C1/C2 Community Liaison Group Meeting 26 November 2020


Agenda • C1 – Britomart / CPO building works • C1 – Britomart / Lower Queen St urban realm design • C2 – Completed! • Wider project update

2


C1 – Building works

3


C1 – Building works

Lower Queen Street

The north tunnel – breaking through to Britomart Station

4


C1 – Building works

Lower Queen Street

The north tunnel – breaking through to Britomart Station

5


C1 – Streetscape

Lower Queen Street

The north tunnel – breaking through to Britomart Station

6


C1 – Streetscape

Lower Queen Street

The north tunnel – breaking through to Britomart Station

7


C1 – Streetscape

Lower Queen Street

The north tunnel – breaking through to Britomart Station

8


C1 – Streetscape

Lower Queen Street

The north tunnel – breaking through to Britomart Station

9


C1 – Streetscape enhancement works

December 2020 Mid 2021 Plaza works Scope differed to a later stage as part of CRL C3 scope of works

Lower Queen Street 10


C2 Update Lucas Nikkel 26 November 2020


C2 Recent Milestones • All works complete

* Some finishing works deferred beside private developments, these are currently under construction and will be completed by Auckland Council.

12


C2 – Wyndham to Swanson (West)

Lower Queen Street

The north tunnel – breaking through to Britomart Station

13


C2 – Wyndham to Swanson (East)

* Some finishing works deferred beside private developments, these are currently under construction and will be completed Lower Queen Street by Auckland Council.

The north tunnel – breaking through to Britomart Station

14


C2 – Swanson to Wolfe (West)

Lower Queen Street

The north tunnel – breaking through to Britomart Station

15


C2 – Swanson to Mills (East)

Lower Queen Street

The north tunnel – breaking through to Britomart Station

16


C2 – Wolfe to Customs (West)

Lower Queen Street

The north tunnel – breaking through to Britomart Station

17


C2 – Mills to Customs (East)

Lower Queen Street

The north tunnel – breaking through to Britomart Station

18


Wider Project Update

Maria Hernandez-Curry

26 November 2020


C2 Albert Street & Te Komititanga – completion event

20


Project notices •

Block of Lines – 26 December to 10 January

•

Christmas working hours vary across sites

•

C5 Western Line connection and C7 Rail Systems contracts confirmed as large variation to C3 Main Works contract

•

New Minister of Transport – Michael Wood

21


Aotea Station construction Aotea Station tunnel and platforms (Under Albert Street) Victoria-Albert St closure June 2021 – mid 2023

Wellesley-Albert Street closed Mar 2020 – June 2021 Mayoral Drive closed Mar 2020 – 2024

22


Karangahape and Mt Eden Station construction

23