C1 presentation October 2019

Page 1

Aotea & C1/C2 Community Liaison Group Meeting 30 October 2019


Agenda • C2 – Albert Street works

• C1 – Britomart / Lower Queen Street works • C1 – Britomart / Lower Queen St urban realm design

• Wider project update • CRL tunnel walkthrough event

2


C2: Albert Street Robyn Findlay


Contract 2 Albert Street - Customs Street to Wyndham Street


Contract 2 Wyndham St West


Contract 2 Wyndham Street Intersection


Contract 2 Albert Street – Wyndham to Swanson St


Contract 2 Swanson St West


Contract 2 Albert Street – Swanson to Wolfe


Contract 2 Mills Lane Intersection


C1: Britomart / Lower Queen Street Maria Hernandez-Curry


C1 – Tunnel construction

Lower Queen Street

The north tunnel – breaking through to Britomart Station

12


C1 – Building works

Lower Queen Street

The north tunnel – breaking through to Britomart Station

13


C1 – Streetscape enhancement works

Lower Queen Street

The north tunnel – breaking through to Britomart Station

14


C1 – Streetscape enhancement works

Lower Queen Street

The north tunnel – breaking through to Britomart Station

15


C1 – Streetscape enhancement works

Lower Queen Street

The north tunnel – breaking through to Britomart Station

16


Urban realm enhancement

17


Urban realm enhancement

18


Urban realm enhancement

19


Urban realm enhancement

20


CRL project update Maria Hernandez-Curry


C6: Mt Eden stormwater realignment works

22


Aotea Station precinct • Engagement with local community • Door-knocks, meetings • Weekly drop-in at 44 Wellesley Street West • Environmental management plans (noise, social impact, traffic). Delivery Work Plans being finalised and published on the City Rail Link website • Canopy removal • Building condition surveys • Installation of monitoring equipment on buildings

• 0800 CRL TALK and station email aotea@linkalliance.co.nz

Utilities 2019

2020

Main Station Works 2021 2022

Streetscape Enhancements 2023 2024 23


Utilities investigations and relocations • Works began mid-September, to identify and relocate utilities away from the station construction footprint

• Work hours 7am-7pm, Monday to Saturday • Works undertaken in stages: • Investigatory works to confirm utility locations. Includes digging small “slot trenches”

• Around 1-2 weeks duration in each area • Relocation works – 4.5m deep trench dug along the footpath, in 50m-60m sections. • Each section 4-6 weeks duration.

A utility relocation trench on Quay Street 24


Investigatory works

Marking up the footpath

Slot trench 253


Construction staging

26


Construction staging

27


Site compound

28


Station overview

29


Station entrances

30


Station concourse level

31


Station excavation and construction

32


Karangahape Station • Utility investigations and relocations – late 2019

• Closure of Beresford Square – early 2020 • Site establishment in Beresford Square (formerly Wilson carpark) – early 2020

• Demolition of buildings (in red zone) – late 2019-early 2020

33


Mt Eden Station

34


C3: Mt Eden Station • Site office established at 97 Mt Eden Road – August 2019

• Soft-strip and salvage work, asbestos removal within the Mt Eden demolition area –mid-2019-late 2019

• Demolition work – October 2019 to Q2 2020

• Utility investigations and relocations – late 2019

• Tunnel portal works – early 2020 to early 2021

• Construction of additional Mt Eden Rd bridge & Ruru St bridge for CRL lines – Q2 2020 35