Skip to main content

C1 industrial and trade activities emp

Page 1

Auckland City Rail Link In association with:

ENABLING WORKS CONTRACT 1 INDUSTRIAL AND TRADE ACTIVITIES ENVIRONMENTAL MANAGEMENT PLAN

Document ref: CRL-BTM-ENV-DOW-PLN-000289

Revision: 6 FINAL June 2016

COMMERCIAL IN CONFIDENCE Tonkin & Taylor Ltd | 105 Carlton Gore Rd, Newmarket, Auckland 1023, New Zealand


Version history Rev.

Date

Version details

Prepared by

Reviewed by

1

December 2015

Draft for Auckland Transport Review

R Van de Munckhof

R Purdy, P Roan

2

January 2016

Draft for CLG Review

R Van de Munckhof

P Roan, R Jenkins

3

April 2016

Draft incorporating Auckland Council comments

R Van de Munckhof

R Purdy

4

May 2016

Draft incorporating CLG Review

R Van de Munckhof

J Urquhart, P Roan, R Jenkins

5

May 2016

Draft for Auckland Transport Review

R Van de Munckhof

J Urquhart, P Roan

6

June 2016

Final

R Van de Munckhof

J Urquhart, P Roan, R Jenkins

Distribution Date

Version

Issued to

Quantity & type

Approved for the DSBJV by

23 December 2015

Draft

Auckland Transport

1x electronic

D Burtenshaw

22 January 2016

Draft

Community Liaison Group

1x electronic

D Burtenshaw

12 May 2016

Draft

Community Liaison Group

1x electronic

D Burtenshaw

21 May 2016

Draft

Auckland Transport

1x electronic

D Burtenshaw

2 June 2016

Final

Auckland Transport

1x Electronic 1 x Hard copy

D Burtenshaw

This document remains the property of DSBJV. Its contents are confidential and shall not be reproduced, destroyed or given away without express, written permission of DSBJV. The electronic version of this document in FULCRUM on designated serves(s) is the Master Copy and is a controlled document. Unless specifically noted, thereon, other copies of this document are uncontrolled. \\albtpfile.ttgroup.local\data\rep\auckland\live\tt\projects\30850\30850.0500 planning\30850.0514 (ita)\workingmaterial\dwp\crl-btmenv-dow-pln-000289 ita final 30 05 16.docx

Industrial and Trade activities Environmental Management Plan

June 2016


Table of contents 1

Introduction 1.1 Purpose of the Industrial and Trade Activities Environmental Management Plan 1.2 Relevant Conditions 1.3 ITA EMP author 1.4 Sustainability 1.5 ITA EMP review and updates

2

Project Description 2.1 Overview 2.2 Construction zones 2.3 Construction Support Areas 2.4 Bentonite and jet grouting plants 2.4.1 Bentonite treatment plant 2.4.2 Jet grouting plant operation 2.5 Stormwater and groundwater treatment

5 5 5 7 8 9 10 11

3

Industrial and Trade Activities 3.1 Environmental work instructions and plans 3.2 Site drainage

12 13 14

4

Management Procedures and Mitigation Measures 4.1 Bentonite plant 4.2 Jet grout plant and operation 4.3 Environmentally hazardous substance management 4.4 Waste management 4.5 Vehicle refuelling 4.6 Wash-down Spill Response

15 15 15 15 16 16 16 18

6

Discharge Monitoring and Reporting 6.1 Monitoring 6.2 Reporting

19 19 19

7

Environmental Compliance Management and Review 7.1 Site inspections 7.2 Environmental audits 7.3 Non-conformance, corrective and preventative action

20 20 20 20

8

Training 8.1 Employees and subcontractors 8.1.1 HSNO Approved Handler training 8.2 Visitors 8.3 Training records

21 21 21 21 21

9

ITA EMP Review 9.1 ITA EMP Review 9.2 ITA EMP Updates

22 22 22

5

Appendix A :

ISCA Requirements

Appendix B:

Work Instructions

Appendix C:

Spill Response Plan

Appendix D:

Site Drainage Plan

Industrial and Trade activities Environmental Management Plan

1 1 2 4 4 4

June 2016


Appendix E :

CLG Comments

Industrial and Trade activities Environmental Management Plan

June 2016


Glossary of abbreviations Acronym

Definition

AC

Auckland Council

ACZ

Active Construction Zone

AT

Auckland Transport

BTC

Britomart Transport Centre

CEMP

Construction Environmental Management Plan

CLG

Community Liaison Group

CPO

Former Chief Post Office building

CRL

City Rail Link

CSA

Construction Support Area

CTMP

Chemical Treatment Management Plan

DWP

Delivery Work Plan

ESCP

Erosion and Sediment Control Plan

ESRP

Emergency Spill Response Plan

HSNO

Hazardous Substances and New Organisms

HSNO Act

Hazardous Substances and New Organisms Act 1996

IS

Infrastructure Sustainability

ISCA

Infrastructure Sustainability Council of Australia

ITA EMP

Industrial and Trade Activities Environmental Management Plan

SDS

Safety Data Sheets

STP

Slurry Treatment Plant

WARRP

Waste Avoidance and Resource Recovery Plan

WI

Work Instruction

Industrial and Trade activities Environmental Management Plan

June 2016


1

1

Introduction

The City Rail Link (CRL) project comprises the construction, operation and maintenance of a 3.4 km underground passenger railway, running between Britomart Station and the North Auckland Rail Line in the vicinity of Mt Eden station. The works relating to this Industrial and Trade Activities Environmental Management Plan (ITA EMP) constitute part of the enabling works for the CRL. The works (the Project) involve the construction of an extension to the existing passenger rail network from the current termination point within the Britomart Transport Centre (BTC), westwards underneath the former Chief Post Office building (CPO) and Lower Queen Street. The Project footprint is shown by the blue shaded area in Figure 1.1 below.

LEGEND CRL alignment BTC designation CRL designation C1 worksite

Figure 1.1: Project Footprint

1.1

Purpose of the Industrial and Trade Activities Environmental Management Plan

This ITA EMP has been prepared to manage adverse effects relating to industrial and trade activities required during construction of the Project, including a bentonite treatment plant, jet grout plant and the storage and handling of hazardous substances. Specifically, the purpose of the plan is to identify those activities to be undertaken at the Project site that may result in contamination of land and/or stormwater, and to document the procedures to be implemented to appropriately manage these risks. The ITA EMP is required under Condition 96 of Discharge Permit R/REG/2014/5436 for the CRL Britomart to Wyndham Street enabling works. The plan is an updated version of the Draft ITA EMP – Britomart to Wyndham, dated December 2014, prepared by Golder Associates (NZ) and submitted to Auckland Council (AC) as part of the regional resource consent applications for the Project. The ITA EMP outlines the following: Identification of industrial and trade activities to be undertaken during the Project that may result in contamination of land and/or water; Identification of potential contaminants associated with these activities; The methods to be used to prevent identified contaminants from contacting with stormwater runoff and methods to manage environmental risks from on-site activities; An appropriate monitoring and auditing programme to ensure site performance is undertaken in accordance with this ITA EMP; and Industrial and Trade activities Environmental Management Plan

June 2016


2 Staff training. This ITA EMP has been prepared by Tonkin & Taylor Ltd (T+T) for the Downer Soletanche Bachy Joint Venture (the Contractor – DSBJV) and forms part of the Construction Environmental Management Plan (CEMP) for the Project.

1.2

Relevant Conditions

Table 1.1 below identifies the relevant conditions of Discharge Permit R/REG/2014/5436 and where these are addressed in the ITA EMP. Table 1.1: Condition No.

Industrial and Trade Activity conditions and location in the document Condition

Relevant section of the Plan

Site Management 96

At least 20 working days prior to the commencement of construction, a final Industrial and Trade Activities Environmental Management Plan (“EMP”) shall be submitted to the Council (Team Leader Central Monitoring) for certification. The Consent Holder shall request the Council’s (Team Leader Central Monitoring) determination as to whether the EMP can be certified, in writing, within 10 working days following receipt of the EMP. The EMP shall be prepared by a senior qualified person and shall include, but not be limited to, the following:

This document

96 (a)

Identification of the specific activities conducted on the site;

Sections 2 and 3

96 (b)

Identification of potential contaminants associated with these activities;

Section 3

96 (c)

Methods used to prevent identified contaminants contacting stormwater runoff as far as practicable and methods to manage environmental risks from site activities;

Sections 4.1 4.6.

96 (d)

An Emergency Spill Response Plan (which includes the provision that all spills over 20 litres, or any spill of Environmentally Hazardous Substances that has entered the stormwater system, a water-body or has contacted unsealed ground, shall be reported immediately to the Auckland Council’s 24 Hour Pollution Hotline (09-377-3107);

Section 5 and Appendix C.

96 (e)

An up-to-date and accurate site drainage plan showing the location of all site catchpits and the final discharge point(s) of the site stormwater system;

Section 3.2 and Appendix D

96 (f)

An appropriate auditing programme to ensure site performance with all components of the sites EMP;

Section 7.2

96 (g)

Methods for providing and recording staff training; and

Section 8.3

96 (h)

A monitoring programme as outlined in Condition 101.

Section 6.1

97

The Consent Holder shall ensure that the site is operated and managed in accordance with the certified EMP to ensure the risks from the site are managed appropriately.

This document

98

The Consent Holder shall ensure that a copy of the certified EMP is kept on site and accessible at all times.

This document

Industrial and Trade activities Environmental Management Plan

Section 1.3

June 2016


3 Condition No.

Condition

Relevant section of the Plan

Structural Controls 99

The Consent Holder shall ensure that the following structural controls are constructed for the following catchment areas and design requirements and they are completed prior to discharges commencing from the site.

Section 2.5 and Project Erosion and Sediment Control Plan (ESCP)1

100

In the event that any minor modifications to the structural controls system are required, the following information shall be provided to Council: a. Plans and drawings outlining the details of the modifications; and b. Supporting information that details how the proposal does not affect the capacity or performance of stormwater management system. All information shall be submitted to, and the proposed modifications certified by the Council (Team Leader Central Monitoring), prior to implementation.

ESCP Section 4.13 and Appendix B (CTMP)

Discharge Monitoring 101

Within 30 days of the installation of the water treatment system, and prior to operation, a discharge monitoring programme, to assess the ongoing adequacy of all management practices, shall be developed and submitted to the Council (Team Leader Central Monitoring) for certification. The monitoring programme shall include, but not be limited to: a. sampling location for final discharge from the site(s); b. sampling locations on site (i.e. swale inlets, outlets etc); c. methods and procedures for discharge sampling on a quarterly basis; d. monitoring parameters for analysis, which shall include: Daily Turbidity (NTU) pH Weekly Total Suspended Solids mg/L Copper (total) mg/L Zinc (total) mg/L Lead (total) mg/L Total Petroleum Hydrocarbons mg/L e. identified trigger levels for each of the above parameters. These trigger levels shall be developed with reference to the ANZECC Guidelines for water quality where applicable; and f. the methods and procedures for investigating and reporting stormwater discharge monitoring results to the Council (Team Leader Central Monitoring).

Section 6.1

102

The discharge monitoring programme shall be implemented upon completion of works required by Condition 99.

Section 6.1

Settlement tanks are located in Construction Support Area A (adjacent to Galway Street) as opposed to Construction Support Area B / Construction Support Area 2 (Lower Queen Street) in order to create a more efficient CSA layout 11

Industrial and Trade activities Environmental Management Plan

June 2016


4 Condition

Relevant section of the Plan

103

Within five working days of sample results showing contaminants exceeding the agreed trigger levels (Condition 101(e)): a. an investigation shall be undertaken to determine why exceedances were detected and to identify any additional source controls or treatment required; and b. the results of the investigation shall be reported to the Council (Team Leader Central Monitoring).

Section 6.2

104

Within eight weeks following the start of the monitoring required by Conditions 101 and 102, a monitoring report shall be submitted to the Council (Team Leader Central Monitoring). The monitoring report shall include, but not be limited to, the following: a. a summary of the monitoring results to date; b. an interpretation of those results and suggestions for improvement to the site operations; c. a programme for ongoing monitoring including the reporting of results; and d. a programme for the ongoing maintenance of the discharge water management and treatment system.

Section 6.2

Condition No. Reporting

1.3

ITA EMP author

This ITA EMP has been prepared by Rob Van de Munckhof. Rob holds a chemical engineering degree and has over 14 years’ experience in environmental management and has experience in Industrial and Trade Activity assessment and management. He has undertaken assessments of surface water discharges from a range of industrial sites and is experienced in undertaking risk assessments to identify priority contaminants. He is experienced in the development of environmental management plans and surface water monitoring plans.

1.4

Sustainability

AT is seeking an Infrastructure Sustainability Council of Australia (ISCA) Infrastructure Sustainability (IS) Rating. Further details can be found in the Project CEMP and Sustainability Rating Management Plan. Project sustainability requirements that relate directly to this ITA EMP are included in Appendix A. These requirements are imbedded within the plans to ensure that sustainability is a key focus and ‘the way we do things’. In some cases the IS requirements and sustainability goals enhance the designation requirements.

1.5

ITA EMP review and updates

This ITA EMP is a living document that will be reviewed and updated if needed during the course of the Project to reflect any material changes associated with construction techniques or the natural environment. Any proposed changes to the ITA EMP must be certified by AC prior to any on-site activity reliant upon the change commencing. A formal review process is described in Section 9 of this ITA EMP.

Industrial and Trade activities Environmental Management Plan

June 2016


5

2

Project Description

2.1

Overview

The Project involves the construction of an extension to the existing passenger rail network from the current termination point within the BTC, westwards underneath the CPO and Lower Queen Street. Separate works are being undertaken to continue the CRL tunnels from this point under the Downtown Shopping Centre site (which is to be redeveloped by Precinct Properties), and then up Albert Street. Significant works beneath the CPO will be undertaken, with the construction of two new rail tunnels extending westwards beneath the basement floor level. In Lower Queen Street, sheet piling will be extended across the road corridor, excavation undertaken to form the rail tunnels followed by reinstatement of the road corridor following the completion of works. During construction, existing ticketing and retail functions and pedestrian access to the station will be accommodated in Station Plaza, at the rear of the CPO building. Surface works will also be required in QEII Square associated with the Downtown Shopping Centre redevelopment, including construction of the CRL rail tunnels beneath this site (Precinct Properties scope of work). A detailed description of the construction works is provided in the CEMP.

2.2

Construction zones

The Project will be divided into four discrete active construction zones (ACZ) as shown in Figure 2.1.

Figure 2.1: Active Construction Zones

The referencing of Project ACZs adopted in this ITA EMP reflects that of the BTC designation in order to ensure consistency across all Project Delivery Work Plans and Environmental Management Plans. It is

Industrial and Trade activities Environmental Management Plan

June 2016


6 noted that under the resource consents, the Project area is separated into two larger ACZ’s – ACZ A (CPO) and ACZ B (Lower Queen Street) – refer to Figure 2.3. A summary of the key construction activities that will be undertaken in each ACZ is outlined in Table 2.1. Table 2.1:

Summary of key construction activities within each ACZ2

Active Construction Zone

Key construction activities

A

Britomart Station modifications Modification of existing platforms and track lines Installation of temporary access stairs, station entry and egress

B

Accommodation within Station Plaza Construction of temporary accommodation buildings and facilities and relocation of ticketing, staff facilities, public amenities, retail/kiosk areas from the CPO building Installation of services.

C

CPO Building Works Removal of the CPO fixtures and fittings Saw cutting and demolition of the CPO ground floor and processing concrete for use as backfill later Installation of guide walls, diaphragm walls and underpinning structures to provide support for the CPO Soil excavation Construction of the base slab, walls and roof for the new rail tunnels Backfill excavation Reinstatement and fit out of CPO building

D

Lower Queen Street Bentonite plant located adjacent to the south west corner of the CPO building on Lower Queen Street Carry out piling and underpinning works Soil excavation Construct base slab, walls and roofs for new rail tunnels Backfill excavation Reinstatement of Lower Queen Street

The Lower Queen Street excavation will be covered with a partial roof structure in order to minimise the potential for water to enter the excavation and the discharge of dust from the site. Works within the CPO will be contained within the building. A detailed description of the construction works is provided in the CEMP.

2

Note these activities are not in order of programme

Industrial and Trade activities Environmental Management Plan

June 2016


7

2.3

Construction Support Areas

Three construction support areas (CSA) are proposed to support the ACZs (refer to Table 2.2 and Figure 2.2 of this ITA EMP. Table 2.2:

Construction Support Areas

Construction Support Area

Location

Construction zone supported

Area

Key Plant/Activities

A

Galway Street

Supports temporary accommodation works in Station Square

400 m2

Material storage Crane location and access to CSA A Stormwater and groundwater treatment tanks

B

Lower Queen Street

Supports CPO and Lower Queen Street construction

3,500 m2

Bentonite treatment plant Jet grout pump and mixing plant Material storage

C

Tyler Street

Provides construction access to the CPO

400 m2

Temporary site office during Stage 1 of the Project Material storage Crane location and access to CSA C Main vehicle entrance to the CPO building

Figure 2.2: Construction Support Areas

Industrial and Trade activities Environmental Management Plan

June 2016


8 Note: Blue hatched areas on Figure 2.2 show the areas of the Lower Queen Street that will be maintained as traffic lanes in order to provide vehicle access from Lower Queen Street to Tyler Street and Galway Street into Lower Queen Street The referencing of Project CSAs adopted in this ITA EMP reflects that of the BTC designation to ensure consistency across all Project Delivery Work Plans and Environmental Management Plans. It is noted that under the resource consents, the Project area is separated into two CSAs – CSA 1 and CSA 2 – refer to Figure 2.3.

Figure 2.3: Resource Consent ACZ and CSA referencing

2.4

Bentonite and jet grouting plants

The diaphragm wall and jet grout columns will require the establishment of bentonite and jet grouting plants on Lower Queen Street adjacent to the CPO building, the location of which are shown on Figure 2.4. The operation of the plants is outlined in Sections 2.4.1 and 2.4.2 below.

Bentonite Treatment Plant

Jet Grout Plant Figure 2.4: Location of bentonite and jet grout plants Industrial and Trade activities Environmental Management Plan

June 2016


9

2.4.1

Bentonite treatment plant

A bentonite plant will be located adjacent to the south west corner of the CPO building on Lower Queen Street. The purpose of the plant is to mix and recycle bentonite slurry associated with the diaphragm wall construction. The plant will cover an area of approximately 350 m2 and comprise the following elements: Four to six 80 m3 silos, approximately 15 m in height, required for the storage of bentonite slurry and waste; Slurry Treatment Plant (STP) / De-sanding Unit - with a capacity of approximately 450 m 3; Bentonite mixer; Bentonite storage bags; Generator; and Excavator. The bentonite plant operation will be as outlined in Table 2.3 and as shown on Figure 2.5. Table 2.3:

Bentonite Plant Operation

Bentonite Storage

Storage of bentonite powder and slurry within silos

Bentonite Mixing and Recycling

Mixing of bentonite with water and additives (sodium bicarbonate and bentocryl) to make a bentonite slurry, which will be temporarily stored within the silos before being used in the piling operations. The bentonite mixer will be covered to control bentonite powder dust emissions. Transfer of the bentonite slurry to the storage silo, which is connected to the circuit of the STP / de-sanding unit and down to the diaphragm wall operations via pipes and hoses. Slurry will be pumped out from the trench and travel back to the de-sanding unit / STP, where it will be treated to remove solids and recover the slurry for re-use.

Spoil Disposal

Dry material recovered from the de-sanding unit will be removed off-site. Liquid spent slurry following de-sanding will be discharged into a temporary spoil pit (approximately 24 m3) to be located on site. The spoil will be excavated and transported via trucks (approximately 3-5 per day) to an approved disposal facility.

Management of Discharges

The entire bentonite plant will be bunded to contain any spilt material or bentonite slurry in the event of a pipe or pump failure during transfer of the slurry. Any surface water collected in the bunded area will be pumped to the sediment control system on-site for removal of sediment prior to discharge. There will be no gravity discharge of any water from the bunded area to the stormwater system. Any spilt material pumped to the sediment control system will be treated as per other sediment laden water on-site with discharge only occurring once the minimum water quality standards are met.

Industrial and Trade activities Environmental Management Plan

June 2016


10

Figure 2.5: Bentonite Slurry Operation

2.4.2

Jet grouting plant operation

The main function of the jet grout plant is to mix the cement grout required for the jet grout columns and transfer it to the jet grouting rig at high pressure. The plant will be located adjacent to the north western corner of the CPO building on Lower Queen Street (refer Figure 2.3). The plant will comprise the following elements: Excavator; Grout Mixer; High Pressure Pump; Generator; Silo for cement powder storage; and Grout Storage Tank (approximately 10 m3). The jet grout mixing plant will involve mixing water and cement and additional additives to create a slurry mix as outlined in Table 2.4. Table 2.4:

Jet Grouting Plant Operation

Material Storage

Cement powder will be delivered to the plant by trucks. It will be pumped to the storage silo through hoses. Dust filters on the silos will be used to control dust emissions.

Cement Grout Mixing

Cement powder will travel to the mixer via a closed screw conveyor. The scale will have a protective cover to control dust. Cement powder will be mixed intermittently with water in the required proportions and the grout will then be stored in a tank.

Cement grout injection:

Grout will travel via hoses, filters and pumps to the high pressure pump, then to the jet grouting rig and through the drill string, which will inject this grout at high pressure, inside the soils, to form jet grouting columns.

Industrial and Trade activities Environmental Management Plan

June 2016


11 Spoil Disposal

The resulting sludge (made of grout, water and soil) will be pumped from the jet grout column location to the spoil pit at the plant. It will be disposed of in a similar manner to the slurry spoil.

Management of Discharges

The jet grout plant will be bunded. Any surface water collected in the bunded area will be pumped to the sediment control system on-site for removal of sediment prior to discharge. There will be no gravity discharge of any water from the bunded area to the stormwater system. Any spilt material pumped to the sediment control system will be treated as per other sediment laden water on-site with discharge only occurring once the minimum water quality standards are met.

2.5

Stormwater and groundwater treatment

Stormwater and groundwater that settles in the excavations in Lower Queen Street and the CPO will be pumped into a settlement tank where sediment will settle out. Assisted sediment settlement using chemical or non-chemical flocculants (the latter being preferred if effective) will be undertaken as required to ensure water discharged from the system will not result in adverse effects on the receiving environment. The treatment tanks will be located adjacent to the south east corner of the CPO adjacent to the glasshouse. The treatment plant is outlined in detail in Section 2 of the Chemical Treatment Management Plan (CTMP) for the Project (Appendix B of the Project ESCP). The treatment plant comprises a total storage capacity of 35,000L, which exceeds the volume requirement of two 12,000L tanks specified in Condition 99 of Discharge Permit R/REG/2014/5436.

Industrial and Trade activities Environmental Management Plan

June 2016


12

3

Industrial and Trade Activities

The main industrial and trade related activities to be undertaken in each ACZ are outlined in Table 3.1. This table also outlines the potential contaminants associated with the activities and the relevant procedural and physical controls to be implemented during the works to minimise any adverse environmental effects. Copies of all work instructions referred to in Table 3.1 are provided at Appendix B to this ITA EMP. Table 3.1: Summary of activities, potential contaminants and controls Active Zone

Activity

ACZ-D

Bentonite treatment plant

Contaminants

Bentonite storage

Procedural controls (DSBJV work instructions and plans)

Physical controls

Sediment

Bentonite Plant Operations and Spill Response Plan. WARRP

Bentonite plant shall be bunded with runoff directed to the on-site sediment control system and settlement tanks.

Mixing unit Slurry storage De-sanding unit Spent bentonite tank Dry debris

ACZ-D

Jet Grout Plant

Sediment, pH3

Jet Grout Plant Operations and Spill Response Plan. WARRP

Jet grout plant area shall be bunded and drain to the on-site sediment control system and settlement tanks.

All zones

Chemical store

Hydrocarbons, oils and greases, fuels

WI 101 WI-103 WI-602 WI 603

All chemicals shall be stored within a bunded enclosure.

ACZ-D

Concrete

Sediment, pH3

WI-602 ESRP WARRP

No washing out of concrete trucks shall be undertaken on-site. All runoff from the site shall be directed to sediment control system and settlement tanks with pH monitoring undertaken.

Hydrocarbons, fuels

WI-101

Refuelling shall be undertaken in

All zones

Vehicle refuelling

3

Cement and other additives that will be used in the Jet Grout Plan and Concreting activities during the Projects can increase or decrease pH outside normal ranges

Industrial and Trade activities Environmental Management Plan

June 2016


13 Active Zone

Activity

Contaminants

Procedural controls (DSBJV work instructions and plans) WI-102 ESRP

General site activities

3.1

Physical controls

Equipment washdown

Sediment, hydrocarbons, oil & grease, heavy metals

Waste handling and storage

Sediment, hydrocarbons, oil & grease, heavy metals

-

accordance with Work Instruction 102 Washing of equipment shall only be undertaken within the excavation area. No vehicle washing shall otherwise be undertaken on-site.

WARRP ESRP

All waste bins shall be stored in a covered area on-site, or have lids.

Environmental work instructions and plans

The DSBJV will operate under a suite of Downer NZ environmental work instructions and plans that have been prepared for a range of activities to be undertaken on-site during the Project. Work instructions and plans relevant to the activities identified in Table 3.1 above are outlined in Table 3.2 below and provided in Appendix B of this ITA EMP. Table 3.2: Reference

Relevant work instructions and plans Title

Work Instructions WI-101

Use and Disposal of Oils and Lubricants

WI-102

Refuelling of Equipment, Machinery and Static Tanks

WI-103

Spill Procedure: Fossil and Synthetic Fuels and Oils

WI-602

Road Transport and Materials Handling

WI-603

Storage and Handling of Dangerous Goods

Environmental Plan WARRP

Waste Avoidance and Resource Recovery Plan (WARRP)

ESRP

Emergency Spill Response Plan (refer to Section 5 and Appendix C of this ITA EMP)

TBC

Bentonite Plant Operations and Spill Response Plan (to be developed)

TBC

Jet Grout Plant Operations and Spill Response Plan (to be developed)

The Project WARRP is relevant to the management of material that needs to be disposed of from the Project area. Refer to Section 4.4 of this ITA EMP for further detail on the WARRP.

Industrial and Trade activities Environmental Management Plan

June 2016


14

3.2

Site drainage

The existing drainage system consists of the AC stormwater network currently in place within the Project area. This drainage system collects runoff from the road pavements and directs it to the stormwater pipelines, which then discharge directly into the Waitemata Harbour through the existing discharge structure located at the Promenade (immediately adjoining the northern side of Quay Street). Refer to Section 4.6.3 of the ‘Auckland City Rail Link Britomart to Wyndham Water Quality Assessment’ dated December and prepared by Golder Associates for information on the receiving environment water quality. Parts of the existing drainage system will need to be removed or closed off during the Project works. A drainage plan showing the existing stormwater drainage system and those sections to be removed is shown attached in Appendix D. The release of contaminants to the stormwater network will be managed using the controls described in the Project ESCP and this ITA EMP. Site layout plans have been prepared (refer to Appendix D of this ITA EMP) to show the location of the bentonite plant, the jet grout plant, truck routes and any chemical storage areas. Final as-built drainage plans for the Project area will be prepared following the completion of the works. These plans will show the locations of all stormwater catch pits and discharge locations within the Project area.

Industrial and Trade activities Environmental Management Plan

June 2016


15

4

Management Procedures and Mitigation Measures

4.1

Bentonite plant

The main environmental risks associated with the bentonite plant are the discharge of chemicals from the operation of the plant and/or the discharge of sediment laden water to stormwater drains within the Project area, which in turn discharge into the Waitemata Harbour. To avoid or minimise any discharges from the bentonite plant to the surrounding environment, the plant will be designed and operated as follows: The entire bentonite plant shall be bunded to contain any spilt material or bentonite slurry in the event of a pipe or pump failure during transfer of the slurry. The outlet of the existing stormwater catchpit in Lower Queen Street that will be located within the bentonite plant operation area (refer to the Stormwater Drainage Plan in Appendix D of this ITA EMP) will be sealed off during the works, and a submersible pump installed to pump any surface water that collects in the bund to the bentonite plant tanks for re-use; or to the sediment treatment plant. Sodium bicarbonate and bentocyrl will be added to the bentonite slurry. Neither chemicals are classified under HSNO as hazardous, and will be stored within the bunded bentonite plant area. No other environmentally hazardous substances will be required as part of the bentonite plant operation. In the event of a spill outside of the bunded area, the standard spill control procedures will be implemented to contain and manage the spill (refer to Section 5 of this ITA EMP). Prior to commissioning of the bentonite plant, an Operations and Spill Response Plan will be prepared for the plant. This Plan will outline the environmental controls and spill response procedures specific to the operation of the plant detailed in Section 2.4.1 of this ITA EMP. The extent of the bunded area and the location of the existing catchpit within the operational area of the bentonite plan that will be sealed off during the works is shown on the Stormwater Drainage Plan in Appendix D.

4.2

Jet grout plant and operation

The main environmental risk associated with operation of the jet grout plant is the discharge of sediment laden water and elevated pH from cement used in the slurry mix. To avoid or minimise any discharges from the jet grout plant into the surrounding environment, the plant will be designed and operated as follows: The jet grout plant shall be bunded with any surface water collected in the bund draining to the onsite sediment treatment plant. The outlet of the existing catchpit in the plant operation area (refer to the Stormwater Drainage Plan in Appendix D) will be sealed off, and a submersible pump installed to pump surface water to the sediment treatment plant. In the event of a spill outside of the bunded area, the standard spill control procedures will be implemented to contain and manage the spill (refer to Section 5 of this ITA EMP). Prior to commissioning of the jet grout plant, an Operations and Spill Response Plan will be prepared for the Plant. . The Plan will include the relevant environmental controls and spill response procedures specific to the operation of the plant detailed in Section 2.4.2 of this ITA EMP.

4.3

Environmentally hazardous substance management

The principal environmentally hazardous substances that will be stored and used during the construction works will include: Petrol; Industrial and Trade activities Environmental Management Plan

June 2016


16 Diesel; Jet grouting additives; and Bentonite. Dangerous and hazardous substances shall be stored on site in accordance with the Hazardous Substances and New Organisms (HSNO) Act 1996 and relevant HSNO regulations, and subject to provisions relating to Location Test Certificates and Approved Handlers, as appropriate. All chemicals will be stored in a secure area with secondary containment to contain any spills. Safety Data Sheets (SDS) for all of the chemicals used or stored in the Project area will be kept in the Project site office with a sub-set on file at each storage location relevant to the specific materials being stored. A Hazardous Substances and SDS register shall be kept on-site and regularly maintained to ensure it is up to date with the chemicals and volumes of chemicals used and stored on-site. Spill kits and associated spill response equipment, will be available at each vehicle entrance (refer to Appendix C of this ITA EMP). The storage, handling and disposal of dangerous goods will be undertaken in accordance with the following DSBJV Environmental Work Instructions: WI 101 Use and Disposal of Oils and Lubricants; WI 102 Refuelling of Equipment, Machinery and Static Tanks; WI 103 Spill Procedure: Fossil and Synthetic Fuels and Oils WI 602 Road Transport and Materials Handling; and WI 603 Storage and Handling of Dangerous Goods.

4.4

Waste management

For the purpose of the Project, waste material refers to items removed from worksites and road carriageways, such as surplus or reject spoil, excavated seal, pipes, rubbish detritus and any other unwanted materials. Appropriate disposal shall be arranged for any material that requires off-site disposal. If hazardous material requires off-site disposal, it will be disposed of safely, through an appropriate contractor authorised to handle, transport, process or safely dispose of the waste concerned to an approved disposal facility. Any waste bins on-site will either be stored undercover, or will be installed with covers to prevent rainwater ingress. Overall waste management or disposal requirements will vary depending on the material concerned and shall be undertaken in accordance with the WARRP.

4.5

Vehicle refuelling

No permanent storage of bulk fuels will occur on-site. Refuelling of plant and equipment will be undertaken using either a mini-tanker for larger equipment, or portable containers (such as jerry cans) for smaller plant and equipment. Refuelling will be undertaken in accordance with work instruction WI 102 - Refuelling of Equipment, Machinery and Static Tanks.

4.6

Wash-down

No vehicle wash-down will be undertaken on-site, apart from localised washing of vehicles and tyres as required in order to prevent the tracking of sediment onto the surrounding road network. The location and nature of the construction works, along with the construction methodology will serve to minimise the Industrial and Trade activities Environmental Management Plan

June 2016


17 potential for site vehicles to drive over areas of open excavation or unpaved areas and track dirt onto the surrounding road network. The removal of spoil from the excavations will be undertaken as follows: Material will be excavated using diggers within the excavation area or a long reach digger on the edge of the excavation; Trucks will back up to the edge of the excavation area on the existing sealed surfaces; and Material will be loaded directly into the trucks to avoid the storage of excavated material on-site. In the event of material being spilled onto the ground around the excavation or from trucks transporting the spoil from the excavation, the material will be cleaned up prior to the vehicle leaving the site. This may involve some localised washing of vehicles and tyres. Any runoff from the wash down area will directed to the on-site sediment control system. Some washing of machinery within the excavation area may be required. In this instance, washing of machinery will be undertaken using a hose or water blaster on-site within the excavation area only.

Industrial and Trade activities Environmental Management Plan

June 2016


18

5

Spill Response

The management of spills at the site will differ depending on the quantity, type of material and location of the spill. As no significant volumes of environmentally hazardous substances apart from those at the bentonite and jet grouting plants are anticipated, the spill response procedures for the Project have been divided into three separate procedures as follows: General Emergency Spill Response Plan, which covers all areas of the site; Bentonite Plant spill response procedures; and Jet Grout Plant spill response procedures. A general Emergency Spill Response Plan (ESRP) has been prepared for the Project (refer to Appendix C of this ITA EMP). The ESRP includes provision that in the event of all spills over 20 litres, or any spill of Environmentally Hazardous Substances, which has entered the stormwater system, a water-body or has contacted unsealed ground, the spill shall be reported immediately to the AC 24 Hour Pollution Hotline (09-377-3107). Additionally, Cooper and Company will be notified if spills (as described above) occur within / or are likely to affect the Britomart Precinct. The spill response procedures for the bentonite and jet grout plants will be detailed in the Operation and Spill Response Plans to be developed prior to commissioning of the respective plants. As both areas will be bunded, the specific spill response requirements will be considered as part of the final development of the site specific controls for each area. A site plan has also be developed, which shows the location of all spill kits in the Project area (refer to Appendix C of this ITA EMP). Spill kits and signage relating to spill response procedures will be located at each vehicle entrance to the site during each stage of work. Each spill kit will have a register of contents and an inspection sheet. Each spill kit will be inspected monthly to ensure all contents are present and there is no rubbish in the kits. The inspection sheet shall be signed during each inspection.

Industrial and Trade activities Environmental Management Plan

June 2016


19

6

Discharge Monitoring and Reporting

6.1

Monitoring

Within 30 days of the installation of the stormwater treatment system (including the settlement tanks and bunding of hazardous substances) and prior to operation, a stormwater monitoring programme will be developed to monitor discharges from the site, including discharges from the sediment treatment system. The monitoring programme will include: The actual sampling locations shown on the final site and drainage plans, including: Sample locations for the final discharge point from the Project area; Any additional sampling locations on-site (e.g. bund outlets, treatment tanks/ ponds prior to discharge); Methods and procedures for sampling; Monitoring parameters for analysis including: Daily: o

Turbidity (NTU); and

o

pH on a daily basis and prior to discharge;

Weekly: o o

Total Suspended Solids; Total metals including copper, zinc and lead; and

o

Total Petroleum Hydrocarbons.

The monitoring programme will include procedures for evaluation against the relevant trigger levels. The results shall be compared to 50 times the ANZECC Guidelines for protection of 95% of marine species (refer to Section 3 of the Project CTMP, which outlines the sampling methods, levels, monitoring parameters and recording requirements in accordance with Condition 101 of REG/2015/4436).

6.2

Reporting

Reporting of the monitoring results shall be undertaken in accordance with Conditions 103 and 104 of Discharge Permit R/REG/2014/5436 as outlined in Table 6.1. Table 6.1:

Monitoring reporting

Condition No.

Condition

103

Within five working days of receipt of sample results showing contaminants exceeding the agreed trigger levels (Condition 101(e)): a. an investigation shall be undertaken to determine why exceedances were detected and to identify any additional source controls or treatment required; and b. the results of the investigation shall be reported to the Council (Team Leader Central Monitoring).

104

Within eight weeks following the start of the monitoring required by Conditions 101 and 102, a monitoring report shall be submitted to the Council (Team Leader Central Monitoring). The monitoring report shall include, but not be limited to, the following: a. a summary of the monitoring results to date; b. an interpretation of those results and suggestions for improvement to the site operations; c. a programme for ongoing monitoring including the reporting of results; and d. a programme for the ongoing maintenance of the discharge water management and treatment system.

Industrial and Trade activities Environmental Management Plan

June 2016


20

7

Environmental Compliance Management and Review

7.1

Site inspections

Regular inspections of the Project area will be undertaken throughout the construction duration as outlined in Section 6 of the CEMP. Site inspections will include inspections of industrial and trade related activities to ensure the integrity of activities and devices is maintained and to minimise the potential for the discharge of contaminants from the Project area that might have adverse effects on the receiving environment. Site inspections will include the following elements: Check bunding and containment systems around hazardous substances are intact; Check water treatment systems are operating correctly to manage contaminated water; Check all loading and unloading areas are clear of spillage and debris; Check the appropriate storage of materials on-site in order to prevent spillage and have appropriate HAZCHEM warning and information signage; Check site for evidence of spills that require clean up; Check construction vehicles for signs of leakage; Check spill kits are fully stocked, clearly labelled and appropriately located; and Check waste skips and containers for capacity, signs of leakage and ensure they are covered to prevent rain water ingress.

7.2

Environmental audits

An internal environmental and sustainability audit will be undertaken 30 days from commencement of each key stage of the Project and at least a quarterly basis (or more frequently as specified in the Project Audit Schedule). The purpose of the audit is to check the implementation of, and compliance with, environmental management procedures and controls, including those outlined in this ITA EMP. The audit findings will be reported accordingly to enable any discrepancies to be identified and actioned. External environmental and sustainability audits will be completed as per the Project Audit Schedule, and at least annually, to assess the effectiveness of the Environmental Management System. Refer to Section 7.2 of the CEMP for further detail on the Project environmental and sustainability audits to be undertaken during construction.

7.3

Non-conformance, corrective and preventative action

Corrective action is required on the basis of the occurrence of substandard performance being observed or experienced, resulting in an environmental complaint, incident or emergency or where a significant environmental incident or emergency could have occurred. Refer to Section 6.2 of the CEMP for further detail on corrective and preventative action during the Project.

Industrial and Trade activities Environmental Management Plan

June 2016


21

8

Training

8.1

Employees and subcontractors

All Project staff (including subcontractors) will undergo general environmental awareness training, along with training in relation to the risks associated with industrial and trade activities outlined in this ITA EMP and to ensure that the appropriate control measures are properly implemented. Suitable induction and ongoing environmental training will be established and maintained to ensure employees and subcontractors are aware of: The importance of conformance with the Environmental Policy, the requirements of the project CEMP and company procedure; The significant environmental aspects, actual or potential, of activities and the environmental benefits of improved performance; Their roles and responsibilities in achieving conformance with the environmental policy, company procedures and this ITA EMP; The potential consequences of departure from specified operating procedures; Spill response and emergency procedures; and Accident and incident reporting and methods of prevention. Refer to Section 4.2.1 of the Project CEMP for further detail on employee training.

8.1.1

HSNO Approved Handler training

The HSNO Act 1996 requires that certain hazardous substances are under the control of an Approved Handler. Any staff required to handle such substances will be required to hold or obtain an Approved Handler Certificate.

8.2

Visitors

Visitors to the site will undergo a shortened visitor induction where there is minimal potential for environmental harm (refer to Section 4.2.2.2 of the Project CEMP). The visitor induction will cover the risks associated with industrial and trade activities outlined in this ITA EMP as required.

8.3

Training records

Staff training will be recorded as outlined in Section 4.2.7 of the Project CEMP.

Industrial and Trade activities Environmental Management Plan

June 2016


22

9

ITA EMP Review

9.1

ITA EMP Review

This ITA EMP will be reviewed throughout the course of the Project: a b

To reflect material changes associated with changes to construction techniques, the natural environment or due to unresolved complaints. As part of the annual management review of the ITA EMP.

A management review of the ITA EMP will be undertaken at least annually by the Project Management Team and AT representatives. The management review will be organised by the Project Environmental and Sustainability Manager and the Project team will be informed of any changes to this ITA EMP through the regular Project communications processes. The review will take into consideration: Compliance with the designation or consent conditions, the CEMP, DWPs and EMPs (including site specific plans) and material changes to these plans. Any significant changes to construction activities or methods. Key changes to roles and responsibilities within the Project team. Changes in industry best practice standards. Changes in legal or other requirements (social and environmental legal requirements, consent conditions, AT objectives and relevant policies, plans, standards, specifications and guidelines). Results of inspections, monitoring and reporting procedures associated with the management of adverse effects during construction. Comments or recommendations from AC regarding the CEMP, DWPs and EMPs. Unresolved complaints and any response to complaints and remedial action taken to address the complaint. Attached as Appendix E is an explanation of how any CLG comments received to date are addressed in the ITA EMP.

9.2

ITA EMP Updates

The process for updating this ITA EMP as a result of a material change to the Project or the annual review, is as follows (refer to CRL designation Condition 23 for further information): Any material change to this EMP must be consistent with the purpose and objective of the relevant conditions listed in Table 1.1 of this document. Affected parties and the CLG must be notified of the review and any material change proposed to this EMP. This EMP must clearly document the comments and inputs received from affected parties in relation to any material changes, along with a clear explanation of where any comments have not been incorporated, and the reasons why not. Any material change proposed to this DWP shall be subject to an independent peer review as required by CRL Condition 11. Any material change proposed to this DWP relating to an adverse effect shall be submitted for approval to Auckland Council Compliance and Monitoring Officer, at least 10 working days prior to the proposed changes taking effect. If any changes are not agreed, the relevant provisions of the RMA relating to approval of outline plans shall apply. A copy of the original ITA EMP document and subsequent versions will be kept for the Project records, and marked as obsolete. Each new / updated version of the ITA EMP documentation will be issued with a version number and date to eliminate obsolete ITA EMP documentation being used.

Industrial and Trade activities Environmental Management Plan

June 2016


23 A summary of the review process will be provided annually to Auckland Council and otherwise be made available on request.

Industrial and Trade activities Environmental Management Plan

June 2016


Appendix A:

ISCA Requirements

Table A identifies the ISCA Credit Requirements relevant to this ITA EMP and where they are addressed in the documents. Table A: ISCA Requirements Credit

Requirement *

Relevant section

Comments

DIS-1 Level 1

Baseline studies of existing receiving water environment have been carried out for the Project

Section 3.2

Refer also to the Water Quality Assessment Report by Golder Associates, dated Dec 2014 and the Chemical Treatment Management Plan

DIS-1 Level 1

Predictions for receiving water quality impacts have been developed for construction

Section 3

Refer also to the Water Quality Assessment Report by Golder Associates, dated Dec 2014 and the Chemical Treatment Management Plan

DIS-1 Level 1

Measures to minimise adverse impacts to local receiving water quality identified and implemented

Sections 1.1, 2.5, 3, 4.1, 4.2, 4.3, 4.4, 4.5, 4.6, 5, 7.1

Refer also to the Chemical Treatment Management Plan and Contaminated Soils Management Plan

DIS-1 Level 1

Monitoring of water discharges and receiving waters is undertaken at appropriate intervals and at times of discharge during construction

Section 6

Refer also to the Chemical Treatment Management Plan

DIS-1 Level 2

Modelling demonstrates no exceedances of water quality goals

Section 6

Refer also to Monitoring Results and Reports

DIS-1 Level 2

All stormwater leaving the site is treated or filtered in accordance with appropriate urban stormwater guidelines unless it occurs during a 6 hour 1 in 5 year storm event

Refer to the Erosion and Sediment Control Plan and the Chemical Treatment Management Plan

* Refer to ISCA Rating Tool for full details of the requirement

Industrial and Trade activities Environmental Management Plan

June 2016


Appendix B:

Work Instructions


WORK INSTRUCTION

WI-101

Purpose

To ensure that operation, servicing and maintenance of onsite machinery and equipment does not pollute the environment during construction operations.

Ensure that there is no contamination of the site.

To minimise the quantity of oils and lubricants used and to dispose of waste in accordance with appropriate legislation.

Use and Disposal of Oils and Lubricants

Scope

This procedure shall apply to all Downer New Zealand worksites or contractors working on behalf of Downer New Zealand.

References

ISO14001:

Clause 4.4.6, 4.4.7

ISO14004:

Clause 4.3.3.3, 4.3.3.4

WI-002:

Evaluating Legal Compliance

WI-002A:

Resources for Assessing Legislative Compliance

Responsibilities

It is the responsibility of the Zero Harm Advisor to ensure that all hazardous materials are stored appropriately and that PPE and spill kits are in place as necessary. All Company employees and contractors alike are to make every effort to ensure we do not pollute sites during servicing and maintenance of onsite machinery and equipment.

Requirement

There shall be minimal storage of oil and lubricants on site. Minor maintenance of plant and machinery shall be carried out onsite and in a manner that prevents spillage of oils and lubricants. The service truck operator shall drain all oils and lubricant for disposal by using containers held on the service vehicle. Spills shall be collected for disposal at a designated disposal site in each Operating Unit where it will be stored. Absorbents, cleaning materials and contaminated soils shall also be disposed of. The project shall only produce minor amounts of oils and fuels for disposal.

Performance Objectives

Downer New Zealand’s spill and containment procedures shall be followed in the case of spilt product.

Fuels shall be stored in designated areas with spill kit located nearby.

All fuel storage will be in accordance with AS/NZS 4681:2000 The Storage and Handling of Class 9 (Miscellaneous) Dangerous Goods and Articles (WI-002).

Spillage of fuels and oils shall be avoided through safe storage practices.

Storage areas shall be bunded by suitable impervious material sufficient to contain 110% of the largest storage container.

Soil contaminated with spilt fuel shall be remedied in situ or where necessary removed from site to a suitable waste disposal area.

Waste oils shall be collected and transported by licensed operators.

All permits and approvals shall be obtained for the use and storage of oils and lubricants and all conditions of the permit and approvals shall be complied with.

Handling procedures and emergency response plans shall be developed and

Issue Date: February 2013 Issued by: National E&S Manager

Page 1 of 2 Warning: Printed documents are UNCONTROLLED

WI-101, Version 002 © Copyright Downer New Zealand Limited


WORK INSTRUCTION

WI-101

Use and Disposal of Oils and Lubricants

documented.

Monitoring and Recording

A stock of relevant absorbents, cleaning materials, neutralising chemicals, equipment and protective clothing and equipment relevant to the oils and lubricants being stored shall be obtained and stored on site.

Refuelling and maintenance shall be carried out in a manner that prevents spillage of oils and lubricants.

Waste oils and semi-fluid lubricants used in compressors, gear cases, vehicles, machinery, drilling equipment etc. shall be collected by specialist firms for reprocessing and/or disposal by the firms through approved means.

Any spills shall be collected for recycling or treatment and disposed of at a designated disposal site. Absorbents, cleaning materials and contaminated soils shall also be treated or disposed of.

Document weekly inspection and appraisal of site use and disposal of oils and lubricants. Assessment of employee awareness of procedures and compliance with the EMS.

Non Conformance

In the event of a problem, it shall be rectified and the cause shall be investigated to ensure that further occurrences are prevented.

Corrective Action

Notify Management, including National Environmental and Sustainability Manager if polluting or potentially polluting incidents occur, and seek advice prior to notification of any regulatory authorities. Ensure that site employees are trained in the implementation of this work instruction.

Audit Provisions

Check disposal programmes especially if potential toxic or hazardous waste. Remedy any pollution or potentially polluting incident.

Issue Date: February 2013 Issued by: National E&S Manager

Page 2 of 2 Warning: Printed documents are UNCONTROLLED

WI-101, Version 002 © Copyright Downer New Zealand Limited


WORK INSTRUCTION

WI-102

Purpose

To ensure that on-site machinery, equipment and storage tanks do cause pollution to the environment during refuelling activities, and to minimise the risk of contamination of the site.

Scope

This procedure shall apply to all Downer New Zealand worksites or contractors working on behalf of Downer New Zealand.

References

ISO14001: Clause 4.4.6, 4.4.7 ISO14004: Clause 4.3.3.3, 4.3.3.4 Resource Management Act 1991 EMSR01: Environmental / Incident Near Miss Hazard Report

Responsibilities

All Company employees and contractors alike are to make every effort to prevent pollution of work sites.

Requirement

Refuelling of plant, machinery and static tanks shall be carried out on site and in a manner that prevents spillage of fuels. The person(s) carrying out the refuelling activity shall use drip trays/buckets held on the service vehicle/tank to prevent ground contamination, and have a suitable spill kit on hand. Spilt material, absorbents, cleaning materials and contaminated soils shall collected for storage at a designated area of site and disposed of responsibly. Where a fuel spill comes into contact with clothing, clothing must be cleaned or replaced prior to recommencing work. Where there is potential for a spill to occur, the refuelling of plant, equipments or static tanks must not proceed until the situation is rectified.

Performance Objectives

Before Refuelling  If you are in doubt about anything which may adversely affect safety, quality or the environment, contact your manager or Zero Harm Advisor and do not proceed until that doubt is removed.  Ensure that there is either an earth strap or connected earth poll, if there is none, inform your supervisor or site foreman immediately and do not commence refuelling until the situation is rectified.  A spill kit MUST be with each storage tank or service vehicle.  Personnel carrying out refuelling MUST be trained and familiar with the contents and use of spill kits prior to undertaking refuelling. During Refuelling  Remain in close attendance throughout pumping.  Do not move the vehicle whilst the hose or earthing wire is attached to the tank.  Stop pumping if in doubt and do not recommence until the fault is rectified.  When manually filling plant, equipment or static tanks, fill to160mm (6 inches) above the bottom of the fill tube. After refuelling  Allow bulk, vertical storage tanks adequate relaxation time for static charges generated through pumping to dissipate before opening them up for gauging or sampling. (30 minutes, or two hours if water is possibly

Issue Date: August 2013 Issued By: National E&S Manager

Refuelling of Equipment, Machinery and Static Tanks

Page 1 of 2 Warning: Printed documents are UNCONTROLLED

WI-102, Version 003 © Copyright Downer New Zealand Limited


WORK INSTRUCTION

WI-102

PPE

Refuelling of Equipment, Machinery and Static Tanks

present). Allow vehicles/tanks at least two minutes relaxation time after loading has ceased before disconnecting loading hoses or dipping.

Minimum PPE requirements are: o Neck-to-toe clothing o PVC gloves o Safety glasses o Safety footwear o Hard hat o Long sleeved hi-vis clothing Refer to the hazard register held by the Site Foreman/Supervisor for a detailed list of possible hazards which may be encountered at the site.

Non Conformance Corrective Action

 

Issue Date: August 2013 Issued By: National E&S Manager

All spills must be reported to the Site Supervisor/Foreman immediately. All spills MUST be documented on the Environmental / Incident Near Miss Hazard Report (EMSR01) and forwarded to the National Environmental and Sustainability Manager. A copy of the completed EMSR01 is to be retained in the job file. All spills must be cleaned up under the supervision, and to the satisfaction of the Site Supervisor/Foreman.

Page 2 of 2 Warning: Printed documents are UNCONTROLLED

WI-102, Version 003 © Copyright Downer New Zealand Limited


WORK INSTRUCTION

WI-103

Spill Procedure:

Purpose

To ensure that the spillage of fuels during storage, operation, servicing and maintenance of on-site plant and equipment, does not pollute the environment.

Fossil and Synthetic Fuels and Oils

To respond quickly in the event of spills which contain fossil and synthetic fuels, oils and chemicals. To stop such pollutants from entering drains or watercourses, contaminating soil or endangering the environment. Scope

This procedure shall apply to all Downer New Zealand worksites or where potentially hazardous substances are used or stored.

References

ISO14001:

Clause 4.4.6, 4.4.7

ISO14004:

Clause 4.3.3.3, 4.3.3.4

EMSR01:

Environmental / Incident Near Miss Hazard Report

Resource Management Act 1991 Responsibilities

All Company employees and contractors alike are to make every effort to minimise and control the spill of potentially hazardous materials. WATER MUST NOT BE USED TO CLEAN UP FUEL/OIL RELATED SPILLS

Procedure

A minor spill is defined as:

Minor Spill

Spill or contaminated material located in an area where there is no possibility of entering drains or waterways A minor spill of contaminated material can be easily removed without the use of heavy machinery. Minor spills of oils and fuels should be dealt with immediately by first isolating the cause of the spill. Once isolated, use the clean up equipment from the on site spill kit. Use the absorption pillows or pads to absorb the spill; you may also use a mineral sponge if required. Once the spill is cleaned up, dispose of the waste in the disposable bags provided. Bags of waste are to be classified as regulated waste and stored until collected and transported to a recycle depot. In an emergency, soil may be used as a clean-up agent. Soil is to be spread over the spill by whatever means necessary, once contaminate is absorbed the soil is to be removed and discarded in the disposable bags provided in the spill kit and treated as regulated waste.

Procedure

Including Diesel Fuel Storage Tank, Drum Storage, Refuelling Tanker

Major Spill A major spill is defined as: Spill material threatening to enter drains or waterways Spill material causing disruption to traffic Spill material causing damage to flora and fauna Spill material unable to be removed easily without the aid of heavy machinery

Issue Date: February 2013 Issued by: National E&S Manager

Page 1 of 2 Warning: Printed documents are UNCONTROLLED

WI-103, Version 002 Š Copyright Downer New Zealand Limited


WORK INSTRUCTION

WI-103

Spill Procedure: Fossil and Synthetic Fuels and Oils

In the event of a major spill, the contaminant must be stopped from entering watercourses or causing damage to the environment. Stopping the flow of fuel and containment of the spill must be the first priority. The spill kit may not be sufficient to cope with a major spill and it may be necessary to cover the spill with earth, other suitable substance or build an earth bund around the spill using plant or machinery. Once the spill has been contained and the earth or other suitable substance has absorbed the contaminant, it must be removed and treated as regulated waste. Contact the emergency services to prevent the risk of fire or explosion. All major spills MUST be reported to the local or government authority. Documenting Requirements

All spills MUST be documented on the Environmental / Incident Near Miss Hazard Report (EMSR01) and those of medium or high risk rating must be forwarded to the General Manager Strategy and Risk. A copy of the completed EMSR01 is to be retained in the job file.

Issue Date: February 2013 Issued by: National E&S Manager

Page 2 of 2 Warning: Printed documents are UNCONTROLLED

WI-103, Version 002 Š Copyright Downer New Zealand Limited


WORK INSTRUCTION Purpose

WI-602

Road Transport and Materials Handling

To ensure safe transportation of construction equipment and materials, including hazardous materials, with minimal disruption to other road users whilst undertaking mobilisation, demobilisation and construction activities. Cartage on roads will require specific maintenance measures during and following haulage to ensure that there is no degradation of the roads. Schedule and operate trucking of construction materials and equipment to site in a way that minimises disruption to normal traffic on public roads. To unload and store materials into appropriate receivable areas. To source construction materials with a view to minimising road transportation on busy public roads where alternatives for sourcing materials exist. To ensure that materials used on site have minimum adverse environmental effects.

Scope

This procedure shall apply to all Downer New Zealand worksites or contractors working on behalf of Downer New Zealand.

References

ISO14001:

Clause 4.4.6, 4.4.7

WI 002:

Evaluating Legal Compliance

WI 002A:

Resources for Assessing Legislative Compliance

WI 004:

Identification of Aspects and Impacts

WI 004A:

Aspects and Impacts Register

WI 210:

Stabilised Concrete Entrance

WI 603:

Storage and Handling of Dangerous Goods

HS06:

Hazard Identification Sheet

Road Transport Safety Authority Regulations Responsibilities

All Company employees and contractors alike are to obey Road Transport Safety Authority Regulations and Safe Material Handling Regulations (WI-603).

Requirements

Drivers, vehicles and loads shall be correctly licensed and approved at all times. Where permitted under specifications, materials and goods causing the minimum adverse environmental impact during their collection, manufacture, transport, use and operation shall be selected. Haul Roads All access routes shall be maintained in a safe condition. Ensure that design features for haul roads and access tracks lessen scouring of the new works and tracking by vehicles (refer WI 210 Stabilised Concrete Entrance if required). Roads are to be kept safe during haulage. Regular watering to prevent dust and general maintenance of haul roads may be required. Standard warning signs and speed limits shall be erected for the duration of the haulage and while maintenance grading is being carried out. Public Roads

Issue Date: February 2013 Issued By: National E&S Manager

Page 1 of 2

WI-602, Version 002 Š Copyright Downer New Zealand Limited


WORK INSTRUCTION

WI-602

Road Transport and Materials Handling

Public roads accessing the site are to be kept clean. As far as practicable, materials shall be sourced to limit use of public roads for hauling bulk construction materials. Road transport shall be coordinated to ensure minimum damage to public roads along cartage routes. Monitoring and Recording

It is the responsibility of the Site Supervisor to check that all drivers are licensed and vehicles are registered, carry legal loads and are operated in a safe manner. Transport routes and operations are to minimise disruption to existing residents and other road users. The roads being used for transport of construction materials must be regularly monitored in terms of their condition and remedial works carried out if necessary to maintain a safe and trafficable condition. A servicing and preventative maintenance programme must be in place for all vehicles. Works must be monitored against road transportation plans to ensure that they are compliant. It is the responsibility of the Project Manager to liaise with local authorities in regards to road conditions and deal with any public concerns related to traffic disruption due to construction haulage operations. It is the responsibility of the Site Supervisor/Manager to undertake weekly inspection of receivable and storage areas to ensure that the area is kept in a clean and tidy state and that excess dust and noise are not a problem.

Non Conformance Corrective Action

It is the responsibility of the Site Manager/Supervisor to ensure that : no driver or vehicle is used that does not comply with requirements; any defective vehicles are repaired or replaced immediately; roads are maintained and that in no way does their condition affect safety or the environment; appropriate safety measures are provided; immediate corrective action or rehabilitation works shall be commenced should any work be found to contravene permit conditions or work instructions; and any complaints or known breaches of legislation, regulations, permits or approvals are assessed and corrective measures implemented. It is the responsibility of the Zero Harm Advisor to review the complaints register during internal audits to ensure all complaints have been addressed.

Audit Provisions

It is the responsibility of the Zero Harm Advisor to carry out regular audits against local and government body specifications, the site environmental management plan and relevant work instructions.

Issue Date: February 2013 Issued By: National E&S Manager

Page 2 of 2

WI-602, Version 002 Š Copyright Downer New Zealand Limited


WORK INSTRUCTION

WI-603

Purpose

To ensure that storage and handling of dangerous goods held on site does not cause pollution of the environment or harm to employees.

Storage and Handling of Dangerous Goods

To ensure safe transportation, storage and handling of chemicals. To ensure that there is no contamination of the site and that it operates at all times in compliance with AS/NZS 4681:2000 (The storage and handling of Class 9 (miscellaneous) dangerous goods and articles).

Scope

This procedure shall apply to all Downer New Zealand worksites or contractors working on behalf of Downer New Zealand.

References

ISO14001:

Clause 4.4.6, 4.4.7

WI002:

Evaluating Legal Compliance

WI004A:

Aspects and Impacts Register

HS06:

Hazard Identification Sheet

AS/NZS 4681:2000: Storage and handling of Class 9 (miscellaneous) dangerous goods and articles Guidelines for the Management and Handling of Used Oil in New Zealand (MfE/OSH, 2000).

Responsibilities

Requirements

All Company employees and contractors alike shall comply with this work instruction, and endeavour to eliminate the risk of contamination at Downer sites. Zero Harm Advisor:

Monthly inspection of the storage facility

Site Supervisor:

Daily visual inspections of site operations

General Requirements: Oils, lubricants, chemicals and fuel shall be stored on the worksite in designated storage facilities located within a compound in the maintenance yard. It is recommended that a pre-placement assessment including photographic record be conducted. This will give an indication of the pre-construction state of the proposed site. A suitable waste reception area must be located close to the store. This area must be paved and with adequate provisions for containing any spills (consider gradients and location of stormwater grates). Lockable storage containers shall be used for storage of hazardous goods. Where fuel is to be stored on site, this arrangement shall be in accordance with AS/NZS 4681:2000. Oil and hydraulic fluids shall be located on the service truck and not stored at any other location. On removal/decommissioning it may be necessary for a simple environmental investigation be conducted. The scale of investigation will be dependent on the scale of the operation and whether any incidents or spills occurred on the site.

Issue Date: November 2012 Š Copyright Downer New Zealand Limited

Page 1 of 5

WI-603 Version 002


WORK INSTRUCTION

WI-603

Storage and Handling of Dangerous Goods

Building Requirements: Storage buildings should be sited so that the risk of contamination of people, crops, animals and the environment is minimised. The building must: be at least 15-20 metres from any source of ignition (fire, workshops, furnace, smoking area, etc); be at least 5 metres from any other building, boundary or deemed road; be sited so that dangerous fumes are not carried into sensitive environments; have easy access for vehicles and emergency services; and be away from vehicle thoroughfares and protected with bollards. Environmental Protection To protect the surrounding environment the building must: have internal bunding sufficient to hold 110% of the contents of the largest container; have an impermeable concrete floor (implies a suitable surface coating); have a bund around the external access (a small nib wall); be as far away as practicable from any storm water grates; and have an emergency spill kit. Construction Materials The Hazardous Substances (Classes 1 to 5 Controls) Regulations require a number of controls for hazardous substance locations in order to reduce the likelihood of unintended ignition of Class 2, 3 or 4 substances, including: fire resistant walls; separation distances from ignition sources; and safety requirements for electrical equipment (construction, design, earthing). In addition, the New Zealand Building Code provides ‘acceptable solutions’ as a means of complying with the Building Act 1991. The recommended generic design must meet the following criteria: Be constructed of non-combustible materials (concrete) Be constructed with no windows, and door opening outwards An impermeable membrane/coating on the floor to contain spills All surfaces painted or sealed to avoid contamination No electrical fittings (if electrical fittings are required for any reason, these must be intrinsically safe) Ventilation For health and safety reasons the building must have adequate ventilation. Static venting using high and low level vents, covered with 0.5mm nominal aperture brass-wire gauze where within 1.5 m of the ground. Forced air extraction is not required. Issue Date: November 2012 © Copyright Downer New Zealand Limited

Page 2 of 5

WI-603 Version 002


WORK INSTRUCTION

WI-603

Storage and Handling of Dangerous Goods

Security The facility must be adequately secured against break-ins and accidental access; including: installation of an intruder alarm monitored by a security firm; regular security patrols; and a lockable door. Goods will be received at the construction office to ensure that quantities are known and monitored. Fire/Spill Protection The following precautions need to be undertaken: Clear identification of stormwater drains Supply of fire extinguishers (dry powder or CO2) Water at adequate volume and pressure available within reach of the facility Suitable location of evacuation points Spill response equipment on hand Signage Signage at the gate of the site should include: hours of operation; contact telephone numbers of key staff and emergency services; HAZCHEM signage (4WE Code); and list of prohibited wastes. Signage on the outside of the storage shed should include: front door signage restricting access due to the dangerous nature of chemicals stored therein; HAZCHEM sign on door (4WE Code); "NO SMOKING" sign; and Labels indicating which storage bay for which chemical class. Signage in the immediate vicinity of the storage shed should include: instructions for depositing waste including a statement that it is prohibited to drop-off unattended wastes; location of first aid kit, fire extinguisher, emergency equipment and evacuation points; and location of safety shower/eyewash station. Personal Protection The following facilities are required at the site: Separate storage areas for emergency equipment and PPE Separate change area, toilets and washroom An eyewash station in or close to the store (note that if it is a bottle, sterile Issue Date: November 2012 Š Copyright Downer New Zealand Limited

Page 3 of 5

WI-603 Version 002


WORK INSTRUCTION

WI-603

Storage and Handling of Dangerous Goods

water must be changed weekly)

The following general safety equipment should be available: First aid equipment (including eyewash). Drum trolley Spill kit Plastic trays/bins for containment of acids/alkalis/corrosives UN approved secondary containment devices and PE bags for secondary containment of leaking containers Adhesive and tie-on labels Waterproof marker pen Type I Approved Segregation Device

Waste Oil Storage

Introduction Waste oil storage facilities should be designed and managed in accordance with the Guidelines for the Management and Handling of Used Oil in New Zealand (MfE/OSH, 2000). Used oil collection facilities are classified as either controlled collection or general collection sites. This classification is based site manager’s ability to prove that other products do not contaminate the used oil on site. Controlled collection sites can meet less stringent design requirements on the basis that provision does not have to be made for highly flammable liquids, such as fuels. Siting The following matters should be considered when siting a waste oil storage tank: Suitable positioning to facilitate supervision by the operator who has responsibility for what is emptied into the container Location on an impermeable surface such as concrete or asphalt Safe access for tankers during unloading The use of bollards if the tank is located near vehicular traffic Location at least two metres away from potential hazards such as recycling or rubbish bins Tanks should be located outdoors, inside a bund able to hold 110% of the contents of the tank The bund should either be roofed, or adequate provision made for the inspection and safe disposal of clean storm water. If the bund is fitted with a drain valve, it should be lockable or the handle should be removed. Construction Generally, the maximum container size for fibreglass or plastic igloos at public used oil collection points should not exceed 1000 litres, and only one tank will be permitted per site. Tanks greater than this size will require consent in writing from the Chief Inspector, Explosives and Dangerous Goods. Used oil containers may be constructed of plastic, metal or glass reinforced plastic, provided they meet certain performance criteria set out in the Guidelines The requirements of the tank include:

Issue Date: November 2012 Š Copyright Downer New Zealand Limited

Page 4 of 5

WI-603 Version 002


WORK INSTRUCTION

WI-603

Storage and Handling of Dangerous Goods a lockable opening at the top of the tank, a permanent mesh at the fill point, a discharge outlet fitted with a lockable valve, and a vent.

The tank should be labelled with: the safe fill level; manufacturer and date of manufacture; content and prohibited substances labels as per the MfE Guidelines; Class 3 dangerous goods diamond. The waste oil collection facility will require a Test Certificate (formerly known as a Dangerous Goods licence). Personal Hygiene For health and safely purposes, personal hygiene must always be strictly maintained. To help maintain personal hygiene when handling chemicals, staff should follow these procedures: NEVER touch your face when you have been handling waste. ALWAYS wash your hands with soap and warm water at least once before eating, smoking, touching your face, or going to the toilet. NEVER smoke in or near the dangerous good storage area. WASH spills off your skin immediately. STOP WORK and get fresh air if you feel unwell. Advise your supervisor. Staff must not take work clothes home for laundering that may have become contaminated with hazardous substances. Any clothing that has become contaminated should be placed in a plastic bag for disposal or, if contamination is light, specific arrangements made with a commercial laundry company.

Monitoring and Recording

Daily visual inspections of site operations by the site supervisor.

Non Conformance Corrective Action

Any change to the storage area, or quantities stored, is to be first agreed by the Zero Harm Advisor.

Audit Provisions

Regular audit is the responsibility of the Zero Harm Advisor, who will check that the site operates in accordance with government legislation, local government specifications and Downer policies and work instructions.

Monthly inspections of the storage facilities by the Zero Harm Advisor.

Non conformances are to be followed up and remedied immediately by the Zero Harm Advisor.

Issue Date: November 2012 Š Copyright Downer New Zealand Limited

Page 5 of 5

WI-603 Version 002


Appendix C:

Spill Response Plan


Auckland City Rail Link – Britomart Enabling Works (Contract 1) Emergency Spill Response Plan 1.0

Purpose and Objective of Plan

Environmentally Hazardous Substances (EHS) will be present in Project construction areas. This ESRP relates to the management of spills of EHS’s and the prevention of adverse environmental effects. The objective of this Emergency Spill Response Plan (ESRP) is to ensure that emergency spills are handled in an appropriate manner to ensure safety of all personnel and to prevent damage to the environment. This ESRP covers the spill response procedures for the general areas included in the Active Construction Zones (ACZs) and Construction Support Areas (CSAs). Spill response procedures for the Bentonite and Jet Grouting plants will be detailed in the specific operations and spill response plans to be developed prior to commissioning of these plants.

2.0

Spill Response in ACZs and CSAs

Spillages within the ACZs will be managed and cleaned up on site in accordance with this ESRP. Any contamination of rain water or groundwater within the trench will be treated as per the Project ESCP prior to release or disposal. Spillages within the CSAs will be managed and controlled within the CSA. Spill risk will be managed through structural and procedural controls. In the event that these controls fail, management will be by way of adherence to the procedures outlined in this ESRP.

3.0

Hazardous Substances and Spill Response Procedures

Safety Data Sheets for all hazardous substances associated with the Project construction works are held at the site office. These will be consulted to determine the appropriate course of action to take in an emergency situation, e.g. spillage. Spill kits and associated equipment, are located at each vehicle entrance to the site as shown on the attached stage plans.

4.0

Key Contacts

Key Project contacts in the event of a spill or release of EHS are listed below: Role

Name

Organisation

Phone

Email

Construction Manager

Nick Adams

AT

(022) 645 1637

Nick.Adams@at.govt.nz

Construction Safety Manager

Mark Durham

AT

(027) 733 2156

Mark.Durham@at.govt.nz

Project Director

Dale Burtenshaw

DSBJV

(021) 115 1819

Dale.Burtenshaw@downer.co.nz

Deputy Project Director / Construction

Fabrice Perez

DSBJV

(021) 913 046

Fabrice.PEREZ@soletanchebachy.com


Role Manager Foundations

Name

Organisation

Phone

Email

Construction Manager – Civil Building

Matt Beswick

DSBJV

(027) 702 6002

Matthew.Beswick@downer.co.nz

Construction Manager MEP

Ian Mather

DSBJV

(021) 790 413

Ian.Mather2@downer.co.nz

Environmental and Sustainability Manager

Sarah Sutherland

DSBJV

TBC

Sarah.Sutherland@downer.co.nz

Zero Harm Manager

Clint Hill

DSBJV

(027) 702 8309

Clint.hill@downer.co.nz

5.0

Key emergency services

Key emergency services to be contacted in the event of a spill or release of EHS are listed below: Emergency Service

Role/Responsibility

Phone Number

Auckland Council Pollution Hotline

Spills to stormwater systems

(09) 377 310

Watercare Services

Spills to stormwater/sewage systems

(09) 442 2222

Police

Traffic Control Evacuation Crowd Control Investigation of Fatalities

111

Ambulance

Treat Injured Transport Injured

111

Fire Service

Fight Fires Contain Spillage Rescue

111


DSBJV Emergency Spill and Runoff Response Are you able to safely deal with the spill?

NO

YES

1.

Evacuate area and call Fire Service 111

BE SAFE:

Determine type of protective equipment required from SDS and use it – isolate area – evacuate non-essential personnel – isolate ignition sources

YES

2. STOP the SOURCE: Plug leak – right or reposition containers – turn off taps, valves or pumps

3.

CONTAIN SPILT PRODUCT:

Cover Sumps (drain covers, sandbags or booms) Close Interceptors Block stormwater drains (sandbags, temporary bunds or drain covers) Cover solid spills with plastic

4. NOTIFY Immediately: Your Supervisor and Auckland Council (09 377 3107) if greater than 20L or likely to enter stormwater drains ASSESS EXTENT OF SPILL, if required notify Fire 111 Police 111 Advise neighbours (where applicable). Cooper and Company to be notified of spills with in / affecting Britomart Precinct

5. CLEAN UP: Only if trained and proper equipment is available Do NOT wash away with water into drains, use materials in spill kit,

6. DISPOSE Properly: Safely collect and dispose of contaminated absorbents and clean up gear by licensed contractor (e.g. ChemWaste)

7. REORDER and REVIEW: Replace all used spill kits materials and absorbents immediately document/record incident - investigate cause of spill - take action to prevent a repeat incident

Industrial and Trade activities Environmental Management Plan

June 2016


Spill kit locations

N

QUAY ST

STAGE 1 CONSTRUCTION ACTIVITIES JULY 2016 TO JANUARY 2017

100

CONSTRUCT TEMPORARY FACILITIES (INCLUDING NEW STAIRS) REMOVE EXISTING STAIRS AND ESCALATORS REMOVE/RELOCATE PUBLIC ARTWORK ROAD AND FOOTPATH ALIGNMENTS MODIFIED

80

90

EMERGENCY EGRESS MAINTAINED WHILE UPPER CPO IS TENANTED

70

TRAFFIC DIRECTION REVERSED ON TYLER ST

SITE ACCESS

SITE EGRESS REMOVE CANOPIES

50

60

QUEEN ELIZABETH II SQUARE

40

LAYDOWN AREA

PRECINCT

SITE EGRESS

10

20

30

(NOT PART OF WORKS)

ORIGINAL SCALE OF MM.

0

CONSTRUCTION ZONE WORK PHASED TO ALLOW EMERGENCY ONLY PUBLIC ACCESS DURING OPERATING HOURS SITE ACCESS

CPO TO REMAIN OPEN. UPPER FLOORS REMAIN TENANTED LAYDOWN AREA

SITE EGRESS

SITE ACCESS COMMERCE ST

QUEEN ST

GALWAY ST

REMOVE CANOPIES

REV

AMENDMENT

BY NAME

DATE

CITY RAIL LINK ENABLING WORKS CONTRACT 1 STAGE 1 OVERVIEW TEMPORARY STATION ENABLING WORKS

CONTRACT No.

880201-250

DWG. SCALE (A3 Original)

1:500 @ A3 DRAWING No.

REVISION

STAGE 1 CONSTRUCTION

09.05.2016


Spill kit locations

N

QUAY ST

STAGE 2 CONSTRUCTION ACTIVITIES JANUARY 2017 TO MAY 2017

100

CONSTRUCT DUST/NOISE BARRIERS STRIP OUT CPO CPO GROUND FLOOR DEMOLITION CPO DIAPHRAGM WALL CONSTRUCTION (BEGIN) B2 TEMPORARY ACCOMMODATION WORKS

80

90

MAIN CONSTRUCTION ACCESS INTO CPO. BUS SHELTERS REMOVED. SITE FENCED AND GLASSHOUSE PROTECTED. SITE PARKING PROVIDED ALONG TYLER ST

70

TRAFFIC DIRECTION REVERSED ON TYLER ST

TYLER ST

PRECINCT

CONSTRUCTION ZONE ALL PUBLIC ACCESS TO CPO CLOSED. UPPER FLOORS VACATED BY TENANTS AND USED AS SITE OFFICES AND STORAGE UNDERTAKE CPO WORKS AND COMMENCE DIAPHRAGM WALL INSTALLATION

WORK AREA SECURELY FENCED

ORIGINAL SCALE OF MM.

0

10

20

30

(NOT PART OF WORKS)

DRYWALL BENTONITE TREATMENT AREA

PUBLIC ACCES NEW STATION LAYOUT IN OPERATION

NOISE/DUST BARRIER BETWEEN CONSTRUCTION AND PUBLIC AREAS

PUBLIC ACCESS

GALWAY ST COMMERCE ST

40

50

60

QUEEN ELIZABETH II SQUARE

QUEEN ST

GALWAY AND COMMERCE STREETS UNAFFECTED

REV

AMENDMENT

BY NAME

DATE

CITY RAIL LINK ENABLING WORKS CONTRACT 1 STAGE 2 OVERVIEW CPO DEMOLITION AND PILING WORKS

CONTRACT No.

880201-250

DWG. SCALE (A3 Original)

1:500 @ A3 DRAWING No.

REVISION

STAGE 2 CONSTRUCTION

09.05.2016


N

QUAY ST

Spill kit locations

STAGE 3 CONSTRUCTION ACTIVITIES MAY 2017 TO MAR 2020 B2 ACCOMMODATION WORKS & B1-B2 ESCALATOR COMPLETE QUEEN ST PILING CPO AND QUEEN ST EXCAVATION UNDERPINNING CPO BREAK-THROUGH INTO PRECINCT WORKS TUNNEL CONSTRUCTION BACKFILL QUEEN ST REINSTATEMENT STATION BOH B2 WORKS CPO REBUILD

100

SITE BOUNDARY EXTENDED TO QUAY ST

80

90

AUXILIARY SITE ACCESS

70

TRAFFIC DIRECTION REVERSED ON TYLER ST

TYLER ST

40

50

60

QUEEN ELIZABETH II SQUARE

PRECINCT

CONSTRUCTION ZONE PUBLIC ACCESS TO CPO REMAINS CLOSED. UPPER FLOORS USED AS SITE OFFICES AND STORAGE COMPLETE UNDERPINNING, EXCAVATION AND CONCRETE WORKS READY TO CPO OPEN

ORIGINAL SCALE OF MM.

0

10

20

30

(NOT PART OF WORKS)

PEDESTRIAN ACCESS MAINTAINED VIA TEMPORARY FOOTBRIDGE OVER EXCAVATION

QUEEN ST CLOSED TO VEHICLES BETWEEN TYLER AND GALWAY. PEDESTRIAN ACCESS MAINTAINED

PUBLIC ACCES

CONSTRUCTION ZONE (BACK OF HOUSE AREA)

NEW STATION LAYOUT IN OPERATION

PUBLIC ACCES

DEMOLISH OFFICES AND CUT THROUGH SECANT PILE WALL

GALWAY ST

REV

AMENDMENT

GALWAY AND COMMERCE STREETS UNAFFECTED

QUEEN ST

SITE BOUNDARY AT QUEEN ST / CUSTOM ST INTERSECTION (EXTENDED TO CUSTOM ST)

COMMERCE ST

SITE ACCESS

BY NAME

DATE

CITY RAIL LINK ENABLING WORKS CONTRACT 1 STAGE 3 OVERVIEW PILING, EXCAVATION, CONCRETE WORK AND BACKFILL

CONTRACT No.

880201-250

DWG. SCALE (A3 Original)

1:500 @ A3 DRAWING No.

REVISION

STAGE 3 CONSTRUCTION

09.05.2016


N

QUAY ST

Spill kit locations

STAGE 4 CONSTRUCTION ACTIVITIES APR 2020 TO JUN 2020

70

80

90

100

CPO OPEN REINSTATEMENT OF QUEEN, TYLER & GALWAY & STATION PLAZA TIE IN RAIL TUNNELS TO EXISTING RAIL AT STATION LINE REMOVE TEMPORARY ACCOMMODATION

NEW PUBLIC REALM REINSTATEMENT

60

QUEEN ELIZABETH II SQUARE

TRAFFIC DIRECTION REVERSED ON TYLER ST

TYLER ST

40

50

REMOVE TEMPORARY ACCOMMODATION BUILDING

PRECINCT

10

20

30

(NOT PART OF WORKS)

0

CPO OPEN ORIGINAL SCALE OF MM.

PUBLIC ACCESS CONSTRUCTION ZONE TIE INTO EXISTING RAIL ALIGNMENT AT STATION LEVEL

QUEEN ST REOPENED

GALWAY AND COMMERCE STREETS UNAFFECTED

QUEEN ST

REV

AMENDMENT

COMMERCE ST

GALWAY ST

BY NAME

DATE

CITY RAIL LINK ENABLING WORKS CONTRACT 1 STAGE 4 OVERVIEW UNDERPINNING REMOVAL AND CPO FIT-OUT

CONTRACT No.

880201-250

DWG. SCALE (A3 Original)

1:500 @ A3 DRAWING No.

STAGE 4 CONSTRUCTION

REVISION

09.05.2016


Appendix D:

Site Drainage Plan


SW

SW

SW SW

SW

SW

US

IL.1

DSIL.2 .03

.68

SW

COMMERCE STREET

SW

SW

DSIL USIL

SW

SW SW

NOTES 1. 2.

SW

SW SW

SERVICES WHICH HAVE BEEN IDENTIFIED FROM UTILITY RECORDS AS ALREADY OUT OF SERVICE. LINES ARE TO BE REMOVED WHERE THEY CONFLICT WITH THE PROPOSED WORKS (REFER NOTE 3)

SW

SHT 1

OUT OF SERVICE:

SW

SW1,SW2

SW

SERVICES ARE TO BE PROTECTED INSITU AND REMAIN LIVE THROUGHOUT CONSTRUCTION

SW

PROTECT:

DSIL.1 .72

SHT 2

ALIGNMENT PROPOSED BORED PILE WALLS EXISTING STORMWATER ABANDON PROTECT OUT OF SERVICE WORKS REFERENCE - REFER UTILITY SUMMARY SPREADSHEET DOWNSTREAM INVERT LEVEL UPSTREAM INVERT LEVEL PIPE DIAMETER

SW

SHT 3 SHT 4

SW

SHT 5

SW

SHT 6

SHT 9 SHT 11

SW

SHT 12

SW

SW

10-18

SHT 8

A

.64

SW

14

SHT 10

SHT 13

SERVICES SHOWN AS ABANDONED ARE SERVICES WHERE PROPOSED WORKS WILL LEAVE THE LINE REDUNDANT OR 2 8 WILL REPLACE THE EXISTING LINE. SERVICES MAY BE EITHER REMOVED OR CAPPED AND LEFT IN PLACE. REFER TO PROPOSED UTILITY DIVERSION ROUTES DRAWINGS FOR PROPOSED UTILITY DIVERSIONS

IL.1 DS SW

SW

20

ABANDON:

SHT 7

SHT 14

LEGEND

PROPOSED WORK DESCRIPTIONS

KEY PLAN

16 SW

SW

7

SW

SW

SW

SW

SW

SW

3.

SW

SW

SW

SW

SW

SW

4.

SW

USIL.1.61

SW

SW

SW

SW

SW

SW

SW

SW

SW

SW

SW

SW SW

SW

SW

SW

SW SW SW

SW

SW

SW

SW

SW

SW

SW

SW

SW

SW

SW

SW

SW

USIL. SW

SW

SW

SW

DSIL.2.58 SW

SW

SW

SW

SW

SW

SW SW

SW

SW

SW SW

SW

USIL.1.1

SW

SW

SW

SW

SW

SWSW

USIL .2 SW

.58 SW

SW

SW

SW

SW SW SW

SW

SW

1.22 SW

SW SW

SW SW

SW

SW

GALWAY STREET

SW

GALWAY STREET

5.

SW

Bentonite Plant bund

SW

ALIGNMENT SHOWN IS DR6. THE LOCATIONS OF SERVICES SHOWN ON THESE DRAWINGS ARE APPROXIMATE ONLY AND ARE BASED ON INFORMATION PROVIDED BY THE RELEVANT SERVICE PROVIDER. NO LIABILITY IS ACCEPTED FOR THE COMPLETENESS OR ACCURACY OF PLOTTED SERVICES. ALL PROPOSED WORKS ARE INDICATIVE ONLY AND ARE BASED ON AVAILABLE SERVICES INFORMATION. ALL WORKS ARE YET TO BE AGREED WITH RELEVANT PROVIDER. PLANS SHALL BE READ IN CONJUNCTION WITH THE FOLLOWING RFP DOCUMENTS: CRL-SYW-UTI-000-RPT-0002 THESE DOCUMENTS CONTAIN DETAILS OF THE AFFECTED UTILITIES AND THE WORKS PROPOSED TO PROTECT OR RELOCATE. DUE TO CONFIDENTIALITY OF THE NETWORK OF SOME PROVIDERS, THESE PLANS ARE NOT TO BE CIRCULATED TO THE GENERAL PUBLIC.

SW

SW

SW

180

SW

SW

SW

170

SW

SW

SW

SW

160

SW

150 SW

SW

SW

SW SW SW

SW

SW

SW

SW

SW SW

SW

SW

SW

SW

SW

SW

.0.84 USIL SW

SW

100

90

80

70

60

50

40

30

20

10

00

110

120

SW

130

SW

SW140

SW

SW

SW

SW

SW2 SW3

SW

SW

SW

SW

EXTENT OF WORKS

180

SW

130

120

110

SW

100

90

SW3

SW

SW

SW

SW SW

SW

SW

SW

SW

SW SW

SW

CRL DOWN MAIN (MC20) SW

SW

SW

SW

SW

SW

SW

SW

SW

SW

SW

SW

SW

SW

SW

SW

SW

SW SW

SW

SW

SW

SW

USIL.1.6

SW

SW

SW SW

SW

SW

SW

SW

SW

SW

SW SW

5 USIL.1.3 SW

SW

SW

SW

SW

SW

SW

SW

SW

SW

SW SW

SW

USIL.1.22 SW SW SW

SW

SW

SW

SW

TYLER STREET

10m

148

SW

S

CLIENT

REV 2.0 3.0 4.0

DATE 18.07.14 25.07.14 15.08.14

REVISION DETAILS ISSUE FOR RFP ISSUE FOR RFP ISSUE FOR RFP

APPROVED

Catchpits to be protected

120S

152

SCALE 1:250

Specific bunded areas

SW

5

QUEEN STREET

1 SW

0

Catchpit outlet to be closed. Submersible pump added to pump to treatment plant

SW

Auckland

COMMERCE STREET

SW

SW

2.5

Stormwater drainage to be removed as part of works

SW

19/08/2014 2:55:55 p.m.

SW

SW

SW

SW

SW

TYLER STREET

2

5 RC

SW

SW

SW

SW

SW

SW

SW

SW

Jet Grout Plant bund

SW

pw:\\DESIGNSHARE.AU.AURECON.INFO:PW_PROD_AU\Documents\Projects\23xxxx\239933 - City Rail Link (CDE)\01-WIP\Drawings\CRL-BTM-STR-000-DRG-0191.dwg

SW

SW

SW

SW

SW

SW

80

SW

USIL.0.86140

70

SW

SW1

SW

SW

SW

SW

SW

USIL.0.9

SW

60

SW

12

160

SW

50

SW

12A

150

QUEEN STREET

SW

40

170

30

SW

B

MATCHLINE - REFER TO SHEET 0002

SW

SW

20

10

00

-20

-10

SW

CRL UP MAIN (MC30)

SCALE

SIZE

1:250

A1

DRAWN

PRELIMINARY NOT FOR CONSTRUCTION

CITY RAIL LINK

PROJECT

TO REMAIN IN Layout SITU ITA UTILITIES Draft Stormwater STORMWATER SERVICES Plan SHEET 1

APPROVED

I.HOLMES

.

DESIGNED

DATE

TITLE

L.DAVIES CHECKED

B.NEWNS

C.McGREGOR 0

20mm ORIGINAL SIZE

40

60

80

100

200

300

400

500

DOCUMENT 600

PROJECT

ZONE

DISCIPLINE

ELEMENT

TYPE

SHEET

REVISION

CRL

PAT

UTI

001

DRG

0001

4.0

700

800


Appendix E:

CLG Comments

Community Liaison Group Comments Comments received from the CLG are as follows: Date

CLG Member

Comment

Response

4 May 2016

Cooper and Company

Section 9, ITA EMP Review, sets out the formal review process and mentions taking into account comments or recommendations of Council but doesn’t mention the CLG. Condition 19 states that the consent holder is required to consult with the CLG upon the review of this plan. Reference should be included here of this obligation.

Section 9 text been updated to reflect Condition 19 requirement to consult with the CLG upon the review of this plan.

4 May 2016

Cooper and Company

Appendix B, Work Instructions – W 102 – Refuelling. The purpose statement is missing a “not” i.e. “To ensure that onsite machinery, equipment and storage tanks do not cause pollution to the environment”.

Appendix 1 text is in the process of being corrected.

4 May 2016

Cooper and Company

Appendix C – Spill Response Plan – Emergency Spill and Runoff Response Flow-chart talks about who will be notified and that neighbours will be notified “where applicable”. Cooper and Company would want to be notified of any spills within/affecting the Britomart Precinct.

Section 5 and the flow chart in Appendix C has been updated to include notification of Cooper and Company of spills within the Britomart prescient when applicable.

20 May 2016

Cooper and Company

Section 5 Spill Response has a typo “as described above”.

Section 5 text updated to fix typo.


Turn static files into dynamic content formats.

Create a flipbook
C1 industrial and trade activities emp by City Rail Link Ltd - Issuu