MINUTES DATE
23 February 2021
TIME
5 PM
LOCATION
4A Cross Street
STAKEHOLDERS TE CLG members and guests –23 attendees including staff IN ATTENDANCE Simon Johanna, DeirdreRichardson, Fitzgerald, Arash John Daly,and Craig RichardMitchell, Northley, AdrianaMcIntosh, Christie, Michael PennyBarzan, Hansen, Miraim Dave STAFF
Mathieson, DanHyde, Trotman, Eva Brosius, AlanSullivan, Whiteley, Richard Jenkins, Croucher, Gav RonnyMichael Franks,Coup, Humphrey Tait, Roch Grady Elliott, Hendrik Tegman
SUBJECT
Karangahape Station update, SIBD consultation, Public Realm
Purpose To provide information regarding: •
Key milestone for Mercury Lane and Beresford Square and an update on tunnel progress.
•
Identify the key proposed design elements for Beresford Square from Stage A consultation, share the plans for Mercury Lane and the process moving forward for Stage B consultation.
Agenda 1. 2. 3. 4. 5.
Brief welcome – Simon Mitchell, Community Manager SIBD audit results – John Daly Karangahape Station overview – Dan Trotman, Site Engineer Urban Realm - Alan Whiteley, urban designer Discussion and questions i. Subject matter experts will be available to answer questions
Meeting notes and Q&As Michael Richardson (KBA)– Expressed he thought the findings from the SIBD were generally good. He wanted to know lessons learned and what could be done better next time. He offered to provide a review of the initial consultation process as he felt there was definite room for improvement, and he would like to provide his input.