
Emission radius (m) Historic/sensitive
Residential
Commercial
16
10
7
Page 5
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
At-risk Receivers
Address
Building type
Distance to works (m)
Risk class
Predicted Vibration (no mitigation) PPV
Management/ mitigation required
Pre-drilling 6 Albert Street
Historic / vibration sensitive
5
High
17 Albert Street
Historic / vibration sensitive
5
High
15 Albert Street
Historic / vibration sensitive
5
High
13 Albert Street
Historic / vibration sensitive
5
High
9 Albert Street
Historic / vibration sensitive
5
High
7 Albert Street
Historic / vibration sensitive
5
High
3 Albert Street
Commercial
5
High
58 Albert Street
Commercial
7
High
51 Albert Street
Historic / vibration sensitive
6
High
38 Wyndham Street
Commercial
6
High
61 Albert Street
Historic / vibration sensitive
6
High
52-56 Albert Street
Historic / vibration sensitive
7
High
57 Albert Street
Historic / vibration sensitive
6
High
55 Albert Street
Historic / vibration sensitive
6
High
41 Albert Street
Historic / vibration sensitive
6
High
23-29 Albert Street
Commercial
6
High
63 Albert Street
Commercial
7
Medium
46-50 Albert Street
Historic / vibration sensitive
7
High
12-26 Swanson Street
Commercial
7
Medium
12 Albert Street
Mixed Use
8
High
70-74 Albert Street
Mixed Use
8
High
22-26 Albert Street
Residential
9
High
Page 6
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
At-risk Services (e.g. roads, underground pipes etc.)
Reference
Address
Receiver type/ comments
Distance to works
Risk class (High or Medium)
Management/ mitigation required
Trench Backfilling and Reinstatement This is a schedule to the Construction Noise and Vibration DWP for the CRL Contract 2 Enabling Works project. This schedule provides specific assessment of the following activity: Construction Activity
Trench Backfill
Road surface reinstatement
Area of works
Activity Start Date
Activity End Date
South end to Swanson
27 Nov 2017
12 Apr 2018
Swanson to Wolfe
05 Mar 2018
03 Jul 2018
Wolfe to North end
16 Aug 2018
22 Nov 2018
South end to Swanson
13 Apr 2018
09 Jul 2018
Swanson to Wolfe
04 Jul 2018
11 Sep 2018
Wolfe to North end
23 Nov 2018
25 Jan 2019
Hours
7am – 7pm Mon – Sat
7am – 7pm Mon – Sat
Vibration sources
Equipment
Construction activity
Roller Compactor (17t)
Emission radius (m)
Fill compaction and road surface reinstatement
Historic/sensitive
Residential
Commercial
15
8
4
At-risk Receivers
Address
Building type/ comments
Distance to works
Risk class (High or Medium)
22 Customs Street
Historic / vibration sensitive
5
High
5 Albert Street
Historic / vibration sensitive
5
High
9 Albert Street
Historic / vibration sensitive
5
High
3 Albert Street
Commercial
5
Medium
Predicted Vibration (no mitigation) PPV
Management/ mitigation required
Page 7
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Address
Building type/ comments
Distance to works
Risk class (High or Medium)
17 Albert Street
Historic / vibration sensitive
5
High
55 Albert Street
Historic / vibration sensitive
6
High
61 Albert Street
Historic / vibration sensitive
6
High
41 Albert Street
Historic / vibration sensitive
6
High
57 Albert Street
Historic / vibration sensitive
6
High
8 Albert Street
Residential
8
High
70-74 Albert Street
Residential
8
High
22-26 Albert Street
Residential
9
Medium
Predicted Vibration (no mitigation) PPV
Management/ mitigation required
At-risk Services (e.g. roads, underground pipes etc.)
Reference
Address
Receiver type/ comments
Distance to works
Risk class (High or Medium)
Management/ mitigation required
Page 8
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
APPENDIX C: Schedule of Identified At-Risk Receivers (Noise)
Page C
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Advanced Utilities Works This is a schedule to the Construction Noise and Vibration DWP for the CRL Contract 2 Enabling Works project. This schedule provides specific assessment of the following activity: Construction Activity
Area of works
Activity Start Date
Duration
Advanced Utilities Relocation Works
Customs St Intersection Stormwater Works
Early May
50 days
Swanson St West Stormwater Works
Early August
12 days
Swanson St East Early Stormwater Works
Early August
20 days
Swanson St East Stormwater Works ANZ Connection
Early September
15 days
Wyndham St Stormwater Works
Early May
25 days
Kingston-Wyndham St Stormwater Works
Early May
35 days
Combined Service Trench – Western Footpath including crossings
Early May
60 days
Wyndham St Chorus Works
Early June
15 days
Hours
7am – 7pm Mon - Sat
Equipment Noise Levels
Works Phase
Equipment
Sound pressure level dB LAeq 5m
Advanced Utilities Works
10m
20m
50m
Concrete Saw
93
87
81
73
Vacuum Excavation truck
84
78
72
69
Excavator (5t)
71
65
59
51
Jackhammer
89
83
77
69
Excavator mounted concrete breaker
90
84
78
70
Truck
83
77
71
63
Hand compactor
86
80
74
66
Page 1
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Predictions
102
-
3 Albert Street
Commercial
1
101
61 Albert Street
Mixed Use
2
100
-
-
57 Albert Street
Commercial
2
100
-
-
17 Albert Street
Commercial
3
100
-
9 Albert Street
Mixed Use
2
100
81
5 Albert Street
Commercial
2
100
80
41 Albert Street
Residential
2
100
-
-
38 Wyndham Street
Commercial
1
97
-
-
23-29 Albert Street
Commercial
3
97
-
12-26 Swanson Street
Commercial
2
93
-
65-71 Albert Street
District Court
2
92
-
22-26 Albert Street
Residential
4
86
34-36 Wyndham Street
Commercial
10
83
80
83
93
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
80
-
-
-
-
-
-
76
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
79
-
-
-
98
-
-
-
-
-
-
-
-
94
78
97
90 -
-
79
-
91
81
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
80
79
89
-
80
76
76 100
-
81
-
-
-
-
78
-
-
-
-
-
-
-
-
-
79
-
Customs Street Watermain
Swanson Street Stormwater - West
Swanson Street Stormwater - East
Customs Street Stormwater - Northeast
Customs Street Stormwater – Southwest
94
-
-
-
92
-
-
80 -
-
Chorus Wyndham Street
2
Wyndham Street Permanent Works
Commercial
Wyndham Street Temporary Diversion
63 Albert Street
Kingston Street to Wyndham Street Stormwater
-
Vector Gas - Mills Lane to Swanson Street
Vector Communications – Customs Street to Mills Lane
Combined Services Trench
Minimum Distance to Works (m)
Building Use
Address
Predicted worst case noise levels (no mitigation), dB LAeq
100
-
91
-
-
-
-
-
-
-
-
76
86
-
Page 2
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
33 Wyndham Street
Commercial
15
82
-
-
8 Albert Street
Mixed Use
3
81
-
-
-
-
-
-
-
-
70-74 Albert Street
Mixed Use
8
80
-
-
-
22 Customs Street
Commercial
3
79
-
-
-
-
-
-
26 Wyndham Street
Commercial
17
78
-
-
-
-
-
-
-
-
-
18 Federal Street
Residential
35
76
-
-
-
-
-
-
-
-
-
-
-
6 Wolfe Street
Vacant
35
76
-
-
-
-
-
-
-
-
-
-
-
9 Wolfe Street
Commercial
27
76
-
-
-
-
-
-
-
-
-
-
-
29 Customs Street
Commercial
19
76
-
-
-
-
-
-
-
-
-
46-50 Albert Street
Commercial
2
-
-
-
-
-
81 Albert Street
Mixed Use
14
-
-
76 Albert Street
Residential
20
-
4 Kingston Street
Commercial
25
-
100 -
97
100
76 -
-
80
77 80
80
76 80
82 -
80
78 -
-
-
78
-
-
91 79
78
-
-
-
-
-
-
-
-
-
-
-
83
-
-
-
-
-
-
-
-
-
-
77
-
-
-
-
-
-
-
-
-
-
76
-
-
-
-
Mitigation
Mitigation is required to meet the noise criteria at the nearest sensitive receivers. The general noise control measures outlined in Section 7 of the CNV DWP will be implemented. Where additional mitigation is required to meet the noise criteria it is detailed in the Advanced Utilities Works SSCNVMP or the SSCNVMPs for specific receivers.
Page 3
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Intersection Piling and Road Deck Construction This is a schedule to the Construction Noise and Vibration DWP for the CRL Contract 2 Enabling Works project. This schedule provides specific assessment of the following activity: Construction Activity
Area of works
Activity Start Date
Activity End Date
Hours
SP1 Advance Utilities Works Install Vector services trench Customs Wyndham
Customs – Wyndham St
01 Apr 2016
Install Customs pipejack
MH in Lower Albert
01 Apr 2016
29 Apr 2016
7am to 7pm
MH in South West
10 Jun 2016
23 Jun 2016
Mon - Sat
Customs Intersection
24 Jun 2016
21 Jul 2016
27 May 2016
7am to 7pm Mon - Sat
Services and Enabling Works Cut back curb
Galleria block
09 May 2016
03 Jun 2016
Locate & Protect Services
Customs Deck 1
10 Jun 2016
16 Jun 2016
Customs Deck 2
10 Jun 2016
16 Jun 2016
Customs Deck 3
05 Sep 2016
09 Sep 2016
Customs Deck 4
02 Dec 2016
08 Dec 2016
7am to 7pm Mon - Sat
Piling Pile
Customs Deck 1
20 Jun 2016
05 Jul 2016
7am to 7pm
Customs Deck 2
09 Jul 2016
20 Jul 2016
Mon - Sat
Customs Deck 3
13 Sep 2016
15 Sep 2016
Customs Deck 4
09 Dec 2016
15 Dec 2016
Pile Caps and Traffic Decks Customs St Deck
Section 1
06 Jul 2016
16 Aug 2016
7am to 7pm
Section 2
21 Jul 2016
31 Aug 2016
Mon - Sat
Section 3
20 Sep 2016
24 Nov 2016
Section 4
16 Dec 2016
22 Feb 2017
The activity involves service location and exposure, installation of CFA piles, jet grouting, excavation and support of exposed services, binding and fixing of reinforcement, placement of concrete and installation of permanent wearing course (night). The activity also includes demolition of the stormwater pumping station and stormwater line. Equipment Noise Levels
Works Phase
Equipment
Type of works
Sound pressure level dB LAeq 5m
CEP 308-001 Customs Street Intersection
10m
20m
50m
Concrete core drill (type TBC)
Surface removal and service clearing
91
85
79
71
Vacuum Excavation (type TBC)
Surface removal and service clearing
84
78
72
64 Page 4
Connectus Project #: 2665 Client: Auckland Transport
Works Phase
Equipment
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Type of works
Sound pressure level dB LAeq 5m
Piling and Road Deck Construction
10m
20m
50m
Soilmec Hydraulic Rotary Rig (est SR80)
Auger drilling and pile casing installation
88
82
76
68
Concrete Truck
Concrete delivery
83
77
71
63
Crane
Service crane and pile reinforcement install
82
76
70
62
Mecbo tracked Concrete Pump
Concrete placement
84
78
72
64
Excavator (est 15t)
Excavation post piling
79
73
67
59
SM-20 Hydraulic Micro drilling Rig
Jet Grouting
82
76
70
62
Hydro-demolition high pressure pump
Removal of concrete encasement on SW main
87
81
75
67
Bob cat loader
Handling materials
82
76
70
62
Crane (est. 40t)
Unloading and placing service supports, steel reinforcement and formwork
82
76
70
62
Concrete saw
Demolition of storm water chamber roof
93
87
81
73
Angle grinder
Pile breaking
86
80
74
66
Excavator mounted concrete breaker
Break back over pour on the piles
90
84
78
70
Concrete vibrators
Concrete placement
75
69
63
55
Roller compactor
Installation of permanent wearing course
85
79
73
65
Concrete boom pump
Placement of concrete in deck slab
86
80
74
66
Page 5
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Predictions
Predicted worst case noise levels (no mitigation), dB LAeq
Jet Grouting
Excavation and support of exposed services
Binding and fixing of reinforcement
Placement of concrete
Stormwater pumping station demolition
Stormwater line demolition
95
99
88
97
90
93
91
90
89
93
82
91
84
87
85
22
80
79
83
-
81
-
77
-
Mixed use (commercial/ residential)
28
77
76
80
-
78
-
-
-
Commercial
29
76
-
79
-
77
-
-
-
Address
Building Use
Minimum Distance to works (m)
Service location and exposure
Installation of CFA piles
22 Customs Street
Commercial
3
96
3 Albert Street
Commercial
8
29 Customs Street
Commercial
8 Albert Street 5 Albert Street
Mitigation
Mitigation is required to meet the noise criteria at the nearest sensitive receivers. The general noise control measures outlined in Section 7 of the CNV DWP will be implemented. Where additional mitigation is required to meet the noise criteria it is detailed in the Customs Street Intersection SSCNVMP.
Page 6
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Albert Street Piling and Capping Beam This is a schedule to the Construction Noise and Vibration DWP for the CRL Contract 2 Enabling Works project. This schedule provides specific assessment of the following activity: Construction Activity
Area of works
Activity Start Date
Activity End Date
Hours
Piling
Install CFA piles
Customs Deck 1 through to Wolfe Street - West side
20 Sep2016
05 Oct 2016
South East Quarter
26 Oct 2016
12 Dec 2016
7am – 7pm
South West Quarter
22 Dec 2016
07 Mar 2017
Mon - Sat
North East Quarter
10 Mar 2017
06 Apr 2017
Wolfe Street - West side
24 Apr 2017
26 Apr 2017
Pile Caps and Traffic Decks
Build pile cap & deck
Customs Deck 1 through to Wolfe Street - West side
27 Sep 2016
18 Oct 2016
South East Quarter
02 Nov 2016
23 Dec 2016
South West Quarter
12 Jan 2017
03 Mar 2017
7am – 7pm
Build cap only West side ANZ to Wolfe Street
27 Feb 2017
15 Mar 2017
Mon - Sat
North East Quarter
17 Mar 2017
24 Apr 2017
Build deck ANZ to Wolfe Street
13 Apr 2017
08 May 2017
The activity involves service location and exposure, installation of CFA piles and installation of pile caps. Equipment Noise Levels
Works Phase
Equipment
Type of works
Sound pressure level dB LAeq 5m
CEP 309-001 Albert Street Piling and Capping Beam
10m
20m
50m
Concrete core drill
Surface removal and service clearing
91
85
79
71
Vacuum Excavation
Surface removal and service clearing
84
78
72
64
Soilmec Hydraulic Rotary Rig (est SR80)
Auger drilling and pile casing installation
88
82
76
68
Crane est 40t
Service crane and pile reinforcement install
82
76
70
62
Mecbo tracked Concrete Pump
Concrete placement
84
78
72
64
Concrete truck
Concrete delivery
83
77
71
63
Hydraulic rock splitter
Installation of pile cap
90
84
78
70
Excavator (est 15t)
Excavation post piling
79
73
67
59 Page 7
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Predicted worst case noise levels (no mitigation), dB LAeq
Address
Building Use
Minimum Distance to Works (m)
Utilities Location and exposure
Installation of CFA Piles
Installation of Pile Caps
15 Albert Street
Vacant
5
96
95
95
13 Albert Street
Vacant
5
96
95
95
9 Albert Street
Mixed Use (commercial / residential)
4
96
95
95
5 Albert Street
Commercial
4
96
95
95
3 Albert Street
Commercial
5
96
95
95
17 Albert Street
Commercial
5
95
94
94
22 Customs Street
Commercial
3
95
94
94
51 Albert Street
Commercial
6
94
93
93
41-45 Albert Street
Residential
6
94
93
93
23-29 Albert Street
Commercial
6
94
93
93
38 Wyndham Street
Commercial
6
93
92
92
58 Albert Street
Commercial
7
93
92
92
63 Albert Street
Commercial
7
93
92
92
61 Albert Street
Mixed Use (commercial / residential)
6
93
92
92
57 Albert Street
Commercial
6
93
92
92
55 Albert Street
Commercial
6
93
92
92
37-39 Albert Street
Construction Site
6
93
92
92
35 Albert Street
Construction Site
6
93
92
92
52-56 Albert Street
Commercial
7
92
91
91
22-26 Albert Street
Residential
9
92
90
90
8 Albert Street
Mixed Use (commercial / residential)
8
92
91
91
70-74 Albert Street
Mixed Use (commercial / residential)
8
91
90
90
46-50 Albert Street
Commercial
7
91
90
90
Page 8
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Predicted worst case noise levels (no mitigation), dB LAeq
Address
Building Use
Minimum Distance to Works (m)
Utilities Location and exposure
Installation of CFA Piles
Installation of Pile Caps
12-26 Swanson Street
Commercial
7
91
90
90
65-71 Albert Street
District Court
11
89
88
88
34-36 Wyndham Street
Commercial
17
84
83
83
29 Customs Street
Commercial
22
82
81
81
33 Wyndham Street
Commercial
20
81
80
80
76 Albert Street
Residential
26
79
78
78
26 Wyndham Street
Commercial
24
79
78
78
6 Wolfe Street
Vacant
37
78
77
77
9 Wolfe Street
Commercial
29
78
77
77
18 Federal Street
Residential
37
77
76
76
Mitigation
Mitigation is required to meet the noise criteria at the nearest sensitive receivers. The general noise control measures outlined in Section 7 of the CNV DWP will be implemented. Where additional mitigation is required to meet the noise criteria it is detailed in the Albert Street Piling SSCNVMP or the SSCNVMPs for specific receivers. Trench Excavation This is a schedule to the Construction Noise and Vibration DWP for the CRL Contract 2 Enabling Works project. This schedule provides specific assessment of the following activity: Construction Activity
Remove existing road surface
Excavation 1st Layer
Area of works
Activity Start Date
Activity End Date
Hours
South end to Ch550
23 Mar 2017
28 Mar 2017
Ch550 to Swanson
23 Mar 2017
27 Mar 2017
7am – 7pm
Swanson to Wolfe
26 May 2017
30 May 2017
Mon - Sat
Wolfe to North end
03 Jul 2017
05 Jul 2017
South end to Ch550
29 Mar 2017
04 Apr 2017
Ch550 to Swanson
28 Mar 2017
19 Apr 2017
Swanson to Wolfe
31 May 2017
28 Jun 2017
Wolfe to North end
06 Jul 2017
02 Aug 2017
7am – 7pm Mon - Sat
Page 9
Connectus Project #: 2665 Client: Auckland Transport
Construction Activity nd
Excavation 2 to Bottom
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Area of works
Activity Start Date
Activity End Date
Hours
South end to Ch550
21 Apr 2017
01 Sep 2017
Ch550 to Swanson
20 Apr 2017
07 Sep 2017
7am – 7pm
Swanson to Wolfe
29 Jun 2017
05 Dec 2017
Mon - Sat
Wolfe to North end
03 Aug 2017
23 Mar 2018
The activity involves removal of the existing road surface, trench excavation and installation of ground support struts. Two steel temporary construction platforms will be installed at CH350 and CH480. These platforms will be used to provide spoil loading points for the material being excavated from the trench. The platforms will be of a sufficient size to support 10-tonne trucks accessing from Albert St, and an 80T crane operating with a clamshell bucket. Equipment Noise Levels
Works Phase
Equipment
Type of works
Sound pressure level dB LAeq 5m
CEP 311-001 Excavation and Spoil Handling
10m
20m
50m
Crawler crane with clamshell bucket 80t
General works, installing temp works, excavation
81
75
69
61
Excavators 12-20t
Excavation, installing temp works
7684
7078
6472
5664
Front end wheel loader
Spoil handling
86
80
74
66
6-wheel tipper trucks
Spoil handling, spoil cartage
85
79
73
65
Long reach excavator
Excavation
81
75
69
61
Page 10
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Predictions
Predicted worst case noise levels (no mitigation), dB LAeq
Address
Building Use
Minimum Distance to works (m)
9 Albert Street
Mixed Use
5
93
88
84
86
-
88
89
5 Albert Street
Commercial
5
93
88
83
-
-
88
89
3 Albert Street
Commercial
5
93
88
83
85
-
87
88
17 Albert Street
Commercial
5
92
87
83
84
-
86
87
15 Albert Street
Vacant
5
92
87
83
85
-
87
88
13 Albert Street
Vacant
5
92
87
83
85
-
87
88
22 Customs Street
Commercial
5
92
87
83
-
-
-
-
38 Wyndham Street
Commercial
6
90
85
79
83
79
85
86
61 Albert Street
Mixed Use
6
90
85
80
83
-
85
86
57 Albert Street
Commercial
6
90
85
80
83
-
85
86
55 Albert Street
Commercial
6
90
85
81
83
-
85
86
41 Albert Street
Residential
6
90
85
81
83
-
85
86
23-29 Albert Street
Commercial
6
90
85
81
83
-
85
86
58 Albert Street
Commercial
7
89
84
79
84
-
86
87
63 Albert Street
Commercial
7
89
84
79
83
83
85
86
46-50 Albert Street
Commercial
7
89
84
78
82
-
84
85
52-56 Albert Street
Commercial
7
89
84
80
84
-
86
87
12-26 Swanson Street
Commercial
7
89
84
79
82
-
84
85
37-39 Albert Street
Construction Site
6
89
84
79
83
-
85
86
Removal of existing road surface
Excavation of 1st Layer
Excavation of 2nd layer to bottom
Rock fall protection netting
Shotcrete placement
Pre-drilling
Drilling and rock dowel installation
Page 11
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
70-74 Albert Street
Mixed Use
8
88
83
78
80
-
82
83
35 Albert Street
Construction Site
6
88
83
79
81
-
83
84
22-26 Albert Street
Residential
9
88
83
78
80
-
82
83
8 Albert Street
Mixed Use
8
88
83
78
82
-
84
85
65-71 Albert Street
District Court
11
85
80
-
-
76
80
80
34-36 Wyndham Street
Commercial
17
80
-
-
-
-
76
77
33 Wyndham Street
Commercial
20
78
-
-
-
-
-
76
Mitigation
Mitigation is required to meet the noise criteria at the nearest sensitive receivers. The general noise control measures outlined in Section 7 of the CNV DWP will be implemented. Where additional mitigation is required to meet the noise criteria it is detailed in the Excavation SSCNVMP or the SSCNVMPs for specific receivers.
Page 12
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Waterproofing and Tunnel Construction This is a schedule to the Construction Noise and Vibration DWP for the CRL Contract 2 Enabling Works project.This schedule provides specific assessment of the following activity: Construction Activity Tunnel Box Construction
Area of works
Activity Start Date
Activity End Date
South end to Swanson
28 Aug 2017
26 Jan 2018
Swanson to Wolfe
01 Dec 2017
05 Jun 2018
Wolfe to North end
26 Mar 2018
15 Aug 2018
Hours
7am – 7pm Mon - Sat
The activity includes construction of the tunnel which will be a rolling process with multiple work faces progressing together. The works will start at the south end of Albert Street, once the excavation plant is clear of the base of the tunnel and all the TW have been installed and signed off. The tunnel construction will be broken into 12m lengths and into the following tasks:
Base drainage and blinding
Waterproofing
Base foundation construction
Wall construction – side walls and dividing walls poured at the same time.
Roof construction
Roof waterproofing
Equipment Noise Levels
Works Phase
Equipment
Type of works
Sound pressure level dB LAeq 5m
CEP 320-001 Waterproofing and Tunnel Construction
10m
20m
50m
Telehandlers
Moving materials
85
79
73
65
Telescopic Crawler Crane
Moving and placement of materials
77
71
65
57
Crawler crane (surface) est 50t
Material lowering from delivery bay to workface
81
75
69
61
Mobile concrete pump
Concrete placement
86
80
74
66
Static pump and boom
Concrete placement
86
80
74
66
Metal beams*
Steel fixing
88*
82*
76*
68*
Rough terrain scissor lift
Working platforms for wall works
84
78
72
64
Page 13
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Predictions
Predicted worst case noise levels (no mitigation), dB LAeq
Address
Building Use
Minimum Distance to works (m)
22 Customs Street
Commercial
5
88
38 Wyndham Street
Commercial
6
87
58 Albert Street
Commercial
6
86
46-50 Albert Street
Commercial
7
86
52-56 Albert Street
Commercial
6
86
12-26 Swanson Street
Commercial
7
86
8 Albert Street
Mixed Use
7
86
70-74 Albert Street
Mixed Use
7
85
63 Albert Street
Commercial
16
84
22-26 Albert Street
Residential
9
83
17 Albert Street
Commercial
14
79
15 Albert Street
Vacant
15
79
13 Albert Street
Vacant
15
79
9 Albert Street
Mixed Use
14
79
5 Albert Street
Commercial
15
79
61 Albert Street
Mixed Use
16
78
57 Albert Street
Commercial
16
78
55 Albert Street
Commercial
16
78
51 Albert Street
Commercial
16
78
41 Albert Street
Residential
16
78
23-29 Albert Street
Commercial
15
78
3 Albert Street
Commercial
16
78
34-36 Wyndham Street
Commercial
16
77
37-39 Albert Street
Construction Site
16
77
65-71 Albert Street
District Court
18
76
35 Albert Street
Construction Site
16
76
Mitigation Mitigation is required to meet the noise criteria at the nearest sensitive receivers. The general noise control measures outlined in Section 7 of the CNV DWP will be implemented. Where additional mitigation is required to meet the noise criteria it is detailed in the Tunnel Construction SSCNVMP or the SSCNVMPs for specific receivers.
Trench Backfilling This is a schedule to the Construction Noise and Vibration DWP for the CRL Contract 2 Enabling Works project. This schedule provides specific assessment of the following activity: Page 14
Connectus Project #: 2665 Client: Auckland Transport
Construction Activity
Trench Backfill
Road surface reinstatement
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Area of works
Activity Start Date
Activity End Date
South end to Swanson
27 Nov 2017
12 Apr 2018
Swanson to Wolfe
05 Mar 2018
03 Jul 2018
Wolfe to North end
16 Aug 2018
22 Nov 2018
South end to Swanson
13 Apr 2018
09 Jul 2018
Swanson to Wolfe
04 Jul 2018
11 Sep 2018
Wolfe to North end
23 Nov 2018
25 Jan 2019
Hours
7am – 7pm Mon - Sat
7am – 7pm Mon - Sat
The activity involves backfilling the trench once the tunnel construction works have progressed sufficiently to provide a suitable length for the filling operation to be carried out (approximately 50m). The backfilling will then continue to follow the tunnel construction as it progresses. Delivery of the granular backfill material into the trench will be primarily by a conveyor system mounted at ground level (at the top of the trench). Within the trench the fill material will be spread using small to medium sized excavators and bobcat loaders, and compacted in layers using a combination of roller compactors and plate compactors. The two steel temporary construction platforms installed at CH350 and CH480 will be used to provide loading points for the construction works within the trench. Equipment Noise Levels
Works Phase
Equipment
Type of works
Sound pressure level dB LAeq 5m
CEP 316-001 Trench Backfilling
10m
20m
50m
7179
6573
5967
5159
86
80
74
66
Excavators 5-15t
Spreading fill material, removing temp works
Front end wheel loader
Fill handling
Bobcat loader
Fill handling
82
76
70
62
6-wheel tipper trucks
Fill delivery
85
79
73
65
Roller compactors
Compacting fill
85
79
73
65
Plate compactors
Compacting fill in low clearance areas
86
80
74
66
Concrete pump
Pumping flowable fill to site
84
78
72
64
Predictions
Address
Building Use
Minimum Distance to works (m)
9 Albert Street
Mixed Use
5 Albert Street
Predicted worst case noise levels (no mitigation), dB LAeq Trench Backfilling
Road surface reinstatement
5
94
89
Commercial
5
94
89
3 Albert Street
Commercial
5
94
89
17 Albert Street
Commercial
5
93
88
15 Albert Street
Vacant
5
93
88
Page 15
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Address
Building Use
Minimum Distance to works (m)
13 Albert Street
Vacant
22 Customs Street
Predicted worst case noise levels (no mitigation), dB LAeq Trench Backfilling
Road surface reinstatement
5
93
88
Commercial
5
93
88
38 Wyndham Street
Commercial
6
91
86
61 Albert Street
Mixed Use
6
91
86
57 Albert Street
Commercial
6
91
86
55 Albert Street
Commercial
6
91
86
51 Albert Street
Commercial
6
91
86
41 Albert Street
Residential
6
91
86
23-29 Albert Street
Commercial
6
91
86
58 Albert Street
Commercial
7
90
85
63 Albert Street
Commercial
7
90
85
46-50 Albert Street
Commercial
7
90
85
52-56 Albert Street
Commercial
7
90
85
12-26 Swanson Street
Commercial
7
90
85
37-39 Albert Street
Construction Site
6
90
85
70-74 Albert Street
Mixed Use
8
89
84
35 Albert Street
Construction Site
6
89
84
8 Albert Street
Mixed Use
8
89
84
65-71 Albert Street
Residential
9
88
83
22-26 Albert Street
District Court
11
88
83
34-36 Wyndham Street
Commercial
17
81
76
33 Wyndham Street
Commercial
20
79
-
26 Wyndham Street
Commercial
24
77
-
Mitigation
Mitigation is required to meet the noise criteria at the nearest sensitive receivers. The general noise control measures outlined in Section 7 of the CNV DWP will be implemented. Where additional mitigation is required to meet the noise criteria it is detailed in the Trench backfilling and Reinstatement SSCNVMP or the SSCNVMPs for specific receivers.
Page 16
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
APPENDIX D: RECORD OF COMMUNICATION / CONSULTATION WITH NOTABLE AND SENSITIVE RECEIVERS
Page D
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Address of Sensitive Receiver
Representatives
Date
Comment
Resolution
41 Albert Street (Albert Street Apartments)
Interview on site with building manager, Body Corporate Chair, and a further resident representative
9/11/15
1. Some residents are at home during the daytime period so will be affected by day time construction activities. 2. All apartments are naturally ventilated so windows overlooking Albert Street are open in most apartments during the day. 3. Ground floor is commercial and currently vacant but the owner is looking to sell it. 4. Concern about the cumulative effects of noise from the Project and noise from construction on 2 adjacent sites. 5. They would like a SSCNVMP for the building 1. Raised general concerns about noise intrusion into the office areas that would prevent them from working. 2. Raised general concerns about the vibration effects of piling
With the mitigation and management measures detailed in Section 7 of the CNV DWP and Sections 5.1 and 5.2 of the 41 Albert Street SSCNVMP implemented, works may be audible but will not be at a level that disturbs residents.
12-26 Swanson Street (NZ trade Centre)
Interview on site with building owner representatives, and representatives of all major tenants
11/11/15
Vibration may be felt but will not be at a level that damages the building. Further discussions have taken place with the affected residents during week commencing 14th March 2016 to discuss the proposed resolution. With the mitigation and management measures detailed in Section 7 of the CNV DWP and Sections 5.1 and 5.2 of the SSCNVMPs (Albert Street Piling, Excavation, Tunnel Construction and Trench Backfilling) implemented, works may be audible but will not be at a level that interferes with business operations. Vibration may be felt but will not be at a level that damages the building. This resolution was discussed at the meeting on 11th November 2015.
Page 1
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Address of Sensitive Receiver
Representatives
Date
Comment
Resolution
22 Customs Street DFS Galleria
Interview on site with building owner representative, Australasian Operations Manager, and New Zealand Deputy Store Manager
11/11/15
1. Raised general concerns about noise impact on the business 2. Raised concerns about vibration effects on the building
With the mitigation and management measures detailed in Section 7 of the CNV DWP and Sections 5.1 and 5.2 of the SSCNVMPs (Customs Street Intersection, Albert Street Piling, Excavation, Tunnel Construction and Trench Backfilling) implemented, works may be audible but will not be at a level that interferes with business operations.
3. Building owner wants on-site noise and vibration monitoring throughout construction.
Secondary glazing has been specified for some rooms. Vibration may be felt but will not be at a level that damages the building. Section 7 of the SSCNVMPs (Customs Street Intersection, Albert Street Piling, Excavation, Tunnel Construction and Trench Backfilling) provides details of the proposed noise and vibration monitoring.
8a Albert Street CityMed Doctors
Interview with building owners and representatives
11/11/15
1. Activities taking place on site are highly sensitive to vibration, and these include surgery and blood collection. Other activities include: radiology, pharmacy, and physiotherapy.
63 Albert Street (AMI Insurance)
Interview with business operator on site
16/11/15
1. Raised general concerns about noise and vibration impact on their operation.
This resolution has been discussed with the building owner and manager via emails during January and March 2016. During further consultation with the City Med doctors representatives and a site visit it was established that most of the noise and vibration sensitive activities take place in the centre of the building or towards the back so will not be affected by the construction works. With the mitigation and management measures detailed in Section 7 of the CNV DWP and Sections 5.1 and 5.2 of the SSCNVMPs (Customs Street Intersection,
Page 2
Connectus Project #: 2665 Client: Auckland Transport
Address of Sensitive Receiver
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Representatives
Date
Comment
Resolution Albert Street Piling, Excavation, Tunnel Construction and Trench Backfilling) implemented, works may be audible but will not be at a level that interferes with business operations. Vibration may be felt but will not be at a level that damages the building.
22/26 Albert Street Expresso Coffee School
Follow up discussion with business owner and general inspection of faรงade, ventilation etc
17/11/15
1. Noise concerns as door is open all day 2. Noise impact on outside seating area
22/26 Albert Street United Travel
Follow up discussion with business owner and general inspection of faรงade, ventilation etc
17/11/15
1. Concerned about noise impacting their operations. They speak to customers all day in person or on the telephone so need reasonably quiet working environment 2. Noise break-in through the door could be an issue as there is a 1-2cm gap around the perimeter of the door. The landlord is proposing to install some seals to rectify this. 1. Needs a quiet environment for clients 2. Treatment rooms are adjacent to the faรงade overlooking Swanson Street 3. Also concerned about vibration
22/26 Albert Street Thai Massage
60 Albert Street City Gardens Apartments
Follow up discussion with business owner and general inspection of faรงade, ventilation etc
Interview on site with Body Corporate Committee
20/11/15
17/11/15
1. Not too concerned about noise and vibration as they are set back from the street 2. Happy that piling is CFA rather than
This resolution was discussed at the meeting on 16th November 2015. With the barriers installed as specified in Section 7 of the CNV DWP and Section 4 of this SSCNVMP noise from all construction activities will comply with the Project Noise Standards at this receiver. With the barriers installed as specified in Section 7 of the CNV DWP and Section 4 of this SSCNVMP noise from all construction activities will comply with the Project Noise Standards at this receiver. With door seals fitted, as currently proposed by the landlord, construction noise will not be at a level that impacts the business operations of this receiver. With the barriers installed as specified in Section 7 of the CNV DWP and Section 4 of this SSCNVMP noise from all construction activities will comply with the Project Noise Standards at this receiver. Vibration is unlikely to be at perceptible levels in this receiver. Noise and vibration are unlikely to be at perceptible levels in any area of this building from the Albert Street Piling works.
Page 3
Connectus Project #: 2665 Client: Auckland Transport
Address of Sensitive Receiver
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Representatives
Date
Comment
Resolution
driven
23-29 Albert Street ANZ Tower Vero
Interview on site with operations manager
19/11/15
1. No concerns over predicted noise and vibration levels
23-29 Albert Street ANZ Tower Chapman Tripp
Interview on site with operations manager
20/11/15
1. No concerns over predicted noise and vibration levels
20/11/15
1. Doors always open during summer 2. Not too concerned about noise and vibration
Interview on site with operations manager
24/11/15
General inspection of some of the hotel rooms, office area and café with operations and maintenance managers
30/11/15
1. General concerns about noise and vibration and impact on their business. Office space and café on 1st floor, swimming pool on 5th floor, floors 5 to 29 are hotel rooms 1. Hotel rooms – with balcony doors closed the rooms are quiet. Very little traffic noise break-in. All rooms are mechanically ventilated 2. Pool area – glass door with no seals opens onto the balcony overlooking Albert Street. Traffic noise levels are masked by mechanical services noise and noise from patrons using the pool. 3. Conference room on levels 5 does not overlook Albert Street 4. Café – doors open onto balcony where there is a seating area. 1-2cm gap around the perimeter of the doors when
17d Albert Street 7 Mart 8a Albert Street Sebel Hotel
Interview on site with business owner
Noise and vibration due to the Project are unlikely to be at perceptible levels in the area of this building occupied by Vero. This th was discussed during the meeting on 19 November 2015. Noise and vibration due to the Project are unlikely to be at perceptible levels in the area of this building occupied by Chapman Tripp. This was discussed during the meeting on 20th November 2015. No comments to incorporate as owner has no noise or vibration concerns. With the mitigation and management measures detailed in Section 7 of the CNV DWP and Sections 5.1 and 5.2 of the SSCNVMPs (Customs Street Intersection, Albert Street Piling, Excavation, Tunnel Construction and Trench Backfilling) implemented, works will be audible but will generally not be at a level that interferes with business operations or disturbs guests. In the SSCNVMPs recommendations have been made to provide acoustic seals to the reception and café doors facing onto Albert Street. Further consultation will take place with the affected parties before works begin to determine if the works can be scheduled for a time that least impacts them.
Page 4
Connectus Project #: 2665 Client: Auckland Transport
Address of Sensitive Receiver
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Representatives
Date
1/12/15
17a Albert Street iDarts
Interview on site with Body Corporate Committee Interview on site with business owner
9-11 Albert Street Food Alley
Interview on site with operations manager
1/12/15
3 Albert Street Bakery
Interview with owner
4/12/15
30/11/15
Comment
Resolution
closed. Doors sometimes left open depending on the weather. Music is played reasonably loudly and masks traffic noise. 5. Office areas – Single glazing. No door or window openings in the façade. 6. Reception – glass doors with 1-2cm gap around the perimeter. Ventilation noise quite loud and music playing. Traffic noise is barely audible. 1. General concerns about noise and vibration impacts
Vibration may be felt but will not be at a level that damages the building.
1. Operates between 3pm and 2am 2. Not concerned about noise and vibration. The bar area is towards the back of the building. They play music quite loud so construction noise is likely to be inaudible. 1. General concerns about noise and vibration. 2. Doors are automated but they open frequently and are sometimes left permanently open during the summer months. 3. There is a reasonable amount of background noise from cooking and other operations within the space. Traffic noise is barely audible. 4. 16 residential apartments on floors 6 and 7 which are all naturally ventilated.
No comments to incorporate as owner has no noise or vibration concerns.
1. Not concerned about noise and vibration 2. Doors open all day so already exposed to high levels of traffic noise.
Section 7 of the SSCNVMPs (Customs Street Intersection, Albert Street Piling, Excavation, Tunnel Construction and Trench Backfilling) provides details of the proposed noise and vibration monitoring.
With the mitigation and management measures detailed in Section 7 of the CNV DWP and Sections 5.1 and 5.2 of the SSCNVMPs (Customs Street Intersection, Albert Street Piling, Excavation, Tunnel Construction and Trench Backfilling) implemented, works will be audible but will generally not be at a level that interferes with business operations or disturbs the residents. Vibration may be felt but will not be at a level that damages the building. This resolution was discussed during the meeting on 1st December 2015. No comments to incorporate as owner has no noise or vibration concerns.
Page 5
Connectus Project #: 2665 Client: Auckland Transport
Address of Sensitive Receiver
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Representatives
Date
Comment
3. 17 Albert Street Kerry Harding, Chair of the Body Corporate, Floor 5 Stephen Ingram, Floor 8 Inna Benitez, Floor 4 Catherine Ellman, Floor 11 Chris Laycock, Building Manager Ashley Bottles, Level 7 Victoria Toon, level 12 Phil Bussant, from Quay West who operates car parks to level 17 David Haines, from Haines Planning
Interview at CRL project offices with the building manager, body corporate chair and tenants representatives
23 – 29 Albert Street ANZ Tower ANZ
Interview on site with the facilities lead, senior support services representative and senior work place manager
7/12/15
1. 2. 3.
4.
Particularly heavy vehicles pulling away from the traffic lights. Radio playing loudly so it can be heard over the traffic noise. Mostly offices with a few residential apartments Particular concerns regarding vibration. Already experiencing rattling windows and building vibration from nearby construction works. Building is mechanically ventilated during business hours
Resolution
With the mitigation and management measures detailed in Section 7 of the CNV DWP and Sections 5.1 and 5.2 of the SSCNVMPs (Customs Street Intersection, Albert Street Piling, Excavation, Tunnel Construction and Trench Backfilling) implemented, works will be audible but will not be at a level that interferes with business operations or disturbs the residents. In the SSCNVMPs recommendations have been made to inspect the window seals and replace as necessary. Secondary glazing is also recommended for the Language School classrooms overlooking Albert Street. The recommendations will help mitigate airborne noise ingress and should also help prevent the windows from rattling.
Vibration may be felt but will not be at a level that damages the building. 8/12/15
1. They occupy the building from the ground floor to floor 31 2. They work from 8am to 6pm with some late functions and VIP events 3. Mostly concerned about noise impact on the ground floor Pavilion Meeting Suites, the café area and the ground floor reception 4. Noise break in through the revolving
With the mitigation and management measures detailed in Section 7 of the CNV DWP and Sections 5.1 and 5.2 of the SSCNVMPs (Customs Street Intersection, Albert Street Piling, Excavation, Tunnel Construction and Trench Backfilling) implemented, works may be audible in the lower levels of the building but will not be at a level that interferes with business
Page 6
Connectus Project #: 2665 Client: Auckland Transport
Address of Sensitive Receiver
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Representatives
Date
Comment
Resolution
doors a concern 5. If they have an important meeting they would like to inform Connectus so that noisy works can be scheduled outside of this time.
operations. The only exception is the ground floor reception / café area where high noise levels may be experienced when works are directly outside of the building. Vibration may be felt but will not be at a level that damages the building. Further consultation has taken place with th this receiver on 4 March 2016 to discuss the potential noise levels in the ground floor area. The café operator took part in the discussion. Noise measurements were taken simultaneously on both sides of the revolving doors. Noise break-in through the doors was found to be less than predicted. Both ANZ and the café owner are willing to accept noise levels of up to 65 dB LAeq for short durations providing that they are well informed of the works.
29 Customs Street AMP Building Kindercare
Interview on site with the property manager
8/12/15
1. They occupy the ground floor of the AMP building 2. Operating from 7am until 6pm 3. External playground adjacent to Customs Street 4. Babies area is closest to the works and they sleep for longer so impact on them
The café owner would appreciate it if noisy works immediately outside of the building stopped during the lunch time period as that is the busiest time for them. ANZ will inform Connectus of any special functions that they may have in the ground floor area and would appreciate it if noisy works could be avoided at these times. Vibration from construction activities associated with the Customs Street intersection works will not be at a level that interferes with business operations and or disturbs the children. Noise from construction activities associated
Page 7
Connectus Project #: 2665 Client: Auckland Transport
Address of Sensitive Receiver
5 Albert Street NZ Gifts
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Representatives
Interview on site with the business owner
Date
10/12/15
Comment
Resolution
is the main concern 5. Buildings mechanically ventilated but door is open for access to the playground area all day. 6. Although exposed to high traffic noise levels they don’t find it intrusive
with the Customs Street intersection works will generally be lower than the current traffic noise levels experienced by the child care facility. In sleeping areas the noise level due to construction activities will be 35 dB LAeq or below.
1. Building is mechanically ventilated. They have automatic doors which are not kept open. Background music playing at a low volume 2. Operational hours are 9.30am to 9.30pm 3. General noise concerns 4. Concerned about vibration rattling items on the shelves
This resolution was discussed during the meeting on 8th December 2015. With the mitigation and management measures detailed in Section 7 of the CNV DWP and Sections 5.1 and 5.2 of the SSCNVMPs (Customs Street Intersection, Albert Street Piling, Excavation, Tunnel Construction and Trench Backfilling) implemented, works may be audible but will generally not be at a level that interferes with business operations. Vibration may be felt but will not be at a level that damages the building.
74 Albert Street Barclay Suites
Interview on site with the general manager
11/12/15
1. Hotel is mechanically ventilated. Front doors leading into the reception are good and reasonably loud background music is playing so traffic noise is not audible. 2. Rooms have sliding doors opening onto balconies and windows are single glazed laminate. 3. Not too concerned about noise and vibration as long as communication is good
This resolution was discussed during the meeting on 10th December 2015. Section 9.1 of the Project CNV DWP details the communication procedures that will be implemented on the Project.
Page 8
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Address of Sensitive Receiver
Representatives
Date
Comment
Resolution
65-71 Albert Street District Court
Interview on site with the Auckland Programme Manager
16/12/15
1. The courts generally operate from 8am to 5pm 2. Courts on level 2 and above. They use electronic transcription and the microphones are extremely sensitive to noise and vibration so low background noise levels are required. 3. All windows are single glazed and the building is mechanically ventilated 4. Layout drawings for each floor were provided so we can see the location of all noise sensitive areas
Secondary glazing is recommended for the second and third floor court rooms on the Albert Street faรงade. Scheduling of construction activities is of particular importance at this location to avoid adverse noise and vibration impacts. With the mitigation and management measures detailed in Section 7 of the CNV DWP and Sections 5.1 and 5.2 of the District Court SSCNVMP implemented, works may be audible but will not be at a level that interferes with the courts operations. Discussions with the District Court are ongoing with regard to the mitigation and management measures.
38 Wyndham Street Hollywood Bakery
Interview on site with the manager
16/12/15
8a Albert Street CityMed Doctors
Interview on site with doctors representatives
22/12/15
1. Operating hours are 6.30am -4.30pm 2. Front doors are permanently open onto Wyndham Street. Traffic noise quite loud especially when vehicles pull away from the traffic lights. Low level background noise music 3. They have some external seating on Albert Street. 4. The bakery sits mostly below the level of Albert Street. 1. Operating hours are from 8am to 5.30pm Monday to Friday 2. Doctor consultation rooms run along the Mills Lane faรงade of the building. The faรงade is fully glazed. All rooms are mechanically ventilated. 3. The 2 operating theatres are at the
No comments to incorporate as no noise or vibration concerns were raised.
The noise and vibration sensive areas of the building are generally located in the centre of the building or at the back away from the Albert Street faรงade. With the mitigation and management measures detailed in Section 7 of the CNV DWP and Sections 5.1 and 5.2 of the
Page 9
Connectus Project #: 2665 Client: Auckland Transport
Address of Sensitive Receiver
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Representatives
Date
Comment
Resolution
back of the building near the car park ramp, furthest from Albert Street. They perform minor operations under local anaesthetic. 4. The radiology area is on the Mills Lane faรงade in the corner furthest from Albert Street.
SSCNVMPs (Customs Street Intersection, Albert Street Piling, Excavation, Tunnel Construction and Trench Backfilling) implemented, works may be audible but will generally not be at a level that interferes with business operations.
5. The radiology operators have no concerns over noise or vibration 6. ECG and audiometry sit within the building away from the faรงades. These are the activities that are most sensitive to noise and vibration. 7. To get to the reception you currently go through the front doors then through another set of doors. However, they are renovating in the New Year and the reception area will be moved closer to the Albert Street faรงade and will be accessed through the front doors. 8. The front doors are glass sliding doors with a large gap at the bottom and no seals.
Vibration may be felt but will not be at a level that damages the building. This resolution was discussed during the nd meeting on 22 December 2015.
Page 10
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
APPENDIX E: RECORD OF CLG & INDEPENDENT PEER REVIEW COMMENTS
Page E
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
CLG COMMENTS Comment Date ID
Time
Forum
Commenter Comment
Resolution
1
13/10/2015
1730-1900
CLG Meeting
Tim Coffey
The plan doesn't identify how noise complaints made to Auckland Council will be directed to the project and managed in a timely fashion. The concern is that many people will follow a traditional course of action and phone AC with noise complaints instead of contacting the CRL project directly.
The CRL Project team work closely with Auckland Council and will provide the CRL contact details to the AC Noise Complaints Team. Section 9 of the CNV DWP will have the following text added: "Connectus will ensure Auckland Council's Noise Complaints Team are provided with contact details for the CRL complaints team to ensure CRL related noise complaints received by AC are passed on quickly"
2
13/10/2015
1730-1900
CLG Meeting
Tim Coffey
This opportunity is being investigated by Connectus. It is more relevant to the Communications plan than the CNV DWP. No change is proposed to the CNV DWP
3
13/10/2015
1730-1900
CLG Meeting
Tim Coffey
Will people contacting the CRL project to make complaints be issued with a 'complaint reference number' or similar to make it easy to complain again about the same issue? Traffic noise - There is concern that traffic going over bumps or causing temporary pavement components to move will generate noise. This should be addressed in the plan.
The CNV DWP will be modified to address this issue. A new subsection (Section 7.8) will be added to the plan. Mitigation measures will include securing loose manhole covers and traffic decks to avoid movement where practicable, or to reduce noise/movement via the inclusion of rubber pads where practicable. In addition, efforts will be made to avoid bumps in the road surface which could lead to tyre noise.
Page 1
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
INDEPENDENT PEER REVIEW – CNV DWP Peer Reviewer: Dr Stephen Chiles Date: 10th November 2015 and 3rd March 20162 Commenter
Date
Forum
CNV DWP Section
Comment
Recommendations
Dr Stephen Chiles
10/11/15
Independent Peer Review
1
The high level split of content between the CEMP, CNV DWP and other DWPs is not clear in the introduction (e.g. communications and complaints procedures are detailed in other parts of the CEMP)
Add a brief summary to section 1 setting out those aspects of construction noise and vibration management which are detailed outside the CNV DWP.
Dr Stephen Chiles
10/11/15
Independent Peer Review
1.1
The CNV DWP is subject to prescriptive review and approval conditions. The process needs to be recorded in the CNV DWP or at least referenced to the relevant place in the CEMP.
Expand the second paragraph of 1.1 to make explicit reference to the processes set out in conditions 22 and 23 (which may limit the extent this can effectively be a living document).
The comment that the CNVMP is a living document is in accordance with good practice, but this is constrained in this instance by the prescriptive conditions. The timeframes needed for review and approval prevent timely updating of some information so alternative methods may be required. Dr Stephen Chiles
2
10/11/15
Independent Peer Review
3
Resolution Summary added to Section 1
Section 1.1 expanded to include the additional information
If it is intended that schedules in the Appendix will be updated without review/approval that should be explicitly stated.
Details or explanation of induction forms and ‘relevant schedules’ should be added.
Details added as requested and an example of an induction form has been included in Appendix F
A second peer review was undertaken on 03/03/16 in conjunction with the SSCVMP’s and also due the inclusion of utilities and an updated traffic deck methodology.
Page 2
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Commenter
Date
Forum
Dr Stephen Chiles
10/11/15
Independent Peer Review
CNV DWP Section
Comment
Recommendations
5.1
The second paragraph references updated information being included in Appendix C, but that provides data in a different format.
The process should either be for Table 5 to be updated directly or a duplicate table should be set out in an appendix. Ideally Table 5 would be updated. Any required reviews/approvals associated with updating the information should be set out in the CNV DWP.
Technically it is not necessary for updates to equipment data to be reviewed or approved. However, this might be required under the conditions. Dr Stephen Chiles
10/11/15
Independent Peer Review
5.1
Mains power should be used as good practice noise and vibration management. Generators are included in the equipment list but this contradicts section 7.4 which lists use of mains power as a mitigation measure in section.
Clarify to what extent mains power will be used, and if so remove generators from the equipment list.
Dr Stephen Chiles
10/11/15
Independent Peer Review
5.1
Condition 36.3(d) requires identification of construction areas
It should be clarified that most works phases set out in tables 5 and 6 will occur throughout the construction area.
Dr Stephen Chiles
10/11/15
Independent Peer Review
5.1.1
Table 7 indicates that all construction activities would be likely to exceed the noise limits without mitigation.
Add note that all activities are likely to require mitigation.
Dr Stephen Chiles
10/11/15
Independent Peer Review
5.2
Reference is made to Table 8 being updated but no details are provided as to how this will occur.
As for updates to Table 5, there should be a process set out for updates to Table 8. Reference should be made to Appendix B.
Resolution Appendix C has been update to include Tables in the same format as Table 5
Clarification has been added.
Clarification has been added.
Note added
Further information has been added as requested.
Page 3
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Commenter
Date
Forum
Dr Stephen Chiles
10/11/15
Independent Peer Review
5.2
Vibration sources should be related to works phases (as has occurred for noise sources).
Dr Stephen Chiles
10/11/15
Independent Peer Review
6.1
Add building addresses to Figure 8
Dr Stephen Chiles Dr Stephen Chiles
10/11/15
Independent Peer Review Independent Peer Review
6.2
Add building addresses to Figure 9
Dr Stephen Chiles
10/11/15
Independent Peer Review
7.2
Add requirement for training to include familiarisation with noise and vibration limits and resulting effects on neighbours.
Dr Stephen Chiles
10/11/15
Independent Peer Review
7.4
Broadband reversing alarms should be used for all mobile equipment.
Dr Stephen Chiles
10/11/15
Independent Peer Review
7.7
Show where noise barriers will be located on plans and specify their construction details.
10/11/15
CNV DWP Section
7
Comment
Scheduling of activities can be a key tool for managing construction noise and vibration effects. This might include respite periods during the day and avoidance of activity on certain days, as well as limiting night works. Given that many neighbours are commercial, in some specific locations night works might be preferable.
Recommendations
Add a subsection on how scheduling may be used to mitigate noise and vibration effects.
Resolution Table containing vibration sources now relates to work phases
Addresses added Addresses added Subsection added
Added information as requested
Added information as requested
Figure showing noise barriers has been added. Further details regarding barrier construction and enclosures has been added
Provide details of relocatable noise barriers and enclosures that will be kept on site.
Page 4
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Commenter
Date
Forum
CNV DWP Section
Comment
Recommendations
Dr Stephen Chiles
10/11/15
Independent Peer Review
8
Dr Stephen Chiles
10/11/15
Independent Peer Review
8
The conditions allow for combined SSCVMPs and SSCNMPs as SSCNVMPs. For specific locations identified in both 8.1 and 8.2 it would be preferable to use combined SSCNVMPs.
Add a subsection noting that some site specific plans may cover both noise and vibration.
Dr Stephen Chiles
10/11/15
Independent Peer Review
10
Statements are made about how equipment data will be updated following measurements but no timeframes are set.
It should be specified that all equipment (predicted to exceed a certain noise level) will be measured off site, prior to operation on site where practicable, and when first operating on site if this is not practicable. The equipment tables/schedules should be updated within one week of the measurements.
Dr Stephen Chiles
10/11/15
Independent Peer Review
10
Noise and vibration monitoring locations are only loosely defined as including all receivers, although routine monitoring is at unspecified representative positions. It would be better to mark specific monitoring locations to be used on a plan. Additional locations could be used in response to specific complaints or activities, but the use of standardised positions will assist in monitoring through the duration of the works.
Add figures showing standard noise and vibration monitoring positions that will be used (not simply all receivers).
Dr Stephen Chiles
10/11/15
Independent Peer Review
10
Add a list of all SSCNVMPs/SSCNMPs/SSCVMPs.
Add details of noise and vibration monitoring equipment and where it will be stored during the works.
Resolution List added
Subsection added
Information added as requested
Figures added
Equipment details added
Page 5
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Commenter
Date
Forum
CNV DWP Section
Comment
10.1
Consideration could be given to use of continuous noise monitoring stations with remote access and alarms.
Dr Stephen Chiles
10/11/15
Independent Peer Review
Dr Stephen Chiles
10/11/15
Independent Peer Review
Dr Stephen Chiles
03/03/16
Independent Peer Review
2.2
Any road cutting outside the hours of 7am to 7pm would breach condition 36.3(b)
Dr Stephen Chiles
03/03/16
Independent Peer Review
7.7
Most receivers are multi-storey buildings which will not receive screening from a 1.8m high barrier.
Dr Stephen Chiles
03/03/16
Independent Peer Review
8.3
Dr Stephen Chiles
03/03/16
Independent Peer Review
10.1
Monitoring positions should be representative of floors of buildings that are not screened by the perimeter barrier.
Specify the height for the monitoring positions in Figure 11 to be at first floor level.
Dr Stephen Chiles
03/03/16
Independent Peer Review
Appendices B &C
Due to the quantity of information, the linear presentation is hard to navigate.
Condense the tables of predictions and ‘at risk’ receivers into matrices of results to allow quicker reference to key information.
Dr Stephen Chiles
03/03/16
Independent Peer Review
Appendices B &C
Tables in Appendices B & C are duplicated in SSCNVMPs. It is likely to lead to inconsistencies if information is maintained in two separate documents.
Use cross references between the CNV DWP and SSCNVMPs to avoid duplicate tables appearing in both.
Appendices B &C
Recommendations
Resolution Continuous noise and vibration monitoring stations will be set up at Stamford Plaza
Add details on timing of activities.
Timing details added Road cutting will not occur outside of these hours
Investigate higher perimeter barriers, in addition to localised screening of specific activities.
Add a table of document reference numbers, versions and dates for all SSCNVMPs
2m high noise barriers have been considered and they provide less than 1 dB of additional attenuation at the receivers. Connectus have indicated that going higher than this will be problematic due to space restrictions. Taller barriers will require greater structural support and there is no space for this. Added
Added
Amended as requested
Cross references added
Page 6
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Commenter
Date
Forum
Dr Stephen Chiles
03/03/16
Independent Peer Review
CNV DWP Section
Comment
Recommendations
Appendix D
In several cases the “resolution” to concerns raised by stakeholders is that no action is required as noise and vibration levels will be reasonable. It is not clear whether this outcome has been explained to the stakeholders who raised the concerns.
Record when the resolution was discussed with the stakeholder.
Comment
Recommendations
Resolution Dates of these discussions added
INDEPENDENT PEER REVIEW – SSCNVMP Peer Reviewer: Dr Stephen Chiles rd
Date: 3 March 2016 Commenter
Date
Forum
Dr Stephen Chiles
03/03/16
Independent Peer Review
Dr Stephen Chiles
03/03/16
Independent Peer Review
Dr Stephen Chiles
03/03/16
Independent Peer Review
Dr Stephen Chiles
03/03/16
Independent Peer Review
SSCNVMP all/multiple SSCNVMPs
Delete glossary and cross reference the CNV DWP.
Resolution Deleted as requested
Glossary all/multiple SSCNVMPs
Add the document reference number, version and date for the CNV DWP
Added as requested
Section 1 all/multiple SSCNVMPs Section 2 all/multiple SSCNVMPs Sections 3 and 4 Dr Stephen Chiles
03/03/16
Independent Peer Review
all/multiple SSCNVMPs Section 5
Conditions 38.4 and 38.5(c) set out how specific vibration criteria should be determined.
Add assessment of vibration affected buildings and specific criteria adopted.
Tables in SSCNVMPs are duplicated in Appendices B & C of the CNV DWP. It is likely to lead to inconsistencies if information is maintained in two separate documents.
Use cross references between the CNV DWP and SSCNVMPs to avoid duplicate tables appearing in both.
Before detailing mitigation, it is necessary to set out the specific effects that are being mitigated. In some cases this is partly addressed
Add details of specific effects on receivers that might result from exceedances of the noise and vibration criteria.
Added
Cross references added
Effects added
Page 7
Connectus Project #: 2665 Client: Auckland Transport
Commenter
Date
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Forum
SSCNVMP
Comment
Recommendations
Resolution
when discussing internal levels but it does not always explicitly set out residual noise and vibration effects. Dr Stephen Chiles
03/03/16
Independent Peer Review
all/multiple SSCNVMPs
Various mitigation measures are listed as “if possible�. The SSCNVMPs should detail specific mitigation that will be implemented and not general good practice measures that are already in the CNV DWP.
Update the mitigation tables to list specific measures that will be implemented.
Section 5.1
Major sound sources in many of the SSCNVMPs are mobile machinery, which can often be attenuated with additional exhaust silencers.
Determine whether it is practical to fit additional exhaust silencers to equipment and, if so, add this as an action to the list of noise control measures.
all/multiple SSCNVMPs
There are recommendations relating to treating buildings but no actions.
There should be actions set out for all building treatment required.
The same treatment for the same buildings is recommended in several SSCNVMPs. There needs to be a single place where the treatment for each building is documented.
Only include details of treatment for each building in one SSCNVMP and then cross reference from other SSCNVMPs where relevant.
Section 5
Dr Stephen Chiles
03/03/16
Independent Peer Review
Dr Stephen Chiles
03/03/16
Independent Peer Review
Dr Stephen Chiles
03/03/16
Independent Peer Review
all/multiple SSCNVMPs
Tables updated
Connectus considers that it is not practical to fit additional exhaust silencers to equipment as it causes other problems such as decreasing engine efficiency, increase fuel burn and void warranties. Connectus will require that all machinery brought to site has exhaust silencers fitted that are free from rust holes and function as intended. Actions added
Section 5.1 all/multiple SSCNVMPs Section 5.1 Dr Stephen Chiles
03/03/16
Independent Peer Review
all/multiple SSCNVMPs
Specify that for secondary glazing the existing window must be sealed before installing the secondary window.
Section 5.1 Dr Stephen Chiles
03/03/16
Independent Peer Review
all/multiple SSCNVMPs Section 6
The table of stakeholder consultation duplicates information in Appendix D of the CNV DWP and in other SSCNVMPs.
Remove the table of stakeholder communication from the SSCNVMPs and replaced with cross references to the relevant lines of Appendix D of the CNV DWP, together with a brief summary of actions arising.
Cross references added
Added
Table removed and cross references added
Page 8
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Commenter
Date
Forum
Dr Stephen Chiles
03/03/16
Independent Peer Review
Dr Stephen Chiles
03/03/16
Independent Peer Review
Dr Stephen Chiles
03/03/16
Independent Peer Review
Dr Stephen Chiles
03/03/16
Independent Peer Review
Dr Stephen Chiles
03/03/16
Independent Peer Review
SSCNVMP
Comment
all/multiple SSCNVMPs
Recommendations Specify that monitoring is at first floor level (unless a specific location at a higher level is specified.
Section 7.1 Customs Street Intersection
Control of compactor vibration should include consideration of the frequency as well as mass.
Resolution Added
Added
Section 5.2 Customs Street Intersection
Cross reference building condition surveys required by the CNV DWP.
Cross reference added
Section 5.2 Customs Street Intersection Section 6 Customs Street Intersection Section 6
Dr Stephen Chiles
03/03/16
Independent Peer Review
Dr Stephen Chiles
03/03/16
Independent Peer Review
An issue raised with the 8a Albert Street CityMed Doctors front door and reception relocation has not been addressed.
Improved sound insulation of the reception area should be investigated with CityMed Doctors.
Equating construction noise to existing traffic noise at the Kindercare facility at 29 Albert Street might understate the potential effects due to the different character of the sound. Potential mitigation, if required, might involve scheduling.
Add more detail on the effects of construction noise on children sleeping.
Trench Backfilling
Control of compactor vibration should include consideration of the frequency as well as mass.
Section 5.2 41 Albert Street Section 5.2 Dr Stephen Chiles
03/03/16
Independent Peer Review
41 Albert Street Section 5.3
Ventilation meeting G4 of the Building Code is not sufficient to prevent residents having to open windows.
Specify that ventilation systems installed will with the requirements in the Transport Agency State highway guide to acoustic treatment of buildings. Add reference to CNV DWP relating to building condition surveys, and the process for these being repeated
This was discussed with CityMed. We have offered to review their design once they have it in place and advise on sound insulation improvements where necessary. Added
Added
Added
Added
Page 9
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
APPENDIX F: CONSTRUCTION NOISE AND VIBRATION INDUCTION
Page F
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Project: CRL Contract 2 Enabling Works 1. There are numerous residential and commercial neighbours in close proximity to the works, where noise and vibration limits apply. To ensure limits are achieved, all staff are responsible for good noise and vibration management. 2. When arriving at work, please drive slowly on site and keep revs to a minimum. Keep stereos off and do not slam doors. 3. No shouting or swearing on site. Either walk over and talk to somebody or use a radio/phone. 4. Be careful with tools and equipment. Place them down and do not drop them. 5. Do not drag materials on the ground. Place them down when you arrive at the work area. 6. Equipment and vehicles should not be left running when not in use. 7. When loading trucks try not to drop material from a height. Load softer material at the bottom. 8. Noise enclosures should always have all doors/hatches closed when the equipment is in use. 9. All equipment is to be well maintained. 10. No work shall be conducted outside the hours of 0700h to 2200h without specific approval (contact the site manager) and all staff involved in the task have read and signed the Construction Noise Management Schedule for that task. 11. All staff will read and sign the Construction Noise Management Schedule for a particular task. 12. If you see anything/anyone making unnecessary noise or vibration then stop it/them. If the source cannot be stopped then report it to the site manager. 13. It is essential that good relationships are maintained with the local community. Any queries from members of the public should be responded to politely and referred to the site manager or Communication and Consultation Manager. Staff shall assist the public to make contact with this person. Staff shall not enter into debate or argue with members of the public.
Page 1
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
APPENDIX G: NOISE MONITORING TEMPLATE
Page G
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Date: _ _ / _ _ / 20 _ _ Equipment set used
Operator: Model:
Serial No. :
Date of last calibration: _ _ / _ _ / 20 _ _
MEASUREMENT DESCRIPTION Machinery / operational noise (Not at a receiver)
Noise at a receiver location
Construction location:
Receiver address:
Distance to machinery / operation:
(m)
Distance to receiver:
(m)
Describe noise sources (e.g. roller, piling, generator) and the location relative to the receiver:
Describe any other unrelated noises (e.g. traffic noise) and the location relative to the receiver:
Describe any reflecting surfaces (e.g. walls, buildings) and the location relative to the receiver:
Describe any other factors such as barriers/terrain, or relative elevations of sources and receivers:
It is useful to attach an aerial photograph where possible. If this is done include the following details: Location of site activity
Measurement Locations
Location of reflecting surfaces
Relative heights
Locations of unrelated sources
Intervening barriers/terrain
It is also useful to include photographs or diagrams of the measurement location, the major sound sources, and any other details you believe may be useful. Additional documents attached
Page 1
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
MEASUREMENT DETAILS
Location reference
Time
Measurement duration, t
LAeq(t)
LAFmax
Adjustment for façade reflection
Equipment operating on site
Sounds heard at measurement location (note dominant and LAFmax sounds) Construction equipment
Other sources
Compliance achieved (y/n)
____h Constant noise Cyclic noise
__:__ _ _ . _ dB
_ _ . _ dB
_ _ . _ dB
_ _ . _ dB
_ _ . _ dB
_ _ . _ dB
_ _ . _ dB
_ _ . _ dB
min:sec
____h Constant noise Cyclic noise
__:__ min:sec
____h Constant noise Cyclic noise
__:__ min:sec
____h Constant noise Cyclic noise
__:__ min:sec
NOTES Please include any issues that were encountered during the measurements or other factors that may influence the validity of this measurement. FURTHER ACTIONS Update the noise schedules in Appendix C of this CNV DWP to reflect the measured noise levels. Update the SSCNVMPs that are applicable to the specific construction activities that were taking place during the monitoring with the measurement results.
Page 2
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
APPENDIX H: VIBRATION MONITORING TEMPLATE
Page H
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
Date: _ _ / _ _ / 20 _ _ Equipment set used
Operator: Model:
Serial No. :
Date of last calibration: _ _ / _ _ / 20 _ _
MEASUREMENT DESCRIPTION Machinery / operational vibration (Not at a receiver)
Vibration at a receiver location
Construction location:
Receiver address:
Distance to machinery / operation:
(m)
Horizontal Distance to receiver:
(m)
Floor Number: Describe vibration sources (e.g. roller, piling, concrete breaking) and the location relative to the receiver:
Describe any other unrelated vibration (e.g. traffic, other construction, footfall, lifts) and the location relative to the receiver:
Describe geometry of foundation (e.g. walls, buildings) and the location relative to the receiver:
Describe the coupling method (geophone to structure)
Describe approximate composition of ground between source and receiver (e.g. basalt, sandstone)
Describe structural resonance observed, if any. For example swaying at higher floors – note the approximate frequency and magnitude.
It is useful to attach an aerial photograph where possible. If this is done include the following details: Location of site activity
Measurement Locations
Location of intervening geometry
Relative heights
Locations of unrelated sources
Changes in composition of terrain
It is also useful to include photographs or diagrams of the measurement location including building plans where available, the major vibration sources, and any other details you believe may be useful. It is important to note whether the measurement was at the foundation, or in the plane of the highest floor. Additional documents attached
Page 1
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
MEASUREMENT DETAILS
Location reference
Time
Measurement PPV duration, t
Dominant axis of movement
Dominant frequency, Hz
Equipment operating on site
Vibrations observed at measurement location
Compliance achieved (y/n)
Construction equipment
Other sources
____h Continuous Transient
__:__ min:sec
__._ mms-1
____h Continuous Transient
__:__ min:sec
__._ mms-1
____h Continuous Transient
__:__ min:sec
__._ mms-1
____h Continuous Transient
__:__ min:sec
__._ mms-1
Page 2
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
NOTES Please include any issues that were encountered during the measurements or other factors that may influence the validity of this measurement. FURTHER ACTIONS Update the vibration schedules in Appendix B of this CNV DWP to reflect the measured vibration levels.
Page 3
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 06, Date: 3 June 2016
APPENDIX I: SITE SPECIFIC CONSTRUCTION NOISE AND VIBRATION MANAGEMENT PLANS
Page I
Auckland City Rail Link In association with:
ENABLING WORKS CONTRACT 2 SITE SPECIFIC CONSTRUCTION NOISE AND VIBRATION MANAGEMENT PLAN: CUSTOMS STREET INTERSECTION Separable Portion 1 – Cut and Cover Works Document Ref: CRL-PAT-ENV-CON-PLN-001182 Revision: 04
FINAL 3rd June 2016
COMMERCIAL IN CONFIDENCE
This page intentionally left blank.
DOCUMENT INFORMATION Organisation:
Connectus
Document Title:
Site Specific Construction Noise and Vibration Management Plan: Customs Street Intersection
Fulcrum Document Number:
CRL-PAT-ENV-CON-PLN-001182
Document based on MMS No:
n/a
Client:
Auckland Transport
Project:
CRL Enabling Works: Contract Two
Location:
Auckland CBD
Project No:
2665
REVISION HISTORY Rev 01
Date 26/01/2016
Details st
nd
1
Author
Approver
Draft for Peer Review
C. Drewery
C Hind
Draft for Peer Review
C. Drewery
C Hind
02
22/02/2016
2
03
21/03/2016
Final
C. Drewery
C Hind
04
3/06/2016
Final
C. Drewery
C Hind
This document remains the property of Connectus. Its contents are confidential and shall not be reproduced, destroyed or given away without the express, written permission of Connects. The electronic version of this document in MMS Database on designated server(s) is the Master Copy and is a controlled document. Unless specifically noted thereon, other copies of this document are uncontrolled.
This page intentionally left blank
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001182 Revision: 04, Date: 3 June 2016
Table of Contents Document information .........................................................................................................................3 Revision History ..................................................................................................................................3 1
Introduction........................................................................................................................7 1.1
Objective
7
1.2
Site plan
7
2
Receivers ..........................................................................................................................8
3
Activities ............................................................................................................................9
4
Predicted Noise and Vibration levels ................................................................................ 10 4.1
Noise
10
4.2
Vibration
11
5
Mitigation ......................................................................................................................... 12 5.1
Noise
12
5.2
Vibration
14
6
Communication and Consultation..................................................................................... 14
7
Monitoring ....................................................................................................................... 15
8
7.1
Noise monitoring
15
7.2
Vibration monitoring
15
Staff................................................................................................................................. 15
Page 5
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001182 Revision: 04, Date: 3 June 2016
This page intentionally left blank
Page 6
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001182 Revision: 04, Date: 3 June 2016
1 INTRODUCTION This plan is a Site Specific Construction Noise and Vibration Management Plan (SSCNVMP) and forms part of the Construction Noise and Vibration Delivery Work Plan (CNV DWP) for the CRL Contract 2 Enabling Works (the ‘Project’). This SSCVNMP provides specific assessment of construction noise and vibration effects from the Customs Street Intersection component of the Project. The SSCNVMP should be read in conjunction with the CNV DWP, Document Ref: CRL-PATENV-CON-PLN-000903 Revision 6 dated 3rd June 2016, as it contains further details of the Project, noise criteria, monitoring, general mitigation measures and other information. Details of the construction methodology are contained in the Project Construction Environmental Management Plan (CEMP). Acoustic terms are defined in the Acoustic Glossary in the CNV DWP.
1.1
OBJECTIVE
The objective of this SSCNVMP is to detail the best practicable option to avoid, remedy or mitigate adverse effects on sensitive receivers resulting from construction noise and vibration that does not comply with the Project Standards defined in Section 1.2 of the CNV DWP.
1.2
SITE PLAN
Figures 1 and 2 show the location and stages of construction for the Customs Street Intersection traffic deck. Figure 1 Site Plan
Customs Street Intersection Work Area
Page 7
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001182 Revision: 04, Date: 3 June 2016
Figure 2 Concrete deck construction stages
2 RECEIVERS Receivers where noise levels due to Customs Street Intersection works have the potential to exceed project noise standards are listed in Table 1, along with building use. The building at 11-27 Customs Street is going to be demolished with tenants beginning to move out early this year so it has not been considered in this SSCNVMP. Table 1 Affected receivers
Historic / vibration sensitive
Address
Building use
22 Customs Street (DFS Galleria)
Commercial
Y
3 Albert Street 29 Customs Street (AMP Building)
Commercial
N
Commercial
N
8 Albert Street (City Med and Quay West) 5 Albert Street (NZ Gifts)
Mixed use (commercial/ residential)
N
Commercial
Y
Minimum Distance to Works, m 3
Noise Criteria, dB dB LAeq LAFmax 75 -
Vibration Criteria, (mm/s) 3
8
75
-
20
22
75
-
20
28
75*
90*
5
29
75
-
3
* This is the Monday to Saturday 07:00 to 22:00 noise criteria. The majority of works will be carried out during this period. For residential receivers the noise limit is reduced to 65 dB L Aeq & 80 dB LAFmax on Sundays and Public Holidays between 07:00 to 22:00 and to 60 dB LAeq & 75 dB LAFmax at all other times.
Page 8
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001182 Revision: 04, Date: 3 June 2016
Designation Condition 38.4 allows for the Project vibration limits to be relaxed by a SSCVMP but only for a building, structure or infrastructure that has been assessed by a suitably qualified and experienced structural engineer and where it has been deemed to be capable of withstanding higher vibration levels without sustaining building or structural damage, and where appropriate vibration and building condition monitoring regimes are in place. Based on the building condition surveys and the initial assessments by the structural engineer the vibration limits will not be reduced.
3 ACTIVITIES Construction activities along with proposed start and end dates, and hours of operation, are shown in Table 2 below. Table 2 Construction activities
Construction Activity
Area of works
Activity Start Date
Activity End Date
Hours
SP1 Advance Utilities Works Install Vector services trench Customs Wyndham
Customs – Wyndham Street
31 May 2016
Customs Street Stormwater Works
Lower Albert Street
31 May 2016
05 Jul 2016
7am to 7pm
Customs Intersection
12 Sep 2016
21 Oct 2016
Mon - Sat
26 Jul 2016
7am to 7pm Mon - Sat
Utilities and Enabling Works Cut back curb
Galleria block
13 Jul 2016
09 Aug 2016
Locate & Protect Utilities
Customs Deck 1
12 Sep 2016
16 Sep 2016
Customs Deck 2
12 Sep 2016
16 Sep 2016
Customs Deck 3
08 Dec 2016
14 Dec 2016
Customs Deck 4
20 Mar 2017
24 Mar 2017
7am to 7pm Mon - Sat
Piling Piling
Customs Deck 1
20 Sep 2016
05 Oct 2016
7am to 7pm
Customs Deck 2
10 Oct 2016
20 Oct 2016
Mon - Sat
Customs Deck 3
15 Dec 2016
19 Dec 2016
Customs Deck 4
11 Apr 2017
19 Apr 2017
Pile Caps and Traffic Decks Road Deck Construction
Section 1
06 Oct 2016
28 Nov 2016
7am to 7pm
Section 2
21 Oct 2016
05 Dec 2016
Mon - Sat
Section 3
22 Dec 2016
10 Mar 2017
Section 4
20 Apr 2017
15 Jun 2017
Ground and Stormwater Management Projects Dewatering System
Customs Street Intersection.
June 2017
Nov 2018
24 hours a day, 7 days a week.
The projects dewatering system will Page 9
Connectus Project #: 2665 Client: Auckland Transport
Construction Activity
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001182 Revision: 04, Date: 3 June 2016
Area of works
Activity Start Date
Activity End Date
Hours
be located in various positions within the intersection dependent on traffic control requirements. Details of construction equipment that is likely to be used for each of the above activities and the associated noise levels can be found in Appendix C of the CNV DWP. Details of the equipment that is expected to generate high levels of vibration can be found in Appendix B of the CNV DWP. The equipment levels detailed in Appendices B and C of the CNV DWP are placeholders. All equipment will be measured operating independently and then actual equipment noise/ vibration levels and model numbers will be recorded and updated within the table.
4 PREDICTED NOISE AND VIBRATION LEVELS 4.1
NOISE
The predicted worst case noise levels from each activity received at the most exposed part of the receiver are shown below in Table 3. These levels correspond to the construction equipment being located at its nearest position to the receiver and assume there is no physical mitigation between the noise source and the faรงade of the building. The predicted noise levels take into account whether works are being carried out at ground level or below the ground. Table 3 Predicted noise levels (no mitigation)
Address
Predicted worst case noise levels (no mitigation), dB LAeq
Service location and exposure 22 Customs Street 3 Albert Street 29 Customs Street 8 Albert Street 5 Albert Street Installation of CFA piles 22 Customs Street 3 Albert Street 29 Customs Street 8 Albert Street Jet Grouting 22 Customs Street 3 Albert Street 29 Customs Street 8 Albert Street 5 Albert Street Excavation and support of exposed services 22 Customs Street 3 Albert Street
Project Noise Standards exceedance, dB
96 90 80 77 76
21 15 5 2 1
95 89 79 76
20 14 4 1
99 93 83 80 79
24 18 8 5 4
88 82
13 7 Page 10
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001182 Revision: 04, Date: 3 June 2016
Binding and fixing of reinforcement 22 Customs Street 3 Albert Street 29 Customs Street 8 Albert Street 5 Albert Street Placement of concrete 22 Customs Street 3 Albert Street Stormwater pumping station demolition 22 Customs Street 3 Albert Street 29 Customs Street Stormwater line demolition 22 Customs Street 3 Albert Street Ground and stormwater management 22 Customs Street 3 Albert Street 29 Customs Street 8 Albert Street
4.2
97 91 81 78 77
22 16 6 3 2
90 84
15 9
93 87 77
18 12 2
91 85
16 10
88 88 86 69
13 13 11 9 (during the night)
VIBRATION
Vibration regression curves and emission radii for the vibration sources can be found in Section 5.2 of the CNV DWP. The emission radius is the distance at which vibration levels from an activity/equipment item are expected to exceed the Project Vibration Standards for a particular type of building. A receiver is classified as ‘high risk’ if it is located within the emission radius for an activity, and ‘medium risk’ if it is close to the contour with possible intermittent exceedance. Buildings which are classed as high or medium risk of damage as a result of the Customs Street Intersection works are shown in Table 4. Table 4 Vibration risk class
Address Installation of CFA piles 22 Customs Street 3 Albert Street
Building type
Distance to works (m)
Risk class
Historic / vibration sensitive
3
Medium
Commercial
8
Medium
Installation of permanent wearing course 22 Customs Street
Historic / vibration sensitive
3
High
3 Albert Street
Commercial
8
Medium
Binding and fixing of reinforcement 22 Customs Street
Historic / vibration sensitive
3
High
3 Albert Street
Commercial
8
Medium
We note that the emission radii are based on generic data based on conservatively sized equipment and ground conditions. Vibration levels from actual equipment at the site may differ and are likely to be Page 11
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001182 Revision: 04, Date: 3 June 2016
less than assumed for the emission radius. Monitoring will be carried out at the earliest opportunity on site to determine the adjustments for ground conditions and actual equipment items.
5 MITIGATION 5.1
NOISE
Mitigation is required to meet the noise criteria at the nearest sensitive receivers. In addition to the general noise and vibration control measures outlined in Section 7 of the CNV DWP, the following specific noise mitigation measures should be implemented (Table 5): Table 5 Specific Noise Mitigation Measures
Equipment/process
Noise control measures
Excavators, bobcats, loaders
Grease tracks regularly
Crane
Use straps rather than chains unless a risk assessment deems the use of straps unsafe.
Concrete Cutting
Use a mobile acoustic enclosure where practicable. Use of a mobile acoustic enclosure may not be practicable when:
Cutting within 300mm of a kerb or canopy structure
Saw cuts need to be made around an obstruction that protrudes above surface level, such as a light pole or street sign.
The road saw needs to be manoeuvred around in a tight space that would be obstructed by the acoustic enclosure
When use of a mobile acoustic enclosure is not practicable works will be planned so that saw cutting directly in front of a receiver is completed within a total of two working days. The building owner will be contacted prior to this occurring to see if the works can be scheduled for a time that least impacts them. Vacuum Excavation
Locate the vehicle so the pump is facing away from the closest noise sensitive properties
Dewatering system
Erect 1.8m noise barriers around the dewatering system. Fully enclose the pumps and generator that will operate through the night to achieve a noise level of 75 dB(A) at 5m or locate the pumps and generator more than 100m from the closest façade of 8 Albert Street during the night time period.
In addition to these measures, noise barriers/hoardings between the work site and the receiver will be used to reduce noise levels. These will be least 1.8m high and have a mass equal to or greater than 2 10 kg/m . Panels will be abutted or overlapped to provide a continuous screen with no gaps. It may be acceptable to use a proprietary barrier with a reduced mass providing the required attenuation can be achieved. The contractor will seek approval from the Project Acoustic Specialist before using a proprietary barrier product on site. Indicative location of noise barriers is shown in green in Figure 3 below.
Page 12
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001182 Revision: 04, Date: 3 June 2016
Figure 3 Noise barriers
5.1.1
Internal noise levels
With the above mitigation and management measures implemented and barriers installed, the noise levels at the most exposed faรงade of 22 Customs Street and 3 Albert Street will still exceed the noise criteria by more than 5 dB during some Project construction activities. The building at 3 Albert Street comprises a ground floor podium with a tower on top. The tower is occupied by offices. It has a glass faรงade and all offices are mechanically ventilated. The attenuation provided by the faรงade is predicted to be 35 dB Rw. Noise levels in the tower section of the building will remain below 45 dB LAeq for the majority of the works. Faรงade sound insulation improvements are therefore not considered necessary at this receiver. The bakery / cafe on the ground floor of 3 Albert Street is the most exposed area of the building. The doors are kept wide open all day and so they are already exposed to high levels of traffic noise, particularly heavy vehicles pulling away from the traffic lights. The radio plays loudly so it can be heard over the traffic noise. To reduce construction noise levels further it would be necessary to fit acoustic seals around the door and to keep it shut during construction activities, except to allow for the timely entry and egress of customers. The business owner indicated that he is not concerned about construction noise and is likely to keep the doors open as usual. Faรงade sound insulation improvements are therefore not currently being considered for this receiver. The building at 22 Customs Street houses a number of retail outlets. It is a masonry building with single glazed timber sash windows. All areas are mechanically ventilated. Music is played in the retail areas masking external noise ingress. Construction noise is unlikely to be an issue in the retail areas as it will be masked by the background music and general operational noise. Traffic noise was clearly audible in the meeting room overlooking Albert Street. The window in this room does not seal adequately when shut and noise break in around the window frame was noticeable. Details of the building treatment that is required for this receiver is detailed in the Albert Street Piling SSCNVMP Document Ref: CRL-PAT-ENV-CON-PLN-001189. With the building treatment applied noise levels in the office/ meeting rooms will meet the AS/NZS 2107:2000 criterion of 45 dB LAeq.
Page 13
Connectus Project #: 2665 Client: Auckland Transport
5.2
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001182 Revision: 04, Date: 3 June 2016
VIBRATION
In addition to the general noise and vibration control measures outlined in Section 7 of the Project CNV DWP the following specific vibration mitigation measures (Table 6) should be implemented if the initial on site vibration monitoring demonstrates that the building damage vibration limits will be exceeded: Table 6 Specific Vibration Mitigation Measures
Equipment/process
Vibration control measures
Excavator mounted rock breaker
Use lower vibration generating equipment such as a hand held jack hammer when within 20m of 22 Customs Street.
Roller compactor (17t)
Use a smaller compactor, less than 10t, when within 20m of 22 Customs Street. The frequency of the compactor should also be considered. It may be acceptable to use a bigger compactor depending on the frequency it is being operated at.
A detailed pre-construction building condition survey will be undertaken at all of the identified buildings in accordance with Section 10.4 of the CNV DWP.
6 COMMUNICATION AND CONSULTATION Section 9.1 of the Project CNV DWP details the communication procedures for the Project. The complaints process is detailed in Section 9.2 of the CNV DWP. Consultation with the stakeholders identified in this SSCNVMP took place from mid-November to midDecember 2015. Topics that were covered included:
Sequencing of construction activities
Likely equipment and associated noise and vibration levels
Proposed mitigation and management measures
Construction of their buildings
Operational hours of their businesses
Operating environment that is required by the businesses
Further details of the meetings and comments made by the stakeholders are provided in Appendix D of the CNV DWP.
Page 14
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001182 Revision: 04, Date: 3 June 2016
7 MONITORING Section 10 of the Project CNV DWP provides details of the methodology for noise and vibration monitoring.
7.1
NOISE MONITORING
Noise monitoring will be carried out 1m from the faรงade of the Bakery at 3 Albert Street when Project works commence on Customs Deck 1 to confirm noise levels are as predicted. Further monitoring will be carried out at this location when piling, jet grouting and rock breaking commence on Customs Deck 1. Noise monitoring will be carried out at 22 Customs Street when Project works begin on Customs Deck 3 to confirm that noise levels both externally, 1m from the faรงade, and internally, in the most exposed retail area and the level 2 meeting/ training room overlooking Albert Street, are as predicted. Further monitoring will be carried out at these locations when piling, jet grouting and rock breaking begin at Customs Deck 3.
7.2
VIBRATION MONITORING
Vibration monitoring will be carried out at 22 Customs Street, for 2 weeks initially, when Project works commence on Customs Deck 3. Depending on the levels of vibration measured it may be necessary to extend the monitoring period to cover the full duration of the Customs Deck 3 works (approximately 2 months). A location at basement or ground floor level close to the Customs Street intersection will be used but the exact location of the monitoring equipment within the building is yet to be finalised as the tenant will soon be carrying out a refit of the building. Discussions with the building owner are ongoing and the final location will be influenced by the timing of the monitoring. They have asked to be contacted a month before the monitoring takes place to finalise a location.
8 STAFF Before working on these activities all staff will receive training in accordance with Section 7.2 of the CNV DWP and will read and comply with this SSCNVMP.
Page 15
Auckland City Rail Link In association with:
ENABLING WORKS CONTRACT 2 SITE SPECIFIC CONSTRUCTION NOISE AND VIBRATION MANAGEMENT PLAN: ADVANCED UTILITIES WORKS Separable Portion 1 – Cut and Cover Works Document Ref: CRL-PAT-ENV-CON-PLN-001263 Revision: 03
FINAL 3rd June 2016
COMMERCIAL IN CONFIDENCE
This page intentionally left blank.
DOCUMENT INFORMATION Organisation:
Connectus
Document Title:
Site Specific Construction Noise Management Plan
Fulcrum Document Number:
CRL-PAT-ENV-CON-PLN-001263
Document based on MMS No:
n/a
Client:
Auckland Transport
Project:
CRL Enabling Works: Contract Two
Location:
Auckland CBD
Project No:
2665
REVISION HISTORY Rev
Date
Details st
01
1
Draft for Connectus review
Author
Approver
C. Drewery
C Hind
02
21/03/16
Final for Issue
C. Drewery
C Hind
03
3/06/16
Final for Issue
C. Drewery
C Hind
This document remains the property of Connectus. Its contents are confidential and shall not be reproduced, destroyed or given away without the express, written permission of Connects. The electronic version of this document in MMS Database on designated server(s) is the Master Copy and is a controlled document. Unless specifically noted thereon, other copies of this document are uncontrolled.
This page intentionally left blank
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 rd Revision: 03, Date: 3 June 2016
Table of Contents Document information .........................................................................................................................3 Revision History ..................................................................................................................................3 1
Introduction........................................................................................................................7 1.1
Objective
7
1.2
Site plan
7
2
Receivers ..........................................................................................................................8
3
Activities .......................................................................................................................... 10
4
Predicted Noise and vibration levels................................................................................. 11 4.1
Noise
11
4.2
Vibration
12
5
Mitigation ......................................................................................................................... 14 5.1
Noise
14
5.2
Vibration
15
6
Communication and Consultation..................................................................................... 15
7
Monitoring ....................................................................................................................... 16
8
7.1
Noise monitoring
16
7.2
Vibration monitoring
16
Staff................................................................................................................................. 17
Page 5
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 rd Revision: 03, Date: 3 June 2016
This page intentionally left blank
Page 6
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 rd Revision: 03, Date: 3 June 2016
1 INTRODUCTION This is a Site Specific Construction Noise and Vibration Management Plan (SSCNVMP) and forms part of the Construction Noise and Vibration Delivery Work Plan (CNV DWP) for the CRL Contract 2 Enabling Works (the ‘Project’). This SSCNVMP provides specific assessment of construction noise and vibration from advanced utilities works within the project designation. This SSCNVMP should be read in conjunction with the CNV DWP (Document Ref: CRL-PAT-ENV-CON-PLN-000903 Revision 6 dated 3rd June 2016) as it contains further details of the project, noise criteria, monitoring, general mitigation measures and other information. Details of the construction methodology are contained in the Project Construction Environmental Management Plan (CEMP). Acoustic terms are defined in the Acoustic Glossary in the CNV DWP.
1.1
OBJECTIVE
The objective of this SSCNVMP is to detail the best practicable option to avoid, remedy or mitigate adverse effects on sensitive receivers resulting from construction noise and vibration that does not comply with the Project Standards defined in Section 1.2 of the CNV DWP.
1.2
SITE PLAN
The locations of the advanced utilities works are shown on Figure 1. Figure 1 Site Plan
Page 7
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 rd Revision: 03, Date: 3 June 2016
2 RECEIVERS Receivers where noise levels due to the advanced utility works within the project designation have the potential to exceed project noise or vibration standards are listed below, along with building use. Table 1 Affected receivers
Historic / vibration sensitive
Minimum Distance to Works, m
Noise Criteria, dB dB LAeq LAFmax
Vibration Criteria, (mm/s)
Address
Building use
38 Wyndham Street
Commercial
N
1
75
-
20
3 Albert Street
Commercial
N
1
75
-
20
63 Albert Street
Commercial
N
2
75
-
20
65-71 Albert Street
This building has its own SSCNVMP so is not included in this plan
46-50 Albert Steet
Commercial
Y
2
75
-
3
12-26 Swanson Street
Commercial
N
2
75
-
20
61 Albert Street
Mixed Use
Y
2
75*
90*
3
35 Albert Street
Construction Site
N
2
-
-
-
37-39 Albert Street
Construction Site
N
2
-
-
-
5-7 Albert Street
Commercial
Y
2
75
-
3
57 Albert Street
Commercial
Y
2
75
-
3
41 Albert Street
This building has its own SSCNVMP so is not included in this plan
58 Albert Street
Commercial
N
2
75
-
20
52-56 Albert Street
Commercial
Y
2
75
-
3
51 Albert Street
Commercial
Y
2
75
-
3
15 Albert Street
Vacant
Y
2
-
-
3
9 Albert Street
Mixed Use
Y
2
75*
90*
3
55 Albert Street
Commercial
Y
2
75
-
3
13 Albert Street
Vacant
Y
2
-
-
3
22 Customs Street
Commercial
Y
3
75
-
3
17 Albert Street
Commercial
Y
3
75
-
3
8 Albert Street
Mixed Use
N
3
75*
90*
5
23-29 Albert Street
Commercial
N
3
75
-
20
22-26 Albert Street
This building has its own SSCNVMP so is not included in this plan
11-27 Customs Street
Commercial but about to be demolished
N
7
75
-
20
70-74 Albert Street
Mixed Use
N
8
75*
90*
5
Bluestone Wall
-
Y
9
-
-
3
Page 8
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 rd Revision: 03, Date: 3 June 2016
34-36 Wyndham Street
Commercial
Y
10
75
-
3
81 Albert Street
Mixed Use
N
14
75*
90*
5
33 Wyndham Street
Commercial
N
15
75
-
20
26 Wyndham Street
Commercial
N
17
76
-
20
29 Customs Street
Commercial
N
19
75
-
20
76 Albert Street
Residential
N
20
75*
90*
5
4 Kingston Street
Commercial
N
25
75
-
20
9 Wolfe Street
Commercial
N
27
75
-
20
18 Federal Street
Residential
N
35
75*
90*
5
* This is the Monday to Saturday 07:00 to 22:00 noise criteria. The majority of works will be carried out during this period. For residential receivers the noise limit is reduced to 65 dB L Aeq & 80 dB LAFmax on Sundays and Public Holidays between 07:00 to 22:00 and to 60 dB LAeq & 75 dB LAFmax at all other times.
Designation Condition 38.4 allows for the Project vibration limits to be relaxed by a SSCVMP but only for a building, structure or infrastructure that has been assessed by a suitably qualified and experienced structural engineer and where it has been deemed to be capable of withstanding higher vibration levels without sustaining building or structural damage, and where appropriate vibration and building condition monitoring regimes are in place. Based on the building condition surveys and the initial assessments by the structural engineer the vibration limits will not be reduced. 2.1.1
Bluestone Wall
In addition to the buildings along Albert Street there is a wall with heritage status, refered to as the Bluestone Wall. The wall is located towards the southern end of the Project area opposite the District Court. The vibration criteria of 3mm/s from DIN 4550:3 is applicable to heritage structures. DIN 4150:3 states that “Experience has shown that if these values are complied with, damage that reduces the serviceability of the building will not occur�. It also states that exceeding the values does not necessarily lead to damage. Table 2 details categories of damage and a description of the damage that could be expected in that category. Providing the vibration criteria of 3mm/s is achieved at the Bluestone Wall the Category of Damage will be 2 or below. Table 2 Categories of Damage
Category of Damage
Normal Degree of Severity
Description of Typical Damage
0
Negligible
Hairline cracks
1
Very Slight
Fine cracks easily treated during normal redecoration. Perhaps isolated slight fracture in building. Cracks in exterior visible upon close inspection.
2
Slight
Cracks easily filled. Redecoration probably required. Several slight fractures inside building. Exterior cracks visible, some repainting may be required for weathertightness. Doors and windows may stick slightly.
3
Moderate
Cracks may require cutting out and patching. Recurrent cracks can be masked by suitable
General Category Aesthetic Damage
Serviceability Damage Page 9
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 rd Revision: 03, Date: 3 June 2016
linings. Brick pointing and possible replacement of a small amount of exterior brickwork may be required. Doors and windows sticking.
3 ACTIVITIES Construction activities along with proposed start and end dates, and hours or operation, are shown in Table 3 below. Table 3 Construction activities
Construction Activity
Area of works
Activity Start Date
Duration
Advanced Utilities Relocation Works
Customs St Intersection Stormwater Works
Early May
50 days
Swanson St West Stormwater Works
Early August
12 days
Swanson St East Early Stormwater Works
Early August
20 days
Swanson St East Stormwater Works ANZ Connection
Early September
15 days
Wyndham St Stormwater Works
Early May
25 days
Kingston-Wyndham St Stormwater Works
Early May
35 days
Combined Service Trench – Western Footpath including crossings
Early May
60 days
Wyndham St Chorus Works
Early June
15 days
Vector Electricity from Swanson Street West across Albert Street down Swanson Street East
Early June
20 days
Hours
7am – 7pm Mon - Sat
Details of construction equipment that is likely to be used for each of the above activities and the associated noise levels can be found in Appendix C of the CNV DWP. Details of the equipment that is expected to generate high levels of vibration can be found in Appendix B of the CNV DWP. The equipment levels detailed in Appendices B and C of the CNV DWP are placeholders. All equipment will be measured operating independently and then actual equipment noise/ vibration levels and model numbers will be recorded and updated within the table. .
Page 10
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 rd Revision: 03, Date: 3 June 2016
4 PREDICTED NOISE AND VIBRATION LEVELS 4.1
NOISE
The predicted worst case noise levels from each activity received at the most exposed part of each receiver are shown below in Table 4. These levels correspond to the construction equipment being located at its nearest position to the receiver and assume there is no physical mitigation between the noise source and the façade of the building. Table 4 Predicted noise levels (no mitigation)
Address
Predicted worst case noise levels (no mitigation), dB LAeq
Project Noise Standards exceedance, dB
Combined Services Trench 63 Albert Street
102
27
61 Albert Street
100
25
57 Albert Street
100
25
38 Wyndham Street
97
22
12-26 Swanson Street
93
18
34-36 Wyndham Street
83
8
33 Wyndham Street
82
7
70-74 Albert Street
80
5
26 Wyndham Street
78
3
18 Federal Street
76
1
Customs Street Stormwater – Southwest 3 Albert Street
94
19
22 Customs Street
80
5
5 Albert Street
78
3
29 Customs Street
77
2
8 Albert Street
76
1
Customs Street Stormwater - Northeast 29 Customs Street
80
5
Swanson Street Stormwater - East 12-26 Swanson Street
90
15
Swanson Street Stormwater - West 23-29 Albert Street
81
6
12-26 Swanson Street
78
3
Kingston Street to Wyndham Street Stormwater 63 Albert Street
92
17 Page 11
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 rd Revision: 03, Date: 3 June 2016
81 Albert Street
83
8
70-74 Albert Street
80
5
38 Wyndham Street
80
5
76 Albert Street
77
2
4 Kingston Street
76
1
Wyndham Street Temporary Diversion 63 Albert Street
94
19
70-74 Albert Street
80
5
38 Wyndham Street
80
5
61 Albert Street
79
4
33 Wyndham Street
76
1
Wyndham Street Permanent Works 61 Albert Street
91
16
63 Albert Street
83
8
33 Wyndham Street
82
7
57 Albert Street
79
4
38 Wyndham Street
76
1
Chorus Wyndham Street 38 Wyndham Street
100
25
63 Albert Street
93
18
34-36 Wyndham Street
86
11
61 Albert Street
81
6
26 Wyndham Street
79
4
70-74 Albert Street
78
3
33 Wyndham Street
78
3
46-50 Albert Street
78
3
Customs Street Watermain 22 Customs Street
91
16
3 Albert Street
89
14
5 Albert Street
76
1
4.2
VIBRATION
Buildings which are classed as high or medium risk of damage as a result of the Advanced Utilities works are shown in Table 5. A receiver is classified as ‘high risk’ if it is located within the emission radius for an activity, and ‘medium risk’ if it is close to the contour with possible intermittent exceedance.
Page 12
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 rd Revision: 03, Date: 3 June 2016
Table 5 Vibration risk class
Distance to works (m)
Address
Building type
Risk class
38 Wyndham Street
Commercial
1
High
3 Albert Street
Commercial
1
High
63 Albert Street
Commercial
2
High
12-26 Swanson Street
Commercial
2
High
61 Albert Street
Historic / Vibration Sensitive
2
High
57 Albert Street
Historic / Vibration Sensitive
2
High
58 Albert Street
Commercial
2
High
52-56 Albert Street
Historic / Vibration Sensitive
2
High
51 Albert Street
Historic / Vibration Sensitive
2
High
55 Albert Street
Historic / Vibration Sensitive
2
High
22 Customs Street
Historic / Vibration Sensitive
3
High
70-74 Albert Street
Residential
8
High
0 Bluestone Wall
Historic / Vibration Sensitive
9
High
34-36 Wyndham Street
Historic / Vibration Sensitive
10
High
It can be seen from the table above that a number of the buildings may experience vibration that exceeds the building damage vibration limits during use of the excavator mounted concrete breaker. Vibration monitoring will be carried out when works begin on site to determine actual equipment vibration levels and the attenuation provided by the local ground conditions.
Page 13
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 rd Revision: 03, Date: 3 June 2016
5 MITIGATION 5.1
NOISE
Mitigation is required to meet the noise criteria at the nearest sensitive receivers. In addition to the general noise and vibration control measures outlined in Section 7 of the CNV DWP, the following specific noise mitigation measures should be implemented (Table 6): Table 6 Specific Noise Mitigation Measures
Equipment/process
Noise control measures
Excavators, bobcats, loaders
Grease tracks regularly
Concrete cutting
Use a mobile acoustic enclosure where practicable. Use of a mobile acoustic enclosure may not be practicable when:
Cutting within 300mm of a kerb or canopy structure Saw cuts need to be made around an obstruction that protrudes above surface level, such as a light pole or street sign.
The road saw needs to be manoeuvred around in a tight space that would be obstructed by the acoustic enclosure
When use of a mobile acoustic enclosure is not practicable works will be planned so that saw cutting directly in front of a receiver / receivers is completed within a total of two working days. The building owner(s) will be contacted prior to this occurring to see if the works can be scheduled for a time that least impacts them. Vacuum Excavation
Locate the vehicle so the pump is facing away from the closest noise sensitive properties
In addition to these measures, noise barriers/hoardings between the work site and the receiver will be used to reduce noise levels. These will be least 1.8m high and have a mass equal to or greater than 10 kg/m2. Panels will be abutted or overlapped to provide a continuous screen with no gaps. It may be acceptable to use a proprietary barrier with a reduced mass, such as Flex Shield providing the required attenuation can be achieved. The contractor will seek approval from the Project Acoustic Specialist before using a proprietary barrier product on site. 5.1.1
Internal noise levels
With the above mitigation and management measures implemented and barriers installed, the noise levels at the most exposed façade of a number of properties will still exceed the noise criteria by more than 5 dB during some Project construction activities. Building mitigation has been recommended for 22 Customs Street to achieve acceptable internal noise levels over the duration of the Project. The recommendations can be found in the SSCNVMP for the Albert Street piling works (Document Reference CRL-PAT-ENV-CON-PLN-001189). The advanced utilities relocation works are located so close to the receviers that internal noise levels will be high, even in 22 Customs Street where building modifications are proposed. Cutting and breaking, where required, are the noisiest activities but an enclosure is unlikely to be practicable in the majority of locations due to space restrictions. The works are of a relatively short duration and cutting and breaking will only take place for a fraction of the time. It will be necessary to consult further with each affected receiver before works begin outside of their building and schedule the noisy activities, where possible, for a time that least impacts them. Page 14
Connectus Project #: 2665 Client: Auckland Transport
5.2
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 rd Revision: 03, Date: 3 June 2016
VIBRATION
In addition to the general noise and vibration control measures outlined in Section 7 of the Project CNV DWP the following specific vibration mitigation measures (Table 7) should be implemented if the initial on site vibration monitoring demonstrates that the building damage vibration limits will be exceeded: Table 7 Specific Vibration Mitigation Measures
Equipment/process
Vibration control measures
Excavator mounted rock breaker
Use lower vibration generating equipment such as a hand held jack hammer
Roller compactor (17t)
Use a smaller compactor, less than 10t
Excavator mounted rock breakers must not be used within 16m of the Bluestone Wall unless on site measurements demonstrate vibration levels are lower than predicted from this item of plant. Hand held jack hammers or alternative low vibration generating equipment should be used within this distance. Similarly, small compactors, less than 10t should be used when within 15m of the Bluestone Wall.
6 COMMUNICATION AND CONSULTATION Section 9.1 of the Project CNV DWP details the communication procedures in relation to construction noise and vibration effects.. The complaints process is detailed in Section 9.2 of the CNV DWP. Consultation with the stakeholders identified in this SSCNVMP took place from mid-November to midDecember 2015. Topics that were covered included:
Sequencing of construction activities
Likely equipment and associated noise and vibration levels
Proposed mitigation and management measures
Construction of their buildings
Operational hours of their businesses
Operating environment that is required by the businesses
Further details of the meetings and comments made by the stakeholders are provided in Appendix D of the CNV DWP.
Page 15
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 rd Revision: 03, Date: 3 June 2016
7 MONITORING Section 10 of the Project CNV DWP provides details of the methodology for noise and vibration monitoring.
7.1
NOISE MONITORING
Noise monitoring will be carried out when concrete breaking and begins within 20m of the building at the locations detailed in Table 8. The monitoring will be carried out at first floor level unless a location at a higher level is specified. Table 8 Noise Monitoring Locations
Receiver
Monitoring Location
3 Albert Street
1m from façade of building
22 Customs Street
1m from façade of building In the most exposed retail area In the Level 2 meeting/ training room overlooking Albert Street
63 Albert Street
1m from façade of building
61 Albert Street
1m from façade of building
70-74 Albert Street
1m from façade of building
12-26 Swanson Street
1m from façade of building
In addition to the above site-specific monitoring locations, overall project noise levels will be monitored on a monthly basis at six standard monitoring locations identified in the CNV DWP.
7.2
VIBRATION MONITORING
Vibration monitoring will be carried out when works begin on site to determine actual equipment vibration levels and the attenuation provided by the local ground conditions. If the initial vibration monitoring demonstrates that the emission radius for the excavator mounted concrete breaker are similar to those detailed in Section 5.2 of the CNV DWP then the monitoring as detailed below will be carried out. If the monitoring demonstrates that vibration levels are significantly lower then less properties may require monitoring, if they are higher then more properties may require monitoring. Vibration monitoring will be carried out at the following receivers when concrete breaking begins within 16m of the building:
22 Customs Street
55 Albert Street
61 Albert Street
57 Albert Street
Vibration monitoring will be carried out at the following receivers when concrete breaking begins within 10m of the building:
70-74 Albert Street
Page 16
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 rd Revision: 03, Date: 3 June 2016
Vibration monitoring will be carried out at the following receivers when concrete breaking begins within 7m of the building:
3 Albert Street
38 Wyndham Street
58 Albert Street
63 Albert Street
In addition to the above site-specific vibration monitoring locations, overall project vibration levels will be monitored on a monthly basis at six standard monitoring locations identified in the CNV DWP.
8 STAFF Before working on these activities all staff will receive training in accordance with Section 7.2 of the CNV DWP and will read and comply with this SSCNVMP.
Page 17
Auckland City Rail Link In association with:
ENABLING WORKS CONTRACT 2 SITE SPECIFIC CONSTRUCTION NOISE AND VIBRATION MANAGEMENT PLAN: ALBERT STREET PILING Separable Portion 1 – Cut and Cover Works Document Ref: CRL-PAT-ENV-CON-PLN-001189 Revision: 03
FINAL 3rd June 2016
COMMERCIAL IN CONFIDENCE
This page intentionally left blank.
DOCUMENT INFORMATION Organisation:
Connectus
Document Title:
SITE SPECIFIC CONSTRUCTION NOISE AND VIBRATION MANAGEMENT PLAN: ALBERT STREET PILING
Fulcrum Document Number:
CRL-PAT-ENV-CON-PLN-001189
Document based on MMS No:
n/a
Client:
Auckland Transport
Project:
CRL Enabling Works: Contract Two
Location:
Auckland CBD
Project No:
2665
REVISION HISTORY Rev
Date
Details st
01
1
Draft for Connectus review
Author
Approver
C. Drewery
C Hind
02
21/3/16
Final for Issue
C. Drewery
C Hind
03
3/6/16
Final
C. Drewery
C Hind
This document remains the property of Connectus. Its contents are confidential and shall not be reproduced, destroyed or given away without the express, written permission of Connects. The electronic version of this document in MMS Database on designated server(s) is the Master Copy and is a controlled document. Unless specifically noted thereon, other copies of this document are uncontrolled.
This page intentionally left blank
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001189 rd Revision: 03, Date: 3 June 2016
Table of Contents Document information .........................................................................................................................3 Revision History ..................................................................................................................................3 1
Introduction........................................................................................................................7 1.1
Objective
7
1.2
Site plan
7
2
Receivers ..........................................................................................................................8
3
Activities ............................................................................................................................9
4
Predicted Noise and vibration levels................................................................................. 10 4.1
Noise
10
4.2
Vibration
11
5
Mitigation ......................................................................................................................... 12 5.1
Noise
12
5.2
Vibration
20
6
Communication and Consultation..................................................................................... 21
7
Monitoring ....................................................................................................................... 22
8
7.1
Noise monitoring
22
7.2
Vibration monitoring
22
Staff................................................................................................................................. 23
Page 5
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001189 rd Revision: 03, Date: 3 June 2016
This page intentionally left blank
Page 6
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001189 rd Revision: 03, Date: 3 June 2016
1 INTRODUCTION This is a Site Specific Construction Noise and Vibration Management Plan (SSCNVMP) and forms part of the Construction Noise and Vibration Delivery Work Plan (CNV DWP) for the CRL Contract 2 Enabling Works (the ‘Project’). This SSCNVMP provides specific assessment of construction noise and vibration effects from the Albert Street Piling component of the Project. This SSCNVMP should be read in conjunction with the CNV DWP (Document Ref: CRL-PAT-ENV-CON-PLN-000903 Revision 6 dated 3rd June 2016) as it contains further details of the project, noise criteria, monitoring, general mitigation measures and other information. Details of the construction methodology are contained in the Project Construction Environmental Management Plan (CEMP). Acoustic terms are defined in the Acoustic Glossary in the CNV DWP.
1.1
OBJECTIVE
The objective of this SSCNVMP is to detail the best practicable option to avoid, remedy or mitigate adverse effects on sensitive receivers resulting from construction noise and vibration that does not comply with the Project Standards defined in Section 1.2 of the CNV DWP.
1.2
SITE PLAN
Figure 1 shows the location of the piling works. Figure 1 Site Plan
Page 7
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001189 rd Revision: 03, Date: 3 June 2016
2 RECEIVERS Receivers where noise levels due to the Albert Street piling works have the potential to exceed project noise or vibration standards are listed below, along with building use. Table 1 Affected receivers
Historic / vibration sensitive
Minimum Distance to Works, m
Noise Criteria, dB dB LAeq LAFmax
Vibration Criteria, (mm/s)
Address
Building use
15 Albert Street
Vacant
Y
5
-
-
3
13 Albert Street
Vacant
Y
5
-
-
3
9 Albert Street
Mixed Use (commercial / residential)
Y
4
75*
90*
3
5 Albert Street
Commercial
Y
4
75
-
3
3 Albert Street
Commercial
N
5
75
-
20
17 Albert Street
Commercial
Y
5
75
-
3
22 Customs Street
Commercial
Y
3
75
-
3
51 Albert Street
Commercial
Y
6
75
-
3
41 Albert Street 23-29 Albert Street
This building has its own SSCNVMP so is not included in this plan 75 20 Commercial N 6
38 Wyndham Street
Commercial
N
6
75
-
20
58 Albert Street
Commercial
N
7
75
-
20
63 Albert Street
Commercial
N
7
75
-
20
61 Albert Street
Mixed Use (commercial / residential)
Y
6
75*
90*
3
57 Albert Street
Commercial
Y
6
75*
90*
3
55 Albert Street
Commercial
Y
6
75
-
3
37-39 Albert Street
Construction Site
-
6
-
-
-
35 Albert Street
Construction Site
-
6
-
-
-
52-56 Albert Street
Commercial
Y
7
75
-
3
8 Albert Street
Mixed Use (commercial / residential)
N
8
75*
90*
5
70-74 Albert Street
Mixed Use (commercial / residential)
N
8
75*
90*
5
46-50 Albert Street
Commercial
Y
7
75
-
3
12-26 Swanson Street
Commercial
N
7
75
-
20
22-26 Albert Street
This building has its own SSCNVMP so is not included in this plan Page 8
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001189 rd Revision: 03, Date: 3 June 2016
65-71 Albert Street
This building has its own SSCNVMP so is not included in this plan
34-36 Wyndham Street
Commercial
29 Customs Street
Y
17
75
-
3
Commercial
N
22
75
-
20
33 Wyndham Street
Commercial
N
20
75
-
20
76 Albert Street
Residential
N
26
75*
90*
5
26 Wyndham Street
Commercial
N
24
75
-
20
6 Wolfe Street
Vacant
N
37
-
-
20
9 Wolfe Street
Commercial
N
29
75
-
20
18 Federal Street
Residential
N
37
75*
90*
5
* This is the Monday to Saturday 07:00 to 22:00 noise criteria. The majority of works will be carried out during this period. For residential receivers the noise limit is reduced to 65 dB L Aeq & 80 dB LAFmax on Sundays and Public Holidays between 07:00 to 22:00 and to 60 dB LAeq & 75 dB LAFmax at all other times.
Designation Condition 38.4 allows for the Project vibration limits to be relaxed by a SSCVMP but only for a building, structure or infrastructure that has been assessed by a suitably qualified and experienced structural engineer and where it has been deemed to be capable of withstanding higher vibration levels without sustaining building or structural damage, and where appropriate vibration and building condition monitoring regimes are in place. Based on the building condition surveys and the initial assessments by the structural engineer the vibration limits will not be reduced.
3 ACTIVITIES Construction activities along with proposed start and end dates, and hours or operation, are shown in Table 2 below. Table 2 Construction activities
Construction Activity
Area of works
Activity Start Date
Activity End Date
Hours
Piling
Install CFA piles
Customs Deck 1 through to Wolfe Street - West side
20 Sep2016
05 Oct 2016
South East Quarter
26 Oct 2016
12 Dec 2016
7am – 7pm
South West Quarter
22 Dec 2016
07 Mar 2017
Mon - Sat
North East Quarter
10 Mar 2017
06 Apr 2017
Wolfe Street - West side
24 Apr 2017
26 Apr 2017
Pile Caps and Traffic Decks
Build pile cap & deck
Customs Deck 1 through to Wolfe Street - West side
27 Sep 2016
18 Oct 2016
South East Quarter
02 Nov 2016
23 Dec 2016
South West Quarter
12 Jan 2017
03 Mar 2017
7am – 7pm Mon - Sat
Page 9
Connectus Project #: 2665 Client: Auckland Transport
Construction Activity
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001189 rd Revision: 03, Date: 3 June 2016
Area of works
Activity Start Date
Activity End Date
Build cap only West side ANZ to Wolfe Street
27 Feb 2017
15 Mar 2017
North East Quarter
17 Mar 2017
24 Apr 2017
Build deck ANZ to Wolfe Street
13 Apr 2017
08 May 2017
Hours
Details of construction equipment that is likely to be used for each of the above activities and the associated noise levels can be found in Appendix C of the CNV DWP. Details of the equipment that is expected to generate high levels of vibration can be found in Appendix B of the CNV DWP. The equipment levels detailed in Appendices B and C of the CNV DWP are placeholders. All equipment will be measured operating independently and then actual equipment noise/ vibration levels and model numbers will be recorded and updated within the table.
4 PREDICTED NOISE AND VIBRATION LEVELS 4.1
NOISE
The predicted worst case noise levels from each activity received at the most exposed part of each receiver are shown below in Table 3. These levels correspond to the construction equipment being located at its nearest position to the receiver and assume there is no physical mitigation between the noise source and the faรงade of the building. Table 3 Predicted noise levels (no mitigation)
Address 15 Albert Street 13 Albert Street 9 Albert Street 5 Albert Street 3 Albert Street 17 Albert Street 22 Customs Street 51 Albert Street 41-45 Albert Street 23-29 Albert Street 38 Wyndham Street 58 Albert Street 63 Albert Street 61 Albert Street 57 Albert Street 55 Albert Street 37-39 Albert Street
Predicted worst case noise levels (no mitigation), dB LAeq 96 96 96 96 96 95 95 94 94 94 93 93 93 93 93 93 93
Project Noise Standards exceedance, dB 21 21 21 21 21 20 20 19 19 19 18 18 18 18 18 18 18
Page 10
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001189 rd Revision: 03, Date: 3 June 2016
35 Albert Street 52-56 Albert Street 8 Albert Street 70-74 Albert Street 46-50 Albert Street 12-26 Swanson Street 34-36 Wyndham Street 29 Customs Street 33 Wyndham Street 76 Albert Street 26 Wyndham Street 6 Wolfe Street 9 Wolfe Street 18 Federal Street
4.2
93 92 92 91 91 91 84 82 81 79 79 78 78 77
18 17 17 16 16 16 9 7 6 4 4 3 3 2
VIBRATION
Buildings which are classed as high or medium risk of damage as a result of the Albert Street Piling works are shown in Table 4. A receiver is classified as ‘high risk’ if it is located within the emission radius for an activity, and ‘medium risk’ if it is close to the contour with possible intermittent exceedance. Table 4 Vibration risk class
Address
Building type
Distance to works (m)
Risk class
Installation of CFA piles 22 Customs Street
Historic / vibration sensitive
3
Medium
5 Albert Street
Historic / vibration sensitive
5
Medium
9 Albert Street
Historic / vibration sensitive
5
Medium
13 Albert Street
Historic / vibration sensitive
5
Medium
15 Albert Street
Historic / vibration sensitive
5
Medium
17 Albert Street
Historic / vibration sensitive
5
Medium
Concrete Breaking - Utilities Location and Installation of Pile Caps 22 Customs Street
Historic / vibration sensitive
3
High
5 Albert Street
Historic / vibration sensitive
5
High
9 Albert Street
Historic / vibration sensitive
5
High
3 Albert Street
Commercial
5
High
17 Albert Street
Historic / vibration sensitive
5
High
23-29 Albert Street
Commercial
6
High
55 Albert Street
Historic / vibration sensitive
6
High
61 Albert Street
Historic / vibration sensitive
6
High
57 Albert Street
Historic / vibration sensitive
6
High
38 Wyndham Street
Commercial
7
High
58 Albert Street
Commercial
7
High
63 Albert Street
Commercial
7
High Page 11
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001189 rd Revision: 03, Date: 3 June 2016
8 Albert Street
Residential
8
High
70-74 Albert Street
Residential
8
High
It can be seen from the table above that a number of the buildings may experience vibration that exceeds the building damage vibration limits when a concrete breaker is used during utilities location and installation of pile caps. Vibration monitoring will be carried out when works begin on site to determine actual equipment vibration levels and the attenuation provided by the local ground conditions.
5 MITIGATION 5.1
NOISE
Mitigation is required to meet the noise criteria at the nearest sensitive receivers. In addition to the general noise and vibration control measures outlined in Section 7 of the CNV DWP, the following specific noise mitigation measures should be implemented (Table 5): Table 5 Specific Noise Mitigation Measures
Equipment/process
Noise control measures
Excavators, bobcats, loaders
Grease tracks regularly
Crane
Use straps rather than chains unless a risk assessment deems the use of straps unsafe.
Concrete cutting
Use a mobile acoustic enclosure where practicable. Use of a mobile acoustic enclosure may not be practicable when:
Cutting within 300mm of a kerb or canopy structure Saw cuts need to be made around an obstruction that protrudes above surface level, such as a light pole or street sign.
The road saw needs to be manoeuvred around in a tight space that would be obstructed by the acoustic enclosure
When use of a mobile acoustic enclosure is not practicable works will be planned so that saw cutting directly in front of a receiver / receivers is completed within a total of two working days. The building owner(s) will be contacted prior to this occurring to see if the works can be scheduled for a time that least impacts them. Vacuum Excavation
Locate the vehicle so the pump is facing away from the closest noise sensitive properties
Construction Vehicles
Tonal reversing alarms will not be used. Broadband alarms will be used instead.
In addition to these measures, noise barriers/hoardings between the work site and the receiver will be used to reduce noise levels. These will be least 1.8m high and have a mass equal to or greater than 2 10 kg/m . Panels will be abutted or overlapped to provide a continuous screen with no gaps. It may be acceptable to use a proprietary barrier with a reduced mass providing the required attenuation can be achieved. The contractor will seek approval from the Project Acoustic Specialist before using a proprietary barrier product on site. Indicative location of noise barriers is shown in green in Figure 2 below.
Page 12
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001189 rd Revision: 03, Date: 3 June 2016
Figure 2 Noise barriers
5.1.1
Internal noise levels
With the above mitigation and management measures implemented and barriers installed, the noise levels at the most exposed faรงade of a number of properties will still exceed the noise criteria by more than 5 dB during some Project construction activities. These properties are detailed in Table 6 along with any further mitigation necessary to achieve acceptable internal noise levels. Table 6 Building Mitigation Measures
Address 15 Albert Street 13 Albert Street 9 Albert Street
Comments Building currently vacant Building currently vacant The bottom floors of the building are occupied by Food Alley. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and patrons and patrons choosing to eat elsewhere. The floors of the building that are occupied by food alley are mechanically ventilated. The glass doors are automated but they open frequently and are sometimes left permanently open during the summer months. The doors are the weak point when considering noise ingress. There is a reasonable amount of background noise from cooking and other operations within the space. Traffic noise is barely audible over background noise. Construction noise is unlikely to be an issue for the majority of the piling works as it will be masked by mechanical services noise and general operational noise. When piling or utilities location works are taking place immediately outside of the building construction noise levels will be elevated and will be audible above background. Utilities location works will be directly outside of the building for approximately 3 days on each side of the road. Piling will be taking place directly outside of the building for approximately 3 days on each side of the road. Further consultation will take place with this receiver before works begin outside of the building and where possible noisy activities will be scheduled
Recommended Building Mitigation None None
None
Page 13
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001189 rd Revision: 03, Date: 3 June 2016
outside of the lunch time period when Food Alley is at its busiest.
5 Albert Street (NZ Gifts)
3 Albert Street
17 Albert Street
There are 16 residential apartments on floors 6 and 7 which are all naturally ventilated. Worst case noise levels at these floors are predicted exceed the noise criteria by less than 5 dB. As this exceedance will be for a short duration façade sound insulation improvements are not considered necessary. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and patrons and patrons choosing to shop elsewhere. The building is mechanically ventilated. They have automatic doors which are not kept open. Background music plays at a low volume. Operational hours are 9.30am to 9.30pm. Construction noise is unlikely to be an issue for the majority of the piling works as it will be masked by the background music. When piling or utilities location works are taking place immediately outside of the building construction noise levels will be elevated and will be audible above background. Further consultation will take place with this receiver before works begin outside of the building and where possible noisy activities will be scheduled to avoid their busiest times. The bakery/ cafe on the ground floor is the most exposed area of the building. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and patrons and patrons choosing to eat elsewhere. However, the doors are kept wide open all day so they are already exposed to high levels of traffic noise, particularly heavy vehicles pulling away from the traffic lights. The radio plays loudly so it can be heard over the traffic noise. To reduce construction noise levels further it would be necessary to fit acoustic seals around the door and to keep it shut during construction activities, except to allow for the timely entry and egress of customers. The business owner indicated that he is not concerned about construction noise and is likely to keep the doors open as usual. The tower is occupied by offices. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and loss of concentration. This part of the building has a glass façade and all offices are mechanically ventilated. The attenuation provided by the façade is predicted to be 35 dB Rw. AS/NZS 2107:2000 “Acoustics – Recommended design sound levels and reverberation times for building interiors” recommends a maximum noise level of 45 dB LAeq for general office areas. Noise levels in the tower section of the building will remain below 45 dB LAeq for the majority of the works. Façade sound insulation improvements are therefore not considered necessary at this receiver. The convenience store on the ground floor is the most exposed area of the building. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and patrons and
None
None
For all windows on the Albert Street façade (up to the 7th Floor) and those on the North and Page 14
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001189 rd Revision: 03, Date: 3 June 2016
patrons choosing to shop elsewhere. The doors are kept wide open all day during the summer and they are already exposed to high levels of traffic noise. The business owner indicated that he is not concerned about construction noise and is likely to keep the doors open as usual. The rest of this building contains mostly offices with a few residential apartments. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff, loss of concentration and reduction in speech intelligibility. The whole building is mechanically ventilated during business hours. The windows on all levels are single glazed in aluminium frame. Seals are in a variable condition, some are slightly perished. The tenants have commented that they currently experience rattling windows due to nearby construction works. Noise measurements were carried out in rooms located on the Albert Street façade to establish the sound reduction performance of the façade with windows closed. A reduction of 25 to 30 dB(A) was measured. When piling or utilities location works are taking place immediately outside of the building construction noise levels will be elevated and will be clearly audible above background. The internal noise level may reach 65 dB LAeq on the first floor and 60 dB LAeq on the second floor during piling if the window seals are deteriorated in these areas. Utilities location works will be directly outside of the building for approximately 5 days on each side of the road. Piling will be taking place directly outside of the building for approximately 5 days on each side of the road. Further consultation will take place with this receiver before works begin outside of the building and where possible noisy activities will be scheduled outside of the most sensitive times.
22 Customs Street
There is a language school at first floor level which requires low background noise levels to operate. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and students, loss of concentration and reduction in speech intelligibility. AS/NZS 2107:2000 “Acoustics – Recommended design sound levels and reverberation times for building interiors” recommends a sound level of 35 to 45 dB LAeq for teaching spaces. The building houses a number of retail outlets. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and patrons and patrons choosing to shop elsewhere. It is a masonry building with single glazed timber sash windows. All areas are mechanically ventilated. Music is played in the retail areas masking any external noise ingress. Construction noise is unlikely to be an issue in the retail areas as it will be masked by the background music and general operational noise. Traffic noise was clearly audible in the meeting room overlooking Albert Street. The window in this room does not seal adequately when shut and noise break in
South façades that are within 10m of the Albert Street façade (up to the 7th Floor) the window seals should be checked and replaced where perished. Secondary glazing is recommended for the following areas: The classrooms of the 1st Floor language school that are located on the Albert Street façade The classrooms of st the 1 Floor language school that are located on the North and South façades within 10m of the Albert Street façade Secondary glazing will be designed to achieve an internal piling noise level of less than 45 dB LAeq within teaching spaces.
Secondary glazing is recommended for the following areas: The ground floor office overlooking Albert Street The level 2 meeting/ training room overlooking Albert Street The level 3 VIP lounge overlooking Customs Street Page 15
Connectus Project #: 2665 Client: Auckland Transport
51 Albert Street 23-29 Albert Street
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001189 rd Revision: 03, Date: 3 June 2016
around the window frame was noticeable. Building soon to be demolished This is the ANZ building. It is occupied by a number of businesses including Chapman Tripp, Vero and ANZ. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff, loss of concentration productivity and reduction in speech intelligibility. ANZ occupy the lower floors of the building that will be most affected by noise. The building has a glazed façade and it is mechanically ventilated. The attenuation provided by the façade is predicted to be 35 dB Rw. AS/NZS 2107:2000 “Acoustics – Recommended design sound levels and reverberation times for building interiors” recommends a maximum noise level of 45 dB LAeq for general office areas. Noise levels in all office areas of the building are predicted to remain at or below 45 dB LAeq for the full duration of the works. The most affected area of the building will be the ground floor atrium that houses the reception area and café. The atrium is extremely reverberant due to its size and the reflective nature of the surface finishes. Once construction noise gets into this space it will build up. The amount of noise in the space is largely dependent on the how much noise breaks in through the revolving door. On 4th March 2016 noise measurements were taken simultaneously on both sides of the revolving doors. Noise break-in through the doors was found to be less than predicted but levels could still reach 65 dB LAeq during the noisiest works immediately outside of the building. Both ANZ and the café owner are willing to accept noise levels of up to 65 dB LAeq for short durations providing that they are well informed of the works.
38 Wyndham Street
Further consultation will also take place with this receiver before works begin outside of the building and where possible noisy activities will be scheduled outside of the most sensitive times. This building is occupied by the Hollywood Bakery at ground floor level and offices above. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and patrons and patrons choosing to eat elsewhere. The operating hours of the bakery are 6.30am to 4.30pm. The front doors are permanently open onto Wyndham Street so they are already exposed to high levels of traffic noise, particularly heavy vehicles pulling away from the traffic lights. They play background noise music at a low volume. The manager indicated that she is not too concerned about construction noise and is likely to keep the doors open as usual.
None
None
None
Despite numerous attempts we were unable to gain access to the main part of the building above the bakery. It is assumed that the building contains offices and is mechanically ventilated throughout. The first three floors above the bakery will be most affected by construction noise. When piling or utilities location works are taking place immediately outside of the building construction Page 16
Connectus Project #: 2665 Client: Auckland Transport
46 to 58 Albert Street 63 Albert Street
61 Albert Street
57 Albert Street 37-39 Albert Street 35 Albert Street 8 Albert Street Sebel Hotel
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001189 rd Revision: 03, Date: 3 June 2016
noise levels on these three floors will likely be audible above background. Utilities location works will be directly outside of the building for approximately 10 days. Piling will be taking place directly outside of the building for approximately 12 days. Buildings soon to be demolished. This building is occupied by AMI insurance at ground floor level and a number of other companies in the offices above. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff, loss of concentration and reduction in speech intelligibility. The building has a glazed façade and it is mechanically ventilated. The attenuation provided by the façade is predicted to be 35 dB Rw. When piling is taking place directly outside of the building internal noise levels are predicted to reach 50 dB LAeq in offices overlooking Albert Street on the th ground to the 5 floor and then reduce to 45 dB LAeq on the remaining floors of the building. This building is occupied by the Shakespeare Hotel and Brewery. There is a bar at ground level which operates from 8am to 4am, a restaurant at first floor level and hotel rooms on the second floor. Loud music is played in the bar area. The owner of this business is not concerned about noise and vibration from the works. Their busiest times are in the evening and through the night when there will be no construction activities taking place. Carpark Construction site Construction site This building contains the Sebel Hotel. There is an office space and café on the 1st floor, a swimming pool on the 5th floor and floors 5 to 29 are hotel rooms. There is a conference room on level 5 but it does not overlook Albert Street. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and guests, loss of concentration, reduction in speech intelligibility and annoyance of café patrons who may then choose to eat elsewhere. The reception area has a glass door leading out on to Albert Street. The door has a 1-2cm gap around the perimeter. Ventilation noise in the reception area is quite loud and background music is played. Traffic noise is barely audible. This area of the building will get the most benefit from the noise barrier but the noise level at the façade is still predicted to be 80 dB LAeq. During the four days of piling directly outside of the building noise level in the reception area are predicted to be 55 dB LAeq. The reception area is going to be exposed to reasonably high noise levels for the duration of the Project. The doors are the weak point in the façade. It is recommended that the gaps around the doors are reduced and acoustic seals fitted.
None
None
None
None None None It is recommended that the gaps around the main doors are reduced and acoustic seals fitted. It is recommended that the gaps around the balcony doors in the café are reduced and acoustic seals fitted. These doors should remain shut during construction works immediately outside of the building.
The hotel rooms are mechanically ventilated with sliding doors leading out to the balconies overlooking Albert Street. When the balcony doors are closed the rooms Page 17
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001189 rd Revision: 03, Date: 3 June 2016
are quiet with very little traffic noise break-in. Only the rooms overlooking Albert Street on levels 5 and 6 will experience noise levels at the façade that exceed the noise criteria by more than 5 dB during piling activities on the east side of Albert Street. With a predicted façade noise reduction of 30 dB Rw the noise levels in these rooms could reach 55 dB LAeq when piling activities are taking place directly outside of the building. The duration of the piling activities that will affect these rooms is 4 days. The pool area has a glass door with no seals opening onto the balcony overlooking Albert Street. Traffic noise levels are masked by mechanical services noise and noise from patrons using the pool. Noise levels due to piling may be audible above the background noise but will not be at a level that interferes with the patron’s use of the pool. The café on the first floor has doors opening onto the balcony overlooking Albert Street where there is a seating area. There is a 1-2cm gap around the perimeter of the doors when closed and the doors are sometimes left open depending on the weather. Music is played reasonably loudly and masks the traffic noise. For four days whilst piling is directly outside of the building construction noise will be audible inside the café even with the music playing. It is recommended that the gaps around the balcony doors in the café are reduced and acoustic seals fitted. Providing that the balcony doors are not left open noise levels should not impact on the cafes operations. Patrons that use the balcony seating area during this four day period will experience noise levels in the region of 85 dB LAeq. Further consultation will take place with the café owner before works begin outside of the building and where possible noisy activities will be scheduled to avoid their busiest times. The office area is on the first floor overlooking Albert Street. The façade is glazed with no window openings. Noise levels in the office are predicted to reach 55 dB LAeq during piling directly outside of the building. 8 Albert Street City Med
The City Med operating hours 8am to 5.30pm Monday to Friday. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and patients, loss of concentration and reduction in speech intelligibility making consultations difficult. To get to the reception area you currently go through the front doors then through another set of doors. However, they are renovating this year and the reception area will be moved closer to the Albert Street façade and will be accessed through the front doors only. The front doors are glass sliding doors with a large gap at the bottom and no seals. The noise impact of piling activities on the reception/ waiting area will depend upon the timing of their renovation works. With the reception/ waiting area in its current location there is unlikely to be any increase in internal noise levels when piling works are being
None
Page 18
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001189 rd Revision: 03, Date: 3 June 2016
carried out. However, if it moves closer to the Albert Street façade construction noise may be an issue. Further advice cannot be given on this area until the exact details of the renovation works are known. There are two operating theatres located at the back of the building near the car park ramp, furthest from Albert Street. Minor operations are conducted here under local anaesthetic. The radiology area is on the Mills Lane façade in the corner furthest from Albert Street. There is unlikely to be any increase in noise levels in these areas. ECG and audiometry are located within the building away from the façades. These are the activities that are most sensitive to noise but there is unlikely to be any increase in noise levels in these areas due to piling works. The doctor’s consultation rooms run along the Mills Lane façade of the building. The façade is fully glazed and all rooms are mechanically ventilated. Noise levels due to piling are predicted to meet the noise criteria along this area of the façade.
70-74 Albert Street
12-26 Swanson Street
The pharmacy is located at the front of the building and is the area that will be most affected by noise from piling activities. Internal noise levels are predicted to reach 55 dB LAeq during piling directly outside of the building on the east side of Albert Street. Piling in this location is expected to last for three days. This building is a hotel. It is mechanically ventilated. Specific effects on this receiver that could result from exceedances of the noise criteria include annoying and disturbing staff or guests. The front doors leading into the reception are good and reasonably loud background music is playing so traffic noise is not audible. The rooms have sliding doors opening onto balconies and windows are single glazed laminate. The piling works do not extend to the area in front of this building. They will only be exposed to noise from piling when it is at the southern tip of the site for approximately 5 days. Only three apartments will be affected (those on the first, second and third floor on the northern end of the Albert Street façade). The general manager is not concerned about noise and vibration providing that there is good communication about the timing and nature of activities that he can pass onto the guests. This building is occupied by the NZ Trade Centre. All areas of the building are mechanically ventilated. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff, loss of concentration and reduction in speech intelligibility.
None
None
The section of the building closest to the works is two stories with a retail/ product display area on the ground floor and parking on the first floor. This part of the building will be most affected by noise from the piling Page 19
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001189 rd Revision: 03, Date: 3 June 2016
works. Noise levels at the first floor are predicted to be 80 to 85 dB LAeq during piling works but as this is a car park no further mitigation is required. Worst case noise levels at the ground floor retail/ product display area are predicted to exceed the noise criteria by no more than 5 dB so no further no further mitigation is required. The main tower section of the building is located further down Swanson Street away from the works. Noise levels at the most exposed façade of this section of the building will not exceed the noise criteria by more than 5 dB during the piling works.
Where building modification is recommended the following actions will be undertaken:
The building owner will be contacted to discuss details of the recommended building mitigation.
If the building owner wishes to proceed with the recommended building mitigation, arrangements will be made to visit the property to inspect the areas of the building where acoustic treatment is proposed and identify any issues that could affect installation of the mitigation. Additional noise measurements will be taken, where necessary, to confirm the acoustic performance requirements of the mitigation.
Any approvals required for the works under the Resource Management Act, Building Act and Historic Place Act will be obtained.
A legal agreement will be prepared for the installation of the acoustic treatment. The agreement will contain an explicit description of the acoustic treatment to be installed. Under the agreement Auckland Transport will take responsibility for commissioning the works (such as airflow and noise from ventilation systems) and for ensuring any required building consent inspections occur. The agreement includes a form to be signed by the property owner following commissioning to acknowledge that the works specified have been completed.
On completion of the mitigation works the property will be reinstated to a similar condition to that existing immediately prior to the works commencing.
Where secondary glazing is recommended the following should be implemented:
5.2
The existing window must be sealed before the secondary window is installed.
The secondary window shall be installed in a separate frame to the primary window, with no direct connections between the two frames.
The reveals between the primary and secondary windows shall be lined with an acoustically absorbent material having at least absorption class C in accordance with ISO 11654:1997.
Opening sections of the secondary window shall be aligned with openings in the primary window.
VIBRATION
In addition to the general noise and vibration control measures outlined in Section 7 of the Project CNV DWP the following specific vibration mitigation measures (Table 7) should be implemented if the initial on site vibration monitoring demonstrates that the building damage vibration limits will be exceeded:
Page 20
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001189 rd Revision: 03, Date: 3 June 2016
Table 7 Specific Vibration Mitigation Measures
Equipment/process
Vibration control measures
Excavator mounted rock breaker
Use lower vibration generating equipment such as a hand held jack hammer
6 COMMUNICATION AND CONSULTATION Section 9.1 of the Project CNV DWP details the communication procedures in relation to construction noise and vibration effects. The complaints process is detailed in Section 9.2 of the CNV DWP. Consultation with the stakeholders identified in this SSCNVMP took place from mid-November to late December 2015. Topics that were covered included:
Sequencing of construction activities
Likely equipment and associated noise and vibration levels
Proposed mitigation and management measures
Construction of their buildings
Operational hours of their businesses
Operating environment that is required by the businesses
Further details of the meetings and comments made by the stakeholders are provided in Appendix D of the CNV DWP.
Page 21
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001189 rd Revision: 03, Date: 3 June 2016
7 MONITORING Section 10 of the Project CNV DWP provides details of the methodology for noise and vibration monitoring.
7.1
NOISE MONITORING
Noise monitoring will be carried out when concrete breaking begins within 20m of the building and when piling begins within 15m of the building at the locations detailed in Table 8. The monitoring will be carried out at first floor level unless a location at a higher level is specified. Table 8 Noise Monitoring Locations
Receiver
Monitoring Location
9 Albert Street
1m from façade of building
5 Albert Street
1m from façade of building Inside the gift shop
3 Albert Street
1m from façade of building
17 Albert Street
1m from façade of building In a Language School classroom overlooking Albert Street. In one of the offices on Level 2
22 Customs Street
1m from façade of building In the most exposed retail area In the Level 2 meeting/ training room overlooking Albert Street
23-29 Albert Street
1m from façade of building In the ground floor reception/ café area
63 Albert Street
1m from façade of building
61 Albert Street
1m from façade of building
8 Albert Street
1m from façade of building
Sebel Hotel
In the hotel reception In the café In one of the Level 5 rooms overlooking Albert Street
8 Albert Street
1m from façade of building
City Med 70-74 Albert Street
1m from façade of building
12-26 Swanson Street
1m from façade of building
7.2
VIBRATION MONITORING
Vibration monitoring will be carried out when works begin on site to determine actual equipment vibration levels and the attenuation provided by the local ground conditions. If the initial vibration monitoring demonstrates that the emission radius for the hydraulic rotary rig and the excavator mounted rock breaker are similar to those detailed in Section 5.2 of the CNV DWP then the monitoring Page 22
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001189 rd Revision: 03, Date: 3 June 2016
as detailed below will be carried out. If the monitoring demonstrates that vibration levels are significantly lower then less properties may require monitoring, if they are higher then more properties may require monitoring. Vibration monitoring will be carried out at the following receivers when CFA piling begins within 5m of the building:
22 Customs Street
5 Albert Street
9 Albert Street
17 Albert Street
Vibration monitoring will be carried out at the following receivers when concrete breaking begins within 16m of the building:
22 Customs Street
5 Albert Street
9 Albert Street
17 Albert Street
55 Albert Street
61 Albert Street
57 Albert Street
Vibration monitoring will be carried out at the following receivers when concrete breaking begins within 10m of the building:
8 Albert Street
70-74 Albert Street
Vibration monitoring will be carried out at the following receivers when concrete breaking begins within 7m of the building:
3 Albert Street
23-29 Albert Street
38 Wyndham Street
58 Albert Street
63 Albert Street
8 STAFF Before working on these activities all staff will receive training in accordance with Section 7.2 of the CNV DWP and will read and comply with this SSCNVMP.
Page 23
Auckland City Rail Link In association with:
ENABLING WORKS CONTRACT 2 SITE SPECIFIC CONSTRUCTION NOISE AND VIBRATION MANAGEMENT PLAN: EXCAVATION Separable Portion 1 – Cut and Cover Works Document Ref: CRL-PAT-ENV-CON-PLN-001187 Revision: 03
FINAL 3rd June 2016
COMMERCIAL IN CONFIDENCE
This page intentionally left blank.
DOCUMENT INFORMATION Organisation:
Connectus
Document Title:
SITE SPECIFIC CONSTRUCTION NOISE AND VIBRATION MANAGEMENT PLAN: EXCAVATION
Fulcrum Document Number:
CRL-PAT-ENV-CON-PLN-001187
Document based on MMS No:
n/a
Client:
Auckland Transport
Project:
CRL Enabling Works: Contract Two
Location:
Auckland CBD
Project No:
2665
REVISION HISTORY Rev
Date
Details st
01
1
Draft for Connectus review
Author
Approver
C. Drewery
C Hind
02
21/03/16
Final
C. Drewery
C Hind
03
3/06/16
Final
C. Drewery
C Hind
This document remains the property of Connectus. Its contents are confidential and shall not be reproduced, destroyed or given away without the express, written permission of Connects. The electronic version of this document in MMS Database on designated server(s) is the Master Copy and is a controlled document. Unless specifically noted thereon, other copies of this document are uncontrolled.
This page intentionally left blank
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001187 rd Revision: 03, Date: 3 June 2016
Table of Contents Document information .........................................................................................................................3 Revision History ..................................................................................................................................3 1
Introduction........................................................................................................................7 1.1
Objective
7
1.2
Site plan
7
2
Receivers ..........................................................................................................................8
3
Activities ............................................................................................................................9
4
Predicted Noise and vibration levels................................................................................. 10 4.1
Noise
10
4.2
Vibration
14
5
Mitigation ......................................................................................................................... 15 5.1
Noise
15
5.2
Vibration
20
6
Communication and Consultation..................................................................................... 21
7
Monitoring ....................................................................................................................... 22
8
7.1
Noise monitoring
22
7.2
Vibration monitoring
22
Staff................................................................................................................................. 23
Page 5
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001187 rd Revision: 03, Date: 3 June 2016
This page intentionally left blank
Page 6
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001187 rd Revision: 03, Date: 3 June 2016
1 INTRODUCTION
This is a Site Specific Construction Noise and Vibration Management Plan (SSCNVMP) and forms part of the Construction Noise and Vibration Delivery Work Plan (CNV DWP) for the CRL Contract 2 Enabling Works (the ‘Project’). This SSCNVMP provides specific assessment of construction noise and vibration from trench excavation and spoil handling, including shotcrete, strip drain and rock dowel installation. This SSCNVMP should be read in conjunction with the CNV DWP (Document Ref: CRLPAT-ENV-CON-PLN-000903 Revision 6 dated 3rd June 2016) as it contains further details of the project, noise criteria, monitoring, general mitigation measures and other information. Details of the construction methodology are contained in the Project Construction Environmental Management Plan (CEMP). Acoustic terms are defined in the Acoustic Glossary in the CNV DWP.
1.1
OBJECTIVE
The objective of this SSCNVMP is to detail the best practicable option to avoid, remedy or mitigate adverse effects on sensitive receivers resulting from construction noise and vibration that does not comply with the Project Standards defined in Section 1.2 of the CNV DWP.
1.2
SITE PLAN
The excavation area is shown in Figure 1. Excavation in the Customs Street Intersection will be below the traffic decks while the remainder of Albert Street will be an open trench. Figure 1 Site Plan
Page 7
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001187 rd Revision: 03, Date: 3 June 2016
2 RECEIVERS
Receivers where noise levels due to excavation works have the potential to exceed project noise or vibration standards are listed below, along with building use. Table 1 Affected receivers
Historic / vibration sensitive
Minimum Distance to Works, m
Noise Criteria, dB dB LAeq LAFmax
Vibration Criteria, (mm/s)
Address
Building use
9 Albert Street
Mixed Use
Y
5
75*
90*
3
5 Albert Street
Commercial
Y
5
75
-
3
3 Albert Street
Commercial
N
5
75
-
20
17 Albert Street
Commercial
Y
5
75
-
3
15 Albert Street
Vacant
Y
5
-
-
3
13 Albert Street
Vacant
Y
5
-
-
3
22 Customs Street
Commercial
Y
5
75
-
3
38 Wyndham Street
Commercial
N
6
75
-
20
61 Albert Street
Mixed Use
Y
6
75*
90*
3
57 Albert Street
Commercial
Y
6
75
-
3
55 Albert Street
Commercial
Y
6
75
-
3
51 Albert Street
Commercial
Y
6
75
-
3
41 Albert Street
This building has its own SSCNVMP so is not included in this plan
23-29 Albert Street
Commercial
N
6
75
-
20
58 Albert Street
Commercial
N
7
75
-
20
63 Albert Street
Commercial
N
7
75
-
20
46-50 Albert Street
Commercial
Y
7
75
-
3
52-56 Albert Street
Commercial
Y
7
75
-
3
12-26 Swanson Street
Commercial
N
7
75
-
20
37-39 Albert Street
Construction Site
N
6
-
-
-
70-74 Albert Street
Mixed Use
N
8
75*
90*
5
35 Albert Street
Construction Site
N
6
-
-
-
22-26 Albert Street 8 Albert Street 65-71 Albert Street
This building has its own SSCNVMP so is not included in this plan Mixed Use
N
8
75*
90*
5
This building has its own SSCNVMP so is not included in this plan
34-36 Wyndham Street
Commercial
33 Wyndham Street 26 Wyndham Street
Y
17
75
-
3
Commercial
N
20
75
-
20
Commercial
N
24
76
-
20
Page 8
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001187 rd Revision: 03, Date: 3 June 2016
* This is the Monday to Saturday 07:00 to 22:00 noise criteria. The majority of works will be carried out during this period. For residential receivers the noise limit is reduced to 65 dB L Aeq & 80 dB LAFmax on Sundays and Public Holidays between 07:00 to 22:00 and to 60 dB LAeq & 75 dB LAFmax at all other times. Designation Condition 38.4 allows for the Project vibration limits to be relaxed by a SSCVMP but only for a building, structure or infrastructure that has been assessed by a suitably qualified and experienced structural engineer and where it has been deemed to be capable of withstanding higher vibration levels without sustaining building or structural damage, and where appropriate vibration and building condition monitoring regimes are in place. Based on the building condition surveys and the initial assessments by the structural engineer the vibration limits will not be reduced.
3 ACTIVITIES Construction activities along with proposed start and end dates, and hours or operation, are shown in Table 2 below. Shotcrete, strip drain and rock dowel installation are contained within the excavation start and end dates for the respective areas and layers shown. Table 2 Construction activities
Construction Activity
Remove existing road surface
Excavation 1st Layer
Excavation 2nd to Bottom
Area of works
Activity Start Date
Activity End Date
Hours
South end to Ch550
23 Mar 2017
28 Mar 2017
Ch550 to Swanson
23 Mar 2017
27 Mar 2017
7am – 7pm
Swanson to Wolfe
26 May 2017
30 May 2017
Mon - Sat
Wolfe to North end
03 Jul 2017
05 Jul 2017
South end to Ch550
29 Mar 2017
04 Apr 2017
Ch550 to Swanson
28 Mar 2017
19 Apr 2017
7am – 7pm
Swanson to Wolfe
31 May 2017
28 Jun 2017
Mon - Sat
Wolfe to North end
06 Jul 2017
02 Aug 2017
South end to Ch550
21 Apr 2017
01 Sep 2017
Ch550 to Swanson
20 Apr 2017
07 Sep 2017
7am – 7pm
Swanson to Wolfe
29 Jun 2017
05 Dec 2017
Mon - Sat
Wolfe to North end
03 Aug 2017
23 Mar 2018
Details of construction equipment that is likely to be used for each of the above activities and the associated noise levels can be found in Appendix C of the CNV DWP. Details of the equipment that is expected to generate high levels of vibration can be found in Appendix B of the CNV DWP. The equipment levels detailed in Appendices B and C of the CNV DWP are placeholders. All equipment will be measured operating independently and then actual equipment noise/ vibration levels and model numbers will be recorded and updated within the table.
Page 9
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001187 rd Revision: 03, Date: 3 June 2016
4 PREDICTED NOISE AND VIBRATION LEVELS 4.1
NOISE
The predicted worst case noise levels from each activity received at the most exposed part of each receiver are shown below in Table 3. These levels correspond to the construction equipment being located at its nearest position to the receiver and assume there is no physical mitigation between the noise source and the faรงade of the building. Table 3 Predicted noise levels (no mitigation)
Address
Predicted worst case noise levels (no mitigation), dB LAeq
Project Noise Standards exceedance, dB
Removal of existing road surface 9 Albert Street
93
18
5 Albert Street
93
18
3 Albert Street
93
18
17 Albert Street
92
17
15 Albert Street
92
17
13 Albert Street
92
17
22 Customs Street
92
17
38 Wyndham Street
90
15
61 Albert Street
90
15
57 Albert Street
90
15
55 Albert Street
90
15
51 Albert Street
90
15
23-29 Albert Street
90
15
58 Albert Street
89
14
63 Albert Street
89
14
46-50 Albert Street
89
14
52-56 Albert Street
89
14
12-26 Swanson Street
89
14
37-39 Albert Street
89
14
70-74 Albert Street
88
13
35 Albert Street
88
13
22-26 Albert Street
88
13
8 Albert Street
88
13
34-36 Wyndham Street
80
5
33 Wyndham Street
78
3
26 Wyndham Street
76
1 Page 10
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001187 rd Revision: 03, Date: 3 June 2016
Excavation of 1st Layer 9 Albert Street
88
13
5 Albert Street
88
13
3 Albert Street
88
13
17 Albert Street
87
12
15 Albert Street
87
12
13 Albert Street
87
12
22 Customs Street
87
12
38 Wyndham Street
85
10
61 Albert Street
85
10
57 Albert Street
85
10
55 Albert Street
85
10
51 Albert Street
85
10
23-29 Albert Street
85
10
58 Albert Street
84
9
63 Albert Street
84
9
46-50 Albert Street
84
9
52-56 Albert Street
84
9
12-26 Swanson Street
84
9
37-39 Albert Street
84
9
70-74 Albert Street
83
8
35 Albert Street
83
8
22-26 Albert Street
83
8
8-12 Albert Street
83 Excavation of 2nd layer to bottom
8
9 Albert Street
84
9
5 Albert Street
83
8
3 Albert Street
83
8
17 Albert Street
83
8
15 Albert Street
83
8
13 Albert Street
83
8
22 Customs Street
83
8
38 Wyndham Street
79
4
61 Albert Street
80
5
57 Albert Street
80
5
55 Albert Street
81
6
51 Albert Street
81
6
23-29 Albert Street
81
6
58 Albert Street
79
4
Page 11
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001187 rd Revision: 03, Date: 3 June 2016
63 Albert Street
79
4
46-50 Albert Street
78
3
52-56 Albert Street
80
5
12-26 Swanson Street
79
4
37-39 Albert Street
79
4
70-74 Albert Street
78
3
35 Albert Street
79
4
8 Albert Street
78
3
Rock fall protection netting 6 Albert Street
85
10
17 Albert Street
84
9
15 Albert Street
85
10
13 Albert Street
85
10
9 Albert Street
86
11
7 Albert Street
86
11
3 Albert Street
85
10
58 Albert Street
84
9
51 Albert Street
83
8
38 Wyndham Street
83
8
61 Albert Street
83
8
52-56 Albert Street
84
9
57 Albert Street
83
8
55 Albert Street
83
8
37-39 Albert Street
83
8
23-29 Albert Street
83
8
63 Albert Street
83
8
46-50 Albert Street
82
7
12-26 Swanson Street
82
7
35 Albert Street
81
6
8 Albert Street
82
7
70-74 Albert Street
80
5
Shotcrete placement 38 Wyndham Street
79
4
63 Albert Street
83
8
65-71 Albert Street
76
1
Pre-drilling 6 Albert Street
87
12
17 Albert Street
86
11
15 Albert Street
87
12
13 Albert Street
87
12 Page 12
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001187 rd Revision: 03, Date: 3 June 2016
9 Albert Street
88
13
5 Albert Street
88
13
3 Albert Street
87
12
58 Albert Street
86
11
51 Albert Street
85
10
38 Wyndham Street
85
10
61 Albert Street
85
10
52-56 Albert Street
86
11
57 Albert Street
85
10
55 Albert Street
85
10
37-39 Albert Street
85
10
23-29 Albert Street
85
10
63 Albert Street
85
10
46-50 Albert Street
84
9
12-26 Swanson Street
84
9
35 Albert Street
83
8
8 Albert Street
84
9
70-74 Albert Street
82
7
34-36 Wyndham Street
76
1
Drilling and rock dowel installation 6 Albert Street
88
13
17 Albert Street
87
12
15 Albert Street
88
13
13 Albert Street
88
13
9 Albert Street
89
14
5 Albert Street
89
14
3 Albert Street
88
13
58 Albert Street
87
12
51 Albert Street
86
11
38 Wyndham Street
86
11
61 Albert Street
86
11
52-56 Albert Street
87
12
57 Albert Street
86
11
55 Albert Street
86
11
37-39 Albert Street
86
11
23-29 Albert Street
86
11
63 Albert Street
86
11
46-50 Albert Street
85
10
12-26 Swanson Street
85
10
35 Albert Street
84
9 Page 13
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001187 rd Revision: 03, Date: 3 June 2016
8 Albert Street
85
10
70-74 Albert Street
83
8
34-36 Wyndham Street
77
2
33 Wyndham Street
76
1
4.2
VIBRATION
Buildings which are classed as high or medium risk of damage as a result of rock dowel pre-drilling are shown in Table 4. A receiver is classified as ‘high risk’ if it is located within the emission radius for an activity, and ‘medium risk’ if it is close to the contour with possible intermittent exceedance. Table 4 Vibration risk class
Address
Building type
Distance to works (m)
Risk class
Pre-drilling 6 Albert Street
Historic / vibration sensitive
5
High
17 Albert Street
Historic / vibration sensitive
5
High
15 Albert Street
Historic / vibration sensitive
5
High
13 Albert Street
Historic / vibration sensitive
5
High
9 Albert Street
Historic / vibration sensitive
5
High
7 Albert Street
Historic / vibration sensitive
5
High
3 Albert Street
Commercial
5
High
58 Albert Street
Commercial
7
High
51 Albert Street
Historic / vibration sensitive
6
High
38 Wyndham Street
Commercial
6
High
61 Albert Street
Historic / vibration sensitive
6
High
52-56 Albert Street
Historic / vibration sensitive
7
High
57 Albert Street
Historic / vibration sensitive
6
High
55 Albert Street
Historic / vibration sensitive
6
High
41-45 Albert Street
Historic / vibration sensitive
6
High
23-29 Albert Street
Commercial
6
High
63 Albert Street
Commercial
7
High
46-50 Albert Street
Historic / vibration sensitive
7
High
12-26 Swanson Street
Commercial
7
Medium
12 Albert Street
Mixed Use
8
High
70-74 Albert Street
Mixed Use
8
High
Page 14
Connectus Project #: 2665 Client: Auckland Transport
5 MITIGATION 5.1
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001187 rd Revision: 03, Date: 3 June 2016
NOISE
Mitigation is required to meet the noise criteria at the nearest sensitive receivers. In addition to the general noise and vibration control measures outlined in Section 7 of the CNV DWP, the following specific noise mitigation measures should be implemented (Table 5): Table 5 Specific Noise Mitigation Measures
Equipment/process
Noise control measures
Excavators, bobcats, loaders
Grease tracks regularly
Crane
Use straps rather than chains unless a risk assessment deems the use of straps unsafe.
In addition to these measures, noise barriers/hoardings between the work site and the receiver will be used to reduce noise levels. These will be least 1.8m high and have a mass equal to or greater than 10 kg/m2. Panels will be abutted or overlapped to provide a continuous screen with no gaps. It may be acceptable to use a proprietary barrier with a reduced mass providing the required attenuation can be achieved. The contractor will seek approval from the Project Acoustic Specialist before using a proprietary barrier product on site. Indicative location of noise barriers is shown in green in Figure 2 below. Figure 2 Noise barriers
5.1.1
Internal noise levels
With the above mitigation and management measures implemented and barriers installed, the noise levels at the most exposed faรงade of a number of properties will still exceed the noise criteria by more than 5 dB during some Project construction activities. These properties are detailed in Table 6 along with any further mitigation necessary to achieve acceptable internal noise levels.
Page 15
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001187 rd Revision: 03, Date: 3 June 2016
Table 6 Building Mitigation Measures
Address 15 Albert Street 13 Albert Street 9 Albert Street
Comments Building currently vacant Building currently vacant The bottom floors of the building are occupied by Food Alley and are mechanically ventilated. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and patrons and patrons choosing to eat elsewhere. The glass doors are automated but they open frequently and are sometimes left permanently open during the summer months. The doors are the weak point when considering noise ingress. There is a reasonable amount of background noise from cooking and other operations within the space. Traffic noise is barely audible over background noise. Construction noise is unlikely to be an issue for the majority of the excavation works as it will be masked by mechanical services noise and general operational noise. In addition to this as the works get deeper into the trench the noise level at the faรงade of the building will reduce.
Recommended Building Mitigation None None
None
The noisiest activity during the excavation phase will be removal of the road surface which will only take two days outside of this receiver.
5 Albert Street (NZ Gifts)
3 Albert Street
There are 16 residential apartments on floors 6 and 7 which are all naturally ventilated. Worst case noise levels at these floors are predicted exceed the noise criteria by less than 5 dB. As this exceedance will be for a short duration faรงade sound insulation improvements are not considered necessary. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and patrons and patrons choosing to shop elsewhere. The building is mechanically ventilated. They have automatic doors which are not kept open. Background music plays at a low volume. Operational hours are 9.30am to 9.30pm. Construction noise is unlikely to be an issue for the majority of the excavation works as it will be masked by the background music. When the road surface is being removed immediately outside of the building construction noise levels will be elevated and will be audible above background. This activity will only take place for two days outside of this receiver. The bakery/ cafe on the ground floor is the most exposed area of the building. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and patrons and patrons choosing to eat elsewhere. The doors are kept wide open all day and so they are already exposed to high levels of traffic noise, particularly heavy vehicles pulling away from the traffic lights. The radio plays loudly
None
None
Page 16
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001187 rd Revision: 03, Date: 3 June 2016
so it can be heard over the traffic noise. The business owner indicated that he is not concerned about construction noise and is likely to keep the doors open as usual.
17 Albert Street
The tower is occupied by offices. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and loss of concentration. It has a glass façade and all offices are mechanically ventilated. Noise levels in the tower section of the building will remain below 45 dB LAeq during the excavation works. Façade sound insulation improvements are therefore not considered necessary at this receiver. The convenience store on the ground floor is the most exposed area of the building. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and patrons and patrons choosing to shop elsewhere. The rest of this building contains mostly offices, a few residential apartments and a language school. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff, loss of concentration and reduction in speech intelligibility.
22 Customs Street
51 Albert Street 23-29 Albert Street
38 Wyndham Street
Recommendations for façade sound insulation improvements are given in the SSCNVMP for the Albert Street piling works (Document Reference CRL-PAT-ENVCON-PLN-001189). With this mitigation implemented noise levels in all areas of the building will be acceptable and will not impact business operations or disturb residents. The building houses a number of retail outlets. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and patrons and patrons choosing to shop elsewhere. Recommendations for façade sound insulation improvements are given in the SSCNVMP for the Albert Street piling works (Document Reference CRL-PAT-ENVCON-PLN-001189). With this mitigation implemented noise levels in all areas of the building will be acceptable and will not impact business operations. Building soon to be demolished None This is the ANZ building. It is occupied by a number of businesses including Chapman Tripp, Vero and ANZ. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff, loss of concentration productivity and reduction in speech intelligibility. ANZ occupy the lower floors of the building that will be most affected by noise. The building has a glazed façade and it is mechanically ventilated. Noise levels in all office areas of the building are predicted to remain at or below 45 dB LAeq for the full duration of the works. None The most affected area of the building will be the ground floor atrium that houses the reception area and café. Both ANZ and the café owner are willing to accept elevated noise levels for short durations providing that they are well informed of the works. Further consultation will also take place with this receiver before works begin outside of the building and where possible noisy activities will be scheduled outside of the most sensitive times. This building is occupied by the Hollywood Bakery at ground floor level and offices above. Specific effects on this receiver that could result from exceedances of the
None
Page 17
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001187 rd Revision: 03, Date: 3 June 2016
noise criteria include the annoyance of staff and patrons and patrons choosing to eat elsewhere. The operating hours of the bakery are 6.30am to 4.30pm. The front doors are permanently open onto Wyndham Street so they are already exposed to high levels of traffic noise, particularly heavy vehicles pulling away from the traffic lights. They play background noise music at a low volume. The manager indicated that she is not too concerned about construction noise and is likely to keep the doors open as usual.
46 to 58 Albert Street 63 Albert Street
61 Albert Street
57 Albert Street 37-39 Albert Street 35 Albert Street 8 Albert Street Sebel Hotel
Despite numerous attempts we were unable to gain access to the main part of the building above the bakery. It is assumed that the building contains offices and is mechanically ventilated throughout. The first three floors above the bakery will be most affected by construction noise. When road surface removal works are taking place immediately outside of the building construction noise levels on these three floors will likely be audible above background. Road surface removal will be directly outside of the building for approximately two days. Buildings soon to be demolished. This building is occupied by AMI insurance at ground floor level and a number of other companies in the offices above. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff, loss of concentration and reduction in speech intelligibility. The building has a glazed façade and it is mechanically ventilated. The attenuation provided by the façade is predicted to be 35 dB Rw. When road surface removal is taking place directly outside of the building internal noise levels are predicted to reach 50 dB LAeq in offices overlooking Albert Street on the ground to the 5th floor and then reduce to 45 dB LAeq on the remaining floors of the building. For all other excavation activities the internal noise levels will be further reduced. This building is occupied by the Shakespeare Hotel and Brewery. There is a bar at ground level which operates from 8am to 4am, a restaurant at first floor level and hotel rooms on the second floor. Loud music is played in the bar area. The owner of this business is not concerned about noise and vibration from the works. Their busiest times are in the evening and through the night when there will be no construction activities taking place. Carpark Construction site
None
None
None
None None
Construction site None This building contains the Sebel Hotel. There is an office space and café on the 1st th floor, a swimming pool on the 5 floor and floors 5 to 29 are hotel rooms. There is a conference room on level 5 but it does not overlook Albert Street. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and guests, loss of concentration, reduction in speech intelligibility and annoyance of café patrons who may then choose to eat elsewhere. During the two days of road surface removal directly outside of the building noise level in the reception area are predicted to be 55 dB LAeq. As the works get deeper into the trench the noise level at the façade of the building will reduce and internal Page 18
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001187 rd Revision: 03, Date: 3 June 2016
noise levels will reduce accordingly. Only the hotel rooms overlooking Albert Street on levels 5 and 6 will experience noise levels at the façade that exceed the noise criteria by more than 5 dB during removal of the road surface in front of the building. With a predicted façade noise reduction of 30 dB Rw the noise levels in these rooms could reach 55 dB LAeq when the road surface is being removed directly outside of the building. The duration of the road surface removal works that will affect these rooms is two days. For two days whilst road surface removal works are directly outside of the building construction noise will be audible inside the café even with the music playing. It is recommended that the gaps around the balcony doors in the café are reduced and acoustic seals fitted. Providing that the balcony doors are not left open noise levels should not impact on the cafes operations. Patrons that use the balcony seating area during this two day period will experience noise levels in the region of 85 dB LAeq. Further consultation will take place with the café owner before works begin outside of the building and where possible noisy activities will be scheduled to avoid their busiest times. As the works get deeper into the trench the noise level at the façade of the building will reduce and internal noise levels will reduce accordingly. Noise levels in the office are predicted to reach 55 dB LAeq during road surface removal directly outside of the building. As the works get deeper into the trench the noise level will reduce. Recommendations for façade sound insulation improvements are given in the SSCNVMP for the Albert Street piling works (Document Reference CRL-PAT-ENVCON-PLN-001189). 8 Albert Street City Med
The City Med operating hours 8am to 5.30pm Monday to Friday. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and patients, loss of concentration and reduction in speech intelligibility making consultations difficult. With the reception/ waiting area in its current location there is unlikely to be any increase in internal noise levels when excavation works are being carried out. However, if it moves closer to the Albert Street façade during renovation of the space, construction noise may be an issue. Further advice cannot be given on this area until the exact details of the renovation works are known. None There is unlikely to be any increase in noise levels in the radiology area, operating theatres, ECG and audiometry during excavation works. Noise levels due to excavation activities are predicted to meet the noise criteria along the area of the Mills Lane façade where the doctors’ consultation rooms are located.
70-74 Albert Street
Internal noise levels are predicted to reach 55 dB LAeq in the pharmacy during road surface removal directly outside of the building. This activity is expected to last for two days then noise levels will begin to reduce as the works get deeper into the trench. This building is a hotel. Specific effects on this receiver that could result from exceedances of the noise criteria include annoying and disturbing staff or guests. It is mechanically ventilated. The excavation works do not
None
Page 19
Connectus Project #: 2665 Client: Auckland Transport
12-26 Swanson Street
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001187 rd Revision: 03, Date: 3 June 2016
extend to the area in front of this building. They will only be exposed to noise from excavation when it is at the southern tip of the site. Only three apartments will be affected (those on the first, second and third floor on the northern end of the Albert Street faรงade). The general manager is not concerned about noise and vibration providing that there is good communication about the timing and nature of activities that he can pass onto the guests. This building is occupied by the NZ Trade Centre. All areas of the building are mechanically ventilated. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff, loss of concentration and reduction in speech intelligibility. The section of the building closest to the works is two stories with a retail/ product display area on the ground floor and parking on the first floor. This part of the building will be most affected by noise from the excavation works. Noise levels at the first floor are predicted to be 80 to 85 dB LAeq during road surface removal but as this is a car park no further mitigation is required. Worst case noise levels at the ground floor retail/ product display area are predicted to exceed the noise criteria by no more than 5 dB so no further no further mitigation is required.
None
The main tower section of the building is located further down Swanson Street away from the works. Noise levels at the most exposed faรงade of this section of the building will not exceed the noise criteria by more than 5 dB during the piling works.
5.2
VIBRATION
In addition to the general noise and vibration control measures outlined in Section 7 of the Project CNV DWP the following specific vibration mitigation measures (Table 7) should be implemented if the initial on site vibration monitoring demonstrates that the building damage vibration limits will be exceeded: Table 7 Specific Vibration Mitigation Measures
Equipment/process
Vibration control measures
Excavator mounted rock breaker
Use lower vibration generating equipment such as a hand held jack hammer
Page 20
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001187 rd Revision: 03, Date: 3 June 2016
6 COMMUNICATION AND CONSULTATION Section 9.1 of the Project CNV DWP details the communication procedures in relation to construction noise and vibration effects. The complaints process is detailed in Section 9.2 of the CNV DWP. Consultation with the stakeholders identified in this SSCNVMP took place from mid-November to late December 2015. Topics that were covered included:
Sequencing of construction activities
Likely equipment and associated noise and vibration levels
Proposed mitigation and management measures
Construction of their buildings
Operational hours of their businesses
Operating environment that is required by the businesses
Further details of the meetings and comments made by the stakeholders are provided in Appendix D of the CNV DWP.
Page 21
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001187 rd Revision: 03, Date: 3 June 2016
7 MONITORING Section 10 of the Project CNV DWP provides details of the methodology for noise and vibration monitoring.
7.1
NOISE MONITORING
Noise monitoring will be carried out when road surface removal begins within 20m of the building at the locations detailed in Table 8. Further monitoring will take place in these locations at regular intervals (monthly as a minimum). The monitoring will be carried out at first floor level unless a location at a higher level is specified. Table 8 Noise Monitoring Locations
Receiver
Monitoring Location
9 Albert Street
1m from façade of building
5 Albert Street
1m from façade of building
3 Albert Street
1m from façade of building
17 Albert Street
1m from façade of building
22 Customs Street
1m from façade of building
23-29 Albert Street
1m from façade of building
63 Albert Street
1m from façade of building
61 Albert Street
1m from façade of building
8 Albert Street (Sebel Hotel)
1m from façade of building
8 Albert Street (City Med)
1m from façade of building
70-74 Albert Street
1m from façade of building
12-26 Swanson Street
1m from façade of building
7.2
VIBRATION MONITORING
Vibration monitoring will be carried out when works begin on site to determine actual equipment vibration levels and the attenuation provided by the local ground conditions. If the initial vibration monitoring demonstrates that the emission radius for the excavator mounted concrete breaker is similar to that detailed in Section 5.2 of the CNV DWP then the monitoring as detailed below will be carried out. If the monitoring demonstrates that vibration levels are significantly lower then less properties may require monitoring, if they are higher then more properties may require monitoring. Vibration monitoring will be carried out at the following receivers when concrete breaking begins within 16m of the building:
22 Customs Street
5 Albert Street
9 Albert Street
17 Albert Street
55 Albert Street Page 22
Connectus Project #: 2665 Client: Auckland Transport
61 Albert Street
57 Albert Street
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001187 rd Revision: 03, Date: 3 June 2016
Vibration monitoring will be carried out at the following receivers when concrete breaking begins within 10m of the building:
8 Albert Street
70-74 Albert Street
Vibration monitoring will be carried out at the following receivers when concrete breaking begins within 7m of the building:
3 Albert Street
23-29 Albert Street
38 Wyndham Street
58 Albert Street
63 Albert Street
8 STAFF Before working on these activities all staff will receive training in accordance with Section 7.2 of the CNV DWP and will read and comply with this SSCNVMP.
Page 23
Auckland City Rail Link In association with:
ENABLING WORKS CONTRACT 2 SITE SPECIFIC CONSTRUCTION NOISE AND VIBRATION MANAGEMENT PLAN: Tunnel Construction Separable Portion 1 – Cut and Cover Works Document Ref: CRL-PAT-ENV-CON-PLN-001184 Revision: 03
FINAL 3rd June 2016
COMMERCIAL IN CONFIDENCE
This page intentionally left blank.
DOCUMENT INFORMATION Organisation:
Connectus
Document Title:
Site Specific Construction Noise and Vibration Management Plan: Tunnel Construction
Fulcrum Document Number:
CRL-PAT-ENV-CON-PLN-001184
Document based on MMS No:
n/a
Client:
Auckland Transport
Project:
CRL Enabling Works: Contract Two
Location:
Auckland CBD
Project No:
2665
REVISION HISTORY Rev
Date
Details st
01
1
Draft for Connectus review
Author
Approver
C. Drewery
C Hind
02
21/03/16
Final
C. Drewery
C Hind
03
3/06/16
Final
C. Drewery
C Hind
This document remains the property of Connectus. Its contents are confidential and shall not be reproduced, destroyed or given away without the express, written permission of Connects. The electronic version of this document in MMS Database on designated server(s) is the Master Copy and is a controlled document. Unless specifically noted thereon, other copies of this document are uncontrolled.
This page intentionally left blank
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001184 rd Revision: 03, Date: 3 June 2016
Table of Contents Document information .........................................................................................................................3 Revision History ..................................................................................................................................3 1
Introduction........................................................................................................................7 1.1
Objective
7
1.2
Site plan
7
2
Receivers ..........................................................................................................................8
3
Activities ............................................................................................................................9
4
Predicted Noise levels .......................................................................................................9
5
Mitigation ......................................................................................................................... 10 5.1
Noise
10
5.2
Vibration
13
6
Communication and Consultation..................................................................................... 13
7
Monitoring ....................................................................................................................... 14
8
7.1
Noise monitoring
14
7.2
Vibration monitoring
14
Staff................................................................................................................................. 14
Page 5
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001184 rd Revision: 03, Date: 3 June 2016
This page intentionally left blank
Page 6
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001184 rd Revision: 03, Date: 3 June 2016
1 INTRODUCTION This is a Site Specific Construction Noise and Vibration Management Plan (SSCNVMP) and forms part of the Construction Noise and Vibration Delivery Work Plan (CNV DWP) for the CRL Contract 2 Enabling Works (the ‘Project’). This SSCNVMP provides specific assessment of construction noise and vibration from waterproofing and tunnel construction. This SSCNVMP should be read in conjunction with the CNV DWP (Document Ref: CRL-PAT-ENV-CON-PLN-000903 Revision 6 dated 3rd June 2016) as it contains further details of the project, noise criteria, monitoring, general mitigation measures and other information. Details of the construction methodology are contained in the Project Construction Environmental Management Plan (CEMP). Acoustic terms are defined in the Acoustic Glossary in the CNV DWP.
1.1
OBJECTIVE
The objective of this SSCNVMP is to detail the best practicable option to avoid, remedy or mitigate adverse effects on sensitive receivers resulting from construction noise and vibration that does not comply with the Project Standards defined in Section 1.2 of the CNV DWP.
1.2
SITE PLAN
The tunnel construction area is shown in Figure 1. Tunnel construction in the Customs Street Intersection will be below the traffic decks while the remainder of Albert Street will be in an open trench. Figure 1 Site Plan
Page 7
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001184 rd Revision: 03, Date: 3 June 2016
2 RECEIVERS Receivers where noise levels due to tunnel construction works have the potential to exceed project noise or vibration standards are listed below, along with building use. Table 1 Affected receivers
Historic / vibration sensitive
Minimum Distance to Works, m
Noise Criteria, dB dB LAeq LAFmax
Vibration Criteria, (mm/s)
Address
Building use
22 Customs Street
Commercial
Y
5
75
-
3
38 Wyndham Street
Commercial
N
6
75
-
20
58 Albert Street
Commercial
N
6
75
-
20
46-50 Albert Street
Commercial
Y
7
75
-
3
52-56 Albert Street
Commercial
Y
6
75
-
3
12-26 Swanson Street
Commercial
N
7
75
-
20
8 Albert Street
Mixed Use
N
7
75
90
5
70-74 Albert Street
Mixed Use
N
7
75
90
5
63 Albert Street
Commercial
N
16
75
-
20
22-26 Albert Street
This building has its own SSCNVMP so is not included in this plan
17 Albert Street
Commercial
Y
14
75
-
3
15 Albert Street
Vacant
Y
15
-
-
3
13 Albert Street
Vacant
Y
15
-
-
3
9 Albert Street
Mixed Use
Y
14
75
90
3
5 Albert Street
Commercial
Y
15
75
-
3
61 Albert Street
Mixed Use
Y
16
75
90
3
57 Albert Street
Commercial
Y
16
75
-
3
55 Albert Street
Commercial
Y
16
75
-
3
51 Albert Street
Commercial
Y
16
75
-
3
41 Albert Street
This building has its own SSCNVMP so is not included in this plan
23-29 Albert Street
Commercial
N
15
75
-
20
3 Albert Street
Commercial
N
16
75
-
20
34-36 Wyndham Street
Commercial
Y
16
75
-
3
37-39 Albert Street
Construction Site
N
16
-
-
-
65-71 Albert Street 35 Albert Street
This building has its own SSCNVMP so is not included in this plan Construction Site
N
16
-
-
-
* This is the Monday to Saturday 07:00 to 22:00 noise criteria. The majority of works will be carried out during this period. For residential receivers the noise limit is reduced to 65 dB L Aeq & 80 dB LAFmax on Sundays and Public Holidays between 07:00 to 22:00 and to 60 dB LAeq & 75 dB LAFmax at all other times.
Page 8
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001184 rd Revision: 03, Date: 3 June 2016
Designation Condition 38.4 allows for the Project vibration limits to be relaxed by a SSCVMP but only for a building, structure or infrastructure that has been assessed by a suitably qualified and experienced structural engineer and where it has been deemed to be capable of withstanding higher vibration levels without sustaining building or structural damage, and where appropriate vibration and building condition monitoring regimes are in place. Based on the building condition surveys and the initial assessments by the structural engineer the vibration limits will not be reduced.
3 ACTIVITIES Construction activities along with proposed start and end dates, and hours or operation, are shown in Table 2 below. Table 2 Construction activities
Construction Activity Tunnel Box Construction
Area of works
Activity Start Date
Activity End Date
South end to Swanson
28 Aug 2017
26 Jan 2018
Swanson to Wolfe
01 Dec 2017
05 Jun 2018
Wolfe to North end
26 Mar 2018
15 Aug 2018
Hours
7am – 7pm Mon - Sat
Details of construction equipment that is likely to be used for each of the above activities and the associated noise levels can be found in Appendix C of the CNV DWP. None of the equipment proposed for these works is expected to generate high levels of vibration. The equipment levels detailed in Appendix C of the CNV DWP are placeholders. All equipment will be measured operating independently and then actual equipment noise levels and model numbers will be recorded and updated within the table.
4 PREDICTED NOISE LEVELS The predicted worst case noise levels from each activity received at the most exposed part of each receiver are shown below in Table 3. These levels correspond to the construction equipment being located at its nearest position to the receiver and assume there is no physical mitigation between the noise source and the façade of the building. Table 3 Predicted noise levels (no mitigation)
Predicted worst case noise levels (no mitigation), dB LAeq
Project Noise Standards exceedance, dB
22 Customs Street
88
13
38 Wyndham Street
87
12
58 Albert Street
86
11
46-50 Albert Street
86
11
52-56 Albert Street
86
11
12-26 Swanson Street
86
11
8 Albert Street
86
11
70-74 Albert Street
85
10
Address
Page 9
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001184 rd Revision: 03, Date: 3 June 2016
63 Albert Street
84
9
17 Albert Street
79
4
15 Albert Street
79
4
13 Albert Street
79
4
9 Albert Street
79
4
5 Albert Street
79
4
61 Albert Street
78
3
57 Albert Street
78
3
55 Albert Street
78
3
51 Albert Street
78
3
23-29 Albert Street
78
3
3 Albert Street
78
3
34-36 Wyndham Street
77
2
37-39 Albert Street
77
2
35 Albert Street
76
1
5 MITIGATION 5.1
NOISE
Mitigation is required to meet the noise criteria at the nearest sensitive receivers. In addition to the general noise and vibration control measures outlined in Section 7 of the CNV DWP, the following specific noise mitigation measures should be implemented (Table 4): Table 4 Specific Noise Mitigation Measures
Equipment/process
Noise control measures
Excavators, bobcats, loaders
Grease tracks regularly
Crane
Use straps rather than chains unless a risk assessment deems the use of straps unsafe.
In addition to these measures, noise barriers/hoardings between the work site and the receiver will be used to reduce noise levels. These will be least 1.8m high and have a mass equal to or greater than 2 10 kg/m . Panels will be abutted or overlapped to provide a continuous screen with no gaps. It may be acceptable to use a proprietary barrier with a reduced mass providing the required attenuation can be achieved. The contractor will seek approval from the Project Acoustic Specialist before using a proprietary barrier product on site. Indicative location of noise barriers is shown in green in Figure 2 below.
Page 10
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001184 rd Revision: 03, Date: 3 June 2016
Figure 2 Noise barriers
5.1.1
Internal noise levels
With the above mitigation and management measures implemented and barriers installed, the noise levels at the most exposed façade of a number of properties will still exceed the noise criteria by more than 5 dB during some Project construction activities. These properties are detailed in Table 5 along with any further mitigation necessary to achieve acceptable internal noise levels. Table 5 Building Mitigation Measures
Address 22 Customs Street
63 Albert Street
8 Albert Street Sebel Hotel
Comments
Recommended Building Mitigation
The building houses a number of retail outlets. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and patrons and patrons choosing to shop elsewhere. Recommendations for façade sound insulation improvements are given in the SSCNVMP for the Albert Street piling works (Document Reference CRL-PAT-ENVCON-PLN-001189). With this mitigation implemented noise levels in all areas of the building will be acceptable and will not impact business operations. This building is occupied by AMI insurance at ground floor level and a number of other companies in the offices above. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff, loss of concentration and reduction in speech intelligibility. The building has a glazed façade None and it is mechanically ventilated. The attenuation provided by the façade is predicted to be 35 dB Rw. When the tunnel construction is taking place directly outside of the building internal noise levels are predicted to be no more than 45 dB LAeq in all areas of the building. st This building contains the Sebel Hotel. There is an office space and café on the 1 th floor, a swimming pool on the 5 floor and floors 5 to 29 are hotel rooms. There is a conference room on level 5 but it does not overlook Albert Street. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and guests, loss of concentration, reduction in speech intelligibility and annoyance of café patrons who may then choose to eat elsewhere. The reception area of the building will get the most benefit from the noise barrier but the noise level at the façade is still predicted to be 80 dB LAeq when the crane is working on the traffic deck directly outside of the building. It is recommended that Page 11
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001184 rd Revision: 03, Date: 3 June 2016
the gaps around the main doors are reduced and acoustic seals fitted. This would reduce noise levels in the reception area to approximately 50 dB LAeq. Noise levels at the façade of the most exposed hotel rooms are predicted to exceed the noise criteria by no more than 5 dB. Providing that the balcony doors are not left open noise levels should not impact on the cafes operations. Patrons that use the balcony seating could experience noise levels in the region of 85 dB LAeq. Noise levels in the office are predicted to reach 55 dB LAeq when the crane is working on the traffic deck directly outside of the building.
8 Albert Street City Med
Recommendations for façade sound insulation improvements are given in the SSCNVMP for the Albert Street piling works (Document Reference CRL-PAT-ENVCON-PLN-001189). The City Med operating hours 8am to 5.30pm Monday to Friday. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and patients, loss of concentration and reduction in speech intelligibility making consultations difficult. With the reception/ waiting area in its current location there will not be any increase in internal noise levels when tunnel construction works are being carried out. However, if it moves closer to the Albert Street façade during renovation of the space, construction noise may be an issue. Further advice cannot be given on this area until the exact details of the renovation works are known.
None
There is unlikely to be any increase in noise levels in the radiology area, operating theatres, ECG and audiometry during excavation works. Noise levels due to tunnel construction activities are predicted to meet the noise criteria along the area of the Mills Lane façade where the doctors’ consultation rooms are located.
70-74 Albert Street
12-26 Swanson Street
Internal noise levels are predicted to reach 55 dB LAeq in the pharmacy when the crane is working on the traffic deck directly outside of the building. This building is a hotel. Specific effects on this receiver that could result from exceedances of the noise criteria include annoying and disturbing staff or guests. The tunnel construction works do not extend to the area in front of this building. They will only be exposed to noise from tunnel construction works when it is at the southern tip of the site. Only three apartments will be affected (those on the first, second and third floor on the northern end of the Albert Street façade). The general manager is not concerned about noise and vibration providing that there is good communication about the timing and nature of activities that he can pass onto the guests. This building is occupied by the NZ Trade Centre. All areas of the building are mechanically ventilated. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff, loss of concentration and reduction in speech intelligibility.
None
None
Page 12
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001184 rd Revision: 03, Date: 3 June 2016
The section of the building closest to the works is two stories with a retail/ product display area on the ground floor and parking on the first floor. This part of the building will be most affected by noise from the tunnel construction works. Noise levels at the first floor are predicted to be 80 to 85 dB LAeq during these works but as this is a car park no further mitigation is required. Worst case noise levels at the ground floor retail/ product display area are predicted to exceed the noise criteria by no more than 5 dB so no further no further mitigation is required. The main tower section of the building is located further down Swanson Street away from the works. Noise levels at the most exposed façade of this section of the building are not predicted to exceed the noise criteria during the tunnel construction works.
5.2
VIBRATION
The proposed equipment items are not expected to generate vibration levels at receiver locations that exceed the Project criteria. If the initial on site vibration monitoring demonstrates otherwise, mitigation measures will be determined and put in place.
6 COMMUNICATION AND CONSULTATION Section 9.1 of the Project CNV DWP details the communication procedures in relation to construction noise and vibration effects. The complaints process is detailed in Section 9.2 of the CNV DWP. Consultation with the stakeholders identified in this SSCNVMP took place from mid-November to late December 2015. Topics that were covered included:
Sequencing of construction activities
Likely equipment and associated noise and vibration levels
Proposed mitigation and management measures
Construction of their buildings
Operational hours of their businesses
Operating environment that is required by the businesses
Further details of the meetings and comments made by the stakeholders are provided in Appendix D of the CNV DWP.
Page 13
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001184 rd Revision: 03, Date: 3 June 2016
7 MONITORING Section 10 of the Project CNV DWP provides details of the methodology for noise and vibration monitoring.
7.1
NOISE MONITORING
Noise monitoring will be carried out when the Telehandlers or Crawler Crane begin working on the construction deck within 15m of the building at the locations detailed in Table 6. Further monitoring will be carried out at these locations at regular intervals (monthly as a minimum). The monitoring will be carried out at first floor level unless a location at a higher level is specified. Table 6 Noise Monitoring Locations
Receiver
Monitoring Location
22 Customs Street
1m from façade of building
23-29 Albert Street
1m from façade of building In the ground floor reception/ café area
63 Albert Street
1m from façade of building
61 Albert Street
1m from façade of building
8 Albert Street
1m from façade of building
Sebel Hotel 8 Albert Street
1m from façade of building
City Med 70-74 Albert Street
1m from façade of building
12-26 Swanson Street
1m from façade of building
7.2
VIBRATION MONITORING
Vibration monitoring is not specifically required for these construction activities.
8 STAFF Before working on these activities all staff will receive training in accordance with Section 7.2 of the CNV DWP and will read and comply with this SSCNVMP.
Page 14
Auckland City Rail Link In association with:
ENABLING WORKS CONTRACT 2 SITE SPECIFIC CONSTRUCTION NOISE AND VIBRATION MANAGEMENT PLAN: BACKFILL AND REINSTATEMENT Separable Portion 1 – Cut and Cover Works Document Ref: CRL-PAT-ENV-CON-PLN-001188 Revision: 03
FINAL 3rd June 2016
COMMERCIAL IN CONFIDENCE
This page intentionally left blank.
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001188 rd Revision: 03, Date: 3 June 2016
DOCUMENT INFORMATION Organisation:
Connectus
Document Title:
SITE SPECIFIC CONSTRUCTION NOISE AND VIBRATION MANAGEMENT PLAN: BACKFILL AND REINSTATEMENT
Fulcrum Document Number:
CRL-PAT-ENV-CON-PLN-001188
Document based on MMS No:
n/a
Client:
Auckland Transport
Project:
CRL Enabling Works: Contract Two
Location:
Auckland CBD
Project No:
2665
REVISION HISTORY Rev
Date
Details st
01
1
Draft for Connectus review
Author
Approver
C. Drewery
C Hind
02
21/03/16
Final
C. Drewery
C Hind
03
3/06/16
Final
C. Drewery
C Hind
This document remains the property of Connectus. Its contents are confidential and shall not be reproduced, destroyed or given away without the express, written permission of Connects. The electronic version of this document in MMS Database on designated server(s) is the Master Copy and is a controlled document. Unless specifically noted thereon, other copies of this document are uncontrolled.
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001188 rd Revision: 03, Date: 3 June 2016
This page intentionally left blank
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001188 rd Revision: 03, Date: 3 June 2016
Table of Contents Document information .........................................................................................................................3 Revision History ..................................................................................................................................3 1
Introduction........................................................................................................................7 1.1
Objective
7
1.2
Site plan
7
2
Receivers ..........................................................................................................................8
3
Activities ............................................................................................................................9
4
Predicted Noise and vibration levels................................................................................. 10 4.1
Noise
10
4.2
Vibration
11
5
Mitigation ......................................................................................................................... 12 5.1
Noise
12
5.2
Vibration
17
6
Communication and Consultation..................................................................................... 18
7
Monitoring ....................................................................................................................... 19
8
7.1
Noise monitoring
19
7.2
Vibration monitoring
19
Staff................................................................................................................................. 20
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001188 rd Revision: 03, Date: 3 June 2016
This page intentionally left blank
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001188 rd Revision: 03, Date: 3 June 2016
1 INTRODUCTION This is a Site Specific Construction Noise and Vibration Management Plan (SSCNVMP) and forms part of the Construction Noise and Vibration Delivery Work Plan (CNV DWP) for the CRL Contract 2 Enabling Works (the ‘Project’). This SSCNVMP provides specific assessment of construction noise and vibration from trench backfilling and road surface reinstatement. This SSCNVMP should be read in conjunction with the CNV DWP (Document Ref: CRL-PAT-ENV-CON-PLN-000903 Revision 6 dated 3rd June 2016) as it contains further details of the project, noise criteria, monitoring, general mitigation measures and other information. Details of the construction methodology are contained in the Project Construction Environmental Management Plan (CEMP). Acoustic terms are defined in the Acoustic Glossary in the CNV DWP.
1.1
OBJECTIVE
The objective of this SSCNVMP is to detail the best practicable option to avoid, remedy or mitigate adverse effects on sensitive receivers resulting from construction noise and vibration that does not comply with the Project Standards defined in Section 1.2 of the CNV DWP.
1.2
SITE PLAN
The trench backfill area is shown in Figure 1. Note that reinstatement of the road surface in the Customs Street Intersection area is covered in the separate SSCNVMP for that area of works. Figure 1 Site Plan
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001188 rd Revision: 03, Date: 3 June 2016
2 RECEIVERS Receivers where noise levels due to trench backfill and road surface reinstatement works have the potential to exceed project noise or vibration standards are listed below, along with building use. Table 1 Affected receivers
Historic / vibration sensitive
Minimum Distance to Works, m
Noise Criteria, dB dB LAeq LAFmax
Vibration Criteria, (mm/s)
Address
Building use
9 Albert Street
Mixed Use
Y
5
75
90
3
5 Albert Street
Commercial
Y
5
75
-
3
3 Albert Street
Commercial
N
5
75
-
20
17 Albert Street
Commercial
Y
5
75
-
3
15 Albert Street
Vacant
Y
5
-
-
3
13 Albert Street
Vacant
Y
5
-
-
3
22 Customs Street
Commercial
Y
5
75
-
3
38 Wyndham Street
Commercial
N
6
75
-
20
61 Albert Street
Mixed Use
Y
6
75
90
3
57 Albert Street
Commercial
Y
6
75
-
3
55 Albert Street
Commercial
Y
6
75
-
3
51 Albert Street
Commercial
Y
6
75
-
3
41 Albert Street
This building has its own SSCNVMP so is not included in this plan
23-29 Albert Street
Commercial
N
6
75
-
20
58 Albert Street
Commercial
N
7
75
-
20
63 Albert Street
Commercial
N
7
75
-
20
46-50 Albert Street
Commercial
Y
7
75
-
3
52-56 Albert Street
Commercial
Y
7
75
-
3
12-26 Swanson Street
Commercial
N
7
75
-
20
37-39 Albert Street
Construction Site
N
6
-
-
-
70-74 Albert Street
Mixed Use
N
8
75
90
5
35 Albert Street
Construction Site
N
6
-
-
-
12 Albert Street
Mixed Use
N
8
75
90
5
22-26 Albert Street
This building has its own SSCNVMP so is not included in this plan
65-71 Albert Street
This building has its own SSCNVMP so is not included in this plan
34-36 Wyndham Street
Commercial
Y
17
75
-
3
33 Wyndham Street
Commercial
N
20
75
-
20
26 Wyndham Street
Commercial
N
24
76
-
20
* This is the Monday to Saturday 07:00 to 22:00 noise criteria. The majority of works will be carried out during this period. For residential receivers the noise limit is reduced to 65 dB L Aeq & 80 dB LAFmax on Sundays and Public Holidays between 07:00 to 22:00 and to 60 dB LAeq & 75 dB LAFmax at all other times.
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001188 rd Revision: 03, Date: 3 June 2016
Designation Condition 38.4 allows for the Project vibration limits to be relaxed by a SSCVMP but only for a building, structure or infrastructure that has been assessed by a suitably qualified and experienced structural engineer and where it has been deemed to be capable of withstanding higher vibration levels without sustaining building or structural damage, and where appropriate vibration and building condition monitoring regimes are in place. Based on the building condition surveys and the initial assessments by the structural engineer the vibration limits will not be reduced.
3 ACTIVITIES Construction activities along with proposed start and end dates, and hours or operation, are shown in Table 2 below. Table 2 Construction activities
Construction Activity
Trench Backfill
Road surface reinstatement
Area of works
Activity Start Date
Activity End Date
South end to Swanson
27 Nov 2017
12 Apr 2018
Swanson to Wolfe
05 Mar 2018
03 Jul 2018
Wolfe to North end
16 Aug 2018
22 Nov 2018
South end to Swanson
13 Apr 2018
09 Jul 2018
Swanson to Wolfe
04 Jul 2018
11 Sep 2018
Wolfe to North end
23 Nov 2018
25 Jan 2019
Hours
7am – 7pm Mon - Sat
7am – 7pm Mon - Sat
Details of construction equipment that is likely to be used for each of the above activities and the associated noise levels can be found in Appendix C of the CNV DWP. Details of the equipment that is expected to generate high levels of vibration can be found in Appendix B of the CNV DWP. The equipment levels detailed in Appendices B and C of the CNV DWP are placeholders. All equipment will be measured operating independently and then actual equipment noise/ vibration levels and model numbers will be recorded and updated within the table.
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001188 rd Revision: 03, Date: 3 June 2016
4 PREDICTED NOISE AND VIBRATION LEVELS 4.1
NOISE
The predicted worst case noise levels from each activity received at the most exposed part of each receiver are shown below in Table 3. These levels correspond to the construction equipment being located at its nearest position to the receiver and assume there is no physical mitigation between the noise source and the faรงade of the building. Table 3 Predicted noise levels (no mitigation)
Address
Predicted worst case noise levels (no mitigation), dB LAeq
Project Noise Standards exceedance, dB
Trench Backfilling 9 Albert Street
94
19
5 Albert Street
94
19
3 Albert Street
94
19
17 Albert Street
93
18
15 Albert Street
93
18
13 Albert Street
93
18
22 Customs Street
93
18
38 Wyndham Street
91
16
61 Albert Street
91
16
57 Albert Street
91
16
55 Albert Street
91
16
51 Albert Street
91
16
23-29 Albert Street
91
16
58 Albert Street
90
15
63 Albert Street
90
15
46-50 Albert Street
90
15
52-56 Albert Street
90
15
12-26 Swanson Street
90
15
37-39 Albert Street
90
15
70-74 Albert Street
89
14
35 Albert Street
89
14
8 Albert Street
89
14
34-36 Wyndham Street
81
6
33 Wyndham Street
79
4
26 Wyndham Street
77
2
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001188 rd Revision: 03, Date: 3 June 2016
Road surface reinstatement 9 Albert Street
89
14
5 Albert Street
89
14
3 Albert Street
89
14
17 Albert Street
88
13
15 Albert Street
88
13
13 Albert Street
88
13
22 Customs Street
88
13
38 Wyndham Street
86
11
61 Albert Street
86
11
57 Albert Street
86
11
55 Albert Street
86
11
51 Albert Street
86
11
23-29 Albert Street
86
11
58 Albert Street
85
10
63 Albert Street
85
10
46-50 Albert Street
85
10
52-56 Albert Street
85
10
12-26 Swanson Street
85
10
37-39 Albert Street
85
10
70-74 Albert Street
84
9
35 Albert Street
84
9
8 Albert Street
84
9
34-36 Wyndham Street
76
1
4.2
VIBRATION
Buildings which are classed as high or medium risk of damage as a result of the road surface reinstatement works are shown in Table 4. A receiver is classified as ‘high risk’ if it is located within the emission radius for an activity, and ‘medium risk’ if it is close to the contour with possible intermittent exceedance. Table 4 Vibration risk class
Address
Building type/ comments
Distance to works
Risk class (High or Medium)
22 Customs Street
Historic / vibration sensitive
5
High
5 Albert Street
Historic / vibration sensitive
5
High
9 Albert Street
Historic / vibration sensitive
5
High
3 Albert Street
Commercial
5
Medium
17 Albert Street
Historic / vibration sensitive
5
High
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001188 rd Revision: 03, Date: 3 June 2016
55 Albert Street
Historic / vibration sensitive
6
High
61 Albert Street
Historic / vibration sensitive
6
High
57 Albert Street
Historic / vibration sensitive
6
High
8 Albert Street
Residential
8
High
70-74 Albert Street
Residential
8
High
5 MITIGATION 5.1
NOISE
Mitigation is required to meet the noise criteria at the nearest sensitive receivers. In addition to the general noise and vibration control measures outlined in Section 7 of the CNV DWP, the following specific noise mitigation measures should be implemented (Table 5): Table 5 Specific Noise Mitigation Measures
Equipment/process
Noise control measures
Excavators, bobcats, loaders
Grease tracks regularly
In addition to these measures, noise barriers/hoardings between the work site and the receiver will be used to reduce noise levels. These will be least 1.8m high and have a mass equal to or greater than 10 kg/m2. Panels will be abutted or overlapped to provide a continuous screen with no gaps. It may be acceptable to use a proprietary barrier with a reduced mass providing the required attenuation can be achieved. The contractor will seek approval from the Project Acoustic Specialist before using a proprietary barrier product on site. Indicative location of noise barriers is shown in green in Figure 2 below. Figure 2 Noise barriers
Connectus Project #: 2665 Client: Auckland Transport
5.1.1
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001188 rd Revision: 03, Date: 3 June 2016
Internal noise levels
With the above mitigation and management measures implemented and barriers installed, the noise levels at the most exposed faรงade of a number of properties will still exceed the noise criteria by more than 5 dB during some Project construction activities. These properties are detailed in Table 6 along with any further mitigation necessary to achieve acceptable internal noise levels. Table 6 Building Mitigation Measures
Address 15 Albert Street 13 Albert Street 9 Albert Street
5 Albert Street (NZ Gifts)
3 Albert Street
Comments Building currently vacant Building currently vacant The bottom floors of the building are occupied by Food Alley and are mechanically ventilated. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and patrons and patrons choosing to eat elsewhere. Construction noise is unlikely to be an issue for the majority of the trench backfill works as it will be masked by mechanical services noise and general operational noise. When these works are taking place immediately outside of the building construction noise levels will be elevated and will be audible above background. Further consultation will take place with this receiver before works begin outside of the building and where possible noisy activities will be scheduled outside of the lunch time period when Food Alley is at its busiest. There are 16 residential apartments on floors 6 and 7 which are all naturally ventilated. Worst case noise levels at these floors are predicted exceed the noise criteria by less than 5 dB. As this exceedance will be for a short duration faรงade sound insulation improvements are not considered necessary. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and patrons and patrons choosing to shop elsewhere. The building is mechanically ventilated. They have automatic doors which are not kept open. Background music plays at a low volume. Operational hours are 9.30am to 9.30pm. Construction noise is unlikely to be an issue for the majority of the trench backfilling works as it will be masked by the background music. When works are taking place immediately outside of the building construction noise levels will be elevated and will be audible above background. Further consultation will take place with this receiver before works begin outside of the building and where possible noisy activities will be scheduled to avoid their busiest times. The bakery/ cafe on the ground floor is the most exposed area of the building. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and patrons and patrons choosing to eat elsewhere. The doors are kept wide open all day and so they are already exposed to
Recommended Building Mitigation None None
None
None
None
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001188 rd Revision: 03, Date: 3 June 2016
high levels of traffic noise, particularly heavy vehicles pulling away from the traffic lights. The radio plays loudly so it can be heard over the traffic noise. The business owner indicated that he is not concerned about construction noise and is likely to keep the doors open as usual.
17 Albert Street
The tower is occupied by offices. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and loss of concentration. The building has a glass façade and all offices are mechanically ventilated. Noise levels in the tower section of the building will remain below 45 dB LAeq for the majority of the works. Façade sound insulation improvements are therefore not considered necessary at this receiver. The convenience store on the ground floor is the most exposed area of the building. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and patrons and patrons choosing to shop elsewhere. The rest of this building contains mostly offices, a few residential apartments and a language school. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff, loss of concentration and reduction in speech intelligibility. Recommendations for façade sound insulation improvements are given in the SSCNVMP for the Albert Street piling works (Document Reference CRL-PAT-ENVCON-PLN-001189). With this mitigation implemented noise levels in all areas of the building will generally be acceptable and will not impact business operations or disturb residents.
22 Customs Street
51 Albert Street 23-29 Albert Street
The building houses a number of retail outlets. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and patrons and patrons choosing to shop elsewhere. Recommendations for façade sound insulation improvements are given in the SSCNVMP for the Albert Street piling works (Document Reference CRL-PAT-ENVCON-PLN-001189). With this mitigation implemented noise levels in all areas of the building will be acceptable and will not impact business operations. Building soon to be demolished None This is the ANZ building. It is occupied by a number of businesses including Chapman Tripp, Vero and ANZ. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff, loss of concentration productivity and reduction in speech intelligibility. ANZ occupy the lower floors of the building that will be most affected by noise. The building has a glazed façade and it is mechanically ventilated. The attenuation provided by the façade is predicted to be 35 dB Rw. AS/NZS 2107:2000 None “Acoustics – Recommended design sound levels and reverberation times for building interiors” recommends a maximum noise level of 45 dB LAeq for general office areas. Noise levels in all office areas of the building are predicted to remain at or below 45 dB LAeq for the full duration of the works. The most affected area of the building will be the ground floor atrium that houses the reception area and café.
Connectus Project #: 2665 Client: Auckland Transport
38 Wyndham Street
46 to 58 Albert Street 63 Albert Street
61 Albert Street
57 Albert Street 37-39 Albert Street 35 Albert Street 8 Albert Street
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001188 rd Revision: 03, Date: 3 June 2016
Both ANZ and the café owner are willing to accept elevated noise levels for short durations providing that they are well informed of the works. Further consultation will also take place with this receiver before works begin outside of the building and where possible noisy activities will be scheduled outside of the most sensitive times. This building is occupied by the Hollywood Bakery at ground floor level and offices above. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and patrons and patrons choosing to eat elsewhere. The operating hours of the bakery are 6.30am to 4.30pm. The front doors are permanently open onto Wyndham Street so they are already exposed to high levels of traffic noise, particularly heavy vehicles pulling away from the traffic lights. They play background noise music at a low volume. The manager indicated that she is not too concerned about construction noise and is likely to keep the doors open as usual. Despite numerous attempts we were unable to gain access to the main part of the building above the bakery. It is assumed that the building contains offices and is mechanically ventilated throughout. The first three floors above the bakery will be most affected by construction noise. When trench backfilling works are taking place immediately outside of the building construction noise levels on these three floors will likely be audible above background. Buildings soon to be demolished. This building is occupied by AMI insurance at ground floor level and a number of other companies in the offices above. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff, loss of concentration and reduction in speech intelligibility. The building has a glazed façade and it is mechanically ventilated. The attenuation provided by the façade is predicted to be 35 dB Rw. When trench backfilling works are taking place directly outside of the building internal noise levels are predicted to reach 50 dB LAeq in offices overlooking Albert Street th on the ground to the 5 floor and then reduce to 45 dB LAeq on the remaining floors of the building. This building is occupied by the Shakespeare Hotel and Brewery. There is a bar at ground level which operates from 8am to 4am, a restaurant at first floor level and hotel rooms on the second floor. Loud music is played in the bar area. The owner of this business is not concerned about noise and vibration from the works. Their busiest times are in the evening and through the night when there will be no construction activities taking place. Carpark Construction site
None
None
None
None
None None
Construction site None st This building contains the Sebel Hotel. There is an office space and café on the 1
Connectus Project #: 2665 Client: Auckland Transport
Sebel Hotel
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001188 rd Revision: 03, Date: 3 June 2016
floor, a swimming pool on the 5th floor and floors 5 to 29 are hotel rooms. There is a conference room on level 5 but it does not overlook Albert Street. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and guests, loss of concentration, reduction in speech intelligibility and annoyance of café patrons who may then choose to eat elsewhere. The reception area of the building will get the most benefit from the noise barrier but the noise level at the façade is still predicted to be 80 dB LAeq. During the trench backfilling works directly outside of the building noise level in the reception area are predicted to be 55 dB LAeq. The reception area is going to be exposed to reasonably high noise levels for the duration of the Project. The doors are the weak point in the façade. It is recommended that the gaps around the doors are reduced and acoustic seals fitted. Only the rooms overlooking Albert Street on levels 5 and 6 will experience noise levels at the façade that exceed the noise criteria by more than 5 dB during trench backfilling activities on the east side of Albert Street. With a predicted façade noise reduction of 30 dB Rw the noise levels in these rooms could reach 55 dB LAeq when these works are taking place directly outside of the building. When trench backfilling works are being carried out directly outside of the building, construction noise will be audible inside the café even with the music playing. It is recommended that the gaps around the balcony doors in the café are reduced and acoustic seals fitted. Providing that the balcony doors are not left open noise levels should not impact on the cafes operations. Patrons that use the balcony seating area during this four day period will experience noise levels in the region of 85 dB LAeq. Further consultation will take place with the café owner before works begin outside of the building and where possible noisy activities will be scheduled to avoid their busiest times. Noise levels in the office are predicted to reach 55 dB LAeq during trench backfilling works directly outside of the building. Recommendations for façade sound insulation improvements are given in the SSCNVMP for the Albert Street piling works (Document Reference CRL-PAT-ENVCON-PLN-001189).
8 Albert Street City Med
The City Med operating hours 8am to 5.30pm Monday to Friday. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and patients, loss of concentration and reduction in speech intelligibility making consultations difficult. With the reception/ waiting area in its current location there is unlikely to be any increase in internal noise levels when these works are being carried out. However, if it moves closer to the Albert Street façade during renovation of the space, construction noise may be an issue. Further advice cannot be given on this area until the exact details of the renovation works are known. There is unlikely to be any increase in noise levels in the radiology area, operating theatres, ECG and audiometry during backfilling and reinstatement works. Noise levels due to trench backfilling are predicted to meet the noise criteria along the area of the Mills Lane façade where the doctors’ consultation rooms are located.
None
Connectus Project #: 2665 Client: Auckland Transport
70-74 Albert Street
12-26 Swanson Street
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001188 rd Revision: 03, Date: 3 June 2016
Internal noise levels are predicted to reach 55 dB LAeq in the pharmacy when these works are directly outside of the building. This building is a hotel. It is mechanically ventilated. Specific effects on this receiver that could result from exceedances of the noise criteria include annoying and disturbing staff or guests. The trench backfilling works do not extend to the area in front of this building. They will only be exposed to noise from these works when it is at the southern tip of the site. Only three apartments will be affected (those on the first, second and third floor on the northern end of the Albert Street faรงade).
None
The general manager is not concerned about noise and vibration providing that there is good communication about the timing and nature of activities that he can pass onto the guests. This building is occupied by the NZ Trade Centre. All areas of the building are mechanically ventilated. Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff, loss of concentration and reduction in speech intelligibility. The section of the building closest to the works is two stories with a retail/ product display area on the ground floor and parking on the first floor. This part of the building will be most affected by noise from the trench backfilling works. Noise levels at the first floor are predicted to be 80 to 85 dB LAeq during these works but as this is a car park no further mitigation is required. Worst case noise levels at the ground floor retail/ product display area are predicted to exceed the noise criteria by no more than 5 dB so no further no further mitigation is required.
None
The main tower section of the building is located further down Swanson Street away from the works. Noise levels at the most exposed faรงade of this section of the building will not exceed the noise criteria by more than 5 dB during the trench backfilling works.
5.2
VIBRATION
In addition to the general noise and vibration control measures outlined in Section 7 of the Project CNV DWP the following specific vibration mitigation measures (Table 7) should be implemented if the initial on site vibration monitoring demonstrates that the building damage vibration limits will be exceeded: Table 7 Specific Vibration Mitigation Measures
Equipment/process
Vibration control measures
Roller compactor (17t)
Use a smaller compactor, less than 10t. The frequency of the compactor should also be considered. It may be acceptable to use a bigger compactor depending on the frequency it is being operated at.
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001188 rd Revision: 03, Date: 3 June 2016
6 COMMUNICATION AND CONSULTATION Section 9.1 of the Project CNV DWP details the communication procedures in relation to construction noise and vibration effects. The complaints process is detailed in Section 9.2 of the CNV DWP. Consultation with the stakeholders identified in this SSCNVMP took place from mid-November to late December 2015. Topics that were covered included:
Sequencing of construction activities
Likely equipment and associated noise and vibration levels
Proposed mitigation and management measures
Construction of their buildings
Operational hours of their businesses
Operating environment that is required by the businesses
Further details of the meetings and comments made by the stakeholders are provided in Appendix D of the CNV DWP.
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 02, Date: 21 March 2016
7 MONITORING Section 10 of the Project CNV DWP provides details of the methodology for noise and vibration monitoring.
7.1
NOISE MONITORING
Noise monitoring will be carried out when trench backfilling activities begin within 20m of the building and when compacting begins within 20m of the building at the locations detailed in Table 8. The monitoring will be carried out at first floor level unless a location at a higher level is specified. Table 8 Noise Monitoring Locations
Receiver
Monitoring Location
9 Albert Street
1m from façade of building
5 Albert Street
1m from façade of building
3 Albert Street
1m from façade of building
17 Albert Street
1m from façade of building In a Language School classroom overlooking Albert Street. In one of the offices on Level 2
22 Customs Street
1m from façade of building In the most exposed retail area In the Level 2 meeting/ training room overlooking Albert Street
23-29 Albert Street
1m from façade of building In the ground floor reception/ café area
63 Albert Street
1m from façade of building
61 Albert Street
1m from façade of building
8 Albert Street
1m from façade of building
Sebel Hotel
In the hotel reception In the café In one of the Level 5 rooms overlooking Albert Street
8 Albert Street
1m from façade of building
City Med 70-74 Albert Street
1m from façade of building
12-26 Swanson Street
1m from façade of building
7.2
VIBRATION MONITORING
Vibration monitoring will be carried out when works begin on site to determine actual equipment vibration levels and the attenuation provided by the local ground conditions. If the initial vibration monitoring demonstrates that the emission radius for the compactor is similar to that detailed in Section 5.2 of the CNV DWP then the monitoring as detailed below will be carried out. If the
Page 19
Connectus Project #: 2665 Client: Auckland Transport
Construction Noise and Vibration Delivery Work Plan Doc. No. CRL-PAT-ENV-CON-PLN-000903 Revision: 02, Date: 21 March 2016
monitoring demonstrates that vibration levels are significantly lower then less properties may require monitoring, if they are higher then more properties may require monitoring. Vibration monitoring will be carried out at the following receivers when the compactor is first used within 15m of the building at:
22 Customs Street
5 Albert Street
9 Albert Street
17 Albert Street
55 Albert Street
61 Albert Street
57 Albert Street
Vibration monitoring will be carried out at the following receivers when concrete breaking begins within 8m of the building at:
8 Albert Street
70-74 Albert Street
Vibration monitoring will be carried out at the following receivers when concrete breaking begins within 5m of the building at:
3 Albert Street
8 STAFF Before working on these activities all staff will receive training in accordance with Section 7.2 of the CNV DWP and will read and comply with this SSCNVMP.
Page 20
Auckland City Rail Link In association with:
ENABLING WORKS CONTRACT 2 SITE SPECIFIC CONSTRUCTION NOISE AND VIBRATION MANAGEMENT PLAN: 41 ALBERT STREET Separable Portion 1 – Cut and Cover Works Document Ref: CRL-PAT-ENV-CON-PLN-001264 Revision: 03
FINAL 3rd June2016
COMMERCIAL IN CONFIDENCE
This page intentionally left blank.
DOCUMENT INFORMATION Organisation:
Connectus
Document Title:
Site Specific Construction Noise Management Plan
Fulcrum Document Number:
CRL-PAT-ENV-CON-PLN-001264
Document based on MMS No:
n/a
Client:
Auckland Transport
Project:
CRL Enabling Works: Contract Two
Location:
Auckland CBD
Project No:
2665
REVISION HISTORY Rev
Date
Details st
01
1
Draft for Connectus review
Author
Approver
C. Drewery
C Hind
02
21/03/16
Final for Issue
C. Drewery
C Hind
03
3/06/16
Final
C. Drewery
C Hind
This document remains the property of Connectus. Its contents are confidential and shall not be reproduced, destroyed or given away without the express, written permission of Connects. The electronic version of this document in MMS Database on designated server(s) is the Master Copy and is a controlled document. Unless specifically noted thereon, other copies of this document are uncontrolled.
This page intentionally left blank
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001264 Revision: 03, Date: 3 June 2016
Table of Contents
...............................................................................................3 Document information .........................................................................................................................3 Revision History ..................................................................................................................................3 1
Introduction........................................................................................................................7 1.1
Objective
7
1.2
Site plan
7
2
Receivers ..........................................................................................................................8
3
Activities ............................................................................................................................8
4
Predicted Noise and vibration levels...................................................................................9 4.1
Noise
4.2
vibration
5
9 11
Mitigation ......................................................................................................................... 12 5.1
Noise
12
5.2
internal noise levels
13
5.3
Vibration
14
6
Communication and Consultation..................................................................................... 15
7
Monitoring ....................................................................................................................... 19
8
7.1
Noise monitoring
19
7.2
Vibration monitoring
19
Staff................................................................................................................................. 19
Page 5
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001264 Revision: 03, Date: 3 June 2016
This page intentionally left blank
Page 6
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001264 Revision: 03, Date: 3 June 2016
1 INTRODUCTION This is a Site Specific Construction Noise and Vibration Management Plan (SSCNVMP) and forms part of the Construction Noise and Vibration Delivery Work Plan (CNV DWP) for the CRL Contract 2 Enabling Works (the ‘Project’). This SSCNVMP provides specific assessment of construction noise and vibration effects on the ‘Prince Albert Apartments’ at 41 Albert Street. This SSCNVMP should be read in conjunction with the CNV DWP (Document Ref: CRL-PAT-ENV-CON-PLN-000903 Revision 6 dated 3rd June 2016) as it contains further details of the Project, noise criteria, monitoring, general mitigation measures and other information. Details of the construction methodology are contained in the Project Construction Environmental Management Plan (CEMP). Acoustic terms are defined in the Acoustic Glossary in the CNV DWP.
1.1
OBJECTIVE
The objective of this SSCNVMP is to detail the best practicable option to avoid, remedy or mitigate adverse effects on the residents of 41 Albert Street, resulting from construction noise and vibration that does not comply with the Project Standards defined in Section 1.2 of the CNV DWP.
1.2
SITE PLAN
Figure 1 shows the location of the main works in relation to 41 Albert Street. Figure 1 Site plan
Page 7
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001264 Revision: 03, Date: 3 June 2016
2 RECEIVERS The property is a split-level terraced, five storey property consisting of lobby and retail (currently under refurbishment) space on the ground floor with the first to fifth level consisting of residential apartments. All apartments are currently naturally ventilated. Table 1 Receiver information
Address
Building use
41 Albert Street
Mixed use (commercial/ residential)
Historic / vibration sensitive
Minimum Distance to Works, m
Noise Criteria, dB dB LAeq LAFmax
Vibration Criteria, (mm/s)
Y
6*
75**
3
90**
* This distance relates to piling, trench excavation and other works within the trench area. Advanced utilities relocation works may be carried out within approximately 2m of the building. ** This is the Monday to Saturday 07:00 to 22:00 noise criteria. The majority of works will be carried out during this period. For residential receivers the noise limit is reduced to 65 dB L Aeq & 80 dB LAFmax on Sundays and Public Holidays between 07:00 to 22:00 and to 60 dB LAeq & 75 dB LAFmax at all other times.
Designation Condition 38.4 allows for the Project vibration limits to be relaxed by a SSCVMP but only for a building, structure or infrastructure that has been assessed by a suitably qualified and experienced structural engineer and where it has been deemed to be capable of withstanding higher vibration levels without sustaining building or structural damage, and where appropriate vibration and building condition monitoring regimes are in place. Based on the building condition surveys and the initial assessments by the structural engineer the vibration limits will not be reduced.
3 ACTIVITIES Construction activities along with proposed start and end dates, and hours of operation, are shown in Table 2 below. Table 2 Construction activities
Works Phase
Construction Activity
Area of works
Activity Start Date
Activity End Date
Advanced Utilities Works
Utilities relocation
Combined Services Trench – Western footpath from Customs Street to Wyndham Street
Start in early May for 60 days
Vector Electricity from Swanson Street West across Albert Street down Swanson Street East
Start in early June for 20 days
Hours 7am to 7pm Mon - Sat
Page 8
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001264 Revision: 03, Date: 3 June 2016
Works Phase
Construction Activity
Area of works
Activity Start Date
Activity End Date
Hours
Albert Street Piling and Capping Beam
Utilities location and exposure
West Side Wyndham St to Wolfe St
29 Nov 2016
05 Dec 2016
7.30am to 6.00pm
22 Dec 2016
07 Mar 2017
23 Mar 2017
27 Mar 2017
Installation of CFA piles
Mon - Sat
Installation of pile cap Excavation and Spoil Handling
Removal of existing road surface
Wyndham St to Swanson St
7am to 7pm Mon - Sat
(Ch550-490)
and st
Excavation 1 layer
28 Mar 2017
03 Apr 2017
Rock Dowel Installation
Excavation 2nd layer to bottom
20 Apr 2017
07 Sep 2017
Waterproofing and Tunnel Construction
Waterproofing and tunnel construction
South end to Swanson St (Ch614-490)
28 Aug 2017
26 Jan 2018
Trench Backfilling
Trench backfilling and reinstatement
South end to Swanson St (Ch614-490)
27 Nov 2017
Shotcrete and Strip Drain Installation and
7am to 7pm Mon – Sat
11 Dec 2018
7am to 7pm Mon - Sat
Details of construction equipment that is likely to be used for each of the above activities and the associated noise levels can be found in Appendix C of the CNV DWP. Details of the equipment that is expected to generate high levels of vibration can be found in Appendix B of the CNV DWP. The equipment levels detailed in Appendices B and C of the CNV DWP are placeholders. All equipment will be measured operating independently and then actual equipment noise/ vibration levels and model numbers will be recorded and updated within the table.
4 PREDICTED NOISE AND VIBRATION LEVELS 4.1
NOISE
The predicted worst case noise levels from each activity received at the most exposed part of the building are shown below in Table 3. These levels correspond to the construction equipment being located at its nearest position to 41 Albert St and assume there is no physical mitigation between the noise source and the façade of the building. The predicted noise levels take into account whether works are being carried out at ground level or below the ground.
Page 9
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001264 Revision: 03, Date: 3 June 2016
Table 3 Predicted noise levels
Construction Activity
Project Noise Standard, dB LAeq
Predicted noise level with no mitigation, dB LAeq
75
100
25
75
100
25
75
98
23
75
93
18
75
90
15
75
85
10
75
81
6
75
91
16
75
78
3
75 75
83 85
8 10
75
86
11
Combined services trench – west Vector Electricity from Swanson Street West across Albert Street down Swanson Street East Utilities location and exposure (inside trench area) Piling Removal of existing road surface Excavation 1st layer Excavation 2nd Layer to Bottom Trench backfilling Waterproofing and tunnel construction Rock fall protection netting Pre-drilling Drilling and rock dowel installation
Project Noise Standards exceedance, dB
Noise levels will decrease with distance from the noise source such that noise levels at higher floors and at facades not directly exposed to the noise source will be lower than those shown above. This is illustrated in Figure 2 showing noise levels due to CFA pile installation decreasing with increasing floor level. Figure 2 CFA Piling - facade noise levels
Page 10
Connectus Project #: 2665 Client: Auckland Transport
4.2
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001264 Revision: 03, Date: 3 June 2016
VIBRATION
Vibration regression curves and emission radii for the vibration sources can be found in Section 5.2 of the CNV DWP. The emission radius is the distance at which vibration levels from an activity/equipment item are expected to exceed the Project Vibration Standards for a particular type of building. For the purposes of assessing vibration, 41 Albert St is classed as Historic / Vibration sensitive. A receiver is classified as ‘high risk’ if it is located within the emission radius for an activity, and ‘medium risk’ if it is close to the contour with possible intermittent exceedance. The emission radii and risk class associated with each vibration source at 41 Albert Street are shown in Table 4. Table 4 Vibration risk class
Works Phase
Equipment
Emission radius (m)
Distance to works (m)
Risk Class
Advanced Utilities Works
Excavator mounted rock breaker
16
2
High
Albert Street Piling and Capping Beam
Soilmec Hydraulic Rotary Rig (est SR80)
3
6
Low
Rock Dowel Installation
Excavator mounted rock breaker
16
6
High
Trench Backfilling
Compactors
8
6
High
We note that the emission radii are based on generic data based on conservatively sized equipment and ground conditions. Vibration levels from actual equipment at the site may differ and are likely to be less than assumed for the emission radius. Monitoring will be carried out at the earliest opportunity on site to determine the adjustments for ground conditions and actual equipment items.
Page 11
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001264 Revision: 03, Date: 3 June 2016
5 MITIGATION 5.1
NOISE
Mitigation is required to meet the noise criteria at the 41 Albert Street. In addition to the general noise and vibration control measures outlined in Section 7 of the CNV DWP, the following specific noise mitigation measures should be implemented (Table 5): Table 5 Specific Noise Mitigation Measures
Equipment/process
Noise control measures
Excavators, bobcats, loaders
Grease tracks regularly
Crane
Use straps rather than chains unless a risk assessment deems the use of straps unsafe.
Concrete cutting
Use a mobile acoustic enclosure where practicable. Use of a mobile acoustic enclosure may not be practicable when:
Cutting within 300mm of a kerb or canopy structure Saw cuts need to be made around an obstruction that protrudes above surface level, such as a light pole or street sign.
The road saw needs to be manoeuvred around in a tight space that would be obstructed by the acoustic enclosure
When use of a mobile acoustic enclosure is not practicable works will be planned so that saw cutting directly in front of a receiver is completed within a total of two working days. The building owner will be contacted prior to this occurring to see if the works can be scheduled for a time that least impacts them.
Vacuum Excavation
Locate the vehicle so the pump is facing away from the closest noise sensitive properties
Construction vehicles
Tonal reversing alarms will not be used. Broadband alarms will be used instead.
In addition to these measures, noise barriers/hoardings between the work site and the receiver will be used to reduce noise levels. These will be least 1.8m high and have a mass equal to or greater than 10 kg/m2. Panels will be abutted or overlapped to provide a continuous screen with no gaps. It may be acceptable to use a proprietary barrier with a reduced mass providing the required attenuation can be achieved. The contractor will seek approval from the Project Acoustic Specialist before using a proprietary barrier product on site. Indicative location of noise barriers is shown in Figure 3 below.
Page 12
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001264 Revision: 03, Date: 3 June 2016
Figure 3 Noise barriers
Noise barriers are generally most effective when placed as close to the noise source as possible, and blocking line of sight between the source and receiver. Barriers are therefore most effective for noise sources located at or below ground level, and received at ground floor level. Little reduction is provided for receivers located at Level 3 and above.
5.2
INTERNAL NOISE LEVELS
Noise measurements were carried out at the 41 Albert Street to determine existing ambient noise levels and the sound reduction provided by the façade. The noise measurements were taken on 7th December between 10am and 11am. The measurement results are detailed in Table 6. Table 6 41 Albert Street Ambient Noise Levels
Measurement Location
Noise Level dB LAeq
Noise sources
Comments
Outside (0.5m from façade)
68
Traffic, construction at 35-39 Albert
Traffic noise dominant, construction (hammering) intermittent
Inside – windows open
53
Traffic, construction
Traffic noise dominant, construction (hammering) intermittent
Inside – windows closed
43
Traffic
Low frequency from buses etc dominant. Construction barely audible
It can be seen from Table 6 that the façade achieves a sound reduction of 15 dB with windows ajar and 25 dB with windows closed. The building is naturally ventilated so windows are usually open during the day. Residents that are home during the day currently experience noise levels in the region of 53 dB LAeq. Open windows are the weak point of the façade. It is recommended that the living rooms of apartments on the Albert Street façade are fitted with mechanical ventilation so that residents who are home during the day can close their windows and still get the required amount of fresh air. Some of the advanced utilities works outside of the trench alignment are within close proximity to the building at 41 Albert Street. The closest works are the Combined Service Trench (Western Footpath). Internal noise levels due to these advanced utilities works are predicted to be up to 70 dB(A) even with mechanical ventilation installed and windows shut. These works will only be directly outside of the
Page 13
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001264 Revision: 03, Date: 3 June 2016
building for a limited duration. Further consultation will take place with the affected parties before these works begin to determine if the works can be scheduled for a time that least impacts them. An alternative option that has been suggested during consultation with the residents is to provide a HOP card for use by residents who are normally home during the day so that when noisy works are closest to the building they can go out for the day. This option should be discussed further with the residents particularly when considering the advanced utilities works. 5.2.1
Building Modification
Where building modification is recommended the following actions will be undertaken:
The building owner will be contacted to discuss details of the recommended building mitigation.
If the building owner wishes to proceed with the recommended building mitigation, arrangements will be made to visit the property to inspect the areas of the building where acoustic treatment is proposed and identify any issues that could affect installation of the mitigation. Additional noise measurements will be taken, where necessary, to confirm the acoustic performance requirements of the mitigation.
Any approvals required for the works under the Resource Management Act, Building Act and Historic Place Act will be obtained.
A legal agreement will be prepared for the installation of the acoustic treatment. The agreement will contain an explicit description of the acoustic treatment to be installed. Under the agreement Auckland Transport will take responsibility for commissioning the works (such as airflow and noise from ventilation systems) and for ensuring any required building consent inspections occur. The agreement includes a form to be signed by the property owner following commissioning to acknowledge that the works specified have been completed.
On completion of the mitigation works the property will be reinstated to a similar condition to that existing immediately prior to the works commencing.
Where mechanical ventilation is recommended it will be designed to achieve the requirements of Clause G4 of the New Zealand Building Code. At the same time as meeting this minimum requirement, the sound of the system shall not exceed 30 dB LAeq(30s) when measured 1 m away from any grille or diffuser. The occupant must be able to control the ventilation rate in increments up to a high air flow setting that provides at least 6 air changes per hour. At the same time as meeting this requirement, the sound of the system shall not exceed 35 dB LAeq(30s) when measured 1 m away from any grille or diffuser.
5.3
VIBRATION
In addition to the general noise and vibration control measures outlined in Section 7 of the Project CNV DWP the following specific vibration mitigation measures (Table 7) should be implemented if the initial on site vibration monitoring demonstrates that the building damage vibration limits will be exceeded: Table 7 Specific Vibration Mitigation Measures
Equipment/process
Vibration control measures
Excavator mounted rock breaker
Use lower vibration generating equipment such as a hand held jack hammer
Roller compactor (17t)
Use a smaller compactor, less than 10t Page 14
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001264 Revision: 03, Date: 3 June 2016
A detailed pre-construction building condition survey will be undertaken in accordance with Section 10.4 of the CNV DWP. A post-construction condition survey will be conducted a week after the conclusion of works in the area that have the potential to generate vibration at levels approaching or exceeding the limits in Condition 33.
6 COMMUNICATION AND CONSULTATION Section 9.1 of the CNV DWP details the communication procedures in relation to construction noise and vibration effects. The complaints process is detailed in Section 9.2 of the CNV DWP. Consultation with the 41 Albert Street took place from mid-November to mid-February. Topics that were covered included:
Sequencing of construction activities
Likely equipment and associated noise and vibration levels
Mitigation & management measures that will be implemented
Construction of the building
Further details of the meetings and comments made by the stakeholders are provided in Table 8.
Page 15
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001264 Revision: 03, Date: 3 June 2016
Table 8 Stakeholder Consultations
Address of Sensitive Receiver
Representatives
41 Albert Street (Albert Street Apartments)
9/11/15 Interview on site with building manager, Body Corporate Chair, and a further resident representative
Issue raised or comment provided Some residents are at home during the daytime period so will be affected by day time construction activities. All apartments are naturally ventilated so windows overlooking Albert Street are open in most apartments during the day. Ground floor is commercial and currently vacant but the owner is looking to sell it. Concern about the cumulative effects of noise from the Project and noise from construction on 2 adjacent sites. They would like a SSCNVMP for the building
Email sent to all affected receivers with apartments on the Albert Street faรงade to get feedback on the option of installing mechanical ventilation. Responses below 31/01/16 Email from the owner of Unit 3A
29/01/16 Email from owner of 4B
Email from owner of 3B
I would be open to having mechanical ventilation installed in the living area to appease the tenant so she did not have to open the windows facing onto Albert Street during the CRL works period. I am unaware of any other options. I am affected, as I am home a lot during the day and therefore a bit worried about the upcoming works. Of course having my ranch-slider open is my main means of ventilation during the summer. Mechanical ventilation- This option is not appealing, because I am sceptical that it would bring enough air in and I think in the long term it
Page 16
How comment was incorporated (or if not incorporated, reason why not) Mechanical ventilation is recommended for living rooms on the Albert Street faรงade. A HOP card is an alternative option for residents who are home during the day to use when particularly noisy works are taking place directly outside of the building. With the mitigation and management measures detailed in Section 7 of the CNV DWP and Section 5 of this SSCNVMP implemented, works may be audible but generally will not be at a level that disturbs residents. Noise levels during the advanced utilities works will be intrusive but for a limited duration. Further consultation will take place with the affected parties before the advanced utilities works begin to determine if the works can be scheduled for a time that least impacts them. Vibration may be felt but will not be at a level that damages the building. Section 7 of this SSCNVMP provides details of the proposed noise and vibration monitoring. This SSCNVMP is for their building.
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001264 Revision: 03, Date: 3 June 2016
would lower the value of our apartment. Would it be removed when construction is complete? We do have the heat pump bringing air from the south side of the building. We have used the fan during the hottest period and it helps, but I don't think it is effective enough to make up for closing the windows. I have someone coming in to service it next week. We will then try the cooler. This of course wouldn't help if they start demolition on 51-53 Albert Street before you have finished with Albert Street. We have very good Windows on this side of the building, and would like to see any construction on that site delayed for 5 years. The property is for sale, perhaps Auckland Transport would like to purchase it and add it to their portfolio of car parks. Scheduling- The number one thing you can do for scheduling is not to do the major work on our block during the height of the summer. Even with the limited construction going on now the impact is far worse during hot and humid weather. Certainly if all the most disruptive work was done in the winter, we would be very happy. Relocation- this is too complicated and disruptive to appeal. Since we are dealing with Auckland Transport an easier and cheaper solution would be for them to provide us with concession HOP cards, so we can escape during the day when the work will be at its worst. Secondary Glazing- this could work if we can get the fresh air we need from the heat pump. Replacing the existing Windows with double glazed Windows would be a huge improvement to this apartment.
Page 17
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001264 Revision: 03, Date: 3 June 2016
3/02/16
When will the work begin outside 41 Albert st
Email from owner of 2A
How long will the work take from begin to end outside our building How many days a week will the workers there ( are you planning on working Saturdays ) What hour of the day will work begin and end Are you offering to help with air filtration, and noise barrier
Page 18
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001264 Revision: 03, Date: 3 June 2016
7 MONITORING Section 10 of the Project CNV DWP provides details of the methodology for noise and vibration monitoring.
7.1
NOISE MONITORING
Noise monitoring will be carried out when concrete breaking begins within 20m of the building and when piling begins within 15m of the building. Measurements will be taken 1m from the faรงade of the building at first floor level and in one of the apartments overlooking Albert Street. The exact location of the internal measurements will be determined closer to commencement of the works in consultation with the affected receivers.
7.2
VIBRATION MONITORING
Vibration monitoring will be carried out when works begin on site to determine actual equipment vibration levels and the attenuation provided by the local ground conditions. Vibration monitoring will be carried out at the ground floor level of 41 Albert Street when concrete breaking begins within 16m of the building. The duration of the monitoring will depend upon the initial results. If levels are lower than predicted further monitoring may not be required. If levels are higher than predicted it may be necessary to set up a continuous logger for the duration of the concrete breaking works in the vicinity.
8 STAFF Before working on these activities all staff will receive training in accordance with Section 7.2 of the CNV DWP and will read and comply with this SSCNVMP.
Page 19
Auckland City Rail Link In association with:
ENABLING WORKS CONTRACT 2 SITE SPECIFIC CONSTRUCTION NOISE AND VIBRATION MANAGEMENT PLAN: DISTRICT COURT - DRAFT Separable Portion 1 – Cut and Cover Works Document Ref: CRL-PAT-ENV-CON-PLN-001265 Revision: 03
FINAL 3rd June 2016
COMMERCIAL IN CONFIDENCE
This page intentionally left blank.
DOCUMENT INFORMATION Organisation:
Connectus
Document Title:
Site Specific Construction Noise Management Plan
Fulcrum Document Number:
CRL-PAT-ENV-CON-PLN-001265
Document based on MMS No:
n/a
Client:
Auckland Transport
Project:
CRL Enabling Works: Contract Two
Location:
Auckland CBD
Project No:
2665
REVISION HISTORY Rev
Date
Details st
01
1
Draft for Connectus review
Author
Approver
C. Drewery
C Hind
02
21/03/16
Final
C. Drewery
C Hind
03
3/06/16
Final
C. Drewery
C Hind
This document remains the property of Connectus. Its contents are confidential and shall not be reproduced, destroyed or given away without the express, written permission of Connects. The electronic version of this document in MMS Database on designated server(s) is the Master Copy and is a controlled document. Unless specifically noted thereon, other copies of this document are uncontrolled.
This page intentionally left blank
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001265 rd Revision: 03, Date: 3 June 2016
Table of Contents Document information .........................................................................................................................3 Revision History ..................................................................................................................................3 1
Introduction........................................................................................................................7 1.1
Objective
7
1.2
Site plan
7
2
Receivers ..........................................................................................................................8
3
ActiVities ...........................................................................................................................8 3.1
Noise
3.2
Vibration
4
8 11
Predicted Noise and vibration levels................................................................................. 11 4.1
Noise
11
4.2
vibration
13
5
Mitigation ......................................................................................................................... 13 5.1
Noise
13
5.2
internal noise levels
15
5.3
Vibration
16
6
Communication and Consultation..................................................................................... 17
7
Monitoring ....................................................................................................................... 17
8
7.1
Noise monitoring
17
7.2
Vibration monitoring
18
Staff................................................................................................................................. 18
Page 5
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001265 rd Revision: 03, Date: 3 June 2016
This page intentionally left blank
Page 6
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001265 rd Revision: 03, Date: 3 June 2016
1 INTRODUCTION This is a Site Specific Construction Noise and Vibration Management Plan (SSCNVMP) and forms part of the Construction Noise and Vibration Delivery Work Plan (CNV DWP) for the CRL Contract 2 Enabling Works (the ‘Project’). This SSCNVMP provides specific assessment of construction noise and vibration received at the District Court located at 65-71 Albert Street. This SSCNVMP should be read in conjunction with the CNV DWP (Document Ref: CRL-PAT-ENV-CON-PLN-000903 Revision 6 dated 3rd June 2016) as it contains further details of the project, noise criteria, monitoring, general mitigation measures and other information. Details of the construction methodology are contained in the Project Construction Environmental Management Plan (CEMP). Acoustic terms are defined in the Acoustic Glossary in the CNV DWP.
1.1
OBJECTIVE
The objective of this SSCNVMP is to detail the best practicable option to avoid, remedy or mitigate adverse effects on sensitive receivers resulting from construction noise and vibration that does not comply with the Project Standards defined in Section 1.2 of the CNV DWP.
1.2
SITE PLAN
Figure 1 Site plan
Site compound
Main works area
District Court
Page 7
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001265 rd Revision: 03, Date: 3 June 2016
2 RECEIVERS The District Court occupies the building at 65-71 Albert Street. The building contains a number of court rooms, offices and meeting rooms. The courts generally operate from 8am to 5pm and are located on level 2 and above. They use electronic transcription and the microphones are extremely sensitive to noise and vibration so low background noise levels are essential. All windows are single glazed and the building is mechanically ventilated throughout. The District Court is located approximately 11m from the proposed cut and cover works. A construction works area is proposed to be located directly outside of the District Court approximately 6m from the building. The advanced utilities works come within 2m of the building.
3 ACTIVITIES 3.1
NOISE
Construction activities which have the potential to give rise to an exceedance of the Project Noise Standards (detailed in Section 1 of the CNV DWP) at the District Court are shown in Table 1 below. Start/end dates and hours of operation are also provided for each area of works. Start and end dates relate to the wider construction works area, and it is expected that activities around the trench itself will only generate significant noise in the vicinity of the District Court for a fraction of the overall activity duration. The main noise sources affecting the District Court will be those located within the construction compound area directly outside of the Court building. This construction works area will be in use for the full duration of the Project. Table 1 Construction activities
Works Phase
Construction Activity
Area of works
Activity Start Date
Activity End Date
Advanced Utilities Works
Utilities Relocation
KingstonWyndham St Stormwater Works
Early May
35 days
Combined Service Trench – Western Footpath including crossings
Early May
60 days
Wyndham St Stormwater Works
Early May
25 days
Wyndham St Chorus Works
Early June
15 days
Albert Street South East Quarter
14 Sep 2016
20 Sep 2016
Albert Street Piling and Capping Beam
Utilities location and exposure
Hours
7am – 7pm Mon - Sat
7am to 7pm
Page 8
Connectus Project #: 2665 Client: Auckland Transport
Works Phase
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001265 rd Revision: 03, Date: 3 June 2016
Construction Activity
Installation of CFA piles
Installation of pile cap
Excavation and Spoil Handling
Removal of existing road surface
Area of works
Activity Start Date
Activity End Date
Hours
Albert South West Quarter
29 Nov 2016
05 Dec 2016
Mon - Sat
Albert Street South East Quarter
26 Oct 2016
12 Dec 2016
Albert South West Quarter
22 Dec 2016
07 Mar 2017
Albert Street South East Quarter
02 Nov 2016
23 Dec 2016
Albert South West Quarter
12 Jan 2017
03 Mar 2017
South End to Ch550
23 Mar 2017
28 Mar 2017
(Ch614-550)
7am to 7pm Mon - Sat
and Shotcrete and Strip Drain Installation
Excavation 1st layer
29 Mar 2017
20 Apr 2017
Excavation 2nd layer to bottom
21 Apr 2017
01 Sep 2017
28 Aug 2017
26 Jan 2018
and Rock Dowel Installation
Waterproofing and Tunnel Construction
Waterproofing and tunnel construction
South End to Swanson
Trench Backfilling
Trench backfilling and reinstatement
South End to Swanson
3.1.1
7am to 7pm Mon – Sat
(Ch614-490) 27 Nov 2017
12 Apr 2018
(Ch614-490)
7am to 7pm Mon - Sat
Equipment
Construction equipment used for each of the above activities is shown in Table 2 with sound pressure level at 5m resulting from individual equipment items, as well as cumulative sound pressure level from simultaneous use of multiple equipment items during each activity. Construction equipment within the construction compound area is shown separately as these noise sources are closest to the District Court. These equipment items may also be included in one or more construction activities.
Table 2 Construction Equipment
Construction Activity
Equipment
Advanced Utilities / Service location and
Concrete saw Vacuum Excavation (type TBC)
Sound pressure level dB LAeq @ 5m 91 84
Cumulative Sound pressure level dB LAeq @ 5m 92 Page 9
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001265 rd Revision: 03, Date: 3 June 2016
Construction Activity
Equipment
exposure
Excavator-mounted rock breaker Soilmec Hydraulic Rotary Rig Excavator (est 15t) Concrete truck Mecbo tracked Concrete Pump Crane (40t) Excavator (est 15t) Hydraulic rock splitter Crane (40t) Road planer / milling machine Excavator 20t 6-wheel tipper trucks (10t) Excavator 20t Small excavator (5t – 14t) 6-wheel tipper trucks (10t) Excavator 14t Front end wheel loader Crawler crane with clamshell bucket (80t) long reach excavator 6-wheel tipper trucks (10t) Telehandlers Telescopic Crawler Crane Rough terrain scissor lift Mobile concrete pump Crane Delivery trucks Excavator mounted drill rig Crane Delivery trucks Angle grinder Excavator-mounted rock breaker Concrete core drill Telehandlers Excavator-mounted drill rig Water bowser Diesel compressor Petrol/diesel generator Crawler crane est 50t Delivery trucks Excavators 5-15t Front end loader Bobcat loader 6-wheel tipper trucks Roller compactors Plate compactors Mobile concrete pump Mobile concrete pump Front end loader Delivery trucks Petrol/diesel generator
Installation of CFA piles
Installation of pile cap Removal of existing road surface Excavation 1st layer
Excavation 2nd Layer to Bottom
Waterproofing and tunnel construction
Rock fall protection netting Pre-drilling
Drilling and rock dowel installation
Trench backfilling
Southern construction compound
Sound pressure level dB LAeq @ 5m 90 88 79 83 84 82 79 90 82 88 84 85 84 79 76 79 86
Cumulative Sound pressure level dB LAeq @ 5m 90
81
88
81 76 85 77 84 86 81 76 92 81 76 86 90 91 85 92 87 79 71 81 76 79 86 82 76 85 86 86 86 86 76 71
91
91
90
85
91
92
94
95
93
89
Page 10
Connectus Project #: 2665 Client: Auckland Transport
3.2
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001265 rd Revision: 03, Date: 3 June 2016
VIBRATION
Construction activities and equipment which are expected to generate significant vibration levels in the vicinity of the District Court are shown in Table 3 below along with start and end dates, and hours of operation. The start and end dates relate to the wider construction works area, and it is expected that activities will only generate significant vibration in the vicinity of the District Court for a fraction of the overall activity duration. Table 3 Vibration sources
Works Phase
Equipment
Type of works
Activity Start Date
Activity End Date
Hours
Advanced Utilities
Excavator mounted rock breaker
Concrete breaking
Early May 2016
June 2016
7am to 7pm
Rock Dowel Installation
Excavator mounted rock breaker
Pile breaking
23 Mar 2017
01 Sep 2017
Trench Backfilling
Roller compactors
Compacting fill
Plate compactors
Compacting fill in low clearance areas
Mon - Sat 7am to 7pm Mon - Sat
27 Nov 2017
12 Apr 2018
7am to 7pm Mon - Sat
4 PREDICTED NOISE AND VIBRATION LEVELS 4.1
NOISE
The predicted worst case noise levels from each activity received at the most exposed part of the District Court building are shown below in Table 4. These levels correspond to the construction equipment being located at its nearest position relative to the building and assume there is no physical mitigation between the noise source and the façade of the building. The predicted noise levels take into account whether works are being carried out at ground level or below the ground. Noise from the southern construction compound directly outside the District Court has been predicted separately although the relevant equipment items have also been included in predicted noise from other activities. Table 4 Predicted noise levels
Construction Activity
Project Noise Standard, dB LAeq
Predicted noise level with no mitigation, dB LAeq
Project Noise Standards exceedance, dB
Kingston-Wyndham St Stormwater Works
75
100
25
Combined Service Trench – Western Footpath
75
92
17
Wyndham St Stormwater
75
91
16 Page 11
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001265 rd Revision: 03, Date: 3 June 2016
Works Wyndham St Chorus Works Service location and exposure Installation of CFA piles Installation of pile cap Removal of existing road surface st Excavation 1 layer nd Excavation 2 Layer to Bottom Trench backfilling Waterproofing and tunnel construction Rock fall protection netting Pre-drilling Drilling and rock dowel installation Southern construction compound
75
77
2
75
89
14
75 75
88 88
13 13
75
85
10
75
80
5
75
76
1
75
88
13
75
76
1
75 75
78 80
3 5
75
81
6
75
83
8
Noise levels will decrease with distance from the noise source such that noise levels at higher floors and at facades not directly exposed to the noise source will be lower than those shown above. g with increasing floor level. Figure 2 2 shows noise levels due to CFA pile installation decreasing with increasing floor level. Figure 2 CFA Piling - facade noise levels
Page 12
Connectus Project #: 2665 Client: Auckland Transport
4.2
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001265 rd Revision: 03, Date: 3 June 2016
VIBRATION
Vibration regression curves and emission radii for the vibration sources in Table 3 can be found in the CNV DWP Section 5.2. The emission radius is the distance at which vibration levels from an activity/equipment item are expected to exceed the Project Vibration Standards for a particular type of building. For the purposes of assessing vibration, the District Court building is classed as historic/ vibration sensitive structure. A receiver is classified as ‘high risk’ if it is located within the emission radius for an activity, and ‘medium risk’ if it is close to the contour with possible intermittent exceedance. The emission radii and risk class associated with each vibration source at the District Court are shown in Table 5. Table 5 Vibration risk class
Works Phase
Equipment
Emission radius (m)
Distance to works (m)
Risk Class
Advanced Utilities Works
Excavator mounted concrete breaker
16
2
High
Rock Dowel Installation
Excavator mounted concrete breaker
16
11
High
We note that the emission radii are based on generic data based on conservatively sized equipment and ground conditions. Vibration levels from actual equipment at the site may differ and are likely to be less than assumed for the emission radius. Monitoring will be carried out at the earliest opportunity on site to determine the adjustments for ground conditions and actual equipment items. Additional monitoring will be conducted within the District Court to determine the building response. If necessary, equipment selections will be modified to ensure that the risk of vibration exceeding the building damage criteria is minimised as far as practicable.
5 MITIGATION 5.1
NOISE
Mitigation is required to meet the noise criteria at the District Court. In addition to the general noise and vibration control measures outlined in Section 7 of the CNV DWP, the following specific noise mitigation measures should be implemented (Table 6): Table 6 Specific Noise Mitigation Measures
Equipment/process
Noise control measures
Excavators, bobcats, loaders
Grease tracks regularly
Crane
Use straps rather than chains unless a risk assessment deems the use of straps unsafe.
Page 13
Connectus Project #: 2665 Client: Auckland Transport
Concrete cutting
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001265 rd Revision: 03, Date: 3 June 2016
Use a mobile acoustic enclosure where practicable. Use of a mobile acoustic enclosure may not be practicable when:
Cutting within 300mm of a kerb or canopy structure
Saw cuts need to be made around an obstruction that protrudes above surface level, such as a light pole or street sign.
The road saw needs to be manoeuvred around in a tight space that would be obstructed by the acoustic enclosure
When use of a mobile acoustic enclosure is not practicable works will be planned so that saw cutting directly in front of a receiver / receivers is completed within a total of two working days. The building owner(s) will be contacted prior to this occurring to see if the works can be scheduled for a time that least impacts them. Vacuum Excavation
Locate the vehicle so the pump is facing away from the closest noise sensitive properties
Construction Vehicles
Tonal reversing alarms will not be used. Broadband alarms will be used instead.
In addition to these measures, noise barriers/hoardings between the work site and the receiver will be used to reduce noise levels. These will be least 1.8m high and have a mass equal to or greater than 10 kg/m2. Panels will be abutted or overlapped to provide a continuous screen with no gaps. It may be acceptable to use a proprietary barrier with a reduced mass providing the required attenuation can be achieved. The contractor will seek approval from the Project Acoustic Specialist before using a proprietary barrier product on site. Indicative location of noise barriers is shown in green in Figure 3 below. Figure 3 Noise barriers
Temporary barrier during piling
Noise barriers are generally most effective when placed as close to the noise source as possible, and blocking line of sight between the source and receiver. Barriers are therefore most effective for noise
Page 14
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001265 rd Revision: 03, Date: 3 June 2016
sources located at or below ground level, and received at ground floor level. Little reduction is provided for receivers located at Level 3 and above. With the above mitigation and management measures implemented and barriers installed, the noise levels at the most exposed façade of the District Court will still exceed the noise criteria by more than 5 dB during some Project construction activities. Further mitigation is therefore necessary to achieve acceptable internal noise levels.
5.2
INTERNAL NOISE LEVELS
Noise measurements were carried out at the District Court to determine existing ambient noise levels. The noise measurements were taken on 21st January between 11am and 12pm. The measurement results are detailed in Table 7. Table 7 District Court Ambient Noise Levels
Measurement Location
dB LAeq
dB LAmax
Noise source(s)
Court Room 4 - 2m from window
37
58
Traffic - cars barely audible; low frequency noise buses/trucks dominant. HVAC on but barely audible
Court Room 4 Centre of room
33
48
Traffic - cars barely audible; low frequency noise buses/trucks dominant. HVAC on but barely audible
Albert St footpath outside ADC, 1m from Kerb
66
78
Traffic, pedestrians
It can be seen from Table 7 that the background noise levels in the Court Rooms when empty are very low. Low background noise levels are required for the electronic transcription service to operate effectively. It is expected that background noise levels will be slightly higher when the court rooms are occupied. An internal construction noise limit of 40 dB LAeq is recommended for the court rooms on the Albert Street façade. The building façade currently provides a sound reduction of approximately 30 dB(A). The windows are the weak point. The building is mechanically ventilated in all areas. The southern construction compound will be in use for the duration of the Project. The noise sources associated with the compound include construction vehicles, generators and loading/ unloading of steel and other construction materials. The noise level at the façade of the second and third floor court rooms is predicted to be 83 dB LAeq due to noise from the construction compound. With the current glazing this would give an internal noise level of approximately 53 dB LAeq which is too high when the courts are operating. It is recommended that the court rooms on the second and third floor that overlook Albert Street (Court 4, Court 15, Court 10 and Court13) and any Jury retiring rooms attached to these court rooms on the Albert Street façade are fitted with secondary glazing. The secondary glazing should be designed so that an internal level of 40 dB LAeq is achieved when the southern construction compound is in use. The following actions will be undertaken with regard to building modification:
The building owner will be contacted to discuss details of the recommended building mitigation.
Page 15
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001265 rd Revision: 03, Date: 3 June 2016
If the building owner wishes to proceed with the recommended building mitigation, arrangements will be made to visit the property to inspect the areas of the building where acoustic treatment is proposed and identify any issues that could affect installation of the mitigation. Additional noise measurements will be taken, where necessary, to confirm the acoustic performance requirements of the mitigation.
Any approvals required for the works under the Resource Management Act, Building Act and Historic Place Act will be obtained.
A legal agreement will be prepared for the installation of the acoustic treatment. The agreement will contain an explicit description of the acoustic treatment to be installed. Under the agreement Auckland Transport will take responsibility for commissioning the works (such as airflow and noise from ventilation systems) and for ensuring any required building consent inspections occur. The agreement includes a form to be signed by the property owner following commissioning to acknowledge that the works specified have been completed.
On completion of the mitigation works the property will be reinstated to a similar condition to that existing immediately prior to the works commencing.
Where secondary glazing is recommended the following should be implemented:
The existing window must be sealed before the secondary window is installed.
The secondary window shall be installed in a separate frame to the primary window, with no direct connections between the two frames.
The reveals between the primary and secondary windows shall be lined with an acoustically absorbent material having at least absorption class C in accordance with ISO 11654:1997.
Opening sections of the secondary window shall be aligned with openings in the primary window.
The installation of secondary glazing in these areas will mitigate all other construction activities in the trench alignment to acceptable levels. Some of the advanced utilities works outside of the trench alignment are within close proximity to the District Court building. The closest works are Kingston to Wyndham Street Stormwater Works, the Combined Service Trench (Western Footpath) and the Wyndham Street Stormwater Works. Internal noise levels due to these advanced utilities works are predicted to be 50 to 60 dB(A) even with secondary glazing fitted. It will therefore be necessary to work closely with the District Court to schedule these activities for a time that will least impact the court and not disrupt court proceedings.
5.3
VIBRATION
In addition to the general noise and vibration control measures outlined in Section 7 of the Project CNV DWP the following specific vibration mitigation measures (Table ) should be implemented if the initial on site vibration monitoring demonstrates that the building damage vibration limits will be exceeded: Table 8 Specific Vibration Mitigation Measures
Equipment/process
Vibration control measures
Excavator mounted rock breaker
Use lower vibration generating equipment such as a hand held jack hammer
Roller compactor (17t)
Use a smaller compactor, less than 10t
Page 16
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001265 rd Revision: 03, Date: 3 June 2016
6 COMMUNICATION AND CONSULTATION Section 9.1 of the CNV DWP details the communication procedures in relation to construction noise and vibration effects. The complaints process is detailed in Section 9.2 of the CNV DWP. Consultation with Auckland Programme Manager at the District Court took place on 16/12/15. Topics that were covered included:
Sequencing of construction activities
Likely equipment and associated noise and vibration levels
Mitigation & management measures that will be implemented
Construction of the building
Operating hours
Locations of particularly noise and vibration sensitive areas in the building
The Auckland Programme Manager raised general concerns about noise and vibration impacts. In particular the Courts on level 2 and above use electronic transcription and the microphones are extremely sensitive to noise and vibration so low background noise levels are required. As indicated in Section 5.2 ongoing consultation is going to be required to schedule the advanced utilities works in the vicinity of the District Court for a time that will not impact court operations.
7 MONITORING In addition to the external noise and vibration monitoring detailed in the CNV DWP, internal noise and vibration measurements will be taken in the most exposed court room when the construction area immediately outside of the building is set up and in use and when piling is occurring within 25m of the building.
7.1
NOISE MONITORING
The Youth Court (Court 15) on Level 2 has been provisionally selected for noise monitoring as it is on the area of the façade most exposed to expected construction noise, taking into account the effect of the noise barriers as described in Section 5.1 and is one of the most noise sensitive areas. Noise st levels will also be measured in the ground floor victim advisors area and 1 floor offices at critical phases of construction (at the commencement of services location and exposure, CFA piling and set up/ use of the construction area outside of the building) to ensure that the noise barriers are providing the required level of noise mitigation in these areas and to check regenerated noise is not an issue. The final location will be confirmed in consultation with District Court to ensure that the measurements do not impede court operations. A microphone and ancillary equipment (logger, battery, case) will be set up in the selected location(s) before the commencement of construction activities in the defined area. Background noise will be measured prior to construction to determine the contribution of extraneous noise sources such as traffic and building services.
Page 17
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001265 rd Revision: 03, Date: 3 June 2016
If the initial internal measurements show noise to be at or close to levels that may impede operations it may be necessary to install continuous noise loggers in the District Court building.
7.2
VIBRATION MONITORING
Vibration from construction activities in the trench alignment is not predicted to exceed the building damage criteria. Vibration monitoring will only be necessary during the advanced utilities works where vibration levels are predicted to exceed the Project criteria. The monitoring will be carried out at ground floor level. The northern end of the corridor outside the victim advisors area has been provisionally selected for monitoring.
8 STAFF Before working on these activities all staff will receive training in accordance with Section 7.2 of the CNV DWP and will read and comply with this SSCNVMP.
Page 18
Auckland City Rail Link In association with:
ENABLING WORKS CONTRACT 2 SITE SPECIFIC CONSTRUCTION NOISE AND VIBRATION MANAGEMENT PLAN: STAMFORD PLAZA HOTEL Separable Portion 1 – Cut and Cover Works Document Ref: CRL-PAT-ENV-CON-PLN-001186 Revision: 07
Final 25th May 2016
COMMERCIAL IN CONFIDENCE
This page intentionally left blank.
DOCUMENT INFORMATION Organisation:
Connectus
Document Title:
SITE SPECIFIC CONSTRUCTION NOISE AND VIBRATION MANAGEMENT PLAN: STAMFORD PLAZA HOTEL
Fulcrum Document Number:
CRL-PAT-ENV-CON-PLN-001186
Document based on MMS No:
n/a
Client:
Auckland Transport
Project:
CRL Enabling Works: Contract Two
Location:
Auckland CBD
Project No:
2665
REVISION HISTORY Rev
Date
Details st
Draft for Connectus review
Author
Approver
C. Drewery
C Hind
01
29/02/16
1
02
11/03/16
IPR Comments Addressed -
C. Drewery
C Hind
03
24/03/16
For Stamford Plaza Review
C. Drewery
C Hind
04
31/03/16
For Stamford Plaza Review – updated to include initial comments
C. Drewery
C Hind
05
9/05/16
For Stamford Plaza Review – updated to include initial comments from Stamford Plaza and their noise expert
C. Drewery
C Hind
06
17/05/16
Final for Issue
C. Drewery
C Hind
07
25/05/16
Final for Issue – updated to include latest comments from Stamford Plaza
C. Drewery
C Hind
This document remains the property of Connectus. Its contents are confidential and shall not be reproduced, destroyed or given away without the express, written permission of Connects. The electronic version of this document in MMS Database on designated server(s) is the Master Copy and is a controlled document. Unless specifically noted thereon, other copies of this document are uncontrolled.
This page intentionally left blank
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001186 Revision: 07, Date: 25 May 2016
Table of Contents _Toc451955877 Document information .........................................................................................................................3 Revision History ..................................................................................................................................3 1
Introduction........................................................................................................................6 1.1
Objective
6
1.2
Site plan
6
2
Receivers ..........................................................................................................................7
3
Activities ............................................................................................................................8
4
Mitigation ......................................................................................................................... 11 4.1
Noise
11
4.2
Vibration
14
5
Predicted Noise and Vibration Levels ............................................................................... 14 5.1
Noise
14
5.2
vibration
17
6
Communication and Consultation..................................................................................... 17
7
Monitoring ....................................................................................................................... 21 7.1
Noise monitoring
21
7.2
Vibration monitoring
22
8
9
Contingency Measures .................................................................................................... 23 8.1
Noise
23
8.2
Vibration – Building Damage
24
8.3
Vibration - Amenity
24
Staff................................................................................................................................. 24 th
Appendix A: Utilities and Piling Programme (As issued to Stamford plaza on 5 May 2016) .............. 25
Page 5
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001186 Revision: 07, Date: 25 May 2016
1 INTRODUCTION This is a Site Specific Construction Noise and Vibration Management Plan (SSCNVMP) and forms part of the Construction Noise and Vibration Delivery Work Plan (CNV DWP) for the CRL Contract 2 Enabling Works (the ‘Project’). This SSCNVMP provides specific assessment of construction noise and vibration effects on the Stamford Plaza Hotel located at 22-26 Albert Street. This SSCNVMP should be read in conjunction with the CNV DWP (Document Ref: CRL-PAT-ENV-CON-PLN-000903 Revision 5 dated 24th March 2016) as it contains further details of the Project, noise criteria, monitoring, general mitigation measures and other information. Details of the construction methodology are contained in the Project Construction Environmental Management Plan (CEMP). Acoustic terms are defined in the Acoustic Glossary in the CNV DWP.
1.1
OBJECTIVE
The objective of this SSCNVMP is to detail the Best Practicable Option to avoid, remedy or mitigate adverse effects on the Stamford Plaza, including itsguests and/or visitors, resulting from construction noise and vibration.
1.2
SITE PLAN
Figure 1 shows the location of the works in relation to the Stamford Plaza hotel. Figure 1 Site plan
Page 6
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001186 Revision: 07, Date: 25 May 2016
2 RECEIVERS The Stamford Plaza Hotel occupies the building at 22-26 Albert Street from the basement up to Level 10. Level 11 and above is occupied by Stamford Residences. The basement level is used for car parking; Ground Floor/Mezzanine for lobby, reception, bar/restaurant, function and conference rooms; Levels 3 and 4 are used for car parking and hotel rooms; and Levels 5 to 10 are used for hotel rooms. All spaces are mechanically ventilated. Measurements by Marshall Day Acoustics (MDA) as documented in the Third Supplementary Statement of Evidence of Craig Michael Fitzgerald, dated 23 October 2013, indicate that the external to internal noise level difference in hotel suites is in the order of 35 dB. Table 1 Receiver information
Address
22-26 Albert Street
Building use
Mixed use (commercial/ residential)
Historic / vibration sensitive
Minimum Distance to Works, m
Project Noise Standards dB dB LAeq LAFmax
Project Vibration Standard s, (PPV mm/s)
Project Vibration Amenity Standards, (PPV mm/s) 0.3mm/s and 35 dBA (10pm-7am in bedrooms) 1.0 mm/s (7am-10pm in bedrooms)
N
9
75*
90*
5 2.0 mm/s (7am-10pm in retail and office spaces (including work areas and meeting rooms)
* This is the Monday to Saturday 07:00 to 22:00 noise criteria. The majority of works will be carried out during this period. For residential receivers the noise limit is reduced to 65 dB L Aeq & 80 dB LAFmax on Sundays and Public Holidays between 07:00 to 22:00 and to 60 dB LAeq & 75 dB LAFmax at all other times.
Stamford Plaza has a number of tenant businesses at ground floor level. These include Grasshopper restaurant, BaaBaaBlack Sheep CafĂŠ, United Travel, Expresso Coffee School, Izakya Kintano Japenese Restaurant, Imagine Fitness Centre and Thai Massage. Designation Condition 38.4 allows for the Project Vibration Standards to be relaxed by a SSCVMP but only for a building, structure or infrastructure that has been assessed by a suitably qualified and experienced structural engineer and where it has been deemed to be capable of withstanding higher vibration levels without sustaining building or structural damage, and where appropriate vibration and building condition monitoring regimes are in place. Based on the building condition surveys and the initial assessments by the structural engineer the building vibration limits could be relaxed. However, it is considered prudent to keep the Project Vibration Building Damage Standards to better enable compliance with the Project Vibration Amenity Standards.
Page 7
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001186 Revision: 07, Date: 25 May 2016
3 ACTIVITIES Construction activities which have the potential to give rise to an exceedance of the Project Noise and/ or Vibration Standards (detailed in Section 1 of the CNV DWP) at the Stamford Plaza are shown in Table 2 below. Start/end dates and hours of operation are also provided for each area of works. The start and end dates relate to the wider construction works area, it is expected that activities will only generate significant noise and/or vibration in the vicinity of the Stamford Plaza for a fraction of the overall activity duration. Table 2 Construction activities
Works Phase
Construction Activity
Area of works
Activity Start Date*
Activity End Date*
Hours
Advanced Utilities Works
Utilities relocation
Between Points A and B:
13 Jun 2016
5 Aug 2016
7am to 7pm
(including saw cutting and vacuum excavation)
Vector Electricity across Albert Street at Swanson Street
Utilities location and exposure
Between Points A and B:
(including saw cutting and vacuum excavation)
Both sides of Albert Street
Installation of CFA piles
Between Points A and B:
Albert Street Piling and Capping Beam
Installation of pile cap Excavation and Spoil Handling
Removal of existing road surface
Both sides of Albert Street
Swanson St to Wolfe St (Ch370490)
Mon - Fri
20 Jun 2016
29 Jul 2016
7.30am to 6.00pm Mon - Sat
8 non consecutive weeks between 10 Oct 2016 and 04 May 2017 as shown in the programme in Appendix A
19 May 2017
8 Jun 2017
7am to 7pm Mon - Sat
and Shotcrete and Strip Drain Installation
st
31 May 2017
28 Jun 2017
nd
29 Jun 2017
05 Dec 2017
05 Jun 2018
Excavation 1 layer
and Rock Dowel Installation
Excavation 2 layer to bottom
Waterproofing and Tunnel Construction
Waterproofing and tunnel construction
Swanson St to Wolfe St (Ch370490)
01 Dec 2017
Trench Backfilling
Trench backfilling and reinstatement
Swanson St to Wolfe St (Ch370490)
05 Mar 2018
7am to 7pm Mon – Sat
11 Sep 2018
7am to 7pm Mon - Sat
Page 8
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001186 Revision: 07, Date: 25 May 2016
* The dates shown in Table 2 are dependent on the Stamford Plaza SSCNVMP being finalised and subsequently agreed to by Auckland Council. If the timeframe for this is delayed then the start of construction will be delayed accordingly. * Up to 5 additional days (which may consist of Saturdays during the period 13 Jun – 5 Aug 2016, or consecutive construction work days immediately following that period) and up to 2 additional weeks may be required as a contingency for the ‘Advanced Utilities Works’ and the ‘Installation of CFA Piles and Installation of Pile Cap’ respectively. Piling, saw cutting and any other activity that produces noise in excess of the Project Noise Criteria (see Table 1) will only be carried out between the hours of 07:30 and 18:00 Monday to Saturday in the area between 20m north of Mills Lane (Point A, shown of Figure 1 above) and 20m south of Swanson Street (Point B, shown of Figure 1 above). Saw cutting, hydro excavation, concrete breaking (if required) and any other activity associated with the prepatory works between Points A and B that produces noise in excess of the Project Noise Criteria will be complete within 40 days as indicated in Table 2. Connectus may continue less noisy activities that comply with the Project Noise Standards, such as completing pavement reinstatement, cable pulling beyond the 40 day period. The piling works on each side of the road will be undertaken in two – three different stages, in order to manage traffic and access into the Stamford site, but the total duration of these different stages will not exceed the specified period as indicated in Table 2. 3.1.1
Equipment
Construction equipment used for each of the above activities is shown in Table 3 with sound pressure level at 5m resulting from individual equipment items. These equipment levels are placeholders. All equipment will be measured operating independently and then actual equipment noise levels and model numbers will be recorded and updated within the table. Figure 2 details the process that will be followed once actual equipment noise levels have been measured. Table 3 Construction Equipment
Construction Activity
Equipment
Utilities relocation, utilities location and exposure
Concrete saw Vacuum Excavation
Installation of CFA piles
Installation of pile cap Removal of existing road surface st
Excavation 1 layer
nd
Excavation 2 to Bottom
Layer
Soilmec Hydraulic Rotary Rig (est SR80) Excavator (est 15t) Concrete truck Mecbo tracked Concrete Pump Crane (40t) Excavator (est 15t) Concrete saw or breaker Crane (40t) Road planer / milling machine Excavator 20t 6-wheel tipper trucks (10t) Excavator 20t Small excavator (5t – 14t) 6-wheel tipper trucks (10t) Excavator 14t Front end wheel loader Crawler crane with clamshell bucket (80t) or long reach excavator
Sound pressure level dB LAeq @ 5m 91 84 88 79 83 84 82 79 91 82 88 84 85 84 79 76 79 86 81 81 Page 9
Connectus Project #: 2665 Client: Auckland Transport
Construction Activity
Waterproofing and tunnel construction
Rock fall protection netting Pre-drilling
Drilling and rock dowel installation
Trench backfilling
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001186 Revision: 07, Date: 25 May 2016
Equipment 6-wheel tipper trucks (10t) Telehandlers Telescopic Crawler Crane Rough terrain scissor lift Mobile concrete pump or Static pump and boom Crane Delivery trucks Excavator mounted drill rig Crane Delivery trucks Angle grinder Excavator-mounted rock breaker Concrete core drill Telehandlers Excavator-mounted drill rig Water bowser Diesel compressor Petrol/diesel generator Crawler crane est 50t Delivery trucks Excavators 5-15t Front end loader Bobcat loader 6-wheel tipper trucks Roller compactors Plate compactors Concrete pump
Sound pressure level dB LAeq @ 5m 76 85 77 84 86 86 81 76 92 81 76 86 90 91 85 92 87 79 71 81 76 79 86 82 76 85 86 84
Page 10
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001186 Revision: 07, Date: 25 May 2016
Figure 2 Process to follow once actual equipment noise levels have been measured
4 MITIGATION 4.1
NOISE
Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance of staff and guests, loss of concentration, reduction in speech intelligibility and annoyance of cafĂŠ/ restaurant patrons who may then choose to eat elsewhere.
Page 11
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001186 Revision: 07, Date: 25 May 2016
Mitigation is required to meet the Project Noise Standards at the Stamford Plaza Hotel. In addition to the general noise and vibration control measures outlined in Section 7 of the CNV DWP, the specific noise mitigation measures detailed in Table 4 will be implemented. These mitigation measures represent the Best Practicable Option to avoid, remedy or mitigate adverse effects on the Stamford Plaza Property, its guests and/or visitors. The mitigation measures detailed in Table 4 and in Section 7 of the CNV DWP reflect BPO as they represent everything that can practicably be done to mitigate noise at the source. Table 4 Specific Noise Mitigation Measures
Equipment/process
Noise control measures
Concrete cutting
Use a mobile acoustic enclosure where practicable. Use of a mobile acoustic enclosure may not be practicable when:
Cutting within 300mm of a kerb or canopy structure Saw cuts need to be made around an obstruction that protrudes above surface level, such as a light pole or street sign.
The road saw needs to be manoeuvred around in a tight space that would be obstructed by the acoustic enclosure
When use of a mobile acoustic enclosure is not practicable works will be planned so that saw cutting directly in front of a receiver is completed within a total of two working days. The building owner will be contacted prior to this occurring to see if the works can be scheduled for a time that least impacts them. Concrete breaking
It is assumed that all concrete can be removed by saw cutting and lifting with an excavator. Concrete breakers will not be used in the vicinity of the Stamford Plaza Hotel unless something is encountered in the ground that cannot be removed by any other method. In this case the smallest breaker capable of completing the task will be used and where practicable the works will be carried out in a mobile acoustic enclosure. Alternatively, muffled breakers will be used.
Vacuum Excavation
Locate the vehicle so the pump is facing away from the closest noise sensitive properties
Piling
The new design has reduced the number of piles within the zone (20m north of Mills Lane to 20m South Of Swanson) on the East side of Albert Street considerably. The original design as presented in the Notice of Requirement hearings used approximately 87 piles. Connectus have been able to reduce this to only 60 piles. The method of piling has also changed from the original design. Piling will now be by Continuous Flight Auger which produces less noise and vibration.
Excavators, bobcats, loaders
Excavators of 15t or less will be used in the vicinity of Stamford Plaza Hotel unless it can be demonstrated by measurement that bigger excavators will meet the noise criteria. Tracks will be greased regularly.
Crane
Straps rather than chains will be used unless a risk assessment deems the use of straps unsafe.
Excavator mounted drilling rig
Localised screening will be used where required. The screens will be positioned to cut line of site between the noisy elements of the drilling rig and locations on the Stamford Plaza façade where the Project Noise Standards would otherwise be exceeded.
Construction Deck
The original construction methodology presented at the Notice of Requirement hearings showed a single deck structure being built across Albert Street in front of Stamford Plaza Hotel. It was proposed that all materials for constructing the tunnel came in and out of this point during the Page 12
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001186 Revision: 07, Date: 25 May 2016
excavation, tunnel construction and backfilling phases. The new design has switched to a continuous deck structure, which has reduced the requirement for plant to be located near Stamford Plaza by at least 50%. Construction vehicles
Tonal reversing alarms will not be used. Broadband alarms will be used instead.
In addition to these measures, noise barriers/hoardings between the work site and the receiver will be used to reduce noise levels. These will be at least 1.8m high during the advanced utilities works and piling and 2m high during the remainder of the works. There will be the ability to increase barrier height during the main trenching works should it be found that items of equipment are significantly noisier than what is authorised by this plan and higher barriers are required to meet the Project Noise Standards. The barriers will have a mass equal to or greater than 10 kg/m2. Panels will be abutted or overlapped to provide a continuous screen with no gaps. It may be acceptable to use a proprietary barrier with a reduced mass providing the required attenuation can be achieved. The contractor will seek approval from the Project Acoustic Specialist before using a proprietary barrier product on site. Indicative location of noise barriers is shown in Figure 3 below. Figure 3 Noise barriers
1.8m noise barriers during advanced utilities works, 2m for remainder
Noise barriers are generally most effective when placed as close to the noise source as possible, and blocking line of sight between the source and receiver. Barriers are therefore most effective for noise sources located at or below ground level, and received at ground floor level. Little reduction is provided for receivers located at Level 3 and above. Table 5 below shows maximum expected noise levels received at each floor level due to installation of CFA piles, with no mitigation and with 1.8m high noise barriers in the location shown in Figure 3 above. The effect of the barriers is also shown in Figure 4. Table 5 Noise levels from CFA piling, with and without noise barriers
Floor level
Noise level, dB LAeq
Noise level, dB LAeq
No barrier
1.8m Barrier
Noise level reduction, dB
GF
90
78
12
Mezzanine
89
82
7
L3
88
84
4 Page 13
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001186 Revision: 07, Date: 25 May 2016
L4
86
85
1
L5
85
85
0
L6
84
83
1
L7
83
82
1
L8
82
81
1
L9
81
81
0
L10
80
80
0
A similar level of noise reduction from noise barriers at each floor can be expected for all other construction activities where the dominant noise source is close to ground level. Different barrier heights (2.4m and 3m) were modelled. Increasing the barrier height had very little effect on the noise levels at the building which reduced by only 1-2 dB. This reduction in noise level would not be perceptible. When considering this limited effect against the structural constraints of increasing the barrier height and the additional cost it is not consider to be practicable to increase the barrier height. Noise levels at the entrance were assessed to determine if installation of a sound lock lobby and/or a revolving door would represent the BPO. Noise levels during piling, which is one of the noisiest activities, are predicted to be 76 dB LAeq at the entrance to the building. This noise level will occur when the piling rig is in the closest location to the entrance and will only be this high for 2-3 pile locations which will take less than a day to complete. At all other pile locations the noise level at the front door will be reduced and will meet the Project Noise Standards. As the Project Noise Standard will be met, other than during a day of piling as indicated above, at the entrance to the hotel, installation of a sound lock lobby or a revolving door is not considered to represent the BPO.
4.2
VIBRATION
In addition to the general noise and vibration control measures outlined in Section 7 of the Project CNV DWP the following specific vibration mitigation measures (Table 6) should be implemented if the initial on site vibration monitoring demonstrates that the building damage vibration limits will be exceeded: Table 6 Specific Vibration Mitigation Measures
Equipment/process
Vibration control measures
Excavator mounted concrete breaker
Concrete breakers will not be used unless something is encountered in the ground that cannot be removed by saw cutting. Should breakers be required a hand held jack hammer rather than an excavator mounted breaker will be used when within 10m of the Stamford Plaza Hotel.
5 PREDICTED NOISE AND VIBRATION LEVELS 5.1
NOISE
The predicted worst case noise levels from each activity received at the most exposed part of the Stamford Plaza building are shown below in Table 7. These levels correspond to the construction Page 14
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001186 Revision: 07, Date: 25 May 2016
equipment being located at its nearest position to Stamford Plaza Hotel and assume that all mitigation detailed in Section 7 of the CNV DWP and Section 4.1 of this SSCNVMP has been implemented. The predicted noise levels take into account whether works are being carried out at ground level or below the ground. Table 7 Predicted noise levels
Construction Activity
Project Noise Standard, dB LAeq
Advanced Utilities Works
75
Predicted noise level with all mitigation measures implemented, dB LAeq 87***
75
87***
12*
75
85
10**
75
75
0
75
74
0
75
71
0
75
74
0
75
74
0
75
75
0
Utilities location and exposure (inside trench area along piling line) Piling Removal of existing road surface st Excavation 1 layer Excavation 2nd Layer to Bottom Drilling – Rock Dowel Waterproofing and tunnel construction Trench backfilling
Project Noise Standards exceedance, dB 12*
*This exceedance is caused by saw cutting **This exceedance is caused by the piling rig *** This level is at the most exposed area of the façade, not directly outside a bedroom or conference room. The level outside of the most exposed bedroom/ conference room is 85 dB LAeq
Noise levels will decrease with distance from the noise source such that noise levels at higher floors and at facades not directly exposed to the noise source will be lower than those shown above. This is illustrated in Figure 4 showing noise levels due to CFA pile installation decreasing with increasing floor level.
Page 15
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001186 Revision: 07, Date: 25 May 2016
Figure 4 CFA Piling - facade noise levels
5.1.1
Internal noise levels
Assuming all mitigation and management measures detailed in Section 7 of the CNV DWP and Section 4.1 of this SSCNVMP are implemented, and an external to internal noise level difference of 35 dB is achieved, internal noise levels are predicted to be 50 dB LAeq or below in all hotel rooms and conference rooms during all construction activities. Façade sound insulation improvements are therefore not considered necessary for the Stamford Plaza Hotel. With regard to the tenant businesses, BaaBaa Black Sheep Café and the Grasshopper restaurant will be most affected as they are located on the Albert Street façade. They are mechanically ventilated with glazed façades. The glass doors are the weak point when considering noise ingress as they do not have seals and there are big gaps around the perimeter of the door. Acoustic seals (bulb seals) should be fitted to the doors. They would not provide much benefit during busy times when the doors are being frequently opened but would provide a noticeable benefit when the doors are shut. When piling or utilities location works are taking place immediately outside construction noise levels will be audible above background and have the potential to annoy staff and customers. Further consultation will take place with these businesses before works begin outside of the building and where possible noisy activities will be scheduled outside of their busiest times. United Travel, Expresso Coffee School, Izakya Kintaro Japenese Restaurant and Thai Massage are located on the Swanson Street façade of the building. Swanson Street is a reasonably steep hill. As these receivers sit below the level of Albert Street the noise barriers detailed in Section 5 of this SSCNVMP will provide a greater level of sound reduction when compared to the tenant businesses located on the Albert Street façade. The noise level at these receivers will meet the Project Noise Standards.
Page 16
Connectus Project #: 2665 Client: Auckland Transport
5.2
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001186 Revision: 07, Date: 25 May 2016
VIBRATION
Vibration regression curves and emission radii for the vibration sources can be found in Section 5.2 of the CNV DWP. The emission radius is the distance at which vibration levels from an activity/equipment item are expected to exceed the Project Vibration Standards for a particular type of building. For the purposes of assessing vibration, the Stamford Plaza Hotel building is classed as Residential. We note that the emission radii are based on generic data, conservatively sized equipment and ground conditions. Vibration levels from actual equipment at the site may differ and are likely to be less than assumed for the emission radius. The only equipment predicted to exceed the Project Vibration Standards is the excavator mounted concrete breaker if used within 10m of the building. As discussed previously this equipment will only be used if something is found during the works that cannot be removed by saw cutting. If something is found that requires the use of a breaker within 10m of the building, Stamford Plaza will be immediately notified and arrangements will be made to monitor vibration in the most affected part of the building for the duration of the breaker activity in this area. Monitoring will be carried out at the earliest opportunity on site to determine the adjustments for ground conditions and actual equipment items. If the initial vibration monitoring demonstrates that the emission radii are similar to those detailed in Section 5.2 of the CNV DWP the mitigation detailed in Section 4.2 of this SSCNVMP will be implemented. Vibration from construction activities will be continuously measured in the Stamford Plaza building to monitor compliance with the Project Vibration Standards, as detailed in Section 7.2 of this SSCNVMP. Section 8 of this SSCNVMP details the process that will be followed if vibration levels in excess of the Project Vibration Standards are measured.
5.3
COMPLIANCE WITH THE PROJECT NOISE AND VIBRATION STANDARDS
This SSCVNMP authorises piling, saw cutting and concrete breaking (should it be required) to exceed the Project Noise Standards. The maximum predicted exceedance is 12 dB, refer to Table 7. This SSCNVMP authorises concrete breaking (should it be required) to exceed the Project Vibration Amenity Standards when carried out within 10m of the building. All other construction activities are predicted to, and must comply with the Project Noise and Vibration Standards
6 COMMUNICATION AND CONSULTATION Section 9.1 of the CNV DWP details the communication procedures in relation to construction noise and vibration effects. The complaints process is detailed in Section 9.2 of the CNV DWP. The Communication and Consultation Manager for the Project is Alan Howard-Smith, telephone number 021 361158, email alan.howard-smith@hawkins.co.nz. All communications and complaints should be directed to him in the first instance either electronically or via telephone. Alternatively the project will be contactable 24/7 through the freephone number, 0800 CRL TALK (275 8255). All complaints, meetings and actions will be recorded on the CRM database.
Page 17
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001186 Revision: 07, Date: 25 May 2016
Consultation with the Stamford Plaza Hotel took from mid-November to mid-February. Topics that were covered included:
Sequencing of construction activities
Likely equipment and associated noise and vibration levels
Mitigation & management measures that will be implemented
Construction of the hotel building
Location of the various tenants and the sensitive spaces in the hotel
Operational hours of the tenants businesses
Operating environment that is required by the hotel and its tenants
Further details of the meetings and comments made by the stakeholders are provided in Table 8.
Page 18
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001186 Revision: 07, Date: 25 May 2016
Table 8 Stakeholder Consultations
Address of Sensitive Receiver 22/26 Albert Street Stamford Plaza Hotel and Tenants:
United Travel Espresso Coffee School
BaaBaa Black Sheep Café
Grasshopper Thai Restaurant
Taiko Japanese Restaurant
Imagine Fitness
Representatives
Issue raised or comment provided
16/11/15
Concern about generator noise
Interviews with all business owners, and hotel General Manager
Concern from some parties about noise in general as they have doors facing onto Swanson Street that remain open. Thai Massage needs quiet conditions to operate
How comment was incorporated (or if not incorporated, reason why not) With the mitigation and management measures detailed in Section 7 of the CNV DWP and Section 4 of this SSCNVMP implemented, works may be audible but will not be at a level that interferes with business operations. Vibration may be felt but will not be at a level that damages the building. Section 7 of this SSCNVMP provides details of the proposed noise and vibration monitoring.
22/26 Albert Street
17/11/15
Noise concerns as door is open all day
Expresso Coffee School
Follow up discussion with business owner and general inspection of façade, ventilation etc
Noise impact on outside seating area
With the barriers installed as specified in Section 7 of the CNV DWP and Section 4 of this SSCNVMP noise from all construction activities will comply with the Project Noise Standards at this receiver.
22/26 Albert Street
17/11/15
United Travel
Follow up discussion with business owner and general inspection of façade, ventilation etc
Concerned about noise impacting their operations. They speak to customers all day in person or on the telephone so need reasonably quiet working environment
With the barriers installed as specified in Section 7 of the CNV DWP and Section 4 of this SSCNVMP noise from all construction activities will comply with the Project Noise Standards at this receiver.
Noise break-in through the door could be an issue as there is a 1-2cm gap around the perimeter of the door. The landlord is proposing to install some seals to rectify this.
Page 19
With door seals fitted, as currently proposed by the landlord, construction noise will not be at a level that impacts the business operations of this receiver.
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001186 Revision: 07, Date: 25 May 2016
22/26 Albert Street
20/11/15
Needs a quiet environment for clients
Thai Massage
Follow up discussion with business owner and general inspection of faรงade, ventilation etc
Treatment rooms are adjacent to the faรงade overlooking Swanson Street
22/26 Albert Street
Also concerned about vibration
Meeting with the hotels building engineer
Meeting to determine where the noise and vibration monitoring equipment could be located in the hotel.
22/26 Albert Street
26/02/16
Stamford Plaza Hotel
Meeting with new General Manager
Meeting with the new General Manager to provide an overview of the noise and vibration management plans.
Stamford Plaza Hotel
Concerns raised over the potential noise and vibration impact on hotel guests. Confirmed that the chosen locations for noise and vibration monitoring are acceptable.
Page 20
With the barriers installed as specified in Section 7 of the CNV DWP and Section 4 of this SSCNVMP noise from all construction activities will comply with the Project Noise Standards at this receiver. Vibration is unlikely to be at perceptible levels in this receiver. The monitoring locations detailed in Section 7 of this SSCNVMP are the ones agreed with Stamford Plaza Hotel. With the mitigation and management measures detailed in Section 7 of the CNV DWP and Section 4 of this SSCNVMP implemented internal noise levels are predicted not to trigger the compensation provisions in the Agreement with Stamford Plaza during all construction activities. Vibration may be felt but will not be at a level that damages the building.
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001186 Revision: 07, Date: 25 May 2016
7 MONITORING In addition to the noise and vibration monitoring detailed in the CNV DWP, noise and vibration from construction activities will be continuously measured to monitor compliance with the Project Noise and Vibration Standards.
7.1
NOISE MONITORING
The location shown in Figure 5 (Level 3 Room 342) has been selected for noise monitoring as it is a laundry storage area, not a room that is used by guests. This location has been agreed with Stamford Plaza Hotel as the equipment will not impede hotel operations. Additional monitoring positions will be utilised, subject to approval by Stamford Plaza, to measure noise in the most exposed locations as work progresses in front of the building. Figure 5 Proposed noise monitoring location
Proposed noise monitoring location
A microphone and ancillary equipment (logger, battery, case) will be set up by a suitably qualified professional in the selected location before the commencement of construction activities. Background noise will be measured prior to construction to determine the contribution of extraneous noise sources such as traffic and building services. Noise levels will be measured continuously in 15 minute intervals for the duration of construction works. Audio may be recorded (with the permission of Stamford Plaza Hotel) along with noise levels to help exclude extraneous sources such as guest conversation, traffic and building services from the results. Noise level data will be downloaded periodically to monitor ongoing compliance with the Project Noise Standards. Noise levels during the 40 consecutive day construction period for the preparatory works will be reported to Stamford Plaza at least every 48 hours. Outside of this period, noise levels will be reported to Stamford Plaza no less than every 7 days. The reports will describe how the noise levels compare to the Project noise Standards.
Page 21
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001186 Revision: 07, Date: 25 May 2016
Simultaneous measurements will be taken 1m from the building faรงade when work commences to determine the level of sound reduction provided by the faรงade in this area. This level will then be used to adjust internal noise levels for comparison with the external Project Noise Standards. Noise levels will also be measured in the ground floor conferencing and lobby/bar areas at critical phases of construction (at the commencement of services location and exposure, CFA piling and rock dowel drilling) to ensure that the noise barriers are providing the required level of noise mitigation in these areas.
7.2
VIBRATION MONITORING
The location shown in Figure 6 has been selected for vibration monitoring as it is at ground floor level in an area not used by staff or guests. This location has been agreed with Stamford Plaza Hotel as the equipment will not impede hotel operations. The proposed monitoring location is representative of the western faรงade of the building where PPV is expected to be highest. Vibration levels will be measured prior to construction to determine the contribution of extraneous vibration sources such as traffic. Additional monitoring positions will be utilised, subject to approval by Stamford Plaza, to measure vibration in the most exposed locations as work progresses in front of the building.
Figure 6 Proposed vibration monitoring location
Proposed vibration monitoring location
Vibration monitoring will also be undertaken at the highest level of the hotel in accordance with the requirements of DIN4150-3 to monitor horizontal motion. Due to the need to ensure the best practicable measures to avoid damage and also manage occupant concerns, vibration levels will be monitored in person when a new activity is undertaken which may produce readily perceptible vibration in the hotel space. Activities that will continue to produce readily perceptible vibration logging results will be reported to Stamford no less thatn every 7 days in Page 22
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001186 Revision: 07, Date: 25 May 2016
accordance with the requirements of DIN 4150-3. The reports will describe how the vibration levels compare to the Project vibration Standards.
8 CONTINGENCY MEASURES Section 11 of the CNV DWP describes the contingency measures to be implemented in the event that noise and vibration limits are exceeded. A summary of those measures is detailed below. Where any construction activity is predicted and/or measured to exceed the Project Noise Standards or the Project Vibration Standards and is not authorised to do so by this SSCNVMP, see Section 5.3, the following process will be applied:
Check that the BPO and all relevant management measures have been implemented (refer Section 7 of the CNVMP and Section 4 of this SSCNVMP)
Communication and Consultation Manager to consult with all affected parties, to understand their particular sensitivities, including times, activities and locations. The Communication and Consultation Manager or their representative shall be available 24/7.
Carry out noise and/or vibration monitoring of the construction activity to verify the extent of any adverse effects.
Implement further mitigation and/or contingency measures to avoid significant adverse effects as agreed with the affected party.
In addition to the measures detailed above, where there is an exceedance of the noise and vibration standards set out in Conditions 31, 33 and 34 of the Designation, the Auckland Council Consent Monitoring Officer has the ability to call for an immediate cessation of the work(s) that is giving rise to the exceedance.
8.1
NOISE
If noise monitoring demonstrates non-compliance with the noise limits the following procedures shall be implemented:
Undertake additional noise measurements, as necessary, to determine the extent of the exceedance. Where additional measurements are required they will be taken immediately.
Discuss additional mitigation options with the Project Manager as soon as the extent of the exceedance has been determined. This may include immediately stopping works.
Implement those additional mitigation options.
Undertake noise measurements within 24 hours of the recommended mitigation measures being implemented to confirm that the mitigation has been effective and the noise limits are now being met.
Preparation of a report recording the findings of the survey and detailing additional mitigation or management options. Copies of the report will be provided to Stamford Plaza, AT, the Project Manager, the Communication and Consultation Manager and the Sustainability Manager within 48 hours of the survey.
Page 23
Connectus Project #: 2665 Client: Auckland Transport
8.2
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001186 Revision: 07, Date: 25 May 2016
VIBRATION – BUILDING DAMAGE
If vibration monitoring demonstrates non-compliance with the vibration building damage limits, the construction activity responsible for the exceedance will cease as soon as safe and practicable to do so. A detailed building condition survey will then be undertaken by a suitably qualified engineer at Connectus’ expense. The survey will be carried out as defined in Section 10.4 of the CNV DWP. This building condition survey is in addition to the building condition survey that will be carried out before work begins. If damage has not occurred then that activity can continue provided the measured vibration level is not exceeded further. If minor damage has occurred, such as cosmetic cracks, further mitigation will be applied if practicable. However, the activity can continue provided the measured vibration level is not exceeded further. If moderate or severe damage has occurred and the best practicable option has been implemented, it will be necessary to stop work, if safe to do so, and investigate alternative construction methods. All damage due to construction activities will be repaired within a reasonable timeframe after the construction phase ceases.
8.3
VIBRATION - AMENITY
If vibration monitoring demonstrates non-compliance with the vibration amenity limits the following procedures shall be implemented:
Undertake additional vibration measurements, as necessary, to determine the extent of the exceedance. Where additional measurements are required they will be taken immediately.
Discuss additional mitigation options with the Project Manager as soon as the extent of the exceedance has been determined. This may include immediately stopping works.
Implement those additional mitigation options.
Undertake vibration measurements within 24 hours of the recommended mitigation measures being implemented to confirm that the mitigation has been effective and the vibration limits are now being met.
Preparation of a report recording the findings of the survey and detailing additional mitigation or management options. Copies of the report will be provided to Stamford Plaza, AT, the Project Manager, the Communication and Consultation Manager and the Sustainability Manager within 48 hours of the survey.
9 STAFF Before working on these activities all staff will receive training in accordance with Section 7.2 of the CNV DWP and will read and comply with this SSCNVMP.
Page 24
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001186 Revision: 07, Date: 25 May 2016
APPENDIX A: UTILITIES AND PILING PROGRAMME (AS ISSUED TO STAMFORD PLAZA ON 5TH MAY 2016)
Page 25
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001186 Revision: 07, Date: 25 May 2016
Page 26
Auckland City Rail Link In association with:
ENABLING WORKS CONTRACT 2 SITE SPECIFIC CONSTRUCTION NOISE AND VIBRATION MANAGEMENT PLAN: STAMFORD RESIDENCES Separable Portion 1 – Cut and Cover Works Document Ref: CRL-PAT-ENV-CON-PLN-001185 Revision: 09
Final 3rd June 2016
COMMERCIAL IN CONFIDENCE
This page intentionally left blank.
DOCUMENT INFORMATION Organisation:
Connectus
Document Title:
Site Specific Construction Noise and Vibration Management Plan: Stamford Residences
Fulcrum Document Number:
CRL-PAT-ENV-CON-PLN-001185
Document based on MMS No:
n/a
Client:
Auckland Transport
Project:
CRL Enabling Works: Contract Two
Location:
Auckland CBD
Project No:
2665
REVISION HISTORY Rev
Date
Details st
Draft for Connectus review
Author
Approver
C. Drewery
C Hind
01
29/02/16
1
02
11/03/16
IPR Comments Addressed
C. Drewery
C Hind
03
24/03/16
For Stamford Residences Review
C. Drewery
C Hind
04
31/03/16
For Stamford Residences Review – updated to include initial comments from Stamford Residences
C. Drewery
C Hind
05
14/04/16
For Stamford Residences Review – updated to include further comments from Stamford Residences
C. Drewery
C Hind
06
29/04/16
For Stamford Residences Review – updated to include comments from Stamford Residences noise expert
C. Drewery
C Hind
07
9/05/16
For Stamford Residences Review – updated to include new program for utilities relocation and piling works
C. Drewery
C Hind
08
10/05/16
Final for Issue
C. Drewery
C Hind
09
3/06/16
Final
C. Drewery
C Hind
This document remains the property of Connectus. Its contents are confidential and shall not be reproduced, destroyed or given away without the express, written permission of Connects. The electronic version of this document in MMS Database on designated server(s) is the Master Copy and is a controlled document. Unless specifically noted thereon, other copies of this document are uncontrolled.
This page intentionally left blank
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001185 rd Revision: 09, Date: 3 June 2016
Table of Contents Document information .........................................................................................................................3 Revision History ..................................................................................................................................3 1
Introduction........................................................................................................................7 1.1
Objective
7
1.2
Site plan
7
2
Receivers ..........................................................................................................................8
3
Activities ............................................................................................................................8 3.2
4
Vibration
11
Mitigation ......................................................................................................................... 11 4.1
Noise
11
4.2
Vibration
13
4.3
Habitation
13
4.4
Residual Effects
13
5
Predicted Noise and Vibration Levels ............................................................................... 14 5.1
Noise
14
5.2
vibration
16
6
Communication and Consultation..................................................................................... 16
7
Monitoring ....................................................................................................................... 17
8
Contingency Measures .................................................................................................... 18
9
8.1
Noise
19
8.2
Vibration – Building Damage
19
Staff................................................................................................................................. 19
Page 6
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001185 rd Revision: 09, Date: 3 June 2016
1 INTRODUCTION This is a Site Specific Construction Noise and Vibration Management Plan (SSCNVMP) and forms part of the Construction Noise and Vibration Delivery Work Plan (CNV DWP) for the CRL Contract 2 Enabling Works (the ‘Project’). This SSCNVMP provides specific assessment of construction noise and vibration effects on the Stamford Residences located at 22-26 Albert Street and has been prepared after reviewing the Agreement between Auckland Transport and Stamford Residences dated 19 August 2015. This SSCNVMP should be read in conjunction with the CNV DWP (Document Ref: rd CRL-PAT-ENV-CON-PLN-000903 Revision 6 dated 3 June 2016) as it contains further details of the project, noise criteria, monitoring, general mitigation measures and other information. Where there is inconsistency between the CNV DWP and this SSCNVMP, then the provisions of the SSCNVMP shall prevail. Details of the construction methodology are contained in the Project Construction Environmental Management Plan (CEMP). Acoustic terms are defined in the Acoustic Glossary in the CNV DWP.
1.1
OBJECTIVE
The objective of this SSCNVMP is to detail the best practicable option to avoid, remedy or mitigate adverse effects on Residents1 resulting from construction noise and vibration.
1.2
SITE PLAN
Figure 1 shows the location of the works in relation to the Stamford Residences. Figure 1 Site plan
1
‘Resident’ means an owner or occupier of part of the Property. ‘Property’ means the property at Levels 12-23, including ancillary areas and common areas owned, used or occupied by the Stamford Residences at 22-26 Albert Street, Auckland Central. Page 7
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001185 rd Revision: 09, Date: 3 June 2016
2 RECEIVERS The Stamford Residences occupies the building at 22-26 Albert Street from Level 12 to Level 23. The lower levels of the building are occupied by the Stamford Plaza Hotel. All apartments have mechanical ventilation. The apartments have enclosed balcony areas along the Albert Street faรงade that have openable louvres for ventilation. Table 1 Receiver information
Address
Building use
Stamford Residences 22-26 Albert Street
Residential
Historic / vibration sensitive
Minimum Horizontal Distance to Works, m
Project Noise Criteria dB dB LAeq LAFmax
Project Vibration Criteria, (PPV mm/s)
N
9
75*
5
90*
Project Vibration Criteria (Amenity), (PPV mm/s) 0.3mm/s and 35 dBA (10pm-7am in bedrooms) 1.0 mm/s (7am-10pm in habitable rooms)
* This is the Monday to Saturday 07:00 to 22:00 noise criteria. The majority of works will be carried out during this period. For residential receivers the noise limit is reduced to 65 dB LAeq & 80 dB LAFmax on Sundays and Public Holidays between 07:00 to 22:00 and to 60 dB LAeq & 75 dB LAFmax at all other times.
Designation Condition 38.4 allows for the Project Vibration Standards to be relaxed by a SSCVMP but only for a building, structure or infrastructure that has been assessed by a suitably qualified and experienced structural engineer and where it has been deemed to be capable of withstanding higher vibration levels without sustaining building or structural damage, and where appropriate vibration and building condition monitoring regimes are in place. Based on the building condition surveys and the initial assessments by the structural engineer the building vibration limits could be reduced. However, it is considered prudent to keep the Project Vibration Building Damage Standards to better enable compliance with the Project Vibration Amenity Standards.
3 ACTIVITIES Construction activities which have the potential to give rise to an exceedance of the Project Noise and/ or Vibration Standards (detailed in Section 1 of the CNV DWP) at the Stamford Residences are shown in Table 2 below. Start/end dates and hours of operation are also provided for each area of works. The start and end dates relate to the wider construction works area, it is expected that activities will only generate significant noise and/or vibration in the vicinity of the Stamford Residences for a fraction of the overall activity duration.
Page 8
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001185 rd Revision: 09, Date: 3 June 2016
Table 2 Construction activities
Works Phase
Construction Activity
Area of works
Activity Start Date*
Activity End Date*
Hours
Advanced Utilities Works
Utilities relocation
Between Points A and B:
13 Jun 2016
5 Aug 2016
7am to 7pm Mon - Sat
Vector Electricity across Albert Street at Swanson Street and part of the Combined Service Trench Swanson Street to Wyndham Street Albert Street Piling and Capping Beam
Utilities location and exposure along piling line
Between Points A and B:
Installation of CFA piles
Between Points A and B:
20 Jun 2016
29 Jul 2016
Mon – Sat
Both sides of Albert Street
Both sides of Albert Street
7.30am to 6.00pm
10 non consecutive weeks between 10 Oct 2016 and 04 May 2017
Installation of pile cap Excavation and Spoil Handling
Removal of existing road surface
Swanson St to Wolfe St (Ch370490)
19 May 2017
8 June 2017
7am to 7pm Mon - Sat
and Excavation 1st layer
31 May 2017
28 June 2017
Rock Dowel Installation
Excavation 2nd layer to bottom
29 June 2017
5 Dec 2017
Waterproofing and Tunnel Construction
Waterproofing and tunnel construction
Swanson St to Wolfe St (Ch370490)
1 Dec 2017
5 June 2018
Trench Backfilling
Trench backfilling and reinstatement
Swanson St to Wolfe St (Ch370490)
5 Mar 2018
Shotcrete and Strip Drain Installation and
7am to 7pm Mon – Sat
11 Sep 2018
7am to 7pm Mon - Sat
* The dates shown in Table 2 are dependent on the Stamford Plaza SSCNVMP being finalised and subsequently agreed to by Auckland Council. If the timeframe for this is delayed then the start of construction will be delayed accordingly. Auckland Transport will use best endeavours to provide written notice six months prior to any predicted exceedances of the Project Noise and/or Vibration Standards and otherwise as soon as reasonably practicable. This notice shall include the start and end date of the period for which exceedances are predicted to arise from: Page 9
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001185 rd Revision: 09, Date: 3 June 2016
(i)
Preparatory activities (including road cutting);
(ii)
Piling on the western side of the CRL trench; and
(iii)
Piling on the eastern side of the CRL trench.
Piling, saw cutting and any other activity that produces the same noise level as piling will only be carried out between the hours of 07:30 and 18:00 Monday to Saturday in the area between 20m north of Mills Lane (Point A) and 20m south of Swanson Street (Point B). Those components of the preparatory works between Points A and B that exceed the Project Noise and/or Vibration Standards will be completed over a total of 40 days. Connectus may continue activities that do not exceed the Project Noise and/or Vibration Standards, such as completing pavement reinstatement and cable pulling, beyond the 40 day period. Between Points A and B piling will take no longer than 6 weeks on each side of the road. The piling works on each side of the road will be undertaken in two – three different stages, in order to manage traffic and access into the Stamford site, but the total duration of these different stages will not exceed the specified 6 weeks on each side of the road. 3.1.1
Equipment
Construction equipment used for each of the above activities is shown in Table 3 with sound pressure level at 5m resulting from individual equipment items. These equipment levels are placeholders. All equipment will be measured operating independently and then actual equipment noise levels and model numbers will be recorded and updated within the table. Table 3 Construction Equipment
Construction Activity
Equipment
Utilities relocation, utilities location and exposure
Concrete saw Vacuum Excavation
Installation of CFA piles
Installation of pile cap Removal of existing road surface st
Excavation 1 layer
nd
Excavation 2 to Bottom
Layer
Waterproofing and tunnel construction
Rock fall protection
Soilmec Hydraulic Rotary Rig (est SR80) Excavator (est 15t) Concrete truck Mecbo tracked Concrete Pump Crane (40t) Excavator (est 15t) Concrete saw or breaker Crane (40t) Road planer / milling machine Excavator 20t 6-wheel tipper trucks (10t) Excavator 20t Small excavator (5t – 14t) 6-wheel tipper trucks (10t) Excavator 14t Front end wheel loader Crawler crane with clamshell bucket (80t) long reach excavator 6-wheel tipper trucks (10t) Telehandlers Telescopic Crawler Crane Rough terrain scissor lift Mobile concrete pump or Static pump and boom Crane Delivery trucks Excavator mounted drill rig
Sound pressure level dB LAeq @ 5m 91 84 88 79 83 84 82 79 91 82 88 84 85 84 79 76 79 86 81 81 76 85 77 84 86 86 81 76 92 Page 10
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001185 rd Revision: 09, Date: 3 June 2016
Construction Activity
Equipment
netting
Crane Delivery trucks Angle grinder Excavator-mounted rock breaker Concrete core drill Telehandlers Excavator-mounted drill rig Water bowser Diesel compressor Petrol/diesel generator Crawler crane est 50t Delivery trucks Excavators 5-15t Front end loader Bobcat loader 6-wheel tipper trucks Roller compactors Plate compactors Concrete pump
Pre-drilling
Drilling and rock dowel installation
Trench backfilling
3.2
Sound pressure level dB LAeq @ 5m 81 76 86 90 91 85 92 87 79 71 81 76 79 86 82 76 85 86 84
VIBRATION
Construction activities and equipment which are expected to generate significant vibration levels in the vicinity of Stamford Residences are shown in Table 4 along with start and end dates, and hours of operation. The start and end dates relate to the wider construction works area, and it is expected that activities will only generate significant vibration in the vicinity of the Stamford Residences for a fraction of the overall activity duration. Table 4 Vibration sources
Works Phase
Equipment
Activity Start Date
Albert Street Piling and Capping Beam
Soilmec Hydraulic Rotary Rig (est SR80)
6 Dec 2016 to 16 Dec 2016
7.30am to 6.00pm
28 Mar 2017 to 12 Apr 2017
Mon - Sat
Trench Backfilling
Roller compactors
5 Mar 2018
7am to 7pm
Plate compactors
Activity End Date
11 Sep 2018
Hours
Mon - Sat
4 MITIGATION 4.1
NOISE
Specific effects on this receiver that could result from exceedances of the noise criteria include the annoyance and disturbance of residents. Mitigation is required to meet the noise criteria at the Stamford Residences. In addition to the general noise and vibration control measures outlined in Section 7 of the CNV DWP, the specific noise mitigation measures detailed in Table 5 will be implemented. These mitigation measures represent the Best Practicable Option to avoid, remedy or mitigate adverse effects on the Stamford Residences. Page 11
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001185 rd Revision: 09, Date: 3 June 2016
Table 5 Specific Noise Mitigation Measures
Equipment/process
Noise control measures
Concrete cutting
Use a mobile acoustic enclosure where practicable. Use of a mobile acoustic enclosure may not be practicable when:
Cutting within 300mm of a kerb or canopy structure Saw cuts need to be made around an obstruction that protrudes above surface level, such as a light pole or street sign.
The road saw needs to be manoeuvred around in a tight space that would be obstructed by the acoustic enclosure
When use of a mobile acoustic enclosure is not practicable works will be planned so that saw cutting directly in front of a receiver is completed within a total of two working days. The building owner will be contacted at least one week prior to this occurring to see if the works can be scheduled for a time that least impacts them. Concrete breaking
It is assumed that all concrete can be removed by saw cutting and lifting with an excavator. Concrete breakers will not be used in the vicinity of the Stamford Residences unless something is encountered in the ground that cannot be removed by any other method. In this case the smallest breaker capable of completing the task will be used and where practicable the works will be carried out in a mobile acoustic enclosure.
Vacuum Excavation
Locate the vehicle so the pump is facing away from the closest noise sensitive properties
Piling
The new design has reduced the number of piles within the zone (20m north of Mills Lane to 20m South Of Swanson) on the East side of Albert Street considerably. The original design as presented in the Notice of Requirement hearings used approximately 87 piles. Connectus have been able to reduce this to only 60 piles. The method of piling has also changed from the original design. Piling will now be by Continuous Flight Auger which produces less noise and vibration.
Excavators, bobcats, loaders
Excavators of 15t or less will be used in the vicinity of Stamford Plaza Hotel unless it can be demonstrated by measurement that bigger excavators will meet the noise criteria. Tracks will be greased regularly.
Crane
Straps rather than chains will be used unless a risk assessment deems the use of straps unsafe.
Excavator mounted drilling rig
Localised screening will be used where required. The screens will be positioned to cut line of site between the noisy elements of the drilling rig and the Stamford Residences.
Construction Deck
The original construction methodology presented at the Notice of Requirement hearings showed a single deck structure being built across Albert Street in front of Stamford Residences. It was proposed that all materials for constructing the tunnel came in and out of this point during the excavation, tunnel construction and backfilling phases. The new design has switched to a continuous deck structure, which has reduced the requirement for plant to be located near Stamford Residences by at least 50%.
Construction vehicles, plant and equipment
Tonal alarms will not be used during the movement of construction vehicles, plant and equipment. Broadband alarms will be used instead.
Page 12
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001185 rd Revision: 09, Date: 3 June 2016
Noise barriers/hoardings will be installed around the work site but they will provide no attenuation to the Stamford Residences which begin at Level 12. Little reduction is provided for receivers located at Level 3 and above.
4.2
VIBRATION
In addition to the general noise and vibration control measures outlined in Section 7 of the Project CNV DWP the following specific vibration mitigation measures (Table 6) should be implemented if the initial on site vibration monitoring demonstrates that the building damage vibration limits will be exceeded: Table 6 Specific Vibration Mitigation Measures
Equipment/process
Vibration control measures
Excavator mounted rock breaker
Concrete breakers will not be used unless something is encountered in the ground that cannot be removed by saw cutting. Should breakers be required a hand held jack hammer rather than an excavator mounted breaker will be used when within 10m of the Stamford Residences building.
4.3
HABITATION
If notwithstanding any mitigation measures set out above and additional to the contingency measures set out in Section 8 of this SSCNVMP, the noise and/or vibration effects on the Residents exceeds the levels set out in Table 7 so as to unreasonably interfere with the Residents habitation and/or renders the relevant space uninhabitable, then temporary relocation and/or the payment of the cost of the temporary relocation shall be offered to the Residents concerned.
Table 7 Internal level at which noise and vibration effects may unreasonably interfere with habitation and/or render the relevant space uninhabitable
Noise
Vibration
Daytime (7am to 7pm) – 60 dB LAeq(T)
Daytime (7am to 10pm) – 2mm/s PPV
Evening (7pm to 10pm) - 50 dB LAeq(T)
Night time (10pm to 7am) – 0.6mm/s PPV
Night time (10pm to 7am) – 40 dB LAeq(T) and 45 dB LAFmax
4.4
RESIDUAL EFFECTS
The intention is that after taking into account the mitigation measures set out above, together with other provisions of this SSCNVMP that (unless Section 4.3 applies) the residual effects of the construction are not likely to cause significant disruption to the activities of the Residents.
Page 13
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001185 rd Revision: 09, Date: 3 June 2016
5 PREDICTED NOISE AND VIBRATION LEVELS 5.1
NOISE
The predicted worst case noise levels from each activity received at the most exposed part of the Stamford Residences (level 12) are shown below in Table 8. These levels correspond to the construction equipment being located at its nearest position relative to the receiver and assume that all mitigation detailed in Section 7 of the CNV DWP and Section 4.1 of this SSCNVMP has been implemented. The predicted noise levels take into account whether works are being carried out at ground level or below the ground. Table 8 Predicted noise levels
Construction Activity
Project Noise Standard, dB LAeq
Predicted noise level with all mitigation measures implemented, dB LAeq
Project Noise Standards exceedance, dB
Vector Electricity across Albert Street at Swanson Street
75
82
7*
Utilities location and exposure (inside trench area) Piling
75
82
7*
75
80
5**
Removal of existing road surface Excavation 1st layer
75
70
0
75
69
0
Excavation 2nd Layer to Bottom Drilling – Rock Dowel
75
65
0
75
69
0
Waterproofing and tunnel construction Trench backfilling
75
69
0
75
70
0
*This exceedance is caused by saw cutting and will occur during the 40 day period for preparatory works. **This exceedance is caused by the piling rig and will occur during the 12 week period for piling works.
Noise levels will decrease with distance from the noise source such that noise levels at higher floors and at facades not directly exposed to the noise source will be lower than those shown above. This is illustrated in Figure 2 showing noise levels due to CFA pile installation decreasing with increasing floor level.
Page 14
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001185 rd Revision: 09, Date: 3 June 2016
Figure 2 CFA Piling - facade noise levels
5.1.1
Internal noise levels
Apartment Environment The faรงade of the building is mostly glazed and all apartments are mechanically ventilated. The apartments have enclosed balcony areas along the Albert Street faรงade that have openable louvres for ventilation. An external to internal noise level difference of 35 dB is predicted in all areas except for the enclosed balconies where the level difference is predicted to be 15-20 dB when the louvres are open. Assuming all mitigation and management measures detailed in Section 7 of the CNV DWP and Section 4.1 of this SSCNVMP are implemented, and an external to internal noise level difference of 35 dB is achieved, internal noise levels noise levels in the most exposed apartments on Level 12 may reach 50 dB LAeq when utilities works are being carried out directly in front of the building on the east side of Albert Street. All other activities associated with the Project will be result in noise levels of 45 dB LAeq or below. Balcony Environment When utilities works and piling are immediately outside of the building noise levels in the enclosed balcony areas of the most exposed apartments on Level 12 may reach 65 dB LAeq. The works in this area will be of a limited duration. The most effective way to reduce noise levels further will be to close the louvres. With the louvres closed the noise levels in the enclosed balcony areas of the most exposed apartments on Level 12 may reach 55 - 60 dB LAeq. Faรงade sound insulation improvements are not considered necessary for the Stamford Residences.
Page 15
Connectus Project #: 2665 Client: Auckland Transport
5.2
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001185 rd Revision: 09, Date: 3 June 2016
VIBRATION
Vibration regression curves and emission radii for the vibration sources can be found in Section 5.2 of the CNV DWP. The emission radius is the distance at which vibration levels from an activity/equipment item are expected to exceed the Project Vibration Standards for a particular type of building. For the purposes of assessing vibration, the Stamford Residences building is classed as Residential. We note that the emission radii are based on generic data, conservatively sized equipment and ground conditions. Vibration levels from actual equipment at the site may differ and are likely to be less than assumed for the emission radius. The only equipment predicted to exceed the Project Vibration Standards is the excavator mounted concrete breaker if used within 10m of the building. As discussed previously this equipment will only be used if something is found during the works that cannot be removed by saw cutting. Monitoring will be carried out at the earliest opportunity on site to determine the adjustments for ground conditions and actual equipment items. If the initial vibration monitoring demonstrates that the emission radii are similar to those detailed in Section 5.2 of the CNV DWP the mitigation detailed in Section 4.2 of this SSCNVMP will be implemented. Vibration from construction activities will be continuously measured in the Stamford Residences building to monitor compliance with the Project Vibration Standards, as detailed in Section 7 of this SSCNVMP. Section 8 of this SSCNVMP details the process that will be followed if vibration levels in excess of the Project Vibration Standards are measured.
6 COMMUNICATION AND CONSULTATION Section 9.1 of the CNV DWP details the communication procedures in relation to construction noise and vibration effects. The Communication and Consultation Manager for the Project is Alan HowardSmith, telephone number 021 361158. All communications and complaints should be directed to him in the first instance. Alternatively the project will be contactable 24/7 through the freephone number, 0800 CRL TALK (275 8255). th
Consultation with the Stamford Residences took place on 17 November 2015. The building manager and representatives of the residents were present. Topics that were covered included:
Sequencing of construction activities
Likely equipment and associated noise and vibration levels
Mitigation & management measures that will be implemented
Construction of the building
The residents representatives raised general concerns about noise and vibration impacts although they were pleased that the predicted noise and vibration levels are lower than indicated during the NoR process. They were also pleased that the piling method is CFA rather than driven piles which they had been told were necessary. th
A further meeting was held with representatives of Stamford Residences on `18 February 2016 to discuss monitoring requirements and suitable locations for noise and vibration monitoring.
Page 16
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001185 rd Revision: 09, Date: 3 June 2016
7 MONITORING Section 10 of the CNV DWP provides details of the noise and vibration monitoring procedure that will be implemented for the duration of the Project. It includes details of monitoring that will be conducted in response to complaints. In addition to the noise and vibration monitoring detailed in the CNV DWP, noise and vibration levels from construction activities in the area between 20m north of Mills Lane and 20m south of Swanson Street will be continuously monitored to inform assessment of compliance with the noise and vibration standards set out in Conditions 31, 33 and 34 of the Designation. Automated noise and vibration loggers will be located at positions that will represent the noise and vibration level in the relevant space for the relevant limits. A suitably qualified professional will set up the noise and vibration loggers and will be responsible for reviewing/ assessing the data from the loggers for the duration of the works. The location shown in Figure 3 (Level 12 Lift Lobby) has been selected for noise monitoring as it is on the most exposed faรงade of the building. This location has been agreed with Stamford Residences as the equipment will not impede residents. Alternative monitoring positions may be utilised subject to approval by Stamford Residences. A microphone and ancillary equipment (logger, battery, case) will be set up in the selected location before the commencement of construction activities in the area between 20m north of Mills Lane and 20m south of Swanson Street. Background noise will be measured prior to construction to determine the contribution of extraneous noise sources such as traffic and building services. Noise levels will be measured continuously in 15 minute intervals for the duration of construction works in the area between 20m north of Mills Lane and 20m south of Swanson Street. Audio may be recorded (with the permission of Stamford Residences) along with noise levels to help exclude extraneous sources such as conversation, traffic and building services from the results. Simultaneous measurements will be taken 1m from the building faรงade when work commences to determine the level of sound reduction provided by the faรงade in this area. This level will then be used to adjust internal noise levels for comparison with the external Project Noise Standards. Vibration monitoring will be conducted in a similar location but at ground floor level. The selected location is representative of the western faรงade of the building where PPV is expected to be highest. This location has been agreed with Stamford Residences as the equipment will not impede residents. Alternative monitoring positions may be utilised subject to approval by Stamford Residences. Vibration monitoring will also be carried out at the top floor of the Residences to check compliance with the Project Vibration Standards. This monitoring will be carried out during works that are predicted to generate the highest levels of vibration. The duration and frequency of monitoring on the top floor level will be determined by the initial measurement results.
Page 17
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001185 rd Revision: 09, Date: 3 June 2016
Figure 3 Proposed noise and vibration monitoring location
Proposed noise and vibration monitoring location
Noise and vibration level data will be downloaded periodically to monitor ongoing compliance with the Project Noise Standards. Noise and vibration levels during the advanced utilities works and the preparatory works for piling will be reported to Stamford Residences at least every 48 hours. Outside of that period, noise and vibration levels will be reported to Stamford Residences no less than every 7 days. The reports will detail how the noise and vibration levels compare to the Project Noise and Vibration Standards.
8 CONTINGENCY MEASURES Section 11 of the CNV DWP describes the contingency measures to be implemented in the event that the Project Noise and Vibration standards are exceeded. A summary of those measures is detailed below. Where any construction activity is measured to exceed the Project Construction Noise or Vibration Standards the following process will be applied:
Check that the BPO and all relevant management measures have been implemented (refer Section 7 of the CNVMP and Section 4 of this SSCNVMP)
Communication and Consultation Manager to consult with all affected parties, to understand their particular sensitivities, including times, activities and locations. The Communication and Consultation Manager or their representative shall be available 24/7.
Carry out noise and/or vibration monitoring of the construction activity to verify the extent of any adverse effects.
Implement further mitigation and/or contingency measures to avoid significant adverse effects as agreed with the affected party.
In addition to the measures detailed above, where there is an exceedance of the noise and vibration standards set out in Conditions 31, 33 and 34 of the Designation, the Auckland Council Consent
Page 18
Connectus Project #: 2665 Client: Auckland Transport
Site Specific Construction Noise and Vibration Management Plan Doc. No. CRL-PAT-ENV-CON-PLN-001185 rd Revision: 09, Date: 3 June 2016
Monitoring Officer has the ability to call for an immediate cessation of the work(s) that is giving rise to the exceedance.
8.1
NOISE
If noise monitoring demonstrates non-compliance with the Project Noise Standards the following procedures shall be implemented:
8.2
Undertake additional noise measurements, as necessary, to determine the extent of the exceedance. Where additional measurements are required they will be taken immediately.
Discuss additional mitigation options with the Project Manager as soon as the extent of the exceedance has been determined. This may include immediately stopping works.
Undertake noise measurements within 24 hours of the recommended mitigation measures being implemented to confirm that the mitigation has been effective and the noise limits are now being met.
Preparation of a report recording the findings of the survey and detailing additional mitigation or management options. Copies of the report will be provided to Stamford Residences, AT, the Project Manager, Communication and Consultation Manager and Sustainability Manager within 48 hours of the survey.
VIBRATION – BUILDING DAMAGE
If vibration monitoring demonstrates non-compliance with the vibration building damage limits, the construction activity responsible for the exceedance will cease as soon as safe and practicable to do so. A detailed building condition survey will then be undertaken by a suitably qualified engineer. The survey will be carried out as defined in Section 10.4 of the CNV DWP. This building condition survey is in addition to the building condition survey that will be carried out before work begins. If damage has not occurred then that activity can continue provided the measured vibration level is not exceeded further. If minor damage has occurred, such as cosmetic cracks, further mitigation will be applied if practicable. However, the activity can continue provided the measured vibration level is not exceeded further. If moderate or severe damage has occurred and the best practicable option has been implemented, it will be necessary to stop work, if safe to do so, and investigate alternative construction methods. All damage due to construction activities will be repaired within a reasonable timeframe after the construction phase ceases.
9 STAFF Before working on these activities all staff will receive training in accordance with Section 7.2 of the CNV DWP and will read and comply with this SSCNVMP.