Skip to main content

C2 designation and resource consent conditions

Page 1

In association with:

ENABLING WORKS CONTRACT 2 Appendix A : Consent and Designation Conditions Separable Portion 1 – Cut and Cover Works

COMMERCIAL IN CONFIDENCE

Appendix A Conditions

Auckland City Rail Link


CRL Designation Conditions 21 October 2015

City Rail Link Notice of Requirement

Page 1


Contents Requiring Authority Designation Conditions – NoR 1, 2, 4, 5 and 6 DEFINITIONS GENERAL CONDITIONS Condition 1 Condition 2 Condition 3 PRE-CONSTRUCTION CONDITIONS Condition 4 – Appointment of Communication and Consultation Manager Condition 5 – Pre-Construction Communication and Consultation Plan Condition 6 – Network Utility Operators Condition 7 – Community Liaison Groups Condition 8 – Mana Whenua Consultation Condition 9 – Network Utility Operator Liaison CONSTRUCTION CONDITIONS Condition 10 – Outline Plan Requirements Condition 11 – Independent Peer Review of CEMP and DWPs Condition 12 – Availability of Outline Plan(s) Condition 13 – Monitoring of Construction Conditions Communication and Consultation Condition 14 – Contact Person Condition 15 – Communication and Consultation Plan Condition 16 – Communications – Notable Noise and Vibration Receivers Condition 17 – Concerns and Complaints Management Condition 18 – “One Network” Consultation Construction Environmental Management Plan (CEMP) and Delivery Work Plans (DWPs) Condition 19 – Preparation, Compliance and Monitoring Condition 20 – CEMP Requirements Condition 21 – CEMP Construction Works Requirements Condition 22 – Review Process for CEMP and DWPs

City Rail Link Notice of Requirement

Page 2


Condition 23 – Update of CEMP and DWPs following review Condition 24 – Network Utilities Transport, Access and Parking Condition 25 – General Transport, Access and Parking Condition 26 – Monitoring of Transport Network Congestion Condition 27 – Transport, Access and Parking: Specific Requirements (Britomart to Mayoral Drive) Condition 28 – Transport, Access and Parking: Specific Requirements (Karangahape Station Area) Condition 29 – Transport, Access and Parking: Specific Requirements (Newton Station Area) Condition 30 – Transport, Access and Parking: Specific Requirements (NAL Area) Noise and Vibration Condition 31 – Project Standards – Construction Noise Condition 32 – Project Standards – Blasting Noise Condition 33 – Project Standards – Construction Vibration Condition 34 – Project Standards – Construction Vibration (Amenity) Condition 35 – Project Standards – MediaWorks Condition 36 – Construction Noise and Vibration DWP Condition 37 – Site Specific Construction Noise Management Plan (SSCNMP) Condition 38 – Site Specific Construction Vibration Management Plan (SSCVMP) Condition 39 – Notable Noise and Vibration Receivers Condition 40 – Construction Noise and Vibration Management Plan – MediaWorks Built Heritage/Archaeology Condition 41 – Historic Character – Built Heritage Condition 42– Historic Character – Archaeology Condition 43 – Heritage Advisory Group and Composition Condition 44 – Heritage Advisory Group Function Condition 45 – Bluestone Wall Management Plan Building Condition Surveys Condition 46 – Process for Building Condition Surveys Urban Design Condition 47 – Urban Design Principles

City Rail Link Notice of Requirement

Page 3


Condition 48 – Mitigation Planting Requirements Condition 49 – Engagement with Mana Whenua and the Mana Whenua Principles Condition 50 – Specific Area Requirements: Britomart to Aotea Station Condition 51 – Specific Area Requirements: Karangahape Station area Condition 52 – Specific Area Requirements: Newton Station area Condition 53 – Specific Area Requirements: North Auckland Line area Condition 54 – Station Plan Requirements Trees and Vegetation Condition 55 – Trees and Vegetation DWP Public Art Condition 56 – Public Art DWP Contamination Condition 57 – Contamination DWP Condition 58 – Contamination Validation Report at Completion of Construction Air Quality Condition 59 – Air Quality DWP Social Impact and Business Disruption Condition 60 – Property Management Strategy Condition 61 – Social Impact and Business Disruption DWP Specific Design Requirements Condition 62 – Specific Design Requirements relating to 152 Vincent Street OPERATIONAL CONDITIONS Condition 63 – Operational Rail Vibration Condition 64 – Operational Noise – Mechanical Ventilation Plant Condition 65 – Operational Noise and Vibration Management Plan (ONVMP) Condition 66 – Operational Noise and Vibration Management – Mediaworks ADVICE NOTES APPENDIX ONE – Buildings for Consideration as to Building Condition Surveys APPENDIX TWO – Heritage Buildings for Consideration as to Building Condition Surveys

City Rail Link Notice of Requirement

Page 4


Requiring Authority Designation Conditions – NoR 3 Condition 1 Condition 2 Condition 3 Condition 4 Condition 5 ADVICE NOTES

City Rail Link Notice of Requirement

Page 5


Requiring Authority Designation Conditions – NoR 1, 2, 4, 5 and 6

Condition Number

Condition

NoR Applies to

DEFINITIONS 1 2 4 5

Consult Consulting Consultation

The process of providing information about the construction works, and receiving for consideration, information from stakeholders, directly affected and affected in proximity parties, regarding those effects and proposals for the management and mitigation of them.

6 1 4 5

Fully operational traffic lane

May include a traffic lane that is subject to a reduced speed limit, or one which may have a temporary reduction in the lane width, due to construction activity.

Two way access

Access into and out from a site or a road. This access may include restrictions (eg. left in, left out) where these are specified within the relevant conditions.

6 1 4 5 6

1 2 4 5

Receivers that undertake activities within spaces that rely on a particularly low noise and vibration environment. For these designations these spaces are defined as: Notable Noise and Vibration Receivers

6

Public Performance Theatres;

Recording Studios, both sound and television (including Mediaworks, except the specific spaces addressed by Condition 35);

In relation to sensitive equipment - Medical Facilities and Scientific Laboratories;

In relation to the requirement to record witness statements - The Auckland District Court in Albert Street

Receivers that may be disturbed during rest, concentration, communication or prayer. For these designations these include (but are not limited to): 1 2 4 5

Sensitive Noise and Vibration Receivers

6

1 2 4

Site Specific Construction Noise and

Dwellings

Offices

Schools, including Child Care Centres and tertiary facilities

Libraries

Hospitals

Rest Homes

Marae and other Cultural Centres

Churches

Hotels or other accommodation facilities

These include site specific construction noise management plans (SSCNMP), site specific construction vibration plans (SSCVMP), or a combination of both noise and vibration in one plan (SSCNVMP) to

City Rail Link Notice of Requirement

Page 6


Condition Number

Condition

NoR Applies to

5 6

Vibration Management Plans

address the effects from the construction activity on notable or sensitive receivers.

1 2 4 5

Best practicable option

Has the meaning under the Resource Management Act 1991 and, for the purpose of these conditions, comprises the best practicable option for minimising the effects of any construction activity (including effects on the transport network or heritage values) on the receiver.

Historic Character

This includes heritage buildings, sites and places identified in the New Zealand Historic Places Trust register or in the Auckland Council District Plan (Isthmus or Central Area Sections) or as specifically identified in conditions.

6 1 2 4 5 6

Mana whenua for the purpose of this designation are considered to be the following (in no particular order), who at the time of Notice of Requirement expressed a desire to be involved in the City Rail Link Project: 1 2 4

Mana Whenua

5 6

1 2 4

Material change

5 6

4 5 6

Ngati Maru

Ngati Paoa

Ngai Tai ki Tamaki

Ngati Te Ata

Ngati Whatua o Orakei

Te Akitai

Te Kawerau o maki

Ngati Tamaoho

Material change will include amendment to any base information informing the CEMP or other Plan or any process, procedure or method of the CEMP or other Plan which has the potential to materially increase adverse effects on a particular receiver. For clarity, changes to personnel and contact schedules do not constitute a material change. Delivery Work Plans will contain specific objectives and methods for avoiding, remedying or mitigating effects and address the following topics: (a) Transport, Access and Parking; (b) Construction noise and vibration;

1 2

Delivery Work Plans

(c)

Historic Character (including Archaeology);

(d) (e)

Urban Design (including landscape and station plans); Trees and vegetation;

(f) (g)

Social Impact and Business Disruption; Air quality;

(h)

Public Art; and

City Rail Link Notice of Requirement

Page 7


Condition Number

Condition

NoR Applies to

(i)

Contamination.

1 2 4 5 6 6

Peak Particle Velocity

The maximum component peak vibration level (in mm/s) measured in any of three orthogonal axes (vertical, transverse, longitudinal).

MediaWorks

MediaWorks means any television, radio and/or interactive media facilities which broadcast from the MediaWorks site (including any successor which conducts the same activities). MediaWorks site means the properties at 2-3 Flower Street and 44-52 New North Road included within the following:

6

MediaWorks site

6

MediaWorks building

6

Studio 1

Lot 1 DP 84213

NA40B/1323

Lot 2 DP 49561

NA2063/54

Lot 4 Section 3 Deeds Plan 45(blue)

NA557/190

Part Lot 5 Section 3 Deeds Plan 45 Blue

NA557/144

Lot 1 DP 60771

NA15C/727

MediaWorks building means the building located at 3 Flower Street, directly adjacent to Nikau Street. Studio 1 means the main broadcasting studio at the MediaWorks building as shown on Diagram 1.

ABBREVIATIONS CEMP

Construction Environmental Management Plan

DWP

Delivery Work Plan

NoR

Notice of Requirement

ONVMP

Operational Noise and Vibration Management Plan

PPV

Peak Particle Velocity

SSCNVMP

Site Specific Noise and Vibration Management Plan

GENERAL CONDITIONS 1 2 1

4 5 6

1.1. Except as modified by the conditions below and subject to final detailed design, the City Rail Link Project shall be undertaken in general accordance with the information provided by the Requiring Authority in the Notice of Requirement dated 23 August 2012 and supporting documents (as updated by information provided by the Requiring Authority up until the close of the Hearing and during the course of Environment Court proceedings) being:

City Rail Link Notice of Requirement

Page 8


Condition Number

Condition

NoR Applies to

(a) Assessment of Environmental Effects report (contained in Volume 2 of the Notice of Requirement suite of documents, dated 15 August 2012 Rev B); (b) Supporting environmental assessment reports (contained in Volume 3 of the Notice of Requirement suite of documents, dated August 2012); (c) The Concept Design Report (contained in Volume 2 of the Notice of Requirement suite of documents, dated 13 August 2012 Rev 3); (d) Plan sets: (i) Land requirement plans (contained in Volume 1 of the Notice of Requirement suite of documents, dated 15 August 2012 and GIS-4214293-100-10 Rev 5 as amended for 32 Normanby Road, dated 14 September 2015); (ii) Plans contained in the Concept Design Report Appendices (contained in Volume 3 of the Notice of Requirement suite of documents, dated 13 August 2012 Rev 3).; (iii) Plan CIV-000-DRG-0001 attached at Appendix 1 to these Conditions. (e) Information provided in response to the Section 92 requests and/or in advance of the Council’s section 42A report, including the following: (i) “City Rail Link Notice of Requirement: Social Impact Assessment” prepared by Beca Carter Hollings & Ferner Ltd (Beca), dated 19 April 2011 (approved for release 19 April 2013); (ii) “City Rail Link – Supplementary Report: Traffic Modelling of Alternative Construction Scenarios” prepared by Flow Transportation Specialists Ltd, dated 22 May 2013. (f) Evidence (including supplementary evidence) provided prior to and at the Council hearing, including but not limited to: (i) Statement of Evidence by Ian Clark (Transport) dated 2 July 2013; (ii) “Drawing 0220, Revision B” dated 20 August 2013, being part of the City Rail Link Project: Mt Eden Worksite set by Aurecon, submitted as part of the Second Supplementary Statement of Evidence of William (Bill) Russell Newns for Auckland Transport; (iii) “City Rail Link Notice of Requirement: Outline Plan Process and Environmental Management Plan System (Indicative)” prepared by Beca Carter Hollings & Ferner Ltd, dated 27 September 2013; (iv) “City Rail Link: Indicative Communication and Consultation Plan” prepared by Auckland Transport, dated September 2013; “Outline Social Impact and Business Disruption Delivery Work Plan” submitted as Attachment A to the Statement of Evidence of Amelia Joan Linzey (Beca Carter Hollings & Ferner Ltd), dated 26 September 2013. (g) All material and evidence (including rebuttal evidence) provided by the Requiring Authority in the Environment Court proceedings (ENV-2014-AKL-000057). 1.2 Where there is inconsistency between: (a) The documents listed above and these conditions, these conditions shall prevail; (b) The information and plans lodged with the requirements and presented at the Council Hearing and during the course of Environment Court proceedings, the most recent information and plans shall prevail; (c) The indicative management plans and evidence presented at the Council Hearing and the management plans (DWPs, CEMP, etc) required by the conditions of these designations and submitted through the Outline Plan, the requirements of the management plans shall prevail.

City Rail Link Notice of Requirement

Page 9


Condition Number

1 2 2

Condition

NoR Applies to

4 5

2.1 In accordance with section 184(1) of the Resource Management Act 1991 (the RMA), these designations shall lapse if not given effect to within 15 10 years from the date on which they are confirmed.

6 3.1 As soon as reasonably practicable, and no later than the point at which any part or parts of the City Rail Link become operational, the Requiring Authority shall: 1 2 3

4 5 6

(a) Review the area and volume of land designated for the City Rail Link; (b) Identify any areas of designated land that are either no longer necessary for construction of the City Rail Link (if the City Rail Link has been constructed in part), or no longer necessary for the on-going operation and/or maintenance of the City Rail Link or for on-going mitigation measures; and (c) Give notice in accordance with Section 182 of the RMA for the removal of those parts of the designation identified in (b) above.

PRE-CONSTRUCTION CONDITIONS Appointment of Communication and Consultation Manager

4

1 2 4 5 6

4.1 Within three months of the confirmation of the designation the Requiring Authority shall appoint a Communication and Consultation Manager to implement the Pre-construction Communication and Consultation Plan (Condition 5). The Communication and Consultation Manager shall be the main and readily accessible point of contact for persons affected by or interested in the City Rail Link Project until the commencement of the construction phase of the Project, or the contact person under Condition 14 is appointed. 4.2 The Communication and Consultation Manager’s contact details (or, if appointed under Condition 14, that contact persons details) shall be listed in the Pre-construction Communication and Consultation Plan and listed on the Requiring Authority website, the City Rail Link Website, and the Auckland Council website. Pre-Construction Communication and Consultation Plan

5

1 2 4 5 6

5.1 The objective of the Pre-construction Communication and Consultation Plan is to set out a framework to ensure appropriate communication and consultation is undertaken with the community, stakeholders, affected parties and affected in proximity parties prior to the commencement of construction of the City Rail Link. 5.2 The Requiring Authority shall prepare a Pre-Construction Communication and Consultation Plan. This Plan shall be submitted to Auckland Councils Major Infrastructure Projects Team Manager, within 2 months of the Designation being confirmed, for confirmation that the Plan has been prepared in accordance with this condition. 5.3 The Plan shall be implemented and complied with within 3 months from the confirmation of the designations until the commencement of the construction of the City Rail Link. 5.4 This Plan shall set out recommendations and requirements (as applicable) that should be adopted by and/or inform the development of the CEMP and DWPs. 5.5 The Pre-construction Communication and Consultation Plan shall set out how the Requiring Authority will: (a) Inform the community of Project progress and likely commencement of construction works and programme; (b) Engage with the community in order to foster good relationships and to provide

City Rail Link Notice of Requirement

Page 10


Condition Number

Condition

NoR Applies to

opportunities for learning about the Project; (c) Obtain (and specify reasonable timeframes for) feedback and input from Stakeholders, directly affected and affected in proximity parties regarding the development of the CEMP and DWPs; (d) Respond to queries and complaints. Information shall include but not be limited to: (i) Who is responsible for responding; (ii) How responses will be provided; (iii) The timeframes that the responses will be provided within. (e) Where feedback (in accordance with this condition) is provided, the Pre-construction Communication and Consultation Plan shall articulate how that feedback has informed the development of the CEMP and DWPs and where it has not, reasons why it hasn’t; (f) Provide updates on the property acquisition process as well as the management strategy for properties acquired by the Requiring Authority for the construction of the City Rail Link. 5.6 The Pre-Construction Communication and Consultation Plan shall be prepared in consultation with Stakeholders, directly affected parties and affected in proximity parties including, but not limited to: (a) All property owners and occupiers (including, subject to Condition 61.5, sub lessees) identified within the designation footprint; (b) All property owners and occupiers adjacent to construction sites (Britomart and Albert Street (NoR 1), Karangahape Road (NoR 4), Newton Station (NoR 5), and the main construction site including grade separation works at Normanby Road and Porters Ave (NoR 6)); (c) New Zealand Historic Places Trust (NZHPT); (d) Department of Corrections; (e) Ministry of Justice; (f) MediaWorks; (g) Network Utility Operators; (h) Bear Park Early Childhood Centre; (i) Body Corporate 164980 & Tenham Investments Limited (j) Community Liaison Group(s) (refer Condition 7); 5.7 The Pre-construction Communication and Consultation Plan shall, as a minimum, include: (a) A communications framework that details the Requiring Authority’s communication strategies, the accountabilities, frequency of communications and consultation, the range of communication and consultation tools to be used (including any modern and relevant communication methods, newsletters or similar, advertising etc.), and any other relevant communication matters; (b) Details of the Communication and Consultation Manager for the pre-construction period (Condition 4 of this designation) including their contact details (phone, email and postal address); (c) The methods for identifying, communicating and consulting with stakeholders, directly affected parties and affected in proximity parties and other interested parties. Such methods shall include but not be limited to: (i) Newsletters; (ii) Newspaper advertising;

City Rail Link Notice of Requirement

Page 11


Condition Number

Condition

NoR Applies to

(iii) Notification and targeted consultation with stakeholders, affected parties and affected in proximity parties; and (iv) The use of the project website for public information. (d) The methods for identifying, communicating and consulting with the owners of 1 Queen Street (HSBC House) and 21 Queen Street (Zurich House) regarding the development of the City Rail Link design and construction methodology between Britomart Transport Centre and Customs Street (through the Downtown Shopping Centre site). (e) The methods for communicating and consulting with mana whenua for the implementation of mana whenua principles for the project (refer to condition 8 and 48); (f) The methods for communicating and consulting with the Community Liaison Group(s); (g) How communication and consultation activity will be recorded; and (h) Methods for recording reasonably foreseeable future planned network utility works so that these can be considered and incorporated, where appropriate, into the City Rail Link design. 5.8 The Pre-construction Communication and Consultation Plan will be publicly available once finalised and for the duration of construction. Network Utility Operators 6.1 Under s 176(1)(b) of the Resource Management Act 1991 (RMA) no person may do anything in relation to the designated land that would prevent or hinder the City Rail Link, without the prior written consent of the Requiring Authority.

1 2 6

4 5 6

6.2 In the period before construction begins on the City Rail Link (or a section thereof), the following activities undertaken by Network Utility Operators will not prevent or hinder the City Rail Link, and can be undertaken without seeking the Requiring Authority’s written approval under section 176(1)(b) of the RMA: (a) Maintenance and urgent repair works of existing Network Utilities; (b) Minor renewal works to existing Network Utilities necessary for the on-going provision or security of supply of Network Utility Operations; (c) Minor works such as new property service connections; (d) Upgrades to existing Network Utilities within the same or similar location with the same or similar effects on the City Rail Link designation. 6.3 For the avoidance of doubt, in this condition an “existing Network Utility” includes infrastructure operated by a Network Utility Operator which was: (a) In place at the time the notice of requirement for the City Rail Link was served on Auckland Council (23 August 2012); or (b) Undertaken in accordance with this condition or the section 176(1)(b) RMA process. Community Liaison Groups

7

1 2 4 5 6

7.1 Within three months of the confirmation of the designations the Requiring Authority shall, in consultation with the Auckland Council, establish at least one Community Liaison Group in each of the following key construction areas: (a) Britomart and Albert Street (NoR 1) (b) Karangahape Road (NoR 4) (c) Newton Station (NoR 5) (d) Main Construction site (NoR 6)

City Rail Link Notice of Requirement

Page 12


Condition Number

Condition

NoR Applies to

7.2 The number of Groups shall be confirmed with the Auckland Council. 7.3 The membership of the Community Liaison Group(s) shall include representative(s) of the Requiring Authority and be open to all directly affected and affected in proximity parties to the Project including, but not limited to the following: (a) Representative(s) for and/or directly affected and affected in proximity property owners and occupiers; (b) CBD Residents Advisory Group; (c) The Karangahape Road Business Association; (d) Eden Terrace Business Association; (e) Heart of the City; (f) Roman Catholic Diocese of Auckland; (g) St Patrick’s Cathedral; and (h) St Benedict’s Parish. 7.4 In addition to the requirements in Condition 5, the purpose of the Groups shall be to: (a) Provide a means for receiving regular updates on Project progress; (b) Monitor the effects of constructing the Project on the community by providing a regular forum through which information about the Project can be provided to the community. (c) Enable opportunities for concerns and issues to be reported to and responded by the Requiring Authority. (d) Provide feedback on the development of the CEMP and DWPS. (e) Proposed potential joint initiatives to the Requiring Authority for the Property Management Strategy regarding the interim use of properties including vacant land acquired for the construction of the City Rail Link. 7.5 The Requiring Authority will consult with the Groups in respect of the development of the CEMP and DWPs. 7.6 The Requiring Authority will appoint one or more persons appropriately qualified in community consultation as the Community Consultation Advisor(s) to: (a) Provide administrative assistance to the Groups; (b) Ensure the Groups are working effectively (including the development of a Code of Conduct) and appropriate procedures for each Group; and (c) Act as a community consultation advisor to the Group. 7.7 The Requiring Authority will use its best endeavours to ensure that the Groups meet at least annually until the commencement of construction and then at least once every three months or as otherwise required once construction commences. 7.8 Once construction has commenced the Requiring Authority will provide an update at least every three months (or as otherwise agreed) to the Groups on compliance with the designation conditions and the CEMP and DWP and any material changes to these plans. 7.9 The Requiring Authority shall provide reasonable administrative support for the Groups including organising meetings at a local venue, inviting all members of the Groups, as well as the taking and dissemination of meeting minutes. 7.10The Groups shall continue for the duration of the construction phase of the Project and for six months following completion of the Project. 8

1 2

Mana Whenua Consultation 8.1 Within three months of the confirmation of the designations the Requiring Authority shall establish a kaitiaki or mana whenua forum to provide for an on-going role in the design

City Rail Link Notice of Requirement

Page 13


Condition Number

Condition

NoR Applies to

4 5 6

and construction of the CRL Project. 8.2 The frequency at which the forum meets shall be agreed between the Requiring Authority and mana whenua. 8.3 The role of the mana whenua forum may include the following: (a) Developing practical measures to give effect to the principles in the Urban Design DWP (refer to Condition 49); (b) Input into, where practicable, the design of the stations (refer to Condition 54); (c) Input into the preparation of the CEMP and DWPs; (d) Working collaboratively with the Requiring Authority around built heritage and archaeological matters; (e) Undertaking kaitiakitanga responsibilities associated with the City Rail Link Project, including monitoring, assisting with discovery procedures, and providing mÄ tauranga MÄ ori input in the relevant stages of the Project; and (f) Providing a forum for consultation with mana whenua regarding the names for the City Rail Link stations, noting that there may be formal statutory processes outside the project (such as the New Zealand Geographic Board) which may be involved in any decision making on station names. 8.4 The mana whenua forum may provide written advice to the Requiring Authority in relation to any of the above matters. The Requiring Authority must consider this advice and the means by which any suggestions may be incorporated in the City Rail Link project. Network Utility Operator Liaison 9.1 The Requiring Authority and its contractor shall: (a) Work collaboratively with Network Utility Operators during the development of the further design for the City Rail Link to provide for the ongoing operation and access to network Utility operations;

1 2 9

4 5 6

(b) Undertake communication and consultation with Network Utility Operators as soon as reasonably practicable, and at least once prior to construction timing being confirmed and construction methodology, and duration being known; and (c) Work collaboratively with Network Utility Operators during the preparation and implementation of the CEMP (Condition 24) and DWPs in relation to management of adverse effects on Network Utility Operations. 9.2 A summary of the communication and consultation undertaken between the Requiring Authority and Network Utility Operators prior to construction commencing shall be provided as part of the Outline Plan. 9.3 The Requiring Authority shall undertake on-going communication and consultation with Network Utility operators throughout the duration of construction, including in relation to changes envisaged by Conditions 22 and 23 affecting Network Utility Operations to ascertain whether or not any changes or updates to the CEMP Network Utilities section are required to address unforeseen effects.

CONSTRUCTION CONDITIONS

10

1

Outline Plan Requirements

2

10.1The Requiring Authority shall submit an Outline Plan to the Auckland Council for the construction of the City Rail Link in accordance with section 176A of the RMA. The Outline Plan shall include: (a) The Communication and Consultation Plan (Condition 15);

4 5

City Rail Link Notice of Requirement

Page 14


Condition Number

Condition

NoR Applies to

6

(b) The Construction Environmental Management Plan (CEMP); (c) Delivery Work Plans (DWPs); (d) Site Specific Construction Noise/Vibration Management Plans (SSCNVMPs) and Notable Receiver Management Plans; and (e) Any other information required by the conditions of this designation associated with the construction of the City Rail Link. 10.2The plans listed in Condition 10.1 above must clearly document the comments and inputs received by the Requiring Authority during its consultation with stakeholders, affected parties and affected in proximity parties, and any recommendations received as part of the Independent Peer Review Panel process (where applicable), along with a clear explanation of where any affected party comments or peer review recommendations have not been incorporated, and the reasons why not. 10.3The Requiring Authority may choose to give effect to the designation conditions associated with the construction of the City Rail Link: (a) Either at the same time or in parts; (b) By submitting one or more: (i) Communication and Consultation Plans; (ii) CEMP; (iii) DWPs; and (iv) SSCNVMPs, SSCNMPs and SSCVMPs 10.4These plans should clearly show how the part integrates with adjacent City Rail Link construction works and interrelated activities. This particularly applies where the Urban Design DWP is submitted as a number of plans. 10.5Early engagement will be undertaken with Auckland Council in relation to preparation and submission of the Outline Plan to establish a programme for the Outline Plan process to ensure achievable timeframes for both parties. 10.6All works shall be carried out in accordance with the Outline Plan(s) required by this condition. Independent Peer Review of CEMP and DWPs

1 2 11

4 5 6

11.1Prior to submitting the CEMP, DWPs, SSCNMPs and SSCVMPs (other than those prepared in accordance with Condition 39) to Auckland Council for the construction of the City Rail Link, the Requiring Authority shall engage suitably qualified independent specialists agreed to by Auckland Council to form an Independent Peer Review Panel. The purpose of the Independent Peer Review Panel is to undertake a peer review of the CEMP, DWPs, SSCNMPs and SSCVMPs (other than those prepared in accordance with Condition 39), and provide recommendations on whether changes are required to those plans in order to meet the objective and other requirements of these conditions. 11.2The CEMP, DWPs, SSCNMPs and SSCVMPs (other than those prepared in accordance with Condition 39) must clearly document the comments and inputs received by the Requiring Authority during its consultation with stakeholders, affected parties and affected in proximity parties, along with a clear explanation of where any comments have not been incorporated, and the reasons why not. This information must be included in the CEMP, DWPs, SSCNMPs and SSCVMPs (other than those prepared in accordance with Condition 39) provided to both the independent peer reviewer and Auckland Council as part of this condition. 11.3The CEMP, DWPs, SSCNMPs and SSCVMPs (other than those prepared in accordance with Condition 39) submitted to Auckland Council shall demonstrate how the recommendations from the independent peer reviewers have been incorporated, and,

City Rail Link Notice of Requirement

Page 15


Condition Number

Condition

NoR Applies to

where they have not, the reasons why not. 11.4In reviewing an Outline Plan submitted in accordance with these designation conditions, Auckland Council shall take into consideration the independent specialist peer review undertaken in accordance with this condition and any additional information provided to Auckland Council by affected parties. Availability of Outline Plan(s) 1 2 12

4 5 6

1 2 13

4 5 6

12.1For the duration of construction the following plans and any material changes to these plans shall be made available for public viewing on the Project web site: (a) CEMP; (b) DWPs (including SSCNVMPs, SSCNMPs and SSCVMPs); and (c) Communication and Consultation Plan. 12.2A copy of these Plans will also be held and made available for viewing at each construction site. Monitoring of Construction Conditions 13.1The Requiring Authority, its contractor team, and the Auckland Council Consent Monitoring officer(s) shall establish and implement a collaborative working process for dealing with day to day construction processes, including monitoring compliance with the designation conditions and with the CEMP and DWPs (including SSCNVMPs, SSCNMPs and SSCVMPs) and any material changes to these plans associated with construction of the City Rail Link. 13.2This collaborative working process shall: (a) Operate for the duration of the construction works and for 6 months following completion of construction works where monitoring of designation conditions is still required, unless a different timeframe is mutually agreed between the Requiring Authority and the Auckland Council; (b) Have a “key contact” person representing the Requiring Authority and a “key contact” person representing the contractor team to work with the Auckland Council Consent Monitoring officer(s); (c) The “key contacts” shall be identified in the CEMP and shall meet at least monthly unless a different timeframe is agreed with the Auckland Council Consent Monitoring officer(s). The purpose of the meeting is to report on compliance with the designation conditions and with the CEMP, DWPs and material changes to these plans and on any matters of non-compliance and how they have been addressed; (d) Once construction has commenced, the Requiring Authority and / or the contractor shall provide an update to the Community Liaison Groups (Condition 7 of this designation) at least once every 3 months, or if in accordance with Condition 7 these groups meet more regularly, at least once every two months. 13.3The purpose and function of the collaborative working process is to: (a) Assist as necessary the Auckland Council Consent Monitoring officer(s) to confirm that: (i) The works authorised under these designations are being carried out in compliance with the designation conditions, the CEMP, DWPs (including SSCNVMPs, SSCNMPs and SSCVMPs) and any material changes to these plans; (ii) The Requiring Authority and its contractor are undertaking all monitoring and the recording of monitoring results in compliance with the requirements of the CEMP and DWPs (including SSCNVMPs, SSCNMPs and SSCVMPs) and any material changes to these plans;

City Rail Link Notice of Requirement

Page 16


Condition Number

Condition

NoR Applies to

(b) Subsequent to a confirmed Outline Plan, provide a mechanism through which any changes to the design, CEMP or DWPs, which are not material changes requiring approval under Condition 10 triggering the requirement for a new Outline Plan, can be required, reviewed and confirmed; (c) Advise where changes to construction works following a confirmed Outline Plan require a new CEMP or DWP (including SSCNVMPs, SSCNMPs and SSCVMPs); (d) Review and identify any concerns or complaints received from, or related to, the construction works monthly (unless a different timeframe is mutually agreed with the Auckland Council Consent Monitoring officer) and adequacy of the measures adopted to respond to these. Communication and Consultation

14

1 2 4 5 6

Contact Person 14.1The Requiring Authority shall make a contact person available 24 hours seven days a week for the duration of construction for public enquiries on the construction works.

Communication and Consultation Plan 15.1The objective of the Communication and Consultation Plan is to set out a framework to ensure appropriate communication and consultation is undertaken with the community, stakeholders, affected parties and affected in proximity parties during the construction of the City Rail Link. 15.2The Requiring Authority shall prepare a Communication and Consultation Plan which shall be implemented and complied with for the duration of the construction of the City Rail Link. 15.3The Communication and Consultation Plan shall set out how the Requiring Authority will: (a) Inform the community of construction progress and future construction activities and constraints that could affect them; (b) Provide early information on key Project milestones;

15

1 2 4 5 6

(c) Obtain and specify a reasonable timeframe (being not less than 10 working days), for feedback and inputs from directly affected and affected in proximity parties regarding the development (as part of the review process provided by Condition 22) and implementation of the CEMP or DWPs (including SSCNVMPs, SSNMPs and SSCVMPs); and (d) Respond to queries and complaints including but not limited to: (i) Who is responsible for responding; (ii) How responses will be provided; (iii) The timeframes that responses will be provided within. 15.4The Communication and Consultation Plan shall as a minimum include: (a) A communications framework that details the Requiring Authority’s communication strategies, the accountabilities, frequency of communications and consultation, the range of communication and consultation tools to be used (including any modern and relevant communication methods, newsletters or similar, advertising etc), and any other relevant communication matters; (b) The Communication and Consultation Manager for the Project including their contact details (phone, email and postal address); (c) The methods for identifying, communicating and consulting with persons affected by

City Rail Link Notice of Requirement

Page 17


Condition Number

Condition

NoR Applies to

the project including but not limited to: (i) All property owners and occupiers within the designation footprint (ii) All property owners and occupiers adjacent to construction sites (Britomart and Albert Street (NoR 1), Karangahape Road (NoR 4), Newton Station (NoR 5), Main Construction site and the works at Normanby Road and Porters Ave (NoR 6)) (iii) New Zealand Historic Places Trust (NZHPT) (iv) Department of Corrections (including the entity contracted by Department of Corrections to administer and run the Mt Eden Corrections facility at 1 Lauder Road) (v) Ministry of Justice (including but not limited to) confirming the details of the contact person required under Condition 14 of this designation, and to provide appropriate details (including but not restricted to timing, duration, scale, noise effects, vibration effects, access restrictions, and disruption to utilities) in respect to any works impacting the operation of the Auckland District Court at 65-71 Albert Street, Auckland. Communication and consultation of such details should be provided to the Ministry of Justice Auckland Property Programme Manager at least 9 months prior to the commencement of such works. (vi) Media Works (vii) Community Liaison Group(s) (refer Condition 7); (viii) Bear Park Early Childhood Centre; (ix) Body Corporate 164980 and Tenham Investments Ltd; (x) Network Utility Operators, including the process: 

To be implemented to capture and trigger where communication and consultation is required in relation to any material changes affecting the Network Utilities;

For the Requiring Authority to give approval (where appropriate) to Network Utility Operators as required by section 176(1)(b) of the RMA during the construction period;

For obtaining any supplementary authorisations (including but not limited to resource consents (including those required under a National Environmental Standard) and easements);

For inspection and final approval of works by Network Utility Operators; and

For implementing conditions 9, 22, 23, and 24 of this designation in so far as they affect Network Utility Operations.

(d) How stakeholders and persons affected by the project will be notified of the commencement of construction activities and works, the expected duration of the activities and works, and who to contact for any queries, concerns and complaints; (e) How stakeholders and persons affected by the project will be consulted in the development and review of the CEMP and DWPs (including SSCNVMPs, SSCNMPs and SSCVMPs), including specifying reasonable timeframes for feedback; (f) Methods for communicating in advance temporary traffic management measures and permanent changes to road networks and layouts to directly affected and in proximity parties, bus (public and private) operators, taxi operators, bus users, and the general public; (g) Methods for communicating in advance to surrounding communities (including sensitive noise and vibration receivers) which must be notified at least 24 hours in advance where construction activities are predicted to:

City Rail Link Notice of Requirement

Page 18


Condition Number

NoR Applies to

Condition

(i) Exceed the noise limits (refer Condition 31); or (ii) Exceed a vibration limit (refer Conditions 33 and 34); or (iii) Be within 200m of a blast site (refer Condition 32). Further provisions for Notable Noise and Vibration Receivers are contained in Condition 16. (h) Methods for communicating in advance proposed hours of construction activities outside of normal working hours and on weekends and public holidays, to surrounding communities, and methods to record and deal with concerns raised about such hours; (i) Methods for communicating and consulting with mana whenua for the duration of construction and implementation of mana whenua principles for the project (refer to Conditions 8 and 49); (j) Methods for communicating and consulting with the Auckland Council Parks Department regarding works to be undertaken to any trees on public land (streets, squares, etc.) located within the City Rail Link surface designation footprint, including how trees not being removed, or in close proximity to the surface designation footprint where works are occurring, will be protected; (k) Methods for communicating and consulting in advance of construction works with emergency services (Police, Fire, Ambulance) on the location, timing and duration of construction works, and particularly in relation to temporary road lane reductions and/or closures and the alternative routes or detours to be used, with specific detail around the management of the Fire and Ambulance from their central stations on Pitt Street; (l) A list of Stakeholders, directly affected and affected in proximity parties to the construction works who will be communicated with; (m) How communication and consultation activity relating to construction activities and monitoring requirements will be recorded; and (n) Methods for communicating and consulting with the Department of Corrections (including the entity contracted by Department of Corrections to administer and run the Mt Eden Corrections facility at 1 Lauder Road), to confirm the details of the contact person required under Condition 14 of this designation, and in respect of any works impacting on access or works in proximity to the Mt Eden Corrections Facility and the Boston Road Community Corrections site; including temporary traffic management measures and permanent changes to road networks and layouts which may impact on access to and from the Facility and the motorway network. 15.5The Communication and Consultation Plan shall also include (as relevant) linkages and cross-references to the CEMP and DWPs (including SSCNVMPs, SSCNMPs and SSCVMPs). 15.6The Communication and Consultation Plan shall include a summary of the communication and consultation undertaken between the Requiring Authority and parties as required by the Pre-construction Communication and Consultation Plan. The summary shall include any outstanding issues or disputes raised by parties. The Communication and Consultation Plan shall be reviewed six monthly for the duration of construction and updated if required. Any updated Communication and Consultation Plan shall be provided to the “key contacts� (see Condition 13) and the Auckland Council Consent Monitoring officer for review and agreement on any further action to be undertaken. Any further action recommended as a result of this review shall be undertaken by the Communication and Consultation Manager for the City Rail Link and confirmation of completion provided back to the Auckland Council Consent Monitoring officer. 15.7If, in the course of amendments undertaken as part of the review process, a material

City Rail Link Notice of Requirement

Page 19


Condition Number

Condition

NoR Applies to

change to the Communication and Consultation Plan is made, those parties affected by the change shall be notified within 1 month of the material change occurring. Communications – Notable Noise and Vibration Receivers

1 16

4 5 6

16.1A SSCNVMP shall be prepared for all Notable Noise and Vibration Receivers (refer Condition 39). As part of the SSCNVMP (and further to Condition 15 of this designation), the Requiring Authority shall undertake communication and consultation, as soon as reasonably practicable (and at least once following confirmation of construction timing and methodology), with any Notable Noise and Vibration Receivers located within 200 metres of blasting, or within 100 metres (either horizontally or vertically) of the designation footprint for other construction activities. Communication and consultation with these parties should focus on a collaborative approach to manage the adverse effects from construction noise and vibration while works are undertaken in the vicinity. 16.2The Requiring Authority shall undertake on-going communication and consultation with notable noise and vibration receivers throughout the duration of construction occurring in the vicinity. This communication shall be reported back to the “key contacts” (see Condition 13) and the Auckland Council Consent Monitoring officer for their review and confirmation of any further action to be undertaken. The Auckland Council Consent Monitoring Officer shall advise the Requiring Authority of its recommendation within 10 working days of receiving this information from the Requiring Authority. Concerns and Complaints Management 17.1Upon receiving a concern or complaint during construction, the Requiring Authority shall instigate a process to address concerns or complaints received about adverse effects. This shall: (a) Identify of the nature of the concern or complaint, and the location, date and time of the alleged event(s); (b) Acknowledge receipt of the concern or complaint within 24 hours of receipt; (c) Respond to the concern or complaint in accordance with the relevant management plan , which may include monitoring of the activity by a suitably qualified expert, implementation of mitigation measures, and, in the case of noise and / or vibration, preparation of a site specific noise and / or vibration management plan (in accordance with Conditions 37 and 38);

1 17

2 4 5 6

17.2A record of all concerns and / or complaints received shall be kept by the Requiring Authority. This record shall include: (a) The name and address of the person(s) who raised the concern or complaint (unless they elect not to provide this) and details of the concern or complaint; (b) Where practicable, weather conditions at the time of the concern or complaint, including wind direction and cloud cover if the complaint relates to noise or air quality; (c) Known City Rail Link construction activities at the time and in the vicinity of the concern or complaint; (d) Any other activities in the area unrelated to the City Rail Link construction that may have contributed to the concern or complaint such as non-City Rail Link construction, fires, traffic accidents or unusually dusty conditions generally; (e) Remedial actions undertaken (if any) and the outcome of these, including monitoring of the activity. 17.3This record shall be maintained on site, be available for inspection upon request, and shall be provided every two months (or as otherwise agreed) to the Auckland Council Consent Monitoring officer, and to the “key contacts” (see Condition 13).

City Rail Link Notice of Requirement

Page 20


Condition Number

Condition

NoR Applies to

17.4Where a complaint remains unresolved or a dispute arises, the Auckland Council Compliance Monitoring Officer will be provided with all records of the complaint and how it has been dealt with and addressed and whether the Requiring Authority considers that any other steps to resolve the complaint are required. Upon receiving records of the complaint the Auckland Council Compliance Monitoring Officer must determine whether a review of the CEMP and/or DWPs is required under Condition 22 to address this complaint. The Auckland Council Compliance Monitoring Officer shall advise the Requiring Authority of its recommendation within 10 working days of receiving the records of complaint. “One Network� Consultation 1 18

4 5 6

18.1The Requiring Authority and its contractor shall work collaboratively with the New Zealand Transport Agency (NZTA) during the preparation of the Traffic, Access and Parking DWP (Conditions 25, 27, 28, 29, and 30) in relation to confirming the management of adverse transport effects on the road network. A record of this consultation and outcomes shall be included in the Traffic, Access and Parking DWP. The Requiring Authority shall consult with the NZTA throughout the duration of construction on any changes or updates to the Traffic, Access and Parking DWP which relate to the management of the road network.

Construction Environmental Management Plan (CEMP) and Delivery Work Plans (DWPs) Preparation, Compliance and Monitoring 19.1The objective of the CEMP and DWPs is to so far as is reasonably practicable, avoid, remedy or mitigate any adverse effects (including cumulative effects) associated with the City Rail Link construction.

19

1 2 4 5 6

19.2All works must be carried out in accordance with the CEMP, the DWPs required by these conditions and in accordance with any changes to plans made under Condition 23. 19.3The CEMP and DWPs shall be prepared, complied with and monitored by the Requiring Authority throughout the duration of construction of the City Rail Link. 19.4The DWPs shall give effect to the specific requirements and objectives set out in these designation conditions. 19.5The CEMP shall include measures to give effect to any specific requirements and objectives set out in these designation conditions that are not addressed by the DWPs. 19.6Where mitigation measures are required to be implemented by the Requiring Authority in relation to the construction of City Rail Link, it shall meet reasonable and direct costs of implementing such mitigation measures. CEMP Requirements 20.1In order to give effect to the objective in Condition 19.1, the CEMP must provide for the following:

20

1 2 4 5 6

(a) In relation to NoR 2, the use of one Tunnel Boring Machine (unless the effects of using more than one Tunnel Boring Machine are not materially different from those associated with the use of one Tunnel Boring Machine); (b) Notice boards that clearly identify the Requiring Authority and the Project name, together with the name, telephone number and email address of the Site or Project Manager and the Communication and Consultation Manager; (c) Training requirements for employees, sub-contractors and visitors on construction procedures, environment management and monitoring; (d) A Travel Management Plan for each construction site outlining onsite car parking management and methods for encouraging travel to the site using forms of transport

City Rail Link Notice of Requirement

Page 21


Condition Number

Condition

NoR Applies to

other than private vehicle to assist in mitigating localised traffic effects; and (e) Where a complaint is received, the complaint must be recorded and responded to as provided for in Conditions 13, 15 and 17. 20.2The CEMP shall include details of: (a) The site or Project Manager and the Communication and Consultation Manager (who will implement and monitor the Communication and Consultation Plan), including their contact details (phone, email and physical address); (b) The Document management system for administering the CEMP, including review and Requiring Authority / Constructor / Auckland Council requirements; (c) Environmental incident and emergency management procedures; (d) Environmental complaint's management procedures (see also Condition 17); (e) An outline of the construction programme of the work, including construction hours of operation, indicating linkages to the DWPs which address the management of adverse effects during construction; (f) Specific details on demolition to be undertaken during the construction period; (g) Means of ensuring the safety of the general public; and (h) Methods to assess and monitor potential cumulative adverse effects. 20.3Subject to any alternative agreement with the landowner(s) of HSBC House and Zurich House, the Requiring Authority shall prepare specific construction methodologies for the works adjacent to 1 Queen Street and 21 Queen Street detailing how they will be undertaken to avoid compromising the structural integrity of the existing structures on the site including their foundation systems. The specific construction methodologies shall be prepared in consultation with the owner(s) of these properties. A record of this liaison and outcomes shall be included in the CEMP as part of the Outline Plan. This summary must provide a clear explanation of where any comments have not been incorporated into the CEMP, and the reasons why not. This summary must be provided to both the Independent Peer Review Panel and Auckland Council as part of the Outline Plan process. CEMP Construction Works Requirements 21.1In order to give effect to the objective in Condition 19.1, the CEMP shall include the following details and requirements in relation to all areas within the surface designation footprint where construction works are to occur, and / or where materials and construction machinery are to be used or stored:

21

1 4 5 6

(a) Where access points are to be located and procedures for managing construction vehicle ingress and egress to construction support and storage areas; (b) Methods for managing the control of silt and sediment within the construction area; (c) Methods for earthworks management (including depth and extent of earthworks and temporary, permanent stabilisation measures and monitoring of ground movement) for earthworks adjacent to buildings and structures; (d) Measures to adopt to keep the construction area in a tidy condition in terms of disposal / storage of rubbish and storage unloading of construction materials (including equipment). All storage of materials and equipment associated with the construction works shall take place within the boundaries of the designation; (e) Measures to ensure all temporary boundary / security fences associated with the construction of the City Rail Link are maintained in good order with any graffiti removed as soon as possible; (f) For the duration of construction affecting Lower Queen Street or Queen Elizabeth II Square, construction fences and / or hoardings shall be placed no closer than 3 metres from the north frontage (building frontage onto Queen Elizabeth II Square) of

City Rail Link Notice of Requirement

Page 22


Condition Number

Condition

NoR Applies to

21 Queen Street in the vicinity of the entrance to the ground level retail space and the main pedestrian entrance to the building. (g) The location and specification of any temporary acoustic fences and visual barriers, and where practicable, opportunities for mana whenua (see Condition 8) and community art or other decorative measures along with viewing screens to be incorporated into these without compromising the purpose for which these are erected; (h) How the construction areas are to be fenced and kept secure from the public and, where practicable and without compromising their purpose how opportunities for public viewing, including provision of viewing screens and display of information about the project and opportunities for mana whenua and community art or other decorative measures can be incorporated to enhance public amenity and connection to the project; (i) The location of any temporary buildings (including workers offices and portaloos) and vehicle parking (which should be located within the construction area and not on adjacent streets); (j) Methods to control the intensity, location and direction of artificial construction lighting to avoid light spill and glare onto sites adjacent construction areas; (k) Methods to ensure the prevention and mitigation of adverse effects associated with the storage, use, disposal, or transportation of hazardous substances; (l) That onsite stockpiling of spoil or fill at Downtown and Lower Albert Street construction yards be minimised where practicable; (m) That site offices and less noisy construction activities be located at the edge of the construction yards where practicable; and (n) Methods for management of vacant areas once construction is completed in accordance with the Urban Design DWP. 21.2Unless expressly agreed in writing with the landowner of the Downtown Shopping Centre (at 7 Queen Street): (a) the Downtown construction yard, (including QEII Square, Downtown Shopping Centre and Lower Albert Street), shall be progressively released from occupation for construction purposes where the area or any part of the area is no longer required for construction of the section of CRL between Britomart and Wyndham Street; and. (b) following completion of the section of the CRL between the Downtown Shopping Centre and Wyndham Street and reinstatement of Albert Street, Lower Albert Street shall not be occupied for construction purposes for any section of CRL south of Wyndham Street. Review Process for CEMP and DWPs

22

1 2 4 5 6

22.1The CEMP and DWPs shall be reviewed at least annually or as a result of a material change to the City Rail Link project or to address unforeseen adverse effects arising from construction or unresolved complaints. Such a review may be initiated by either Auckland Council or the Requiring Authority. The review shall take into consideration: (a) Compliance with designation conditions, the CEMP, DWPs (including SSCNVMPs, SSCNMPs and SSCVMPs) and material changes to these plans; (b) Any changes to construction methods; (c) Key changes to roles and responsibilities within the City Rail Link project; (d) Changes in industry best practice standards; (e) Changes in legal or other requirements; (f) Results of monitoring and reporting procedures associated with the management of

City Rail Link Notice of Requirement

Page 23


Condition Number

Condition

NoR Applies to

adverse effects during construction; (g) Any comments or recommendations received from Auckland Council regarding the CEMP and DWPs (including SSCNVMPs, SSCNMPs and SSCVMPs); and (h) Any unresolved complaints and any response to the complaints and remedial action taken to address the complaint as required under Condition 17. 22.2A summary of the review process shall be kept by the Requiring Authority, provided annually to the Auckland Council, and made available to the Auckland Council upon request. Update of CEMP and DWPs following Review 23.1Following the CEMP and DWPs review process described in Condition 22, the CEMP may require updating.

23

1 2 4 5 6

23.2Any material change to the CEMP and DWP must be consistent with the purpose and objective of the relevant condition. 23.3 Affected parties will be notified of the review and any material change proposed to the CEMP and DWPs (including SSCNVMPs, SSCNMPs and SSCVMPs). 23.4The CEMP and DWPs must clearly document the comments and inputs received by the Requiring Authority from affected parties about the material change, along with a clear explanation of where any comments have not been incorporated, and the reasons why not. 23.5Any material change proposed to the CEMP and DWPs shall be subject to an independent peer review as required by Condition 11. 23.6Following that review any material change proposed to the CEMP and DWPs relating to an adverse effect shall be submitted for approval to Auckland Council Compliance and Monitoring Officer, at least 10 working days prior to the proposed changes taking effect. If any changes are not agreed, the relevant provisions of the RMA relating to approval of outline plans shall apply. Network Utilities 24.1To manage the adverse effects on Network Utilities Operations during the construction of the City Rail Link, the following shall be included in the CEMP.

24

1 4 5 6

24.2The purpose of this section of the CEMP shall be to ensure that the enabling works and construction of the City Rail Link adequately take account of, and include measures to address the safety, integrity, protection or, where necessary, relocation of existing network utilities that traverse, or are in close proximity to, the designation during the construction of the City Rail Link. 24.3For the avoidance of doubt and for the purposes of this condition an “existing Network Utility� includes infrastructure operated by a Network Utility Operator which was: (a) In place at the time the notice of requirement for the City Rail Link was served on Auckland Council (23 August 2012); or (b) Undertaken in accordance with condition 6 of this designation or the section 176(1)(b) RMA process. 24.4The CEMP shall be prepared in consultation with Network Utility Operators who have existing Network Utilities that traverse, or are in close proximity to, the designation and shall be adhered to and implemented during the construction of the City Rail Link. The CEMP shall include as a minimum: (a) Cross references to the Communication and Consultation Plan for the methods that will be used to liaise with all Network Utility Operators who have existing network utilities that traverse, or are in close proximity to, the designation;

City Rail Link Notice of Requirement

Page 24


Condition Number

NoR Applies to

Condition

(b) Measures to be used to accurately identify the location of existing Network Utilities, and the measures for the protection, support, relocation and/or reinstatement of existing Network Utilities; (c) Methods to be used to ensure that all construction personnel, including contractors, are aware of the presence and location of the various existing Network Utilities (and their priority designations) which traverse, or are in close proximity to, the designation, and the restrictions in place in relation to those existing Network Utilities. This shall include: (i) Measures to provide for the safe operation of plant and equipment, and the safety of workers, in proximity to existing Network Utilities; (ii) Plans identifying the locations of the existing Network Utilities (and their designations) and appropriate physical indicators on the ground showing specific surveyed locations; (d) Measures to be used to ensure the continued operation of Network Utility Operations and the security of supply of the services by Network Utility Operators at all times; (e) Measures to be used to enable Network Utility Operators to access existing Network Utilities for maintenance at all reasonable times on an ongoing basis during construction, and to access existing Network Utilities for emergency and urgent repair works at all times during the construction of the City Rail Link; (f) Contingency management plans for reasonably foreseeable circumstances in respect of the relocation and rebuild of existing Network Utilities during the construction of the City Rail Link; (g) A risk analysis for the relocation and rebuild of existing Network Utilities during the construction of the City Rail Link; (h) Earthworks management (including depth and extent of earthworks and temporary and permanent stabilisation measures), for earthworks in close proximity to existing Network Utilities; (i) Vibration management and monitoring for works in close proximity to existing Network Utilities; (j) Emergency management procedures in the event of any emergency involving existing Network Utilities; (k) The process for providing as-built drawings showing the relationship of the relocated Network Utilities to the City Rail Link to Network Utility Operators and the timing for providing these drawings; (l) Measures to ensure that network utility services are not interrupted to the Mt Eden Corrections Facility as a result of City Rail Link works. The requiring authority shall advise the Department of Corrections and the entity contracted by Department of Corrections to administer and run the Mt Eden Corrections facility at 1 Lauder Road, of any works on network utilities in the vicinity of the Mt Eden Corrections Facility which may impact on utility service provision to the Mt Eden Corrections Facility at least 14 days prior to those works occurring to allow the Department of Corrections (and the entity contracted to administer and run the facility at 1 Lauder Road) to arrange suitable contingencies. Communication and consultation with the Department of Corrections, and the entity contracted to administer and run the facility at 1 Lauder Road, shall be recorded in accordance with condition 15) of this designation. The Requiring Authority shall be responsible for ensuring that construction works do not interrupt network utility services to the Mt Eden Corrections Facility, unless by prior arrangement with Department of Corrections and

City Rail Link Notice of Requirement

Page 25


Condition Number

Condition

NoR Applies to

the entity contracted by Department of Corrections to administer and run the Mt Eden Corrections facility at 1 Lauder Road. (m) A summary of the consultation (including any methods or measures in dispute and the Requiring Authorities response to them) undertaken between the Requiring Authority and any Network Utility Operators during the preparation of the CEMP. 24.5If the Requiring Authority and a Network Utility Operator cannot agree on the methods proposed under the CEMP to manage the construction effects on the Operator’s network utility operation, unless otherwise agreed, each party will appoint a suitably qualified and independent expert, who shall jointly appoint a third such expert to advise the parties and make a recommendation. That recommendation will be provided by the Requiring Authority as part of the CEMP along with reasons if the recommendation is not accepted. Transport, Access and Parking General Transport, Access and Parking 25.1A Transport, Access and Parking DWP shall be prepared to manage the adverse effects of construction of the City Rail Link, or any part of it, on the transport network. 25.2The objective of the Transport, Access and Parking DWP is to so far as is reasonably practicable, avoid, remedy or mitigate the adverse effects of construction on transport, parking and property access. This is to be achieved by: (a) Managing the road transport network for the duration of construction by adopting the best practicable option to manage congestion; (b) Maintaining pedestrian access to private property at all times; and (c) Providing on-going vehicle access to private property to the greatest extent possible. 25.3To achieve the above objective, the following shall be included in the Transport, Access and Parking DWP:

25

1 4 5 6

(a) The road routes which are to be used by construction related vehicles, particularly trucks to transport construction related materials, equipment, spoil, including how the use of these routes by these vehicles will be managed to mitigate congestion, and to the greatest extent possible, avoid adverse effects on residential zoned land and education facilities; (b) Transport route options for the movement of construction vehicles carrying spoil, bulk construction materials or machinery shall be identified and details provided as to why these routes are considered appropriate routes. In determining appropriate routes, construction vehicles carrying spoil, bulk construction materials or machinery shall as far as practicably possible only use roads that: (i) Form part of the regional arterial network; (ii) Are overweight / over dimensioned routes; (iii) Or other routes (specified below) where no other practical option is available. (c) For the purposes of this condition the following routes (that at the time this designation was confirmed were not part of the regional arterial network and / or overweight / over dimensioned) shall be used where practicable for the movement of construction vehicles carrying spoil, bulk construction materials or machinery: (i) Ngahura Road, for trucks heading to/from Eden Terrace construction site; (ii) Dundonald Street and Basque Road, for trucks heading to/from the Newton Station construction sites; (iii) Pitt Street (between Hobson Street and Hopetoun Street), Beresford Square, Mercury Lane, Canada Street and Upper Queen Street (between Canada Street and Karangahape Road), for trucks heading to/from Karangahape Station

City Rail Link Notice of Requirement

Page 26


Condition Number

NoR Applies to

Condition

construction sites; (iv) Wellesley Street (between Nelson Street and east of Albert Street), Cook Street (between Mayoral Drive and Hobson Street) and Mayoral Drive (between Wellesley Street and Cook Street) for trucks heading to/from Aotea Station construction sites; (v) Nelson Street (north of Wellesley Street), Hobson Street (north of Cook Street) and Lower Albert Street, for trucks heading to/from the Albert Street and Downtown construction sites. (d) Where other routes are necessary (other than those routes identified above), the Transport, Access and Parking DWP shall identify any residential zoned land and education facilities and shall provide details on how adverse effects from these vehicle movements are to be mitigated through such measures as: (i) Communication and consultation (in accordance with Condition 15 of this designation) with these properties in advance of the vehicle movements occurring; (ii) Restricting vehicle movements on Monday to Friday to between 9.30am and 4pm, and on Saturday to between 9am and 2pm. (e) Proposed temporary road lane reductions and / or closures, alternative routes and temporary detours, including how these have been selected and will be managed to mitigate congestion as far as practicably possible and how advance notice will be provided; (f) How disruption to the use of private property will be mitigated through: (i) Ensuring pedestrian and cycle access to private property is retained at all times; (ii) Providing vehicle access to private property as far as practicably possible at all times, except for temporary closures where landowners and occupiers have been communicated and consulted with in reasonable advance of the closure; and (iii) How the loss of any private car parking will be mitigated through alternative car parking arrangements. (g) Where an affected party unexpectedly finds their vehicle blocked in as a result of a temporary closure, the Requiring Authority shall (within reasonable limits) offer alternative transport such as a taxi, rental car, or other alternative. Note: For the purposes of designation Conditions 25, 27, 28, 29 and 30 “temporary closure� is defined as the following: (i) In place for less than six hours, the Requiring Authority shall communicate and consult on the closure at least 24 hours in advance, but is not required to offer or provide alternative parking arrangements, though it may choose to offer this on a case by case basis in consultation with the affected party; and (ii) In place for between six and 72 hours, the Requiring Authority shall communicate and consult on the closure at least 72 hours in advance, and will offer and provide where agreed with the affected party alternative parking arrangements. The alternative parking arrangement should be as close to the site affected as is reasonably practicable. (h) How disruption to use of the road network will be mitigated for emergency services, public transport, bus users, taxi operators, freight and other related vehicles, pedestrians and cyclists through: (i) Prioritising, as far as practicably possible, pedestrian and public transport at intersections where construction works are occurring;

City Rail Link Notice of Requirement

Page 27


Condition Number

NoR Applies to

Condition

(ii) Relocating bus stops and taxi stands to locations which, as far as practicably possible, minimise disruption; and (iii) Identifying alternate heavy haul routes where these are affected by construction works. (i) Cross references to the specific sections in the Communication and Consultation Plan that detail how emergency services, landowners, occupiers, public transport users, bus and taxi operators, and the general public are to be consulted with in relation to the management of the adverse effects on the transport network. (j) The alternative (to road) transport options that are available (including the option of rail use at the main construction site adjacent the North Auckland Rail Line) and that have been considered and assessed for the transportation of spoil. This will include as applicable: (i) Benefits that could be provided by alternative options; (ii) Potential adverse effects associated with alternative options; (iii) Where an alternative option is proposed, methods for managing potential adverse effects; and (iv) Reasons for either adopting or not adopting alternative transport options. Monitoring of Transport Network Congestion 26.1To achieve the objective of Condition 25.2(a), the Requiring Authority will undertake monitoring of the transport network and implement additional mitigation measures as required to manage congestion to achieve the best practicable option. 26.2The purpose of the monitoring is to monitor congestion on the transport network by measuring average delays for traffic travelling along specified routes. The evaluation times will be: (a) The average travel times over the weekday two hour morning peak period; and (b) The average travel times over the weekday two hour evening peak period; and (c) The average weekday inter-peak travel times between 9am to noon, noon to 2pm and 2 to 4pm. 26.3The Requiring Authority shall carry out continuous monitoring for the duration that construction of the City Rail Link is occurring. The intention is that this monitoring is to be continuous, although it is acknowledged that there may be occasional malfunctions. 26

1

26.4If a congestion incident occurs (such as an accident), the monitoring during the affected period will be considered unrepresentative. 26.5Monitoring shall commence six months prior to construction of the City Rail Link to establish a baseline of existing transport congestion. 26.6The monitoring will establish whether the City Rail Link construction works have increased traffic delays as follows: (a) Either by more than 10 minutes (from the monitoring previously undertaken in accordance with this condition) (b) Or if the travel times are more than three minutes or 30% greater than the forecast modelled increases along that route (according to the most recent traffic model test of that scenario, undertaken prior to the start of construction. The modelled time is to be based on the Auckland City Centre SATURN traffic model or a different traffic model approved by the Requiring Authority). (c) The 30% above shall only apply for an increase predicted to be over four minutes. 26.7If the travel times exceed the above criteria on any one of the specified routes, then additional mitigation shall be implemented by the Requiring Authority in its role as the

City Rail Link Notice of Requirement

Page 28


Condition Number

NoR Applies to

Condition

Road Controlling Authority (under its statutory obligation). The additional mitigation could include but is not limited to advertising alternative routes, removing on street car parking or implementing operational measures, such as lane reconfigurations or signal phasing, to increase capacity on the surrounding network where reasonably possible at that time. 26.8The purpose of additional mitigation measures is to mitigate the increases in traffic delays, reducing these to below the levels identified in Condition 26.6 as far as is reasonably achievable. 26.9For the purposes of this condition, the following are the specified routes: (a) Wellesley Street (between Victoria Street and Princes Street) (b) Victoria Street (between Wellesley Street and Princes Street) (c) Customs Street/Fanshawe Street (between Nelson Street and Tangihua Street) (d) Quay Street/Lower Hobson Street (between Fanshawe Street/Hobson Street and Tangihua Street) (e) Nelson Street/Hobson Street (between Pitt Street and Fanshawe Street) (f) Queen Street (between Mayoral Drive and Customs Street) (g) New North Road/Symonds Street (between Dominion Road and Newton Road) (h) Mount Eden Road (between Normanby Road and Symonds Street) (i) Khyber Pass Road between the southern motorway ramps and Symonds Street if this route is to be used by construction related trucks (j) Newton Road between the northwestern motorway ramps and Symonds Street 26.10 The specified routes shall exclude whichever east-west route has its intersection with Albert Street closed at the time of the surveys. Transport, Access and Parking: Specific Requirements (Britomart to Mayoral Drive) 27.1To achieve the objective in Condition 25, the following measures shall be implemented: (a) A vehicle access lane at least 3m wide shall be provided along the eastern side of Albert Street between Customs Street and Victoria Street to provide access to properties (except that while the Albert Street/Victoria Street intersection is closed, this access lane is only to be provided between Customs Street and Durham Street); (b) A vehicle access lane at least 3m wide shall be provided along the western side of Albert Street between Customs Street and Victoria Street to provide access to properties, except that:

27

1

(i) While the Albert Street/Customs Street intersection is closed, this access lane is only to be provided between Victoria Street and Wolfe Street; and (ii) While the Albert Street/Victoria Street intersection is closed, this access lane is only to be provided between Kingston Street and Customs Street. (c) The east-west / west-east connection (two fully operational traffic lanes in each direction) is to be maintained in each direction at two of the Customs Street, Victoria Street and Wellesley Street intersections with Albert Street during the period when the third of those intersections is otherwise fully closed; (d) The left turn movement from Customs Street (from the east) into Albert Street, and the left turn from Customs Street (from the west) into Albert Street, shall be retained while the Albert Street / Customs Street intersection is fully closed; (e) The left turn from Durham Street into Queen Street shall be reopened while the Albert Street/Victoria Street intersection is fully closed; (f) Two way access shall be provided on the single service lane along the western side of Albert Street between 87 Albert Street and Kingston Street while the Albert

City Rail Link Notice of Requirement

Page 29


Condition Number

NoR Applies to

Condition

Street/Victoria Street intersection is fully closed; (g) Vehicular access into and egress from: (i) Mills Lane to and from either Albert Street or Swanson Street; and (ii) The Stamford Plaza Auckland main entrance and forecourt area is to be provided at all times and for the avoidance of doubt cannot be temporarily closed during construction. (h) Providing pedestrian and cycle access to private property at all times; (i) Providing footpaths of at least 1.5m in width along either side of Albert Street; (j) At a minimum two safe crossing passageways (which are “fully accessible� with a minimum width of 1.5m wide and well lit ), need to be provided in the vicinity of Swanson Street and Wyndham Street, in addition to pedestrian crossings at the intersections of Victoria Street and Customs Street; and (k) Ensuring that construction traffic does not use Swanson Street, Wolf Street or Federal Street north of Swanson Street; 27.2The Traffic, Access and Parking DWP shall demonstrate how these measures will be implemented and shall also include the following: (a) How construction works will be undertaken to mitigate congestion on Albert Street, Wellesley Street, Victoria Street, Customs Street, and Quay Street including retaining east-west traffic movements across Albert Street on Customs Street, Victoria Street and Wellesley Street; (b) The timing and sequencing of temporary road lane reductions and / or closures, and the alternative routes and temporary detours to be used, including: (i) How these have been selected and will be managed to, where practicable, mitigate congestion on the surrounding road network; (ii) How the Albert Street/Wyndham Street intersection will be reopened as soon as practically possible; (c) How disruption to the use of private property located immediately adjacent the designation with access onto Galway Street, Tyler Street, Queen Elizabeth Square, Customs Street, Albert Street, Victoria Street and Wellesley Street will be mitigated through: (i) Providing vehicle access to private property as practicably possible at all times; (ii) Retaining local vehicle access to properties located along Albert Street (which may include only left in, left out access ); (iii) Retaining access for loading and unloading of goods located along the service lane on the eastern side of Albert Street, between Victoria Street and Wellesley Street ; and; (iv) Providing an on street loading bay on Customs Street, Lower Albert Street or Lower Queen Street to provide servicing to 21 Queen Street if access during construction cannot be provided to the existing loading bay area for 21 Queen Street, accessed from Lower Albert Street; (d) How disruption to the use of the local road network will be mitigated for private bus users, pedestrians and cyclists through: (i) Providing, where practicable, for the continued operation of private bus operators from hotels and other pick up / drop off locations in the city centre area (cross references to the Communication and Consultation Plan for consulting with private bus operators shall be included in the CEMP and Traffic, Access and Parking DWP); and (ii) Retaining pedestrian and cycle access through Lower Queen Street and / or

City Rail Link Notice of Requirement

Page 30


Condition Number

NoR Applies to

Condition

Queen Elizabeth Square to provide access to and from the Ferry terminal and Customs Street; and (e) How disruption to pedestrians and cyclists requiring the ability to cross from east to west (and vice versa) across Albert Street between Victoria Street and Customs Street can be mitigated through providing, where practicable, safe pedestrian and cyclist passageways across the construction works on Albert Street. Transport Access and Parking: Specific Requirements (Karangahape Station Area) 28.1To achieve the objective in Condition 25, the following measure shall be implemented: (a) Retaining one lane of traffic in each direction on Pitt Street (unless otherwise agreed with the Auckland Council Consent Monitoring officer); and (b) Spoil trucks shall not use East Street where practicable and on-street parking at the Southern end of East Street will be retained. 28.2 The Traffic, Access and Parking DWP shall demonstrate how these measures will be implemented and shall also include the following:

28

4

(a) How construction of the shafts providing access to the Station can be undertaken to mitigate congestion on Pitt Street, Karangahape Road, and Mercury Lane; (b) The timing and sequencing of temporary road lane reductions and / or closures on Pitt Street, Mercury Lane, and the western end of Beresford Street, and the alternative routes and temporary detours to be used, including how these have been selected and will be managed to, where practicable, mitigate congestion on the surrounding road network; (c) How disruption to the use of private property located immediately adjacent the surface designation with access onto Beresford Street, Pitt Street, Mercury Lane, and East Street will be mitigated through: (i) Providing pedestrian and cycle access to private property at all times, particularly those businesses located at the eastern end of Beresford Street and the northern end of Mercury Lane; (ii) Providing vehicle access to private property, which may include only a turn in and a turn out in the same direction), as practicably possible at all times, except for temporary closures where landowners and occupiers have been communicated and consulted with in reasonable advance of the closure; (iii) Providing local vehicle access to properties located along Beresford Street and Samoa House Lane (which may include only a turn in and a turn out in the same direction); (iv) Alternative parking arrangements or other offers for resolving the temporary loss of car parking during construction for the Hopetoun Alpha Building. Transport, Access and Parking: Specific Requirements (Newton Station Area)

29

5

29.1To achieve the objective in Condition 25, the Traffic, Access and Parking DWP shall include the following: (a) How construction of the shafts providing access to the Newton Station, although constructed wholly on private land, can be undertaken to mitigate construction related congestion on Symonds St, the Symonds Street / Mt Eden Road / New North Road intersection, Dundonald Street, and the western end of Basque Road; (b) The timing and sequencing of temporary road lane reductions and / or closures on Symonds St in the vicinity of the intersection of Symonds Street / Mt Eden Road and New North Road , Dundonald Street, and the western end of Basque Road, and the alternative routes and temporary detours to be used, including how these have been selected and will be managed to, where practicable, mitigate congestion on the

City Rail Link Notice of Requirement

Page 31


Condition Number

NoR Applies to

Condition

surrounding road network; (c) How disruption to the use of private property located immediately adjacent the surface designation with access onto Symonds Street, Dundonald Street, and the western end of Basque Road will be mitigated through: (i) Providing pedestrian and cycle access to private property at all times, particularly for those businesses and residences located along Symonds Street and Dundonald Street; (ii) Providing vehicle access to private property, which may include only a turn in and a turn out in the same direction), as practicably possible at all times, except for temporary closures where landowners and occupiers have been communicated and consulted with in reasonable advance of the closure. How the loss of public pay and display parking located at the Auckland Transport Symonds Street Public Car Park will be mitigated through alternative parking arrangements. The Requiring Authority may be able to arrange such alternative car parking at the Burleigh Street car park. (d) The effects of the temporary use of the Symonds Street car park as a construction site are to be mitigated by the Requiring Authority by active parking management and enforcement, within 400m of the car park, to maximise short term parking within this area Transport and Property Access: Additional Requirements (NAL Area) 30.1To achieve the objective in Condition 25, the following measures shall be implemented: (a) The retention of at least two traffic lanes (one in either direction) on Mt Eden Road during the construction of the replacement Mt Eden Road Bridge; (b) During the closure of the Normanby Road level crossing to construct the grade separated crossing, the Mt Eden Road and Normanby Road intersection shall be signalised and a second traffic lane shall be provided on the Boston Road approach to its intersection with Mt Eden Road intersection. Additionally, the no parking restrictions on Boston Road shall be extended along the length of Boston Road and considered for any adjacent local roads to facilitate through traffic; (c) A temporary pedestrian crossing (over the rail line) at Normanby Road is to be provided for the period of the temporary closure of the Normanby Road connection;

30

6

(d) Access will be maintained to Nikau Street at all times by at least one lane (minimum 3m), and two lanes on Nikau St between Flower and Korari Streets. Access to sites within Flower Street and Korari Street is to be retained, from Nikau Street or New North Road, at all times; (e) Construction works will be undertaken to ensure two-way access is maintained at all times for vehicles to all accessways to the MediaWorks site including staff and visitors cars, trucks and service vehicles; (f) Providing for traffic to turn right out of Ruru Street to reduce any congestion (particularly at peak times) resulting from not being able to travel via Nikau Street to the traffic lights at Flower Street and New North Road; (g) Providing accessibility along Mt Eden and Normanby Roads as a priority for, where practicable: public transport (buses), emergency services, access to properties for pedestrians, and cyclists; (h) Construction works will be undertaken to ensure two-way access is maintained at all times for all vehicles accessing the Mt Eden Corrections Facility at Lauder Road (including staff and visitors’ cars, service vehicles, prison vans, emergency vehicles and buses), communication and consultation with the Department of Corrections, and the entity contracted by Department of Corrections to administer and run the Mt

City Rail Link Notice of Requirement

Page 32


Condition Number

NoR Applies to

Condition

Eden Corrections facility at 1 Lauder Road, on this matter shall be recorded in accordance with Condition 15) of this designation. The Requiring Authority shall be responsible for ensuring that the construction works do not restrict 24-hour two-way access for all vehicles accessing the Mt Eden Corrections Facility at Lauder Road; (i) Construction works will be undertaken to ensure two-way access is maintained at all times for vehicles accessing the premises at 51-63 Normanby Road, including staff and visitors cars, trucks and service vehicles. The measures shall: (i) Ensure safe and reasonable access to and from the site, to Austroads standards; (ii) Not result in the loss of any on site parking; (iii) Incorporate a crossing width sufficient not to reduce the range of vehicles required to access the site, relative to the existing situation; (iv) It is noted that the site is used occasionally by large trucks of up to 18m. These vehicles are to be provided for in the design of the access (i.e. the vehicle crossing and the access onto the site); (v) Following completion of the grade separation of Normanby Road safe and reasonable access will be provided to and from the property at 51-63 Normanby Road to meet the relevant Austroads and NZS2890.1 standards or the applicable standard required by the road controlling authority. (j) Construction works will be undertaken to ensure pedestrian and two-way vehicle access is maintained at all times to access the premises at 32 Normanby Road, including staff and visitors cars, trucks and service vehicles. The measures shall: (i) Ensure safe and reasonable access to and from the site, to Austroads standards; (ii) Incorporate a crossing width sufficient not to reduce the range of vehicles required to access the site, relative to the existing situation; (iii) Should the Requiring Authority require part of the site at 32 Normanby Road that is currently used for 40 car parking spaces for the construction of the City Rail Link 34 alternative car parking spaces will be provided at 14-22 Boston Road (in accordance with Plan DRG 0052 Rev 2.0 and DRW 0058 Rev 5.0). The Requiring Authority shall provide safe pedestrian access across the North Auckland Line and into the site for customers and staff, visiting or employed at the site in accordance with Condition 30.1(c) until the grade separation works are completed and permanent access is reinstated to the site. (k) At completion of the grade separation of Normanby Road safe and reasonable pedestrian and vehicle access to and from the site and 34 on site car parking spaces will be provided for the property at 32 Normanby Road. In the case of pedestrian and vehicle access and parking arrangements, this will be in accordance with Plan DRG 0058 Rev 5.0, and meet the following requirements: (i) The ramp access will meet relevant Austroads, NZS2890.2 and the Auckland Council District Plan: Isthmus Section design standards; (ii) The 34 car parking spaces will be provided across the site and the adjoining KiwiRail property. The spaces will be compliant with the appropriate Auckland Council District Plan: Isthmus Section parking standards for dimension and manoeuvring; (iii) The design, structures and barriers associated with the ramp and pedestrian access to the site will be subject to the urban design process of Condition 47; and (iv) Provision for landscape planting both on the site and on the KiwiRail land in the area shown on DRG 0058 Rev 5.0 and if appropriate beyond the site (in accordance with Condition 47.2). Indicative widths of landscaping on DRG 0058

City Rail Link Notice of Requirement

Page 33


Condition Number

NoR Applies to

Condition

Rev 5.0 are 1m for the section shown alongside the railway and 0.5m for the section on the southern side of the ramp. (l) The KiwiRail land required by condition (k) above for car parking spaces, landscaping and the ramp access will be provided by the Requiring Authority until such time as the vehicle access ramp is no longer required by the landowner. If the vehicle access ramp is no longer required to provide access to the property it shall be removed by the Requiring Authority at its cost within 3 months unless otherwise agreed with the landowner. (m) Construction of the grade separation works at Normanby Road on the parcels of land identified on the CRL NoR6 Sheet 2 as parcels 242, 243, 244, 245, 246, 393, 394, 399, 400 and 401 shall not commence until the KiwiRail land is available and written confirmation of this has been provided by the Requiring Authority to Auckland Council. 30.2The Traffic, Access and Parking DWP shall demonstrate how these measures will be implemented and shall also include the following: (a) How construction works can be undertaken to mitigate congestion on New North Road, Ruru Street, Korari Street, Flower Street, Nikau Street, Ngahura Street, Porters Avenue, Mt Eden Road, Normanby Road, Boston Road, Nugent Street, and the road network in general in this area including: (b) Which routes are to be used by construction trucks to remove spoil from the construction yard including how the use of these routes by these vehicles will be managed to mitigate congestion; (c) Which routes are to be used by construction related traffic (especially trucks) to deliver construction materials and other related goods and services to the construction yard including how the use of these routes by these vehicles will be managed to mitigate congestion; (d) The grade separation of Porters Ave so that it is undertaken at a time when vehicles, pedestrians, and cyclists can be managed and accommodated on Dominion Road, Mt Eden Road and Normanby Road to an extent which mitigates where practicable, delays to travel journeys from congestion on these roads resulting from City Rail Link construction works; (e) The grade separation of Normanby Road so that it is undertaken at a time when vehicles, pedestrians, and cyclists can be managed and accommodated on Dominion Road, Mt Eden Road and Porters Avenue, to an extent which mitigates where practicable, delays to travel journeys from congestion on these roads resulting from City Rail Link construction works; (f) Any reduction in the number of fully operational traffic lanes associated with the closure of Porters Avenue and Normanby Road, and the reduction in the number of vehicle lanes on the Mount Eden Road bridge, is to be undertaken on only one of these three routes at a time; (g) The timing and sequencing of temporary road lane reductions and / or closures at the Symonds Street / New North Road / Mt Eden Road intersection , Ruru Street, Korari Street, Flower Street, Nikau Street, Ngahura Street, Porters Avenue, Mt Eden Road in the vicinity of the bridge over the rail line, Normanby Road, Boston Road, Nugent Street in the vicinity of the rail crossing, and the alternative routes and temporary detours to be used, including how these have been selected and will be managed to, where practicable, mitigate congestion on the surrounding road network; (h) How disruption to the use of property located immediately adjacent to the surface designation with access onto New North Road, Ruru Street, Korari Street, Flower

City Rail Link Notice of Requirement

Page 34


Condition Number

Condition

NoR Applies to

Street, Nikau Street, Ngahura Street, Porters Avenue, Mt Eden Road, Normanby Road, Boston Road, Nugent Street will be mitigated through: (i) Providing pedestrian and cycle access to private property at all times; (ii) Providing local vehicle access and pedestrian access at all times to properties located along Flower Street (between Nikau Street and Shaddock Street) and Shaddock Street (between Flower Street and its dead end to the east), which are not located within the designation footprint, except for temporary closures where landowners and occupiers have been communicated and consulted with in reasonable advance of the closure; (iii) Retaining local vehicle and pedestrian access to properties located outside the designation footprint along Haultain Street, Fenton Street, Porters Avenue, Ngahura Street, Ruru Street, Korari Street, Flower Street, Nikau Street, Mt Eden Road, Boston Road, Nugent Street, and Normanby Road at all times except for temporary closures where landowners and occupiers have been communicated and consulted with in reasonable advance of the closure; and (iv) Full accessibility to those parts of Porters Avenue not affected by, but in the vicinity of, the construction works; and (i) How disruption to the use of Mt Eden Rail Station will be mitigated through providing, where practicable, access during construction works associated with the replacement of Mt Eden Road Bridge. Noise and Vibration Project Standards - Construction Noise 31.1Construction noise shall comply with the following Project Standards (unless otherwise provided for in a SSCNMP which is approved under Condition 37, 39 or 40):

1 31

4 5 6

Receiver Type

Monday to Saturday 0700 – 2200

Sundays and Public Holidays 0700 – 2200

Occupied commercial and industrial buildings (including offices)

75 dB LAeq

75 dB LAeq

Sensitive Noise and Vibration Receivers (excluding offices)

75 dB LAeq 90 dB LAFmax

65 dB LAeq 80 dB LAFmax2

Early Childhood Education Centres (whilst occupied during normal opening hours) Bear Park Early Childhood Education Centre at 32 Akiraho Street (whilst occupied during normal opening hours)

At all other times

1

2200 – 0700

75 dB LAeq

60 dB LAeq 75 dB LAFmax

35 dB LAeq in sleeping areas

35 dB LAeq in sleeping areas 65 dB LAeq in outdoor playing areas

City Rail Link Notice of Requirement

Page 35


Condition Number

Condition

NoR Applies to

Notes: 1. 60dB LAeq for NoR 5 and NoR 6; and 2. 75dB LAFmax for NoR 5 and NoR 6. 31.2Construction noise shall be measured and assessed in accordance with the provisions of NZS 6803:1999 Project Standards - Blasting Overpressure and Vibration For the avoidance of doubt this condition only applies to NoR 6 where blasting is required.

32

6

32.1Prior to commencement of production blasts (ie. blasting that is undertaken as part of the construction process), trial blasts (ie. preliminary blasts that occur prior to production blasts for the purpose of data acquisition), shall be undertaken to demonstrate how adverse effects will be managed and how compliance with Conditions 32.2, 32.3 and 32.4 will be achieved in production blasting. Trial blasts will determine site-specific attenuation characteristics, air overpressure levels and maximum instantaneous charge weight (MIC) thresholds. Outcomes shall be documented in a Trial Blasting Report. This Trial Blasting Report shall be used for subsequent design of production blasting. 32.2Air overpressure from the blast events shall not exceed 120 dB L Zpeak at the facade of any occupied building measures and assessed in accordance with the provisions of the Australian Standard AS 2187.2-2006 Explosives – Storage and use – Use of explosives. 32.3Air overpressure from blast events shall not exceed 133dB LZpeak at the facade of any unoccupied building measured and assessed in accordance with the provisions of Australian Standard AS 2187.2-2006 Explosives – Storage and use – Use of explosives. 32.4Unless a SSCNVMP is approved under Conditions 38, 39 or 40 which includes an alternative blasting vibration standard: (a) Vibration from blast events shall not exceed 10mm/s PPV for 95% of blast events and 15mm/s for 100% blast events when measured at the foundation of any building that will be occupied during the blast event when measured and assessed in accordance with the provisions of DIN 4150-3:1999. (b) Vibration from blast events shall not in any case exceed the limits specified in Condition 33 when measured at the foundation of any building when measured and assessed in accordance with the provisions of Condition 33. 32.5 For the purposes of 32.2 and 32.3, a building is deemed to be occupied if there are persons inside only during the blast event (ie. if the occupants of a dwelling are out (eg. at work) during the blast event then the dwelling is deemed to be unoccupied). 32.6 Blasts must be performed at set times during the daytime only, between 9am and 5pm, Monday to Saturday only. 32.7 Comprehensive vibration and air overpressure level predictions must be performed prior to every blast event. 32.8 Blasting shall not be carried out where overpressure levels are predicted to be above the Project Standards in 32.1 and 32.2 at any building. Blasting shall not be carried out where vibration levels are predicted to be above the project standards in Condition 32.4 at any building. 32.9 These criteria may be varied only by a Site Specific Construction Noise Management Plan (SSCNMP) that has been approved under Condition 37.

33

1

Project Standards - Construction Vibration

2

33.1Construction vibration (including blasting) shall comply with the following Project Standards for building damage (unless otherwise provided for in a SSCVMP which is approved under Condition 38, 39 or 40)

4 5

City Rail Link Notice of Requirement

Page 36


Condition Number

Condition

NoR Applies to

6 Short-term (transient) vibration1

Type of Structure

PPV at the foundation at a frequency of

Long-term (continuous) vibration

PPV at horizontal plane of highest floor (mm/s)

PPV at horizontal plane of highest floor (mm/s)

1-10Hz (mm/s)

10-50 Hz (mm/s)

50-100 Hz (mm/s)

Commercial/ Industrial

20

20 – 40

40 – 50

40

10

Residential/ School

5

5 – 15

15 – 20

15

5

Historic or sensitive structures

3

3–8

8 – 10

8

2.5

Note: 1. Standard DIN 4150-3:1999 defines short-term (transient) vibration as “vibration which does not occur often enough to cause structural fatigue and which does not produce resonance in the structure being evaluated”. Long-term (continuous) vibration is defined as all other vibration types not covered by the short-term vibration definition. 33.2Construction vibration (including blasting) shall be measured in accordance with German Standard DIN 4150-3:1999. Project Standards - Construction Vibration (Amenity) 34.1Between the hours of 10pm and 7am vibration generated by construction activities (excluding blasting) shall not exceed: (a) a Peak Particle Velocity (PPV) of 0.3mm/s when measured at any part of the floor of any bedroom; (b) a noise level of 35 dB LAeq(15min) when measured in any bedroom. 1 2 34

35

4 5 6

34.2 Between the hours of 7am and 10pm vibration generated by construction activities (excluding blasting) shall not exceed: (a) A Peak Particle Velocity (PPV) of 1mm/s as measured on the floor of the receiving room for residentially occupied habitable rooms, bedrooms in temporary accommodation and medical facilities; and (b) A Peak Particle Velocity (PPV) of 2mm/s as measured on the floor of the receiving room for retail and office spaces (including work areas and meeting rooms); 34.3 The limits in 34.1 and 34.2 shall only be investigated and applied upon the receipt of a complaint from any building occupant. They shall not be applied where there is no concern from the occupant of the building. 34.4 Where the limits in 34.1 and 34.2 are found (through measurement) to be exceeded then a SSCVMP shall be prepared for that receiver (Condition 38). Project Standards – MediaWorks 35.1 The noise and vibration limits set out in Conditions 35.2 and 35.3 shall apply only during Sensitive Times. For the purposes of MediaWorks, Sensitive Times are defined as follows: (a) During scheduled live broadcasting

City Rail Link Notice of Requirement

Page 37


Condition Number

NoR Applies to

Condition

(b) During emergency/breaking news live broadcasting (c) During scheduled recording sessions If the limits are complied with in Studio 1, the noise and vibration levels in all other Studios will be acceptable. For the avoidance of doubt, (a)-(c) above include sound checks as well as actual broadcast/recording time. 35.2 Noise Limits – Studios The noise level (whether air borne or reradiated from ground vibration) from all construction sources as received inside Studio 1 shall not exceed 30dB LAeq (5 min) and 33 dB LAeq (1 sec). These limits apply to the construction component of the total noise. However for up to two periods of tunnelling, each no more than 15 consecutive days, the noise limits may be up to 5 decibels higher (ie. 35dB LAeq (5 min) and 38 dB LAeq (1 sec)) during Sensitive Times, other than during the Live Broadcasting Periods as follows: (a) Weekdays: 0600-0900 hours 1200-1230 hours 1730-1930 hours 2230-2330 hours (b) Christmas holiday season (Saturday prior to Christmas Day to Sunday following New Years Day inclusive) and weekends: 1730-1900 hours The Requiring Authority must give MediaWorks at least 12 days notice of the commencement of each such period. 35.2A Rockbreaking shall not be used for tunnel excavation within 100m of the MediaWorks site during Sensitive Times unless compliance with the noise limits in Condition 35.2 can be demonstrated in accordance with the methodology set out in the SSCNVMP. 35.3 Vibration Limits – Studios For the protection of studio camera image quality, the construction vibration level (including blasting) as received inside Studio 1 shall not exceed 0.1mm/s PPV. This limit may be elevated by agreement of both the Requiring Authority and MediaWorks where image quality is found to be unaffected. 35.4 Noise level measurements inside Studio 1 shall be undertaken at a position that is representative to the level received within 2m from, and at a similar height to, the microphone of the main presenter(s). 35.4 Noise level measurements inside Studio 1 shall be undertaken with all doors to the studio closed. 35.5 For the protection of amenity, the construction vibration level as received in inside office areas, meeting rooms and technical suits shall not exceed 1mm/s PPV (as received on the floor of the receiving room) when those spaces are in use. 35.6 For the prevention of building damage, the construction vibration level shall not exceed the limits in Condition 33 at all times. 35.7 For the protection of sensitive equipment, the construction vibration (including blasting) level shall not exceed 200mg (2m/s2) between 5-500Hz. Levels are to be measured on the floor supporting the Sensitive Equipment. 35.8 All attended noise and vibration measurements shall be undertaken by a suitably qualified and experienced expert. 35.9 For the avoidance of doubt, the MediaWorks conditions (Conditions 35, 40 and 66)

City Rail Link Notice of Requirement

Page 38


Condition Number

Condition

NoR Applies to

only apply for so long as television, radio and/or interactive media facilities broadcast from the MediaWorks site. 35.10 Blasting shall not occur during MediaWorks Sensitive Times (as defined in Condition 35.1). Blasting shall occur at times to be agreed with MediaWorks and as documented in the SSCNVMP. Construction Noise and Vibration DWP For the avoidance of doubt, this condition is applicable to the management of construction noise and vibration on all receivers, including sensitive and notable receivers. 36.1A Construction Noise and Vibration DWP shall be prepared and implemented. The objective of the Construction Noise and Vibration DWP is to provide for the development and implementation of identified best practicable option to avoid, remedy or mitigate the adverse effects on receivers of noise and vibration resulting from construction. 36.2The Construction Noise and Vibration DWP shall: (a) Adopt the noise and vibration standards for construction set out in Conditions 31, 32, 33 and 34 of these designations; (b) Be generally consistent with the draft Construction Noise and Vibration management plan submitted as part of the Notice of Requirement documentation (dated 23 August 2013); and (c) Identify methods to achieve best practicable option for mitigating adverse effects.

1 2 36

4 5 6

36.3To achieve this objective, the Construction Noise and Vibration DWP shall include: (a) The roles and responsibilities of the noise and vibration personnel in the contractor team with regard to managing and monitoring adverse noise and vibration effects; (b) That piling and road cutting will be restricted to between the hours of 7am to 7pm, Monday to Saturday; (c) Construction machinery and equipment to be used and their operating noise and vibration levels; (d) Identification of construction activities that are likely to create adverse noise and vibration effects, the location of these in the construction site areas, and the distance to comply with the Project Criteria in Conditions 31, 32, 33 and 34; (e) The timing of construction activities that are likely to create an adverse noise and vibration effect; (f) The location of sensitive noise and vibration receivers; (g) A record of communication and consultation with sensitive noise and vibration receivers. The record must include a clear explanation of where any comments from sensitive receivers have not been incorporated in the Construction Noise and Vibration DWP, and the reasons why not. This information must be included in the Construction Noise and Vibration DWP provided to both the Independent Peer Review Panel and Auckland Council as part of the Outline Plan process specified in Condition 11; (h) Specific measures to address the concerns raised by those sensitive receivers; (i) Specific training procedures for construction personnel including: (i) The project noise and vibration performance standards for construction (conditions 31, 32, 33 and 34); (ii) Information about noise and vibration sources within the construction area and the locations of sensitive noise and vibration receivers; and (iii) Construction machinery operation instructions relating to mitigating noise and

City Rail Link Notice of Requirement

Page 39


Condition Number

NoR Applies to

Condition

vibration; (j) Methods and measures to mitigate adverse noise and vibration effects including, but not limited to, structural mitigation such as barriers and enclosures, the scheduling of high noise and vibration construction, use of low noise and vibration machinery, temporary relocation of affected receivers or any other measures or offer agreed to by the Requiring Authority and the affected receiver; (k) The proposed methods for monitoring construction noise and vibration to be undertaken by a suitably qualified person for the duration of construction works including: (i) Updating the predicted noise and vibration contours based on the final design and construction activities; (ii) Confirm which buildings are to be subject to a pre and post building condition survey in accordance with Condition 46. This includes consideration of those buildings in Appendix One and Two to these conditions; (iii) The timing and location for monitoring of buildings during construction is required (Note that the flow charts contained in Appendices B and C of Appendix J of the technical noise and vibration report provided as part of the Notice of Requirement should be used as a guide); (iv) Identifying appropriate monitoring locations for receivers of construction noise and vibration; (v) Procedures for working with the Communication and Consultation Manager to respond to complaints received on construction noise and vibration, including methods to monitor and identify noise and vibration sources; (vi) Procedures for monitoring construction noise and vibration and reporting to the Auckland Council Consent Monitoring officer; and (vii) Procedures for how works will be undertaken should they be required as a result of the building condition surveys; (l) Cross references to the specific sections in the Communication and Consultation Plan which detail how landowners and occupiers are to be communicated with around noise and vibration effects. Site Specific Construction Noise Management Plan (SSCNMP)

1 37

2 4 5 6

For the avoidance of doubt, this condition does not apply to MediaWorks. 37.1The objective of a SSCNMP is to detail the best practicable option to avoid, remedy or mitigate adverse effects on a receiver resulting from construction noise that does not comply with the Project Noise Standards. 37.2Further to the Construction Noise and Vibration DWP in Condition 36, a SSCNMP shall be prepared for any receiver or activity for which air overpressure is either predicted or measured to exceed the limits in Condition 32, or where construction noise is either predicted or measured to exceed the Project Noise Standards in Condition 31, except where the exceedance of the standards in Condition 31 is less than 5 decibels and does not exceed : (a) 0700-2200: 1 period of up to 2 consecutive weeks in any 2 months (b) 2200-0700: 1 period of up to 2 consecutive nights in any 10 days 37.3For predicted exceedances of less than 5 decibels (refer 37.2) monitoring shall be undertaken to confirm the actual noise levels. If exceedance is shown to be more than 5 decibels, or the period exceeds those detailed, then a SSCNMP will be prepared. 37.4 In addition to the SSCNMPs prepared in accordance with Condition 37.2, and notwithstanding Condition 37.1, the Requiring Authority shall prepare SSCNMPs

City Rail Link Notice of Requirement

Page 40


Condition Number

NoR Applies to

Condition

specifying the best practicable option for management, methods and measures to mitigate all noise effects for the properties located at: (a) 1 Queen Street (Lot 1 DP 165403); (b) 21 Queen Street (Lot 1 DP 67723); (c) 29 Customs Street West (Lot 7 DP 77037) (d) 188 Quay Street (Lot 5 DP 63972 and Lot 1 DP 78340); and (e) 23-29 Albert Street (Lot 1 DP 116724). 37.4 SSCNMPs will identify: (a) The extent to which noise may exceed the Project Noise Standards in Condition 31 or the overpressure limits in Condition 32; (b) The timing and duration of any exceedance; (c) Details of the type of activity causing any exceedance; (d) The summary of the communication and consultation undertaken with the receiver. The summary must include a clear explanation of where any comments have not been incorporated, and the reasons why not. This information must be included in the SSCNMP provided to both the Independent Peer Review Panel and Auckland Council as part of the Outline Plan process specified in Condition 11; (e) The methods and measures to mitigate noise effects, including but not limited to, potential to offer temporary relocation of affected receivers, alternative ventilation, faรงade sound insulation improvements, building condition surveys in the case of overpressure generated by blast events, or other offers made by the Requiring Authority and whether these have been agreed to by the affected receiver; (f) The reasons why the management and mitigation measures and methods reflect best practicable option. 37.6 The SSCNMP shall be submitted for the review of Auckland Council as part of the Outline Plan. The works shall then be undertaken in accordance with the SSCNMP confirmed by the Requiring Authority as part of the Outline Plan. Site Specific Construction Vibration Management Plan (SSCVMP) For the avoidance of doubt, this condition does not apply to MediaWorks. 38.1The objective of a SSCVMP is to detail the best practicable option to avoid, remedy or mitigate adverse effects on a receiver resulting from vibration that does not comply with the Project Vibration Standards. 38.2Further to the Construction Noise and Vibration DWP in Condition 36, a SSCVMP shall be prepared: 1 2 38

4 5 6

(a) For any unoccupied building, structure or infrastructure for which construction vibration is either predicted or measured to exceed the Project Vibration Standards in Condition 33; (b) Where a complaint or concern is raised and the vibration level exceeds the amenity levels of Condition 34.2(a) and 34.2(b); (c) In response to other concerns or complaints where required (refer Condition 17).; (d) For the properties listed in Condition 37.4. 38.3Where the amenity limits in Conditions 34.2(a) and 34.2(b) are exceeded: (a) Best practicable management of vibration must be applied; and (b) The vibration activity shall be scheduled to avoid disturbance. If this is not practicable then reasonable respite periods shall be provided to reduce vibration exposure.

City Rail Link Notice of Requirement

Page 41


Condition Number

NoR Applies to

Condition

38.4The limits in condition 33 may be relaxed by a SSCVMP but only for a building, structure or infrastructure that has been assessed by a suitably qualified and experienced structural engineer and where it has been deemed to be capable of withstanding higher vibration levels without sustaining building or structural damage, and where appropriate vibration and building condition monitoring regimes are in place. 38.5SSCVMPs will identify: (a) The timing and duration of any exceedance; (b) Details of the type of activity giving rise to any exceedance; (c) Site Specific vibration criteria that addresses the issue(s) of concern (i.e. building damage, amenity and sensitive equipment). Site Specific criteria shall be determined by a suitably qualified independent vibration expert; (d) The summary of the communication and consultation undertaken with the receiver. The summary must include a clear explanation of where any comments have not been incorporated, and the reasons why not. This information must be included in the SSCVMP provided to both the Independent Peer Review Panel and Auckland Council as part of the Outline Plan process specified in Condition 11; (e) The methods and measures to mitigate vibration effects, including but not limited to, investigating alternative low-vibration construction methods, undertaking highvibration works outside sensitive times, vibration barriers, building condition surveys, potential to offer temporary relocation of affected receivers, or other offers made by the Requiring Authority and agreed to by the affected receiver; (f) The reasons why the management and mitigation measures and methods reflect best practicable option. 38.6The SSCVMP shall be submitted for the review of Auckland Council. The works shall then be undertaken in accordance with the SSCVMP confirmed by the Requiring Authority as part of the Outline Plan. Notable Receivers Notable Noise and Vibration Receivers For the avoidance of doubt, Conditions 39.5 and 39.6 do not apply to MediaWorks. 39.1Further to Condition 36, the Requiring Authority and its contractor, in conjunction with a suitably qualified expert, shall work collaboratively with each notable receiver during the preparation of a SSCNVMP to confirm the extent and management of adverse effects on each Notable Receiver.

39

1 2 4 5 6

39.2In addition to the Construction Noise and Vibration DWP, a SSCNVMP shall be prepared for each identified Notable Receiver. The objective of the SSCNVMP is to detail the best practicable option to avoid, remedy or mitigate adverse noise and vibration effects on each Notable Receiver. 39.3The Requiring Authority shall consult with the notable receiver throughout the duration of construction and update the SSCNVMP as required to achieve the objective in 39.2. 39.4The SSCNVMP shall include: (a) The level at which noise and vibration effects on the notable receiver will unreasonably interfere with its operation. This will enable development of the site specific criteria. In the case of MediaWorks this is set out in Condition 40; (b) Construction activities and equipment which are likely to create adverse noise and vibration effects and the location and timing of these in relation to the notable receiver; (c) The methods and measures associated with the worksite including, but not limited

City Rail Link Notice of Requirement

Page 42


Condition Number

NoR Applies to

Condition

to, structural mitigation such as barriers and enclosures, use of low noise and vibration machinery and the scheduling of high noise and vibration construction; (d) The methods and measures associated with the notable receiver building or operation including, but not limited to, potential for isolation of sensitive areas and equipment, dampening of reradiating surfaces and temporary relocation of affected receivers that are proposed to minimise adverse noise and vibration effects on the notable receiver; (e) Details about the methods to be adopted by the Requiring Authority to minimise construction noise and vibration effects on the notable receiver and the anticipated effectiveness of those methods; (f) A summary of the communication and consultation undertaken with the notable receiver. The summary must include a clear explanation of where any comments have not been incorporated, and the reasons why not; (g) Offers made by the Requiring Authority to the notable receiver to mitigate effects and the response by the operators, such as relocation, and whether those offers were accepted or not by the notable receiver; 39.5If the parties cannot agree on any of the matters above they shall each appoint a suitably qualified and independent expert, who shall jointly appoint an independent and suitably qualified third expert who shall certify the following matters to be included in the SSCNVMP: (a) The level at which noise and vibration effects on the notable receiver unreasonably interfere with its operation (the certified noise and vibration limit); (b) The mitigation methods and measures within the worksite (at source) including, but not limited to, structural mitigation such as barriers and enclosures, use of low noise and vibration machinery and the scheduling of high noise and vibration construction; (c) The mitigation methods and measures at the notable receiver including but not limited to: isolation of sensitive areas and equipment; dampening of reradiating surfaces; any response to such offers; and temporary relocation of affected receivers; (d) Whether or not the mitigation methods and measures reflect best practicable management; and (e) Whether or not the residual effects are likely to cause significant disruption to the activities of the notable receiver. 39.6Following the above process the SSCNVMP shall be submitted for the review of Auckland Council as part of the Outline Plan. For the avoidance of doubt, the Requiring Authority shall not be entitled to make any changes to the SSCNVMP through the Outline Plan process following any agreement reached with the notable receiver and/or through the above certification process without the consent of the notable receiver. The works shall then be undertaken in accordance with the SSCNVMP confirmed by the Requiring Authority as part of the Outline Plan process.

40

6

Construction Noise and Vibration Management Plan – Mediaworks Further to Condition 36, a SSCNVMP shall be prepared for MediaWorks implementing the project standards in Condition 35. 40.1 The MediaWorks SSCNVMP shall identify high noise or vibration plant and machinery, and list the relevant items that require testing in accordance with Condition 40.4 and 40.8. 40.2 Prior to any demolition or construction commencing, the Requiring Authority shall undertake a noise survey to determine the Transmission Loss (TL) performance of the MediaWorks building envelope. This testing shall only be undertaken outside of

City Rail Link Notice of Requirement

Page 43


Condition Number

NoR Applies to

Condition

Sensitive Times. 40.3 Prior to any demolition or construction commencing, the Requiring Authority shall undertake a vibration survey to determine the transfer function of the MediaWorks building structure from ground vibration outside the building to reradiated noise in Studio 1. This testing shall only be undertaken outside of Sensitive Times. 40.4 All high noise plant and machinery to be used at a location where it is predicted to generate noise levels in excess of 3 dB below the limits specified in Condition 35.2 shall be tested prior to use, to determine its Sound Power Level (L w) at a sufficient distance from the MediaWorks building to ensure compliance. These measured Lws shall be used to predict the noise level at the MediaWorks building faรงade(s) from proposed construction scenarios. The faรงade TL (refer Condition 40.2) shall then be applied to predict the noise levels in the relevant rooms. 40.5 All high noise plant and machinery may not be used until Condition 40.4 is satisfied, taking into account the cumulative noise levels from active sources on the site. 40.6 The Requiring Authority and its contractor, in conjunction with a suitably qualified expert, shall work collaboratively with MediaWorks during the preparation of a SSCNVMP to confirm the extent and management of adverse effects on MediaWorks. 40.7 The SSCNVMP shall set out the requirements for monitoring, the number of monitors, the instrument location, any adjustments necessary if a proxy position is required and any other procedures or requirements that are necessary. The data shall be available in real time to the Requiring Authority, Auckland Council and MediaWorks. 40.8 Prior to the use of any high vibration equipment to be used at a location where it is predicted to generate vibration levels greater than 75% of the PPV vibration limits in Condition 35.3, 35.6, 35.7 and 35.8, or reradiated noise within 3 decibels of the limits in Condition 35.2, the Requiring Authority shall undertake vibration measurements at a sufficient distance from the MediaWorks building to ensure compliance, applying the transfer function required by Condition 40.3 to assess reradiated noise. These measurements shall be used to determine minimum set-back distances from the building to avoid potential exceedances of the vibration limits in Conditions 35.2, 35.3, 35.67, 35.7 and 35.8. The results of the testing and the outcomes affecting construction operations shall be set out in the SSCNVMP. 40.9 The noise and vibration levels from construction shall be monitored to determine compliance with conditions 35.2, 35.3, 35.6, 35.7 35.8 and 35.89 continuously by automated noise and vibration monitors located at positions that will represent the noise and vibration level in the relevant spaces and for the relevant noise and vibration limits. The SSCNVMP shall set out the requirements for monitoring, the instrument location, any adjustments necessary if a proxy position is required and any other procedures or requirements that are necessary including methods to exclude extraneous sources. The data shall be available in real time to the Requiring Authority, Auckland Council and MediaWorks. 40.10 Monitoring to determine compliance or otherwise with Condition 35.67 relating to office amenity shall only be undertaken in response to complaints from MediaWorks. The measurements must be attended by a suitably qualified person. 40.11 The SSCNVMP shall set out corrective action measures that must be adopted in situations where any of the noise and vibration limits in Conditions 35.2, 35.3, 35.6, 35.7, and 35.8 are exceeded and where the noise and/or vibration levels are unacceptable to MediaWorks. The corrective action measures must include the following: (a) Immediate cessation of the work(s) that is giving rise to the exceedance; (b) A procedure to require the implementation of whatever measures are necessary to reduce the noise or vibration levels;

City Rail Link Notice of Requirement

Page 44


Condition Number

Condition

NoR Applies to

(c) A monitoring procedure to determine compliance (once the remediation works are complete); (d) A requirement to ensure that the work(s) responsible for the exceedance are not recommenced during Sensitive Times; (e) A complaints procedure that is capable of effecting the immediate cessation of works including making a point of contact directly available 24 hours, seven days a week. 40.12

40.13

If there is a disagreement between the Requiring Authority and MediaWorks as to the content of the SSCNVMP, they shall each appoint a suitably qualified and independent expert, who shall jointly appoint an independent and suitably qualified third expert who shall certify the matters set out in Condition 40.11 and any other matters in dispute in the SSCNVMP. Following the above process the SSCNVMP shall be submitted for the review of Auckland Council as part of the Outline Plan. For the avoidance of doubt, the Requiring Authority shall not be entitled to make any changes to the SSCNVMP through the Outline Plan process following any agreement reached with MediaWorks and/or through the above certification process without the consent of MediaWorks. The works shall then be undertaken in accordance with the SSCNVMP confirmed by the Requiring Authority as part of the Outline Plan process.

Built Heritage/Archaeology Historic Character – Built Heritage 41.1The Historic Character DWP shall be prepared to manage the adverse effects on built heritage and archaeology that may result from associated works prior to, during, and after the construction of the City Rail Link or any part of it.

1 41

2 4 5 6

41.2The objective of the Built Heritage section is to avoid, remedy or mitigate adverse effects on built heritage as far as reasonably practicable. To achieve the above objective, the following shall, as a minimum, be included in the built heritage section of the Historic Character DWP: (a) Preparation of a Building Record and Salvage Strategy that outlines a suitable set of procedures for the removal, storage and for later refitting and reuse of elements of heritage buildings and/or structures identified for demolition including the Griffiths Building, Beresford Toilets, Bluestone Toilets, and the rear annex to the building at 223-227 Symonds Street. (b) The proposed methods for monitoring building damage that is to be undertaken by a suitably qualified person for the duration of construction works. This includes confirming which Built Heritage buildings and structures are to be subject to a pre and post building condition survey through: (i) Using the updated predicted vibration contours undertaken in Condition 36; (ii) Reviewing those buildings in Appendix 2 to these conditions in accordance with Condition 46.1; (iii) Reviewing buildings within the designation footprint (including above sub-strata designation) or located in close proximity to identify buildings which have been recognised as having heritage value as a result of scheduling under the Historic Places Act 1993 or in the Auckland Unitary Plan. (c) Identification and methodology for recording of Built Heritage directly affected by the construction, or associated pre- and post-construction works (i.e. within the surface designation footprint), which cannot be retained and / or adaptively re-used / partially retained. For the avoidance of doubt, the following buildings and structures may be demolished:

City Rail Link Notice of Requirement

Page 45


Condition Number

Condition

NoR Applies to

(i) Bluestone Toilets (SCDP Category B); (ii) Beresford Toilets; (iii) Rear annex to building at 229-231 Symonds Street; and (iv) Griffiths Building. (d) Identification and methodology for recording Built Heritage directly affected by the construction, or associated pre- and post-construction, which are to be: (i) Adaptively reused; (ii) Partially retained in design and construction; or (iii) Built heritage elements have been integrated into other elements of the City Rail. (iv) In particular, the Requiring Authority shall explore the adaptive re-use of the buildings at 51-53 Victoria Street West (known as Martha’s Corner building) with complete demolition only considered as a last resort. As guidance, an appropriate level of adaptive re-use could include retention of the façade on all street frontages or the utilisation and incorporation of elements of the building into the design: (e) How Built Heritage Buildings and Structures will be protected during construction through the use of screening or other protective measures to mitigate adverse construction effects; (f) How mitigation or rectification of damage to Built Heritage Buildings and Structures will be addressed; and (g) Cross references to the specific sections in the Communication and Consultation Plan which detail how the Auckland Council Heritage Department, the New Zealand Historic Places Trust, and mana whenua (see condition 15) are consulted, and the communication with the general public on the management of the adverse effects relating to Built Heritage. Historic Character - Archaeology 42.1A Historic Character DWP shall be prepared to manage the adverse effects on built heritage and archaeology that may result during construction of the City Rail Link or any part of it.

42

1 4 5 6

42.2The objective of the Archaeology section of the Historic Character DWP is to avoid, remedy or mitigate adverse effects on archaeological remains during construction, as far as reasonably practicable. 42.3To achieve the above objective the following matters shall be included in the Archaeology section of the Historic Character DWP: (a) Constructor roles and responsibilities, stand-down periods and reporting requirements are to be clearly identified; (b) How procedures for archaeological investigations and monitoring of preliminary earthworks are to be implemented in areas where there is potential for archaeological remains to be discovered; (c) Procedures for the discovery of, including accidental discovery of archaeological remains including: (i) The ceasing of all physical construction works in the immediate vicinity of the discovery; (ii) Practices for dealing with the uncovering of cultural or archaeological remains and the parties to be notified (including, but not limited to, appropriate iwi authorities, the Auckland Council Consents Monitoring officer, the New Zealand

City Rail Link Notice of Requirement

Page 46


Condition Number

Condition

NoR Applies to

Historic Places Trust, and the New Zealand Police (if koiwi (human skeletal remains) are discovered); (iii) Procedures to be undertaken before physical works in the area of discovery can start again, including any iwi protocols, recording of sites and material, recovery of any artefacts, and consultation to be undertaken with iwi, Auckland Council Consent Monitoring officer and Heritage Unit, and with the New Zealand Historic Places Trust; and (iv) Procedures for recording any archaeological remains or evidence before it is modified or destroyed, including opportunities for the conservation and preservation of artefacts and ecofacts (biological material) that are discovered. Consideration shall be given to the incorporation of in-situ material or artefacts into the design of stations and / or public places associated with the City Rail Link project. Consideration shall also be given to the provision for ‘post-excavation’ assessment analysis and publication of material within 24 months of completion of construction. (v) Provision for ‘post-excavation’ archiving, assessment and analysis of the archaeological records and materials; publication of results of that work within 24 months of completion of construction assessment analysis and publication of material within 24 months of completion of construction. (d) Training procedures for all contractors are to be undertaken in advance of construction, regarding the possible presence of cultural or archaeological sites or material, what these sites or material may look like, and the relevant provisions of the Historic Places Act 1993 if any sites or material are discovered; (e) Cross references to the specific sections in the Communication and Consultation Plan which details how the Auckland Council Heritage Department, the New Zealand Historic Places Trust, mana whenua (see condition 8) are consulted, and the communication with the general public on the management of the adverse effects relating to archaeology. Heritage Advisory Group and Composition

43

1

43.1The Requiring Authority must engage, at its expense, a panel of suitably qualified and experienced heritage experts to discharge the functions required by conditions 44 and 45. The Heritage Advisory Group will consist of three independent experts, whose members will not be directors or employees of the Requiring Authority, the New Zealand Historic Places Trust or the consent authority. The Heritage Advisory Group will comprise one nominee from the Requiring Authority, one nominee from the consent authority, and a third nominee appointed jointly by the Requiring Authority's and consent authority's nominees. 43.2Before establishing the Heritage Advisory Group the Requiring Authority shall seek the opinion of NZHPT on the appointment of the Heritage Advisory Group. 43.3The Heritage Advisory Group may determine its own processes and procedures for conducting its meetings and performing its functions as it sees fit, including methods for ensuring any disagreements between panel members are resolved, and must meet as necessary to fulfil its functions. All costs associated with the role and function of the Heritage Advisory Group and appropriate administrative support must be paid by the Requiring Authority. If any member of the Heritage Advisory Group is unable to continue in the role for whatever reason, then a replacement member must be appointed using the process set out in this condition.

44

1

Heritage Advisory Group Function

City Rail Link Notice of Requirement

Page 47


Condition Number

Condition

NoR Applies to

44.1The functions of the Heritage Advisory Group are to review the assessment of the alternatives and option selected by the Requiring Authority to manage the adverse effects on the heritage values of the Bluestone wall and the Martha’s Corner building. 44.2In relation to Bluestone Wall, the Heritage Advisory Group will: (a) Certify that the method selected by the Requiring Authority under Condition 45 will have the least impact on the heritage value of the Bluestone wall compared to other reasonably practicable methods; or (b) Prepare a report as to why the method selected by the Requiring Authority under Condition 45 will not have the least impact on the heritage value of the Bluestone wall and set out details as to an alternative recommended reasonably practicable method. 44.3In relation to Martha’s Corner, the Heritage Advisory Group will: (a) Certify that the heritage outcomes for Martha’s Corner adhere to the intent of Condition 41; or (b) Prepare a report as to why the method selected by the Requiring Authority will not adhere to the intent of Condition 41 and set out details as to the recommended reasonably practicable method. 44.4The Requiring Authority must provide Auckland Council with the Heritage Advisory Group’s certification or report, and if applicable the reasons the Requiring Authority has not selected the method recommended by the Heritage Advisory Group. Bluestone Wall Management Plan 45.1A Bluestone Wall Management Plan shall be prepared to manage the adverse effects on the heritage values of the Bluestone wall during the construction of the City Rail Link. 45.2The objective of this Plan is to minimise adverse effects on the heritage values of the Bluestone wall during the construction of the City Rail Link by adopting the best practicable option. 45

1

45.3To achieve the above objective, the following shall be included in the Bluestone Wall Management Plan: (a) Identification of the key heritage values of the wall; (b) Assessment of the alternative construction methods to ensure that construction of the City Rail Link has the least impact on the heritage value of the Bluestone wall, within the practical constraints of constructing the project; and (c) The option selected by the Requiring Authority. 45.4The Bluestone Management Plan shall be prepared in consultation with the NZHPT and the Heritage Advisory Group (set out in Condition 43).

Building Condition Surveys

1 46

2 4 5 6

Process for Building Condition Surveys 46.1Prior to construction, as a minimum those buildings listed in Appendix One and Appendix Two or identified pursuant to Condition 41.2(b) will be considered for a building condition survey. A building condition survey will be undertaken where it is assessed that there is potential for damage to buildings or structures arising from construction as determined by an independent suitably qualified person appointed by the Requiring Authority based on the criteria below unless the relevant industry criteria applied at the time or heightened building sensitivity or other inherent building vulnerability requires it. Building damage criteria will initially be assessed in accordance with Burland, J.B. (1997) “Assessment of Risk of Damage to Buildings due to Tunnelling and Excavation”.

City Rail Link Notice of Requirement

Page 48


Condition Number

Condition

NoR Applies to

Additional factors which may be considered in determining whether a building condition survey will be undertaken include: (a) Age of the building; (b) Construction types; (c) Foundation types; (d) General building condition; (e) Proximity to any excavation; (f) Whether the building is earthquake prone; and (g) Whether any basements are present in the building. 46.2Where prior to construction it is determined that a Building Condition Survey is required in accordance with Condition 46.1, or if measurements exceed the criteria in Condition 33: (a) The Requiring Authority shall employ a suitably qualified person to undertake the building condition surveys and that person shall be identified in the CEMP; (b) The Requiring Authority shall provide the building condition survey report to the relevant property owner within 15 working days of the survey being undertaken, and additionally it shall notify and provide the Auckland Council Consent Monitoring officer a copy of the completed survey report; (c) The Requiring Authority shall contact owners of those buildings and structures where a Building Condition Survey is to be undertaken to confirm the timing and methodology for undertaking a pre-construction condition assessment; (d) The Requiring Authority shall record all contact, correspondence and communication with owners and this shall be available on request for the Auckland Council Consent Monitoring Officer; (e) Should agreement from owners to enter property and undertake a condition assessment not be obtained within 3 months from first contact, then the Requiring Authority shall not be required under these designation conditions to undertake these assessments; (f) The Requiring Authority shall undertake a visual inspection during "active construction" if requested by the building owner where a pre-construction condition assessment has been undertaken. (g) The Requiring Authority shall develop a system of monitoring the condition of existing buildings which is commensurate with the type of the existing building and the proximity of the CRL works. The purpose of monitoring is to assess whether or not active construction is compromising the structural integrity of the building. (h) The Requiring Authority shall, during the Building Condition Survey, determine whether the building is classified as Commercial / Industrial / School or a Historic or sensitive structure in terms of Condition 33. 46.3 During construction: (a) The Requiring Authority shall implement procedures that will appropriately respond to the information received from the monitoring system. Where necessary this may include the temporary cessation of works in close proximity to the relevant building until such time as measures are implemented to avoid further damage or compromise of the structural integrity of the building. (b) Any damage to buildings or structures shall be recorded and repaired by the Requiring Authority and costs associated with the repair will met by the Requiring Authority.

City Rail Link Notice of Requirement

Page 49


Condition Number

Condition

NoR Applies to

46.4 Following construction: (a) The Requiring Authority shall, within 12 months of the commencement of operation of the City Rail Link, contact owners of those buildings and structures where a Building Condition Survey was undertaken to confirm the need for undertaking a post-construction condition assessment; (b) Where a post-construction building condition survey confirms that the building has deteriorated as the result of construction or operation works relating to the City Rail Link, the Requiring Authority shall, at its own cost, rectify the damage; and 46.5 Where the Requiring Authority is required to undertake building repairs in accordance with Conditions 46.3(b) or 46.4(b), such repairs shall be undertaken as soon as reasonably practicable and in consultation with the owner of the building. Urban Design Urban Design Principles 47.1 The objective of the Urban Design DWP is to enable the integration of the CRL’s permanent works into the surrounding landscape and urban design context. 47.2An Urban Design DWP shall be developed to ensure that the areas within the designation footprint used during the construction of the City Rail Link are to be restored and the permanent works associated with the CRL are developed in accordance with urban design principles. The following Principles from the Urban Design Framework submitted as part of the Notice of Requirement documents will be used to inform the Urban Design and Landscape Plan: (a) Mana Whenua Principles – see Condition 49; (b) Movement and Connections –

1 47

4 5 6

(i) Existing Networks - Structures of the CRL should not interrupt or adversely change the function of existing public open space, street networks and infrastructure. (ii) Entrance Location - Station entrances should be clearly identifiable and conveniently located in relation to existing and anticipated main pedestrian routes and destinations. (iii) Intuitive Orientation - The location and nature of structures resulting from the CRL (station entrances in particular) should facilitate intuitive orientation and support a legible street network. (iv) Way Finding - Coherent signage should be utilised to aid intuitive orientation and way finding. (v) Mode Integration - Spatial integration with bus stops as well as kiss and ride should be facilitated where possible without imposing on the quality of public realm. (vi) Bicycle Parking – Appropriate numbers of safe bicycle storage or parking should be provided in each station environment. (vii) Street Crossings - Safe pedestrian street crossings shall be provided in the immediate vicinity of station entrances to the extent practicable. The provision of level street crossings is preferable over any grade separated solutions. (viii) Footpaths – Footpaths surrounding stations need to be adequate to provide for pedestrians entering and exiting the stations. (ix) Grade separated rail crossings – Structures associated with grade separated rail crossings need to be carefully and sensitively designed and in accordance with crime prevention through environmental design principles to ensure appropriate

City Rail Link Notice of Requirement

Page 50


Condition Number

Condition

NoR Applies to

amenity and safety are retained or achieved. Measures to achieve this may include: a. b.

Utilising permeable balustrades on overbridges; Maximising the width of the footpath at grade in street reserves;

c.

Orientating any steps parallel to overbridges;

d.

Providing appropriate levels of lighting (in accordance with the Auckland Transport Street Lighting Policy (Appendix 1) for “Pathways in high risk, high brightness areas”); and e. Treatment of the sides of ramps and footpaths to enhance visual amenity. (x) Grade separated rail crossings – Permeable balustrades on overbridges should be required not only for crime prevention purposes but to enable views into the neighbouring sites. For clarity all balustrades comprised within Normanby Road grade separation works (as defined in condition 30.1(l) shall be permeable including without limitation the ramp to be constructed into the site at 32 Normanby Road. (c) Public Realm and Landscape – (i) Existing Streetscape – Structures of the CRL should be designed to respect and contribute positively to the form and function of existing public open space. (ii) Universal Access – Station environments should promote universal access (e.g. footpath ramps and smooth ground surfaces). (iii) Safe Environments – Structures resulting from the CRL should promote safe environments. The station entrances should release patrons into safe public spaces that are well lit at night, overlooked by other users (e.g. residents or workers) and have sufficiently wide and unobstructed footpaths. (iv) Reinstated Surfaces - The design and construction of reinstated streetscapes should be coherent with the wider area and/or recent public realm upgrades in the area. (v) Station Plazas - The design and construction of station plazas should be coherent with the wider area and/or recent public realm upgrades in the area. (vi) Public Art - Integration of art and design should foster local identity and character and reflect and/or interpret local characteristics including natural heritage and Mana Whenua cultural narratives, history, art and particular traits of the local community. (vii) Landscape Planting – Plant species used in station environments and/or as part of landscape plantings should consider the opportunity to acknowledge the area’s pre-human ecology as and where appropriate. This may include species which connect strongly with Mana Whenua cultural narratives. (viii) Entrances within the Road Reserve - Designs for station entrances within the road reserve should be designed to consider the impacts upon other modes of traffic, including the expected pedestrian patronage. (ix) Utility Structures - Above ground utility structures (e.g. vents, access services) should be designed to minimise any negative effect on public realm. Where possible these structures should be integrated with other buildings. (x) Where landscape planting is affected by construction works on private properties, replanting and/or mitigation of any such landscaping shall be undertaken in consultation with those landowners, and in recognition of wider mitigation works required for those properties (e.g. vehicle parking and access

City Rail Link Notice of Requirement

Page 51


Condition Number

Condition

NoR Applies to

requirements). 47.3The Urban Design DWP shall show how these principles have been used to guide and influence the design of permanent works associated with the CRL, and how the design has responded or otherwise to these principles and initiatives. 47.4The work to restore those areas within the designation footprint used during construction of the City Rail Link will occur as part of construction or within six months of the City Rail Link being operational. Auckland Council Urban Design Panel 47.5The Requiring Authority shall request the Auckland Council to refer the Urban Design DWP to the Auckland Urban Design Panel (or other equivalent entity (if any) at that time) and invite the Auckland Urban Design Panel to comment on: (a) The degree to which the Urban Design DWP has appropriately responded to the principles listed in 47.2 and 49.1; (b) The degree to which station plans have appropriately responded to the principles listed in Condition 54.1. 47.6As part of the Urban Design DWP submitted, the Requiring Authority shall: (a) Provide a record of feedback received from the Auckland Urban Design Panel (or equivalent entity at that time); (b) Provide detail of how the Urban Design DWP has responded to any feedback received from the Auckland Urban Design Panel (or equivalent entity at that time) and, where they have not, the reasons why; (c) Provide detail regarding the degree to which the community stakeholder, affected party and affected in proximity party feedback has been considered and where applicable incorporated into design. Where feedback has not been incorporated, the Requiring Authority shall provide comment as to reasons why the feedback has not been incorporated; (d) The information set out in (a), (b) and (c) above must be included in the Urban Design DWP submitted to both the independent peer reviewer and Auckland Council as part of the Outline Plan. Mitigation Planting Requirements

1 48

4 5 6

48.1The Urban Design DWP shall include any replacement planting proposed to mitigate the adverse effects of tree and vegetation removal from within the designation footprint. It is acknowledged that the mitigation of effects of tree and vegetation removal will be considered in response to the urban design principles of Condition 47. 48.2Any landscaping included under the Urban Design DWP shall be implemented in accordance with this plan within the first planting season following the City Rail Link being operational. If the weather in that planting season is unsuitable for planting, as determined by the Auckland Council Consent Monitoring officer (in consultation with the Auckland Council Parks Department), the landscaping shall instead be implemented at the first practicable opportunity thereafter. The next practicable opportunity shall be agreed by the Auckland Council Consent Monitoring officer. 48.3The landscaping will be maintained by the Requiring Authority for a period of 5 years for specimen trees and 3 years for all other landscape planting.

49

1

Engagement with Mana Whenua and the Mana Whenua Principles

4 5

49.1The Urban Design DWP shall include: (a) How mana whenua (see Condition 8) have been engaged with during its

City Rail Link Notice of Requirement

Page 52


Condition Number

NoR Applies to

6

Condition

development in relation to the implementation and interpretation of the Principles set out under Condition 47, and particularly in relation to the mana whenua principles set out below: (i) Mana / Rangatiratanga – As the original local authorities of Tamaki Makaurau, Iwi require high level Treaty based relationships with all key stakeholders including the Requiring Authority and Auckland Council which recognise their Tangata Whenua status in order to fulfil their roles as kaitiaki. Such partnership relationships can then inform engagement with AT / Council at all levels including direct involvement with design consortia. Relationships are required at governance and senior management levels. Such relationships are a precursor to actualising the other 6 principles. (ii) Whakapapa – Names and genealogical connections– reviving names revives mana through Iwi connections to specific ancestors and events / narratives associated with them. An Iwi inventory of names associated with a given site can be developed so that the most appropriate names are identified to develop design, interpretation and artistic responses. (iii) Tohu – Acknowledging the wider significant Iwi cultural land marks associated with the CRL route and their ability to inform the design of the station precincts, entrances and exits. In particular exploring opportunities to maximise view shafts to such tohu / landmarks as a way of both enhancing cultural landscape connections and as way finding / location devices. (iv) Taiao – Exploring opportunities to bring natural landscape elements back into urban /modified areas e.g. specific native trees, water / puna wai (springs) – promoting bird, insect and aquatic life to create meaningful urban eco systems which connect with former habitats, mahinga kai (food gathering areas) and living sites. (v) Mauri tu – Ensuring emphasis on maintaining or enhancing environmental health / life essence of the wider site – in particular focusing on the quality of wai / water (puna / springs), whenua / soil and air. In particular any puna or underground waterways encountered should be carefully treated with Mana Whenua assistance to ensure their mauri is respected and enhanced where possible. It is also important to minimise the disturbance to Papatuanuku through carefully planned ground works. (vi) Mahi toi – Harnessing the Creative dimension through drawing on names and local tohu to develop strategies to creatively re-inscribe iwi narratives into architecture, interior design, landscape, urban design and public art. (vii) Ahi kaa – need to explore opportunities to facilitate living presences for iwi / hapu to resume ahi-kaa and kaitiaki roles in and around the CRL route and new station precincts; and (b) A summary of the engagement with mana whenua (see Condition 15) and identification of where design has incorporated the mana whenua principles and other mana whenua aspirations. The summary must include a clear explanation of where any comments have not been incorporated and the reasons why not. The summary must be included in the Urban Design DWP submitted to both the Independent Peer Review Panel and Auckland Council as part of the Outline Plan. Specific Area Requirements: Britomart to Aotea Station

50

1

50.1For this designation the Urban Design DWP shall include how the following are to be restored following completion of the City Rail Link construction works: (a) Queen Elizabeth Square and lower Queen Street between Quay Street and Customs

City Rail Link Notice of Requirement

Page 53


Condition Number

Condition

NoR Applies to

Street; (b) Albert Street between Quay Street and Victoria Street; and (c) Albert Street between Victoria Street and Mayoral Drive including those part of Victoria and Wellesley Streets, the Council owned land on the southeast corner of Albert and Wellesley Streets which is to be used as a construction area, affected by surface construction works . 50.2The restoration plan for this designation shall demonstrate how street upgrades and public realm improvements have been considered when Albert Street and Mayoral Drive are reinstated. This should include as a minimum how the design and construction utilises material palettes, planting schedules and street furniture that are coherent with the surrounding streetscape character. Specific Area Requirements: Karangahape Station area

51

4

51.1For this designation the Urban Design DWP shall include restoration plans (showing how the following are to be restored following completion of the City Rail Link construction works): (a) Beresford Square and Street including where surface works have occurred within Pitt Street; and (b) Mercury Lane. 51.2The restoration plan for this designation shall demonstrate how street upgrades and public realm improvements have been considered when Beresford Street, Pitt Street and Mercury Lane are reinstated. This should include as a minimum: (a) How the design and construction utilises material palettes, planting schedules and street furniture that are coherent with the surrounding streetscape character. (b) Methods for street upgrades and public realm improvements.

52

5

Specific Area Requirements: Newton Station area 52.1For this designation the Urban Design DWP shall include restoration plans (showing how the following are to be restored following completion of the City Rail Link construction works) for those areas used for surface construction works within the designation footprint, including the construction yard located on the northeast corner of Mt Eden Road and Symonds Street. Specific Area Requirements: North Auckland Line area 53.1For this designation the Urban Design DWP shall include the following: (a) Restoration Plans showing how the worksite area will be maintained during the construction period.

53

6

(b) Restoration Plans showing how the following are to be restored after construction completion: (i) The replacement of Mt Eden Road Bridge; (ii) The area used for the grade separation of Porters Avenue; (iii) The area used for the grade separation of Normanby Road; and (iv) The replacement of the pedestrian connection, to be provided over the railway, between Ngahura Street and Fenton Street, including a connection to the Mount Eden Station.

54

1

Station Plan Requirements

4 5

54.1The Urban Design DWP shall include a Station Plan/s (report and design plan/s as required) and include the following: (a) The design details showing both the above ground and below ground elements of the

City Rail Link Notice of Requirement

Page 54


Condition Number

Condition

NoR Applies to

station/s; (b) How the above ground and below ground design of the stations has taken into account the following principles: (i) Overarching - stations should achieve a successful and memorable transport experience. (ii) Function - stations will provide safe, functional and clear transport solutions. (iii) Performance - stations will provide a credible, sustainable design outcome that responds to climate, site and social economics. (iv) Personality - stations will provide an expression that contributes to their context and local identity and will respond to an appropriate network wide identity. (v) Existing and New Building Structures. (vi) Built Heritage: 

Where built heritage is required for City Rail Link station requirements, adaptive reuse strategies should be considered to preserve the building’s role in establishing the streetscape and urban character.  The development of new buildings and structures should minimise impact on, and disturbance of, Built heritage listed by the New Zealand Historic Places Trust or the Auckland Council District Plan that play a significant role in establishing the streetscape and urban character of the local area. (vii) Bulk, Scale and Massing: 

 

Bulk, scale and massing of structures resulting from the City Rail Link (station buildings in particular) should be sympathetic with the surrounding built urban form. Aotea Station building frontages should correspond with the road reserve boundary unless a specific station plaza area is intended. Karangahape Road station building(s) should be sensitively designed so as to contribute positively and to complement the good public realm and urban form qualities that currently exist in this area of Karangahape Road, Pitt Street and the upper end of Beresford Street. The redevelopment of land acquired for the Newton Station provides the opportunity for a continuous active building frontage to correspond with the road reserve boundary, providing:  This does not conflict with the operation requirements of the station; or  Unless a specific station plaza area is intended.

(viii) Active Frontage – Structures resulting from the City Rail Link should present an active frontage towards public spaces like streets, squares, pedestrian walkways or station plaza areas provided that this doesn’t conflict with the operation requirements of the station. : Where no active frontage is proposed, an explanation of the reasons shall be outlined in the Urban Design DWP. (ix) Weather Protection – Where practicable, station entrances should provide some weather protection along their frontage (e.g. verandahs, awnings, canopies etc.) and these should be considered as part of the design. (x) Adaptability – The design of structures resulting from the City Rail Link should be able to adapt to change over time (e.g. change of uses, innovations in technology etc.) where reasonably practicable and anticipate opportunities (e.g. additional entrances) that may become possible in the future. The station design should

City Rail Link Notice of Requirement

Page 55


Condition Number

Condition

NoR Applies to

not inhibit wider development opportunities (e.g. above or around station entrances). (xi) Identity – The design of the station entrances should provide an expression that reflects their respective context and local cultural identity. They could reflect, respond and/or interpret local characteristics like natural or Mana Whenua heritage, history, art, particular traits of the local community and unique architectural and urban forms of the area. (xii) Construction Quality – The design and construction of structures resulting from the City Rail Link (station buildings in particular) should be of a quality that lasts over time. Materials should be selected that are highly durable, elegant and vandal resistant where they come into contact with patrons. (xiii) Mana Whenua Principles – see Condition 49. (c) How these principles have been used to guide and influence the design, and how the design has responded, or otherwise, to these principles and initiatives; and (d) A summary of the engagement with mana whenua (see Condition 15) and identification of where design has incorporated the mana whenua principles and other mana whenua aspirations into station design. The summary must include a clear explanation of where any comments have not been incorporated and the reasons why not. The summary must be included in the Urban Design DWP submitted to both the Independent Peer Review Panel and Auckland Council as part of the Outline Plan. Trees and Vegetation Trees and Vegetation DWP 55.1A Trees and Vegetation DWP shall be prepared to manage the adverse effects from the removal of trees and vegetation during the construction of the City Rail Link or any part of it. 55.2The objective of the Trees and Vegetation DWP is to avoid the removal of scheduled trees as far as practicable. Where trees are identified for removal in surface works the Requiring Authority will remedy or mitigate the adverse effects of construction on trees and vegetation. 55.3To achieve the above objective the following shall be included in the Trees and Vegetation DWP and implemented as required: 1 55

4 5 6

(a) Confirmation of the trees to be removed due to surface construction works and whether it is appropriate and feasible to relocate or store these trees for replanting. The removal of schedule trees which form a significant group should only be undertaken as a last resort; (b) A list of trees, which due to being located in proximity to construction works, have root systems and / or foliage within and / or overhanging the surface designation footprint, and the methods to be used, where practicable, to protect these trees from construction works; (c) Cross references to the Urban Design DWP and the proposed mitigation of any tree / vegetation removal through replanting trees at a 1:1 ratio, re-instatement of the area, and other methods.. In preparing the Trees and Vegetation DWP, the Requiring Authority shall seek input from the Auckland Council Parks Department with regard to tree species / vegetation selection, tree pit construction where deemed necessary, and the positioning of replacement trees and from directly affected land owners with regards to preferences for any replacement planting for vegetation / trees removed from private property or for any replacement planting on private property;

City Rail Link Notice of Requirement

Page 56


Condition Number

Condition

NoR Applies to

(d) Other methods to be used to monitor and report on the management of the adverse effects from tree / vegetation removal; and (e) Cross references to the specific sections in the Communication and Consultation Plan which detail how the Auckland Council Parks Department, mana whenua (see condition 8) are consulted, and communication with the general public on the management of the adverse effects relating to the removal of trees and vegetation. Public Art Public Art DWP 56.1A Public Art DWP shall be prepared to manage the adverse effects on public art located within or in close proximity to the designation footprint. 56.2The objective of the Public Art DWP is to enable: (a) The appropriate removal and / or relocation of one piece of public art directly affected by the construction of the City Rail Link; (b) The protection of two pieces of public art that are located on public land in close proximity to the City Rail Link construction works.

56

1

56.3To achieve the above objective the following shall be included in the Public Art DWP and implemented as required: (a) The process that will be undertaken to remove the public art work known as "Enduring Fires" (at the time of the Notice of Requirement process located within Queen Elizabeth Square), including the consultation undertaken with the Auckland Council and Ngati Whatua ki Tamaki or Ngati Whatua o Orakei as to its removal, storage, re-establishment or relocation and / or replacement (as part of the restoration works associated with the City Rail Link construction); (b) The process that will be undertaken to protect or remove the public art work known as "Maori Warrior" (at the time of the Notice of Requirement process located on the pavement of Quay Street adjacent to 1 Queen Street), including the consultation undertaken with the Auckland Council as to its protection during construction or whether it should be removed, stored, relocated and / or replaced (as part of the restoration works associated with the City Rail Link construction); (c) The process to protect the public art known as "Matahorua Anchor and Tainui Anchor" (at the time of the Notice of Requirement process located at the northern end of the Bledisloe Building on Wellesley Street) from construction works to the west, including the consultation undertaken with the Auckland Council as to its protection. 56.4If one does not already exist, an asset management plan shall be prepared by the Requiring Authority in collaboration with Auckland Council for any of the above listed public art works as part of any protection or removal process. 56.5Should the above public art works be removed from these sites prior and separate to the City Rail Link project, this condition will not need to be complied with.

Contaminated Land Contamination DWP 4

57.1A Contamination DWP shall be prepared to manage the adverse effects relating to contaminated land during the construction of the City Rail Link or any part of it.

5 6

57.2The objective of the Contamination DWP is to avoid, remedy or mitigate the adverse effects of construction on human health which may result from the disturbance of contaminated materials during construction.

1 57

57.3To achieve the above objective the following shall be included in the Contamination DWP

City Rail Link Notice of Requirement

Page 57


Condition Number

Condition

NoR Applies to

and implemented as required: (a) A health and safety plan that addresses: (i) Worker safety in relation to hazardous substances; and (ii) Worker training with regard to handling hazardous substances, identifying potentially contaminated soil / material, and notification procedures for discovery of contamination; (b) Procedures for how erosion and sediment control, storm water, dust, and odour control measures will manage the removal of contaminated soil / material; (c) Procedures for contaminated soil classification, management and disposal of contaminated soil / material; (d) Where any trenches/excavations during civil works are to be sealed as a result of contamination and how this is to be recorded; (e) How and which work areas are to be restricted to authorised personnel only and procedures to limit the presence of ignition sources in these areas (e.g. no smoking within or adjacent to construction area, no welding or open flames near areas with high concentrations of hydrocarbon contamination); (f) Procedures for the monitoring and management of the removal of contaminated soil / material by a suitably qualified environmental specialist; (g) How the placement of re-used contaminated soil / material will be recorded and tracked; (h) Where areas for stockpiling and storing contaminated soil / material will be established on the construction site and the procedures for managing the containment of the contaminated soil / material in these areas; (i) Cross references to the specific sections in the Communication and Consultation Plan which detail how the general public are to be communicated with on the management of the adverse effects relating to the removal of contaminated soil / material. Contamination Validation Report at Completion of Construction 1 58

4 5 6

58.1At the completion of construction works a validation report will be prepared in accordance with any Ministry for the Environment guidelines and submitted to the Auckland Council Consent Monitoring officer documenting the management of soil and evidence of appropriate disposal. The validation report shall include a record of all analytical results, volumes, tip dockets, and any incidents or complaints and how these were addressed. The validation report shall also identify any areas which need on-going monitoring and management by the Requiring Authority.

Air Quality Air Quality DWP

1 59

4 5 6

59.1An Air Quality DWP shall be prepared to avoid, remedy or mitigate the adverse effects on air quality during the construction of the City Rail Link or any part of it. 59.2The objective of the Air Quality DWP is to detail the best practicable option to avoid dust and odour nuisance being caused by construction works and to remedy any such effects should they occur. 59.3To achieve the above objective the following shall be included in the Air Quality DWP and implemented as required: (a) The procedures to be implemented for the continuous monitoring of Total Suspended Particulate (TSP) concentrations and meteorology including, but not limited to, the establishment of two monitoring sites (to the north and south of the

City Rail Link Notice of Requirement

Page 58


Condition Number

Condition

NoR Applies to

site); (b) Identification of the sensitive locations, and the specific methods for monitoring, including trigger limits to determine whether further action (such as implementation of the mitigation measures discussed below or other mitigation measures) is required; (c) Procedures for responding to malfunctions with construction machinery or works causing accidental dust discharges including, but not limited to, the requirement to remedy any malfunction within 24 hours; (d) Procedures for monitoring weather conditions and the requirement that water spray is used on soil stockpiles, any non-paved construction areas, and the wheels of trucks where dust may disperse beyond the site; (e) Procedures for establishing when the covering of trucks will be required; (f) Procedures for determining when hard surfaced areas in construction yards and active construction areas should be cleaned including, but not limited to, the requirement that such areas be cleaned whenever dust generation occurs due to traffic on these surfaces; (g) Procedures for responding to discharges of odour (including in the event of excavation of contaminated sites) including, but not limited to, the requirement to address discharge of objectionable odour by immediately ceasing the activity causing the discharge; (h) Procedures for equipment inspection (including timeframes for regular inspections), maintenance, monitoring and recording, including baghouses, pressure relief valves and high level alarms to mitigate dust emissions; (i) Procedures for, where practicable, limiting dust and odour nuisance and the methods for monitoring these procedures including Identification of contingency measures to address identified and verified adverse effects on sensitive receptors. Contingency measures may include options such as: (i) Cleaning of air filtration intakes; or (ii) Cleaning of other buildings and infrastructure; and (j) Procedures for responding to any complaints received and the timeframes for response to complaints and reporting; (k) Cross references to the specific sections in the Communication and Consultation Plan which detail how the communities in the vicinity of construction works are to be communicated with on the management of the adverse effects relating to air quality. Social Impact and Business Disruptions

1 60

4 5 6

Property Management Strategy 60.1The Requiring Authority will prepare a Property Management Strategy and shall submit the Strategy to Auckland Council within 3 months of the Designation being confirmed for confirmation that the Strategy has been prepared in accordance with this condition. 60.2The purpose of the Strategy is to set out how the Requiring Authority will ensure the properties acquired for the City Rail Link are appropriately managed so they do not deteriorate and adversely affect adjoining properties and the surrounding area. The Strategy shall identify measures and methods to ensure the properties are managed in a manner that: (a) Does not significantly change the character, intensity and scale of the effects of the existing use of the land; (b) Maintains the condition of the property at that which existed at the time of purchase

City Rail Link Notice of Requirement

Page 59


Condition Number

NoR Applies to

Condition

by the Requiring Authority; (c) Contributes to the functioning of the area within which the property is located; (d) Maintains occupancy as far as reasonably practicable; and (e) Provides confidence to occupants, adjoining property owners, and the community that the properties are managed responsibly pending construction. Social Impact and Business Disruption DWP 61.1The Requiring Authority shall prepare a Social Impact and Business Disruption DWP. The objective of the Social Impact and Business Disruption DWP is to avoid, remedy or mitigate the adverse effects arising from disruption to businesses, residents and community services/facilities so far as reasonably practicable. 61.2To achieve this objective the Requiring Authority shall engage a suitably qualified specialist(s) to prepare a Social Impact and Business Disruption DWP to address the following specific issues: (a) How disruption to access (including pedestrian, cycle, passenger transport and service/private vehicles) for residents, community services and businesses as a result of construction activities will, so far as is reasonably practicable, be avoided, remedied or mitigated; (b) How the disruption effects that result or are likely to result in the loss of customers to businesses as a result of construction activities will, so far as is reasonably practicable, be avoided, remedied or mitigated; (c) How the loss and/or relocation of community facilities and the loss or change to catchments associated with these facilities as a result of the property acquisition process particularly to the Chinese Community Centre and Life Centre Church and the temporary loss of car parking at Hopetoun Alpha will be mitigated; and 1 61

4 5 6

(d) How loss of amenity for residents, community services and businesses as a result of construction activities will be or has been mitigated through the CEMP and other DWPs. 61.3The Social Impact and Business Disruption DWP shall be prepared in consultation with the community, community facility operators, business owners, affected parties and affected in proximity parties to: (a) Understand client and visitor behaviour and requirements and operational requirements of community facilities and businesses; (b) Identify the scale of disruption and adverse effects likely to result to businesses, residents and community services/facilities as a result of construction of the City Rail Link; (c) Assess access and servicing requirements and in particular any special needs of residents, community facilities and businesses; and (d) To develop methods to address matters outlined in (b) and (c) above, including: (i) The measures to maximise opportunities for pedestrian and service access to businesses, residents and social services/facilities that will be maintained during construction, within the practical requirements of the Transport, Access and Parking conditions (Conditions 25 to 30) and the Transport, Access and Parking DWP; (ii) The measures to mitigate potential severance and loss of business visibility issues by way-finding and supporting signage for pedestrian detours required during construction; (iii) The measures to promote a safe environment, taking a crime prevention

City Rail Link Notice of Requirement

Page 60


Condition Number

NoR Applies to

Condition

through environmental design approach; (iv) Other measures to assist businesses and social services/facilities to maintain client/customer accessibility, including but not limited to client/customer information on temporary parking or parking options for access; (v) Other measures to assist residents, businesses and social services/facilities to provide for service delivery requirements; (vi) The process (if any) for re-establishment and promotion of normal business operation following construction; (vii) If appropriate and reasonable, requirements for temporary relocation during construction and/or assistance for relocation (including information to communities using these services and facilities to advise of relocations); and (viii) The measures to remedy and mitigate the disruption impacts to the community as a result of any closure and/or relocation of community services and facilities required by the Project. 61.4The Social Impact and Business Disruption DWP shall include: (a) A summary of the findings and recommendations of the Social Impact Assessment report (2013); (b) A record of the consultation undertaken with the community including specific access and operational requirements of individual businesses and residents including, if relevant, consultation on the necessity for, and the feasibility of, options and requirements for temporary relocation during construction and/or assistance for relocation); (c) An implementation plan of the methods to mitigate the disruption effects (as developed in 61.3 above); (d) Reference to any site/business specific mitigation plans that exist (though these may not be included in the DWP); (e) Cross reference to detail on how the CEMP and DWPs have responded to the issues of resident, business and social service/facility accessibility and amenity; (f) Details of on-going consultation with the local community through the Community Liaison Groups to provide updates and information relating to the timing for project works and acquisition; (g) Details of best endeavours steps undertaken with regard to acquisition and/or relocation of the Chinese Community Centre and Life Centre Church under the Public Works Act 1981; and (h) The process for resolution of any disputes or complaints in relation to the management / mitigation of social impacts (including business disruption impacts). 61.5In relation to the site at 32 Normanby Road, the Requiring Authority shall consult with sub-lessees in the presence of the landowner and head lessee when developing site/business specific mitigation plans, unless the sub-lessee(s) request otherwise. 61.6 The Social Impact and Business Disruption DWP shall be implemented and complied with for the duration of the construction of the City Rail Link and for up to 12 months following the completion of the Project if required. 61.7 Suitably qualified independent specialists for the social impact and business disruption mitigation (whose appointment shall be agreed by the Council) shall peer review the Social Impact and Business Disruption DWP pursuant to Condition 11. 61.8 The Requiring Authority shall prepare an annual report on the identification, monitoring, evaluation and management of the effects outlined in the Social Impact and Business Disruption DWP together with a summary of matters raised by the community, and how

City Rail Link Notice of Requirement

Page 61


Condition Number

Condition

NoR Applies to

these have been responded to. The report shall be presented to the Community Liaison Groups. Specific Design Requirements 62

2

62.1The operational tunnel will avoid running under the building footprint of the property at 152 Vincent Street.

OPERATIONAL CONDITIONS Operational Rail Vibration 63.1The Requiring Authority shall confirm that operational rail vibration and reradiated noise levels comply with the following Project Criteria at any noise or vibration sensitive receiver existing at the time of lodgement of the CRL NoR: Building Type

Vibration Criteria

Reradiated Noise Criteria (dB LASmax re: 20 Pa)

PPV (mm/s)

1 2 63

4 5 6

Commercial uses with primarily daytime use1

0.2

40

Residences and buildings where people normally sleep

0.15

35

Auditoria/Theatres1

0.1

30

TV/Recording Studios

0.06

25

Note: 1. 2.

Such as offices, businesses, churches, schools, universities and libraries. This includes Albert Street District Court.

63.2For any noise or vibration sensitive building types that are not provided for in the table above, the upper limit for vibration and reradiated noise shall not exceed 0.3 mm/s PPV and 50 dB LASmax respectively. 63.3For the avoidance of doubt this does not apply to the North Auckland Line and Britomart Designations. 63.4When assessing operational rail vibration and reradiated noise, compliance with Conditions 63.1 and 63.2 shall be achieved for at least 95% of any 20 consecutive train pass-by ‘events’. Operational Noise – Mechanical Ventilation Plant

1 64

2 4 5

64.1Operational noise from mechanical ventilation plant servicing the underground rail sections of the City Rail Link shall be measured and assessed in accordance with the following Project Criteria: Location

Period

Auckland Central Area

7.00am to 11:00pm

65

11:00pm to 7:00am

60

7.00am to 10:00pm

60

Auckland Isthmus Area

dB LAeq

dB LAFmax 75

City Rail Link Notice of Requirement

Page 62


Condition Number

NoR Applies to

Condition

10:00pm to 7:00am

55

75

64.2Measurements shall be undertaken in accordance with New Zealand Standard NZS 6801:2008 “Acoustics – Measurement of environmental sound” and assessed in accordance with New Zealand Standard NZS 6802:2008 “Acoustics - Environmental Noise”. 64.3For the avoidance of doubt this does not apply to the North Auckland Line and Britomart Designations. Operational Noise and Vibration Management Plan (ONVMP) 65.1To manage the adverse effects from the maintenance and operation of the City Rail Link, the Requiring Authority shall, prior to the operation of the CRL, prepare an Operational Noise and Vibration Management Plan, (ONVMP) to the satisfaction of Auckland Council’s Compliance Monitoring Manager. The objective of the ONVMP shall be to ensure that the tracks, rolling stock and associated infrastructure (including ventilation and other mechanical plant) are maintained and operated in accordance with maintenance standards as outlined in the Requiring Authority’s maintenance programme for the City Rail Link, so that operational noise and vibration levels received at noise sensitive receiver locations, and vibration levels comply with Conditions 63 and 64. . 65.2The ONVMP shall set out procedures for: 1 2 65

4 5

(a) The maintenance of rolling stock to minimise noise and vibration emissions including, but not limited to, the management of wheel roughness and flats, braking systems, cooling systems, suspension systems and any other significant source associated with the operation of locomotives; (b) The maintenance of tracks to minimise noise and vibration emissions, including, but not limited to, the management of curve squeal, rail roughness, joint constructions and any other significant source associated with the use of the tracks; (c) The implementation of mitigation measures associated with the operation and maintenance of the City Rail Link, for the operational life of the City Rail Link; (d) The management of noise from the operation of the line, including, but not limited to, the use of audible warning devices and acceleration / deceleration controls (where relevant); and (e) The management of noise and maintenance of noise-generating equipment from stations and associated ventilation and mechanical plant infrastructure including, but not limited to, PA systems, fans and ventilation noise and audible warning devices. 65.3The ONVMP shall be adhered to at all times. It may be updated or amended at any time with the approval of Auckland Council’s Compliance Monitoring Manager. 65.4For the avoidance of doubt this does not apply to the North Auckland Line and Britomart Designations.

66

6

Operational Noise and Vibration Management – MediaWorks 66.1At least six months prior to the opening of the CRL, the Requiring Authority shall provide a report from a suitably qualified noise and vibration expert to Auckland Council’s Compliance Monitoring Manager and to MediaWorks. The report shall confirm the trackform mitigation applied to the project has been designed to ensure that operational noise will not exceed the levels as set out in Condition 63. 66.2The Requiring Authority shall implement continuous vibration monitoring on the tunnel structure on the East Link Down Main line within 20m of the closest point of the CRL tunnel to Studio 1 to determine compliance with Condition 63 during the operation of

City Rail Link Notice of Requirement

Page 63


Condition Number

NoR Applies to

Condition

the CRL (but only for so long as MediaWorks remains located at the MediaWorks site). The monitoring regime shall: (a) Be based on PPV measurements; (b) Ensure that measurement equipment and signal chain complies with the manufacturers guidelines for accuracy and calibration; (c) Capture every train pass-by on the line which may be triggered by vibration level radio frequency tag, interrupted beam or any other practicable triggering method; (d) Ensure the retention of the PPV data for every train pass-by on the line; (e) Ensure the transmission of PPV data for every train pass-by to the Requiring Authority at an interval not exceeding 48 hours between data uploads to enable records to be viewed and interrogated as required without requiring access to the monitoring location; (f) Ensure that the Requiring Authority, Auckland Council’s Compliance Monitoring Manager and MediaWorks are alerted to PPV values exceeding a value at the tunnel monitoring location that corresponds to 90% of the limits specified in Condition 63.1 for TV/Recording Studios to enable the Requiring Authority to instigate preventative maintenance of tracks and rolling stock with the aim of avoiding exceedences of the noise and vibration limits at the MediaWorks building. The ONVMP required by Condition 65 shall set out the method for determining the transfer function between the tunnel monitoring location and the floor of Studio 1, and what the vibration trigger level is (based on measurements on the tunnel structure) for investigation and corrective action measures relative to Condition 66.2(f) above. The transfer function shall be accurately determined prior to the railway becoming operational using the tunnel monitoring location and the floor of Studio 1. 66.3Condition 63 shall be complied with at the MediaWorks building for the life of the CRL. 66.4Noise shall be measured in accordance with the requirements of NZS6801:2008 Acoustics - Measurement of Environmental Sound. Vibration shall be measured in accordance with the requirements of German Standard DIN 4150-3:1999 Structural vibration - Effects of vibration on structures. 66.5In the event of any exceedance of any noise or vibration limit in Condition 63 during Sensitive Times (as defined in Condition 35.1) measures to reduce the noise or vibration below the relevant limit in Condition 63 shall be implemented as soon as reasonably practicable. ADVICE NOTES

1 AN1

4 5 6

1 2 AN2

4 5 6

The Requiring Authority will require an Authority under the Historic Places Act 1993 to destroy, damage or modify any archaeological site. This Authority is required in advance of earthworks commencing in the area where the archaeological site is located. It is expected that there will be staged Section 12 Authority applied for to cover the earthworks programme. In the event of unanticipated archaeological sites or koiwi being uncovered the Requiring Authority shall cease activity in the vicinity until it has the relevant approvals, and consulted with the Historic Places Trust and relevant iwi interests. The Requiring Authority will need to acquire the relevant property interests in land subject to the designation before it undertakes any works on that land pursuant to the designation. That may include a formal Public Works Act 1981 land acquisition process. It is acknowledged that property rights issues are separate from resource management effects issues and that the resolution of property issues may be subject to confidentiality agreements between the Requiring Authority and the relevant landowners.

City Rail Link Notice of Requirement

Page 64


Condition Number

NoR Applies to

Condition

1

Prior to construction if Network Utility Operators are carrying out works that do not require prior written consent of the Requiring Authority in accordance with condition 6 of this designation, they must carry out those works in accordance with the Corridor Access Request (CAR) Process (as set out in Part 4 of the National Code of Practice for Utility Operators’ Access to Transport Corridors 2011) where that process applies to the works being carried out.

2 AN3

4 5 6 1

AN4

2 4

Under section 176 of the RMA no person may do anything in relation to the land subject to the designation that would prevent or hinder the Rail Link without the written approval of the Requiring Authority.

5 6 1 AN5

2 4 5

Some of the land is subject to existing designations. Nothing in these designation conditions negates the need for the Requiring Authority to adhere to the provisions of section 177 of the RMA.

AN6

6

Some of the land is subject to existing designations. Nothing in these designation conditions negates the need for the Requiring Authority to adhere to the provisions of section 177 of the RMA. For the avoidance of doubt, the Requiring Authority shall obtain the written consent of the Minister of Corrections in accordance with section 177 of the RMA for any work authorised by the City Rail Link designation on the Mt Eden Corrections Facility site at 1 Lauder Road.

AN7

1

Modifications to Britomart Transport Centre to connect the City Rail Link tracks into the rail network are separate to this designation and are covered under the Britomart Transport designation.

AN8

6

Works required to connect the City Rail Link to the North Auckland Rail Line occurring within the North Auckland Rail Line designation are separate to this designation and are covered under the North Auckland Line Rail designation.

City Rail Link Notice of Requirement

Page 65


Appendix One to Designation Conditions (NoR 1, 2, 4, 5 and 6) Condition 36 of this designation requires as part of the CEMP process the confirmation of where and when building condition surveys will be undertaken in relation to vibration and settlement. Note that those buildings classed in the “heritage� category are covered under the Appendix Two below. In accordance with condition 46, at a minimum building condition surveys shall be considered for the following buildings:. No

Address

Property Known As

1

8-12 Albert Street

Quay West Hotel

2

17 Albert Street

Cohesive Technology House

3

22-26 Albert Street

The Stamford

4

74 Albert Street

Chifley Suites

5

76-84 Albert Street

City Gardens Apartments

6

103,105,107 Albert Street

Manhattan Apartments

7

109-125 Albert Street

Sky City - Grand Hotel & Convention Centre

8

106-108 Albert Street

Elliot Tower (Proposed)

9

128 Albert Street

Crown Plaza

10

103 Vincent Street

YWCA Accommodation

11

109 Vincent Street

The Rodney Apartments

12

113 Vincent Street

Winsun Heights Apartments

13

135 Vincent Street

Dynasty Gardens Hotel

14

150 Vincent Street

The City Lodge

15

156 Vincent Street

Eclipse Apartments

16

71-87 Mayoral Drive

Rendezvous Grand Hotel

17

29,39,41 Pitt Street

Hopetoun Delta Apartments

18

22-28 Beresford Square

The Beresford

19

259-281 Karangahape Road

Retail and Residential building

20

14 East Street

Residential Building

21

9 A-C Mercury Lane

Residential Building

22

18 East Street

Residential Building

23

153 Newton Road

Beatnik

24

10 Flower Street

Eden Terrace Apartments

25

1 Akiraho Street

Eden Oaks

26

21 Queen Street

Zurich House (Anzo Tower)

27

7 Albert Street

Retail and Office building

28

9-11 Albert Street

Food Alley

29

23-29 Albert Street

ANZ Centre

30

12-26 Swanson Street

Affco House Carpark

City Rail Link Notice of Requirement

Page 66


No

Address

Property Known As

31

58 Albert Street

APN NZ Complex

32

63 Albert Street

AMI House

33

65-69 Albert Street

Auckland District Court

34

38 Wyndham Street

Wyndham Towers

35

92-96 Albert Street

Former Telecom Tower

36

85 Albert Street

Retail and Office building

37

87-89 Albert Street

Albert Plaza

38

99 Albert Street

AA Building

39

135 Albert Street

ASB Building

40

120 Albert Street

BDO Tower

41

44-52 Wellesley Street West

Wellesley Centre

42

67-101 Vincent Street

Auckland Police Station

43

22 Dundonald Street

Soundcraft Ltd

44

3 Flower Street

TV3 Building

45

32 Normanby Road

Commercial Building

46

3 Enfield Street

Horse and Trap

47

101 Mount Eden Road

Hometune

48

1 Ngahura Street

Auckland Boxing Association

49

1 Queen Street

HSBC House

50

125 Queen Street

New World Supermarket tenancy

51

148 Quay Street

Tenham Investments and Body Corporate 184960

52

29 Customs Street West

AMP Centre

53

15-19 East Street

54

32 Akiraho Street

Bear Park Early Childhood Centre

City Rail Link Notice of Requirement

Page 67


Appendix Two to Designation Conditions (NoR 1, 2, 4, 5 and 6) Condition 41 of this designation requires as part of the CEMP process the confirmation of where and when building condition surveys will be undertaken in relation to Built Heritage (including those affected as a result of excavation). In accordance with condition 46, at a minimum building condition surveys shall be considered for the following buildings: No

Address

Property Known As

1

12 – 32 Customs Street

Customs House

2

2 Queen Street

Endeans Building

3

12 Queen Street

Former CPO - Britomart Transport Centre

4

3 Albert Street

West Plaza

5

13 Albert Street Auckland Central

Yates Building

6

15 Albert Street

Link House

7

35 Albert Street Auckland Central

Price Buchanan Building

8

37 – 39 Albert Street Auckland Central

9

41 Albert Street

10

46 Albert Street

11

49 Albert Street Auckland Central

12

53 Albert Street Auckland Central

13

55 Albert Street

14

57 Albert Street

15

61 Albert Street Auckland Central

Shakespeare Hotel and Brewery

16

76 to 78 Albert Street Auckland Central

Bluestone Wall + toilets under wall

17

83 to 85 Albert Street Auckland Central

18

102 Albert Street

19

26, 34 – 36 Wyndham Street

Former Gas Co Building

20

9 – 11 Durham Street

Bluestone Store

21

37-43 Victoria Street West

22

51-53 Victoria Street West

23

61-65 Victoria Street West

24

66 Victoria Street West

London Dairy

25

68 Victoria Street West

J H Hannan

26

24 Wellesley Street West

Bledisloe House

27

15-31 Wellesley Street West

Archibald and Sons Warehouse/ T & G Building

New Zealand Herald

Martha’s Corner

City Rail Link Notice of Requirement

Page 68


No

Address

Property Known As

28

42 Wellesley Street

Griffiths Holdings Building

29

33 Wyndham Street

30

Aotea Square Aotea Centre (rear section)

31

11 Mayoral Drive

Former Public Trust

32

105 Vincent Street

Auckland Chinese Presbyterian Church

33

133 Vincent Street

Juliette’s

34

53 Pitt Street

Former Central Ambulance Station

35

59 Pitt

36

65 Pitt Street

37

70 – 74 Pitt Street

The Chatham

38

78 Pitt Street Pitt Street

Wesleyan Church

39

78 Pitt Street

Wesleyan Bicentennial Hall

40

1 Beresford Square Auckland Central

Former Pitt Street Fire Station

41

16 – 18 Beresford Square

42

211-235 Karangahape Road

Pitt Street Buildings (O’Malley’s Corner)

43

238 Karangahape Road

George Court Building

44

1 Cross Street

George Court Factory Building

45

243 Karangahape Road

Naval and Family Hotel

46

246-254 Karangahape Road

Hallenstein Brothers Building

47

251 – 253 Karangahape Road

48

256 Karangahape Road

49

257 Karangahape Road

50

258-266 Karangahape Road

51

268 Karangahape Road

52

259-261 Karangahape Road

53

270 Karangahape Road

54

283 Karangahape Road

Samoa House

55

9 Mercury Lane

Mercury Theatre former Kings Theatre

56

151 Newton Rd

Retail/Recording Studio

57

206-208 Symonds Street

Cheapskates/Penny Farthing Bike Shop

58

210 Symonds Street Retail

French Café

Mercury Theatre entrance - Norman Ng Building

City Rail Link Notice of Requirement

Page 69


No

Address

Property Known As

59

215 Symonds Street

Edinburgh Castle Building

60

221 Symonds Street

61

224 Symonds Street

62

227 Symonds Street

63

231 Symonds Street Retail

64

233 Symonds Street

65

235 Symonds Street

66

237 Symonds Street

67

239-241 Symonds Street

68

243 Symonds Street

69

245 Symonds Street

70

249 Symonds Street

71

253 Symonds Street

72

1-13 Mt Eden Road

73

15-17 Mt Eden Road

74

21 New North Road

75

14 New North Road

Villa Dalmacija

76

St Patrick’s Square 43 Wyndham Street

St Patrick’s Cathedral

77

59 Alex Evans Street

St Benedict’s Church

78

1 – 9 St Benedicts Street

St Benedict's Presbytery

79

6 St Benedicts Street

Residential

80

43 Wyndham Street & Hobson Street

St Patrick’s Presbytery

81

Beresford Square

Forrester’s Hall

Former Post Office

City Rail Link Notice of Requirement

Page 70


Proposed Draft Notice of Requirement Conditions – NoR 3 Condition Number

NoR Applies to

Proposed Draft Condition 1.1 Except as modified by the conditions below, the City Rail Link Project shall be undertaken in general accordance with the information provided by the Requiring Authority in the Notice of Requirement dated 23 August 2012 and supporting documents being: (a) Assessment of Environmental Effects report (contained in Volume 2 of the Notice of Requirement suite of documents, dated 15 August 2012 Rev B); (b) Supporting environmental assessment reports (contained in Volume 3 of the Notice of Requirement suite of documents, dated August 2012);

1

3

(c) The Concept Design Report (contained in Volume 2 of the Notice of Requirement suite of documents, dated 13 August 2012 Rev 3); (d) Plan sets: (i) Land requirement plans (contained in Volume 1 of the Notice of Requirement suite of documents, dated 15 August 2012); (ii) Plans contained in the Concept Design Report Appendices (contained in Volume 3 of the Notice of Requirement suite of documents, dated 13 August 2012 Rev 3). 1.2. Where there is inconsistency between the documents listed above and these conditions, these conditions shall prevail.

2

3

3

3

2.1 In accordance with section 184(1) of the Resource Management Act 1991 (the RMA), this designation shall lapse if not given effect to within 15 10 years from the date on which it is confirmed. 3.1 The Requiring Authority shall, as soon as reasonably practicable, but no later than at completion of detailed design: (a) Review the area and volume of land of NoR 3 required to protect the structural integrity of the two tunnels (including the relevant considerations at Condition 5.5); (b) Identify any areas of designated land that are no longer necessary to protect the structural integrity, safety or operation of the two tunnels; and (c) Then give notice in accordance with Section 182 of the RMA for the removal of those parts of the designation identified in (b) above. 4.1 Under s 176(1)(b) of the Resource Management Act 1991 (RMA) no person may do anything in relation to the designated land that would prevent or hinder the City Rail Link, without the prior written consent of the Requiring Authority. 4.2 In the periods pre, during and post construction of the City Rail Link, the following activities undertaken by Network Utility Operators will not prevent or hinder the City Rail Link, and can be undertaken without seeking the Requiring Authority’s written approval under section 176(1)(b) of the RMA:

4

3

(a) Maintenance and urgent repair works of existing Network Utilities; (b) Minor renewal works to existing Network Utilities necessary for the on-going provision or security of supply of Network Utility Operations; (c) Minor works such as new property service connections; (d) Upgrades to existing Network Utilities within the same or similar location with the same or similar effects on the City Rail Link designation. 4.3 For the avoidance of doubt, in this condition an “existing Network Utility” includes

City Rail Link Notice of Requirement

Page 71


Condition Number

NoR Applies to

Proposed Draft Condition infrastructure operated by a Network Utility Operator which was: (a) In place at the time the notice of requirement for the City Rail Link was served on Auckland Council (23 August 2012); or (b) Undertaken in accordance with this condition or section 176(1)(b) RMA process. 5.1 This designation does not authorise any CRL works but restricts development from proceeding without the approval of the Requiring Authority where that development would result in an adverse effect on the CRL in terms of safety, operation or construction. 5.2 The Requiring Authority will work with developers in a collaborative manner and may require alterations or changes to development proposals for the purpose in 5.1. 5.3 The Requiring Authority may require alterations or changes to any proposal for development including but not limited to construction of basements and foundations where such works disturb the ground in a way that is likely to result in loading changes and result in deformations or produce other risks to the integrity of the CRL structures. 5.4 Reasons shall be given by the Requiring Authority for these changes to demonstrate they are reasonably necessary to provide for safety, construction or operation of the CRL,

5

3

5.5 Any proposal for physical works or activities within the designation shall be provided to the Requiring Authority and will be assessed on the following: (a) Building height, size, mass and proximity to the CRL structures; (b) Foundation and basement designs; (c) Geotechnical conditions; (d) Separation between the CRL structures and the proposed development; (e) Nature of the activities including methods and staging of construction; (f) The predicted loading change on the CRL structures resulting from the development; and (g) Any other relevant information necessary to determine the likelihood and extent of any adverse effect that may occur as a result of the proposed development. These factors will also be relevant considerations in the drawback of the designation as provided for in Condition 3.1. 5.6 That assessment shall be peer reviewed by an independent certified engineer, paid for by the Requiring Authority, and the findings supplied to the landowner/ developer and the Auckland Council for information.

Advice Notes relating to the Designation

AN 1

3

This is a designation for protection purposes only. It protects the City Rail Link infrastructure to be constructed, operated and maintained in a separate designation located beneath this designation. The use of the land within this designation is subject to the agreement of the Requiring Authority to protect the subterranean works below. Any person proposing to undertake physical works within this designation is required to contact the Requiring Authority and obtain its approval in accordance with provisions set out in section 176(1)(b) of the Resource Management Act 1991.

AN 2

3

If Network Utility Operators are carrying out works that do not require prior written consent of the Requiring Authority in accordance with condition 6 of this designation, they must carry out those works in accordance with the Corridor Access Request (CAR) Process

City Rail Link Notice of Requirement

Page 72


Condition Number

NoR Applies to

Proposed Draft Condition (as set out in Part 4 of the National Code of Practice for Utility Operators’ Access to Transport Corridors 2011) where that process applies to the works being carried out.

City Rail Link Notice of Requirement

Page 73


Diagram 1

City Rail Link Notice of Requirement

Page 74


Decision following the hearing of an application for resource consents under the Resource Management Act 1991 (RMA) Application for resource consents under section 88 of the RMA by Auckland Transport necessary to construct the Britomart Station to Wyndham Street section of the proposed City Rail Link. Pursuant to sections 104, 104B, 105, 106, 107 and 108 of the RMA these resource consents are GRANTED. The reasons are set out below.

Application Numbers:

R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

Site Address:

Britomart Station, Lower Queen Street, Customs Street West, Wolfe Street, Victoria Street West, Albert Street, Wyndham Street, Auckland Central.

Applicant:

Auckland Transport (“AT” or “the applicant”) 6, 7, and 8 July 2015

Hearing Dates: Hearing Panel:

Appearances:

Mr Alan Watson Mr Michael Parsonson Ms Rebecca Macky Mr Basil Morrison For the Applicant: Andrew Beatson – Legal Counsel Scott Elwarth – Corporate Dean Ingoe – Consenting Strategy & Consultation Bill Newns – Design & Construction Alan Pattle – Groundwater Bill Newns – Settlement Craig Stevenson – Building Settlement Bruce Petry – Built Heritage Andrew Hart – Contamination Richard Chilton - Air Quality Paul Kennedy – Water Quality & Management Jennifer Carvill – Planning Carol Greensmith – Communications Manager For the Submitters: Noel Playle - Body Corporate Committee 095035 Gordon Nelson - Endean’s Scheme Committee Amanda Stoltz – Legal Counsel, Stamford Residences Owners Corp Vicki Morrison-Shaw – Legal Counsel, Cooper & Company NZ Vijay Lala – Resource Management Planning consultant

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

1


Richard Brabant – Barrister, for 148, 153 Quay Street Body Corp, Mercure Hotel/Pandy, 8 Customs Street Gavin Alexander- Technical Director Beca Duncan McKenzie – Heritage New Zealand Pouhere Taonga For Council: Andrew Gysberts - Team Manager Major Infrastructure Projects Fritha Witton - Senior Planner Aidan Nelson - Groundwater Engineers, Earthtech Consulting Ltd Philip Kelsey - Groundwater Engineers, Earthtech Consulting Ltd Nick Hazard - Groundwater Specialist Leon Blackburn - Water Quality, Discharges of contaminants to stormwater John Brown - Built Heritage Patrick Shorten - Fraser Thomas Limited Barry Brown - Fraser Thomas Limited Peter Goldsmith - Fraser Thomas Limited

Hearing adjourned

Tania Bonsall - Democracy Advisor - Hearings 8 July 2015

Commissioners’ site visit

As the Commissioners are all generally familiar with the site, it was left to individual Commissioners to undertake any site visit he or she considered necessary.

Hearing Closed:

29 July 2015

INTRODUCTION Commissioners’ appointment 1.

This decision is made on behalf of the Auckland Council (the Council or AC) by Independent Hearing Commissioners Alan Watson, Michael Parsonson, Rebecca Macky and Basil Morrison appointed and acting under delegated authority under sections 34 and 34A of the Resource Management Act 1991 (the RMA).

2.

Mr Parsonson was unable to attend Day 1 of the hearing due to illness. With the agreement of all parties, the hearing proceeded with the issues other than groundwater and settlement, which were addressed on Day 2.

3.

Throughout the hearing, and whilst the formal proceedings continued, experts representing the applicant, the Council and at times, some submitters, met in conference and conferred in an endeavour to narrow and resolve outstanding points of difference.

4.

This decision contains the findings from our deliberations on the applications for resource consent and has been prepared in accordance with section 113 of the RMA.

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

2


Information 5.

As the Commissioners, we were provided with copies of the application details, further information provided by the applicant and the submissions. The Council officer’s section 42A RMA report was provided to all interested parties before the hearing and the applicant’s evidence was pre-circulated before the hearing.

6.

On 3 July 2015, Council’s reporting planner circulated a memorandum to the Hearings Commissioners outlining the interactions which had taken place between AC and AT following the pre-circulation of evidence and to state AC’s position relating to the Burland methodology used by the applicant; changes in AT’s methodology; the level of total and differential settlement that could cause damage; and conditions of consent. Notification and submissions

7.

The application was publicly notified on 5 February 2015 at the request of the applicant and notice of the application was also served that day on those persons identified as being potentially adversely affected by the proposal. As part of this process, the interested Mana Whenua groups were directly notified of the application (via the identified RMA administrative addresses) and invited to make a submission.

8.

At the close of the submission period, submissions had been received as follows: 1 in support, 2 in support subject to conditions, 2 neutral and 21 in opposition. The key issues raised in submissions were: Issues raised:

No. of times issue raised

1.

Rates increase

1

2.

CRL is an unnecessary project

1

3.

High density housing along the route of the proposed rail tunnel be abandoned, zoning needs to match character

1

4.

Expected timeframe for the works outside the Stamford Residences

1

5.

Major disruption

2

6.

Transportation of soil to and from the sites

1

7.

Noise

8.

Removal of loading zones for bus stops

9.

Construction induced adverse effects on the fabric of buildings given soil and groundwater conditions

10.

Vibration effects on buildings

11.

Adverse construction effects on occupants of buildings (including businesses) and visitors

12.

Temporary access constraints on Tyler Street and other street frontages

3

13.

Sediment discharges

5

14.

Temporary access constraints on Galway Street and other street frontages

3

15.

General support

1

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

11 1 13 6 10

3


16.

Proposal compromises the interests of Ngati Maru

1

17.

Consultation is incomplete

1

18.

Access and traffic effects

7

19.

Health and safety

1

20.

Applications do not cover all the consents necessary to authorise the works

1

21.

Adverse effects, particularly on the Chief Post Office Building and other heritage buildings

2

22.

Measures and conditions proposed by AT to manage effects do not adequately avoid, remedy or mitigate those effects

1

23.

Lack of certainty i.e. the management of adverse effects through conditions are left to be considered through various management plans that are yet to be written.

2

24.

Dust effects on building occupants and the building itself

4

25.

Incomplete application

1

26.

Guidance on the construction programme is lacking

1

27.

Loss of amenity

1

28.

Risk to human health from the disturbance of contaminated land

1

29.

Reduction in employment opportunities due to adverse traffic effects

2

30.

Archaeology conditions

1

31.

Draft conditions are inadequate

1

32.

Alternative methodologies

1

The relief sought in the submissions was as follows: Relief sought:

No. of times this relief is sought

A.

Rates are kept within the consumer price index for each year and that the City Rail project be abandoned.

1

B.

Timeframe of no more than 24 months to complete the works outside the Stamford Residences.

1

C.

Compensation for loss of property value attributable to the works should we sell the property.

1

D.

Ensure Stamford Residences building is cleaned regularly

1

E.

Instead of filling in the tunnel construct several levels of parking above the track below Albert Street and offer the spaces to Albert Street residences and businesses

1

F.

No construction noise at night

2

G.

Leave loading zones alone

1

H.

Application be declined if detailed/particular conditions are not included (as outlined in submissions)

8

I.

Conditions of consent be imposed which will avoid adverse effects on the building foundations, structure and fabric, and which will require full remediation/repair place reinstatement at the cost of the consent holder in the event that avoidance of any adverse effects is not possible or does not occur

7

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

4


J.

Conditions be included covering the following effects or concerns: -

control quantities of groundwater to be pumped, diverted or dammed

-

continuous monitoring programme, including buildings potentially at risk from adverse effects

-

comprehensive groundwater control and monitoring network and programme including appropriate groundwater alert levels

-

contingency plan, including measures to be implemented if trigger levels are exceeded including a response plan

-

continuous monitoring and reporting

-

post construction monitoring programme

-

if damage, complete and full remediation at the cost of the Consent Holder

-

further conditions as required to address the potential for adverse effects

-

avoid adverse effects from vibration

-

all earthworks are managed to minimise any discharges beyond the site to either land or stormwater drainage systems

-

erosion and sediment control plan

-

inspection of sediment control measures

-

prompt mitigation or rectification if a discharge of debris, soil, silt, sediment or sediment-laden water occurs

-

covering of material during transportation

-

prescribe maximum levels of dust concentrations in the air

-

methods to ensure exposed surfaces remain damp and to minimise dust emissions

-

control vehicle speed limits

-

require appropriate number of wheel washes

-

measures for handling of cement products

-

procedure for responding to continuous dust monitoring

-

operate and maintain mobile continuous dust monitors

-

avoid, or if not reasonably practicable, minimise disruption of access to by the owners tenants or visitors to buildings in the area

6

K.

Cleaning of building at 152 Quay Street to remove dust

3

L.

Ensure continuous access through Tyler Street for the building’s occupants and visitors

3

M.

Specify circumstances and terms and conditions upon which Tyler Street could be temporarily used for access or temporarily occupied

3

N.

Prior to works commencing and at the expense of the Consent Holder (and as a minimum) a pre-construction condition survey of Endeans Building (corner of Quay and Queen Streets) with suitable terms and conditions.

1

O.

Prior to works commencing and at the expense of the Consent Holder (and as a minimum) a pre-construction condition survey of Harbour View Building at 152 Quay Street with suitable terms and conditions.

1

P.

Prior to works commencing and at the expense of the Consent Holder (and as a minimum) a pre-construction condition survey of the building at 148 Quay Street with suitable terms and conditions.

1

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

5


Q.

Prior to works commencing and at the expense of the Consent Holder (and as a minimum) a pre-construction condition survey of the Mercure Hotel building (corner Customs and Queen Streets) with suitable terms and conditions.

2

R.

Cleaning of Mercure Hotel building (corner Customs and Queen Streets) to remove dust

2

S.

Ensure continuous access through Galway Street

3

T.

Ensure 24/7 access to the Mercure Hotel building (corner Customs and Queen Streets) loading dock, and the hotel valet parking

2

U.

Specify circumstances and terms and conditions upon which Galway Street could be temporarily used for access or temporarily occupied

3

V.

Support the project

1

W.

Consultation requirements

3

X.

Access at all times to Quay West building

1

Y.

Further information

2

Z.

Consent applications are placed on hold until such time as:

1

-

Obtained either a district land use consent to authorise works under and in the vicinity of the CPO site or a variation to the designation to allow such works in relation the CPO site

-

Obtained the consents necessary to authorise the construction of the remainder of the CRL line and the operation of the entire line

-

Further information which sets out the precise scope and extent of the proposed underpinning works including earthworks and groundwater effects

-

Further information on the potential effects on neighbouring heritage buildings

AA.

If granted, specific notation included that the consents cannot be exercised until other related authorisations are provided

2

BB.

Effects on CPO and other heritage buildings are avoided, remedied or mitigated

1

CC.

If granted, consents include a review mechanism

1

DD.

Specific measures in AT’s expert reports included as consent conditions

1

EE.

Further detail in management plan conditions, including consultation requirements

3

FF.

Notification to building owners affected by the works

1

GG.

Requirement for an affected party liaison group

1

HH.

Appropriate construction management

1

II.

Groundwater and settlement monitoring, including appropriate trigger levels, and contingency measures

2

JJ.

Specific measures to address adverse air quality effects

2

KK.

Pre and post construction structural condition assessment, regular monitoring prior to and during construction, and expedient remediation of any damage to Stamford Residences’ Building at 22-26 Albert St

1

LL.

Decline applications

4

MM.

Prohibiting the proposed activities from being carried out during specified hours

2

NN.

Requiring the full width of all roads, streets, lanes and footpaths affected to be freely

2

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

6


available for use

9.

OO.

Prior to works commencing and at the expense of the Consent Holder (and as a minimum) a pre-construction condition survey of building in which McDonald’s Restaurant is located, with suitable terms and conditions.

1

PP.

Cleaning of the building in which McDonald’s Restaurant is located (corner of Customs, Galway and Queen Streets) to remove dust

1

QQ.

24/7 access to the McDonald’s Restaurant loading dock

1

RR.

Pre and post construction structural condition assessment, regular monitoring prior to and during construction, and expedient remediation of any damage to 17 Albert St

1

SS.

Monitoring of identified utility services

1

TT.

Excavated contaminated land material be immediately encapsulated and secured until AT’s remediation plan is drafted, consulted and implemented

1

UU.

Appropriate stormwater controls to prevent contaminated land discharges

1

VV.

Gas monitoring for construction and CRL operation, including personalised staff visitor gas monitoring

1

WW.

Appropriate health and safety management including emergency management plans

1

XX.

Monitoring of fire suppression systems

1

YY.

Personnel responsible for contaminated land management hold appropriate licences

1

ZZ.

Amendments to contaminated soil management plan

1

AB.

Definition of treated groundwater

1

AC.

Full assessment of impact on quality of residential apartments in the area

1

AD.

Additional assessment of the effects on archaeological sites

1

AE.

Ongoing involvement and consultation

1

Late submissions Submission 26, from Heritage New Zealand Pouhere Taonga, was received late on the 6 March 2015 (the submission period closed at 5:00pm on 5 March 2015). Pursuant to section 37 of the RMA, the Commissioners accepted the reporting planner’s recommendation and extended the time for the receipt of submissions to accept the late submission.

Written approvals 10. The applicant has not obtained written approval from any persons. Amendments to the application following notification 11. After the submission period ended, the applicant provided further information on a number of matters. 12. That information formed part of the application and was considered by the Commissioners. The Commissioners accepted that the further information provided was to be within the scope of the original application and, therefore, renotification of the application was not required. 13. All submitters were contacted on 29 May 2015 (by email or letter) and were made aware that further information was provided to Council pursuant to section 92 of City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

7


the RMA. The further information was uploaded onto the Council website alongside the original application material for review and consideration by submitters. This information was available for viewing on the Council website from 2 June 2015. THE PROPOSAL, THE SITE, AND BACKGROUND The Proposal 14. The resource consent package (called Package 1) applied for includes resource consent applications associated with the construction of the CRL infrastructure from the existing Britomart Station to a point just south of the Wyndham and Albert Streets intersection in Auckland City. This includes resource consents for the following matters: 

earthworks, including within a heritage overlay and within an identified floodplain;

activities in and on contaminated land, including under the National Environmental Standard for Assessing and Managing Contaminants in Soil to Protect Human Health;

groundwater take and diversion;

air discharges; and

various discharges to land or water.

15. The operational resource consents that are required for the operation of the CRL will be applied for as part of Resource Consent Package 2 (as defined at paragraphs 27 and 28 of this report). 16. The Britomart Station to Wyndham Street section includes the following construction works: 

cut and cover tunnels from Britomart Station to a point just south of the Albert and Wyndham Streets intersection (approximately 610m in total length);

underpinning of the Chief Post Office (CPO) building;

excavating tunnels that extend into Queen Elizabeth II Square (QE2S) and the Downtown Shopping Centre Site; and

excavating tunnels across Customs Street West and along Albert Street to Wyndham Street.

17. The applicant has divided the proposed construction work into five distinct Active Construction Zones (ACZs), labelled A-E. In addition, six Construction Support Areas (CSAs) are required, labelled 1-6. The CSAs will provide for general activities such as site offices, machinery, parking, construction material storage, wheel washing areas and waste storage and collection. A jet grout pump and City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

8


mixing plant is proposed at CSA 2 and 4 and stormwater and groundwater treatment tanks are proposed at all CSAs with the exception of CSAs 5 and 6. The applicant has stated that storage of up to 24m3 of spoil, engineering fill, drainage material or demolition debris will be provided for at all CSAs with the exception of CSA 6. 18. The applicant has provided a description of the works that are proposed to take place within each ACZ: in summary, the table below describes these works. ACZ

Construction Method

Construction Work

Construction Support Area

A – Britomart Station West

Underpinning, cut and cover bottom up

Construction of two tunnels and underpinning of the CPO

CSA 1 and 2

B – Lower Queen Cut and cover bottom Street Tunnels up

Construction of two tunnels (approximately 43m in length) from CPO building at Britomart Station to a location west of the pedestrian underpass stairs and lift with QE2S

CSA 2

C - Downtown Shopping Centre

Open trench

Construction of two tunnels merging CSA 3 to one tunnel from QE2S to the south west corner of the DSC site (approximately 112m of tunnelling within this ACZ).

D – Customs Street West

Cut and cover bottom up

Construction of one tunnel with two tracks (approximately 30m in length)

CSA 4 and 5

E- Albert Street

Cut and cover bottom up

Construction of one tunnel with two tracks approximately 330m in length

CSA 4, 5 and 6

Site, locality, catchment and environs description 19. The applicant has provided a description of the site, locality, catchment and surrounding environment in the AEE report. 20. In summary, the proposed works are within Auckland’s Central Business District which is a highly modified, intensely developed urban environment. The surrounding land uses include high density office buildings, residential and visitor accommodation, retail, restaurants and bars. As such, the area is highly pedestrianised and is classified as a pedestrian orientated area in the Auckland Council District Plan - Central Area Section 2005. 21. The CRL route in this area has a sloping alignment from north to south, with Albert Street located on the edge of the Queen Street valley and near the ridgeline of Hobson Street. As such, adjoining streets (such as Swanson Street and Wyndham Street) that run down the valley slopes to Queen Street are relatively steep. Britomart Station is located on the route’s lowest point, approximately eight metres below sea level. There are various flood hazards that traverse the works sites, including the CSAs.

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

9


Background CRL Notices of Requirement (NoRs) 22. AT gave notice on 23 August 2013 to Auckland Council of its requirement to designate land in the Auckland Council District Plan (Operative Auckland City Central Area Section and Operative Auckland City Isthmus Section) for the construction, operation and maintenance of the CRL. A total of six NoRs were publicly notified on 25 January 2013 and submissions closed on 19th March 2013. 23. The hearing for the six NoRs was held between August and November 2013. In March 2014 the independent commissioners who heard submissions recommended that the designations be confirmed subject to a range of conditions. There were six appeals lodged and the one outstanding appeal was heard in the Environment Court in June 2015. Contractor Procurement Process 24. AT is progressing an Early Contractor Involvement (ECI) procurement process in relation to the CRL construction works for the Britomart to Wyndham section. The ECI procurement is broken into two packages known as Enabling Works Contract 1 and Contract 2. The construction of the proposed works that are the subject of this report falls within both Contracts 1 and 2. In more detail: 

Contract 1 – includes the building modification works at the western end of Britomart Station, underpinning of the CPO building, and the construction of tunnels and a reinstated pedestrian subway that extends into QE2S.

Contract 2 – includes the cut and cover works from the Customs Street West/Albert Street intersection up to Wyndham Street. This contract also includes a major stormwater diversion between Wellesley Street and Swanson Street, labelled the Albert Street Stormwater Main Realignment.

Britomart Station Designation 25. AT lodged an alteration to the Britomart Transport Centre Designation 314 on 29 May 2015. This alteration includes specific conditions that will apply to the construction and modifications associated with the CRL and ongoing operation and maintenance of the transit centre described in the Auckland Council District Plan (Operative Auckland City Central Area Section) as the Britomart Transport Centre. 26. AT has confirmed that the works being proposed to support the alteration to designation are consistent with those proposed as part of this application. Other consents Resource Consent Package 2 – Aotea Station to the North Auckland Line (NAL) 27. AT has stated that this package will include resource consent applications for the CRL from Aotea Station to the NAL, including the construction of Aotea Station, City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

10


Karangahape Road Station, key utility diversions at the NAL end, as well as the Mt Eden Station extension and connections to the NAL. Package 2 will also seek the necessary resource consents required for the operation of the entire CRL from Britomart Station to the NAL. 28. Package 2 is due to be lodged with the Council for processing in December 2015. Albert Street Stormwater Main Realignment 29. The Albert Street Stormwater Main Realignment project is part of Enabling Works Contract 2 and was granted resource consent by Independent Commissioners for the Council on 20 May 2015. No appeals have been received by the Environment Court on the decision to grant resource consent. Precinct Properties Ltd – Downtown Shopping Centre Redevelopment 30. Precinct Properties Ltd (PPL) has recently been granted resource consents for the re-development of the Downtown Shopping Centre site. The resource consents for the “below ground” works, which include the CRL running tunnels through their proposed basement, were granted on 5 May 2015 on a non-notified basis. The land use consents for the “above ground” works were granted on 10 June 2015 on a non-notified basis. Certificates of Compliance 31. AT has applied for several Certificates of Compliance (CoCs) for the Britomart to Wyndham section, which are being assessed by the Council. RESOURCE CONSENTS REQUIRED AND ACTIVITY STATUS 32. The proposal requires resource consent for the following reasons. Land use consents (s9) – R/REG/2014/5430 Auckland Council Regional Plan: Sediment Control (ACRP:SC) 

The total area of excavation within the Sediment Control Protection Area is 4,200m2 or 0.42 ha which exceeds the 0.25ha permitted threshold and the trenching proposed is greater than 100m. This requires a restricted discretionary activity resource consent pursuant to Rule 5.4.3.1 of the ACRP:SC.

Proposed Auckland Unitary Plan (PAUP) 

The total earthworks for network utilities and road networks within the Business: City Centre zone in excess of 2,500m2 or 2,500m3 that cannot meet the permitted activity standards, specifically the development alters the configuration of an overland flow path, is within 20m of a scheduled historic heritage place and various scheduled sites and places of significance to mana whenua, requires restricted discretionary resource consent pursuant to Rule G.2.3.2 of the PAUP.

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

11


Land use consents (s9) – R/LUC/2014/5428 PAUP 

Earthworks greater than 2,500m2 or 2,500m3 for network utilities and road networks within the Historic Heritage Overlay, specifically the Chief Post Office (CPO) building (reference: 02021), requires a discretionary activity resource consent pursuant to Rule H.4.2.1.2 (activity table). The total amount of earthworks within the CPO totals approximately 20,000m3 of cut and 12,000m3 of fill.

Earthworks greater than 2,500m2 or 2,500m3 for network utilities and road networks within the 100-year Annual Recurrence Interval (ARI) flood plain requires a restricted discretionary resource consent pursuant to Rule H.4.2.1.2 (activity table). A section of the proposed earthwork will occur within the 100 year ARI floodplain.

NES for Assessing and Managing Contaminants in Soil to Protect Human Health (NES:soil) 

The proposed volume of soil disturbance exceeds 25m3 per 500m2 and the volume of soil proposed to be removed from the site will exceed 5m3 per 500m2. The applicant has stated that it cannot be concluded at this time that the soil contamination will not exceed the applicable standards in Regulation 7 and, as such, the soil disturbance requires a discretionary activity resource consent pursuant to Regulation 11 of the NES:soil.

Water permits (s14) – R/REG/2014/5432 Auckland Council Regional Plan: Air, Land & Water (ACRP:ALW) 

The temporary and permanent diversion of groundwater as a result of the proposal may result in potential adverse effects on buildings, structures and services. This requires a restricted discretionary activity resource consent pursuant to Rule 6.5.77 of the ACRP:ALW.

The taking of groundwater for the purposes of a groundwater diversion under Rule 6.5.77 of the ACRP:ALW requires a restricted discretionary activity resource consent pursuant to Rule 6.5.43 of the ACRP:ALW.

The new bores for the proposed dewatering system will be in place for longer than the three month permitted activity standard period and, as a result, a controlled activity resource consent is required pursuant to Rule 6.5.26 of the ACRP:ALW.

PAUP 

The temporary and permanent groundwater diversion from the proposed tunnel excavations will be greater than 1m in diameter. This activity requires a restricted discretionary resource consent pursuant to Rule H.4.17.1 (activity table).

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

12


The dewatering associated with a groundwater diversion that requires a restricted discretionary resource consent also requires a restricted discretionary resource consent pursuant to Rule H.4.17.1 (activity table).

New bores for the proposed dewatering system for purposes not otherwise specified (all zones) requires a controlled activity resource consent pursuant to Rule H.4.17.1 (activity table).

Discharge permits (s15) – R/REG/2014/5435 ACRP:ALW 

The findings of the site investigation report state that soil contamination has not been identified above permitted activity criteria. However, the investigations were limited in scope due to site constraints and, as such, there is potential for contaminated fill to be present within the project footprint. As such, the discharge of contaminants to land and water from the proposed land disturbance requires a restricted discretionary activity resource consent pursuant to Rule 5.5.44A of the ACRP:ALW.

PAUP 

The findings of the site investigation report state that soil contamination has not been identified above permitted activity criteria. However, the investigations were limited in scope due to site constraints and, as such, there is potential for contaminated fill to be present within the project footprint. As such, contaminated land discharges from the proposed land disturbance require restricted discretionary activity resource consent pursuant to Rule H.4.5.1 (activity table).

Note: The applicant originally applied for resource consent for the ongoing discharge of contaminants to land or water pursuant to H.4.5.1 (activity table) and Rule 5.5.43 of the ACRP: ALW. In response to this, although an undefined amount of passive discharge of contaminants may be occurring from this material (given the widespread placement of fill material throughout this are of the CBD), Auckland Council has confirmed that a long term consent for the discharge of contaminants will not be required following the completion of the construction works. Discharge permits (s15) – R/REG/2014/5436 ACRP:ALW 

The proposed discharge of wastewater and/or washwater to land or water is subject to the “other” discharge provisions and can be considered a permitted activity pursuant to Rule 5.5.54 and 5.5.55 if the applicable standards can be met. The applicant has stated that there remains uncertainty regarding the quality of discharges as a result of potential unknown ground contamination. As such, the proposed discharges to land or water requires a discretionary activity resource consent pursuant to Rule 5.5.68 of the ACRP:ALW.

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

13


PAUP 

The proposed discharge of water or wastewater can be considered a permitted activity pursuant to Rule H.4.18.1 (activity table) if the permitted activity standards can be met at section H.4.18.2.1.1. The applicant has stated that there remains uncertainty regarding the quality of discharges as a result of potential unknown ground contamination. As such, the discharge of water or wastewater requires a discretionary activity resource consent pursuant to Rule H.4.18.1 (activity table).

Discharges for the purpose of dewatering trenches or other excavations can be considered a permitted activity pursuant to Rule H.4.18.1 (activity table) if the permitted activity standards can be met at section H.4.18.2.1.5. The applicant has stated that there remains uncertainty regarding the quality of discharges as a result of potential unknown ground contamination. As such, the discharge for the purpose of dewatering trenches or other excavations requires a discretionary activity resource consent pursuant to Rule H.4.18.1 (activity table).

Discharge permits (s15) – R/REG/2014/5437 ACRP:ALW 

While the applicant has stated that it is their intention to manage the works to ensure compliance with the permitted activity rule standards (Rule 4.5.49), because of the very close proximity and high sensitivity of the receiving environment the applicant has applied for a restricted discretionary resource consent is required pursuant to Rule 4.5.56 of the ACRP:ALW.

PAUP 

While the applicant has stated that it is their intention to manage the works to ensure compliance with the permitted activity rule standards (section H.4.1.3.1.1), because of the very close proximity and high sensitivity of the receiving environment the applicant has applied for a restricted discretionary resource consent is required pursuant to Rule H.4.1.1 (activity table) of the PAUP.

33. The proposal involves multiple resource consents under different plans. In this instance the consents required are either controlled, restricted discretionary or discretionary. Where there is an overlap between the consents and / or the effects of the activities, so that consideration of one could affect the outcome of another, the appropriate practice is to treat the applications together. The applicant has applied for the relevant resource consents, required under both the operative plans and the proposed plan, together as a ‘bundled’ application and Council is considering the applications in the same holistic manner. Overall the proposal has been considered as a discretionary activity. City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

14


Representations at the hearing 34. The section 42A report prepared by the Council’s reporting planner had been precirculated and was taken as read. 35. Mr Beatson presented opening legal submissions for the applicant and called a range of expert witnesses to present summaries of their evidence and respond to questions. 36. We then heard from submitters and from Council officers and consultants. 37. Mr Beatson completed his right of reply verbally, except for the final set of draft conditions which were circulated on 8 July 2015 for comments by 10 July 2015. Relevant statutory provisions considered 38. When considering an application for resource consent for a discretionary or noncomplying activity we must have regard to Part 2 (“purpose and principles” – sections 5 to 8), and sections 104 and 104B and, where relevant, sections 105, 107 and 108. 39. When considering any actual or potential effects, we may disregard any adverse effects that arise from permitted activities in a NES or a plan (the permitted baseline); we have a discretion whether to apply this permitted baseline. Relevant standards, policy statements and plan provisions considered 40. In accordance with section 104(1)(b)(i)-(vi) of the RMA, we have had regard to the relevant policy statements and plan provisions of the following documents, noting that no national policy statements are relevant to this application. 

National Environmental Standard – s104(1)(b)(i) o

National Environmental Standard for Assessing and Managing Contaminants in Soil to Protect Human Health (NES:soil)

o

National Environmental Standard for Air Quality (NES:AQ)

New Zealand Coastal Policy Statement – s104(1)(b)(iv) (NZCPS)

Hauraki Gulf Marine Park Act 2000 – s104(1)(b)(iv) (HGMPA)

Auckland Council Regional Policy Statement – s104(1)(b)(v)

Part 1 of the Proposed Auckland Unitary Plan – s104(1)(b)(v)

Plan or Proposed Plan – section 104(1)(b)(vi) o

Auckland Council Regional Plan: Air, Land & Water

o

Auckland Council Regional Plan: Sediment Control (ACRP:SC)

o

Proposed Auckland Unitary Plan

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

15


Weighting 41. The Commissioners agree with the reporting planner that as the Project is not contrary to the objectives and policies under both the operative plans and the proposed plan. And as the outcomes are the same under the operative and the proposed plan frameworks, no weighting is necessary. Summary of evidence heard 42. The Council planning officer’s recommendation report was circulated prior to the hearing and taken as read. 43. The evidence presented at the hearing responded to the issues and concerns identified in the Council’s section 42A report, the application itself and the submissions made on the application. Applicant 44. The evidence presented by the applicant at the hearing is summarised below, including legal submissions presented by Mr Beatson which addressed the following: 

Confirmation that the current application seeks resource consents for construction of the Britomart to Wyndham Street section of the CRL (the Project) and that consents for the remainder of the CRL from Wyndham Street to the North Auckland Line at Mt Eden Station are due to be lodged in late 2015.

The key issues, being groundwater and settlement effects, and the impact that those effects will have on surrounding buildings; and the use of alert, alarm and stop work levels to ensure that no more than ‘slight’ damage will be caused to buildings (as defined by Burland).

The proposal to engage an independent buildings specialist to assist in determining and avoiding damage to buildings caused by settlement.

The need for the CRL; construction sequencing in the five active construction zones (ACZs); and the key effects of the consent package.

A response to the Council section 42A report, and in particular the degree of conservatism applied in predicting groundwater and settlement effects; the adaptive management technique and the ability to rely on conditions.

A response to submissions and statutory matters, including Part 2.

All the expert evidence of the applicant had been pre-read by the Commissioners, enabling the applicant’s witnesses to summarise their statements and respond to questions. Scott Elwarth, AT’s Construction Manager, advised that the cut and cover construction of this section of the CRL is critical to the Project; that the proposed strategy of CRL enabling works contracts will mitigate disruption and enable other developments to proceed; and completing the enabling works ahead of other planned projects will avoid disruption to newly established operations and potential damage to newly built infrastructure. City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

16


Colin Ingoe, of AT’s Infrastructure Division, observed that the rationale for the adopted CRL consenting strategy is robust and appropriate to enable the CRL Project, and outlined the consultation and engagement undertaken, stating that it was appropriate, given the scale and nature of the Project. Bill Newns, Chartered Engineer, presented three statements 

In the first statement, relating to design and construction, Mr Newns summarised the proposed works and construction methodology – engineering design and indicative construction methodologies including work site and construction support area locations and activities, design constraints and alternatives considered, and an indicative construction programme, referring to a draft Erosion and Sediment Control Management Plan and the draft Environmental Management Plan.

In his second statement, Mr Newns commented on ground settlement matters - the technical assessment methodology, settlement estimates, assessment of the effects on utilities, roads and infrastructure, monitoring and contingency measures, and proposed conditions, concluding that “Whilst adverse construction effects and in particular ‘damage’ can and should be mitigated as far as reasonably practicable, they cannot in all instances be subject to a requirement that they be avoided as there are always elements of uncertainty in geotechnical engineering and the costs of ‘avoiding’ the potential effects may be disproportionate to the costs of rectification. Very few of the buildings along the CRL Enabling Works corridor are subject to these very small risks ….In the most unlikely event of such risks occurring, and where it is demonstrated to be a result of the works …. Such damage will in all cases be repaired by 1 AT. ”

In his supplementary statement of evidence, Mr Newns updated the position following further discussions with AC and responses to submitters, concluding that “The potential effects of settlement associated with the construction of the Britomart Station to Wyndham Street section of the City Rail Link will be less than minor and are able to be 2 managed through the conditions proposed. ”

Alan Pattle, an engineer with a recognised speciality in water resources (including groundwater flow) and environmental engineering, addressed groundwater issues, conditions and effects, expected cumulative impacts of the Project with the Downtown Shopping Centre Re-development, conditions and other relevant matters. He advised that groundwater levels would be monitored and alert trigger levels established to provide a check that the measured levels are within modelled predictions, noting that groundwater response is an indicator of potential ground settlement. Eric Stevenson, Structural Engineer, provided two statements of evidence: 

1 2

In the first, he addressed the combined potential adverse effects on building structures associated with construction excavation induced settlement along the tunnel alignment and advised that potential adverse effects on buildings can be avoided by good design and workmanship; implementation of pre-construction building assessments; and construction phase monitoring of buildings. If any adverse

Second statement of evidence of Bill Newns dated 19 June 2015, paragraph 85 Supplementary statement of evidence of Bill Newns dated 6 July 2015, paragraph 55

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

17


effects do occur, in Mr Stevenson’s opinion, these would be acceptable, in terms of being negligible to slight, with regard to potential structural damage to all the buildings within the Project’s zone of influence. That is, any damage would only be of a superficial or aesthetic nature. 

In his supplementary statement of evidence, Mr Stevenson updated his evidence in chief and provided a memorandum setting out building settlement assessment calculations. He confirmed his opinion that the potential effects of excavation-induced mechanical settlement and settlement resulting from consolidation of the soil due to groundwater drawdown on built structures would generally be acceptable and able to be managed through conditions, detailed design and construction.

Bruce Petry, Heritage and Conservation Architect, advised that the potential construction effects on heritage values of identified scheduled buildings will be minor; and confirmed that any potential effects on identified built heritage resulting from ground settlement could be appropriately managed through monitoring and mitigation measures, including pre- and post-condition surveys, and the rectification of any damage. Andrew Hart, Senior Environmental Scientist, provided evidence on the assessment and management of contaminated land in the Project area. Key findings of his evidence were that there are potential contamination effects associated with proposed soil disturbance; and that mitigation of these effects can be achieved through excavation and disposal methods, and by following the relevant management plan. Richard Chilton, Senior Air Quality Scientist, noted that without mitigation, the Project has the potential to generate offensive or objectionable dust effects in the sensitive receiving environment; but that with the proposed mitigation and monitoring effectively implemented, these effects will be no more than minor. Sarah Sutherland, Senior Environmental Scientist, addressed water management aspects of the Project, identifying stormwater runoff discharge measures from the CSAs to the stormwater system, and that all water generated within the ACZs will be collected and treated onsite prior to discharge to the stormwater system. Jennifer Carvill, Planner and Resource Management Consultant, provided two statements of evidence: 

In the first, Ms Carvill gave comprehensive evidence of the proposal, the existing environment, reasons for consent, assessment of effects, the statutory assessment, a response to submissions and the Council section 42A report, and then discussed the proposed conditions. Ms Carvill found that the Project is consistent with relevant objectives and policies; that any adverse effects can be appropriately avoided, remedied or mitigated; and that the Project is in accordance with Part 2 of the RMA. Ms Carvill provided a set of conditions and identified those areas in respect of which discussions with relevant Council officers were ongoing.

In her supplementary statement, Ms Carvill updated her evidence in chief in relation to conditions of consent.

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

18


Submitters 45. The evidence presented by the submitters at the hearing is summarised below. Duncan McKenzie, Heritage Advisor Planning, for Heritage New Zealand Pouhere Taonga, provided a statement of evidence relating to effects on heritage buildings and archaeology, and further notes dated 7 July 2015. Mr McKenzie spoke to his written evidence at the hearing and responded to questions from the Hearing Panel. . Mr McKenzie confirmed that Heritage New Zealand’s concerns relating to built heritage are met to the extent that he has no further concerns, and that given the archaeological authority sought by the applicant, no accidental discovery protocols would be required. Mr McKenzie did request that the project take the opportunity to provide public education on the history of the site and any archaeological material identified or recovered during the works. Richard Brabant, Legal Counsel, appeared for 152 Quay Street (Harbour View Building) Body Corporate 107678; 148 Quay Street Body Corporate 164980; and Pandy Hotel Corporation (building owner of the hotel building on the corner of Custom and Queen Streets). He expressed his clients’ concerns relating to ground settlement and commented on conditions of consent. Gavin Alexander, Technical Director Beca, provided two statements of evidence in support of Mr Brabant’s clients: 

In his first statement, Mr Alexander addressed the buildings at 148 Quay Street, 152 Quay Street and 2-8 Customs Street, all in the vicinity of the CPO and Lower Queen Street (LQS) portion of the CRL Project. Mr Alexander expected these structures to be relatively resistant to the effects of settlement occurring in the soils overlying the Waitemata Group rock at this location. However, he did express reservations regarding the level of certainty inherent in the applicant’s groundwater drawdown predictions. Mr Alexander promoted the inclusion of alarm and stop-work limits for groundwater drawdown, in addition to the applicant’s proposed triggers for ground settlement.

His supplementary statement responded to Mr Newns’ supplementary statement and commented on updated conditions following discussions held with the applicant’s team.

Noel Playle and Gordon Nelson appeared for the Endeans’ Building, Body Corporate 095035, 2 Queen Street, noting their concerns and the lack of consultation with the applicant in respect of their heritage building. Mr Playle stressed the building’s age (100 years’ old) and the recent substantial repair and upgrade that had been carried out. He raised issues relating to access to the building during construction; noise levels and hours of operation; dust, safety and security. Mr Nelson provided details of the building’s construction and foundation piles, raising concerns about construction-related settlement, particularly given the recent building upgrade to a high standard. Noise was also raised as an issue. Mr Nelson also sought certainty that access would be maintained to complete the building maintenance works that must be completed within the CRL construction period. City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

19


The applicant and the submitters took the opportunity during the hearing to remedy the perceived lack of consultation and the airing of the submitters’ concerns was taken on board by the applicant. Amanda Stoltz, Legal Counsel, appeared on behalf of the Stamford Residences’ Owners Corporation, 22-26 Albert Street. Her client sought a site-specific management plan for the property or alternative conditions to address her client’s concerns through the proposed Construction Environmental Management Plan and the Groundwater and Settlement Monitoring and Contingency Plan. Air discharge concerns were also raised. Vicki Morrison-Shaw, Legal Counsel, appeared for Cooper and Company NZ, identifying that her client’s key remaining areas of concern related to other approvals necessary; affected party liaison group; review and groundwater / settlement. Vijay Lala, resource management planning consultant, gave evidence in support of Ms Morrison-Shaw’s client. Mr Lala advised that subject to the adoption of Council’s recommended conditions, and the submitter’s concerns identified by Counsel being adequately addressed through conditions, potential adverse effects could be avoided, remedied or mitigated. Trevor Wilkinson, who resides in the Quay West Apartments, Albert Street, tabled evidence seeking that his genuine concerns relating to health and safety are safeguarded. Catherine Reaburn, planning consultant, tabled evidence on behalf of Precinct Properties Ltd (which has an interest in 1, 7 and 21 Queen Street and 23 Albert Street and did not appear at the hearing. Ms Reaburn expressed support for the Council’s recommended conditions in relation to construction management and groundwater monitoring and contingency. 46. For the Council, Mr Gysberts advised that discussions with the applicant and interested submitters was ongoing and useful, resulting in refinements to the conditions. 47. Following Mr Beatson’s partial right of reply, the hearing was adjourned as at midday on Wednesday 8 July 2015, to provide the opportunity for discourse between the parties attending the hearing regarding the draft conditions. 48. Subsequent to the hearing, AT and AC officers met and agreed on a draft set of conditions, which was forwarded to all parties attending the hearing for comment by Friday 10 June 2015. 49. Feedback was received, and the Commissioners then met on Tuesday 28 July 2015 to consider the latest set of conditions and the feedback from various submitters. Following that meeting, they determined that they had sufficient information to close the hearing and the hearing was declared closed on 29 July 2015. PRINCIPAL ISSUES IN CONTENTION 50. The parties were in agreement over most aspects of the Project and no party appearing at the hearing was opposed to the Project occurring, subject to appropriate conditions.

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

20


51. At the commencement of the hearing, Auckland Council had held reservations about the applicability of the Burland Stage 2 method for the calculation of tensile strain, and as a consequence expressed uncertainty regarding the reliability of the predicted actual and potential effects on buildings and services. At that time, Auckland Council was not satisfied that building damage would be limited to the ‘slight’ (Burland Class 2) category, based on the information provided by the applicant. 52. However, and as noted above, parties took the opportunity during the hearing to conduct parallel, side-bar discussions on matters of concern and the wording of conditions to address those concerns. As a result, the Commissioners were presented with an agreed set of conditions with which to work. Consequently, in addition to the broader considerations under the RMA and the relevant planning documents, our attention was focused on: 

The extent of actual or potential adverse effects on the environment and whether these effects can be avoided, remedied or mitigated to be minor, or avoided or mitigated to an acceptable level;

Whether the various management plans proposed would effectively address the matters of concern; and

The wording of the agreed conditions.

53. We comment on these principal issues below in the discussion on adverse effects FINDINGS ON PRINCIPAL ISSUES – ADVERSE EFFECTS ON THE ENVIRONMENT What is the ‘environment’ for the purposes of considering the actual and potential adverse effects of the proposal? 54. The existing environment comprises a busy, high-density built-up urban area with a range of land uses and including busy traffic routes and heritage buildings. The land uses are all sensitive to varying degrees to the potential effects associated with the proposed construction works, including traffic disruption, noise and vibration. Effects that must be disregarded Any effect on a person who has given written approval to the application No person has given their written approval to the application. Trade competition There are no trade competition effects that must be disregarded. Effects that may be disregarded – Permitted Baseline assessment 55. The permitted baseline approach, which refers to permitted activities on the subject site, is of limited value for this application, and the Commissioners have not relied on it to discount adverse effects from permitted activities. However AT’s applications for CoCs for various aspects of the Project do constitute the permitted baseline for this project. City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

21


Assessment of Effects Positive Effects 56. In the AEE, the applicant identified potential positive effects that will result from the Project as well as the broader positive effects from the wider CRL project. The Commissioners agree with the applicant’s assessment of positive effects. Effects from Earthworks 57. The proposal is for approximately 143,000m3 of cut and 82,000m3 of fill along the route, over a cumulative area of approximately 11,000m2. The main methods of sediment and erosion control include clean water diversions, settlement tanks, stormwater inlet protection, chemical treatment and progressive stabilisation. The immediate receiving environment for any generated runoff will be to the stormwater network and subsequently the Waitemata Harbour, discharging near the ferry terminal. All of these methods are in accordance with the industry best practice and Auckland Council’s Technical Publication 90 – Erosion and Sediment Control Guidelines for Land Disturbing Activities in the Auckland Region (TP90). 58. We accept that the applicant’s assessment and evidence adequately identify the potential adverse effects resulting from the earthworks and that the proposed mitigation measures are appropriate given the relatively small volume and area of earthworks and the receiving environment. 59. The final Erosion and Sediment Control Plan (ESCP) will be submitted to Council for certification prior to any earthworks commencing as part of the overall Construction Environmental Management Plan (CEMP). This will be supported by a Chemical Treatment Management Plan (CTMP) that will outline the procedures for chemically flocculating sediment laden water prior to being discharged from the site. We agree with the Council’s specialist for earthworks, Stephanie Benucci, that subject to the measures included in these plans being implemented correctly, adverse effects relating to the discharge of treated sediment laden water from the proposed earthworks will not be significant and will be appropriately mitigated. We find the adverse effects from earthworks on the environment will be minor. 60. We note that the conditions provided to us, as agreed between the applicant and Auckland Council, could better reflect the degree of integration necessary between the ESCP, the CTMP and the Contaminated Soils Management Plan (CSMP). Consequently, we have made minor changes to those conditions to reflect the inter-related function of those management plans. Effects on Existing Flood Plains 61. Relatively small, isolated areas of 1% AEP flood plain (localised ponding) are identified at several locations along the proposed route, as denoted on the PAUP maps. Works within these areas trigger restricted discretionary activity rule infringement under Chapter H4.2 of the PAUP. Potential adverse effects from flooding were not raised by submitters and we accept the assessment by Council’s specialist, Scott Paton, that finished levels around the shafts will be City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

22


similar to the pre-existing condition and will not alter floodwater characteristics. We find that the works will not have an adverse effect on flooding within or beyond the site. Air Quality Effects 62. Air quality effects from the potential discharges of contaminants to air from construction and earthworks associated with the Project were assessed by Paul Crimmins, Senior Consents and Compliance Advisor, Air Quality Team in AC’s Natural Resources and Specialist Input Unit. 63. Mr Crimmins concurred with the applicant that any potential dust effects can be adequately mitigated through the Air Quality Management Plan (AQMP) so that adverse effects arising from these discharges are not significant. 64. We accept the unanimous opinion of the experts that the mitigation measures proposed in the draft AQMP – including the monitoring regime – represent the Best Practicable Option (BPO) for minimising discharges of contaminants to air, in particular, the most significant contaminant, which is dust. 65. Any odorous discharges which may arise from excavations, particularly if soils which have been contaminated by hydrocarbons are encountered, will be addressed through a specific Contaminated Soils Management Plan (CSMP). Cultural Effects 66. The Cultural Impact Assessment (“CIA”) information requirement in the PAUP is triggered by the proposal, in order for Council to assess the adverse effects on Mana Whenua values. Whilst AT’s engagement with Manu Whenua groups has been appropriate, no CIAs have been prepared to date. 67. One submission was received from Mana Whenua, being Ngāti Maru, but to date, no determination has been provided to Council as to whether Ngāti Maru wishes to prepare and submit a CIA. The issues raised are that the proposal compromises the interests of Ngāti Maru protected by the RMA and that the consultation on the proposal is incomplete. The Commissioners reject the latter issue, as we find that the consultation undertaken to date by the applicant has been thorough and extensive. 68. The applicant has emphasised the areas where Mana Whenua interest relating to this project has been identified, being earthworks, stormwater and groundwater and the corresponding discharges to the environment; the protection of the Hauraki Gulf from contaminants such as stormwater; and improving water quality outcomes in the catchment. We are satisfied that the applicant is proposing to use best practice methods to ensure the receiving environment is not compromised by the proposed discharges. 69. The Commissioners accept that the actual and potential effects on cultural values have been adequately addressed.

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

23


Contaminated Land Discharge Effects 70. The effects from the discharge of contaminants to land and water from the disturbance of contaminated land have been addressed in the evidence of Andrew Hart and Sarah Sutherland and covered in the draft Contaminated Soils Management Plan (CSMP), which provides management procedures and measures relevant to handling and disposal of contaminated material to mitigate potential adverse effects on the environment and human health. The measures include erosion and sediment controls, measures for monitoring groundwater quality and alternative disposal procedures, and procedures for the excavation, handling and disposal of contaminated and potentially contaminated soil. These details have been assessed by the Council’s in-house expert for contaminated land, Andrew Kalbarczyk and consultant expert Rob Burden, who have reported that with implementation of the CSMP, adverse effects can be appropriately mitigated and managed. Only one submission was received on these matters, that being from the Auckland Regional Public Health Service. Mr Burden is satisfied that the proposed conditions will adequately address the matters raised in that submission. 71. The Commissioners agree with Mr Kalbarczyk and Mr Burden, and the evidence presented on behalf of the applicant. Given the concentrations of contaminants are low and are isolated occurrences, the proposed mitigation measures will appropriately address excavation and disposal of soil and groundwater. The submission of the final CSMP as part of the overall CEMP for certification by Council, and its implementation, will ensure that the adverse effects on the environment from the disturbance and handling of potentially contaminated soil and groundwater will be minor. Again, we have made minor changes to the agreed conditions to better link the CSMP with the ESCP. Effects from the Discharge of Wastewater and/or Washwater on Water Quality 72. The effects from the discharge of wastewater and/or washwater to land and water during construction have been assessed. There are a number of potential sources of water that require management during construction, and in addition to the treatment of discharges, source controls are proposed to reduce sediment loadings in the discharge. The use of an Environmental Management Plan (EMP) will manage the CSAs, ensuring that structural controls are installed and implemented. 73. The applicant proposes an ongoing monitoring regime to ensure that the anticipated water quality standards are met and has included options if limits are exceeded. 74. The Commissioners accept that given the proposed site and wastewater and/or washwater management measures, any adverse effects of the proposed discharge activity on the environment will be less than minor.

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

24


Transport Network Effects 75. The Commissioners have adopted the view that construction related effects on the transport network associated with the earthworks activity is a matter that should be considered. 76. Through the assessment of the NoRs, the effects from construction traffic associated with the proposal were assessed and it was found that adverse temporary effects to the existing road transport network and property accesses during the construction of the CRL will be significant; that the establishment of various construction areas will generate additional traffic in the form of construction vehicles; and that the level of service on the Quality Transit Network in the City Centre can be expected to be low to moderate. 77. The actual and potential construction related effects on the transport network were assessed under the NoRs and various conditions were subsequently confirmed by AT. The Commissioners accept that the construction traffic related conditions for the NoRs are generally appropriate to avoid, remedy or mitigate the actual and potential effects from construction traffic. Specifically, the Transport, Access and Parking Delivery Work Package, monitoring requirements, the specific requirements for the Britomart Station to Mayoral Drive section and the communication and consultation requirements required in the confirmed conditions will achieve this outcome. Construction Noise Effects 78. Construction noise is a district plan land use matter and has been addressed through the NoR process; however, as it is currently drafted, the PAUP suggests that construction noise effects associated with the earthworks activity is a matter that should be considered by Council. 79. The actual and potential construction noise effects were assessed by an independent Hearing Panel for the NoRs and various conditions were recommended and subsequently confirmed by AT. The confirmed conditions seek to avoid, remedy or mitigate specific construction noise effects and include specific construction noise project standards for various construction activities and for various types of receivers. A Site Specific Construction Noise Management Plan (SSCNMP) must be developed in specified circumstances and a Construction Noise and Vibration Delivery Work Package (CNVDWP) must also be submitted to Council. 80. Whilst various submitters have raised concerns with respect to construction noise, the Commissioners accept that the condition framework in the CRL NoRs appropriately avoids, remedies or mitigates the adverse construction noise effects from the proposal. Effects on Utilities 81. The applicant has identified the existing services in the project area and the Council’s assessment is that any effects from ground settlement can be avoided, City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

25


remedied or mitigated subject to the recommended conditions of consent. Damage can also result from uncovering services in unknown locations but such events can be managed by ensuring contact with utility operators and suitable measures being taken to ensure that services are adequately supported or managed once exposed. 82. On that basis we agree that any adverse effects on existing infrastructure will be appropriately managed so that the effects will be minor. Dewatering/settlement, takes and diversion of groundwater 83. Potential settlement effects on buildings, structures and utilities is a key matter raised in submissions and was the main point of conjecture between the applicant and Auckland Council at the commencement of the hearing, noting that those parties have subsequently agreed on all recommended conditions. 84. In brief, technical reports and evidence relating to the potential effects of the proposal on buildings, other structures and services was focussed on the following elements: 

The extent to which groundwater levels will be altered during excavation and post excavation;

The likely ground response (consolidation and mechanical settlement) that will occur as a result of groundwater changes; and

The potential effects that ground responses will have on various buildings in the vicinity of the works.

85. Leading into the hearing, Auckland Council indicated acceptance of the Burland Stage 1 method for categorising levels of effects of ground settlement on buildings. However, it expressed concern about the application of the Burland Stage 2 method for the calculation of tensile strain, and consequently held uncertainty on the likely actual and potential effects on buildings and services. At that time the Auckland Council was not satisfied that building damage would be limited to the ‘slight’ (Burland Class 2) category, based on the information provided by the applicant. 86. Submitters representing building owners along the route could be grouped into those within the predicted settlement contours, and those immediately beyond those contours. The former included buildings along Albert Street (including Stamford Residences represented by Ms Stoltz), the Precinct Properties Building at 23 Albert Street and 7 Queen Street (addressed by Ms Reaburn), and the Chief Post Office Building (CPO) leased by Cooper & Co (addressed by Mr Lala and represented by Ms Morrison-Shaw). The latter groups include the body corporates represented by Mr Brabant, the Endeans Building (represented by Messrs Playle and Nelson), and the Precinct Properties buildings at 1 and 21 Queen St (addressed by Ms Reaburn).

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

26


87. For submitters, those within the predicted settlement contours sought assurance that effects would be within the predicted range (no more than ‘slight’ on the Burland scale), and that an appropriate extent and duration of monitoring, and responses to repair effects would be undertaken. 88. Submitters representing owners of buildings outside the predicted settlement contours sought assurance that the effects of the works would be no more than ‘negligible’ on the Burland scale, and that an appropriate extent and duration of monitoring, and response would be undertaken. Those submitters sought a clear separation in consent conditions between their properties and those within the predicted settlement contours. 89. The predicted building responses were influenced by the variability of ground conditions along the route as well as the foundation conditions of various buildings, with newer buildings being founded on unweathered East Coast Bays Formation (ECBF) rock. 90. The final set of conditions presented to us during the adjournment provided an agreed position between the Auckland Council and the applicant. They also accommodated many changes sought by submitters. In summary, those conditions: 

Distinguish between buildings inside and outside the predicted settlement contours;

Include identified buildings located outside the predicted settlement contours in the list of buildings to be subject to pre-construction surveys and to be monitored during and post-construction (Appendix 1).

Include specific building movement alarm and trigger levels for the identified buildings located outside the predicted settlement contours (Appendix 4).

Require that the project be monitored and managed to ensure that building damage within the predicted settlement contours does not exceed the “slight” category of Burland Class 2 (Condition 88).

Require that the project be monitored and managed to ensure that building damage outside the predicted settlement contours does not exceed the “negligible” category of the Burland Class 1 (Condition 88).

Provide additional building monitoring marks on 2-8 Customs Street (Mercure Hotel)

91. The applicant also included a detailed condition that specifically requires that any damage to buildings, structures or services that is caused wholly or in part by the exercising of the consent shall be remedied at the consent holder’s expense. 92. In considering the potential groundwater and settlement effects of the proposal, we must be satisfied that the predictions of settlement and effects on buildings presented to us is appropriately reliable and conservative to the extent that adverse effects are generally avoided and, where not avoided, within the predicted scale of effects that have been considered by submitters. City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

27


93. Mr Pattle described additional modelling undertaken in response to Auckland Council feedback, and the level of conservatism he anticipated in the model outputs. He considered likely groundwater drawdowns and informed the predictions of consolidation of compressible soils provided by Mr Newns. Mr Pattle’s modelling was based on cut-off walls and soldier pile walls extending to the top of the un-weathered ECBF rock, and the cut-off walls under the CPO building extending 2m into the un-weathered ECBF. 94. With respect to Britomart Station and the CPO, he considered effects to be within the range experienced during the previous development of the Britomart Station and within seasonal variations, which provided a level of confidence regarding likely effects in that location. Continuous pile walls will be constructed in the vicinity of the CPO building and lower Queen Street, and a consent condition has been offered and included limiting groundwater egress in that area to “no visible seepage”. ACZA and sheet piles and temporary soldier pile walls are proposed along the route of the cut and cover tunnels for the Britomart Station to lower Albert Street. A condition has also been included to reinforce the requirement for temporary perimeter cut-off walls from the CPO to chainage 300m (lower Albert Street) to achieve no more than 0.3m3/day ingress (though the wall) of groundwater per 10m of wall. 95. Along Albert Street Mr Pattle predicts that the most significant groundwater changes will occur within the shallower, perched water tables in the upper horizons of soil and fill. These changes are predicted to be limited in lateral extent and will have been influenced by previous building construction. 96. Post-construction, Mr Pattle predicted that groundwater levels will return to the pre-construction state. 97. In addition to their evidence in chief, Messrs Newns and Stevenson provided supplementary evidence to address ground settlement predictions and building responses respectively. Mr Newns provided further background to the Burland method for assessing building damage risk. They both re-affirmed their confidence in the Burland method (Stage 1 and 2) as being appropriate for use in the context of this project. 98. Mr Stevenson explained the output of additional modelling undertaken that reassessed mechanical settlement effects utilising the method preferred by the Auckland Council technical reviewers. This modelling particularly sought to address the Auckland Council concerns regarding the predictions of tensile strain and subsequently suitability of Burland Stage 2. Mr Stevenson also reiterated and explained his confidence in his earlier modelling. Mr Stevenson and Mr Newns reported on a reassessment of consolidation settlement, based on revised data provided by Mr Pattle, and a reassessment of combined mechanical and consolidation induced settlements. These calculations indicated a potential increase in settlement predictions. However, Mr Stevenson reaffirmed that the predicted building damage within the predicted settlement contours would be no more than the ‘slight’ range under Burland Class 2, as originally predicted. City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

28


99. Mr Newns explained that the detailed design of the project will be subject to the building consent process, which will ensure that the design achieves the performance criteria of the resource consent conditions. Mr Hazard, on behalf of Auckland Council, confirmed that this process is successfully occurring on other infrastructure projects and expressed confidence that the appropriate level of integration between the resource consent compliance and building consent functions of the Council would be achieved in this instance. 100. A key element of the set of conditions now agreed between the applicant and Auckland Council is the linkage between imposed performance standards, the establishment and implementation of a Groundwater and Settlement Monitoring and Contingency Plan (“GSMCP”), pre-construction building condition assessments, ongoing building assessments (based on specific criteria), and responses to identified damage. Building inspections are to be undertaken by an independent senior qualified person, whose role will include inspecting and reporting on any identified damage that is attributable to the project, and methods to remedy such damage. The independent senior qualified person shall also assess and advise on mitigation measures that may be necessary to avoid damage in the event that ground or building monitoring alert levels are triggered. The role of the independent senior qualified person will be independent of, and will not diminish, the Auckland Council’s compliance monitoring and enforcement function. 101. We are now satisfied that the applicant has undertaken an appropriate level of investigation and has achieved the necessary level of certainty regarding the likely effects of the works, and how those effects will be minimised and mitigated. Further, we are satisfied that the agreed conditions provide an appropriate range of performance standards, monitoring and response processes that will ensure that the effects of the project remain within the predicted levels. We are also satisfied that the agreed conditions accommodate the matters sought by submitters to an appropriate extent, and correctly distinguish between the anticipated maximum building damage effects anticipated by submitters within, and outside, the predicted settlement contours. 102. Overall, we find that the groundwater, settlement and potential building damage effects from the project will be negligible to minor, and will be appropriately managed and mitigated through implementation of conditions. Effects from Earthworks on Built Heritage 103. The proposed works are within the Heritage Overlay for the CPO (12 Queen Street) and are also within close proximity of several other scheduled historic places. The applicant has provided a Built Heritage Risk Assessment Summary concerning each of these buildings, which have been assessed to fall within the “Negligible” to “Slight” damage classifications under the Burland damage classification categories which corresponds to aesthetic damage only. 104. As a result of strengthening work carried out on the CPO, and given the recommended conditions of consent, differential movement and settlement in this City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

29


area is very unlikely; in addition, post-construction monitoring will be undertaken for a minimum of three months after completion of construction. 105. The Commissioners accept that the effects from the proposed earthworks on identified heritage buildings within 20m of the Heritage Overlay in the PAUP will be appropriately avoided, remedied or mitigated subject to the recommended consent conditions. 106. Specific heritage issues raised by submitters have been addressed by the applicant. Adverse Effects – Summary and Conclusion 107. In summary, construction of the Project will give rise to a range of temporary adverse environmental effects; some may be more than minor for a limited or longer period. However, when considered overall and in the context of their temporary nature, we agree that the revised and finalised conditions of consent agreed by the applicant, Council officers and those submitters present at the hearing, and, in particular the monitoring and mitigation measures, will ensure that actual and potential effects can be avoided, remedied or adequately mitigated. 108. In conclusion, we find that the actual and potential effects from this project, including dust, sediment, contamination, ground settlement, water quality, public health, built heritage effects from earthworks, construction traffic and noise effects are temporary in nature and can be avoided, remedied or mitigated through implementation of the consent conditions. 109. The positive effects from the proposal must not be overlooked, particularly realising the potential of the existing infrastructure and unlocking the Auckland rail network by enabling Britomart to become a through station rather than a terminus station. 110. The proposal has been assessed against the provisions of the relevant planning documents in the application details, in the section 42A report and in the evidence of Ms Carvill. In the latter statement it is pointed out the project requires resource consent pursuant to the following regional plans and unitary plan: 

Auckland Council Regional Plan: Air, Land, Water 2013 (ACRP: ALW);

Auckland Council Regional Plan: Sediment Control 2001 (ACRP: SC);

Proposed Auckland Unitary Plan 2013 (PAUP).

111. In addition, resource consent is required pursuant to the Resource Management (National Environmental Standard for Assessing and Managing Contaminants and Soil to Protect Human Health) Regulations 2011 (NESSoil). The resource consents required are land use consents, water permits and discharge permits and, in addition, the land use consent pursuant to the NESSoil to disturb soil. 112. It is also relevant to note, as is covered in another part of this decision, that the area surrounding the project corridor is occupied by a number of identified heritage buildings that are potentially affected and works are also proposed within City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

30


a scheduled historic heritage place (the Chief Post Office). Further, part of the project corridor runs through a scheduled site of significance to mana whenua (Ngahu Wera) and within 20m of another scheduled site of significance (Nga Wharau a Tako). 113. We note that in applying the most restrictive activity status, which was the common approach of the Council’s reporting officer and the expert witnesses at the hearing, that when bundled, the overall activity status for the resource consent applications is discretionary. 114. We find that the proposal is consistent with the above listed planning documents in providing for a public work with benefits to the City while also appropriately managing the potential adverse effects arising from its construction. The CRL benefits include:  Increased train movements on the Auckland rail network by developing Britomart as a through station and unlocking the current capacity constraint.  Improved commuter access to the city centre.  Building on the benefits of existing investment in the electrification of Auckland’s rail network.  Freeing up road space for freight and other trips.  Creating new transport hubs around the underground railway stations with complementary opportunities for a range of land use activities. 115. The range of potential adverse effects arise out of earthworks, flooding, ground settlement and associated effects on heritage values, contaminated land, groundwater quality, stormwater quality, dust, and effects on cultural values. The evidence of the experts providing input to the project, and evidence provided by others, demonstrated to us that these potential effects can be appropriately managed. In particular, standard and specific mitigation measures will be implemented through a range of management plans, and remediation is proposed where necessary to address effects on structures resulting from ground settlement. 116. In all of the above respects, we find the application to be consistent with the relevant planning documents. Any other matters 117. We also considered the following other matters to be relevant and reasonably necessary to determine the application in accordance with section 104(1)(c) of the RMA:  The Auckland Plan sets out the vision for Auckland over the next 30 years and seeks to address relevant issues. The Commissioners accept that the proposal to construct a piece of the CRL infrastructure directly supports the vision contained in the Auckland Plan to improve and complete the existing road and railway network. City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

31


 Submissions have all been reviewed by the Commissioners and considered in the assessment of the Project.  No comments were received from the Waitemata or the Albert-Eden Local Boards.  The applicant has confirmed that an Archaeological Authority will be sought from Heritage NZ pursuant to the Heritage New Zealand Pouhere Taonga Act 2014. Other relevant RMA provisions Matters relevant to discharge and coastal permits – s105 118. The proposal requires consents to discharge contaminants to air and to land and water under s15. Under section 105, regard must be had to additional matters for any application for a discharge permit or a coastal permit that would contravene s15 or s15B of the RMA. The Commissioners agree with the reporting planner that the proposal satisfies the matters set out in section 105 for the reasons set out in her report. Restrictions on discharge permits – s107 119. Regard must be had to the restriction on the granting of certain discharge permits that would contravene sections 15 or 15A. Section 107 states that a discharge permit cannot be granted to do something that would otherwise contravene section 15 allowing the discharge of a contaminant or water into water, if, after reasonable mixing, the contaminant or water discharged is likely to give rise to all or any of stated effects in the receiving waters. The Commissioners are satisfied that the proposal satisfies the provisions of section 107. Conditions of resource consents – s108 120. Conditions of consent have been set out below. PART 2 RMA – PURPOSE AND PRINCIPLES 121. We find that the proposal is consistent with Part 2 of the RMA because: 

The completed CRL will provide for the social and economic wellbeing of people and communities in Auckland by improving transport access into and around the city centre, improving the efficiency and resilience of the transport network of urban Auckland, contributing to increasing Auckland’s economic growth and providing a sustainable transport solution that minimizes environmental impacts.

The conditions included as part of the consent will ensure the adverse effects on the environment will be appropriately avoided, remedied or mitigated. In particular, a range of construction mitigation measures will be implemented through an approved CEMP, along with a range of key management and monitoring plans.

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

32


The matters raised by submitters have been given particular attention through the discussion during the hearing regarding the inclusion of conditions of consent that have regard to submitters’ concerns.

There are no identified outstanding natural features and landscapes, areas of significant vegetation and significant habitats of indigenous fauna that must be protected in the project area.

The applicant has supplied a supporting Heritage Impact Assessment and additional information that has been reviewed by Council’s Principal, Built Heritage Specialist who has concluded that the potential effects on the scheduled structures will be minor subject to appropriate conditions of consent. We agree with that assessment and review and with the evidence presented for the applicant and Heritage New Zealand. Conditions are accordingly included as part of this decision and as such, the protection of historic heritage will be ensured.

The construction techniques and practices, coupled with conditions on the consent, will appropriately minimize potential and actual adverse effects on the environment. As such, the project represents an efficient use and development of natural and physical resources and serves to maintain and enhance both amenity values and the quality of the environment.

Given the extent of consultation undertaken with Mana Whenua, the requirements of sections 6(e), 7(a), 7(aa), and 8 of the RMA have been provided for and had regard to. In particular, there has been engagement with eight Mana Whenua groups who have self-identified an interest in the project and that engagement has been on-going via the CRL Mana Whenua Forum and targeted hui. Accidental discovery protocols and consent conditions will enable the relationship of Mana Whenua with any unidentified archaeological sites within the project site to occur. In addition, the applicant has stated that on-going consultation and engagement will continue through all stages of planning and construction.

Decision 122. In exercising our delegation under sections 34 and 34A of the RMA and having regard to the foregoing matters, sections 104, 104B, 105, 106, 107 and 108 and Part 2 of the RMA, we determine that the resource consents be granted subject to the conditions set out below. The resource consents granted by this decision are collectively a discretionary activity and provide for the construction of the Britomart Station to Wyndham Street section of the proposed City Rail Link. The respective resource consents are land use consents, water permits and discharge permits which are referenced as R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436 and R/REG/2014/543. The location is the lower part of the central business district of Auckland City comprising the Britomart Station and parts of Lower Queen Street, Customs Street West, Wolfe Street, Victoria Street West, Albert Street and Wyndham Street. City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

33


Reasons for the decision 123. The reasons for this decision are covered in the discussion above in this decision report but can be summarised as follows: 

Overall, the proposal enables people to provide for their economic and, in turn, social wellbeing as the CRL will improve transport access into and around the city centre and improve the efficiency and resilience of the transport network of urban Auckland. It will therefore contribute to increasing Auckland’s economic growth and further, provide a sustainable transport solution that minimizes environmental impacts.

The effects associated with the project, including dust, sediment, contamination, settlement, water quality, earthworks with respect to heritage, construction, traffic, construction noise, utility disruption and flood capacity changes are found to be temporary in nature and can be appropriately avoided, remedied or mitigated through implementation of a certified CEMP. That includes the specific certified management plans and other conditions of the consent.

The particular concerns of submitters have been addressed through conditions of consent that address matters potentially impacting on identified properties.

The project has been found to not be contrary to the relevant provisions and policy statements, plans and proposed plans that are relevant and as prepared under the RMA.

The proposal has been assessed with regard to the relevant Part 2 matters and found to be consistent with the purpose and principles of the RMA as included as this part of it.

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

34


Conditions General Conditions These conditions apply to all resource consents. Definitions AEE - Assessment of Environmental Effects prepared by Aurecon New Zealand Limited/ Golder Associates (NZ) Limited, dated 19 December 2014 AQMP - Air Quality Management Plan, based on the draft Air Quality Management Plan – Britomart to Wyndham dated December 2014 prepared by Golder Associates (NZ) Limited CCP - Communication and Consultation Plan CEMP - Construction Environmental Management Plan CLG - Community Liaison Group Commencement of construction – in all conditions which refer to ‘commencement of construction’, construction has the same meaning as the Construction Contracts Act 2002 and includes work such as site clearance, earthmoving and earthworks, excavation, tunnelling, and boring; and the construction, erection, installation, carrying out, alteration, repair, restoration, renewal, maintenance, extension, demolition, removal, or dismantling of any building or structure; and all other matters referred to in section 6 of that Act. CPO - Chief Post Office CRL – City Rail Link CSMP - Contaminated Soils Management Plan CTMP - Chemical Treatment Management Plan EMP - Industrial and Trade Activities Environmental Management Plan ESCP - Erosion and Sediment Control Management Plan ESC – Erosion and Sediment Control GSMCP - Groundwater and Settlement Monitoring and Contingency Plan IBA - Independent Building Assessor – The person engaged under Condition 120. The role of the Independent Building Assessor shall be to make recommendations to Council on building serviceability and damage matters. Key contacts - are identified in the CEMP and are a “key contact” person representing the Consent Holder and a “key contact” person representing the contractor team to work with the Council (Team Leader Central Monitoring). Refer Condition 29 Mana Whenua Groups - Ngati Maru, Ngati Paoa, Ngai Tai Ki Tamaki, Ngati Te Ata Waiohua, Te Kawerau a Maki, Ngati Whatua o Orakei, Te Akitai, and Ngati Tamaoho PCCP - Pre-Construction Communication and Consultation Plan

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

35


Project – the City Rail Link Britomart Station to Wyndham Street Section Referee – the independent and appropriately qualified senior person to whom a dispute is referred under Condition 8 Senior qualified person - means a person with a post-graduate degree in environmental science, chemistry, biology, geology (including a Chartered Professional Engineer (CPEng)) or similar field; or sufficient technical experience that is at least equivalent and at least five years professional experience. Services – includes including gas, water, sewerage, telecoms, stormwater, fibre optics and power Upper Albert Street zone – the zone defined as that part of Albert Street between Swanson Street and Wyndham Street See also definitions specific to water permit R/REG/2014/5432 Take and Diversion of Groundwater. 1.

The scope and extent of works envisaged by this project shall be carried out in general accordance with the plans and all information submitted with the application, detailed below, and all referenced by the Council as consent numbers R/LUC/2014/5428, R/REG/2014/5430, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436 and R/REG/2014/5437. 

Application Form, and Assessment of Environmental Effects (AEE) prepared by Aurecon New Zealand Limited/Golder Associates (NZ) Limited, dated 19 December 2014, including the following: Report title and reference

Author

Rev

Dated

Design and Construction Report (Appendix B)

Aurecon New Zealand Limited

December 2014

Groundwater Effects Assessment (Appendix C)

Pattle Delamore Partners Limited

December 2014

Assessment of Settlement Effects (Appendix D)

Aurecon New Zealand Limited

December 2014

Contaminated Land Assessment (Appendix E)

Golder Associates (NZ) Limited

December 2014

Water Quality Assessment (Appendix F)

Golder Associates (NZ) Limited

December 2014

Industrial and Trade Activities Assessment (Appendix G)

Golder Associates (NZ) Limited

December 2014

Air Quality Assessment (Appendix H)

Golder Associates (NZ) Limited

December 2014

Draft Erosion and Sediment Control Plan (Appendix I)

Aurecon New Zealand Limited

December 2014

Heritage Impact Assessment (Appendix J)

Salmond Reed Architects Limited

December 2014

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

36


Plan title and reference

Author

Rev

Dated

LOCATION PLAN AND EXTENT OF WORKS CRL-BTM-RME-000-DRG-0001

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

DR6A ALIGNMENT CRL DOWN (MC20) PLAN AND LONGSECTION SHEET 1 CRL-PAT-RME-000-DRG-0001 DR6A ALIGNMENT CRL DOWN (MC30) PLAN AND LONGSECTION SHEET 1 CRL-PAT-RME-000-DRG-0002 CPO PLAN, DEMOLITION, SLAB PROPPING AND TEMPORARY DECK CRL-BTM-RME-000-DRG-1021 CPO PLAN, BASEMENT WITH UNDERPINNING CRL-BTM-RME-000-DRG-0123 CPO LONGSECTION CRL-BTM-RME-000-DRG-0191 CPO CROSS SECTION WITH UNDERPINNING GRID 1 CRL-BTM-RME-000-DRG-0231 CPO CROSS SECTION REINSTATEMENT WORKS GRID 1 CRL-BTM-RME-000-DRG-0241 CPO AND QUEEN ST TUNNEL BOX REINFORCEMENT AND WATERPROOFING DETAILS CRL-BTM-RME-000-DRG-0305 CPO MONITORING LOCATIONS AT COLUMN UNDERPINNING CRL-BTM-RME-000-DRG-0452 CPO FAÇADE MONITORING LOCATIONS CRL-BTM-RME-000-DRG-0453 QUEEN ST AND QUEEN ELIZABETH SQUARE –QUEEN STREET - TYPICAL SECTIONS CRL-BTM-RME-000-DRG- 0535 QUEEN ST AND QUEEN ELIZABETH SQUARE QUEEN ST LONG SECTION UP TRACK CRL-BTM-RME-000-DRG-0551 QUEEN ST AND QUEEN ELIZABETH SQUARE- TYPICAL DETAILS GROUNDWATER DRAINAGE SHEET 1 OF 2 CRL-BTM-RME-000-DRG-0621 QUEEN ST AND QUEEN ELIZABETH SQUARE PUMP STATION SUMP AND CROSS PASSAGEWAY SECTIONS

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

37


CRL-BTM-RME-000-DRG-0661 PRECINCT - OVERALL LAYOUT PLAN

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

CRL-BTM-RME-000-DRG-0009 ENABLING WORKS CONTRACT 1 WORKSITES WITH PLANT BRITOMART TO QE SQUARE STAGE 2 OF 4 CRL-BTM-RME-000-DRG-0102 ENABLING WORKS CONTRACT 1 WORKSITES WITH PLANT BRITOMART TO QE SQUARE STAGE 3 OF 4 CRL-BTM-RME-000-DRG-0103 ENABLING WORKS CONTRACT 2 WORK SITE WITH PLANT AND TRAFFIC INTERFACE BETWEEN PRECINCT AND CONTRACT 2 IN LOWER ALBERT ST CRL-PAT-RME-000-DRG-0114 CUSTOMS ST TUNNEL CROSS SECTION AND DETAIL OF TYPICAL TUNNEL IN CUSTOMS ST CRL-PAT-RME-000-DRG-0171 ALBERT ST TUNNEL PLAN SHEET 1 OF 5 CRL-PAT-RME-000-DRG-0201 ALBERT ST TUNNEL PLAN SHEET 2 OF 5 CRL-PAT-RME-000-DRG-0202 ALBERT ST TUNNEL PLAN SHEET 3 OF 5 CRL-PAT-RME-000-DRG-0203 ALBERT ST TUNNEL PLAN SHEET 4 OF 5 CRL-PAT-RME-000-DRG-0204 ALBERT ST TUNNEL PLAN SHEET 5 OF 5 CRL-PAT-RME-000-DRG-0205 ALBERT ST TUNNEL STRUCTURAL LONGSECTION (MC30) SHEET 1 OF 5 CRL-PAT-RME-000-DRG-0211 ALBERT ST TUNNEL STRUCTURAL LONGSECTION (MC30) SHEET 2 OF 5 CRL-PAT-RME-000-DRG-0212 ALBERT ST TUNNEL STRUCTURAL LONGSECTION (MC30) SHEET 3 OF 5 CRL-PAT-RME-000-DRG-0213 ALBERT ST TUNNEL STRUCTURAL LONGSECTION (MC30) SHEET 4 OF 5 CRL-PAT-RME-000-DRG-0214 ALBERT ST TUNNEL STRUCTURAL LONGSECTION (MC30) SHEET 5 OF 5 CRL-PAT-RME-000-DRG-0215 ALBERT ST TUNNEL TYPICAL SECTION – CH 440 TO CH 465 (MC20)

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

38


CRL-PAT-RME-000-DRG-0252 ALBERT ST TUNNEL TYPICAL SECTION – CH 465 TO CH 580 (MC20)

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

17/10/2014

Aurecon

1.0

19/12/2014

Aurecon

1.0

19/12/2014

Aurecon

1.0

19/12/2014

Aurecon

1.0

19/12/2014

Aurecon

1.0

17/12/2014

Aurecon

3.0

19/12/2014

Aurecon

1.0

01/11/2014

Aurecon

5.0

02/07/2015

CRL-PAT-RME-000-DRG-0253 ALBERT ST TUNNEL TYPICAL DETAILS – PILE WALL SUPPORT STRUCTURE CRL-PAT-RME-000-DRG-0301 ALBERT ST WORKSITE AND TEMPORARY TRAFFIC MANAGEMENT CONSTRUCTION PHASING SHEET 2 OF 5 CRL-PAT-RME-000-DRG-0053 ALBERT ST WORKSITE AND TEMPORARY TRAFFIC MANAGEMENT CONSTRUCTION PHASING SHEET 3 OF 5 CRL-PAT-RME-000-DRG-0054 ALBERT ST WORKSITE AND TEMPORARY TRAFFIC MANAGEMENT CONSTRUCTION PHASING SHEET 4 OF 5 CRL-PAT-RME-000-DRG-0055 ALBERT ST WORKSITE AND TEMPORARY TRAFFIC MANAGEMENT CONSTRUCTION PHASING SHEET 5 OF 5 CRL-PAT-RME-000-DRG-0056 ENABLING WORKS CONTRACT 2 CUSTOMS ST INTERSECTION CONSTRUCTION STAGING FOR CONSENTING SHEET 1 OF 3 CRL-PAT-RME-000-DRG-0111 ENABLING WORKS CONTRACT 2 CUSTOMS ST INTERSECTION CONSTRUCTION STAGING FOR CONSENTING SHEET 2 OF 3 CRL-PAT-RME-000-DRG-0112 ENABLING WORKS CONTRACT 2 CUSTOMS ST INTERSECTION CONSTRUCTION STAGING FOR CONSENTING SHEET 3 OF 3 CRL-PAT-RME-000-DRG-0113 ENABLING WORKS CONTRACT 2 ENVISAGED WORKSITE AND TRAFFIC INTERFACE ALBERT ST SOUTH FOR CONSENTING CRL-PAT-RME-000-DRG-0104 ENABLING WORKS PROPOSED AND EXISTING GROUNDWATER MONITORING LOCATIONS CRL-SYW-GEO-000-DRG-0007 ALBERT STREET MONITORING LOCATIONS CRL-PAT-STR-000-DRG-0401 QUEEN STREET MONITORING LOCATIONS CRL-PAT-STR-000-DRG-0404 ENABLING WORKS MONITORING NOTES

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

39


CRL-PAT-STR-000-DRG-0400 NOTES ON SCOPE AND METHOD SHEET 3 OF 4

Aurecon

6.0

15/12/2014

Aurecon

1.0

15/12/2014

Aurecon

1.0

21/10/2014

GEOLOGICAL CROSS SECTION GALWAY STREET CRL-SYW-GEO-000-SKE-0022

Aurecon

2.0

20/05/2015

GEOLOGICAL CROSS SECTION TYLER STREET CRL-SYW-GEO-000-SKE-0023

Aurecon

1.0

23/04/2015

GEOLOGICAL LONG SECTION SHEET 0 EXTENSION OF MC20 LONG SECTION -300 TO 180M CRL-SYW-GEO-000-SKE-0024

Aurecon

1.0

23/04/2015

Aurecon

1.0

23/04/2015

Aurecon

1.0

23/04/2015

Aurecon

2.0

17/11/2014

Aurecon

3.0

09/07/2015

Aurecon

3.0

09/07/2015

Aurecon

2.0

03/07/2015

CRL-SYW-STR-000-DRG-0053 NOTES ON SCOPE AND METHOD SHEET 4 OF 4 CRL-SYW-STR-000-DRG-0054 GEOLOGICAL CROSS SECTION CUSTOMS STREET CRL-SYW-GEO-000-SKE-0021

GEOLOGICAL AND HYDROGEOLOGICAL MODEL MC20 LONG SECTION SHEET 1 CRL-SYW-GEO-000-SKE-0025 COMPARISON OF MC20 LONG SECTION (PART) WITH SECTION THROUGH MODFLOW MODEL AT ROW 26 CRL-SYWGEO-000-SKE-0026 SETTLEMENT CONTOURS DUE TO CUT AND COVER AND PIPEJACK SHEET 1 OF 2 CRL-SYW-CIV-000-DRG-0030 BRITOMART TO WYNDHAM GROUNDWATER AND SETTLEMENT MONITORING AND CONTINGENCY PLAN SHEET 1 OF 3 CRLPAT- RME- 000- DRG- 0403 BRITOMART TO WYNDHAM GROUNDWATER AND SETTLEMENT MONITORING AND CONTINGENCY PLAN SHEET 2 OF 3 CRLPAT- RME- 000- DRG- 0404 BRITOMART TO WYNDHAM GROUNDWATER AND SETTLEMENT MONITORING AND CONTINGENCY PLAN SHEET 3 OF 3 CRLPAT- RME- 000- DRG- 0405

Other additional information

Author

Rev

Dated

Further Information Letter, including attachments (Attachments A-G) except for Attachment E

Damien McGahan from Aurecon New Zealand Limited

1.0

06/05/2015

Further Information Addendum Letter, including attachments (Attachments A-C)

Damien McGahan from Aurecon New Zealand Limited

1.0

22/05/2015

Further Information Addendum 2 Letter

Damien McGahan from Aurecon New Zealand Limited

1.0

28/05/2015

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

40




Groundwater and Settlement Monitoring and Contingency Plan Resource Consent Package 1 Britomart Station to Wyndham Street Section

Evidence provided prior to and at the Council hearing:

Aurecon

2.0

02/06/2015

Author

Rev

Dated

Sarah Louise Sutherland of Golder Associates (NZ) Ltd

19 June 2015

Richard Leslie Chilton of Golder Associates (NZ) Ltd

19 June 2015

Andrew Thomas Hart of Golder Associates (NZ) Ltd

19 June 2015

Bruce Mitchell Petry of Reverb Consultancy Ltd

19 June 2015

Colin Dean Ingoe of Auckland Transport

19 June 2015

Jennifer Marie Carvill of Golder Associates (NZ) Ltd

19 June 2015

William Russell Newns of Aurecon New Zealand

19 June 2015

William Russell Newns of Aurecon New Zealand

19 June 2015

Statement of Evidence of Scott Elwarth

Scott Elwarth of Auckland Transport

19 June 2015

Statement of Evidence of Alan David Pattle

Alan David Pattle of PDP Ltd

19 June 2015

Eric Craig Stevenson of Aurecon New Zealand

19 June 2015

Supplementary Statement of Evidence of William Russell Newns

William Russell Newns of Aurecon New Zealand

6 July 2015

Supplementary Statement of Evidence of Jennifer Marie Carvill

Jennifer Marie Carvill of Golder Associates (NZ) Ltd

6 July 2015

Supplementary Statement of Evidence of Eric Craig Stevenson

Eric Craig Stevenson of Aurecon New Zealand

6 July 2015

Statement of Evidence of Sarah Louise Sutherland Statement of Evidence of Richard Leslie Chilton

Statement of Evidence of Andrew Thomas Hart

Statement of Evidence of Bruce Mitchell Petry

Statement of Evidence of Colin Dean Ingoe Statement of Evidence of Jennifer Marie Carvill

Statement of Evidence of William Russell Newns

Statement of Evidence of Eric Craig Stevenson

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

41


If there is any conflict between the application documents and the specific conditions which follow, the specific conditions will prevail. All Charges Paid 2.

These consents (or any part thereof) shall not commence until such time as the following charges, which are owing at the time the Council's decision is notified, have been paid in full: a. All fixed charges relating to the receiving, processing and granting of these resource consents under section 36(1) of the Resource Management Act 1991 (RMA); and b. All additional charges imposed under section 36(3) of the RMA to enable the Council to recover its actual and reasonable costs in respect of this application, which are beyond challenge.

3.

The consent holder shall pay any subsequent further charges imposed under section 36 of the RMA relating to the receiving, processing and granting of these resource consents within 20 days of receipt of notification of a requirement to pay the same, provided that, in the case of any additional charges under section 36(3) of the RMA that are subject to challenge, the consent holder shall pay such amount as is determined by that process to be due and owing, within 20 days of receipt of the relevant decision. Compliance Monitoring Charge

4.

The consent holder shall pay the Council an initial consent compliance monitoring charge of $8,000 (inclusive of GST), plus any further monitoring charge or charges to recover the actual and reasonable costs that have been incurred to ensure compliance with the conditions attached to these consents. Advice Note: The initial monitoring charge is to cover the cost of inspecting the site, carrying out tests, reviewing conditions, updating files, etc, all being work to ensure compliance with resource consents. In order to recover actual and reasonable costs, inspections, in excess of those covered by the base fee paid, shall be charged at the relevant hourly rate applicable at the time. The consent holder will be advised of the further monitoring charge or charges as they fall due. Such further charges are to be paid within one month of the date of invoice. Only after all conditions of the resource consent have been met, will Council issue a letter confirming compliance on request of the consent holder.

Lapse Date 5.

Under section 125 of the RMA, these consents or any one of these consents lapse 10 years after the consent commences unless: a. The consent is given effect to; or b. The Council extends the period after which the consent lapses.

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

42


Copies of Resource Consent 6.

All personnel working on the project shall be made aware of, and have access to, at least one copy of these resource consents, associated reference documents and associated certified management plans. Site Access

7.

Subject to compliance with the Consent Holder's health and safety requirements and provision of reasonable notice, servants or agents of Auckland Council shall be permitted to have access to relevant parts of the surface construction sites controlled by the Consent Holder at all reasonable times for the purpose of carrying out inspections, surveys, investigations, tests, measurements and/or to take samples. Dispute Resolution

8.

In the event of any dispute, disagreement or inaction arising from the implementation of these consents, including  any Auckland Council certification required by these conditions, or  implementation of, or monitoring required by, the conditions, the disputed matter shall be referred in the first instance to the Consent Holder and Council (Team Leader Central Monitoring), to determine a resolution process. If a resolution process cannot be agreed, then the matter shall be referred to an independent and appropriate senior qualified person (‘the referee’), agreeable to both parties (such agreement not to be unreasonably withheld by either party). The referral shall set out in writing the details of the matter to be referred for determination and the reasons why the parties have not agreed. The referee shall be appointed within 10 working days of the Consent Holder or the Council giving notice to the other of its intention to seek an expert determination. Following appointment, the referee shall issue a written decision on the matter, including the reasons for his or her decision. In making the decision, the referee shall be entitled to seek further information and to hear from the parties as he or she sees fit in his or her sole discretion. The reasonable fees of the referee shall be paid equally by both disputing parties. Advice Note 1: The dispute resolution process provided for by this condition does not prejudice any parties’ right to take enforcement action in relation to implementation of these conditions. However, the dispute resolution process will be applied before any formal enforcement action is taken by the Council, except in urgent situations. Advice Note 2: The Auckland Transport contact for this resolution process is the Central and Joint Initiatives Team Lead, Property and Planning Team, Capital Development Division

Pre-Construction Communication and Consultation Plan (“PCCP”) 9.

In order to set out a framework to ensure appropriate communication and consultation is undertaken with the community, stakeholders, affected parties

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

43


and affected in-proximity parties prior to the commencement of construction, the Consent Holder shall prepare a PCCP. 10.

The PCCP shall be submitted to Council (Team Leader Central Monitoring), within 40 working days of the resource consent decision, for confirmation that the PCCP has been prepared in accordance with the conditions of consent.

11.

The PCCP shall be implemented and complied with within 60 working days from the resource consent decision until the commencement of construction.

12.

This PCCP shall set out recommendations and requirements (as applicable) that should be adopted by and/or inform the development of the Construction Environmental Management Plan (“CEMP”) and other management plans.

13.

The PCCP shall set out how the Consent Holder will: a. Inform the community of Project progress and the likely commencement of construction and the programme; b. Engage with the community in order to foster good relationships and to provide opportunities for learning about the Project; c. Obtain (and specify reasonable timeframes for) feedback and input from stakeholders, directly affected and affected in-proximity parties regarding the development of the CEMP and other management plans; d. Respond to queries and complaints by providing as a minimum the following information: i)

Who is responsible for responding to the query / complaint;

ii)

How responses will be provided;

iii)

The timeframes within which responses will be provided.

e. Where feedback (in accordance with this condition) is provided, the PCCP shall articulate how that feedback has informed the development of the CEMP and other management plans and where it has not, reasons why it has not. 14.

The PCCP shall be prepared in consultation with stakeholders, directly affected parties and affected in-proximity parties including, but not limited to: a. All property owners and occupiers of the sites that are identified at Appendix 5, adjacent to the Project’s construction sites (Britomart Station to Wyndham Street Section (as defined by the Britomart Transport Centre Designation 314 and CRL NoR 1)); b. Heritage New Zealand (Heritage NZ); c. Network Utility Operators; and d. The Community Liaison Group (refer Conditions 16 to 24).

15.

The PCCP shall, as a minimum, include:

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

44


a. A communications framework that details the Consent Holder’s communication strategies, accountabilities, frequency of communications and consultation, the range of communication and consultation tools to be used (including any modern and relevant communication methods, newsletters or similar, advertising etc.), and any other relevant communication matters; b. Details of the Communication and Consultation Manager for the preconstruction period including contact details (phone, email and postal address); c. The 0800 CRL TALK phone number; d. The methods for identifying, communicating and consulting with stakeholders, directly affected parties and affected in-proximity parties and other interested parties. Such methods shall include but not be limited to: i) Newsletters; ii) Newspaper advertising; iii) Notification and targeted consultation with stakeholders, affected parties and affected in-proximity parties; and iv) The use of the project website for public information. e. The methods for communicating and consulting with the Community Liaison Group (refer Conditions 16 to 24); f. How communication and consultation activity will be recorded; and g. Methods for recording reasonably foreseeable future planned network utility works so that it can be considered and incorporated, where appropriate, into the Britomart Station to Wyndham Street Section design. The PCCP will be publicly available once finalised for the duration of the Project’s preconstruction period. Advice Note: At the time these resource consents were granted, the Communication and Consultation Manager for the Project was Carol Greensmith, phone 0800 CRL TALK.

Community Liaison Group (“CLG”) 16.

Within 60 working days of the resource consent decision the Consent Holder shall, in consultation with the Council (Team Leader Central Monitoring), establish a Community Liaison Group in the construction area (Britomart Station to Wyndham Street Section, as defined by the Britomart Transport Centre Designation 314 and CRL NoR 1).

17.

The Consent Holder shall ensure that membership of the CLG shall include representative(s) of the Consent Holder and be open to all directly affected and affected in-proximity parties to the Project including, but not limited to the following: a. Representative(s) for and/or directly affected and affected in-proximity property owners and occupiers;

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

45


b. CBD Residents Advisory Group; c. Heart of the City; and d. Mana Whenua (any or all of Ngati Maru, Ngati Paoa, Ngai Tai Ki Tamaki, Ngati Te Ata Waiohua, Te Kawerau a Maki, Ngati Whatua o Orakei, Te Akitai and Ngati Tamaoho) unless any of those named advise the Consent Holder of a different liaison process. 18.

In addition to involvement in the PCCP (refer Conditions 9 to 15), the Consent Holder shall ensure that the CLG shall: a. Receive regular updates on Project progress; b. Enable the effects of constructing the Project on the community to be monitored by providing a regular forum through which information about the Project can be provided to the community; c. Enable opportunities for concerns and issues to be reported to and responded by the Consent Holder; and d. Be provided with feedback on the development of, and any material changes to the CEMP and other management plans.

19.

The Consent Holder shall consult with the CLG in respect of the development and review of the CEMP and other management plans.

20.

Prior to preparation of the PCCP under Condition 10, the Consent Holder shall appoint one or more persons appropriately qualified in community consultation as the Community Consultation Advisor(s) to: a. Provide administrative assistance to the CLG; b. Ensure the CLG is working effectively (including the development of a Code of Conduct and appropriate procedures for the CLG); and c. Act as a community consultation advisor to the CLG.

21.

The Consent Holder must use its best endeavours to ensure that the CLG meets at least annually until the commencement of construction and then at least once every three months or as otherwise required once construction commences.

22.

Once construction has commenced, the Consent Holder shall provide an update at least every three months (or as otherwise agreed) to the CLG on compliance with resource consent conditions, including the CEMP and other management plans, and any material changes to these plans.

23.

The Consent Holder shall provide reasonable administrative support for the CLG including organising meetings at a local venue, inviting all members of the CLG, and taking responsibility for keeping and disseminating meeting minutes.

24.

The CLG shall continue for the duration of the Project and for six months following completion of the Project. Communication and Consultation Plan (“CCP�)

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

46


25.

In order to set out a framework to ensure appropriate communication and consultation with the community, stakeholders, affected parties and affected in-proximity parties during the construction of the Project, the Consent Holder shall prepare a CCP which shall be implemented and complied with for the duration of the construction of the Project.

26.

The CCP shall set out how the Consent Holder will: a. Inform the community of construction progress and future construction activities and constraints that could affect them; b. Provide early information on key Project milestones; and c. Obtain and specify a reasonable timeframe (being not less than 10 working days), for feedback and inputs from directly affected and affected in-proximity parties regarding the implementation and review of the CEMP or other management plans. d. Respond to queries and complaints including but not limited to: i)

Who is responsible for responding;

ii) How responses will be provided; and iii) The timeframes within which responses will be provided. 27.

The CCP shall (as a minimum) include: a. A communications framework that details the Consent Holder’s communication strategies, accountabilities, frequency of communications and consultation, the range of communication and consultation tools to be used (including any modern and relevant communication methods, newsletters or similar, advertising etc.), and any other relevant communication matters; b. The Communication and Consultation Manager for the Project including contact details (phone, email and postal address); c. The 0800 CRL TALK phone number; d. The methods for identifying, communicating and consulting with persons affected by the project including but not limited to: i)

All property owners and occupiers of the sites that are identified at Appendix 5, adjacent to the Project’s construction sites (Britomart Station to Wyndham Street Section (as defined by the Britomart Transport Centre Designation 314 and CRL NoR 1));

ii)

Heritage New Zealand Pouhere Taonga (Heritage NZ); and

iii) The Community Liaison Group (refer Conditions 16 to 24). e. How stakeholders and persons affected by the project will be notified of the commencement of construction, the expected duration of the activities and works, and who to contact for any queries, concerns and complaints;

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

47


f. How stakeholders and persons affected by the project will be consulted in the development and review of the CEMP and other management plans, including specifying reasonable timeframes for feedback; g. A list of stakeholders, directly affected and affected in-proximity parties to the construction works with whom the Consent Holder will communicate; h. A summary of communication and consultation undertaken between the Consent Holder and parties as required by the PCCP. The summary shall include any outstanding issues or disputes raised by parties; i.

How communication and consultation activity relating to construction activities and monitoring requirements will be recorded; and

j.

How opportunities to interpret and display archaeological finds within the project area will be identified and implemented, including how Heritage NZ will be involved in this process.

Advice Note: At the time this resource consent was granted, the Communication and Consultation Manager for the Project was Carol Greensmith, phone 0800 CRL TALK.

28.

The CCP shall also include (as relevant) linkages and cross-references to the CEMP and other management plans.

29.

The CCP shall be reviewed six monthly for the duration of construction and updated if required. Any updates to the CCP shall be provided to “key contacts” and the Council (Team Leader Central Monitoring) for review and agreement on any further action to be undertaken.

30.

Any further action recommended as a result of the review under Condition 29 shall be undertaken by the Consent Holder’s Communication and Consultation Manager for the Project and confirmation of completion shall be provided to the Council (Team Leader Central Monitoring).

31.

If, in the course of amendments undertaken as part of the review process under Condition 29, a material change to the CCP is made, the Consent Holder shall notify those parties affected by the change within 20 working days of the material change occurring. Pre-Construction Meetings and Notification

32.

Prior to commencement of any stage of construction, the Consent Holder shall arrange a pre-construction meeting with Council (Team Leader Central Monitoring in conjunction with the relevant technical specialists, as required) as well as the site contractor and shall invite the following Mana Whenua groups to attend: Ngati Maru, Ngati Paoa, Ngai Tai Ki Tamaki, Ngati Te Ata Waiohua, Te Kawerau a Maki, Ngati Whatua o Orakei, Te Akitai, and Ngati Tamaoho (“the Mana Whenua Groups”). a. The meeting shall be located on the Project site unless otherwise agreed; b. The meeting shall be scheduled no less than five working days before the anticipated commencement of construction;

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

48


c. The meeting shall include representation from the contractor who will undertake the works; d. The following information shall be made available by the Consent Holder at the pre- construction meeting: i) Conditions of consent; ii) Approved (signed/stamped) construction plans for that stage; iii) Timeframes for key stages of the works authorised under this consent; iv) Contact details of the site contractor, site stormwater engineer and other key contractors; v) All certified management plans; and Advice note: by this stage, all of the management plans referred to in Condition 33(i) should have been certified, given the plans are required to be lodged 20 working days prior to commencement of construction).

vi) A copy of the Corridor Access Request from Auckland Transport. e. Appropriate provision to the extent sought by the Manu Whenua Groups, or their nominated representative(s), shall be made for a cultural induction of the contractor's staff. Advice Note: To arrange the pre-start meeting required by Condition 32 please contact Steve Pearce, Team Leader Central Monitoring to arrange this meeting on steve.pearce@aucklandcouncil.govt.nz, or 09 301 01 01. The conditions of consent should be discussed at this meeting. All additional information required by the Council should be provided two days prior to the meeting.

Construction Management 33.

Prior to the commencement of construction authorised by these consents, the Consent Holder shall prepare a Construction Environmental Management Plan (CEMP) including all certified Management Plans which form part of these conditions to ensure compliance with the resource consents. The CEMP shall include details of: a. Final project details and staging of works to illustrate that the works remain within the limits and standards approved under these consents and that the construction activities avoid, remedy or mitigate adverse effects on the environment. b. The site or Project Manager and the Communication and Consultation Manager, including their contact details (phone, email and physical address); c. the “key contacts� referred to in Condition 29; d. communication and consultation procedures for ensuring that residents, road users and businesses in the immediate vicinity of construction areas are given prior notice of the commencement of construction and are informed about the expected duration and effects of the work. In particular the procedures shall provide for the following in relation to residents, road users and businesses potentially affected by the construction works:

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

49


i) consultation prior to the commencement of construction; ii) notice periods for changes to pedestrian and vehicle access; iii) regular updates on construction progress; iv) key dates for major milestones such as road closure and re-opening; and v) communication on any other matters potentially affecting residents or business operations in the vicinity of the works. e. notice boards that clearly identify the Consent Holder and the Project name, together with the name, telephone number and email address of the Site or Project Manager and the Communication and Consultation Manager; f. general site layout and management; g. an outline of the Project’s construction programme, including construction hours of operation; h. means of ensuring the safety of the general public; i.

certified management plans which form part of these conditions, being: i)

Erosion and Sediment Control Plan;

ii) Chemical Treatment Management Plan; iii) Air Quality Management Plan; iv) Groundwater and Settlement Monitoring and Contingency Plan; v) Contaminated Soils Management Plan; and vi) Industrial and Trade Activity Environmental Management Plan. j.

Water Discharge Quality Monitoring Programme; and

k. identification of the suitably independent, qualified Chartered Professional Engineer, or member of the Royal Institution of Chartered Surveyors, who will be undertaking the condition surveys required by the conditions of consent. 34.

The CEMP shall be provided to the Council (Team Leader Central Monitoring) for certification at least 20 working days prior to the commencement of construction. The Consent Holder shall request the Council’s (Team Leader Central Monitoring) determination, in writing, as to whether the CEMP can be certified as per the requirements of the consent conditions within 10 working days of receipt of the CEMP. Construction shall not commence until written certification is obtained from Council (Team Leader Central Monitoring). Advice note: The Consent Holder may provide CEMPs in a staged manner to Council (Team Leader Central Monitoring) for certification.

35.

The CEMP required by Condition 33 shall be implemented and maintained throughout the entire construction period for the Project, or relevant Project stage, to manage potential adverse effects arising from the construction and shall be updated as necessary (or as required by Conditions 37 and 38).

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

50


Any change to the CEMP shall be submitted to the Council (Team Leader Central Monitoring) for certification and no activity reliant upon a change to the CEMP can be undertaken until the change has been certified. The Consent Holder shall request the Council’s (Team Leader Central Monitoring) determination as to whether the proposed change can be certified, in writing, within 10 working days of submission of the change. Construction Traffic 36.

The Consent Holder shall, so far as is it is reasonably practicable, avoid, remedy or mitigate the adverse effects of construction on transport, parking and property access. This is to be achieved through the following objectives: a. managing the road transport network for the duration of the construction by adopting the best practicable option to manage congestion; b. maintaining pedestrian access to private property at all times; and c. providing on-going vehicle access to private property to the greatest extent possible. Advice Note 1: Condition 36 refers to objectives to be achieved. The requirement to provide mechanisms to achieve these objectives is included in the relevant CRL or Britomart Transport Centre designation conditions. Advice Note 2: This resource consent does not provide approval to close or occupy temporarily Tyler or Galway Streets. If such actions are required they will be sought and managed under the CRL designation and / or an application to vary the Britomart Transport Centre designation.

Review Process for CEMP and other Management Plans 37.

The Consent Holder shall review the CEMP and other management plans at least annually or 

as a result of a material change to the Project; or



to address unforeseen adverse effects arising from construction or unresolved complaints.

Such a review may be initiated by either the Council (Team Leader Central Monitoring) or the Consent Holder and shall take into consideration: a. Compliance with resource consent conditions, the CEMP, other management plans and material changes to these plans; b. Any changes to construction methods; c. Key changes to roles and responsibilities relating to the Project; d. Changes in industry best practice standards; e. Changes in legal or other requirements; f. Results of monitoring and reporting procedures associated with the management of adverse effects during construction;

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

51


g. Any comments or recommendations received from Council (Team Leader Central Monitoring) or as a result of the CCP process regarding the CEMP and other management plans; and h. Any complaints and any response to complaints and remedial action taken to address the complaint as required under Conditions 39 to 42. 38.

A summary of the review process shall be kept by the Consent Holder, provided annually to the Council (Team Leader Central Monitoring), and made available to the Council (Team Leader Central Monitoring) upon request. Concerns and Complaints Management

39.

Upon receiving a concern or complaint during construction, the Consent Holder shall instigate a process to address concerns or complaints received about adverse effects. This shall: a. Identify of the nature of the concern or complaint, and the location, date and time of the alleged event(s); b. Acknowledge receipt of the concern or complaint within 24 hours of receipt; and c. Respond to the concern or complaint in accordance with the relevant management plan, which may include (for example) monitoring of the activity by a suitably qualified expert, and implementation of mitigation measures.

40.

A record of all concerns and / or complaints received shall be kept by the Consent Holder. This record shall include: a. The name and address of the person(s) who raised the concern or complaint (unless they elect not to provide this) and details of the concern or complaint; b. Where practicable and relevant, weather conditions at the time of the concern or complaint, including wind direction and cloud cover if the complaint relates to air quality; c. The relevant known construction activities being undertaken at the time and in the vicinity of the concern or complaint; d. Any other activities in the area unrelated to the Project that may have contributed to the concern or complaint such as non-related construction, fires, traffic accidents or unusually dusty conditions generally; and e. Remedial actions undertaken (if any) and the outcome of these, including monitoring of the activity.

41.

This record shall be maintained on site, be available for inspection upon request, and shall be provided every two months (or as otherwise agreed) to the Council (Team Leader Central Monitoring).

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

52


42.

Where a complaint remains unresolved or a dispute arises, the Council (Team Leader Central Monitoring) will be provided with a copy of all records of the complaint and advice as to 

how it has been dealt with and addressed; and

whether the Consent Holder considers that any other steps to resolve the complaint are required.

Upon receiving records of the complaint the Council (Team Leader Central Monitoring) may determine whether a review of the CEMP and/or management plans is required under Condition 37 to address the complaint. The Council (Team Leader Central Monitoring) will be asked to advise the Consent Holder of its recommendation within 10 working days of receiving the records of complaint.

Specific conditions – land use consent R/LUC/2014/5428 Contaminated Land and Resource Management (National Environmental Standard for Assessing and Managing Contaminants in Soil to Protect Human Health) Regulations 2011 43.

Works shall cease immediately in the vicinity of any contamination not previously identified and the Council (Team Leader Central Monitoring) shall be advised immediately.

Specific conditions – land use consent R/REG/2014/5430 Earthworks Consent Duration 44.

This resource consent shall expire 15 years after the consent commences unless it has been surrendered or been cancelled at an earlier date pursuant to the RMA. Erosion and Sediment Control Plan (“ESCP”)

45.

At least 20 working days prior to the commencement of construction, a finalised ESCP which provides for the management of all bulk earthworks to minimise any discharge of debris, soil, sediment or sediment-laden water beyond the site to either land and/ or stormwater drainage systems shall be prepared and submitted to the Council (Team Leader Central Monitoring) for certification.

46.

No construction activity shall commence until certification from Council is provided.

47.

The Consent Holder shall request the Council’s (Team Leader Central Monitoring) determination as to whether the ESCP can be certified, in writing, within 10 working days of receipt of the ESCP.

48.

The ESCP shall include, but not be limited to, the following matters: a. identification of construction zones and construction support areas; b. specific erosion and sediment control works for each Active Construction Zone (location, dimensions, capacity supporting calculations and design drawings), which should be in line with Industry Best Practice that will meet or exceed the

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

53


performance of measures detailed in Auckland Council Technical Publication No. 90, Erosion & Sediment Control: Guidelines for Land Disturbing Activities in the Auckland Region (TP90); c. catchment boundaries; d. the timing and duration of construction and operation of control works (in relation to the staging and sequencing of bulk earthworks); e. details relating to the management of exposed areas; f. reference to the Chemical Treatment Management Plan and confirmation of ESC measures necessary to give effect to that plan; g. reference to the Contaminated Soils Management Plan and confirmation of ESC measures necessary to give effect to that plan; and h. monitoring and maintenance requirements, including information on complaint investigation and response procedures, training, and roles and responsibilities. 49.

Any change to the ESCP shall be submitted to the Council (Team Leader Central Monitoring) for certification. No activity reliant upon a change to the ESCP can be undertaken until the change has been certified. The Consent Holder shall request the Council’s (Team Leader Central Monitoring) determination as to whether the proposed change can be certified, in writing, within 10 working days of submission of the change. Chemical Treatment Management Plan (“CTMP”)

50.

At least 20 working days prior to the commencement of construction, a CTMP which confirms the measures that will be taken to ensure that construction of the Project or Project Stage will be generally consistent with the Water Quality Assessment and the Industrial and Trade Activities Assessment prepared by Golder Associates (NZ) Limited, both dated December 2014 shall be submitted to Council (Team Leader Central Monitoring) for certification.

51.

The Consent Holder shall request the Council’s (Team Leader Central Monitoring) determination as to whether the CTMP can be certified, in writing, within 10 working days of receipt of the CTMP.

52.

The CTMP shall include, but not be limited to, the following matters: a. Specific design details of the chemical treatment system based on a batch dosing methodology for the site’s settlement tanks, including the potential for use of nonchemical flocculants (e.g. chitin based flocculants such as Haloklear); b. Monitoring, maintenance (including post-storm) and contingency programme (including a record sheet); c. Details of optimum dosage (including assumptions); d. Results of initial chemical treatment trial; e. A spill contingency plan; and

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

54


f. Details of the person or bodies that will hold responsibility for the long term operation and maintenance of the chemical treatment system and the organisational structure which will support this system. 53.

Any change to the CTMP shall be submitted to the Council (Team Leader Central Monitoring) for certification. No activity reliant upon a change to the CTMP can be undertaken until the change has been certified. The Consent Holder shall request the Council’s (Team Leader Central Monitoring) determination as to whether the proposed change can be certified, in writing, within 10 working days of submission of the change. As-built Certification

54.

Prior to construction (bulk earthworks) commencing, a certificate signed by a senior qualified person shall be submitted to the Council (Team Leader Central Monitoring) to certify that the erosion and sediment controls have been constructed in accordance with the certified ESCP(s) as required by Condition 45 of this consent.

55.

Certified controls shall include diversion bunds, silt fences, and sumps. The certification for these subsequent measures shall be supplied immediately upon completion of construction of those measures. Information supplied, if applicable, shall include: a. contributing catchment area; b. shape of structure (dimensions of structure); c. position of inlets/outlets; and d. stabilisation of the structure. General Performance Standards

56.

The Consent Holder shall ensure that there shall be no deposition of earth, mud, dirt or other debris on any road or footpath resulting from bulk earthworks on the subject site. In the event that such deposition does occur, it shall immediately be removed. In no instance shall roads or footpaths be washed down with water without appropriate erosion and sediment control measures in place to prevent contamination of the stormwater drainage system, watercourses or receiving waters.

57.

The operational effectiveness and efficiency of all erosion and sediment control measures specifically required as a condition of resource consent, including the certified ESCP referred to in Condition 45, shall be maintained throughout the duration of bulk earthworks, or until the Project site is permanently stabilised against erosion.

58.

The site shall be progressively stabilised against erosion at all stages of earthworks activity, and shall be sequenced to minimise the discharge of contaminants to groundwater or surface water.

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

55


59.

The Consent Holder shall ensure that the erosion and sediment control measures shall be constructed and maintained in accordance with Auckland Council’s Technical Publication 90: Erosion and Sediment Control Guidelines for Soil Disturbing Activities in the Auckland Region, and any amendments to this document, except where a higher standard is detailed in the documents referred to in conditions above, in which case the higher standard shall apply.

60.

Sediment control measures shall be inspected on a weekly basis and after a significant storm event to ensure effective operation. In the event that a discharge of debris, soil, silt, sediment or sediment-laden water occurs, the activity which resulted in the discharge shall cease immediately and the discharge shall be mitigated and/or rectified to the satisfaction of the Council (Team Leader Central Monitoring).

61.

The Consent Holder shall ensure that all material removed from or delivered to the Project site shall be covered during transportation.

62.

Upon completion or abandonment of bulk earthworks on the Project site all areas of bare earth shall be permanently stabilised against erosion to the satisfaction of the Council (Team Leader Central Monitoring). Review Condition for land use consent R/REG/2014/5430

63.

Pursuant to section 128 of the RMA the conditions of this consent may be reviewed by the Council (Team Leader Central Monitoring) at the Consent Holder’s cost, by giving notice pursuant to section 129 of the Act, within six months after commencement of bulk earthworks and subsequently at intervals of not less than one year thereafter in order to achieve the following: a. To deal with any adverse effects on the environment which may arise or potentially arise from the exercise of this consent and which it is appropriate to deal with at a later stage; b. To alter erosion and sediment control requirements as a result of previous monitoring outcomes, and/or in response to changes to the environment and/or hydro-geological knowledge, and/or changes to industry best practice; c. If, at any time, it is found that the information made available to the Council in the application contained inaccuracies which materially influenced the decision and the effects of the exercise of the consent are such that it is necessary to apply more appropriate conditions; and d. If, at any time, CRL-related works being undertaken under a designation providing for aspects of the Project, or a separate resource consent, leads to an inconsistent approach to the management of effects.

Specific conditions – discharge permit R/REG/2014/5437 Discharge to Air Consent Duration City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

56


64.

This resource consent shall expire 15 years after the consent commences unless it has been surrendered or been cancelled at an earlier date pursuant to the RMA.

65.

The Consent Holder shall ensure that all processes on the Project worksite shall be implemented, operated, maintained, supervised, monitored and controlled so that any emissions authorised by this consent are maintained at the minimum practicable level.

66.

Unless provided for by Condition 67, there shall be no dust or odour beyond the boundary of the Project worksite caused as a result of on-site processes which, in the opinion of Council, is noxious, offensive or objectionable.

67.

All offensive or objectionable dust or odours beyond the boundary of the Project worksite caused as a result of construction and earthworks activities associated with the Project shall be mitigated as soon as practicable in accordance with the requirements of the certified Air Quality Management Plan as required by Condition 69.

68.

The Consent Holder shall ensure that beyond the boundary of the Project worksite, there shall be no hazardous air pollutant, caused as a result of construction and earthworks activities associated with the Project that causes, or is likely to cause, adverse effects on human health, environment or property. Air Quality Management Plan (“AQMP”)

69.

The Consent Holder shall review the draft Air Quality Management Plan – Britomart to Wyndham dated December 2014 (“draft AQMP”), prepared by Golder Associates (NZ) Limited and submit to Council (Team Leader Central Monitoring) a final AQMP(s) which is (are) generally consistent with the draft AQMP provided in support of the application material.

70.

The final AQMP(s) shall be prepared by a senior qualified person, provided to the Council (Team Leader Central Monitoring) for certification at least 20 working days prior to the commencement of construction and shall include: a. a clear identification of the type and location of the controls proposed; b. a detailed framework for the management, mitigation and monitoring of construction and earthworks activities associated with the Project; c. a focus principally on the sources of dust discharges, and d. an assessment of the risk of discharges from each Active Construction Zone and the associated Construction Support Areas.

71.

The final AQMP(s) shall also provide detailed methods including, but not limited to, the following matters: a. methods to ensure the exposed surfaces remain dampened to minimise dust emissions (possible examples include a suspended water spray system or other suitable system, water carts and other suppression methods);

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

57


b. a 20 km/hr vehicle speed limit within the Active Construction Zones and Construction Support Areas; c. installation of wheel washes; d. regular sweeping of public roads around the exit points of Active Construction Zones and Construction Support Areas and sealed vehicle accessways within these areas; e. measures for dampening any temporary stock piles (which are to be limited to no more than 24 mÂł of spoil at any one time in each Active Construction Zone); f. measures for the handling of cement associated with forming of cement stabilised columns, including filter systems and high level alarms where a silo is used; g. covering of loads of material being delivered and removed from the site; h. instrumental monitoring of dust concentrations (identification of a monitoring methodology, monitoring network and appropriate alert thresholds) to ensure that any significant dust effects arising from the Active Construction Zones or Construction Support Areas are identified and remedied as soon as practicable throughout the Project; i.

the locations of instrumental dust monitoring sites, including one re-locatable monitor to be associated with Active Construction Zones A to D and fixed monitors associated with Active Construction Zone E;

j.

measures for responding to continuous instrumental dust monitoring trigger alarms, including contingency measures to reduce measured concentrations below the trigger thresholds and provisions for responding after standard operating hours;

k. measures for undertaking meteorological observations and visual inspections of dust or other air discharges from the Project, to be completed at least on a daily basis, with all relevant information logged; and l.

information regarding complaint logging, investigation and response procedures, training and roles and responsibilities.

72.

The Consent Holder shall request the Council’s (Team Leader Central Monitoring) provides its determination as to whether the AQMP(s) can be certified, in writing, within 10 working days of receipt of the AQMP(s).

73.

Any change to the AQMP(s) shall be submitted to the Council (Team Leader Central Monitoring) for certification. No activity reliant upon a change to the AQMP can be undertaken until the change has been certified. The Consent Holder shall request the Council’s (Team Leader Central Monitoring) determination as to whether the change can be certified, in writing, within 10 working days of submission of the change.

74.

All works shall be undertaken in accordance with the certified AQMP(s).

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

58


Monitoring Requirements 75.

Prior to construction commencing, and for the duration of excavation and construction associated with the Project which have the potential for significant dust emissions, the Consent Holder shall install, operate and maintain mobile instrumental continuous dust monitors for the purposes of monitoring Total Suspended Particulates (TSP) and/or fine particulate matter (PM10). The monitors shall be operated at locations and according to methods detailed in the certified AQMP(s) required by Condition 69.

76.

The instrumental dust monitoring equipment shall be fitted with an alarm system that, when dust concentrations exceed alert levels specified by the certified AQMP(s), send a warning to the responsible person identified by the AQMP(s). The Consent Holder shall ensure that the responsible person, or other nominated person, is available at all times to take immediate action to reduce dust emissions from the site.

Specific conditions – discharge permit R/REG/2014/5435 Contaminated Land Consent Duration 77.

This resource consent shall expire 15 years after the consent commences unless it has been surrendered or been cancelled at an earlier date pursuant to the RMA. Contaminated Soils Management Plan (“CSMP”)

78.

At least 20 working days prior to the commencement of construction, a final CSMP shall be submitted to the Council (Team Leader Earthworks and Contaminated Land, Natural Resources and Specialist Input and Team Leader Central Monitoring) for certification. The CSMP shall be prepared by a suitably qualified and experienced Contaminated Land Professional in accordance with Schedule 13 (A4) of the Auckland Council Regional Plan: Air, Land and Water (ACRP:ALW). The Consent Holder shall request the Council’s (Team Leader Central Monitoring) determination as to whether the CSMP can be certified, in writing, within 10 working days of receipt of the CSMP.

79.

No construction shall commence until certification is provided from the Council (Team Leader Earthworks and Contaminated Land, Natural Resources and Specialist Input and Team Leader Central Monitoring) that the CSMP meets the requirements of Schedule 13 (A4) of the ACRP:ALW.

80.

All measures identified in that CSMP must be established prior to the commencement of bulk earthworks.

81.

The CSMP shall address the following matters: a. Identification of mitigation measures to ensure that discharges from the construction support areas to land or water are minimised, and to ensure that

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

59


potential effects on the health of workers on the site and nearby sites can be appropriately managed b. The areas within the project site designated for the excavation works, including depths and extent of the proposed works, and an updated map showing the land disturbance activity areas; c. Excavation, management, and disposal procedures for soil, sediment, dust, surface run-off water, perched groundwater, and groundwater, if encountered; d. Temporary containment, treatment, and testing procedures for any water getting in contact with the contaminated material if disposal option to the stormwater system or marine environment is considered; e. Contingency measures for unexpected discovery of contamination; f. Proposed gas monitoring in the Lower Queen Street area, and any other proposed sampling and analysis, if applicable; and g. Proposed Works Summary Reporting. Advice Note: The Council acknowledges that the CSMP is intended to provide flexibility of the management of the works and contaminant discharge. Accordingly, the plan may need to be further updated. Any updates must be limited to the scope of this consent and be consistent with the conditions of this consent. If you would like to confirm that any proposed updates are within scope, please contact the Council (Team Leader Earthworks and Contaminated Land, Natural Resources and Specialist Input) on (09) 301 0101.

82.

All disturbance of contaminated and potentially contaminated soil as part of the bulk earthworks activity shall be carried out in accordance with the certified CSMP required by Condition 78 and any changes to the plan shall be submitted to the Council (Team Leader Earthworks and Contaminated Land, Natural Resources and Specialist Input and Team Leader Central Monitoring) for certification prior to the change being implemented. No activity reliant upon a change to the CSMP can be undertaken until the change has been certified. The Consent Holder shall request the Council’s (Team Leader Central Monitoring) determination as to whether the proposed change can be certified, in writing, within 10 working days of submission of the change. Notification of Works

83.

The Consent Holder shall notify the Council (Team Leader Earthworks and Contaminated Land, Natural Resources and Specialist Input and Team Leader Central Monitoring) at least two working days prior to the commencement of bulk earthworks on the subject site. Advice Note: Condition 83 requires the consent holder to notify the Council of their intention to begin works in contaminated areas a minimum of two working days prior to commencement of construction. Please contact the Team Leader, Earthworks and Contaminated Land, Natural Resources and Specialist Input at david.hampson@aucklandcouncil.govt.nz to advise of the start of works. The following details should also be provided:  Name and telephone number of the project manager and the site owner;

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

60


 Site address to which the consents relate;  Activity to which the consents relate; and  Expected duration of the works.

84.

All disturbance of contaminated soil shall be supervised by a suitably qualified and experienced Contaminated Land Professional who shall ensure that soil management and disposal procedures, contingency measures outlined in the certified CSMP required by Condition 78, and all relevant consent conditions are adhered to. Regular inspections of the works area shall be carried out by the Contaminated Land Professional. These inspections shall be documented and the relevant records shall be retained and provided to Council (Team Leader Earthworks and Contaminated Land, Natural Resources and Specialist Input) as part of the Works Summary Report required by Condition 93.

85.

All land disturbance works shall be managed to avoid the potential for crosscontamination of materials to occur. In particular, movement of contaminated soil around the site and/or deposition of contaminated soil on other parts of the site shall be avoided. Soils that are identified for off-site disposal must be loaded directly for removal where possible, and all material shall be covered during transportation offsite.

86.

To minimise the spread of contaminated material, any temporary stockpiles of excavated contaminated material shall be located within the catchment of erosion and sediment controls for the site. All stockpiles shall be covered with either polythene or an equivalent impermeable material when the site is not being worked and during periods of heavy rain.

87.

Excess soil or waste materials removed from the Project worksite shall be deposited at a disposal site that holds a resource consent to accept the relevant level and type of contamination.

88.

Where it can be demonstrated that the soil has been fully characterised and meets the definition of ‘cleanfill’ in accordance with the Ministry for the Environment’s publication ‘A Guide to the Management of Cleanfills’ (2002), the removal of such material to a consented disposal facility is not required. In such circumstances, a record of the location, depth, and volume of the material removed as ‘cleanfill’ shall be kept for the purpose of being included in the Works Summary Report required by Condition 93.

89.

Any perched groundwater or surface run-off water encountered within the excavation area requiring removal shall be considered as potentially contaminated, and shall either: a. be disposed of by a licensed liquid waste contractor; or b. pumped to sewer, providing relevant permits are obtained; or c. discharged to the stormwater system, provided testing demonstrates compliance with 50 times the Australian and New Zealand Environment Conservation Council

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

61


(ANZECC) Guidelines for Fresh and Marine Water Quality (2000) for the protection of 95 percent of marine water species. 90.

Where contaminants are identified that have not been anticipated by the application, works in the area containing the unexpected contamination shall cease until the contingency measures outlined in the certified CSMP required by Condition 78 have been implemented, and have been notified to the Council (Team Leader, Earthworks and Contaminated Land, Natural Resources and Specialist Input). Any unexpected contamination encountered during the works and contingency measures implemented shall be documented in the Works Summary Report required by Condition 93. Advice Note: In accordance with Condition 90 any unexpected contamination may include separate phase hydrocarbons, contaminated soil, perched water or groundwater. The consent holder is advised that where unexpected contamination is significantly different in extent and concentration from that anticipated, handling the contamination may be outside the scope of this consent. Advice should be sought from the Council (Team Leader Earthworks and Contaminated Land, Natural Resources and Specialist Input) prior to carrying out any further work in the area of the unexpected contamination to ensure this is within the scope of this consent.

91.

All imported fill shall: a. comply with the definition of 'cleanfill' in the Ministry for the Environment publication 'A Guide to the Management of Cleanfills’ (2002); b. be solid material of an inert nature; and c. not contain hazardous substances or contaminants above recorded natural background levels of the receiving site. Advice Note: Background contamination levels for the site receiving cleanfill can be found in the Technical Publication No. 153, Background concentrations of inorganic elements in soils from the Auckland Region, Auckland Regional Council (2001).

92.

All sampling and testing of contamination on the site shall be overseen by the Contaminated Land Professional and shall be undertaken in accordance with Contaminated Land Management Guidelines, No.5 – Site Investigation and Analysis of Soils, Ministry for the Environment (revised 2011). Advice Note: All testing and analysis should be undertaken in a laboratory with suitable experience and ability to carry out the analysis. For more details on how to confirm the suitability of the laboratory please refer to Part 4: Laboratory Analysis, of Contaminated Land Management Guidelines No.5.

93.

Within three months of the completion of bulk earthworks on the site, a Works Summary Report shall be provided to the Council (Team Leader Earthworks and Contaminated Land, Natural Resources and Specialist Input and Team Leader Central Monitoring). The Works Summary Report shall be prepared by a suitably qualified and experienced Contaminated Land Professional in accordance with Schedule 13 (A5) of the Auckland Council Regional Plan: Air, Land and Water and Contaminated Land Management Guidelines, No.1 - Reporting on Contaminated Sites in New Zealand, Ministry for the Environment (revised 2011).

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

62


94.

The Works Summary Report shall address the following matters: a. a summary of the works undertaken, including a statement confirming whether the excavation of the site has been completed in accordance with the certified CSMP required by Condition 78; b. the location and dimensions of the excavations carried out, including a site plan; c. a summary of soil, perched water and groundwater testing undertaken (if applicable) including tabulated analytical results, and interpretation of the results in the context of the Contaminated Land Rules of the Auckland Council Regional Plan: Air, Land and Water and the Proposed Auckland Unitary Plan; d. copies of the disposal dockets for the contaminated soil and ‘cleanfill’ material removed from the site; e. records of any unexpected contamination encountered during the works and contingency measures undertaken (if applicable); f. details regarding any complaints and/or breaches of the procedures set out in the certified CSMP required by Condition 78 and the conditions of this consent; g. results of testing, if required, of any spoil disposed offsite; and h. results of testing of any imported fill material to ensure compliance with the definition of 'cleanfill', as per 'A Guide to the Management of Cleanfills’, Ministry for the Environment (2002).

Specific conditions – discharge permit R/REG/2014/5436 Washwater and Wastewater Discharges Consent Duration 95.

This consent shall expire 15 years after the consent commences unless it has been surrendered or been cancelled at an earlier date pursuant to the Resource Management Act 1991. Site Management

96.

At least 20 working days prior to the commencement of construction, a final Industrial and Trade Activities Environmental Management Plan (“EMP”) shall be submitted to the Council (Team Leader Central Monitoring) for certification. The Consent Holder shall request the Council’s (Team Leader Central Monitoring) determination as to whether the EMP can be certified, in writing, within 10 working days following receipt of the EMP. The EMP shall be prepared by a senior qualified person and shall include, but not be limited to, the following: a. identification of the specific activities conducted on the site; b. the identification of potential contaminants associated with these activities;

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

63


c. methods used to prevent identified contaminants contacting stormwater runoff as far as practicable and methods to manage environmental risks from site activities; d. an Emergency Spill Response Plan (which includes the provision that all spills over 20 litres, or any spill of Environmentally Hazardous Substances that has entered the stormwater system, a water-body or has contacted unsealed ground, shall be reported immediately to the Auckland Council’s 24 Hour Pollution Hotline (09-377-3107)); e. an up-to-date and accurate site drainage plan showing the location of all site catchpits and the final discharge point(s) of the site stormwater system; f. an appropriate auditing programme to ensure site performance with all components of the sites EMP; g. methods for providing and recording staff training; and h. a monitoring programme as outlined in Condition 101. 97.

The Consent Holder shall ensure that the site is operated and managed in accordance with the certified EMP to ensure the risks from the site are managed appropriately.

98.

The Consent Holder shall ensure that a copy of the certified EMP is kept on site and accessible at all times. Structural Controls

99.

The Consent Holder shall ensure that the following structural controls are constructed for the following catchment areas and design requirements and they are completed prior to discharges commencing from the site. Works

Device catchment area

Design requirements

Settlement Tanks (2x 12,000l tanks), located in CSAs 2 and 4

All ACZs

Discharge levels as per monitoring Condition 101

Bunding of Environmentally Hazardous Substances

As required

110% of largest container

100. In the event that any minor modifications to the structural controls system are required, the following information shall be provided to Council: a. Plans and drawings outlining the details of the modifications; and b. Supporting information that details how the proposal does not affect the capacity or performance of stormwater management system. All information shall be submitted to, and the proposed modifications certified by the Council (Team Leader Central Monitoring), prior to implementation. Discharge Monitoring

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

64


101. Within 30 days of the installation of the water treatment system, and prior to operation, a discharge monitoring programme, to assess the ongoing adequacy of all management practices, shall be developed and submitted to the Council (Team Leader Central Monitoring) for certification. The monitoring programme shall include, but not be limited to: a. sampling location for final discharge from the site(s); b. sampling locations on site (i.e. swale inlets, outlets etc); c. methods and procedures for discharge sampling on a quarterly basis; d. monitoring parameters for analysis, which shall include: Daily  Turbidity (NTU)  pH Weekly  Total Suspended Solids  Copper (total)  Zinc (total)  Lead (total)  Total Petroleum Hydrocarbons

mg/L mg/L mg/L mg/L mg/L

e. identified trigger levels for each of the above parameters. These trigger levels shall be developed with reference to the ANZECC Guidelines for water quality where applicable; and f. the methods and procedures for investigating and reporting stormwater discharge monitoring results to the Council (Team Leader Central Monitoring). 102. The discharge monitoring programme shall be implemented upon completion of works set out in Condition 99. Reporting 103. Within five working days of receipt of sample results showing contaminants exceeding the agreed trigger levels (Condition 101(e)): a. an investigation shall be undertaken to determine why exceedances were detected and to identify any additional source controls or treatment required; and b. the results of the investigation shall be reported to the Council (Team Leader Central Monitoring). 104. Within eight weeks following the start of the monitoring required by Conditions 101 and 102, a monitoring report shall be submitted to the Council (Team Leader Central Monitoring). The monitoring report shall include, but not be limited to, the following: a. a summary of the monitoring results to date;

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

65


b. an interpretation of those results and suggestions for improvement to the site operations; c. a programme for ongoing monitoring including the reporting of results; and d. a programme for the ongoing maintenance of the discharge water management and treatment system.

Specific conditions – water permit R/REG/2014/5432 Take and Diversion of Groundwater DEFINITIONS: Commencement of Dewatering:

Means commencement of bulk excavation and/or commencing taking any groundwater from the tunnel excavation and/or any dewatering prior to excavation.

Completion of Excavation:

When all bulk excavation has been completed

Completion of Dewatering:

Means when the tunnel has been constructed, all backfilling has been completed and effectively no further groundwater is being taken for the construction of the tunnel.

Completion of Construction

Means when the Certificate of Completion is issued by AC.

Significant damage

When damage is considered to affect serviceability or structural integrity.

Damage

Includes aesthetic, serviceability and significant damage.

Alert Level

Monitoring reaches a level close to, or equal to the design value, which is below the level where damage could occur unless movement continues unchecked, and requires review to assess the future trend.

Alarm Level

Monitoring reaches the value, and/or level close to which damage could occur, and requires immediate action including the cessation of ground dewatering and other construction activities that may have an effect on ground deformation

Manager:

Means the Team Leader Water Allocation, NRSI, AC, or nominated AC staff acting on the Team Leader’s behalf.

RL:

Means Reduced Level.

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

66


Services:

Includes for example fibre optic cables, sanitary drainage, stormwater pipes, gas and water mains, power and telephone, road infrastructure assets such as footpaths, kerbs, catch-pits, pavements and street furniture, settlement monitoring stations and groundwater monitoring bores.

Consent Duration 105. This consent shall expire 35 years after the consent commences unless it has been surrendered or been cancelled at an earlier date pursuant to the Resource Management Act 1991. Performance Standards 106. The Consent Holder shall ensure that all excavations, dewatering systems, retaining structures and associated works (including backfilling) for the tunnel construction and associated works shall be designed, constructed and maintained so as to avoid any damage that affects serviceability of structures and services. 107. Within the settlement contours on drawings CRL-PAT-RME-000-DRG-0403, Rev 3.0 dated 09/07/2015 and 0404, Rev 3.0 dated 09/07/2015 and 0405, Rev 2.0 dated 03/07/2015 attached to these conditions in Appendix 2, the Consent Holder must ensure that the damage to buildings from the Project does not exceed the “slight damage” category extent detailed in the table below. 108. Beyond the settlement contours on drawings CRL-PAT-RME-000-DRG-0403, Rev 3.0 dated 09/07/2015 and 0404, Rev 3.0 dated 09/07/2015 and 0405, Rev 2.0 dated 03/07/2015 attached to these conditions in Appendix 2, the Consent Holder must ensure that the damage to buildings from the Project does not exceed the “negligible damage” extent detailed in the table below.

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

67


109. The Consent Holder shall not exceed the maximum extent and magnitude of total settlement as defined by the settlement contours presented on drawings CRL-PAT-RME-000-DRG-0403, Rev 3.0 dated 09/07/2015 and 0404, Rev 3.0 dated 09/07/2015 and 0405, Rev 2.0 dated 03/07/2015 attached to these conditions in Appendix 2. 110. The Consent Holder shall construct the CRL trench no deeper than 1.2m below the base of tunnel design invert levels shown on Plan: CRL-PAT-RME-000-DRG0001-1.0 dated 17 October 2014. The maximum excavation depth for the CRL trench is RL-8.5m. 111. The Consent Holder shall design, construct and continuously maintain the temporary perimeter cut-off walls to achieve no more than 0.3m3/ day ingress (through the wall) of groundwater per 10m of wall for both the Chief Post Office Excavation Ch50m to Ch95m (“CPO�) and the CRL Trench Excavation Ch95m to Ch300m. 112. There shall be no visible seepage of water through the walls of the excavations at the CPO and Lower Queen Street area throughout construction. Any visible leakage shall be caulked, or otherwise sealed, as soon as is practicable. 113. The Consent Holder shall ensure that the cut-off walls within the CPO shall be installed a minimum of 2m into unweathered East Coast Bays Formation. City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

68


114. The cut off walls within the CRL trench excavation between Ch95 and Ch300 shall be installed to the top of the unweathered East Coast Bays formation bedrock. 115. After completion of construction, groundwater levels adjacent to the tunnel alignment shall not reduce below pre-existing seasonal low levels or rise above seasonal high levels measured during pre-construction monitoring in accordance with Condition 130. 116. The Consent Holder shall ensure that there is no long term ground settlement caused by post construction dewatering or long term mounding by the tunnel alignment damming. Groundwater and Settlement Monitoring and Contingency Plan (“GSMCP”) 117. At least 20 working days prior to the commencement of dewatering, the Consent Holder shall prepare and submit a GSMCP to Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit) for certification. 118. The Consent Holder shall request: a. Certification by Council be undertaken by an independent peer reviewer; and b. Council’s (Team Leader Water Allocation, Natural Resources and Specialist Input Unit) determination as to whether the GSMCP can be certified, in writing, within 10 working days following receipt of the GSMCP. 119. No dewatering on the subject site shall commence until certification from Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit) is provided. 120. Prior to the Consent Holder submitting the GSMCP under Condition 117, the Consent Holder shall request that Council engage, at the cost of the Consent Holder, a suitably qualified independent specialist, agreed to by the Consent Holder, to fill the role of Independent Building Assessor (“IBA”). 121. The Consent Holder shall ensure that the IBA, required by Condition 120, provides a written report to Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit) prior to commencement of construction and at no less than monthly intervals following commencement of construction and at key construction stages. The report may include recommendations to Council on building serviceability and damage matters, and how these matters may be addressed, having regard to the following: a. displacement and damage predictions of the affected buildings; b. monitoring methodology and the results of that monitoring; c. alert and alarm limits; and d. any monitoring reports prepared in accordance with Conditions 135, 136, 157, 158 and 159.

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

69


122. The GSMCP, required by Condition 117, shall include the requirements of this resource consent including, but not limited to, the following: a. an “as built� survey plan of all monitoring locations based on approximate positions located on the plans entitled CRL-PAT-RME000-DRG-0403, Rev 3.0 dated 09/07/2015 and 0404, Rev 3.0 dated 09/07/2015 and 0405, Rev 2.0 dated 03/07/2015 (Appendix 2) and any further building-specific monitoring requirements determined from the detailed pre-construction building condition assessment; b. full details of groundwater (including construction logs), ground surface, building, retaining wall, inclinometer monitoring programme and conditions surveys required by this consent; c. a bar chart, such as a Gantt chart, showing the timing and frequency of the condition surveys and monitoring required by this consent relative to the commencement of dewatering and the completion of dewatering; d. groundwater alert and alarm triggers, including methodology for their determination. The Consent Holder shall use existing groundwater level data and the groundwater levels measured as required by Condition 129, to establish seasonal low groundwater levels; e. details of all alert and alarm triggers for each ground, building and retaining wall deformation marks and inclinometers as determined by conditions of consent or as revised by further detailed design; f. details of the contingency measures to be implemented if alert or alarm triggers are exceeded including a Response Plan (required by Condition 158). In particular, in relation to groundwater alarm triggers, contingency measures must include actions to prevent further groundwater drawdowns or rise; g. identification of any adjacent services susceptible to damage and details of any pre and post construction monitoring or inspection; h. details of the monitoring proposed to be undertaken to protect 35 Albert Street (Consent No. 43669) and Downtown Precinct Development (Consent No. 43792) consent holders against cumulative settlement effects; i.

identification of existing basements which could be subject to potential flooding from post-construction groundwater mounding. Details of monitoring of long-term groundwater mounding effects. Details of groundwater drain maintenance to prevent groundwater mounding; and

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

70


j.

review following the construction building condition surveys (required by Condition 133) the proposed alarm and alert trigger levels in Appendix 4 to confirm they are appropriately set to ensure the “slight� damage category will not be breached and whether monitoring frequency is adequate.

123. The GSMCP may be varied, including frequency of monitoring, subject to the certification of the Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit). 124. Once certified, the GSMCP shall be implemented for the periods specified in conditions of this consent. Upper Albert Street Building Assessment Conditions 125. Additional site investigations shall be carried out at the detailed design stage to confirm the preliminary design assumptions for soil stiffness affecting the upper Albert Street zone. The additional site investigations will consist of a minimum of two additional Cone Penetrometer Tests on the eastern side of the upper Albert Street zone. The predicted total settlement contours shown on drawings CRL-PAT-RME-000DRG-0403, Rev 3.0 dated 09/07/2015 and 0404, Rev 3.0 dated 09/07/2015 and 0405, Rev 2.0 dated 03/07/2015 shall be modified to take the site specific data into account. 126. Detailed building condition surveys shall be carried out, predesign and preconstruction, to determine the existing damage category of each building in the upper Albert Street zone and their sensitivity to any further settlement. 127. Should the pre-construction building condition survey and assessment highlight greater sensitivity of buildings to settlement than envisaged by the application, additional design measures ( that may include modifications to the design of the retention system or further geotechnical investigation) shall be undertaken. 128. The Consent Holder shall prepare a report which shall include the outcomes from the assessment required to be undertaken by Conditions 125, 126 and 127 and any design modifications made. The Consent Holder shall submit the report to the Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit) for certification. Certification must be obtained prior to commencement of dewatering within a minimum 30m chainage distance from any particular building. Monitoring - Groundwater 129. The Consent Holder shall install, maintain and replace if necessary, groundwater monitoring boreholes listed in Appendix 3 of this consent and shown on drawings CRL-PAT-RME-000-DRG-0403, Rev 3.0 dated 09/07/2015 and 0404, Rev 3.0 dated 09/07/2015 and 0405, Rev 2.0 dated 03/07/2015 of this consent, for the period required by the conditions of this consent. City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

71


130. The Consent Holder shall measure and record groundwater levels at the monitoring boreholes specified in drawings CRL-PAT-RME-000-DRG-0403, Rev 3.0 dated 09/07/2015 and 0404, Rev 3.0 dated 09/07/2015 and 0405, Rev 2.0 dated 03/07/2015 (Appendix 2): a. at a minimum of weekly intervals for a period of at least 3 months before commencing dewatering (to establish baseline groundwater variability), and then b. at least three times weekly for all monitoring boreholes during dewatering until either the completion of dewatering, or until such time following the completion of dewatering that stable measurements are demonstrated and certification is provided by the Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit). All water level data shall be recorded to an accuracy of at least ± 10mm (to be calibrated by the instrument supplier). These records, reported in reduced level, shall be compiled and submitted to the Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit) at monthly intervals. 131. The provisional groundwater alert trigger level criteria are listed in Schedule B and Schedule B.1 below for the monitoring boreholes. The GSMCP, when lodged for certification by Council as required by Condition 117, may amend the provisional groundwater alert and alarm trigger levels below:

1

Schedule B: Provisional Alert Trigger Level Criteria – Non Britomart Alert Trigger Low Level (from chainage 300 to 0.5 metres below seasonal low in fill and Tauranga 610) Alluvium Alert Trigger High Level Seasonal high level in fill, Tauranga marine sediments and Tauranga Alluvium Alert Trigger Low Level – ECBF 90% of predicted drawdown response in ECBF (EU & ER) Note 1: Schedule B applies to the area from chainage 300 to 610, being the area other than that defined as “Britomart” in Schedule B.1.

2

Schedule B.1: Provisional Alert and Alarm Trigger Level Criteria – Britomart Alert Trigger Low Level 0.8 metre below seasonal low in fill, Tauranga marine sediments and Tauranga Alluvium Alert Trigger Low Level – ECBF 90% of predicted drawdown response in ECBF (EU & ER) Alarm Trigger Low Level 1.0 metre below seasonal low in fill, Tauranga marine sediments and Tauranga Alluvium Alarm Trigger High Level Seasonal high level in fill, Tauranga marine sediments and Tauranga Alluvium Note 2: Schedule B.1 applies to the Britomart area only, being that area from chainage 50 to 300.

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

72


132. Where groundwater alert and alarm trigger levels are exceeded, as identified from monitoring data obtained pursuant to Condition 130, the actions set out in the certified GSMCP shall be undertaken and the Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit) shall be notified within 2 working days and advised of the trigger exceedance, the risk of settlement causing damage to buildings, and details of the actions taken. Building Inspection 133. Prior to the commencement of perimeter piling adjacent to the relevant structure and/or commencement of dewatering (whichever is the sooner), the Consent Holder shall employ an independent senior qualified person to undertake a detailed pre-construction condition survey, of all buildings specified in Appendix 1 to confirm their existing condition, subject to the approval of the property owner. The survey shall include, but not be limited to, the following: a. any information about the type of foundations; b. existing levels of damage considered to be of an aesthetic or superficial nature; c. existing levels of damage considered to affect the serviceability of the building where visually apparent and without recourse to intrusive or destructive investigation; d. a professional opinion as to whether observed damage may or may not be associated with actual structural damage; e. susceptibility of the building or structure to further movement; f. specific assessment of building damage from the predicted total settlement contours showing on drawings CRL-PAT-RME-000-DRG-0403, Rev 3.0 dated 09/07/2015 and 0404, Rev 3.0 dated 09/07/2015 and 0405, Rev 2.0 dated 03/07/2015 and with reference to the trigger levels identified in Appendix 4; g. review of proposed alarm and alert trigger levels to confirm they are appropriately set and movement less than trigger levels set will not exacerbate damage, and whether the monitoring frequency and locations of monitoring points are adequate; and h. photographic evidence of (b) and (c). 134. Where the Consent Holder is required to access property (including buildings or structures) owned by a third party to undertake monitoring, surveys or inspections and that access is declined or subject to what the Consent Holder considers to be unreasonable terms, the Consent Holder shall notify the Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit) of that circumstance, and provide an alternative monitoring plan which includes the matters stated in Condition 122.

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

73


135. Any condition survey undertaken in accordance with Condition 133, or any other condition surveys undertaken by the Consent Holder, shall be undertaken as follows: a. The Consent Holder shall employ an independent senior qualified person to undertake the condition surveys and that person shall be identified in the CEMP (required by Condition 33); b. The Consent Holder shall contact owners of those buildings and structures where a condition survey is to be undertaken to confirm the timing and methodology for undertaking a pre-construction condition survey; c. The Consent Holder shall record all contact, correspondence and communication with owners and this shall be available on request for the Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit); d. The Consent Holder shall provide the building condition survey or structure condition survey report to the relevant property owner and the Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit) within 15 working days of the survey being undertaken; e. The Consent Holder shall undertake a visual inspection during construction if requested by the building or structure owner where a pre-construction condition survey has been undertaken. Where a condition survey has been undertaken by the building or structure owner, the Consent Holder shall continue to undertake monthly visual inspections until the Completion of Dewatering of the project; and f. The Consent Holder shall develop a system of monitoring the condition of existing buildings or structures which is commensurate with the type of the existing building or structure and the proximity of the project works in order to assess whether or not construction activities are compromising the structural integrity of the building or structure. 136. The Consent Holder shall carry out a visual inspection of the surrounding ground and external building facades of the listed buildings in Appendix 1 adjacent to the tunnel trench to monitor any deterioration or movement of any pre-existing cracks. Unless otherwise agreed to by Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit), after consultation with the relevant building owner, this is to be carried out at least twice per week from the commencement of dewatering until completion of excavation and then at least weekly until completion of dewatering. A record is to be kept of the time, date and any observations for each inspection. This record is to be maintained and submitted to the Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit) in accordance with Condition 159.

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

74


137. The Consent Holder shall ensure that no earlier than 6 months after completion of dewatering and within 6 months of completion of construction, a postconstruction condition survey covering the matters identified in Condition 133 be completed of any building that had a pre-construction survey as identified in Appendix 1. The condition survey report shall include a determination of the cause of damage identified (if any) since the pre-construction condition survey or previous survey and steps to repair it as provided for in Condition 157. The requirements of this condition need not be fulfilled for any particular building where the Consent Holder can provide written evidence to the Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit) that the current owner of that building has agreed they do not require such a condition survey. 138. The Consent Holder shall, without delay, at the reasonable request of the Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit) undertake an additional condition survey on any building within the area defined by the groundwater monitoring, deformation monitoring and modelling undertaken pursuant to the conditions of this consent potentially affected by the excavation for the purpose of checking for damage and for following up on a report of damage to that building. The requirement for any such condition survey will cease 6 months after the completion of construction unless the requirements of Condition 137 have not been met and subject to a consistent pattern of deformation records having been obtained in this period in which no evidence of adverse effects is apparent. 139. During construction the Consent Holder shall implement procedures that will appropriately respond to the information received from the monitoring system, including assessment at each excavation stage of the actual retention and building response against the predictions determined from the detailed design. For the Albert Street excavations and in particular the upper Albert Street zone, should the actual response exceed those predicted for the first stages of excavation, contingency measures pre-determined from the detailed design and detailed in the Response Plan required by Condition 158 shall be implemented to increase the effective stiffness of the retention system and reduce wall deflections during subsequent excavation stages. 140. The Consent Holder shall include potential cumulative settlement effects from the basement excavation of the development at 35 Albert Street, Auckland Central, as authorised by Consent 42859 and from the Albert Street Stormwater Main Realignment Consent as authorised by Consent 43669, detailed in the respective consent conditions, for the assessment of ground and building settlement trigger levels on and adjacent to 12 to 26 Swanson Street and 41 Albert Street, Auckland Central until the completion of ground and building settlement monitoring at 35 Albert Street, Auckland Central. City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

75


141. The Consent Holder shall include potential cumulative settlement effects from the basement excavation of the re-development of the Downtown Shopping Centre site, Auckland Central, as authorised by Consent 43792, and detailed in the respective consent conditions, for the assessment of ground and building settlement trigger levels on the Zurich Building (21 Queen Street), the HSBC building (1 Queen Street) and the Old Customs House building (12-32 Customs Street West) until the completion of ground and building settlement monitoring required by Resource Consent 43792. Ground Surface and Building Monitoring 142. The Consent Holder shall establish and maintain a settlement monitoring network of ground settlement monitoring marks and building movement monitoring marks to detect any deformation (vertical and/or horizontal movement) for the period required by the conditions of this consent, as follows: a. The minimum scope of settlement monitoring is shown on Drawings CRL-PAT-RME-000-DRG-0403, Rev 3.0 dated 09/07/2015 and 0404, Rev 3.0 dated 09/07/2015 and 0405, Rev 2.0 dated 03/07/2015 (Appendix 2); b. Subject to the owners’ approval, at least two sets of building movement monitoring marks shall be located on each building listed in Appendix 1; and c. The final location and number of building movement monitoring marks shall take into account the building type and size, accessibility to survey the marks and risk of damage from ground settlement and the effects of differential settlement from the predicted settlement contours on drawings CRL-PAT-RME-000-DRG-0403, Rev 3.0 dated 09/07/2015 and 0404, Rev 3.0 dated 09/07/2015 and 0405, Rev 2.0 dated 03/07/2015. 143. The Consent Holder shall survey and record each ground settlement and building movement monitoring mark at least three times prior to the commencement of dewatering to establish a baseline elevation. 144. All settlement and building monitoring mark surveys shall be to a horizontal and vertical accuracy of at least ¹ 2mm or as otherwise achieved by precise levelling. These records shall be compiled and submitted to the Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit) prior to the commencement of dewatering. 145. The Consent Holder shall survey and record the readings at each ground settlement and building monitoring mark on a monthly basis, until either the completion of dewatering, or until such time following the completion of excavation/ dewatering that stable measurements are demonstrated and certification is provided by the Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit). City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

76


146. The Consent Holder shall survey and record the readings at each ground settlement and building monitoring mark within 50m of trench excavations during excavations/dewatering on a daily basis, until either the completion of dewatering, or until such time following the completion of excavation that stable measurements are demonstrated and certification is provided by the Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit). Retaining Wall Monitoring 147. The Consent Holder shall ensure that retaining wall deformation pins are installed along the top of the boundary walls of the tunnel excavation at a distance of approximately 6.0 metre intervals to monitor both vertical and lateral wall movement. 148. Baseline monitoring before commencement of dewatering shall be undertaken three times to a horizontal and vertical accuracy of +/-2mm achieved by precise levelling and the results of monitoring shall be submitted to the Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit), prior to the commencement of dewatering. 149. Alert and Alarm trigger levels for retaining pin monitoring as required in Condition 147 shall be confirmed and/or revised following the completion of the preconstruction building surveys and assessments required in Conditions 125, 126, 127 and 128. The final trigger levels shall take into account the building type and potential risk of damage from ground settlement quantified from these surveys and assessments. 150. From the commencement of excavation to one month after completion of excavation the Consent Holder shall measure the monitoring marks at an average of each 2 metres depth of excavation, at a maximum frequency of weekly intervals. 151. From one month after completion of excavation to the completion of dewatering, monitoring shall be at fortnightly intervals. Monitoring carried out shall be reported and submitted to Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit) in accordance with Condition 161. 152. Inclinometers shall be installed along the excavation within the zones shown on the drawings CRL-PAT-RME-000-DRG-0403, Rev 3.0 dated 09/07/2015 and 0404, Rev 3.0 dated 09/07/2015 and 0405, Rev 2.0 dated 03/07/2015 either within a retaining pile or immediately behind one and extending to the base of the retaining pile. The specific locations will be confirmed following detailed design and will be confirmed in the final GSMCP. Measurement accuracy shall be to best practice.

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

77


153. The Consent Holder shall survey, record and report the readings of the inclinometer as per Schedule C below: Schedule C: Inclinometer Surveys Baseline: Pre Construction

Commencement of excavation to one month after Completion of Excavation unless otherwise agreed under Condition 123 Inclinometer

Frequency:

Reporting:

Best practice

Submitted to the Council (Team Leader Water Allocation, NRSI) prior to the Commencement of Dewatering

Daily intervals unless a different frequency has been agreed to in writing by Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit) As per Condition 161

154. The Inclinometer Deformation Alert Levels of deflection and the Inclinometer Deformation Alarm levels of deflection are as follows: a. Adjacent to existing buildings – as specified in the GSMCP; and b. Precinct Properties Ltd building – Downtown Shopping Centre redevelopment - alarm levels are subject to cumulative effects and require consultation in accordance with Condition 141. Services 155. The Consent Holder shall identify potentially affected services and, prior to the commencement of dewatering, undertake a condition survey of all such services in consultation with the relevant service providers. The monitoring of any settlement effects on those potentially affected services shall be in accordance with Conditions 142, 145 and 146. In the event that the services trigger levels listed in Appendix 4 are breached, remedial actions must be in accordance with Conditions 157 and 158. 156. A condition survey of potentially affected services shall be completed by the Consent Holder no earlier than 6 months after completion of dewatering and no later than completion of construction, to confirm in writing to the Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit) and the asset owner the results of the survey. The survey shall include a determination of the cause of any damage identified (if any) since the condition survey provided for in Condition 155. The post- condition survey need not be completed where the Consent Holder has written evidence that a post-condition survey was not required by the service provider.

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

78


Contingency 157. If any damage to buildings, structures or services is caused wholly or in part by the exercising of this consent, the consent holder shall: a. notify the Council (Team Leader Water Allocation Natural Resources and Specialist Input Unit) and the asset owner as soon as practical; b. engage a senior qualified person to prepare a report as soon as practical describing the damage and identifying methods to avoid and mitigate the potential for further damage and to remedy any damage caused wholly or in part by the exercising of this consent and provide a copy of the report to the Council (Team Leader Water Allocation Natural Resources and Specialist Input Unit) and the asset owner; and c. thereafter promptly undertake (at the entire cost of the Consent Holder) all necessary repairs to fully restore and remedy the damage caused by the exercise of this consent. “Entire cost” includes all design and consenting costs as well as all construction costs. This obligation as a condition of the resource consent shall enure until: i)

Two years after completion of dewatering, or

ii) In the case of the Lower Queen Street area, two years after extraction of sheet piles; iii) One year after groundwater levels have stabilised; and iv) Six months after any completion of any other works associated with the Project which have the potential to cause settlement. 158. The Response Plan, included in the GSMCP, shall be prepared in accordance with drawings CRL-PAT-RME-000-DRG-0403, Rev 3.0 dated 09/07/2015 and 0404, Rev 3.0 dated 09/07/2015 and 0405, Rev 2.0 dated 03/07/2015 (Appendix 2), and shall be implemented in the event that differential settlement between any two ground settlement monitoring marks exceeds the identified triggers, or total settlement exceeds the identified triggers in Appendix 4. The Appendix 4 trigger levels are to be revised, in accordance with Condition 133(g), if recommended by the building and structure condition surveys carried out in accordance with Conditions 133 and 138. 159. In the event of any Alert or Alarm trigger level exceedance at any of the ground surface and building monitoring stations and/or trigger level exceedance of groundwater levels in the monitoring bores, associated with the construction works, then the Consent Holder shall undertake the following activities: a. Notify the Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit) and the Independent Building Assessor within 24 hours; b. If measurements exceed any of the alert values then a senior qualified person engaged by the Consent Holder or the Consent Holder’s Contractor shall reassess the works constructed up to that time to identify the reasons for higher City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

79


movements and confirm whether measures (if any) are required to restrain further increases in movement and confirm that possible ensuing effects will not adversely impact building serviceability. Measures (if any) to be implemented are to be as identified in the GSMCP, and may include an increase in the frequency of monitoring, or additional support measures. c. The senior qualified person shall prepare and submit a written report to the Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit), within one week of alert level exceedance, which provides analyses of all monitoring data, relating to the exceedance of any of the trigger levels and any actions taken; d. If measurements exceed any of the alarm values the Consent Holder shall: i)

Follow the process identified in Condition 159(b);

ii)

Commission and submit a written report, prepared by the senior qualified person engaged in accordance with Condition 159(b) to the Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit), within one week of alarm level exceedance, which provides analyses of all monitoring data, relating to the exceedance of any of the trigger levels and any recommendations for remedial actions if required in order to complete construction so as to avoid damage that will affect building serviceability; and

iii) Implement the recommendations of the report. In the instance that the recommendation is to stop work pursuant to Conditions 159(b) and (d), the remedial action(s) that have been recommended shall be undertaken before the works recommence. e. In relation to alarm level exceedance, recommendations of the IBA (refer Condition 120), which may include remedial actions up to and including stopping the works if that is in the best interests of preventing building serviceability damage, shall be implemented (unless the building owner(s) request in writing that the construction works are to be completed in accordance with the report prepared under Condition 159(c)(ii)). Advice Note: Condition 159 operates independently from and does not detract from, but may assist to inform, Council’s role in relation to monitoring, and ensuring compliance with conditions of consent, including Condition 106.

Reporting 160. The Consent Holder shall advise the Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit), in writing, of the date of the proposed commencement of dewatering. 161. All data collected as required by conditions of this consent from commencement of dewatering to completion of monitoring are to be compiled, compared with the relevant trigger levels and submitted to the Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit) at two monthly intervals, unless

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

80


otherwise specified in this consent, setting out the previous results, providing an explanation for any trends and providing a construction progress timeline. Review Condition – Water Permit R/REG/2014/5432 162. The conditions of this consent may be reviewed by the Council (Team Leader Water Allocation, Natural Resources and Specialist Input Unit) pursuant to Section 128 of the Resource Management Act 1991, by the giving of notice pursuant to Section 129 of the Act, within six months after commencement of dewatering and subsequently at intervals of not less than one year thereafter in order: a. to vary the monitoring and reporting requirements, and performance standards in order to take account of information, including the results of previous monitoring and changed environmental knowledge, on: i) ground conditions; ii) aquifer parameters; iii) groundwater levels; and iv) ground surface deformation. b. to deal with any adverse effect on the environment arising or potentially arising from the exercise of this consent, and in particular effects on buildings, structures and services.

Advice notes 1.

If you disagree with any of the above conditions, or disagree with the additional charges relating to the processing of the application, you have a right of objection pursuant to sections 357A or 357B of the Resource Management Act 1991. Any objection must be made in writing to Council within 15 working days of notification of the decision.

2.

The Consent Holder is responsible for obtaining all other necessary consents, permits, and licences, including those under the Building Act 2004, and the Heritage New Zealand Pouhere Taonga Act 2014. This consent does not remove the need to comply with all other applicable Acts (including the Property Law Act 2007), regulations, relevant Bylaws, and rules of law. This consent does not constitute building consent approval. Please check whether a building consent is required under the Building Act 2004.

3.

This development involves undertaking construction work to Watercare’s wastewater network. The Consent Holder will be responsible for ensuring all necessary approvals are obtained from Watercare. See Watercare’s website (www.watercare.co.nz) for more information.

4.

If any archaeological features are uncovered on the site, it is recommended that works cease and council’s representative monitoring your application is notified immediately. For guidance and advice on managing the discovery of archaeological features contact the Team Leader Cultural Heritage Implementation on 09 301 0101. Please note in the event of a discovery, contacting Heritage New Zealand, as well as the local Mana Whenua is recommended.

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

81


5.

The Consent Holder shall be advised that any works, structures (including ground-anchors) or access required to facilitate the excavations/retaining/foundation construction both permanent and temporary on adjacent properties or land may require the written consent of the affected property owner to be submitted with building and/or resource consent application(s). For more advice the Consent Holder shall contact Auckland Council town planning and building control help desks.

6.

It is unlawful to modify or destroy an archaeological site without the prior authority of Heritage New Zealand issued under the Heritage New Zealand Pouhere Taonga Act 2014. That authority will include a comprehensive set of conditions in respect of archaeological evidence that may be encountered.

7.

The Consent Holder shall be advised that any works authorised under this consent, which rely on the alteration to the Britomart Transport Centre designation, shall not commence within the Britomart Transport Centre designation area until the alteration to the Britomart Transport Centre designation has been approved.

8.

The Consent Holder will prepare an Air Quality Management Plan in compliance with the requirements under both the conditions of this resource consent and the CRL designation conditions.

Alan Watson Chair of the Commissioners

Date: 28 August 2015

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

82


Appendix 1 to Resource Consent Conditions Conditions 133 to 138 of this resource consent require building condition surveys to be undertaken prior to commencement of dewatering. In accordance with Conditions 133 to 138, at a minimum, building condition surveys shall be undertaken for the following buildings:

ID

Address

Property Known As

1

12 Queen Street

CPO

2

21 Queen Street

Zurich House

3

23-29 Albert Street

ANZ Centre

4

12-26 Swanson Street

Affco House Carpark

5

35 Albert Street

Price Buchanan Building

6

37 Albert Street

7

39 Albert Street

8

46-50 Albert Street

APN NZ Complex

9

52-56 Albert Street

APN NZ Complex

10

41 Albert Street

Prince Albert Apartments

11

51-53 Albert Street

12

55 Albert Street

13

57 Albert Street

14

61 Albert Street

Shakespeare Hotel Brewery

15

58 Albert Street

APN NZ Complex

16

38 Wyndham Street

Wyndham Towers

17

63 Albert Street

AMI House

18

2 Queen Street

Endeans Building

19

12-32 Customs Street West

Old Customs House

20

20 Customs Street East

Levy Building

21

14-18 Customs Street East

Former Sofrana House

22

10 Customs Street East

Barrington Building

23

13 Albert Street

Yates Building

24

3 Albert Street

West Plaza

25

148 Quay Street

26

152 Quay Street

Harbour View Building

27

2 – 8 Customs Street

Mercure Hotel

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

83


Appendix 2 to Resource Consent Conditions Plans (three in total): CRL-PAT-RME-000-DRG-0403, Rev 3.0 dated 09/07/2015 and 0404, Rev 3.0 dated 09/07/2015 and 0405, Rev 2.0 dated 03/07/2015

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

84


Appendix 3 to Resource Consent Conditions Groundwater Monitoring Bores:

Monitoring Bore Screen Geology Existing Borehole ID

Screen Geology

BH34-1

(Fill/TL)1

BH34-2

(ER /TA)1

BH34-3

(EU)1

BH35-1

(Fill/TL)1

BH35-2

(ER /TA)1

BH35-3

(EU)1

QS1-1

(Fill/TL)1

QS1-2

(ER/TA)1

QS1-3

(EU)1

QS2-1

(Fill/TL)1

QS2-2

(ER /TA)1

QS2-3

(EU)1

BH32-1

(Fill/TL)1

BH32-2

(ER /TA)1

BH32-3

(EU)1

BH43-1

(Fill/TL)1

BH43-2

(ER /TA)1

BH43-3

(EU)1

BH52-1

(Fill/TL)1

BH52-2

(ER /TA)1

BH52-3

(EU)1

BH45-1

(Fill/TL)1

BH45-2

(ER /TA)1

BH45-3

(EU)1

EB301

(Fill/TL)

EB302

(Fill/TL/EU)

BH23

New Borehole ID

Screen Geology

EB302

(Fill)

BH401-1

Fill/TL

BH401-2

ER /TA

BH401-3

EU

(EU)1

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

85


BH202A

(EU)

BH202B

(EU)

BH251 - A

(EU)

BH251 - B

(EU)

BH203

(EU)

BH255

EU

BH204-1

(ER/EW

BH204-2

EU

EB305

ER/EW

EB306

ER/EW

EB307

ER/EW

BH205

ER

BH205

EU

BH402

(EU)

BH403

Fill/TA

BH404

Fill/TA

BH405

Fill/TA

BH406 A

ER

BH406 B

Top of EU

BH407 A

Top of EU

BH407 B

ER

BH408 A

TA

BH408 B

ER

BH409 A

TA

BH409 B

ER

BH409 C

Top of the EU

BH410

TA

BH411 A

TA

BH411 B

ER

BH411 C

Top of EU

BH412 A

Top of the TA

BH412 AA

Base of the TA

BH412 B

ER/EW

BH412 C

Top of EU

BH413 - A

Fill/TL

BH413 - B

TA/ER

BH413 - C

EU

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

86


BH414 - A

TA

BH414 - B

ER

BH Endeans Base of TL Note 1: Installed as part of Britomart Station investigation and monitoring conditions. These historic holes proposed for monitoring have not yet been assessed for accessibility or functionality. Note 2: Could be combined with Swanson Shaft-specific groundwater monitoring well.

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

87


Appendix 4 to Resource Consent Conditions Deformation Limits – Buildings Note: Further detailed design may modify the trigger levels presented below. Any revisions based on further design shall not increase the number of properties affected nor increase the potential building damage impacts above the aesthetic levels presented by the application. This appendix relates to Conditions 122(j), 133(f), 126, 155 and 158.

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

88


LOCATION

TRIGGER LEVELS [+/-]

ID NO4

ADDRESS

1

12 QUEEN STREET

REFER TO NOTE 6 ON DRAWING CRL-PAT-STR-000-DRG-0400 [5.0]

2

21 QUEEN STREET

DISPLACEMENT MONITORING TRIGGER LEVELS SPECIFIC TO ZURICH BUILDING ARE OUTLINED ON DRAWING CRL-SYW-STR-000-DRG-0054

MOVEMENT

ALERT

HORIZONTAL AT FACE OF BUILDING3 3

23-29 ALBERT STREET

VERTICAL AT FACE OF BUILDING

3

DIFFERENTIAL VERTICAL SLOPE ACROSS BUILDING2 (I.E. ACROSS ZONE 2) HORIZONTAL AT FACE OF BUILDING

4

12-26 SWANSON STREET

VERTICAL AT FACE OF BUILDING

3

DIFFERENTIAL VERTICAL SLOPE ACROSS BUILDING2 (I.E. ACROSS ZONE 2) HORIZONTAL AT FACE OF BUILDING

5

35 ALBERT STREET

3

37 ALBERT STREET

7mm

9mm

14mm

18mm

1/950

1/750

14mm

18mm

20mm

25mm

1/950

1/750

3

VERTICAL AT FACE OF BUILDING3 DIFFERENTIAL VERTICAL SLOPE ACROSS BUILDING2 (I.E. ACROSS ZONE 2) HORIZONTAL AT FACE OF BUILDING3

6

ALARM

VERTICAL AT FACE OF BUILDING3 DIFFERENTIAL VERTICAL SLOPE ACROSS BUILDING2 (I.E. ACROSS ZONE 2)

BUILDINGS DEMOLISHED. LIMITS FOR NEW BUILDING TO BE CONFIRMED.

HORIZONTAL AT FACE OF BUILDING3 7

8

39 ALBERT STREET

46-50 ALBERT STREET

1

ZONE 2 : GROUND SURFACE MOVEMENT ACROSS BUILDINGS (INCLUDING ROADS INTERSECTING ALBERT STREET)

9

10

11

12

13

14

52-56 ALBERT STREET

41 ALBERT STREET

51-53 ALBERT STREET

55 ALBERT STREET

57 ALBERT STREET

61 ALBERT STREET

VERTICAL AT FACE OF BUILDING3 DIFFERENTIAL VERTICAL SLOPE ACROSS BUILDING2 (I.E. ACROSS ZONE 2) HORIZONTAL AT FACE OF BUILDING3

7mm

9mm

VERTICAL AT FACE OF BUILDING3

17mm

21mm

DIFFERENTIAL VERTICAL SLOPE ACROSS BUILDING2 (I.E. ACROSS ZONE 2)

1/900

1/700

HORIZONTAL AT FACE OF BUILDING3

7mm

9mm

VERTICAL AT FACE OF BUILDING3

17mm

21mm

DIFFERENTIAL VERTICAL SLOPE ACROSS BUILDING2 (I.E. ACROSS ZONE 2)

1/900

1/700

HORIZONTAL AT FACE OF BUILDING3

8mm

10mm

VERTICAL AT FACE OF BUILDING3

20mm

25mm

DIFFERENTIAL VERTICAL SLOPE ACROSS BUILDING2 (I.E. ACROSS ZONE 2)

1/800

1/650

HORIZONTAL AT FACE OF BUILDING3

8mm

10mm

VERTICAL AT FACE OF BUILDING3

20mm

25mm

DIFFERENTIAL VERTICAL SLOPE ACROSS BUILDING2 (I.E. ACROSS ZONE 2)

1/800

1/650

HORIZONTAL AT FACE OF BUILDING3

8mm

10mm

VERTICAL AT FACE OF BUILDING3

20mm

25mm

DIFFERENTIAL VERTICAL SLOPE ACROSS BUILDING2 (I.E. ACROSS ZONE 2)

1/800

1/650

HORIZONTAL AT FACE OF BUILDING3

8mm

10mm

VERTICAL AT FACE OF BUILDING3

20mm

25mm

DIFFERENTIAL VERTICAL SLOPE ACROSS BUILDING2 (I.E. ACROSS ZONE 2)

1/800

1/650

HORIZONTAL AT FACE OF BUILDING3

8mm

10mm

VERTICAL AT FACE OF BUILDING3

20mm

25mm

1/750

1/600

DIFFERENTIAL VERTICAL SLOPE ACROSS BUILDING2 (I.E. ACROSS ZONE 2) HORIZONTAL AT FACE OF BUILDING

15

58 ALBERT STREET

VERTICAL AT FACE OF BUILDING3 DIFFERENTIAL VERTICAL SLOPE ACROSS BUILDING2 (I.E. ACROSS ZONE 2) HORIZONTAL AT FACE OF BUILDING

16

38 WYNDHAM STREET

3

3

8mm

9mm

17mm

21mm

1/650

1/500

5mm

7mm

VERTICAL AT FACE OF BUILDING3

12mm

15mm

DIFFERENTIAL VERTICAL SLOPE ACROSS BUILDING2 (I.E.

1/1050

1/850

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

89


ACROSS ZONE 2)

17

63 ALBERT STREET

HORIZONTAL AT FACE OF BUILDING3

6mm

8mm

VERTICAL AT FACE OF BUILDING3

14mm

18mm

1/950

1/750

DIFFERENTIAL VERTICAL SLOPE ACROSS BUILDING2 (I.E. ACROSS ZONE 2) HORIZONTAL AT FACE OF BUILDING

ALL OTHER PROPERTIES

EXISTING BUILDING EXTERNAL COLUMN/FACADE

ALL PROPERTIES

BUILDING MOVEMENT

148 QUAY STREET 152 QUAY STREET 2-8 CUSTOMS STREET EAST 10-12 CUSTOMS STREET EAST 14-18 CUSTOMS STREET EAST 20 CUSTOMS STREET EAST 2 QUEEN STREET

3

8mm

10mm

VERTICAL AT FACE OF BUILDING3

8mm

10mm

DIFFERENTIAL VERTICAL SLOPE ACROSS BUILDING2 (I.E. ACROSS ZONE 2)

1/900

1/700

DIFFERENTIAL HORIZONTAL IN PLANE WITH THE COLUMN/FACADE

8mm

10mm

HORIZONTAL AT FACE OF BUILDING

3mm

4mm

VERTICAL AT FACE OF BUILDING

5mm

8mm

DIFFERENTIAL HORIZONTAL IN PLANE WITH THE COLUMN/FACADE

N/A

N/A

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

90


Deformation Limits – Services and Infrastructure Trigger Levels Table Note: Applies to ground surface movement within Albert Street and Lower Albert Street and roads intersecting Albert Street (includes footpaths, verge and road), Customs Street West, Fanshawe Street, lower Queen Street, Tyler Street, Galway Street. SERVICES

MOVEMENT

TRIGGER LEVELS [+/-] ALERT5 ALARM STOP

ALL SERVICES WITH A DIAMETER GREATER THAN 200mm1

DIFFERENTIAL VERTICAL GROUND MOVEMENT WITHIN ALBERT STREET4

1/200

1/160

1/140

ALL RIGID SERVICES WITH A DIAMETER LESS THAN 200mm

DIFFERENTIAL VERTICAL GROUND MOVEMENT WITHIN ALBERT STREET4

1/200

1/160

1/140

NON-RIGID2 SERVICES WITH A DIAMETER LESS THAN 200mm1

DIFFERENTIAL VERTICAL GROUND MOVEMENT WITHIN ALBERT STREET4

1/75

1/60

1/50

IDENTIFIED CRITICAL INFRASTRUCTUR E3

DIFFERENTIAL VERTICAL GROUND MOVEMENT WITHIN ALBERT STREET4

1/200

1/160

1/140

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

91


Appendix 5 to Resource Consent Conditions Plan: CRL-BTM-RME-000-DRG-0004, revision 1, titled: “Location Plan Showing Sites Adjacent to Construction Sites”, dated 18.08.2015

City Rail Link Application Nos.: R/REG/2014/5430, R/LUC/2014/5428, R/REG/2014/5432, R/REG/2014/5435, R/REG/2014/5436, R/REG/2014/5437

92


LEGEND

KEY PLAN DESIGNATION ALIGNMENT PROPOSED WORKS BRITOMART TRANSPORT CENTRE IDENTIFIED SITES

GORE ST

VICTORIA ST EAST

GALWAY ST

COMMERCE ST

EXTENT OF WORKS CPO AND LOWER QUEEN ST RUNNING TUNNELS

MILLS LANE

QES AND PRECINCT TUNNELS

ALBERT ST TUNNEL

ELLIOT ST

TEMPORARY WORK SUPPORT AREA

ALBERT ST

MAYORAL DRIVE

SW SW

SW

X

X

SW

X

X

SW

X

SW

X

ALBERT ST

LOWER ALBERT ST

MILLS LANE

DURHAM LANE

DURHAM STREET WEST

MILLS LANE

WYNDHAM STREET

CUSTOMS ST WEST

SWANSON STREET

QUEEN ST

QUEEN ST

pw:\\designshare.au.aurecon.info:PW_PROD_AU\Documents\Projects\23xxxx\239933 - City Rail Link (CDE)\01-WIP\Drawings\CRL-BTM-RME-000-DRG-0004.dwg

QUEEN ST

WELLESLEY ST WEST

FORT ST

GALWAY ST

QUAY ST

TYLER ST

SHORTLAND ST

FORT LANE

VICTORIA ST WEST

CUSTOMS ST EAST

BRITOMART

DARBY ST

TYLER ST

COMMERCE ST

ALBERT ST

FEDERAL ST

FEDERAL ST

NS

FA

VICTORIA ST WEST

EXTENT OF TUNNEL PHYSICAL WORKS. REFER TO ALIGNMENT AND CIVIL DRAWINGS FOR EXACT LOCATION OF WORK EXTENTS.

WE

HA ST

Auckland

WELLESLEY ST WEST

KINGSTON STREET

WYNDHAM STREET

SWANSON STREET

TEMPORARY WORK SUPPORT AREA

WOLFE ST

CUSTOMS ST WEST

BLUESTONE WALL

18/08/2015 11:46:02 a.m.

HOBSON ST

12.5

0

25

50m

CLIENT

SCALE 1:1250

REV DATE REVISION DETAILS 1.0 18.08.15 ISSUED FOR CONSENT

APPROVED T.IRELAND

SCALE

SIZE

1:1250

A1

DRAWN

PRELIMINARY NOT FOR CONSTRUCTION

AUCKLAND CITY RAIL LINK

PROJECT

LOCATION PLAN SHOWING SITES ADJACENT TO CONSTRUCTION SITES

APPROVED

B.HINGSTON

.

DESIGNED

DATE

TITLE

M.TAYLOR CHECKED

T.IRELAND

D.MCGAHAN 0

20mm ORIGINAL SIZE

40

60

80

100

200

300

400

500

DOCUMENT 600

PROJECT

ZONE

DISCIPLINE

ELEMENT

TYPE

SHEET

REVISION

CRL

BTM

RME

000

DRG

0004

1.0

700

800


Turn static files into dynamic content formats.

Create a flipbook