Aotea & C1/C2 Community Liaison Group Meeting 30 October 2019
Agenda • C2 – Albert Street works
• C1 – Britomart / Lower Queen Street works • C1 – Britomart / Lower Queen St urban realm design
• Wider project update • CRL tunnel walkthrough event
2
C2: Albert Street Robyn Findlay
Contract 2 Albert Street - Customs Street to Wyndham Street
Contract 2 Wyndham St West
Contract 2 Wyndham Street Intersection
Contract 2 Albert Street – Wyndham to Swanson St
Contract 2 Swanson St West
Contract 2 Albert Street – Swanson to Wolfe
Contract 2 Mills Lane Intersection
C1: Britomart / Lower Queen Street Maria Hernandez-Curry
C1 – Tunnel construction
Lower Queen Street
The north tunnel – breaking through to Britomart Station
12
C1 – Building works
Lower Queen Street
The north tunnel – breaking through to Britomart Station
13
C1 – Streetscape enhancement works
Lower Queen Street
The north tunnel – breaking through to Britomart Station
14
C1 – Streetscape enhancement works
Lower Queen Street
The north tunnel – breaking through to Britomart Station
15
C1 – Streetscape enhancement works
Lower Queen Street
The north tunnel – breaking through to Britomart Station
16
Urban realm enhancement
17
Urban realm enhancement
18
Urban realm enhancement
19
Urban realm enhancement
20
CRL project update Maria Hernandez-Curry
C6: Mt Eden stormwater realignment works
22
Aotea Station precinct • Engagement with local community • Door-knocks, meetings • Weekly drop-in at 44 Wellesley Street West • Environmental management plans (noise, social impact, traffic). Delivery Work Plans being finalised and published on the City Rail Link website • Canopy removal • Building condition surveys • Installation of monitoring equipment on buildings
• 0800 CRL TALK and station email aotea@linkalliance.co.nz
Utilities 2019
2020
Main Station Works 2021 2022
Streetscape Enhancements 2023 2024 23
Utilities investigations and relocations • Works began mid-September, to identify and relocate utilities away from the station construction footprint
• Work hours 7am-7pm, Monday to Saturday • Works undertaken in stages: • Investigatory works to confirm utility locations. Includes digging small “slot trenches”
• Around 1-2 weeks duration in each area • Relocation works – 4.5m deep trench dug along the footpath, in 50m-60m sections. • Each section 4-6 weeks duration.
A utility relocation trench on Quay Street 24
Investigatory works
Marking up the footpath
Slot trench 253
Construction staging
26
Construction staging
27
Site compound
28
Station overview
29
Station entrances
30
Station concourse level
31
Station excavation and construction
32
Karangahape Station • Utility investigations and relocations – late 2019
• Closure of Beresford Square – early 2020 • Site establishment in Beresford Square (formerly Wilson carpark) – early 2020
• Demolition of buildings (in red zone) – late 2019-early 2020
33
Mt Eden Station
34
C3: Mt Eden Station • Site office established at 97 Mt Eden Road – August 2019
• Soft-strip and salvage work, asbestos removal within the Mt Eden demolition area –mid-2019-late 2019
• Demolition work – October 2019 to Q2 2020
• Utility investigations and relocations – late 2019
• Tunnel portal works – early 2020 to early 2021
• Construction of additional Mt Eden Rd bridge & Ruru St bridge for CRL lines – Q2 2020 35