RLAA17 DC s127 decision v1.1
Decision on notification of an application to vary conditions of a resource consent under section 127 of the Resource Management Act 1991 Application number:
R/LUC/2016/5464 R/REG/2016/5466 R/REG/2016/5473 R/REG/2016/5474 R/REG/2016/5477 R/REG/2016/5478
Consent holder:
City Rail Link Limited
Site address:
26 Mt Eden Road, end of Water Street, Corner of Ruru and Water Street, Boston Road (in road reserve), Normanby Road (in road reserve)
Legal description:
N/A
Proposal: To change condition 1 of resource consents R/LUC/2016/5464, R/REG/2016/5466, R/REG/2016/5473, R/REG/2016/5474, R/REG/2016/5477, R/REG/2016/5478, and conditions 23, 27a, 29, 29a, 34 and 36 of resource consents R/REG/2016/5466 and R/REG/2016/5473 in order to reflect changes in the construction methodology for part of the City Rail Link (CRL) project. This part of the CRL project is to enable construction of the future CRL tunnels by realigning the Nikau Street Stormwater Main. The appointed contractor for the works has proposed a slightly different design and construction methodology to that originally proposed. The relevant conditions of the consents then require consideration to being changed to accommodate the revised construction methodology. To be considered in terms of section 127 of the Resource Management Act 1991.
Decision on notification I have read the application, supporting documents, and the report and recommendations on the application to change conditions of the resource consents. I am satisfied that I have sufficient information to consider the matters required by the Resource Management Act 1991 (RMA) and make a decision under delegated authority on notification.
Public notification Under section 95A of the RMA this application shall proceed without public notification because: 1.
Under step 1, public notification is not mandatory as: a.
the applicant has not requested it
b.
there are no outstanding or refused requests for further information, and
c.
2.
3.
4.
the application does not involve any exchange of recreation reserve land under s15AA of the Reserves Act 1977.
Under step 2, public notification is not precluded as: a.
there is no rule or NES that specifically precludes public notification of the activities, and
b.
the application is for an activity other than those specified in s95A(5)(b).
Under step 3, public notification is not required as: a.
the application is for an activity that is not subject to a rule that specifically requires it, and
b.
the adverse effects on the environment as a result of the changes will be less than minor because the main matters to be considered in terms of effects are dealt with as follows: o
Ground settlement and groundwater diversion are appropriately monitored in respect of the scale of the activity.
o
Appropriate traffic management measures are implemented through the TAP DWP to minimise any risks from construction vehicles movements to and from the construction sites.
o
Construction noise and vibration will be managed to within the consented levels via the CNV DWP.
o
Adverse effects in respect of other matters are suitably addressed through the existing conditions of consents and the CE MP.
Under step 4, there are no special circumstances that warrant the application being publicly notified because there is nothing exceptional or unusual about the application, and the proposal has no features that are out of the ordinary to suggest that public notification should occur.
Limited notification Under section 95B of the RMA this application shall proceed without limited notification because: 1.
2.
3.
Under step 1, limited notification is not mandatory as: a.
there are no protected customary rights groups or customary marine title groups affected by this proposal, and
b.
no persons to whom a statutory acknowledgement is made is adversely affected by this proposal.
Under step 2, limited notification is not precluded as: a.
there is no rule or NES that specifically precludes limited notification of the activities, and
b.
the application is for an activity other than those specified in s95B(6)(b).
Under step 3, limited notification is not required as:
R/LUC/2016/5464; R/REG/2016/5466; R/REG/2016/5473; R/REG/2016/5474; R/REG/2016/5477; R/REG/2016/5478 Page 2
4.
a.
this application is not for a boundary activity or prescribed activity, and
b.
there are no persons adversely affected by the proposed changes to conditions as the scale, intensity and character of the effects are similar to the consented reference design and methodology; effects on the traffic network are manageable; noise generating activities have been moved away for the most noise sensitive location at Eden Terrace; and, effects on additional sensitive receivers can be managed via SSCNV MP’s. These measures all contribute the adverse effects of the changes to the conditions having less than minor adverse effects. The works will not result in any adversely affected persons, noting the need for the consent holder to comply with existing conditions of consent.
Under step 4, there are no special circumstances that warrant the application being limited notified to any persons because there is nothing exceptional or unusual about the application, and the proposal has no features that are out of the ordinary to suggest that notification to any other persons should occur.
Accordingly, this discretionary activity application shall proceed on a NON-NOTIFIED basis.
AR Watson Duty Commissioner 25 June 2018
R/LUC/2016/5464; R/REG/2016/5466; R/REG/2016/5473; R/REG/2016/5474; R/REG/2016/5477; R/REG/2016/5478 Page 3
Decision on an application to vary conditions of a resource consent under section 127 of the Resource Management Act 1991 Application number:
R/LUC/2016/5464 R/REG/2016/5466 R/REG/2016/5473 R/REG/2016/5474 R/REG/2016/5477 R/REG/2016/5478
Consent holder:
City Rail Link Limited
Site address:
26 Mt Eden Road, end of Water Street, Corner of Ruru and Water Street, Boston Road (in road reserve), Normanby Road (in road reserve)
Legal description:
N/A
Proposal: To change condition 1 of resource consents R/LUC/2016/5464, R/REG/2016/5466, R/REG/2016/5473, R/REG/2016/5474, R/REG/2016/5477, R/REG/2016/5478, and conditions 23, 27a, 29, 29a, 34 and 36 of resource consents R/REG/2016/5466 and R/REG/2016/5473 in order to reflect changes in the construction methodology for the City Rail Link (CRL) project. This part of the CRL project is to enable construction of the future CRL tunnels by realigning the Nikau Street Stormwater Main. The appointed contractor for the works has proposed a slightly different design and construction methodology to that originally proposed. The relevant conditions of consents then require consideration to being changed to accommodate the revised construction methodology. To be considered in terms of section 127 of the Resource Management Act 1991.
Decision I have read the application, supporting documents, and the report and recommendations on the application for changes to the conditions of resource consent(s). I am satisfied that I have sufficient information to consider the matters required by the Resource Management Act 1991 (RMA) and to make a decision under delegated authority on the application. Under sections 127,104, 104B and Part 2 of the RMA this application to change condition 1 of resource consents R/LUC/2016/5464; R/REG/2016/5466; R/REG/2016/5473; R/REG/2016/5474; R/REG/2016/5477; R/REG/2016/5478, and conditions 23, 27a, 29, 29a, 34 and 36 of resource consents R/REG/2016/5466 and R/REG/2016/5473 is GRANTED. The reasons for this decision are the adverse effects on the environment as a result of the changes to the conditions will be acceptable because the main matters to be considered in terms of effects are dealt with as follows:
R/LUC/2016/5464; R/REG/2016/5466; R/REG/2016/5473; R/REG/2016/5474; R/REG/2016/5477; R/REG/2016/5478 Page 1
1.
Ground settlement and groundwater diversion is appropriately monitored and mitigated by the GWS DWP in respect of the scale of the activity and adverse effects will therefore be avoided.
2.
Appropriate traffic management measures are implemented through the TAP DWP to minimise the effects from construction vehicles movements to and from the construction sites on the surrounding network.
3.
Construction noise and vibration will be managed to within the consented levels via the CNV DWP.
4.
Adverse effects in respect of other matters are suitably addressed by the existing conditions and the CE MP.
Changes Under section 127 of the RMA conditions 1 of resource consents R/LUC/2016/5464, R/REG/2016/5466, R/REG/2016/5473, R/REG/2016/5474, R/REG/2016/5477, R/REG/2016/5478, and conditions 23, 27a, 29, 29a, 34 and 36 of resource consents R/REG/2016/5466 and R/REG/2016/5473 are changed as set out below. Bold underlined text denotes new text. Strikethrough text denotes deleted text. 1. The Nikau Street Stormwater Main Realignment project shall be carried out in general accordance with the plans and all information submitted with the application, detailed below, and all referenced by the Council as consent numbers R/LUC/2016/5464, R/REG/2016/5466, R/REG/2016/5473, R/REG/2016/5474, R/REG/2016/5477 and R/REG/2016/5478;
Application Form, and Assessment of Effects titled “Auckland City Rail Link Nikau Street Stormwater Main Realignment Assessment of Environmental Effects” prepared by Aurecon, document Ref CRL-SYW-RME-000-RPT-0063, revision 3, dated December 2016
S127 Application Form, and accompanying Assessment of Effects, prepared by Beca, document reference 4217071, dated 4 May 2018
Report title and reference
Author
Rev #
Dated #
Appendix D Construction Environmental Management Plan
J, Luty, Aurecon
CRL-SYW-RME-000-RPT-0066
Dec 2016
CRL-SYW-RME-000-RPT-0066
March 2018 Rev 9
Construction Environmental Management Plan Appendix E Groundwater Assessment
Blair Thornburrow, PDP
CRL-SYW-RME-000-RPT-0071
Dec 2016
Appendix F
J. Lokes,
CRL-MTE-RME-000-RPT-0083,
Dec 2016
R/LUC/2016/5464; R/REG/2016/5466; R/REG/2016/5473; R/REG/2016/5474; R/REG/2016/5477; R/REG/2016/5478 Page 2
Settlement Assessment
Aurecon
Rev 4
Groundwater and Settlement Assessment Memo
WSP
PS107014-PLA-MEM-001 Rev C
April 2018
Appendix G Groundwater and Settlement Monitoring and Contingency Plan
J. Lokes, Aurecon
CRL-SYW-RME-000-RPT-0075, Rev 3
Dec 2016
Appendix H Water Quality Assessment
Golder and Associates
CRL-SYW-RME-000-RPT-0071
Dec 2016
Appendix I Contaminated Land Assessment
Golder and Associates
CRL-SYW-RME-000-RPT-0070
Dec 2016
Appendix J Air Quality Assessment
Golder and Associates
CRL-SYW-RME-000-RPT-0072
Dec 2016
Appendix K Noise and Vibration Assessment
Micky Yang, Marshall Day Acoustics
CRL-SYW-RME-000-RPT-0078
Dec 2016
CRL C6 Section 127 Application Construction Noise and Vibration Assessment Memo
Craig Fitzgerald, Marshall Day Acoustics
Appendix L Arboricultural Assessment
Stephen Bishop, Amenity Tree Consultants Ltd
CRL-SYW-RME-000-RPT-0082
Dec 2016
Appendix M Archaeological Assessment
S. Macready, R. Clough
CRL-SYW-RME-000-RPT-0079
Dec 2016
Transport Access and Parking Delivery Work Program
Aurecon
CRL-SYW-RME-000-RPT-0077
Dec 2016
Transport, Access and Parking Delivery Work Plan
Flow / Graeme Inglis
Status - Revised for section 127
June 2018 Rev 4
April 2018
R/LUC/2016/5464; R/REG/2016/5466; R/REG/2016/5473; R/REG/2016/5474; R/REG/2016/5477; R/REG/2016/5478 Page 3
Condition 1 Document – Reference Design
Proposed Replacement Document – MBJV Detailed Design
Name
Document Title
Rev #
Name
Document Title
Rev #
CRL-MTE-UTI-000DRG-1101
CONTRACT 6 GENERAL ARRANGEMENT PLAN
5
Ps107014-UTI-1101
GENERAL ARRANGEMENT PLAN
D03
CRL-MTE-UTI-000DRG-1121
CONTRACT 6 1950MM DIA DIVERSION LONGITUDINAL SECTION
2
PS107014-UTI-1121
2000MM DIA DIVERSION LONGITUDINAL SECTION D03
CRL-MTE-UTI-000DRG-1201
CONTRACT 6 WATER STREET GENERAL ARRANGEMENT
2
PS107014-UTI-1201
WATER STREET SHAFT GENERAL ARRANGEMENT
D03
CRL-MTE-UTI-000DRG-1202
CONTRACT 6 WATER STREET GENERAL ARRANGEMENT PLAN VIEWS AND SETOUT
2
PS107014-UTI-1202
WATER STREET SHAFT GENERAL ARRANGEMENT PLAN VIEWS AND SETOUT
D03
CRL-MTE-UTI-000DRG-1203
CONTRACT 6 WATER STREET GENERAL ARRANGEMENT SECTIONS
2
PS107014-UTI-1203
WATER STREET SHAFT GENERAL ARRANGEMENT SECTIONS
D03
CRL-MTE-UTI-000DRG-1204
CONTRACT 6 WATER STREET SECTION THROUGH PERMANENT WORKS
2
PS107014-UTI-1204
WATER STREET SHAFT SECTION THROUGH PERMANENT WORKS
D03
CRL-MTE-UTI-000DRG-1223
CONTRACT 6 WATER STREET SHAFT TEMPORARY WORKS – MINED TUNNELLING DETAILS
2
PS107014-UTI-1223
WATER STREET SHAFT TEMPORARY WORKS CONNECTION TRENCH DETAILS
D03
CRL-MTE-UTI-000DRG-1241
CONTRACT 6 WATER STREET SHAFT UTILITY DIVERSION DETAILS
2
PS107014-UTI-1241
WATER STREET UTILITY DIVERSION DETAILS
D03
CRL-MTE-UTI-000DRG-1252
CONTRACT 6 WATER STREET SHAFT PERMANENT STORMWATER MANHOLE AND DROPPER PLAN
2
PS107014-UTI-1252
WATER STREET SHAFT PERMANENT STORWMATER MANHOLE AND DROPPER PLAN
D03
CRL-MTE-UTI-000DRG-1442
CONTRACT 6 NIKAU STREET SHAFT TEMPORARY 2 WORKS – CASSION DETAILS
PS107014-UTI-1442
NIKAU STREET SHAFT UTILITIES DIVERSION SECTIONS AND REINSTATEMENT
D03
CRL-MTE-UTI-000DRG-1521
CONTRACT 6 SETTLEMENT CONTOURS LAYOUT 3 PLAN
PS107014-UTI-1521
SETTLEMENT CONTOURS LAYOUT PLAN
D03
CRL-MTE-UTI-000-
CONTRACT 6 INSTRUMENTATION AND
PS107014-UTI-1522
INSTRUMENTATION AND SETTLEMENT
D03
5
R/LUC/2016/5464; R/REG/2016/5466; R/REG/2016/5473; R/REG/2016/5474; R/REG/2016/5477; R/REG/2016/5478 Page 4
CONTOURS GENERAL NOTES AND TRIGGER LEVELS
DRG-1522
SETTLEMENT CONTOURS GENERAL NOTES AND TRIGGER LEVELS
CRL-MTE-UTI-000DRG-1523
CONTRACT 6 INSTRUMENTATION AND SETTLEMENT CONTOURS LAYOUT PLAN
5
PS107014-UTI-1523
INSTRUMENTATION AND SETTLEMENT CONTOURS LAYOUT PLAN
D03
CRL-MTE-UTI-000DRG-1524
CONTRACT 6 INSTRUMENTATION AND SETTLMENT CONTOURS GPT MONITORING DETAILS
1
CRL-MTE-UTI-000DRG-1524
CONTRACT 6 INSTRUMENTATION AND SETTLMENT CONTOURS GPT MONITORING DETAILS
1
CRL-MTE-UTI-000DRG-1601
CONTRACT 6 WATER STREET SHAFT TEMPORARY WORKS LAYDOWN AREA
3
710919-W-SK021
SITE ESTABLISHMENT PLAN STAGE 2
B
CRL-MTE-UTI-000DRG-1611
CONTRACT 6 WATER STREET SHAFT TEMPORARY WORKS SITE LAYOUT AND TTM
3
710919-W-SK021
SITE ESTABLISMENT PLAN STAGE 2
B
CRL-MTE-UTI-000DRG-1651
CONTRACT 6 WATER STREET SHAFT EROSION AND SEDIMENT CONTROL PLAN
4
344-022
WATER STREET EROSION AND SEDIMENT CONTROL
A
R/LUC/2016/5464; R/REG/2016/5466; R/REG/2016/5473; R/REG/2016/5474; R/REG/2016/5477; R/REG/2016/5478 Page 5
Groundwater diversion & take (s14) R/REG/2016/5466 & R/REG/2016/5473 conditions 23. The activity shall not cause any settlement or movement greater than the Alarm Level thresholds specified in Schedule A below. Alert and Alarm Levels are triggered when the following Alert and Alarm Trigger thresholds are exceeded:
R/LUC/2016/5464; R/REG/2016/5466; R/REG/2016/5473; R/REG/2016/5474; R/REG/2016/5477; R/REG/2016/5478 Page 6
R/LUC/2016/5464; R/REG/2016/5466; R/REG/2016/5473; R/REG/2016/5474; R/REG/2016/5477; R/REG/2016/5478 Page 7
R/LUC/2016/5464; R/REG/2016/5466; R/REG/2016/5473; R/REG/2016/5474; R/REG/2016/5477; R/REG/2016/5478 Page 8
These levels may be amended subject to certification by the Team Leader Central Monitoring as part of the Groundwater Settlement Monitoring and Contingency Plan (GSMCP) certification process, and, after the receipt of pre-dewatering monitoring data, building condition surveys and recommendations from a suitably qualified engineering professional, that the information indicates avoidance of damage to building, structures and services from new levels can still be achieved. Advice Note: There are conditions below that must be complied with when the Alert and Alarm Level triggers are exceeded. These include actions that must be taken immediately including seeking the advice of a suitably qualified and experienced person. R/LUC/2016/5464; R/REG/2016/5466; R/REG/2016/5473; R/REG/2016/5474; R/REG/2016/5477; R/REG/2016/5478 Page 9
27. The overall objective of the GSMCP shall be to set out the practices and procedures to be adopted to ensure compliance with the consent conditions and shall include, at a minimum, the following information: a) Monitoring location plans showing the location and type of all Monitoring Stations including groundwater monitoring bores, ground movement pins, inclinometers, wall deflection and deformation pins. The monitoring plans should be based on the drawings entitled ‘CONTRACT 6 IMPLEMENTATION AND SETTLEMENT CONTOURS LAYOUT PLAN’ reference CRL-MTE-UIT-000-DRG-1523 rev 5.0 dated 22/03/2017 and ‘INSTRUMENTATION AND SETTLEMENT CONTOURS LAYOUT PLAN’ reference PS107014-UTI-1523 Rev D03 dated 03/04/2018 and ‘COTRACT 6 INSTRUMENTATION AND SETTLEMENT CONTOURS GPT MONITORING DETAILS’ Reference CRL-MTE-UTI-000-DRG-1524 rev 1.0 dated 10/04/17 appended to these conditions (Appendix A). In any case where the location of a Monitoring Station differs substantively from that shown on the drawings in Appendix A, a written explanation for the difference shall be provided at the same time that the CSMPCP is provided. b) Final completed schedules B to E (as per the conditions below) for the groundwater, ground surface, building, retaining wall, inclinometer and deformation monitoring programme (including any proposed changes to the monitoring frequency) as required by conditions below. c) All monitoring data, the identification of services susceptible to damage and all building/service condition surveys undertaken to date, and required by conditions below. d) A bar chart (such as a Gantt chart) showing the timing and frequency of condition surveys, visual inspections and all other monitoring required by this consent, and, a sample report template for the required 2 monthly monitoring. e) All Alert and Alarm Level triggers (including reasons if changes to such are proposed; for example, as a result of recommendations in the building condition surveys or data obtained from pre-dewatering monitoring). f)
Details of the contingency actions to be implemented if Alert or Alarm Levels are exceeded.
Pre-dewatering building and structure survey 29. Prior to the commencement of excavation or dewatering (whichever comes first), an external visual inspection or a detailed condition survey of buildings and structures as specified in Schedule B below and prepared by a suitably qualified and experienced engineering professional, shall be submitted for certification by the Team Leader Central Monitoring. Note: This condition shall not apply where written evidence is provided to the Team Leader Central Monitoring that the owner of a property has confirmed they do not require a condition survey. The detailed condition survey/s shall include: a) Confirmation of the installation of deformation pins as required in Schedule B below in the locations specified on the drawing entitled ‘CONTRACT 6 INSTRUMENTATION AND R/LUC/2016/5464; R/REG/2016/5466; R/REG/2016/5473; R/REG/2016/5474; R/REG/2016/5477; R/REG/2016/5478 Page 10
SETTLEMENT CONTOURS LAYOUT PLAN’ reference CRL-MTE-UTI-000-DRG-1523 rev 5.0 dated 2/03/2017 ‘INSTRUMENTATION AND SETTLEMENT CONTOURS LAYOUT PLAN’ reference PS107014-UTI-1523 Rev D03 dated 03/04/2018 appended to these conditions. b) A description of the type of foundations. c) A description of existing levels of damage considered to be of an aesthetic or superficial nature. d) A description of existing levels of damage considered to affect the serviceability of the building where visually apparent without resource to intrusive or destructive investigation. e) An assessment as to whether existing damage may or may not be associated with actual structural damage and an assessment of the susceptibility of the buildings/structure to further movement and damage, to the extent predicted. f)
Photographic evidence of existing observable damage.
g) A review of proposed Alarm and Alert levels to confirm they are appropriately set and confirmation that any ground settlement less than the Alarm Level will not cause damage. h) An assessment of whether the monitoring frequency is appropriate. i)
An assessment of whether the location and density of existing deformation pins is adequate and appropriate for the effective detection of change to building and structure conditions.
The external visual inspection/s shall include: a) Confirmation of the installation of deformation pins as required in Schedule B below in the locations specified on the drawings entitled ‘CONTRACT 6 INSTRYMENTATION AND SETTLEMENT CONTOURS LAYOUT PLAN’ reference CRL-MTE-UTI-DRG-1523 rev 5.0 dated 22/03/2017 ‘INSTRUMENTATION AND SETTLEMENT CONTOURS LAYOUT PLAN; reference PS107014-UTI-1523 Rev D03 dated 03/04/2018 appended to these conditions. b) A visual inspection if all exterior observable damage. c) Photographic evidence of all exterior observable damage. Schedule B: Building inspection and deformation pins Number
Address
Type of survey
Number of deformation pins required
1
45 Boston Road
External visual inspection
0
2
47 Boston Road
External visual inspection
0
3
24 Mt Eden Road
Detailed condition survey / external visual inspection
2
0
R/LUC/2016/5464; R/REG/2016/5466; R/REG/2016/5473; R/REG/2016/5474; R/REG/2016/5477; R/REG/2016/5478 Page 11
Advice Note: Where settlements are predicted to be in excess of 10mm, building surveys may need to be completed by a specialist structural engineer. In such circumstances, prior consultation with Council is advisable. 34. Groundwater monitoring bores are to be installed at least two months before the commencement of dewatering, and thereafter maintained, in the locations shown on the drawing entitled ‘CONTRACT 6 INSTRUMENTATION AND SETTLEMENT CONTOURS LAYOUT PLAN’ reference CRL-MTE-UTI-000-1523 rev 5.0 dated 22/03/2017 ‘INSTRUMENTATION AND SETTLEMENT CONTOURS LAYOUT PLAN: reference PS107014-UTI-1523 Rev D03 dated 03/04/2018, appended to these conditions 9Appendix A) or, in the approved GSMCP. Groundwater level monitoring is to be undertaken in accordance with Schedule C below: Schedule C: Groundwater Monitoring Frequency Bore name
Location
Groundwater level monitoring frequency (to an accuracy of 10mm)
Easting
Northing
From bore construction until one month before Commencement of Dewatering
One month before Commencement of Dewatering to Completion of Dewatering
From Completion of Dewatering until 3 months later
BHM2
1756748
5918436
Monthly
Monthly
BH461
1757119
5918350
Monthly
BH307
1756968
5918289
Monthly
Hourly recording, retrieved at least three times weekly
Monthly Monthly
The monitoring frequency may be changed if approved by the Team Leader Central Monitoring. Any change shall be specified in the GSMCP. In addition, the 3 month monitoring period post Completion of Dewatering may be extended, the the Team Leader Central monitoring, if measured groundwater levels are not consistent with inferred seasonal trends of predicted groundwater movement. Advice Note: if groundwater level measurements show an inconsistent pattern immediately prior to the Commencement of Dewatering (for example varying more than +/- 200mm during a month), then further reading may be required to ensure that an accurate groundwater level baseline is established before dewatering commences. Groundwater surface and building deformation monitoring 35. Ground surface and building deformation Monitoring Stations shall be established and maintained at the approximate locations shown on the drawing entitled ‘CONTRACT 6 INSTRUMENTATION AND SETTLEMENT CONTOURS LAYOUT PLAN’ reference CRL-MTEUTI-000-DRG-1523 rev 5.0 dated 22/03/2017 ‘INSTRUMENTATION AND SETTLEMENT CONTOURS LAYOUT PLAN’’ reference CRL-MTE-UTI-1523 Rev D03 dated 03/04/2018 and ‘CONTRACT 6 INSTRUMENTATION AND SETTLEMENT CONTOURS GPT R/LUC/2016/5464; R/REG/2016/5466; R/REG/2016/5473; R/REG/2016/5474; R/REG/2016/5477; R/REG/2016/5478 Page 12
MONITORING DETAILS; reference CRL-MTE-UTI-000-DRG-1524 rev 1.0 dated 10/04/17, appended to these conditions (Appendix A) or, in the approved GSMCP. The monitoring stations will be monitored at the frequency set out in Schedule D. The purpose of the monitoring is to record any vertical or horizontal (including differential) movement. Benchmark positions shall be established no less than 50 metres away from the excavated area. Schedule D: Ground and Building Monitoring Monitoring station and name
Ground surface stations: WS5, WS16, ME7-ME18, ME30-ME34-ME40-ME67, ME70-ME72, NS3-NS6 and NS8-NS11, NS15-NS17, NS20-26 and G1-1 to G2-6
Frequency PreCommencement of Excavation
Commencement to Excavation to Completion of Dewatering
PostCompletion of Dewatering
Twice to a vertical accuracy of +/-2mm
Daily where station is within 50m of active works, otherwise weekly
Monthly for 6 months
Ground surface stations: WS8, ME1ME7, ME30-ME34, ME40-ME51, ME70ME71, NS3-NS6 and NS8-NS11, NS15-NS17, NS20NS26 and G1-1 to G2-6 Building stations: ME21, ME23
The monitoring frequency may be changed, if approved by the Team Leader Central Monitoring, through the CSMCP. Retaining wall monitoring 36. Eight (8) Five (5) retaining wall deflection stations (WS1-WS4, ME1, ME6, ME19, ME24, NS1, NS2 and NS7) (WS1-WS4, ME20, NS1, NS2, and NS7), for the measurement of vertical and lateral wall movement, shall be installed along the top of or immediately behind the shaft walls, and, a single inclinometer shall be installed immediately behind the Mt Eden shaft retaining wall and extending to the base of the retaining wall, as shown on the drawing entitled ‘CONTRACT 6 INSTRUMENTATION AND SETTLEMENT CONTOURS LAYOUT PLAN’ reference CRL-MTE-UTI-000-DRG-1523 rev 5.0 dated 22/03/2017 ‘INSTRUMENTATION AND SETTLEMENT CONTOURS LAYOUT PLAN’’ reference PS107014-UTI-1523 Rev D03 dated 03/04/2018, appended to these conditions (Appendix A) Monitoring of the retaining wall pins and inclinometer shall be undertaken and recorded in accordance with Schedule E below and shall be carried out using precise levelling. Schedule E: Retaining Wall Monitoring R/LUC/2016/5464; R/REG/2016/5466; R/REG/2016/5473; R/REG/2016/5474; R/REG/2016/5477; R/REG/2016/5478 Page 13
Frequency PreCommencement of Excavation
Commencement of Excavation to one month after Completion of Excavation
One month after Completion of Excavation to Completion of Dewatering
Retaining wall stations and inclinometer
Retaining wall stations
Inclinometer
Retaining wall pins
Inclinometer
Twice to a horizontal and vertical accuracy of +/-2mm
Daily where station within 50m of active works, otherwise weekly
Daily where station within 50m of active works, otherwise weekly
Fortnightly
Monthly
The monitoring frequency may be changed, if certified by the Team Leader Central Monitoring, through the GSMCP. All other conditions of resource consents R/LUC/2016/5464, R/REG/2016/5466, R/REG/2016/5473, R/REG/2016/5474, R/REG/2016/5477, R/REG/2016/5478 remain unchanged and in effect
Advice notes 
The consent holder is reminded that the decision on this section 127 application/decision does not affect the lapse period for the resource consent.
AR Watson, Duty Commissioner 25 June 2018