β’ 5:30 β Testing and Commissioning β Simon Mitchell, Community Manager
β’ 5:35 β Station Entrances and Urban Realm β Michael Coup, Construction Manager
β’ 5:50 β Station Design Elements β Simon Lough, Design & Delivery Manager, City Rail Link Limited
β’ 6:00 β Karanga-a-Hape Station precinct integration project β Manoj Nathoo, Auckland Transport
β’ 6:10 β Questions
β’ 6:20 β Endβ



Simon Mitchell, Community Manager
Highlights since first test train - 12 February
- Checks on the catenary/pantograph interface with the overhead line
- Train clearance at speeds between 5 to 40 kph
- Train journeys at up to 70kph this month
- Certifying train drivers in the CRL tunnels.
Upcoming tests
- Multiple trains
- Regular journey through the CRL, stopping at the new stations
- Noise and vibration
- Tunnel Ventilation System.




Michael Coup, Construction Manager







- Roofing complete
- Membrane completion
- Northern laneway construction begun




- Batten ceiling - Chiller units
- TVS flushing - Balustrade installs
- Ticket gate installs





- Platform ceilings - Adit 3 hatches and ceilings - B1 ceilings




- Platform ceilings
- Adit 3 hatches and ceilings
- B1 (first level underground) ceilings - Adit 2 GRC arches
- Escalator fitout

Square Buildings β December
β’ Glass canopy install and cladding underway
β’ Entrance paving complete



Square Buildings β March
β’ Glass canopy install and cladding underway
β’ Entrance paving complete




Beresford Square below ground β March
- Shadowbox install
- Crossbeam cladding and escalator fitout





Michael Coup, Construction Manager
Square β December
- Concrete paving base complete
- Pavers - Approx 40% complete
- Vector works complete



Square β March 2025





- Station connections ongoing (approx 95% complete)
- Pavement on Pitt Street East complete

- Traffic switch completed and handed to Project K
- Vector 22kV works complete



- Cladding panels for pou installed
- Bollard installs
- Paving ongoing


- Entrance planters underway
- Noise shed removal preparation underway





Simon Lough, Design and Delivery Manager, Link Alliance












β’ Western side β laying ducting, installing light pole foundations, preparing base layers of the footpath.
β’ Karangahape Road frontage β laying ducting, installing traffic light foundations, preparing the new cycle lane.


Works include:

β’ Installing a new watermain in front of the Fire Station
β’ Installing new intersection at Poynton Terrace
β’ Ducting between Poynton Terrace and Karangahape Road
β’ Tree pit and footpath works between Poynton Terrace and the Methodist Church.




Our recommendations:
β’ Improve lighting:
o Add better pedestrian orientated lighting
o Reinstate streetlights on the northern side of Canada Street and Lower Mercury Lane
o There is a need for lighting to filter down into the Mercury Theatre driveway from the station building
o Install beacons at the Greys Avenue pedestrian crossing
o Ensure existing lights are well maintained and veranda ceiling lights are left on at night
β’ Install more CCTV cameras to enhance surveillance and deter criminal activity, particularly around the Mercury Lane entrance, behind Beresford Square, and in East Street behind the station
β’ Provide support on activations to increase foot traffic and for more natural surveillance
β’ Provide clear wayfinding signage
β’ Work with Auckland Council to ensure there is a regular maintenance schedule to keep the area clean and free of graffiti.